JP5388346B2 JP2009220359A JP2009220359A JP5388346B2 JP 5388346 B2 JP5388346 B2 JP 5388346B2 JP 2009220359 A JP2009220359 A JP 2009220359A JP 2009220359 A JP2009220359 A JP 2009220359A JP 5388346 B2 JP5388346 B2 JP 5388346B2
Authority
JP
Japan
Prior art keywords
current
main line
phase
load
breaker
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2009220359A
Other languages
Japanese (ja)
Other versions
JP2011072109A (en
Inventor
崇 稲次
慶 川口
淳一 川幡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panasonic Corp
Panasonic Holdings Corp
Original Assignee
Panasonic Corp
Matsushita Electric Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Panasonic Corp, Matsushita Electric Industrial Co Ltd filed Critical Panasonic Corp
Priority to JP2009220359A priority Critical patent/JP5388346B2/en
Publication of JP2011072109A publication Critical patent/JP2011072109A/en
Application granted granted Critical
Publication of JP5388346B2 publication Critical patent/JP5388346B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Description

本発明は、主として集合住宅に用いられ、幹線ブレーカを設けた幹線から複数の住戸用に分岐した電路にそれぞれメインブレーカが設置されている電力配線系において、各住戸への供給電流の増大による幹線ブレーカの遮断を抑制する集合住宅幹線電流制御システムに関する。   The present invention is mainly used in an apartment house, and in a power wiring system in which a main breaker is installed in an electric circuit branched from a main line provided with a main line breaker to a plurality of dwelling units, a main line due to an increase in supply current to each dwelling unit The present invention relates to an apartment house main line current control system that suppresses breaker interruption.

従来、幹線に過電流が流れたときに各住戸の負荷(例えば、エアコン、冷蔵庫、テレビ等)に流れる電流を個別に制限する集合住宅幹線電流制御システムがある。この種のシステムが特許文献1で開示されており、この文献で開示されたシステムでは、幹線に所定の閾値以上の電流が所定時間以上流れた場合に当該電流に応じた負荷制御を行うようにしている。すなわち、特許文献1に記載された集合住宅幹線電流制御システムは、単相3線式の配電線に設置される配線用遮断器の遮断を防止することを目的としており、遮断器の動作特性と配電線を流れる電流を比較し、配電線に流れる電流が遮断器の動作電流時間領域に達することを検出して集合住宅の個々の住戸の負荷を遮断(すなわち、負荷への電源の遮断)するようにしている。   2. Description of the Related Art Conventionally, there is an apartment house main line current control system that individually restricts the current flowing through loads (for example, an air conditioner, a refrigerator, and a television) of each dwelling unit when an overcurrent flows through the main line. This type of system is disclosed in Patent Document 1, and in the system disclosed in this document, when a current exceeding a predetermined threshold flows through a main line for a predetermined time or more, load control corresponding to the current is performed. ing. That is, the apartment house trunk line current control system described in Patent Document 1 is intended to prevent the breaker of the wiring breaker installed in the single-phase three-wire distribution line, and the operation characteristics of the breaker and Compares the current flowing through the distribution line, detects that the current flowing through the distribution line reaches the operating current time range of the circuit breaker, and blocks the load of each dwelling unit of the apartment house (that is, shuts off the power to the load) I am doing so.

特開2008−178275号公報JP 2008-178275 A

しかしながら、特許文献1に記載された集合住宅幹線電流制御システムは、単相3線式の2つある電源の相のいずれかに流れる電流が遮断器の動作電流時間領域に達することを判断するようにしているものであり、制御される個々の住戸の負荷が遮断器の動作電流時間領域に達すると判断された電源の相(すなわち、制御対象の電源の相)に接続されているかどうかにかかわらず遮断するため、制御対象の電源の相に接続されていない負荷も同時に遮断されて、住居人に必要のない不便をかけてしまうという課題がある。   However, the apartment house main line current control system described in Patent Document 1 determines that the current flowing in one of the two power supply phases of the single-phase three-wire system reaches the operating current time region of the circuit breaker. Whether or not the load of the individual controlled unit is connected to the phase of the power source determined to reach the operating current time range of the circuit breaker (ie, the phase of the controlled power source). Therefore, there is a problem that loads that are not connected to the phase of the power source to be controlled are also cut off at the same time, causing unnecessary inconvenience for residents.

本発明は、係る事情に鑑みてなされたものであり、幹線電流が幹線ブレーカにおける過電流領域に至っている状態が規定の制限時間に達した場合に、住戸の全ての負荷を制限することなく一部に限定することができる集合住宅幹線電流制御システムを提供することを目的とする。   The present invention has been made in view of such circumstances, and when the state where the main line current reaches the overcurrent region in the main line breaker reaches a specified time limit, the load is limited without limiting all the loads on the dwelling unit. An object of the present invention is to provide a multi-family house main line current control system that can be limited to a part.

本発明の集合住宅幹線電流制御システムは、複数の住戸に配電する幹線に設置された幹線ブレーカと、前記幹線ブレーカの下流において前記幹線から各住戸用に分岐した電路のそれぞれに設置され、各住戸に配置した住宅分電盤に収納されたリミッタとメインブレーカの少なくともいずれか一方と、前記幹線ブレーカを通過する幹線電流を電源相別に検出する幹線電流検出手段と、前記幹線電流検出手段により検出された電源相別の幹線電流のそれぞれが前記幹線ブレーカにおける過電流領域である状態が規定の制限時間に達したか否かを判定する第1の電流判定手段と、前記リミッタまたはメインブレーカを通過する住戸電流を電源相別に検出する住戸電流検出手段と、前記第1の電流判定手段により制限時間に達したと判定され、かつ前記住戸電流検出手段で検出された電流値が前記リミッタまたはメインブレーカの定格電流に対して規定した閾値以上となったとき、前記第1の電流判定手段によって検出された電源相を示す相情報を出力する第2の電流判定手段と、前記第2の電流判定手段から前記相情報が出力された場合、住戸内に設けられた負荷のうち、前記相情報で示される電源相に接続された負荷に対して電流制限制御を行う負荷制御手段と、を備えた。   The apartment house trunk line current control system of the present invention is installed in each of a trunk line breaker installed on a trunk line that distributes power to a plurality of dwelling units, and an electric circuit branched from the trunk line for each dwelling unit downstream of the trunk line breaker. At least one of a limiter and a main breaker housed in a residential distribution board arranged on the main line, a main line current detecting means for detecting a main line current passing through the main line breaker for each power supply phase, and detected by the main line current detecting means First current determination means for determining whether or not a state where each of the main line currents for each power supply phase is an overcurrent region in the main line breaker has reached a specified time limit, and the limiter or the main breaker. It is determined that the time limit has been reached by the dwelling current detection means for detecting the dwelling current for each power supply phase and the first current determination means, and before When the current value detected by the dwelling unit current detection means becomes equal to or greater than a threshold value defined for the rated current of the limiter or main breaker, phase information indicating the power supply phase detected by the first current determination means is output. When the phase information is output from the second current determination unit and the second current determination unit, the load connected to the power supply phase indicated by the phase information among the loads provided in the dwelling unit Load control means for performing current limit control on the control unit.

上記構成によれば、幹線電流が幹線ブレーカにおける過電流領域である状態が規定の制限時間(契約した電流値に応じて規定されている制限時間)に達した場合、制御対象の電源の相に属する負荷を優先的に制御するので、各住戸における負荷において、電流制限対象となる負荷を一部に限定することができ、住居人に必要のない不便をかけてしまうことが無くなる。例えば、制御対象の電源相にエアコンが接続されていて、非制御対象の電源相に電子レンジが接続されている場合、制御対象の電源相に接続されたエアコンのみ電流制限を行うので、電子レンジは継続して使用することができる。   According to the above configuration, when the state in which the main line current is in the overcurrent region in the main line breaker reaches the specified time limit (the time limit specified according to the contracted current value), the phase of the power supply to be controlled Since the load to which the unit belongs is preferentially controlled, it is possible to limit the load subject to current limitation to a part of the load in each dwelling unit, thereby eliminating unnecessary inconvenience for the resident. For example, if an air conditioner is connected to the control target power phase and a microwave oven is connected to the non-control target power phase, only the air conditioner connected to the control target power phase performs current limiting. Can be used continuously.

