JP5570893B2 - How to install the three-sided frame - Google Patents

How to install the three-sided frame Download PDF

Info

Publication number
JP5570893B2
JP5570893B2 JP2010155148A JP2010155148A JP5570893B2 JP 5570893 B2 JP5570893 B2 JP 5570893B2 JP 2010155148 A JP2010155148 A JP 2010155148A JP 2010155148 A JP2010155148 A JP 2010155148A JP 5570893 B2 JP5570893 B2 JP 5570893B2
Authority
JP
Japan
Prior art keywords
way frame
piece
pair
jig
bolt holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2010155148A
Other languages
Japanese (ja)
Other versions
JP2012017174A (en
Inventor
俊一 菊池
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Elevator and Building Systems Corp
Original Assignee
Toshiba Elevator Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Elevator Co Ltd filed Critical Toshiba Elevator Co Ltd
Priority to JP2010155148A priority Critical patent/JP5570893B2/en
Publication of JP2012017174A publication Critical patent/JP2012017174A/en
Application granted granted Critical
Publication of JP5570893B2 publication Critical patent/JP5570893B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Elevator Door Apparatuses (AREA)

Description

本発明の実施形態は、三方枠の設置方法に関する。   Embodiments of the present invention relate to a method for installing a three-way frame.

エレベータを備えた建物において、各階床にエレベータの乗場出入口を形成する三方枠が設けられている。前記三方枠は、例えば、一対の縦枠と、一方の縦枠から他方の縦枠に亘って設けられた幕板とを有している。前記幕板は、前記縦枠のそれぞれの上部に取り付けられている。   In a building equipped with an elevator, a three-way frame that forms an elevator entrance / exit is provided on each floor. The three-way frame has, for example, a pair of vertical frames and a curtain plate provided from one vertical frame to the other vertical frame. The curtain is attached to each upper part of the vertical frame.

このような三方枠は、工場において組立てられ、さらに治具を取り付けられて据付現場に搬送される。前記治具は、例えば、前記縦枠のそれぞれの下部に取り付けられる。前記治具は、前記一対の縦枠の相対位置を保持する。   Such a three-way frame is assembled in a factory, and further, a jig is attached and conveyed to the installation site. The jig is attached to each lower part of the vertical frame, for example. The jig holds a relative position of the pair of vertical frames.

前記治具は、前記三方枠が設置される据付現場において、前記三方枠から取り外される。前記三方枠は、据付現場に設けられた敷居の上に載置される。前記敷居は、前記乗場出入口の床面を形成する。前記敷居に前記一対の縦枠を固定することで、前記三方枠が設置される。   The jig is removed from the three-way frame at an installation site where the three-way frame is installed. The three-way frame is placed on a sill provided at the installation site. The threshold forms a floor surface of the landing entrance. The three-way frame is installed by fixing the pair of vertical frames to the sill.

特開2009−214990号公報JP 2009-214990 A

据付現場において、前記三方枠は、前記敷居に設置されるまで前記治具を外されている。前記三方枠から前記治具が外されていると、前記一対の縦枠が所定の相対位置からずれる可能性がある。   At the installation site, the jig is removed until the three-way frame is installed on the sill. When the jig is removed from the three-way frame, the pair of vertical frames may be displaced from a predetermined relative position.

前記一対の縦枠の相対位置がずれると、前記三方枠を設置する前に、前記一対の縦枠の相対位置を矯正する工程が追加される。これにより、三方枠を設置するための作業時間が増大する。   If the relative position of the pair of vertical frames is shifted, a step of correcting the relative position of the pair of vertical frames is added before the three-way frame is installed. This increases the work time for installing the three-way frame.

本発明は、一対の縦枠の相対位置のずれを防止する三方枠の設置方法を提供することを目的とする。   An object of this invention is to provide the installation method of the three-way frame which prevents the shift | offset | difference of the relative position of a pair of vertical frame.

一つの実施の形態に係る三方枠の設置方法は、
連結部材によって互いに連結された第1の部材と第2の部材とを含む治具を、エレベータの三方枠に含まれる一対の縦枠に取り付け、前記第1の部材および前記第2の部材から前記連結部材を取り外し、前記第2の部材を前記三方枠および前記第1の部材から取り外し、前記三方枠を乗場出入口の床面の一部を形成する敷居の上に載置し、前記三方枠を前記敷居に固定し、前記第1の部材を前記三方枠から取り外すことを特徴としている。
The installation method of the three-way frame according to one embodiment is as follows:
A jig including a first member and a second member connected to each other by a connecting member is attached to a pair of vertical frames included in a three-way frame of an elevator, and the first member and the second member are used to Remove the connecting member, remove the second member from the three-way frame and the first member, place the three-way frame on a sill that forms a part of the floor surface of the landing doorway, The first member is fixed to the threshold and the first member is removed from the three-way frame.

