JP5382394B1 - A method for linking and installing a reinforced steel bar and a reinforced steel frame for the same. - Google Patents

A method for linking and installing a reinforced steel bar and a reinforced steel frame for the same. Download PDF

Info

Publication number
JP5382394B1
JP5382394B1 JP2013070250A JP2013070250A JP5382394B1 JP 5382394 B1 JP5382394 B1 JP 5382394B1 JP 2013070250 A JP2013070250 A JP 2013070250A JP 2013070250 A JP2013070250 A JP 2013070250A JP 5382394 B1 JP5382394 B1 JP 5382394B1
Authority
JP
Japan
Prior art keywords
reinforcing bar
reinforcing
frame
divided
connecting member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2013070250A
Other languages
Japanese (ja)
Other versions
JP2014173418A (en
Inventor
義信 林
Original Assignee
株式会社恵信工業
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社恵信工業 filed Critical 株式会社恵信工業
Priority to JP2013070250A priority Critical patent/JP5382394B1/en
Application granted granted Critical
Publication of JP5382394B1 publication Critical patent/JP5382394B1/en
Publication of JP2014173418A publication Critical patent/JP2014173418A/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

【課題】 分割鉄筋籠を連結して連結鉄筋籠体として建込むときの連結擦れ及び連結外れを防止すること。
【解決手段】 縦杭2に分割鉄筋籠1の一段目を建込みすると共に二段目の分割鉄筋籠1の接続部4同士を並設させて保持固定し、該一段目と二段目の直近の補強枠8同士に連結部材19で跨いで橋架するように保持固定し、また該連結部材19が両端に掛止部20を有する係止連結部材21とし、補強枠8同士を掛止して橋架すると共に保持固定し、また該連結部材19が延伸連結部材22として該分割鉄筋篭1の両端の間の各補強枠8に橋設保持固定すると共に次段の分割鉄筋篭1の補強枠8まで延設保持固定して各段を一体の連結鉄筋籠体1aとする連結建込み方法と、該分割鉄筋籠1が隣接する直近の補強枠8同士を連結部材19、又は係止連結部材21、又は延伸連結部材22で橋設保持固定して一体の連結鉄筋篭体1aとしている。
【選択図】図1
PROBLEM TO BE SOLVED: To prevent connection rubbing and disengagement when connecting divided reinforcing bar rods and building them as a connecting reinforcing bar frame.
[MEANS FOR SOLVING PROBLEMS] A first stage of a split reinforcing bar rod 1 is installed in a vertical pile 2 and connecting portions 4 of the second stage split reinforcing bar rods 1 are juxtaposed and fixed to each other. The connecting members 19 are held and fixed so as to be bridged by the connecting members 19 between the nearest reinforcing frames 8, and the connecting members 19 are the locking connecting members 21 having the locking portions 20 at both ends, and the reinforcing frames 8 are hooked together. The connecting member 19 is bridged and fixed to each reinforcing frame 8 between both ends of the split reinforcing bar 1 as a stretched connecting member 22 and the reinforcing frame of the next stage split reinforcing bar 1 is supported. 8 and extending and holding and fixing each stage to be an integrally connected reinforcing bar frame 1a, and the nearest reinforcing frame 8 adjacent to the divided reinforcing bar bar 1 is connected to the connecting member 19 or the locking connecting member. 21 or the extended connecting member 22 is held and fixed by the bridge to form an integrally connected reinforcing bar frame 1a. .
[Selection] Figure 1

Description

本発明は、分割で組み立てられた鉄筋篭を各連結接続して建込みする分割鉄筋篭の連結建込み方法と、その鉄筋篭を連結接続する連結鉄筋篭体に関する。  TECHNICAL FIELD The present invention relates to a method for connecting and installing divided reinforcing bars to which the reinforcing bars assembled by division are connected to each other and a connecting reinforcing bar frame for connecting and connecting the reinforcing bars.