上記構成において、前記負荷制御手段は、電流制限対象の負荷が接続される電源相を設定する相設定手段を備え、前記第2の電流判定手段から出力された前記相情報と前記相設定手段で設定された設定情報を比較し、一致する相情報がある場合に電流制限制御を行う。   In the above configuration, the load control unit includes a phase setting unit that sets a power supply phase to which a load to be limited in current is connected, and includes the phase information output from the second current determination unit and the phase setting unit. The set setting information is compared, and if there is matching phase information, current limit control is performed.

上記構成によれば、負荷を任意の電源相に接続しても、接続した方の電源相に設定手段の設定を行うことで、接続した方の電源相で過電流状態が生じた場合に、確実に該電源相に接続された負荷に対して電流制限制御を行うことができる。   According to the above configuration, even if the load is connected to an arbitrary power supply phase, by setting the setting means in the connected power supply phase, when an overcurrent state occurs in the connected power supply phase, Current limit control can be reliably performed on the load connected to the power supply phase.

本発明の集合住宅幹線電流制御システムは、複数の住戸に配電する幹線に設置された幹線ブレーカと、前記幹線ブレーカの下流において前記幹線から各住戸用に分岐した電路のそれぞれに設置され、各住戸に配置した住宅分電盤に収納されたリミッタとメインブレーカの少なくともいずれか一方と、前記幹線ブレーカを通過する幹線電流を電源相別に検出する幹線電流検出手段と、前記幹線電流検出手段により検出された電源相別の幹線電流のそれぞれが前記幹線ブレーカにおける過電流領域である状態が規定の制限時間に達したか否かを判定する第1の電流判定手段と、前記リミッタまたはメインブレーカを通過する住戸電流を電源相別に検出する住戸電流検出手段と、負荷に供給される電流を制限する制御を行う少なくとも1個の負荷制御手段と、前記負荷制御手段ごとに接続先の電源相を設定可能な相設定手段と、前記第1の電流判定手段により制限時間に達したと判定され、かつ前記住戸電流検出手段で検出された電流値が前記リミッタまたはメインブレーカの定格電流に対して規定した閾値以上となったとき、その電源相を示す相情報と前記相設定手段で設定された前記負荷制御手段ごとの設定情報を比較し、一致する全ての負荷制御手段を選択し、選択した負荷制御手段にのみ制御指令を与える第2の電流判定手段とを備え、前記負荷制御手段は、前記第2の電流判定手段からの制御指令を受け取ると、電流制限対象となる負荷に対して電流制限制御を行う。   The apartment house trunk line current control system of the present invention is installed in each of a trunk line breaker installed on a trunk line that distributes power to a plurality of dwelling units, and an electric circuit branched from the trunk line for each dwelling unit downstream of the trunk line breaker. At least one of a limiter and a main breaker housed in a residential distribution board arranged on the main line, a main line current detecting means for detecting a main line current passing through the main line breaker for each power supply phase, and detected by the main line current detecting means First current determination means for determining whether or not a state where each of the main line currents for each power supply phase is an overcurrent region in the main line breaker has reached a specified time limit, and the limiter or the main breaker. A dwell unit current detecting means for detecting a dwell unit current for each power supply phase and at least one load system for controlling the current supplied to the load. Means, phase setting means capable of setting the connection destination power supply phase for each load control means, and the first current determination means determines that the time limit has been reached, and is detected by the dwelling current detection means When the current value is equal to or greater than the threshold specified for the rated current of the limiter or main breaker, the phase information indicating the power phase is compared with the setting information for each load control means set by the phase setting means. And a second current determining means for selecting all matching load control means and giving a control command only to the selected load control means, wherein the load control means is a control command from the second current determining means. Is received, current limit control is performed on the load to be current limited.

上記構成によれば、負荷制御手段ごとの相情報を設定可能な相設定手段を有し、第2の電流判定手段が受け取った相情報と前記相設定手段で設定された負荷制御手段ごとの設定情報を比較し、一致する全ての負荷制御手段を選択し、選択した負荷制御手段にのみ制御指令を与え、過電流に陥っている電源相に関係する負荷のみ電流の供給制限を行うので、各住戸における負荷において、電流制限対象となる負荷を一部に限定することができ、住居人に必要のない不便をかけてしまうことが無くなる。   According to the above configuration, the phase setting means that can set phase information for each load control means is provided, and the phase information received by the second current determination means and the setting for each load control means set by the phase setting means. Compare information, select all matching load control means, give control commands only to the selected load control means, and limit the supply of current only to the load related to the power supply phase falling into overcurrent, so each In the load in the dwelling unit, the load that is the current restriction target can be limited to a part, and the inconvenience unnecessary for the resident is eliminated.

本発明の集合住宅幹線電流制御システムは、複数の住戸に配電する幹線に設置された幹線ブレーカと、前記幹線ブレーカの下流において前記幹線から各住戸用に分岐した電路のそれぞれに設置され、各住戸に配置した住宅分電盤に収納されたリミッタとメインブレーカの少なくともいずれか一方と、前記幹線ブレーカを通過する幹線電流を電源相別に検出する幹線電流検出手段と、前記幹線電流検出手段により検出された電源相別の幹線電流のそれぞれが前記幹線ブレーカにおける過電流領域である状態が規定の制限時間に達したか否かを判定する第1の電流判定手段と、前記リミッタまたはメインブレーカを通過する住戸電流を電源相別に検出する住戸電流検出手段と、負荷に供給される電流を制限する制御を行う少なくとも1個の負荷制御手段と、前記負荷制御手段が電流制限対象の負荷への電流供給を制限したことを通知してくると、その旨を前記第1の電流判定手段に通知し、その後、前記第1の電流判定手段から前記電流制限対象の負荷が接続された電源相を示す相情報を受けることで該相情報を記憶し、また前記電源相を示す相情報の返信を受け、さらに前記第1の電流判定手段から負荷遮断要求の制御信号を受けると、該制御信号に含まれる相情報と記憶している負荷制御手段ごとの相情報とを照合し、電流制限すべき負荷制御手段を選択し、選択した負荷制御手段にのみ制御指令を与える第2の電流判定手段とを備え、前記第1の電流判定手段は、前記第2の電流判定手段から電流供給を制限した通知を受けると、幹線電流を電源相別に監視している前記幹線電流検出手段の判定結果に基づき電流の減少した電源相を検出し、検出した相情報を前記第2の電流判定手段に送信し、前記負荷制御手段は、前記第2の電流判定手段からの制御指令を受け取ると、前記電流制限対象の負荷に対して電流制限制御を行う。   The apartment house trunk line current control system of the present invention is installed in each of a trunk line breaker installed on a trunk line that distributes power to a plurality of dwelling units, and an electric circuit branched from the trunk line for each dwelling unit downstream of the trunk line breaker. At least one of a limiter and a main breaker housed in a residential distribution board arranged on the main line, a main line current detecting means for detecting a main line current passing through the main line breaker for each power supply phase, and detected by the main line current detecting means First current determination means for determining whether or not a state where each of the main line currents for each power supply phase is an overcurrent region in the main line breaker has reached a specified time limit, and the limiter or the main breaker. A dwell unit current detecting means for detecting a dwell unit current for each power supply phase and at least one load system for controlling the current supplied to the load. And the load control means notify that the current supply to the current limiting load has been restricted, notifies the first current judging means to that effect, and then the first current judging The phase information is stored by receiving phase information indicating the power supply phase to which the load subject to current limitation is connected from the means, the phase information indicating the power supply phase is received, and the first current determination means When receiving a load cutoff request control signal, the phase information included in the control signal is checked against the stored phase information for each load control means, the load control means to be current-limited is selected, and the selected load is selected. Second current determination means for giving a control command only to the control means, and when the first current determination means receives a notification that the current supply is restricted from the second current determination means, the main current is supplied to the power supply phase. The main current monitored separately Based on the determination result of the output means, the power supply phase with reduced current is detected, the detected phase information is transmitted to the second current determination means, and the load control means is controlled by the control command from the second current determination means. Is received, current limit control is performed on the current limit target load.