一つの実施形態に係る治具が取り付けられた三方枠を示す斜視図。The perspective view which shows the three-way frame to which the jig | tool which concerns on one embodiment was attached. 実施形態の治具および三方枠を示す側面図。The side view which shows the jig | tool and three-way frame of embodiment. 実施形態の治具を示す斜視図。The perspective view which shows the jig | tool of embodiment. 実施形態の治具を分解して示す斜視図。The perspective view which decomposes | disassembles and shows the jig | tool of embodiment. 実施形態の第1の部材から第2の部材が取り外される状態を示す側面図。The side view showing the state where the 2nd member is removed from the 1st member of an embodiment. 実施形態の三方枠を敷居に載置する状態を示す斜視図。The perspective view which shows the state which mounts the three-way frame of embodiment on a threshold. 実施形態の三方枠が敷居に固定された状態を示す側面図。The side view which shows the state by which the three-way frame of embodiment was fixed to the threshold. 実施形態の三方枠から第1の部材が取り外される状態を示す側面図。The side view showing the state where the 1st member is removed from the three-way frame of an embodiment.

一つの実施形態について、図1ないし図8を参照して説明する。図1は、治具10が取り付けられたエレベータの三方枠11を示す斜視図である。図2は、治具10および三方枠11を示す側面図である。なお、本明細書において、三方枠11を建物に設置した場合における重力が作用する方向を下方向、その反対方向を上方向と定義する。   One embodiment will be described with reference to FIGS. FIG. 1 is a perspective view showing a three-way frame 11 of an elevator to which a jig 10 is attached. FIG. 2 is a side view showing the jig 10 and the three-way frame 11. In this specification, the direction in which gravity acts when the three-way frame 11 is installed in a building is defined as a downward direction, and the opposite direction is defined as an upward direction.

三方枠11は、建物に設置されることでエレベータの乗場出入口を形成する。図1に示すように、三方枠11が建物に据え付けられる前は、治具10が三方枠11に取り付けられる。   The three-way frame 11 is installed in a building to form an elevator entrance / exit. As shown in FIG. 1, the jig 10 is attached to the three-way frame 11 before the three-way frame 11 is installed in the building.

三方枠11は、一対の縦枠15,16と、幕板17とを備えている。一対の縦枠15,16は、ブラケット18と、壁部21と、乗場側縁部22と、昇降路側縁部23とをそれぞれ有している。   The three-way frame 11 includes a pair of vertical frames 15 and 16 and a curtain plate 17. The pair of vertical frames 15, 16 have a bracket 18, a wall portion 21, a landing side edge portion 22, and a hoistway side edge portion 23.

壁部21は、平坦な板状に形成されている。縦枠15の壁部21と、縦枠16の壁部21とは、互いに対向している。なお、一対の縦枠15,16は、例えばV字状のような他の配置をされても良い。   The wall portion 21 is formed in a flat plate shape. The wall portion 21 of the vertical frame 15 and the wall portion 21 of the vertical frame 16 face each other. It should be noted that the pair of vertical frames 15 and 16 may have other arrangements such as a V shape.

乗場側縁部22は、壁部21の一方の側縁に形成されている。昇降路側縁部23は、壁部21の他方の側縁に形成されている。乗場側縁部22と、昇降路側縁部23とは、それぞれ同じ方向に向かって曲げられている。図2に示すように、昇降路側縁部23の下方向の端部は、壁部21の下方向の端部から僅かに離れている。   The landing side edge portion 22 is formed on one side edge of the wall portion 21. The hoistway side edge portion 23 is formed on the other side edge of the wall portion 21. The landing side edge 22 and the hoistway side edge 23 are each bent in the same direction. As shown in FIG. 2, the lower end of the hoistway side edge 23 is slightly separated from the lower end of the wall 21.

図1に示すように、幕板17は、一対の縦枠15,16の間に設けられている。幕板17は、一対の縦枠15,16のそれぞれの乗場側縁部22に沿っている。幕板17は、一対の縦枠15,16のそれぞれの壁部21に密着して固定されている。   As shown in FIG. 1, the curtain plate 17 is provided between a pair of vertical frames 15 and 16. The curtain plate 17 extends along the landing side edge 22 of each of the pair of vertical frames 15 and 16. The curtain plate 17 is fixed in close contact with the respective wall portions 21 of the pair of vertical frames 15 and 16.

ブラケット18は、それぞれL字状に形成されている。ブラケット18は、固定部26と、締結部27とをそれぞれ有している。固定部26は、接着剤によって一対の縦枠15,16のそれぞれ壁部21に固定されている。   Each bracket 18 is formed in an L shape. The bracket 18 has a fixing part 26 and a fastening part 27. The fixing part 26 is fixed to the wall part 21 of each of the pair of vertical frames 15 and 16 by an adhesive.

