JP5443928B2 - Method for constructing soil cement structure, soil cement structure - Google Patents

Method for constructing soil cement structure, soil cement structure Download PDF

Info

Publication number
JP5443928B2
JP5443928B2 JP2009227987A JP2009227987A JP5443928B2 JP 5443928 B2 JP5443928 B2 JP 5443928B2 JP 2009227987 A JP2009227987 A JP 2009227987A JP 2009227987 A JP2009227987 A JP 2009227987A JP 5443928 B2 JP5443928 B2 JP 5443928B2
Authority
JP
Japan
Prior art keywords
soil cement
constructing
soil
rod
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2009227987A
Other languages
Japanese (ja)
Other versions
JP2011074675A (en
Inventor
正 金子
敏己 須藤
伴師 横山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2009227987A priority Critical patent/JP5443928B2/en
Publication of JP2011074675A publication Critical patent/JP2011074675A/en
Application granted granted Critical
Publication of JP5443928B2 publication Critical patent/JP5443928B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Earth Drilling (AREA)

Description

本発明は、複数のソイルセメント柱が連結されてなるソイルセメント構造体の構築方法に関する。   The present invention relates to a method for constructing a soil cement structure in which a plurality of soil cement columns are connected.

従来より、山留め壁としてソイルセメント壁、特に、円柱状のソイルセメント柱が連結されてなるソイルセメント柱列壁が広く用いられている(例えば、特許文献1参照)。かかるソイルセメント柱列壁は、隣接するソイルセメント柱同士を部分的に重なり合うように構築することにより一体に構築される。   Conventionally, a soil cement wall, in particular, a soil cement column wall formed by connecting cylindrical soil cement columns, is widely used as a retaining wall (see, for example, Patent Document 1). Such a soil cement pillar row wall is constructed integrally by constructing adjacent soil cement pillars so as to partially overlap each other.

特開2009―57682号公報JP 2009-57682 A

しかしながら、上記のようにソイルセメント柱同士を部分的に重なり合うように構築するためには、一方のソイルセメント柱が硬化した後、これに隣接する他方のソイルセメント柱に相当する部分を掘削する際に、硬化した一方のソイルセメント柱の側部を切削しなければならない。このため、掘削装置として硬質のソイルセメント柱を掘削可能な大型の装置を用いる必要があり、狭隘な敷地での施工が困難になる。   However, in order to construct the soil cement columns so as to partially overlap each other as described above, after one soil cement column is hardened, when excavating a portion corresponding to the other soil cement column adjacent thereto. In addition, the side of one of the hardened soil cement columns must be cut. For this reason, it is necessary to use a large apparatus capable of excavating a hard soil cement column as an excavating apparatus, and construction on a narrow site becomes difficult.

本発明は、上記の問題に鑑みなされたものであり、その目的は、狭隘な敷地において、ソイルセメント柱が連結されてなるソイルセメント構造物を構築できるようにすることである。   This invention is made | formed in view of said problem, The objective is to enable it to construct | assemble the soil cement structure by which a soil cement pillar is connected in a narrow site.

本発明のソイルセメント構造物の構築方法は、複数のソイルセメント柱が連結されてなるソイルセメント構造物を構築する方法であって、使用する地盤改良装置は、ロッド、該ロッドに起振力を与える起振装置、前記ロッドを回転させる回転装置、及び前記ロッドの先端に設けられた掘削ビットを備える単軸の装置であり、前記掘削ビットは、前記ロッドの先端から延びセメントミルクを排出する軸部、該軸部の先端部に側方に延びるように設けられた掘削翼本体、該掘削翼本体に設けられたビット、前記軸部における前記掘削翼本体より上側に外周に向かって延びるように設けられた複数の攪拌翼を備え、隣接するソイルセメント柱のうち一方を構築する第1のステップと、前記掘削ビットを前記起振装置により振動させながら前記回転装置により回転させることで、前記一方のソイルセメント柱の側部を切削するとともに、他方のソイルセメント柱に相当する部分に、前記軸部からセメントミルクを噴射しながら削孔攪拌することで、他方のソイルセメント柱を構築する第2のステップとを備え、前記ソイルセメント構造物は、3つ以上のソイルセメント柱が連結されてなり、前記第1のステップでは、前記ソイルセメント柱を一つおきに構築し、前記第2のステップでは、残りのソイルセメント柱を構築することを特徴とする。
なお、上記の「他方のソイルセメント柱に相当する部分に、セメントミルクを噴射しながら削孔攪拌する」とは、他方のソイルセメント柱に相当する部分にセメントミルクを噴射するとともに地盤を削孔攪拌する場合、及び、他方のソイルセメント柱に相当する部分を削工攪拌した後、セメントミルクを噴射しながら掘削土とセメントミルクを攪拌する場合を含む。
The method for constructing a soil cement structure according to the present invention is a method for constructing a soil cement structure in which a plurality of soil cement pillars are connected, and the ground improvement device to be used includes a rod and a vibration force applied to the rod. An exciter for applying, a rotating device for rotating the rod, and a single-shaft device provided with a drilling bit provided at the tip of the rod, the drilling bit extending from the tip of the rod and discharging the cement milk An excavation blade body provided to extend laterally at the tip of the shaft portion, a bit provided on the excavation blade main body, and extending toward the outer periphery above the excavation blade body in the shaft portion comprising a plurality of stirring blades provided, a first step of constructing the one of the adjacent soil cement pillar, the rotary instrumentation while vibrating the drill bit by the exciter device By By rotating, thereby cutting the sides of the one soil cement pillar, a portion corresponding to the other of the soil cement pillar, from the shaft portion by stirring drilled while spraying the cement milk, the other A second step of constructing a soil cement pillar , wherein the soil cement structure is formed by connecting three or more soil cement pillars, and in the first step, every other one of the soil cement pillars is connected. constructs, wherein in the second step, characterized that you build the remaining soil cement pillar.
The above-mentioned “stirring while drilling cement milk into the portion corresponding to the other soil cement column” means that the cement milk is injected into the portion corresponding to the other soil cement column and the ground is drilled. It includes the case of stirring, and the case of stirring the excavated soil and the cement milk while spraying the cement milk after the portion corresponding to the other soil cement column is shaved and stirred.