上記構成によれば、各負荷制限手段の相情報を設定する手段を省くことができるだけでなく、第1の電流判定手段が検出した電源相と第2の電流判定手段が検出した電源相とが入れ替わっていても影響なく負荷制御が行えるため、施工の際に幹線電流検出手段の相を確認することなく、一切の設定が不要となる。これにより、簡便かつ間違いのない施工が可能となる。   According to the above configuration, not only the means for setting the phase information of each load limiting means can be omitted, but also the power supply phase detected by the first current determination means and the power supply phase detected by the second current determination means. Since the load control can be performed without being affected even if it is replaced, no setting is required without confirming the phase of the trunk current detection means at the time of construction. Thereby, construction which is simple and without mistakes is possible.

また、後々の結線変更などで負荷の電源の相が変更されたとしても毎回相情報の確認を行うことで自動的に設定を更新することができるので、設定し忘れなどもなく、保守性にも優れている。   In addition, even if the power supply phase of the load is changed due to a later connection change, the setting can be automatically updated by checking the phase information every time, so there is no need to forget to set it and maintainability Is also excellent.

上記構成において、前記第2の電流判定手段は、前記第1の電流判定手段から受け取る負荷遮断要求に含まれる相情報に一致する電源相に接続されていない負荷を電流制限対象とする前記負荷制御手段に対して電流制限を解除するための制御指令を与える。   In the above configuration, the second current determination unit is configured to limit the load that is not connected to the power supply phase that matches the phase information included in the load cutoff request received from the first current determination unit. A control command for releasing the current limit is given to the means.

上記構成によれば、電源相に流れる電流が減少したとき復帰動作電流時間領域に達した電源相のみに接続されている負荷を優先して復帰制御できるため、負荷の制御時間をより短くすることができる。   According to the above configuration, when the current flowing in the power supply phase decreases, the load connected to only the power supply phase that has reached the recovery operation current time region can be controlled with priority, so the load control time can be shortened. Can do.

上記構成において、前記相情報を記憶する不揮発性の記憶媒体を用いた相情報記憶手段を備える。   In the above configuration, phase information storage means using a nonvolatile storage medium that stores the phase information is provided.

上記構成によれば、電流制限対象の負荷が接続された電源相を情報として記憶するので、停電などによって情報の損失が回避でき、復電後の情報再構築が不要で、復電直後でも、不要動作を少なくすることができる。   According to the above configuration, since the power phase to which the current limit target load is connected is stored as information, loss of information due to a power failure or the like can be avoided, information reconstruction after power recovery is unnecessary, even immediately after power recovery, Unnecessary operations can be reduced.

上記構成において、前記第1の電流判定手段によって電流制限が必要と検出された電源相を流れる電流の値と前記住戸電流検出手段により検出された前記リミッタまたはメインブレーカを流れる電流の値とを表示する表示手段を備えた。   In the above-described configuration, the value of the current flowing through the power supply phase detected as needing current limitation by the first current determination unit and the value of the current flowing through the limiter or main breaker detected by the dwelling unit current detection unit are displayed. The display means is provided.

上記構成によれば、第1の電流判定手段によって検出された電源相を流れる電流の値と住戸電流検出手段により検出されたリミッタまたはメインブレーカを流れる電流の値とを表示するので、住居人は自身の負荷が遮断される順位等に関しての納得感を得やすくなる。   According to the above configuration, since the value of the current flowing through the power supply phase detected by the first current determination unit and the value of the current flowing through the limiter or main breaker detected by the dwelling unit current detection unit are displayed, the resident This makes it easier to obtain a sense of satisfaction regarding the order in which the load is cut off.

本発明は、幹線電流が幹線ブレーカにおける過電流領域にある状態が規定の制限時間に達した場合、住戸の全ての負荷機器を制限することなく一部に限定し、制限しない負荷は継続して使用可能にするので、住居人に必要のない不便をかけてしまうことがない。   In the present invention, when the state in which the main line current is in the overcurrent region in the main line breaker reaches the specified time limit, the load unit of the dwelling unit is limited to a part without limiting, and the load not limited continues. Because it can be used, there will be no unnecessary inconvenience for residents.

本発明の実施の形態1に係る集合住宅幹線電流制御システムの集合住宅への設置状態を概略的に示す図The figure which shows schematically the installation state to the apartment house of the apartment house trunk line current control system which concerns on Embodiment 1 of this invention. 本発明の実施の形態1に係る集合住宅幹線電流制御システムの概略構成を示すブロック図The block diagram which shows schematic structure of the apartment house trunk line current control system which concerns on Embodiment 1 of this invention. 図2の負荷制御装置の概観を示す図The figure which shows the general view of the load control apparatus of FIG. 本発明の実施の形態2に係る集合住宅幹線電流制御システムの概略構成を示すブロック図The block diagram which shows schematic structure of the apartment house trunk line current control system which concerns on Embodiment 2 of this invention. 図4の子局の概観を示す図The figure which shows the general view of the slave station of FIG. 本発明の実施の形態3に係る集合住宅幹線電流制御システムの概略構成を示すブロック図The block diagram which shows schematic structure of the apartment house trunk line current control system which concerns on Embodiment 3 of this invention. 図6の集合住宅幹線電流制御システムにおける動作を説明するためのシーケンス図FIG. 6 is a sequence diagram for explaining the operation in the residential housing trunk line current control system of FIG.

以下、本発明を実施するための好適な実施の形態について、図面を参照して詳細に説明する。   DESCRIPTION OF EXEMPLARY EMBODIMENTS Hereinafter, preferred embodiments for carrying out the invention will be described in detail with reference to the drawings.

(実施の形態1)
図1は、本発明の実施の形態1に係る集合住宅幹線電流制御システムの集合住宅への設置状態を概略的に示す図、図2は本実施の形態に係る集合住宅幹線電流制御システムの概略構成を示すブロック図である。
(Embodiment 1)
FIG. 1 is a diagram schematically showing an installation state of an apartment house trunk line current control system according to Embodiment 1 of the present invention in an apartment house, and FIG. 2 is an outline of the apartment house trunk line current control system according to the present embodiment. It is a block diagram which shows a structure.

図1及び図2において、本実施の形態の集合住宅幹線電流制御システムでは、集合住宅100には2系統の幹線10が配線され、それぞれの幹線10に幹線ブレーカ20が設置され、各幹線ブレーカ20の下流において、2系統の幹線10のそれぞれが複数系統(図示例では4系統)に分岐しているものとする。住宅分電盤30には、リミッタ31及びメインブレーカ32が内器としてそれぞれ収納され、幹線10から各住戸用に分岐した電路(以下、“住戸線”と呼ぶ)11にリミッタ31及びメインブレーカ32が設置される。   1 and 2, in the collective housing main line current control system of the present embodiment, two lines of main lines 10 are wired in the collective housing 100, and a main line breaker 20 is installed in each main line 10. It is assumed that each of the two main trunk lines 10 branches into a plurality of systems (four systems in the illustrated example). A limiter 31 and a main breaker 32 are housed in the residential distribution board 30 as internal units, respectively, and the limiter 31 and the main breaker 32 are connected to an electric circuit (hereinafter referred to as “dwelling unit line”) 11 branched from the main line 10 to each dwelling unit. Is installed.

幹線10及び住戸線11は、それぞれ中性線LNと電源線L1及びL2とからなる単相3線のものである。2個の幹線ブレーカ20は、集合住宅100の共用部分110に親局40と共に配置される。幹線10において幹線ブレーカ20の下流側にはCT(Current Transformer)を用いた電流計測装置50が幹線10の電源線L1及びL2のそれぞれに設置されている。   The trunk line 10 and the dwelling unit line 11 are single-phase three-wires each including a neutral line LN and power supply lines L1 and L2. The two main line breakers 20 are arranged together with the master station 40 in the common part 110 of the apartment house 100. In the main line 10, a current measuring device 50 using a CT (Current Transformer) is installed on each of the power lines L <b> 1 and L <b> 2 of the main line 10 on the downstream side of the main line breaker 20.