締結部27は、固定部26からほぼ直角に曲げられている。締結部27は、縦枠15,16の下方向の端部にそれぞれ沿っている。図2に示すように、締結部27は、縦枠15,16の下方向の端部から僅かに離れて配置されている。締結部27の下方向の端部は、昇降路側縁部23の下方向の端部と同一平面上に配置されている。   The fastening portion 27 is bent from the fixed portion 26 at a substantially right angle. The fastening part 27 is along the downward direction edge part of the vertical frames 15 and 16, respectively. As shown in FIG. 2, the fastening portion 27 is disposed slightly apart from the lower ends of the vertical frames 15 and 16. The lower end of the fastening portion 27 is disposed on the same plane as the lower end of the hoistway side edge 23.

締結部27に、2つのボルト孔28と、1つのボルト孔29とがそれぞれ設けられている。ボルト孔29は、縦枠15,16のそれぞれの昇降路側縁部23の近傍に設けられている。   The fastening portion 27 is provided with two bolt holes 28 and one bolt hole 29. The bolt hole 29 is provided in the vicinity of the hoistway side edge 23 of each of the vertical frames 15 and 16.

図3は、治具10を示す斜視図である。図4は、治具10を分解して示す斜視図である。図4に示すように、治具10は、第1の部材31と、第2の部材32とを備えている。第1の部材31と、第2の部材32とは、ともに金属製である。   FIG. 3 is a perspective view showing the jig 10. FIG. 4 is an exploded perspective view showing the jig 10. As shown in FIG. 4, the jig 10 includes a first member 31 and a second member 32. Both the first member 31 and the second member 32 are made of metal.

第1の部材31は、第1の載置部35と、第1の片部36と、第2の片部37と、一対の補強部38とを備えている。第1の載置部35は、平坦な矩形状に形成されている。図1に示すように、第1の載置部35に縦枠15,16が置かれる。   The first member 31 includes a first placement portion 35, a first piece portion 36, a second piece portion 37, and a pair of reinforcing portions 38. The first placement portion 35 is formed in a flat rectangular shape. As shown in FIG. 1, the vertical frames 15 and 16 are placed on the first placement unit 35.

図3に示すように、第1の載置部35に、4つのボルト孔41が設けられている。4つのうち2つのボルト孔41は、第1の載置部35の一方の側部35aに沿って配置されている。残りのボルト孔41は、他方の側部35bに沿って配置されている。第1の載置部35のボルト孔41は、締結部27のボルト孔28にそれぞれ対応した位置に設けられている。   As shown in FIG. 3, the first mounting portion 35 is provided with four bolt holes 41. Two of the four bolt holes 41 are arranged along one side portion 35 a of the first placement portion 35. The remaining bolt holes 41 are arranged along the other side portion 35b. The bolt holes 41 of the first placement portion 35 are provided at positions corresponding to the bolt holes 28 of the fastening portion 27, respectively.

第1の片部36は、第1の載置部35の一方の端部に設けられている。第1の片部36は、第1の載置部35を折り曲げて形成されている。第1の片部36の下縁部36aは、直線状に形成されている。第1の片部36の一対の角部36bは、面取りを施されている。   The first piece 36 is provided at one end of the first placement portion 35. The first piece 36 is formed by bending the first placement portion 35. The lower edge portion 36a of the first piece portion 36 is formed in a straight line shape. The pair of corners 36b of the first piece 36 is chamfered.

第2の片部37は、第1の載置部35の他方の端部に設けられている。第2の片部37は、第1の載置部35を折り曲げて形成されている。第2の片部37は、第1の片部36と対向している。   The second piece portion 37 is provided at the other end portion of the first placement portion 35. The second piece portion 37 is formed by bending the first placement portion 35. The second piece 37 faces the first piece 36.

図2に示す第2の片部37の下縁部37aは、直線状に形成されている。図4に示すように、第2の片部37の一対の角部37bは、面取りを施されている。第2の片部37に、複数のボルト孔42が設けられている。   The lower edge portion 37a of the second piece portion 37 shown in FIG. 2 is formed in a straight line shape. As shown in FIG. 4, the pair of corners 37b of the second piece 37 is chamfered. A plurality of bolt holes 42 are provided in the second piece 37.

第1の部材31に、複数の第1の開口部43が設けられている。第1の開口部43は、開口部の一例である。第1の開口部43は、それぞれ第1の載置部35から第2の片部37に跨って設けられている。第1の開口部43は、人間が手を入れることができる大きさに形成されている。第1の開口部43は、第2の片部37の複数のボルト孔42のそれぞれに臨む位置に設けられている。第1の開口部43は、ボルト孔42をそれぞれ露出させる。   A plurality of first openings 43 are provided in the first member 31. The first opening 43 is an example of an opening. The first openings 43 are provided so as to straddle the first piece portion 35 and the second piece portion 37, respectively. The 1st opening part 43 is formed in the magnitude | size which a human can put in. The first opening 43 is provided at a position facing each of the plurality of bolt holes 42 of the second piece 37. The first openings 43 expose the bolt holes 42, respectively.