また、前記複数のソイルセメント柱を円環状に構築してもよい。
また、本発明のソイルセメント構造物は、上記の方法により構築されたことを特徴とする。
また、本発明の場所打ち杭の構築方法は、請求項1に記載のソイルセメント構造物の構築方法を用いて、前記複数のソイルセメント柱が円環状に並んだソイルセメント壁を構築する工程と、前記ソイルセメント壁の内側を、TBH工法で用いられる掘削機により孔内に安定液を満たした状態で掘削する工程と、掘削した孔内に配筋しコンクリートを打設する工程とを備えることを特徴とする。
Further, the plurality of soil cement columns may be constructed in an annular shape.
The soil cement structure of the present invention is constructed by the above method.
Moreover, the construction method of the cast-in-place pile of this invention uses the construction method of the soil-cement structure of Claim 1, and the process of constructing | assembling the soil-cement wall in which these several soil-cement pillars arranged in the annular | circular shape, And a step of excavating the inside of the soil cement wall in a state in which the hole is filled with a stabilizing liquid by an excavator used in the TBH method, and a step of arranging the concrete in the excavated hole and placing concrete. It is characterized by.

本発明によれば、起振装置により上下に起振力を加えながら掘削ビットを回転させて掘削を行うため、小型の掘削装置であっても、先行して構築されたソイルセメント柱の側部を切削しながら、地盤を掘削することが可能となる。これにより、狭隘な敷地においても、隣接するソイルセメント柱同士を互いに部分的に重なり合うように構築することができ、ソイルセメント柱が連結されてなるソイルセメント構造物を構築することができる。   According to the present invention, excavation is performed by rotating the excavation bit while applying an exciter force up and down by the exciter, so even if it is a small excavator, the side portion of the soil cement column constructed in advance The ground can be excavated while cutting. Thereby, even in a narrow site, adjacent soil cement columns can be constructed so as to partially overlap each other, and a soil cement structure in which the soil cement columns are connected can be constructed.

地盤改良装置を示す図である。It is a figure which shows a ground improvement apparatus. 掘削ビットの詳細な構成を示し、(A)は正面図、(B)は側面図、(C)は見上げ図である。The detailed structure of a drill bit is shown, (A) is a front view, (B) is a side view, (C) is a top view. 本実施形態の場所打ち杭の構築方法を説明するための図(その1)である。It is a figure (the 1) for demonstrating the construction method of the cast-in-place pile of this embodiment. 本実施形態の場所打ち杭の構築方法を説明するための図(その2)である。It is FIG. (2) for demonstrating the construction method of the cast-in-place pile of this embodiment. 本実施形態の場所打ち杭の構築方法を説明するための図(その3)である。It is a figure (the 3) for demonstrating the construction method of the cast-in-place pile of this embodiment. 本実施形態の場所打ち杭の構築方法を説明するための図(その4)である。It is FIG. (4) for demonstrating the construction method of the cast-in-place pile of this embodiment. ソイルセメント壁を構築する方法を説明するための図である。It is a figure for demonstrating the method to construct | assemble a soil cement wall. ソイルセメント柱を構築する様子を示す鉛直断面図である。It is a vertical sectional view which shows a mode that a soil cement pillar is constructed | assembled.