親局40には、2個の電流計測装置50それぞれの出力から幹線10の電源線L1及びL2それぞれを通過する幹線電流を計測する電流計測部401と、電流計測部401で計測された幹線10の電源線L1及びL2それぞれにおける幹線電流が幹線ブレーカ20の過電流領域である状態が規定の制限時間に達した否かを判定する電流判定部(第1の電流判定手段)402と、電流判定部402に前記幹線電流が過電流と判断する閾値を設定する設定部403と、電流判定部402において、幹線10の電源線L1及びL2それぞれを通過する幹線電流の両方もしくはいずれか一方が幹線ブレーカ20の過電流領域である状態が規定の制限時間に達したと判定されたときに、幹線ブレーカ20の下流のメインブレーカ32を収納している各住戸101の住宅分電盤30に制御信号を送信する通信部404とが収納される。なお、電流計測部401で用いられる制限時間とは、幹線ブレーカ20の過電流領域に応じて規定されている時間である。2個の電流計測装置50と電流計測部401は幹線電流検出部(幹線電流検出手段)60を構成する。   The master station 40 includes a current measuring unit 401 that measures the main line current passing through the power lines L1 and L2 of the main line 10 from the outputs of the two current measuring devices 50, and the main line 10 measured by the current measuring unit 401. A current determination unit (first current determination unit) 402 that determines whether or not the state where the main line current in each of the power supply lines L1 and L2 is in the overcurrent region of the main line breaker 20 has reached a specified time limit, and current determination In the setting unit 403 for setting a threshold for determining that the main line current is an overcurrent in the unit 402, and in the current determination unit 402, both or one of the main line currents passing through the power lines L1 and L2 of the main line 10 is a main line breaker. When it is determined that the state of the 20 overcurrent region has reached the specified time limit, each residence that houses the main breaker 32 downstream of the main line breaker 20 And a communication unit 404 is housed which transmits a control signal to the residential distribution board 30 of 101. The time limit used in the current measuring unit 401 is a time defined according to the overcurrent region of the main line breaker 20. The two current measuring devices 50 and the current measuring unit 401 constitute a main line current detecting unit (main line current detecting means) 60.

通信部404は、電流判定部402において制限時間に達したと判定されたことをトリガとして制御信号を送信する。この制御信号には、過電流となっている幹線10の電源相を示す相情報が含まれる。すなわち、幹線10の電源線L1を通過する幹線電流のみが幹線ブレーカ20の過電流領域を超え、かつその状態が規定の制限時間に達した場合、電源線L1を流れる幹線電流が過電流状態となっているので、この電源線L1を示す相情報が含まれる。また、幹線10の電源線L2を通過する幹線電流のみが幹線ブレーカ20の過電流領域を超え、かつその状態が規定の制限時間に達した場合、電源線L2を流れる幹線電流が過電流状態となっているので、この電源線L2を示す相情報が含まれる。また、幹線10の電源線L1と電源線L2の双方を通過する幹線電流が共に幹線ブレーカ20の過電流領域を超え、かつその状態が規定の制限時間に達した場合、電源線L1及び電源線L2のそれぞれを流れる幹線電流が過電流状態となっているので、電源線L1と電源線L2を示す相情報が含まれる。このように、親局40の通信部404から送信される相情報は、L1、L2、L1+L2の3種類のうちの1つである。   The communication unit 404 transmits a control signal triggered by the current determination unit 402 determining that the time limit has been reached. This control signal includes phase information indicating the power supply phase of the main line 10 that is overcurrent. That is, when only the main line current passing through the power line L1 of the main line 10 exceeds the overcurrent region of the main line breaker 20, and the state reaches a specified time limit, the main line current flowing through the power line L1 is in an overcurrent state. Therefore, phase information indicating the power supply line L1 is included. In addition, when only the main line current passing through the power line L2 of the main line 10 exceeds the overcurrent region of the main line breaker 20 and the state reaches the specified time limit, the main line current flowing through the power line L2 becomes the overcurrent state. Therefore, phase information indicating the power supply line L2 is included. Further, when both the main line currents passing through both the power line L1 and the power line L2 of the main line 10 exceed the overcurrent region of the main line breaker 20, and the state reaches a specified time limit, the power line L1 and the power line Since the main line current flowing through each of L2 is in an overcurrent state, phase information indicating the power supply line L1 and the power supply line L2 is included. Thus, the phase information transmitted from the communication unit 404 of the master station 40 is one of the three types of L1, L2, and L1 + L2.

一方、住宅分電盤30には、リミッタ31及びメインブレーカ32のほか、メインブレーカ32の下流において複数に分岐した住戸線11にそれぞれ設置される分岐ブレーカ33と、メインブレーカ32を通過する電流(つまり、各住戸で使用している住戸電流)をメインブレーカ32の上流において検出するCT(Current Transformer)を用いた電流計測装置80とが収納される。すなわち、住戸線11の電源線L1及びL2のそれぞれに電流計測装置80が設置されている。   On the other hand, in addition to the limiter 31 and the main breaker 32, the residential distribution board 30 includes a branch breaker 33 installed in each of the dwelling unit wires 11 branched into a plurality of downstreams of the main breaker 32, and a current ( That is, a current measuring device 80 using a CT (Current Transformer) that detects the dwelling current used in each dwelling unit) upstream of the main breaker 32 is housed. That is, the current measuring device 80 is installed in each of the power supply lines L1 and L2 of the dwelling unit line 11.

また、各住戸101には、住宅分電盤30の近傍に子局70が設置される。なお、子局70は住宅分電盤30に収納されることもある。子局70には、2個の電流計測装置80それぞれの出力から住戸線11の電源線L1及びL2それぞれを通過する住戸電流を計測する電流計測部701と、親局40の電流判定部402により規定の制限時間に達したと判定され、かつ後述する住戸電流検出部90で計測された住戸電流の電流値がメインブレーカ32の定格電流に対して規定した閾値以上となった場合、親局40の電流判定部402により規定の制限時間に達したと判定された電源相情報を出力する電流判定部(第2の電流判定手段)702と、電流判定部702に前記閾値を設定する設定部703と、親局40の通信部404と通信を行い、通信部404から送信された制御信号を受信する通信部704とが収納される。子局70の通信部704は、親局40の通信部404から送信された制御信号を受信したときに、受信した制御信号に相情報が含まれていれば、その相情報を全ての負荷制御装置34に与える。2個の電流計測装置80と電流計測部701は住戸電流検出部(住戸電流検出手段)90を構成する。   In each dwelling unit 101, a slave station 70 is installed in the vicinity of the residential distribution board 30. The slave station 70 may be stored in the residential distribution board 30. The slave station 70 includes a current measurement unit 701 that measures the dwelling unit current passing through the power supply lines L1 and L2 of the dwelling unit line 11 from the outputs of the two current measurement devices 80, and a current determination unit 402 of the parent unit 40. When it is determined that the specified time limit has been reached, and the current value of the dwelling current measured by the dwelling current detection unit 90 described later is equal to or greater than the threshold defined for the rated current of the main breaker 32, the master station 40 A current determination unit (second current determination unit) 702 that outputs power phase information determined by the current determination unit 402 to have reached the specified time limit, and a setting unit 703 that sets the threshold value in the current determination unit 702 And a communication unit 704 that communicates with the communication unit 404 of the master station 40 and receives a control signal transmitted from the communication unit 404 is housed. When the communication unit 704 of the slave station 70 receives the control signal transmitted from the communication unit 404 of the parent station 40, if phase information is included in the received control signal, the phase information is transferred to all load controls. To device 34. The two current measuring devices 80 and the current measuring unit 701 constitute a dwelling unit current detection unit (dwelling unit current detection means) 90.

親局40の通信部404と子局70の通信部704の間における制御信号の伝送路には幹線10及び住戸線11が用いられる。つまり、電力線を用いて制御信号の伝送を行う。この種の技術は電力線通信(PLC)として知られており、本実施の形態では、相情報を含む制御信号を送るだけであるから、低速電力線通信で十分である。電力線通信の技術を用いて制御信号を伝送することにより、別途に通信線を配線する必要がなくなる。また、既存の建物であっても幹線10及び住戸線11を用いることで制御信号の伝送が可能になる。図2における破線500は、親局40の通信部404と子局70の通信部704との間の制御信号の経路を示している。   The trunk line 10 and the dwelling unit line 11 are used for the transmission path of the control signal between the communication unit 404 of the master station 40 and the communication unit 704 of the slave station 70. That is, the control signal is transmitted using the power line. This type of technology is known as power line communication (PLC), and in the present embodiment, only a control signal including phase information is sent, so low speed power line communication is sufficient. By transmitting the control signal using the power line communication technique, it is not necessary to separately wire the communication line. Moreover, even if it is an existing building, transmission of a control signal is attained by using the trunk line 10 and the dwelling unit line 11. A broken line 500 in FIG. 2 indicates a control signal path between the communication unit 404 of the master station 40 and the communication unit 704 of the slave station 70.