第2の部材32は、第2の載置部45と、第3の片部46と、第4の片部47とを備えている。第2の載置部45は、平坦な矩形状に形成されている。図1に示すように、第2の載置部45に縦枠15,16が置かれる。   The second member 32 includes a second placement portion 45, a third piece portion 46, and a fourth piece portion 47. The second placement portion 45 is formed in a flat rectangular shape. As shown in FIG. 1, vertical frames 15 and 16 are placed on the second placement portion 45.

図3に示すように、第2の載置部45に、一対のボルト孔51が設けられている。第2の載置部45のボルト孔51は、締結部27のボルト孔29にそれぞれ対応した位置に設けられている。一対のボルト孔51は、互いに近づく方向および互いに離れる方向にそれぞれ延びた長孔である。   As shown in FIG. 3, the second mounting portion 45 is provided with a pair of bolt holes 51. The bolt holes 51 of the second mounting portion 45 are provided at positions corresponding to the bolt holes 29 of the fastening portion 27, respectively. The pair of bolt holes 51 are long holes extending in a direction approaching each other and a direction away from each other.

図4に示すように、第3の片部46は、第2の載置部45の一方の端部に設けられている。第3の片部46は、第2の載置部45を折り曲げて形成されている。図2に示すように、第3の片部46は、第2の片部37に重ねられる。   As shown in FIG. 4, the third piece 46 is provided at one end of the second placement portion 45. The third piece 46 is formed by bending the second placement portion 45. As shown in FIG. 2, the third piece 46 is overlaid on the second piece 37.

図4に示すように、第3の片部46の下縁部46aは、直線状に形成されている。第3の片部46の一対の角部46bは、面取りを施されている。第3の片部46に、複数のボルト孔52が設けられている。第3の片部46のボルト孔52は、第2の片部37のボルト孔42にそれぞれ対応する位置に設けられている。   As shown in FIG. 4, the lower edge 46a of the third piece 46 is formed in a straight line. The pair of corners 46b of the third piece 46 are chamfered. The third piece 46 is provided with a plurality of bolt holes 52. The bolt holes 52 of the third piece 46 are provided at positions corresponding to the bolt holes 42 of the second piece 37, respectively.

第4の片部47は、第2の載置部45の他方の端部に設けられている。第4の片部47は、第2の載置部45を折り曲げて形成されている。第4の片部47は、第3の片部46と対向している。図2に示す第4の片部47の下縁部47aは、直線状に形成されている。第4の片部47の一対の角部47bは、面取りを施されている。   The fourth piece portion 47 is provided at the other end portion of the second placement portion 45. The fourth piece portion 47 is formed by bending the second placement portion 45. The fourth piece 47 faces the third piece 46. The lower edge 47a of the fourth piece 47 shown in FIG. 2 is formed in a straight line. A pair of corners 47b of the fourth piece 47 is chamfered.

第2の部材32に、複数の第2の開口部53が設けられている。第2の開口部53は、開口部の一例である。第2の開口部53は、それぞれ第2の載置部45から第3の片部46に跨って設けられている。第2の開口部53は、人間が手を入れることができる大きさに形成されている。第2の開口部53は、第3の片部46の複数のボルト孔52のそれぞれに臨む位置に設けられている。第2の開口部53は、ボルト孔52をそれぞれ露出させる。   A plurality of second openings 53 are provided in the second member 32. The second opening 53 is an example of an opening. The second openings 53 are provided so as to extend from the second placement portion 45 to the third piece portion 46, respectively. The 2nd opening part 53 is formed in the magnitude | size which a human can put in. The second opening 53 is provided at a position facing each of the plurality of bolt holes 52 of the third piece 46. The second openings 53 expose the bolt holes 52, respectively.

図2に示すように、一対の補強部38は、第1の片部36と第2の片部37との間に亘って設けられている。一対の補強部38は、第1の載置部35と、第1の片部36と、第2の片部37とにそれぞれ溶接されている。図4に示すように、一対の補強部38は、複数のボルト孔41よりも第1の載置部35の内側にそれぞれ配置されている。   As shown in FIG. 2, the pair of reinforcing portions 38 is provided between the first piece portion 36 and the second piece portion 37. The pair of reinforcing portions 38 are welded to the first placement portion 35, the first piece portion 36, and the second piece portion 37, respectively. As shown in FIG. 4, the pair of reinforcing portions 38 are respectively disposed inside the first placement portion 35 with respect to the plurality of bolt holes 41.

治具10は、第1の部材31と第2の部材32とを連結する複数の連結部材55をさらに備えている。図2に示すように、連結部材55は、第2の片部37のボルト孔42と、第3の片部46のボルト孔52とにそれぞれ挿通される。連結部材55によって、第2の片部37と第3の片部46とが取り外し可能に連結される。連結部材55として、例えばボルトおよびナットが適用される。   The jig 10 further includes a plurality of connecting members 55 that connect the first member 31 and the second member 32. As shown in FIG. 2, the connecting member 55 is inserted through the bolt hole 42 of the second piece 37 and the bolt hole 52 of the third piece 46. The second piece 37 and the third piece 46 are detachably connected by the connecting member 55. For example, a bolt and a nut are applied as the connecting member 55.