以下、本発明のソイルセメント構造物の構築方法の一実施形態を図面を参照しながら説明する。なお、以下の説明では、ソイルセメント構造物として場所打ち杭を構築するための土留め壁を構築する場合を例として説明する。
まず、本実施形態においてソイルセメント構造物を構築するために用いられる地盤改良装置について説明する。図1は地盤改良装置10を示す図である。同図に示すように、地盤改良装置10はキャタピラからなる移動機構20と、移動機構20上に設置された台座部30と、台座部30により鉛直に延びるように支持された案内部40と、案内部40に取り付けられた起振装置50と、起振装置50に接続されたロッド70と、ロッド70を回転させる回転装置60と、ロッド70の先端に取り付けられた掘削ビット80と、ロッド70の内部を通じて掘削ビット80の先端からセメントミルクを排出するセメントミルク供給装置90とを備える。
Hereinafter, an embodiment of a method for constructing a soil cement structure according to the present invention will be described with reference to the drawings. In addition, in the following description, the case where the earth retaining wall for constructing a cast-in-place pile as a soil cement structure is constructed is described as an example.
First, a ground improvement device used for constructing a soil cement structure in the present embodiment will be described. FIG. 1 is a diagram showing a ground improvement device 10. As shown in the figure, the ground improvement device 10 includes a moving mechanism 20 composed of a caterpillar, a pedestal portion 30 installed on the moving mechanism 20, and a guide portion 40 supported by the pedestal portion 30 so as to extend vertically. Exciter 50 attached to guide 40, rod 70 connected to exciter 50, rotating device 60 for rotating rod 70, excavation bit 80 attached to the tip of rod 70, rod 70 And a cement milk supply device 90 for discharging cement milk from the tip of the excavation bit 80 through the inside of the drill bit.

起振装置50は、例えば、偏芯重錘を回転させることにより生じた起振力をロッド70に伝達する装置である。ロッド70に伝達する起振力は、上下方向又は横方向のうち少なくとも何れかの成分を含んでいればよいが、起振装置50を用いた場合には両方の成分を含むことになる。起振装置50は、ロッド70及び回転装置60とともに案内部40に沿って移動可能である。
回転装置60は、ロッド70にその軸を中心とした回転力を加える装置である。
The vibration generating device 50 is a device that transmits a vibration generating force generated by rotating an eccentric weight to the rod 70, for example. The vibration force transmitted to the rod 70 only needs to include at least one component in the vertical direction or the horizontal direction, but when the vibration generator 50 is used, both components are included. The vibration generating device 50 is movable along the guide portion 40 together with the rod 70 and the rotating device 60.
The rotating device 60 is a device that applies a rotational force about the axis to the rod 70.

図2は、掘削ビット80の詳細な構成を示し、(A)は正面図、(B)は側面図、(C)は下面図である。同図に示すように、掘削ビット80は、ロッド70に接続される軸部81と、軸部81の先端部に側方に延びるように取り付けられた掘削翼本体83と、掘削翼本体83に取り付けられたビット84と、外周に向かって延びるように軸部81に接続された複数の攪拌翼82と、軸部81の先端に取り付けられたビット85とを備える。セメントミルク供給装置90によりロッド70を通じて供給されたセメントミルクは、軸部81の先端から排出される。   2A and 2B show a detailed configuration of the excavation bit 80, where FIG. 2A is a front view, FIG. 2B is a side view, and FIG. 2C is a bottom view. As shown in the drawing, the excavation bit 80 includes a shaft portion 81 connected to the rod 70, a drill blade main body 83 attached to the tip of the shaft portion 81 so as to extend laterally, and a drill blade main body 83. A bit 84 attached, a plurality of stirring blades 82 connected to the shaft portion 81 so as to extend toward the outer periphery, and a bit 85 attached to the tip of the shaft portion 81 are provided. The cement milk supplied through the rod 70 by the cement milk supply device 90 is discharged from the tip of the shaft portion 81.

地盤改良装置10は、回転装置60によりロッド70を介して、掘削ビット80を回転させることで、掘削翼本体83に取り付けられたビット84により地盤を掘削することができる。また、セメントミルク供給装置90により、掘削孔内にセメントミルクを噴射するとともに、掘削ビット80が回転することで、攪拌翼82がセメントミルクと掘削土とを混合攪拌し、ソイルセメントを形成することができる。   The ground improvement device 10 can excavate the ground by the bit 84 attached to the excavation blade main body 83 by rotating the excavation bit 80 through the rod 70 by the rotation device 60. Further, the cement milk is sprayed into the excavation hole by the cement milk supply device 90, and the excavation bit 80 rotates so that the agitating blade 82 mixes and agitates the cement milk and the excavated soil to form a soil cement. Can do.

図3A〜図3Dは、本実施形態の場所打ち杭の構築方法を説明するための図である。なお、図3A(A)及び図3B〜図3Dは鉛直断面図、図3A(B)は同図(A)におけるI−I断面図である。   Drawing 3A-Drawing 3D are figures for explaining a construction method of a cast-in-place pile of this embodiment. 3A (A) and FIGS. 3B to 3D are vertical cross-sectional views, and FIG. 3A (B) is a cross-sectional view taken along the line II in FIG. 3 (A).