メインブレーカ32には単相3線の住戸線11が接続されるから、電流計測装置80は電流計測装置50と同様に、中性線LNを除く2本の電源線L1及びL2のそれぞれを通過する電流を検出する。電流判定部702は、住戸電流の電流値がメインブレーカ32の定格電流に対して規定した閾値以上であるときに、全ての負荷制御装置34に対して負荷200に供給する電流を制限するように指示する。前記規定の閾値は、例えば定格電流の50%に設定する(勿論、50%は一例であり、他の割合でもよい)。住戸電流の電流値が閾値未満の場合には、電流判定部702から全ての負荷制御装置34に負荷200に供給する電流の制限を指示せず、負荷200に供給する電流は現状維持される。   Since the single-phase three-wire dwelling unit wire 11 is connected to the main breaker 32, the current measuring device 80 passes through each of the two power supply lines L1 and L2 except for the neutral wire LN, like the current measuring device 50. Detect the current to be. The current determination unit 702 restricts the current supplied to all the load control devices 34 to the load 200 when the current value of the dwelling unit current is equal to or greater than the threshold value defined for the rated current of the main breaker 32. Instruct. The prescribed threshold value is set to, for example, 50% of the rated current (of course, 50% is an example, and other ratios may be used). When the current value of the dwelling unit current is less than the threshold value, the current determination unit 702 does not instruct all the load control devices 34 to limit the current supplied to the load 200, and the current supplied to the load 200 is maintained as it is.

負荷制御装置34は、住戸101ごとに住宅分電盤30に収納され、負荷200に供給される電流を制限する。すなわち、負荷制御装置34は電流を制限したい負荷200がある場合に用いられるものであり、住戸線11の電圧線L1側の分岐ブレーカ33又は電圧線L2側の分岐ブレーカ33に接続される。図2の場合、負荷200であるエアコン(1)とエアコン(2)は住戸線11の電源線L2側に接続されている。   The load control device 34 is housed in the residential distribution board 30 for each dwelling unit 101 and limits the current supplied to the load 200. That is, the load control device 34 is used when there is a load 200 whose current is to be limited, and is connected to the branch breaker 33 on the voltage line L1 side or the branch breaker 33 on the voltage line L2 side of the dwelling unit line 11. In the case of FIG. 2, the air conditioner (1) and the air conditioner (2) that are the loads 200 are connected to the power line L 2 side of the dwelling unit line 11.

負荷制御装置34には、負荷200が接続される電源相を設定するための相設定スイッチ(相設定手段)34Aが設けられている。親局40から送信される相情報は、L1又はL2又はL1+L2の3種類であるので、相設定スイッチ34Aはこの3種類に対応させている。図3は負荷制御装置34の概観を示す図であり、この図に示すように相設定スイッチ34AはL1、L2及びL1+L2のいずれか1つを設定できるようになっている。図3ではL1+L2に設定されている。   The load control device 34 is provided with a phase setting switch (phase setting means) 34A for setting a power supply phase to which the load 200 is connected. Since the phase information transmitted from the master station 40 is of three types, L1, L2, or L1 + L2, the phase setting switch 34A corresponds to these three types. FIG. 3 is a diagram showing an overview of the load control device 34. As shown in this figure, the phase setting switch 34A can set any one of L1, L2, and L1 + L2. In FIG. 3, it is set to L1 + L2.

負荷制御装置34は、子局70の電流判定部702から与えられた相情報と自身の相設定スイッチ34Aの設定情報を比較し、一致する場合に自身に接続された負荷200への電流を遮断する。相設定スイッチ34AがL1+L2に設定された場合で、電源線L1及びL2のいずれかにおいて過電流状態になると、全ての負荷200への電流が遮断される。また、相設定スイッチ34Aが電源線L1に設定された場合で、電源線L1において過電流状態になると、電源線L1に接続されている負荷200に対して電流が遮断される。また、相設定スイッチ34Aが電源線L2に設定された場合で、電源線L2において過電流状態になると、電源線L2に接続されている負荷200に対して電流が遮断される。このように、負荷制御装置34が子局70から相情報を受け取り、自身の相設定スイッチ34Aの設定情報と比較し、一致する場合に電流遮断を行うので、過電流に陥っている電源相に関係する負荷200だけを遮断制御することが可能となる。   The load control device 34 compares the phase information given from the current determination unit 702 of the slave station 70 with the setting information of its own phase setting switch 34A, and cuts off the current to the load 200 connected to itself when they match. To do. In the case where the phase setting switch 34A is set to L1 + L2, if an overcurrent state occurs in any of the power supply lines L1 and L2, the current to all the loads 200 is cut off. Further, when the phase setting switch 34A is set to the power supply line L1 and the power supply line L1 enters an overcurrent state, the current is cut off from the load 200 connected to the power supply line L1. Further, when the phase setting switch 34A is set to the power supply line L2 and the power supply line L2 enters an overcurrent state, the current is cut off from the load 200 connected to the power supply line L2. In this way, the load control device 34 receives the phase information from the slave station 70, compares it with the setting information of its own phase setting switch 34A, and performs current interruption when the two coincide with each other. Only the related load 200 can be controlled to be cut off.

また、各住戸101の住宅分電盤30には、本実施の形態の集合住宅幹線電流制御システムの状態を示す表示装置(表示手段)35が収納されており、この表示装置35には負荷200を制限していることを示す表示や音声案内に加えて、子局70の電流判定部702により検出された電源相の電流値(又は電流値の大きさを示すレベル情報に置き換えたもの)と、過電流と検出された電源相の住戸電流検出部90にて検出された電流値(又は電流値の大きさを示すレベル情報に置き換えたもの)とが並べて表示される。住居人はこの表示を見ることで、負荷200を遮断されたときの自身の住戸内での消費電流の多さを確認したり、逆に幹線電流の少ない相の電源を優先的に使うようにしたりすることで、負荷200を制限されることなく快適に使用することができるようになる。また、複数の負荷200のそれぞれに対して遮断制御する優先順位を設定する場合、住居人は遮断される順位に関しての納得感を得やすくなる。   The housing distribution board 30 of each dwelling unit 101 houses a display device (display means) 35 that indicates the state of the collective housing trunk line current control system of the present embodiment. In addition to the display and voice guidance indicating that the current is limited, the current value of the power supply phase detected by the current determination unit 702 of the slave station 70 (or the level information indicating the magnitude of the current value) and The current value detected by the dwelling current detection unit 90 of the power supply phase detected as an overcurrent (or the value replaced with level information indicating the magnitude of the current value) is displayed side by side. Residents can check this display to check the amount of current consumed in their dwelling unit when the load 200 is cut off, or conversely use the power source of the phase with a low mains current. The load 200 can be comfortably used without being restricted. Moreover, when setting the priority order to perform the blocking control for each of the plurality of loads 200, the resident can easily obtain a sense of satisfaction regarding the order of blocking.

このように本実施の形態の集合住宅幹線電流制御システムによれば、親局40において、幹線電流を電源相別に監視し、過電流になったときには、過電流状態となっている電源線L1、L2又はL1+L2を示す相情報を含む制御信号を子局70に送信し、子局70に接続された全ての負荷制御装置34のそれぞれが、自身の相設定スイッチ34Aで設定された設定情報と子局70を介して親局40から与えられた相情報を比較し、一致する場合に電流の供給を制限するので、過電流に陥っている電源相に関係する負荷200のみ電流制限することが可能となり、住居人に必要のない不便をかけてしまうことが無くなる。   As described above, according to the apartment house trunk line current control system of the present embodiment, the master station 40 monitors the trunk line current for each power supply phase, and when the overcurrent occurs, the power line L1 in an overcurrent state, A control signal including phase information indicating L2 or L1 + L2 is transmitted to the slave station 70, and each of all the load control devices 34 connected to the slave station 70 receives the setting information and the child set by the own phase setting switch 34A. Since the phase information given from the master station 40 is compared via the station 70 and the supply of the current is limited if they match, it is possible to limit the current only for the load 200 related to the power supply phase that is in the overcurrent state. This eliminates unnecessary inconvenience for residents.

(実施の形態2)
図4は、本発明の実施の形態2に係る集合住宅幹線電流制御システムの概略構成を示すブロック図である。なお、図4において前述した図2と共通する部分には同一の符号を付けて、その説明を省略する。
(Embodiment 2)
FIG. 4 is a block diagram showing a schematic configuration of an apartment house trunk line current control system according to Embodiment 2 of the present invention. 4 that are the same as those in FIG. 2 described above are denoted by the same reference numerals and description thereof is omitted.