図3に示すように、複数の連結部材55は、第1の部材31の複数の第1の開口部43からそれぞれ露出される。さらに、複数の連結部材55は、第2の部材32の複数の第2の開口部53からそれぞれ露出される。このように、複数の第1の開口部43および複数の第2の開口部53は、複数の連結部材55に臨んでそれぞれ設けられている。   As shown in FIG. 3, the plurality of connecting members 55 are respectively exposed from the plurality of first openings 43 of the first member 31. Further, the plurality of connecting members 55 are exposed from the plurality of second openings 53 of the second member 32, respectively. As described above, the plurality of first openings 43 and the plurality of second openings 53 are respectively provided facing the plurality of connecting members 55.

治具10は、次のように三方枠11に取り付けられる。三方枠11の一対の縦枠15,16が、第1の載置部35および第2の載置部45にそれぞれ置かれる。この際、図2に示すように、締結部27のボルト孔28は、第1の載置部35のボルト孔41にそれぞれ重ねられる。さらに、締結部27のボルト孔29は、第2の載置部45のボルト孔51にそれぞれ重ねられる。   The jig 10 is attached to the three-way frame 11 as follows. A pair of vertical frames 15 and 16 of the three-way frame 11 are placed on the first placement portion 35 and the second placement portion 45, respectively. At this time, as shown in FIG. 2, the bolt holes 28 of the fastening portion 27 are overlapped with the bolt holes 41 of the first placement portion 35, respectively. Further, the bolt holes 29 of the fastening portion 27 are overlapped with the bolt holes 51 of the second placement portion 45, respectively.

締結部27のボルト孔28と、第1の載置部35のボルト孔41とに、固定部材57がそれぞれ挿通される。固定部材57として、例えばボルトおよびナットが適用される。固定部材57によって、第1の部材31が三方枠11のブラケット18に取り外し可能に固定される。   The fixing members 57 are inserted through the bolt holes 28 of the fastening portion 27 and the bolt holes 41 of the first placement portion 35, respectively. For example, a bolt and a nut are applied as the fixing member 57. The first member 31 is detachably fixed to the bracket 18 of the three-way frame 11 by the fixing member 57.

締結部27のボルト孔29と、第2の載置部45のボルト孔51とに、固定部材58がそれぞれ挿通される。固定部材58として、例えばボルトおよびナットが適用される。固定部材58によって、第2の部材32が三方枠11のブラケット18に取り外し可能に固定される。   The fixing members 58 are inserted through the bolt holes 29 of the fastening portion 27 and the bolt holes 51 of the second placement portion 45, respectively. For example, a bolt and a nut are applied as the fixing member 58. The second member 32 is detachably fixed to the bracket 18 of the three-way frame 11 by the fixing member 58.

次に、本実施形態の治具10を用いた三方枠11の設置方法の一例について説明する。工場で組立てられた三方枠11に、治具10が取り付けられる。治具10は、縦枠15,16の所定の相対位置を保って縦枠15,16に取り付けられる。   Next, an example of a method for installing the three-way frame 11 using the jig 10 of the present embodiment will be described. The jig 10 is attached to the three-way frame 11 assembled at the factory. The jig 10 is attached to the vertical frames 15 and 16 while maintaining a predetermined relative position between the vertical frames 15 and 16.

治具10が取り付けられた三方枠11は、図1に示すように床面Gに立てられた状態で据付現場に搬送される。第1の片部36の下縁部36a、第2の片部37の下縁部37a、第3の片部46の下縁部46a、および第4の片部47の下縁部47aは、それぞれ同一平面上で直線状に形成されている。このため、三方枠11は床面Gに対して真直ぐ立てられることができる。   The three-way frame 11 to which the jig 10 is attached is transported to the installation site while standing on the floor G as shown in FIG. The lower edge portion 36a of the first piece portion 36, the lower edge portion 37a of the second piece portion 37, the lower edge portion 46a of the third piece portion 46, and the lower edge portion 47a of the fourth piece portion 47 are: Each is formed linearly on the same plane. For this reason, the three-way frame 11 can stand upright with respect to the floor G.

図5は、第1の部材31から第2の部材32が取り外される状態を示す側面図である。三方枠11が据付現場に搬送されると、複数の固定部材58が、締結部27および第2の部材32からそれぞれ取り外される。さらに、複数の連結部材55が、第1の部材31および第2の部材32からそれぞれ取り外される。   FIG. 5 is a side view showing a state where the second member 32 is removed from the first member 31. When the three-way frame 11 is transported to the installation site, the plurality of fixing members 58 are removed from the fastening portion 27 and the second member 32, respectively. Further, the plurality of connecting members 55 are detached from the first member 31 and the second member 32, respectively.