以下、上記の地盤改良装置10を用いて場所打ち杭を構築する方法を説明する。
まず、図3Aに示すように、場所打ち杭の構築位置の周囲に相当する位置に円筒状のソイルセメント壁100を構築する。ソイルセメント壁100は、複数の円柱状のソイルセメント柱110が環状に連結されてなる。これらソイルセメント柱110は、隣接するソイルセメント柱110の中心間の距離がソイルセメント柱110の直径よりも小さく、各ソイルセメント柱110の両側部が隣接するソイルセメント柱110と部分的に重なり合うように構築されている。また、ソイルセメント壁100は、下端が地下水位よりも低い深さまで到達している。
Hereinafter, a method for constructing a cast-in-place pile using the ground improvement device 10 will be described.
First, as shown in FIG. 3A, a cylindrical soil cement wall 100 is constructed at a position corresponding to the circumference of the construction position of the cast-in-place pile. The soil cement wall 100 is formed by connecting a plurality of cylindrical soil cement columns 110 in an annular shape. These soil cement pillars 110 are such that the distance between the centers of adjacent soil cement pillars 110 is smaller than the diameter of the soil cement pillars 110 so that both sides of each soil cement pillar 110 partially overlap the adjacent soil cement pillars 110. Has been built. In addition, the soil cement wall 100 has a lower end reaching a depth lower than the groundwater level.

なお、ソイルセメント柱110としては、例えば、直径2500mm程度の場所打ち杭を構築する場合には、直径600mm程度とすればよい。また、後述するように、ソイルセメント壁100に周囲の地盤から圧縮荷重が作用した際に、ソイルセメント柱110同士の間でこの圧縮荷重を伝達することができるように、隣接するソイルセメント柱110の互いに重なり合う部分の幅(後述する、図4(B)におけるD)を、例えば、150mm程度としてもよい。ただし、ソイルセメント柱110の直径や重なり合う部分の幅はこれらに限定されるものではない。   As the soil cement pillar 110, for example, when a cast-in-place pile having a diameter of about 2500 mm is constructed, the diameter may be about 600 mm. Further, as will be described later, when a compressive load is applied to the soil cement wall 100 from the surrounding ground, the adjacent soil cement columns 110 can be transmitted between the soil cement columns 110. The width of the overlapping portions (D in FIG. 4B described later) may be, for example, about 150 mm. However, the diameter of the soil cement pillar 110 and the width of the overlapping portion are not limited to these.

図4は、かかるソイルセメント壁100を構築する方法を説明するための図である。まず、図4(A)に示すように、ソイルセメント壁100を構成するソイルセメント柱110Aを一つおきに構築していく。   FIG. 4 is a view for explaining a method of constructing such a soil cement wall 100. First, as shown in FIG. 4A, every other soil cement pillar 110A constituting the soil cement wall 100 is constructed.

図5は、ソイルセメント柱110を構築する様子を示す鉛直断面図である。同図に示すように、地盤改良装置10の回転装置60によりロッド70を介して掘削ビット80を毎分20〜60回転の速度で回転させながら、下端が支持層3の上部に到達するまで地盤1を掘削して掘削孔4を形成する。この際、起振装置50によりロッド70を介して掘削ビット80に例えば、20〜50Hz程度の起振力を加える。これにより、掘削ビット80も上下に振動するため、切削効率が向上する。また、掘削ビット80が上下に振動し、この振動が地盤1に伝達されることで、地盤1中の大きな礫や岩が振動により移動するため容易に掘削を行える。   FIG. 5 is a vertical sectional view showing how the soil cement pillar 110 is constructed. As shown in the figure, the ground until the lower end reaches the upper part of the support layer 3 while rotating the excavation bit 80 through the rod 70 at a speed of 20 to 60 revolutions per minute by the rotation device 60 of the ground improvement device 10 1 is excavated to form an excavation hole 4. At this time, for example, a vibration force of about 20 to 50 Hz is applied to the excavation bit 80 through the rod 70 by the vibration generator 50. Thereby, since the excavation bit 80 also vibrates up and down, cutting efficiency improves. Moreover, since the excavation bit 80 vibrates up and down and this vibration is transmitted to the ground 1, excavation can be easily performed because large gravel and rock in the ground 1 move by vibration.