前述した実施の形態1の集合住宅幹線電流制御システムは、子局70の電流判定部702が親局40より受け取った相情報を全ての負荷制御装置34に与え、各負荷制御装置34が電流判定部702から与えられた相情報と自身の相設定スイッチ34Aの設定情報を比較し、一致する場合に電流の供給制限を行うものであったが、本実施の形態の集合住宅幹線電流制御システムは、子局70Aが負荷制御装置37ごとの相情報を設定可能な相設定スイッチ705を有し、子局70Aの電流判定部702Aが親局40より受け取った相情報と相設定スイッチ(相設定手段)705で設定された負荷制御装置37ごとの設定情報を比較し、一致する全ての負荷制御装置37を選択し、選択した負荷制御装置37にのみ制御指令を与え、過電流に陥っている電源相に関係する負荷200のみ電流の供給制限を行うものである。   In the housing complex main line current control system according to the first embodiment described above, the phase information received by the current determination unit 702 of the slave station 70 from the master station 40 is given to all the load control devices 34, and each load control device 34 determines the current. The phase information given from the unit 702 and the setting information of its own phase setting switch 34A are compared, and if they match, the current supply is limited, but the collective housing trunk line current control system of the present embodiment is The slave station 70A has a phase setting switch 705 that can set phase information for each load control device 37, and the current determination unit 702A of the slave station 70A receives the phase information and the phase setting switch (phase setting means). ) The setting information for each load control device 37 set in 705 is compared, all matching load control devices 37 are selected, a control command is given only to the selected load control device 37, and an overcurrent occurs. Only load 200 relating to the power supply phase and performs a supply current limitation.

図5は、子局70Aの概観を示す図であり、この図に示すように子局70Aには4個の負荷200のそれぞれに対して相設定(L1、L2、L1+L2)を行える相設定スイッチ(例えば、DIPスイッチ)705と、各負荷制御装置37と電気的に接続するためのコネクタ70A1とを有している。   FIG. 5 is a diagram showing an overview of the slave station 70A. As shown in FIG. 5, the slave station 70A has a phase setting switch that allows phase setting (L1, L2, L1 + L2) for each of the four loads 200. (For example, a DIP switch) 705 and a connector 70A1 for electrically connecting to each load control device 37.

このように本実施の形態の集合住宅幹線電流制御システムによれば、親局40は、幹線電流を電源相別に監視し、過電流が生じた場合に相情報を含めた制御信号を各住戸101に設置された子局70Aに送信し、各住戸101の子局70Aの電流判定部702Aが通信部704で受信された相情報と相設定スイッチ705で設定された負荷制御装置37ごとの設定情報を比較し、一致する全ての負荷制御装置37を選択し、選択した負荷制御装置37にのみ制御指令を与えるので、過電流に陥っている電源相に関係する負荷200のみ電流の供給制限を行うことができる。また、全ての負荷制御装置37に対して相情報を含む制御指令を与えるのに比べて、選択した負荷制御装置37にのみ制限の有無のみを含む制御指令を与えるので、負荷制御装置37への通信を単純に少なくできるといった利点も得られる。   As described above, according to the apartment house trunk line current control system of the present embodiment, the master station 40 monitors the trunk line current for each power supply phase, and when an overcurrent occurs, a control signal including phase information is sent to each dwelling unit 101. Phase information received by the communication unit 704 by the current determination unit 702A of the slave station 70A of each dwelling unit 101 and setting information for each load control device 37 set by the phase setting switch 705 Are selected, all the matching load control devices 37 are selected, and a control command is given only to the selected load control device 37, so that the current supply is limited only to the load 200 related to the power supply phase in the overcurrent state. be able to. Further, compared to giving a control command including phase information to all the load control devices 37, only the selected load control device 37 is given a control command including only whether or not there is a restriction. There is also an advantage that communication can be simply reduced.

なお、本実施の形態において、複数の負荷制御装置37のそれぞれの相を設定する相情報設定スイッチ705として前述したDIPスイッチの他に、ロータリスイッチを用いることもできる。DIPスイッチやロータリスイッチを用いることで、設定を一度に実施することができる。また、本実施の形態においても複数の負荷制御装置37のそれぞれに対して優先順位を付与し、その優先順位に従って各負荷200に対する電流の供給制限を行うようにしても良い。   In the present embodiment, a rotary switch can be used in addition to the above-described DIP switch as the phase information setting switch 705 for setting each phase of the plurality of load control devices 37. By using a DIP switch or a rotary switch, the setting can be performed at a time. Also in the present embodiment, priority may be given to each of the plurality of load control devices 37, and current supply to each load 200 may be restricted according to the priority.

(実施の形態3)
図6は、本発明の実施の形態3に係る集合住宅幹線電流制御システムの概略構成を示すブロック図である。なお、図6において前述した図2と共通する部分には同一の符号を付けて、その説明を省略する。
(Embodiment 3)
FIG. 6 is a block diagram showing a schematic configuration of an apartment house main line current control system according to Embodiment 3 of the present invention. 6 that are the same as those in FIG. 2 described above are denoted by the same reference numerals and description thereof is omitted.

本実施の形態の集合住宅幹線電流制御システムは、負荷制御装置37Bごとに相情報を記憶する不揮発性の記憶媒体を用いた相情報記憶部(相情報記憶手段)707を有する子局70Bを備える。このシステムにおいては、図7のシーケンス図に示すように、負荷制御装置37Bが負荷200への電流供給を遮断すると、その旨を子局70Bの電流判定部702Bが親局40の電流判定部402に通知し(すなわち、負荷制限通知を行い)、親局40の電流判定部402は、この負荷制限通知を受けたとき、幹線電流を電源相別に監視している幹線電流検出部60の監視結果に基づき電流の減少した電源相を検出し、前記負荷200が接続された電源相を判断し、その相情報を子局70Bの電流判定部702Bに返信する。   The apartment house main line current control system according to the present embodiment includes a slave station 70B having a phase information storage unit (phase information storage means) 707 using a nonvolatile storage medium that stores phase information for each load control device 37B. . In this system, as shown in the sequence diagram of FIG. 7, when the load control device 37 </ b> B cuts off the current supply to the load 200, the current determination unit 702 </ b> B of the slave station 70 </ b> B informs that effect. When the current determination unit 402 of the master station 40 receives the load limitation notification, the monitoring result of the main line current detection unit 60 that monitors the main line current for each power supply phase is received. Based on the power supply phase, the power supply phase to which the load 200 is connected is detected, the power supply phase to which the load 200 is connected is determined, and the phase information is returned to the current determination unit 702B of the slave station 70B.

電流判定部702Bは、電流判定部402から返信された相情報を受け取ることで、負荷制御装置37Bの相情報を知ることができる。すなわち、負荷制御装置37Bがどの電源相に接続されているかを知ることができる。これは、負荷制限を通知してきた全ての負荷制御装置37Bについて言える。   The current determination unit 702B can know the phase information of the load control device 37B by receiving the phase information returned from the current determination unit 402. That is, it can be known to which power supply phase the load control device 37B is connected. This can be said for all the load control devices 37B that have notified the load limitation.

電流判定部702Bは、受け取った相情報を相情報記憶部707に記憶する。その後、過電流の発生に伴い、電流判定部402から改めて負荷遮断要求の制御信号を受けると、該制御信号に含まれる相情報と相情報記憶部707に記憶されている負荷制御装置37Bごとの相情報とを照合し、制限すべき負荷制御装置37Bを選択する。そして、選択した負荷制御装置37Bにのみ制御指令を与える。この結果、過電流に陥っている電源相に関係する負荷200のみ電流の供給制限を行うことができる。   The current determination unit 702B stores the received phase information in the phase information storage unit 707. Thereafter, when a load cutoff request control signal is received again from the current determination unit 402 due to the occurrence of an overcurrent, the phase information included in the control signal and each load control device 37B stored in the phase information storage unit 707 are received. The load control device 37B to be restricted is selected by collating with the phase information. Then, a control command is given only to the selected load control device 37B. As a result, only the load 200 related to the power supply phase falling into the overcurrent can be limited in current supply.