連結部材55は、第1の開口部43または第2の開口部53に挿通されたレンチのような工具によってそれぞれ取り外される。なお、連結部材55は、第1の開口部43または第2の開口部53に挿通された作業者の手によって取り外されても良く、他の手段よって取り外されても良い。   The connecting member 55 is removed by a tool such as a wrench inserted through the first opening 43 or the second opening 53, respectively. The connecting member 55 may be removed by the operator's hand inserted through the first opening 43 or the second opening 53, or may be removed by other means.

図5に示すように、第2の部材32は、三方枠11および第1の部材31から取り外される。第2の部材32が取り外されても、第1の部材31は三方枠11に取り付けられている。このため、第1の部材31は、一対の縦枠15,16の所定の相対位置を保つ。   As shown in FIG. 5, the second member 32 is detached from the three-way frame 11 and the first member 31. Even if the second member 32 is removed, the first member 31 is attached to the three-way frame 11. For this reason, the first member 31 maintains a predetermined relative position between the pair of vertical frames 15 and 16.

図6は、三方枠11を敷居61に載置する状態を示す斜視図である。図6に示すように、据付現場に乗場62と昇降路63とを隔てる壁64が設けられている。昇降路63は、エレベータの乗籠が昇降する通路である。   FIG. 6 is a perspective view showing a state where the three-way frame 11 is placed on the threshold 61. As shown in FIG. 6, a wall 64 that separates the landing 62 and the hoistway 63 is provided at the installation site. The hoistway 63 is a passage through which the elevator ride goes up and down.

壁64に、設置部66が設けられている。設置部66は、壁64に開口する孔である。設置部66は、エレベータの乗籠が着床する階床ごとに設けられている。設置部66は、三方枠11を立てて通すことができる大きさに形成されている。   An installation part 66 is provided on the wall 64. The installation portion 66 is a hole that opens in the wall 64. The installation unit 66 is provided for each floor on which the elevator rides. The installation part 66 is formed in a size that allows the three-way frame 11 to pass upright.

敷居61は、乗場出入口の床面の一部を形成する。敷居61は、設置部66に隣接して壁64に固定されている。敷居61は、壁64から昇降路63に飛び出すように配置されている。なお、敷居61は、設置部66の下面66aに固定されていても良い。   The threshold 61 forms a part of the floor of the hall entrance / exit. The threshold 61 is fixed to the wall 64 adjacent to the installation portion 66. The sill 61 is arranged so as to jump out from the wall 64 to the hoistway 63. The threshold 61 may be fixed to the lower surface 66a of the installation part 66.

敷居61の上面61aは、設置部66の下面66aよりも上方向に配置されている。敷居61の上面61aに、乗場62に取り付けられるドアが沿って動くレールが形成されている。   The upper surface 61 a of the sill 61 is disposed above the lower surface 66 a of the installation portion 66. A rail on which a door attached to the landing 62 moves is formed on the upper surface 61 a of the threshold 61.

敷居61は、一対の載置部材71を有している。一対の載置部材71は、敷居61の乗場62に面した端部61bに固定されている。一対の載置部材71は、それぞれL字状に形成されており、平坦な載置面72を有している。載置面72は、敷居61の上面61aと同一平面上に形成されている。   The threshold 61 has a pair of placement members 71. The pair of mounting members 71 are fixed to end portions 61 b facing the landing 62 of the sill 61. The pair of placement members 71 are each formed in an L shape and have a flat placement surface 72. The mounting surface 72 is formed on the same plane as the upper surface 61 a of the threshold 61.

一対の載置部材71の載置面72に、ボルト孔73がそれぞれ設けられている。一対のボルト孔73は、互いに近づく方向および互いに離れる方向にそれぞれ延びた長孔である。一対のボルト孔73は、締結部27の一対のボルト孔29にそれぞれ対応する位置に設けられている。   Bolt holes 73 are respectively provided in the mounting surfaces 72 of the pair of mounting members 71. The pair of bolt holes 73 are long holes extending in a direction approaching each other and a direction away from each other. The pair of bolt holes 73 are provided at positions corresponding to the pair of bolt holes 29 of the fastening portion 27.

図6に示すように、三方枠11が敷居61の上に載置される。これにより、ブラケット18のそれぞれの締結部27が、載置面72の上に載置される。上記のように、載置面72は敷居61に含まれる。この際、締結部27のボルト孔29と、載置部材71のボルト孔73とが重ねられる。   As shown in FIG. 6, the three-way frame 11 is placed on the threshold 61. Thereby, each fastening portion 27 of the bracket 18 is placed on the placement surface 72. As described above, the mounting surface 72 is included in the threshold 61. At this time, the bolt hole 29 of the fastening portion 27 and the bolt hole 73 of the mounting member 71 are overlapped.

三方枠11が敷居61の上に載置されると、複数の取付金具によって縦枠15,16が設置部66の側面66bに繋がれる。当該取付金具は、設置部66の側面66bにそれぞれ固定されるとともに、縦枠15,16にそれぞれ取り付けられる。当該取付金具は、三方枠11を支持する。   When the three-way frame 11 is placed on the sill 61, the vertical frames 15 and 16 are connected to the side surface 66b of the installation portion 66 by a plurality of mounting brackets. The mounting brackets are fixed to the side surfaces 66b of the installation portion 66 and attached to the vertical frames 15 and 16, respectively. The mounting bracket supports the three-way frame 11.