また、上記の掘削作業と平行して、セメントミルク供給装置90により、ロッド70の内部を通じて掘削孔4内にセメントミルクを噴射する。掘削ビット80の下方の地盤1にはロッド70の先端からセメントミルクが噴射されるとともに掘削ビット80から起振力が伝達されることで、地盤1がセメントミルクを含んだ状態で振動することで液状化して軟化するため、掘削ビット80により容易に切削することができる。このように、地盤改良装置10によれば、起振装置50により起振力が加えられることで掘削ビット80による掘削効率が向上する。   In parallel with the excavation work, cement milk is injected into the excavation hole 4 through the inside of the rod 70 by the cement milk supply device 90. Cement milk is sprayed from the tip of the rod 70 to the ground 1 below the excavation bit 80 and an exciter force is transmitted from the excavation bit 80, so that the ground 1 vibrates in a state containing cement milk. Since it is liquefied and softened, it can be easily cut by the excavation bit 80. As described above, according to the ground improvement device 10, excavation efficiency by the excavation bit 80 is improved by applying an excitation force by the vibration generation device 50.

そして、掘削ビット80により切削された土砂とロッド70の先端から噴射されたセメントミルクとが、攪拌翼により攪拌されることで掘削孔4内にソイルセメントが形成される。   Then, the soil cement cut from the excavation bit 80 and the cement milk sprayed from the tip of the rod 70 are agitated by the agitating blade, so that a soil cement is formed in the excavation hole 4.

次に、図4(B)に示すように、間隔を空けて構築されたソイルセメント柱110Aの間に、地盤改良装置10により新たにソイルセメント柱110Bを構築する。なお、新たにソイルセメント柱110Bを構築すべく地盤を掘削する際に、既に構築が完了した隣接するソイルセメント柱110Aの側部を切削する。そして、掘削孔内においてセメントミルクを掘削土と混合攪拌することで、隣接するソイルセメント柱110同士が一体に連結される。   Next, as shown in FIG. 4B, a soil cement pillar 110B is newly constructed by the ground improvement device 10 between the soil cement pillars 110A constructed with a space therebetween. When excavating the ground to newly construct the soil cement pillar 110B, the side portion of the adjacent soil cement pillar 110A that has already been constructed is cut. And the adjacent soil cement pillars 110 are integrally connected by mixing and stirring cement milk with excavated soil in the excavation hole.

この際、上記のソイルセメント柱110Aを掘削する場合と同様に、地盤改良装置10の回転装置60によりロッド70を介して掘削ビット80を回転させるとともに、起振装置50によりロッド70を介して掘削ビット80に起振力を加える。これにより、掘削ビット80による掘削効率が向上するため、容易に硬化したソイルセメント柱110Aの側部を切削しながら、地盤を掘削することが可能となる。   At this time, as in the case of excavating the soil cement column 110A, the excavating bit 80 is rotated through the rod 70 by the rotating device 60 of the ground improvement device 10 and the excavating device 50 is excavated through the rod 70. An exciting force is applied to the bit 80. Thereby, since the excavation efficiency by the excavation bit 80 is improved, it is possible to excavate the ground while cutting the side portion of the soil cement pillar 110A that has been easily hardened.

このようにして環状のソイルセメント壁100を構築した後、図3Bに示すように、ソイルセメント壁100の内側を、掘削機200により所定深さまで地盤1を掘削して掘削孔130を形成する。掘削機200としては、狭隘な敷地でも掘削可能な、例えば、TBH工法に用いられる掘削機などが適している。この際、内部に掘削孔130内に安定液を満たすこととなるが、ソイルセメント壁100が掘削孔130の周囲を囲繞しており、ソイルセメント壁100が止水性を有するため、安定液が周囲に漏れ出すのを防止できる。すなわち、場所打ち杭300の構築の対象となる敷地の周囲に地下構造物などがある場合には、掘削孔130から安定液が漏れ出すと地下構造物内に安定液が侵入してしまい問題となるが、本実施形態ではこれを防止できる。また、ソイルセメント壁100が止水性を有するため、地下水が内部へ染み出すのも防止することができる。   After the annular soil cement wall 100 is constructed in this manner, as shown in FIG. 3B, the ground 1 is excavated to a predetermined depth inside the soil cement wall 100 by the excavator 200 to form the excavation hole 130. As the excavator 200, for example, an excavator that can be excavated even in a narrow site, for example, used in the TBH method is suitable. At this time, the inside of the excavation hole 130 is filled with the stabilizing liquid. However, since the soil cement wall 100 surrounds the excavation hole 130 and the soil cement wall 100 has a water-stopping property, To prevent leakage. That is, when there is an underground structure around the site where the cast-in-place pile 300 is to be constructed, if the stable liquid leaks from the excavation hole 130, the stable liquid may enter the underground structure. However, this embodiment can prevent this. Moreover, since the soil cement wall 100 has a water-stopping property, it is possible to prevent the groundwater from seeping out.

地盤1を掘削すると、ソイルセメント壁100には周囲の地盤1から土水圧が作用するが、ソイルセメント壁100が環状に形成されているため、リングコンプレッション効果によりこの土水圧に対して抵抗することができる。また、ソイルセメント壁100は止水性を有するため、地下水が内部へ染み出すのを防止できる。   When excavating the ground 1, soil water pressure acts on the soil cement wall 100 from the surrounding ground 1, but since the soil cement wall 100 is formed in an annular shape, it resists this soil water pressure by the ring compression effect. Can do. Moreover, since the soil cement wall 100 has a water-stopping property, it can prevent that groundwater oozes out inside.