本実施の形態の集合住宅幹線電流制御システムでは、各負荷制限装置37Bの相情報を設定する手段を省くことができるだけでなく、親局40の電流判定部402で検出した電源の相と子局70Bの電流判定部702Bで検出した電源の相とが入れ替わっていても影響なく負荷制御が行えるため、施工の際に幹線電流検出部60の相を確認することなく、一切の設定が不要となる。これにより、簡便かつ間違いのない施工が可能となる。   In the apartment house main line current control system of the present embodiment, not only the means for setting the phase information of each load limiting device 37B can be omitted, but also the phase of the power source detected by the current determination unit 402 of the master station 40 and the slave station Even if the phase of the power source detected by the current determination unit 702B of 70B is switched, load control can be performed without any influence, so that no setting is required without confirming the phase of the main current detection unit 60 during construction. . Thereby, construction which is simple and without mistakes is possible.

また、後々の結線変更などで負荷の電源の相が変更されたとしても毎回相情報の確認を行うことで自動的に設定を更新することができるので、設定し忘れなどもなく、保守性にも優れている。   In addition, even if the power supply phase of the load is changed due to a later connection change, the setting can be automatically updated by checking the phase information every time, so there is no need to forget to set it and maintainability Is also excellent.

当然のことながら通電の初期状態では相情報を得ることができないため、子局70Bの電流判定部702Bは、親局40の電流判定部402から送られる相情報を利用せずに、負荷制御装置37に対して順次、負荷制御の指令を送ることになる。このようなことから、子局70Bに不揮発性の記憶媒体を用いた相情報記憶部707を備えている。この相情報記憶部707に相情報を記憶させておくことで、停電等による情報喪失による復電後初回でも、効率的な負荷制御を行うことができる。   As a matter of course, since the phase information cannot be obtained in the initial energization state, the current determination unit 702B of the slave station 70B does not use the phase information sent from the current determination unit 402 of the master station 40, and the load control device The load control command is sent to 37 sequentially. For this reason, the slave station 70B includes a phase information storage unit 707 that uses a nonvolatile storage medium. By storing the phase information in the phase information storage unit 707, efficient load control can be performed even after the first power recovery due to information loss due to power failure or the like.

10 幹線
11 住戸線
20 幹線ブレーカ
30 住宅分電盤
31 リミッタ
32 メインブレーカ
33 分岐ブレーカ
34、37、37B 負荷制御装置
34A、705 相設定スイッチ
35 表示装置
40 親局
50、80 電流計測装置
60 幹線電流検出部
70、70A、70B 子局
90 住戸電流検出部
100 集合住宅
101 住戸
110 共用部分
200 負荷
401 電流計測部
402 電流判定部
403 設定部
404 通信部
701 電流計測部
702、702A、702B 電流判定部
703 設定部
704 通信部
707 相情報記憶部
10 trunk line 11 dwelling unit line 20 trunk line breaker 30 residential distribution board 31 limiter 32 main breaker 33 branch breaker 34, 37, 37B load control device 34A, 705 phase setting switch 35 display device 40 master station 50, 80 current measurement device 60 trunk line current Detection unit 70, 70A, 70B Slave station 90 Dwelling current detection unit 100 Apartment house 101 Dwelling unit 110 Shared part 200 Load 401 Current measurement unit 402 Current determination unit 403 Setting unit 404 Communication unit 701 Current measurement unit 702, 702A, 702B Current determination unit 703 Setting unit 704 Communication unit 707 Phase information storage unit

Claims (7)