図7は、三方枠11が敷居61に固定された状態を示す側面図である。締結部27のボルト孔29と、載置部材71のボルト孔73とに、固定部材75が挿通される。固定部材75として、例えばボルトおよびナットが適用される。固定部材75によって、締結部27が載置部材71に固定される。これにより、三方枠11が敷居61に固定される。なお、前述した取付金具によって縦枠15,16を設置部66に繋ぐ作業は、三方枠11が敷居61に固定された後に行なわれても良い。   FIG. 7 is a side view showing a state in which the three-way frame 11 is fixed to the sill 61. The fixing member 75 is inserted into the bolt hole 29 of the fastening portion 27 and the bolt hole 73 of the mounting member 71. For example, a bolt and a nut are applied as the fixing member 75. The fastening portion 27 is fixed to the mounting member 71 by the fixing member 75. As a result, the three-way frame 11 is fixed to the threshold 61. In addition, the operation | work which connects the vertical frames 15 and 16 to the installation part 66 with the mounting bracket mentioned above may be performed after the three-way frame 11 is fixed to the sill 61. FIG.

図8は、三方枠11から第1の部材31が取り外される状態を示す側面図である。三方枠11が敷居61に固定されると、複数の固定部材57が締結部27および第1の部材31からそれぞれ取り外される。   FIG. 8 is a side view showing a state in which the first member 31 is removed from the three-way frame 11. When the three-way frame 11 is fixed to the sill 61, the plurality of fixing members 57 are removed from the fastening portion 27 and the first member 31, respectively.

図8に示すように、第1の部材31は、三方枠11から取り外される。第1の部材31が取り外されても、三方枠11は敷居61に固定されている。このため、一対の縦枠15,16は、所定の相対位置を保つ。
以上説明したように、三方枠11が敷居61に設置される。
As shown in FIG. 8, the first member 31 is removed from the three-way frame 11. Even when the first member 31 is removed, the three-way frame 11 is fixed to the threshold 61. For this reason, a pair of vertical frames 15 and 16 maintain a predetermined relative position.
As described above, the three-way frame 11 is installed on the threshold 61.

前記構成の治具10および治具10を用いた三方枠11の設置方法の一例によれば、第2の部材32が取り外されても、第1の部材31が三方枠11に取り付けられている。さらに、第1の部材31が取り外されても、三方枠11は敷居61に固定されている。これにより、一対の縦枠15,16は、所定の相対位置に保たれる。したがって、一対の縦枠15,16の相対位置のずれを防止できる。   According to the example of the jig 10 having the above-described configuration and the installation method of the three-way frame 11 using the jig 10, the first member 31 is attached to the three-way frame 11 even when the second member 32 is removed. . Furthermore, even if the first member 31 is removed, the three-way frame 11 is fixed to the threshold 61. Thereby, a pair of vertical frames 15 and 16 are maintained at a predetermined relative position. Accordingly, it is possible to prevent the relative positions of the pair of vertical frames 15 and 16 from being shifted.

第1の開口部43および第2の開口部53は、連結部材55をそれぞれ露出させる。これにより、連結部材55が第1の部材31および第2の部材32から取り外される際に、連結部材55が目視される。したがって、三方枠11を設置する作業が容易になる。   The first opening 43 and the second opening 53 expose the connecting member 55, respectively. Thereby, when the connecting member 55 is removed from the first member 31 and the second member 32, the connecting member 55 is visually observed. Therefore, the operation of installing the three-way frame 11 is facilitated.

第1の片部36の一対の角部36b、第2の片部37の一対の角部37b、第3の片部46の一対の角部46b、および第4の片部47の一対の角部47bは、それぞれ面取りを施されている。これにより、治具10が取り付けられた三方枠11を据付現場に搬送する際、治具10が床面に引っ掛かることを防止できる。したがって、三方枠11を設置する作業が容易になる。   A pair of corners 36 b of the first piece 36, a pair of corners 37 b of the second piece 37, a pair of corners 46 b of the third piece 46, and a pair of corners of the fourth piece 47 Each portion 47b is chamfered. Thereby, when conveying the three-way frame 11 to which the jig 10 is attached to the installation site, the jig 10 can be prevented from being caught on the floor surface. Therefore, the operation of installing the three-way frame 11 is facilitated.

本発明の実施形態を説明したが、この実施形態は、例として提示したものであり、発明の範囲を限定することは意図していない。この新規な実施形態は、その他の様々な形態で実施されることが可能であり、発明の要旨を逸脱しない範囲で、種々の省略、置き換え、変更を行うことができる。この実施形態やその変形は、発明の範囲や要旨に含まれるとともに、特許請求の範囲に記載された発明とその均等の範囲に含まれる。   Although the embodiment of the present invention has been described, this embodiment is presented as an example and is not intended to limit the scope of the invention. The novel embodiment can be implemented in various other forms, and various omissions, replacements, and changes can be made without departing from the scope of the invention. This embodiment and its modifications are included in the scope and gist of the invention, and are included in the invention described in the claims and the equivalents thereof.