次に、図3Cに示すように、掘削孔130内に鉄筋かご140を建て込む。なお、鉄筋かご140は、予め、長さ方向に複数に分割されたものを、建て込みながら連結するとよい。   Next, as shown in FIG. 3C, the rebar cage 140 is installed in the excavation hole 130. In addition, it is good to connect the reinforcement | strengthening cage | basket | car 140 previously, what was divided | segmented into the length direction is built.

次に、図3Dに示すように、掘削孔130内にトレミー管210を挿入し、トレミー管210を通して掘削孔130内にコンクリート150を打設する。打設したコンクリート150が硬化することで場所打ち杭300の構築が完了する。   Next, as shown in FIG. 3D, the treme tube 210 is inserted into the excavation hole 130, and the concrete 150 is placed in the excavation hole 130 through the treme tube 210. Construction of the cast-in-place pile 300 is completed when the cast concrete 150 is hardened.

本実施形態によれば、地盤改良装置10の起振装置50により掘削ビット80に起振力を加えることで掘削力が向上する。これにより、硬化したソイルセメント柱110Aの側部を切削しながら地盤1を掘削することが可能となるため、ソイルセメント柱110を一体に連結してソイルセメント壁100を構築することができる。   According to the present embodiment, the excavation force is improved by applying an excitation force to the excavation bit 80 by the vibration generation device 50 of the ground improvement device 10. Accordingly, the ground 1 can be excavated while cutting the side portion of the hardened soil cement column 110A. Therefore, the soil cement wall 110 can be constructed by connecting the soil cement columns 110 together.

また、従来、地盤改良装置10の掘削効率を向上するためには大型の装置を用いていたが、本実施形態では、地盤改良装置10の掘削ビット80に起振力を加えることで掘削効率を向上しているため、小型の装置であっても強度の高い地盤の掘削が可能となる。このため、地盤の強度の高く、狭隘な敷地であっても施工が可能となる。   Conventionally, a large apparatus has been used to improve the excavation efficiency of the ground improvement device 10. However, in this embodiment, the excavation efficiency is increased by applying an excitation force to the excavation bit 80 of the ground improvement device 10. Since it is improved, it is possible to excavate the ground with high strength even with a small device. For this reason, construction is possible even in a narrow site with high ground strength.

また、従来の方法では、鋼管杭の圧入中に地中障害が発見された場合には、施工を中断し、鋼管杭を撤去しなければ、地中障害を撤去することができなかったが、本実施形態によれば、先行して掘削孔を形成しており、この際、地中障害を撤去することができるため、施工を中断することなく施工できる。   In addition, in the conventional method, if a ground fault was found during the press-fitting of the steel pipe pile, the construction could not be removed without interrupting the construction and removing the steel pipe pile. According to the present embodiment, the excavation hole is formed in advance, and in this case, since the underground obstacle can be removed, the construction can be performed without interruption.

なお、本実施形態では、図2を参照して説明した掘削ビット80を用いることとしたが、これに限らず、その他の形状の掘削ビットを用いることとしてもよい。   In the present embodiment, the excavation bit 80 described with reference to FIG. 2 is used. However, the present invention is not limited to this, and an excavation bit having another shape may be used.

また、本実施形態では、円環状に並ぶソイルセメント柱110を一つおきに構築した後、残りのソイルセメント柱110を構築するものとしたが、これに限らず、ソイルセメント柱110を周方向に順次構築してもよく、要するにソイルセメント柱110の構築する順序は問わない。   In this embodiment, every other soil cement column 110 arranged in an annular shape is constructed, and then the remaining soil cement columns 110 are constructed. However, the present invention is not limited to this, and the soil cement columns 110 are arranged in the circumferential direction. The soil cement pillar 110 may be constructed in any order.

また、本実施形態では、場所打ち杭を構築する際の土留壁としてソイルセメント壁100を構築する場合について説明したが、これに限らず、他の用途のソイルセメント構造物を構築する場合であっても、本発明のソイルセメント構造物の構築方法を適用できる。   Further, in the present embodiment, the case where the soil cement wall 100 is constructed as a retaining wall when constructing a cast-in-place pile has been described. However, the construction method of the soil cement structure of the present invention can be applied.