複数の住戸に配電する幹線に設置された幹線ブレーカと、
前記幹線ブレーカの下流において前記幹線から各住戸用に分岐した電路のそれぞれに設置され、各住戸に配置した住宅分電盤に収納されたリミッタとメインブレーカの少なくともいずれか一方と、
前記幹線ブレーカを通過する幹線電流を電源相別に検出する幹線電流検出手段と、
前記幹線電流検出手段により検出された電源相別の幹線電流のそれぞれが前記幹線ブレーカにおける過電流領域である状態が規定の制限時間に達したか否かを判定する第1の電流判定手段と、
前記リミッタまたはメインブレーカを通過する住戸電流を電源相別に検出する住戸電流検出手段と、
前記第1の電流判定手段により制限時間に達したと判定され、かつ前記住戸電流検出手段で検出された電流値が前記リミッタまたはメインブレーカの定格電流に対して規定した閾値以上となったとき、前記第1の電流判定手段によって検出された電源相を示す相情報を出力する第2の電流判定手段と、
前記第2の電流判定手段から前記相情報が出力された場合、住戸内に設けられた負荷のうち、前記相情報で示される電源相に接続された負荷に対して電流制限制御を行う負荷制御手段と、
を備えた集合住宅幹線電流制御システム。
A main breaker installed on the main line that distributes power to multiple units,
At least one of a limiter and a main breaker housed in a residential distribution board placed in each dwelling unit, installed in each of the electric circuits branched from the main line for each dwelling unit downstream of the main line breaker,
A main line current detecting means for detecting a main line current passing through the main line breaker for each power supply phase;
First current determination means for determining whether or not a state where each of the main line currents detected by the main line current detection means is an overcurrent region in the main line breaker has reached a specified time limit;
Dwelling unit current detection means for detecting the dwelling unit current passing through the limiter or the main breaker for each power supply phase;
When it is determined that the time limit has been reached by the first current determination unit, and the current value detected by the dwelling unit current detection unit is equal to or greater than a threshold value defined for the rated current of the limiter or the main breaker, Second current determination means for outputting phase information indicating the power supply phase detected by the first current determination means;
Load control for performing current limit control on a load connected to the power supply phase indicated by the phase information among the loads provided in the dwelling unit when the phase information is output from the second current determination unit Means,
Apartment house mains current control system equipped with.
前記負荷制御手段は、電流制限対象の負荷が接続される電源相を設定する相設定手段を備え、前記第2の電流判定手段から出力された前記相情報と前記相設定手段で設定された設定情報を比較し、一致する相情報がある場合に電流制限制御を行う請求項1に記載の集合住宅幹線電流制御システム。   The load control means includes phase setting means for setting a power supply phase to which a load to be limited in current is connected, and the phase information output from the second current determination means and the setting set by the phase setting means The apartment house main line current control system according to claim 1, wherein the current limit control is performed when the information is compared and there is matching phase information. 複数の住戸に配電する幹線に設置された幹線ブレーカと、
前記幹線ブレーカの下流において前記幹線から各住戸用に分岐した電路のそれぞれに設置され、各住戸に配置した住宅分電盤に収納されたリミッタとメインブレーカの少なくともいずれか一方と、
前記幹線ブレーカを通過する幹線電流を電源相別に検出する幹線電流検出手段と、
前記幹線電流検出手段により検出された電源相別の幹線電流のそれぞれが前記幹線ブレーカにおける過電流領域である状態が規定の制限時間に達したか否かを判定する第1の電流判定手段と、
前記リミッタまたはメインブレーカを通過する住戸電流を電源相別に検出する住戸電流検出手段と、
負荷に供給される電流を制限する制御を行う少なくとも1個の負荷制御手段と、
前記負荷制御手段ごとに接続先の電源相を設定可能な相設定手段と、
前記第1の電流判定手段により制限時間に達したと判定され、かつ前記住戸電流検出手段で検出された電流値が前記リミッタまたはメインブレーカの定格電流に対して規定した閾値以上となったとき、その電源相を示す相情報と前記相設定手段で設定された前記負荷制御手段ごとの設定情報を比較し、一致する全ての負荷制御手段を選択し、選択した負荷制御手段にのみ制御指令を与える第2の電流判定手段とを備え、
前記負荷制御手段は、前記第2の電流判定手段からの制御指令を受け取ると、電流制限対象となる負荷に対して電流制限制御を行う集合住宅幹線電流制御システム。
A main breaker installed on the main line that distributes power to multiple units,
At least one of a limiter and a main breaker housed in a residential distribution board placed in each dwelling unit, installed in each of the electric circuits branched from the main line for each dwelling unit downstream of the main line breaker,
A main line current detecting means for detecting a main line current passing through the main line breaker for each power supply phase;
First current determination means for determining whether or not a state where each of the main line currents detected by the main line current detection means is an overcurrent region in the main line breaker has reached a specified time limit;
Dwelling unit current detection means for detecting the dwelling unit current passing through the limiter or the main breaker for each power supply phase;
At least one load control means for controlling to limit the current supplied to the load;
Phase setting means capable of setting a power supply phase of a connection destination for each load control means;
When it is determined that the time limit has been reached by the first current determination unit, and the current value detected by the dwelling unit current detection unit is equal to or greater than a threshold value defined for the rated current of the limiter or the main breaker, The phase information indicating the power phase is compared with the setting information for each load control means set by the phase setting means, all matching load control means are selected, and a control command is given only to the selected load control means Second current determining means,
When the load control unit receives a control command from the second current determination unit, the load control unit performs current limit control on a load to be current limited.
複数の住戸に配電する幹線に設置された幹線ブレーカと、
前記幹線ブレーカの下流において前記幹線から各住戸用に分岐した電路のそれぞれに設置され、各住戸に配置した住宅分電盤に収納されたリミッタとメインブレーカの少なくともいずれか一方のメインブレーカと、
前記幹線ブレーカを通過する幹線電流を電源相別に検出する幹線電流検出手段と、
前記幹線電流検出手段により検出された電源相別の幹線電流のそれぞれが前記幹線ブレーカにおける過電流領域である状態が規定の制限時間に達したか否かを判定する第1の電流判定手段と、
前記リミッタまたはメインブレーカを通過する住戸電流を電源相別に検出する住戸電流検出手段と、
負荷に供給される電流を制限する制御を行う少なくとも1個の負荷制御手段と、
前記負荷制御手段が電流制限対象の負荷への電流供給を制限したことを通知してくると、その旨を前記第1の電流判定手段に通知し、その後、前記第1の電流判定手段から前記電流制限対象の負荷が接続された電源相を示す相情報を受けることで該相情報を記憶し、また前記電源相を示す相情報の返信を受け、さらに前記第1の電流判定手段から負荷遮断要求の制御信号を受けると、該制御信号に含まれる相情報と記憶している負荷制御手段ごとの相情報とを照合し、電流制限すべき負荷制御手段を選択し、選択した負荷制御手段にのみ制御指令を与える第2の電流判定手段とを備え、
前記第1の電流判定手段は、前記第2の電流判定手段から電流供給を制限した通知を受けると、幹線電流を電源相別に監視している前記幹線電流検出手段の判定結果に基づき電流の減少した電源相を検出し、検出した相情報を前記第2の電流判定手段に送信し、
前記負荷制御手段は、前記第2の電流判定手段からの制御指令を受け取ると、前記電流制限対象の負荷に対して電流制限制御を行う集合住宅幹線電流制御システム。
A main breaker installed on the main line that distributes power to multiple units,
Installed in each of the electric circuits branched from the main line for each dwelling unit downstream of the main line breaker, the main breaker at least one of a limiter and a main breaker housed in a residential distribution board arranged in each dwelling unit,
A main line current detecting means for detecting a main line current passing through the main line breaker for each power supply phase;
First current determination means for determining whether or not a state where each of the main line currents detected by the main line current detection means is an overcurrent region in the main line breaker has reached a specified time limit;
Dwelling unit current detection means for detecting the dwelling unit current passing through the limiter or the main breaker for each power supply phase;
At least one load control means for controlling to limit the current supplied to the load;
When the load control means informs that the current supply to the load subject to current restriction is restricted, the load control means notifies the first current judging means to that effect, and then the first current judging means The phase information indicating the power supply phase connected to the load to be limited by current is received, the phase information is stored, the phase information indicating the power supply phase is received, and the load is cut off from the first current determination means. When the requested control signal is received, the phase information included in the control signal is compared with the stored phase information for each load control means, the load control means to be current-limited is selected, and the selected load control means And a second current determining means for giving only a control command,
When the first current determination unit receives a notification that the current supply is limited from the second current determination unit, the current decrease based on the determination result of the main line current detection unit that monitors the main line current for each power phase. Detected power phase, and transmits the detected phase information to the second current determination means,
When the load control unit receives a control command from the second current determination unit, the load control unit performs a current limit control on the current limit target load.
前記第2の電流判定手段は、前記第1の電流判定手段から受け取る負荷遮断要求に含まれる相情報に一致する電源相に接続されていない負荷を電流制限対象とする前記負荷制御手段に対して電流制限を解除するための制御指令を与える請求項4に記載の集合住宅幹線電流制御システム。   The second current determination unit is configured to control the load control unit that targets a load that is not connected to the power supply phase that matches the phase information included in the load cutoff request received from the first current determination unit. The apartment house trunk line current control system according to claim 4 which gives a control command for canceling current limitation. 前記相情報を記憶する不揮発性の記憶媒体を用いた相情報記憶手段を備える請求項4又は請求項5に記載の集合住宅幹線電流制御システム。   The apartment house trunk line current control system according to claim 4 or 5, further comprising phase information storage means using a nonvolatile storage medium for storing the phase information. 前記第1の電流判定手段によって電流制限が必要と検出された電源相を流れる電流の値と前記住戸電流検出手段により検出された前記リミッタまたはメインブレーカを流れる電流の値とを表示する表示手段を備えた請求項1乃至請求項6のいずれかに記載の集合住宅幹線電流制御システム。   Display means for displaying the value of the current flowing through the power supply phase detected as requiring current limitation by the first current judging means and the value of the current flowing through the limiter or main breaker detected by the dwelling unit current detecting means; The apartment house main line current control system according to any one of claims 1 to 6 provided.
JP2009220359A 2009-09-25 2009-09-25 Apartment house main line current control system Active JP5388346B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009220359A JP5388346B2 (en) 2009-09-25 2009-09-25 Apartment house main line current control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009220359A JP5388346B2 (en) 2009-09-25 2009-09-25 Apartment house main line current control system

Publications (2)

Publication Number Publication Date
JP2011072109A JP2011072109A (en) 2011-04-07
JP5388346B2 true JP5388346B2 (en) 2014-01-15

Family

ID=44016830

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009220359A Active JP5388346B2 (en) 2009-09-25 2009-09-25 Apartment house main line current control system

Country Status (1)

Country Link
JP (1) JP5388346B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5867149B2 (en) * 2012-02-22 2016-02-24 Tdk株式会社 Power control unit and power control system
CN104442407B (en) * 2014-08-27 2016-08-31 南车南京浦镇车辆有限公司 Pantagraph current collector and third rail system matching detection method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4633951B2 (en) * 2001-03-30 2011-02-16 テンパール工業株式会社 Single-phase three-wire electric circuit load limiter

Also Published As

Publication number Publication date
JP2011072109A (en) 2011-04-07

Similar Documents

Publication Publication Date Title
KR101412711B1 (en) The method and equipment of public address broadcasting system for abnormal load analysis and processing
JP5044225B2 (en) Apartment house main line current control system
JP4937826B2 (en) Power distribution system
KR101052471B1 (en) Neutral wire replacement device in power system and method
GB2449677A (en) A system for identifying a risk of fire in a power network
JP2014202572A (en) Power measurement device and power measurement system
RU2623456C2 (en) Overload detection device
KR102023954B1 (en) Monitoring and load controlling system of distribution panel
JP5388346B2 (en) Apartment house main line current control system
JP2017017794A (en) Power distribution line abnormality monitoring system
EP2498361A1 (en) Power distribution system for building and protection method for main line thereof
CN110073563A (en) The overcurrent protection of electric loading and its connection line
KR101030193B1 (en) Distrtibuting board cabinet panel with neutral line replacement and method thereof
JP6701019B2 (en) Overcurrent prevention device and power supply device
KR20190122444A (en) System for earth leakage circuit breaking
KR102018235B1 (en) DC power automatic switcher
JP6664824B2 (en) Signal output device for panel
JP5452016B2 (en) Apartment house main line current control system
KR20190096633A (en) Motor protection relay and motor protection system comprising the same
US11469613B2 (en) System for household electrical management and charging of electric vehicles and/or other high load appliances
RU181981U1 (en) Device for automatically limiting the overload of a high-voltage cable power line
JP6129679B2 (en) Power system stabilization system and power system stabilization method
KR20140013646A (en) Device for prevention disaster of abnormal voltage protection in electric power system and method thereof
JP2018191453A (en) Operation controller and power generation facility
JP2018153002A (en) Wiring system

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20120116

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120711

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130910

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20131007

R150 Certificate of patent or registration of utility model

Ref document number: 5388346

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150