10…治具,11…三方枠,15,16…縦枠,31…第1の部材,32…第2の部材,35…第1の載置部,36…第1の片部,36b,37b,46b,47b…角部,37…第2の片部,43…第1の開口部,45…第2の載置部,46…第3の片部,47…第4の片部,53…第2の開口部,55…連結部材,61…敷居。   DESCRIPTION OF SYMBOLS 10 ... Jig, 11 ... Three-way frame, 15, 16 ... Vertical frame, 31 ... 1st member, 32 ... 2nd member, 35 ... 1st mounting part, 36 ... 1st piece part, 36b, 37b, 46b, 47b ... corner, 37 ... second piece, 43 ... first opening, 45 ... second mounting part, 46 ... third piece, 47 ... fourth piece, 53 ... 2nd opening part, 55 ... Connecting member, 61 ... Sill.

Claims (1)

連結部材によって互いに連結された第1の部材と第2の部材とを含む治具を、エレベータの三方枠に含まれる一対の縦枠に取り付け、
前記第1の部材および前記第2の部材から前記連結部材を取り外し、
前記第2の部材を前記三方枠および前記第1の部材から取り外し、
前記三方枠を乗場出入口の床面の一部を形成する敷居の上に載置し、
前記三方枠を前記敷居に固定し、
前記第1の部材を前記三方枠から取り外す三方枠の設置方法。
A jig including a first member and a second member connected to each other by a connecting member is attached to a pair of vertical frames included in a three-way frame of the elevator,
Removing the connecting member from the first member and the second member;
Removing the second member from the three-way frame and the first member;
Place the three-way frame on a sill that forms part of the floor of the landing entrance,
Fixing the three-way frame to the threshold,
A three-way frame installation method for removing the first member from the three-way frame.
JP2010155148A 2010-07-07 2010-07-07 How to install the three-sided frame Active JP5570893B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010155148A JP5570893B2 (en) 2010-07-07 2010-07-07 How to install the three-sided frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010155148A JP5570893B2 (en) 2010-07-07 2010-07-07 How to install the three-sided frame

Publications (2)

Publication Number Publication Date
JP2012017174A JP2012017174A (en) 2012-01-26
JP5570893B2 true JP5570893B2 (en) 2014-08-13

Family

ID=45602712

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010155148A Active JP5570893B2 (en) 2010-07-07 2010-07-07 How to install the three-sided frame

Country Status (1)

Country Link
JP (1) JP5570893B2 (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07215644A (en) * 1994-01-31 1995-08-15 Toshiba Erebeeta Technos Kk Elevator gateway access device
JP3944867B2 (en) * 1996-09-04 2007-07-18 東芝エレベータ株式会社 Elevator hall three-way transportation aid

Also Published As

Publication number Publication date
JP2012017174A (en) 2012-01-26

Similar Documents

Publication Publication Date Title
JP6223571B2 (en) Elevator cab and its assembly method
JP5198664B2 (en) Elevator door glass plate fixing device
JP5058269B2 (en) Elevator car and its installation method
JP2006248632A (en) Jamb of elevator
JP5570893B2 (en) How to install the three-sided frame
JP2007161447A (en) Skirt guard device of passenger conveyor
KR20200006325A (en) Scaffold connecting bracket
JP6925600B2 (en) Guide rail structure of the opening and closing body
JP4902597B2 (en) Elevator car structure
JP2016050102A (en) Temporary work floor device for elevator
JP6218161B2 (en) Elevator Fesher Plate and Assembling Method of Fesher Plate
JP5638383B2 (en) Elevator car handrail device
JP2012017175A (en) Jamb and method for installing the same
JP4528311B2 (en) Top hanging rail sliding door
JP5920675B2 (en) Elevator curtain panel assembly and renewal elevator panel installation method
JP6210776B2 (en) Passenger conveyor skirt guard attaching / detaching device
JP2018167952A (en) Passenger conveyor
WO2018083760A1 (en) Smoke-blocking landing sill extension device for elevator doors
JP6716042B2 (en) Elevator hall equipment
JP5361218B2 (en) Elevator door equipment
JP2010159573A (en) Running board for scaffolding
JP5698038B2 (en) Curing device in clean room
JP2006044843A (en) Working bench scaffold for hoistway
JP5634097B2 (en) Partition system
JP4403743B2 (en) Door device with smoke barrier

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20121004

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20130828

A977 Report on retrieval

Effective date: 20131010

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Effective date: 20131015

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Effective date: 20131213

Free format text: JAPANESE INTERMEDIATE CODE: A523

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140527

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140625

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Country of ref document: JP

Ref document number: 5570893