また、本実施形態では、円環状にソイルセメント柱110を連結してなるソイルセメント構造物を構築する場合について説明したが、これに限らず、ソイルセメント柱110を一列に接続してなるソイルセメント構造物を構築してもよいし、要するに、ソイルセメント柱が連結されてなるソイルセメント構造物を構築する場合であれば、本発明を適用できる。
また、本実施形態では、ソイルセメント柱110Bを構築する際に、地盤改良装置10によりセメントミルクを噴射しながら地盤を削孔攪拌したが、本発明においては、これに限らず、水を噴射しながら所定の深さまで削孔攪拌した後、掘削ビット80を引き上げる際にセメントミルクを掘削土内に噴射しながら掘削ビット80により掘削土とセメントミルクとを攪拌することとしてもよい。
Moreover, although this embodiment demonstrated the case where the soil cement structure formed by connecting the soil cement pillar 110 in a ring shape was constructed, it is not limited to this, and the soil cement formed by connecting the soil cement pillars 110 in a row. A structure may be constructed, or in short, the present invention can be applied to constructing a soil cement structure in which soil cement columns are connected.
Further, in this embodiment, when the soil cement pillar 110B is constructed, the ground is drilled and stirred while cement milk is sprayed by the ground improvement device 10, but the present invention is not limited to this, and water is jetted. However, after agitating the hole to a predetermined depth, the excavating soil and cement milk may be agitated by the excavating bit 80 while the cement milk is jetted into the excavating soil when the excavating bit 80 is pulled up.

1 地盤
3 支持層 4 掘削孔
10 地盤改良装置 20 移動機構
30 台座部 40 案内部
50 起振装置 60 回転装置
70 ロッド 80 掘削ビット
90 セメントミルク供給装置 100 ソイルセメント壁
110 ソイルセメント柱 130 掘削孔
150 コンクリート 200 掘削機
210 トレミー管 300 場所打ち杭
DESCRIPTION OF SYMBOLS 1 Ground 3 Support layer 4 Excavation hole 10 Ground improvement apparatus 20 Movement mechanism 30 Base part 40 Guide part 50 Exciting apparatus 60 Rotating apparatus 70 Rod 80 Excavation bit 90 Cement milk supply apparatus 100 Soil cement wall 110 Soil cement pillar 130 Excavation hole 150 Concrete 200 Excavator 210 Tremy pipe 300 Cast-in-place pile

Claims (4)

複数のソイルセメント柱が連結されてなるソイルセメント構造物を構築する方法であって、
使用する地盤改良装置は、ロッド、該ロッドに起振力を与える起振装置、前記ロッドを回転させる回転装置、及び前記ロッドの先端に設けられた掘削ビットを備える単軸の装置であり、
前記掘削ビットは、前記ロッドの先端から延びセメントミルクを排出する軸部、該軸部の先端部に側方に延びるように設けられた掘削翼本体、該掘削翼本体に設けられたビット、前記軸部における前記掘削翼本体より上側に外周に向かって延びるように設けられた複数の攪拌翼を備え、
隣接するソイルセメント柱のうち一方を構築する第1のステップと、
前記掘削ビットを前記起振装置により振動させながら前記回転装置により回転させることで、前記一方のソイルセメント柱の側部を切削するとともに、他方のソイルセメント柱に相当する部分に、前記軸部からセメントミルクを噴射しながら削孔攪拌することで、他方のソイルセメント柱を構築する第2のステップとを備え
前記ソイルセメント構造物は、3つ以上のソイルセメント柱が連結されてなり、
前記第1のステップでは、前記ソイルセメント柱を一つおきに構築し、
前記第2のステップでは、残りのソイルセメント柱を構築することを特徴とするソイルセメント構造物の構築方法。
A method for constructing a soil cement structure in which a plurality of soil cement pillars are connected,
The ground improvement device to be used is a single shaft device including a rod, a vibration generating device for applying a vibration force to the rod, a rotating device for rotating the rod, and an excavation bit provided at the tip of the rod,
The excavation bit includes a shaft portion that extends from the tip of the rod and discharges cement milk, a drill blade body that is provided to extend laterally at the tip portion of the shaft portion, a bit provided in the drill blade body, A plurality of stirring blades provided to extend toward the outer periphery above the excavation blade body in the shaft portion,
A first step of constructing one of the adjacent soil cement columns;
The excavator bit is rotated by the rotating device while being vibrated by the vibration generator , so that the side portion of the one soil cement column is cut, and the portion corresponding to the other soil cement column is separated from the shaft portion. A second step of constructing the other soil cement pillar by stirring the hole while spraying the cement milk ,
The soil cement structure is formed by connecting three or more soil cement pillars,
In the first step, every other soil cement pillar is constructed,
In the second step, how to build a soil cement structure characterized that you build the remaining soil cement pillar.
請求項1記載のソイルセメント構造物の構築方法であって、
前記複数のソイルセメント柱を円環状に構築することを特徴とするソイルセメント構造物の構築方法。
A method of constructing claim 1 Symbol placement of soil cement structure,
A method for constructing a soil cement structure, wherein the plurality of soil cement columns are constructed in an annular shape.
請求項1又は2に記載の方法により構築されたことを特徴とするソイルセメント構造物。 A soil cement structure constructed by the method according to claim 1 or 2 . 請求項1に記載のソイルセメント構造物の構築方法を用いて、前記複数のソイルセメント柱が円環状に並んだソイルセメント壁を構築する工程と、Using the method for constructing a soil cement structure according to claim 1, constructing a soil cement wall in which the plurality of soil cement columns are arranged in an annular shape;
前記ソイルセメント壁の内側を、TBH工法で用いられる掘削機により孔内に安定液を満たした状態で掘削する工程と、A step of excavating the inside of the soil cement wall in a state in which the hole is filled with a stable liquid by an excavator used in the TBH method,
掘削した孔内に配筋しコンクリートを打設する工程とPlacing the concrete in the excavated hole and placing concrete;
を備えることを特徴とする場所打ち杭の構築方法。A method for constructing cast-in-place piles, comprising:
JP2009227987A 2009-09-30 2009-09-30 Method for constructing soil cement structure, soil cement structure Active JP5443928B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009227987A JP5443928B2 (en) 2009-09-30 2009-09-30 Method for constructing soil cement structure, soil cement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009227987A JP5443928B2 (en) 2009-09-30 2009-09-30 Method for constructing soil cement structure, soil cement structure

Publications (2)

Publication Number Publication Date
JP2011074675A JP2011074675A (en) 2011-04-14
JP5443928B2 true JP5443928B2 (en) 2014-03-19

Family

ID=44018932

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009227987A Active JP5443928B2 (en) 2009-09-30 2009-09-30 Method for constructing soil cement structure, soil cement structure

Country Status (1)

Country Link
JP (1) JP5443928B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013167114A (en) * 2012-02-16 2013-08-29 Ohbayashi Corp Underground structure and construction method thereof
JP6216561B2 (en) * 2013-07-31 2017-10-18 株式会社大林組 Cast-in-place pile wall protector and its construction method

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5838571B2 (en) * 1980-11-07 1983-08-24 西松建設株式会社 Augus creu for creating underground continuous walls
JPS6225616A (en) * 1985-07-24 1987-02-03 Shimizu Constr Co Ltd Blade built-in type auger excavator
JPH0485413A (en) * 1990-07-27 1992-03-18 Sumitomo Cement Co Ltd Earth retaining method
JPH0718677A (en) * 1993-07-01 1995-01-20 Kengi Kaihatsu Kk Pillar line type underground continuous wall construction method
JPH0860650A (en) * 1994-08-23 1996-03-05 Yoshihiko Kawai Excavation method
KR0144777B1 (en) * 1995-01-21 1998-09-15 박정구 Auger drill machine and spiral groove manufacturing method of underground hole and spiral foundation pile
JP2700781B2 (en) * 1995-09-13 1998-01-21 株式会社丸徳基業 Construction method of soil cement pile
JP2004251057A (en) * 2003-02-21 2004-09-09 Shimizu Corp Low-altitude head excavator

Also Published As

Publication number Publication date
JP2011074675A (en) 2011-04-14

Similar Documents

Publication Publication Date Title
KR101641943B1 (en) An deep wing mixing vibratinal agitator for hardening ground and the deep wing mixing method thereof
JP5690864B2 (en) Construction method of mountain retaining wall, construction method of cast-in-place pile
KR102091646B1 (en) Ground improvement type composite pile construction method
KR101662694B1 (en) Construction Method for PHC Pile by Inner Excavation
JP2016160700A (en) Foundation reinforcement method
JP5443928B2 (en) Method for constructing soil cement structure, soil cement structure
JP6901928B2 (en) Pile construction method
JP5075090B2 (en) Cast-in-place pile construction method and cast-in-place pile
JP5648085B2 (en) How to build a pile
JP5557503B2 (en) Steel pipe pile insertion method
JP5634036B2 (en) Method for constructing retaining wall, method for constructing pile, retaining wall, pile
JP5075094B2 (en) Construction method and foundation structure of foundation structure in structure
JP2008031772A (en) Construction method of precast pile, and cover for use in the construction method
JP2005282043A (en) Earth retaining wall reinforcing method
JP2011012443A (en) Construction method for soil cement structure and the soil cement structure
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
JP4236119B2 (en) Construction method of mountain retaining wall
JP5075093B2 (en) Construction method and foundation structure of foundation structure in structure
KR102138899B1 (en) Detachable vibro-hammer with vibratory rubber and construction method of drilling and ground reinforcement thereof
JP2011042966A (en) Drilling and agitating unit, and soil improving apparatus
JP2017197910A (en) Construction method of earth retaining wall structure, and earth retaining wall structure
JP6832761B2 (en) How to rebuild the building
JP6769751B2 (en) Frame laying method
JP2013167114A (en) Underground structure and construction method thereof
JP5536825B2 (en) Tapered pile construction method and taper pile construction casing

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120817

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130627

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130709

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130917

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20131111

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20131126

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20131220

R150 Certificate of patent or registration of utility model

Ref document number: 5443928

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250