従来、場所打ち杭(現場で組んだ円筒状の鉄筋篭を、掘削した地盤の縦坑の中に落とし込み、後からコンクリートを穴の中に流し込み、固めて杭を形成するもの。)に用いられる鉄筋篭は、前記掘削した地盤の中に鉄筋篭を落とし込みする時、上下の鉄筋篭を複数段連結接続して一体の連結鉄筋篭体としている。  Conventionally, it is used for cast-in-place piles (in which a cylindrical reinforcing bar constructed in the field is dropped into a vertical shaft of excavated ground, and then concrete is poured into a hole and hardened to form a pile). When a reinforcing bar is dropped into the excavated ground, a plurality of upper and lower reinforcing bars are connected and connected to form an integrated connecting reinforcing bar.

その鉄筋篭は、環状のフープ筋及び補強枠と縦主筋を格子状に組み立てられた分割鉄筋籠とし、そして該分割鉄筋篭同士を直列に連結接続するとき、その直列に連結接続する部材は、該縦主筋の先端面同士を当接した状態でスリーブ状ネジ部材により螺着接続し、又は同様にスリーブにより圧着し、又は該縦主筋を並設させて該連結接続する接続部にスリーブで圧着し、上述それぞれのネジ部材、スリーブの接続部内にグラウト(空洞、空隙、隙間などを埋めるために注入する流動性の液体。)を注入して間隙を埋めることで補強して、該分割鉄筋籠を連結接続して連結鉄筋籠体としている。  The reinforcing bar rod is a split reinforcing rod rod in which a ring-shaped hoop bar and a reinforcing frame and longitudinal main bars are assembled in a lattice shape, and when the divided reinforcing rod rods are connected in series, the members connected in series are: The longitudinal main bars are in contact with each other with a sleeve-like screw member in a state where they are in contact with each other, or are similarly crimped with a sleeve, or the longitudinal main bars are juxtaposed with each other and crimped with a sleeve to the connecting and connecting portion. Then, a grout (a fluid liquid to be injected to fill a cavity, gap, gap, etc.) is injected into the connecting portion of each of the above screw members and sleeves, and the gap is filled to reinforce the divided reinforcing bar rod. Are connected to form a connected rebar frame.

また、該鉄筋篭の縦主筋端部同士を所定量互いに当接させて並設すると共に該並設部の所定位置にUボルト、結束線等で保持固定し、さらに溶接で溶着して連結接続することが一般的に行われていた。  Further, the longitudinal main bar ends of the reinforcing bar rods are arranged side by side in contact with each other by a predetermined amount, and held and fixed at predetermined positions of the side by side with U-bolts, binding wires, etc. It was generally done.

しかし、主筋の溶接構造に関して、社団法人 日本道路協会が、平成24年3月に発行する「道路橋示方書・同解説」の「19.8 鉄筋かごの製作及び建込み」の(1)の、ただし書きに「…ただし、鉄筋の組立においては、組立上の形状保持などのための溶接を行ってはならない。」とされ、その解説に、「…、溶接による…施工品質の確保が困難であり鉄筋の断面減少等の欠陥が生じるおそれがあるため、…」として、鉄筋かごの主要構成部材である主筋に直接の溶接を用いてはならないよう規定するに至って、主筋の無溶接工法の対応策が急がれる。  However, with regard to the welded structure of the main reinforcement, the Japan Road Association issued in March 2012 “Road Bridge Specification / Description” in “19.8 Production and Installation of Reinforcing Bars”. However, it is stated in the proviso that “... in the assembly of reinforcing bars, welding must not be performed to maintain the shape of the assembly.”, And in its explanation, “…, it is difficult to ensure construction quality by welding. Because there is a possibility that defects such as cross-section reduction of reinforcing bars will occur, it will be prescribed that the main reinforcing bar, which is the main component of the reinforcing bar cage, should not be used for direct welding. Measures are rushed.

しかして、鉄筋籠の建込みに関連する先行技術として、「カプラーナット10とロックナット11を用いて、上側の柱鉄筋篭Bの芯筋2を下側の柱鉄筋篭Aの芯筋2に接続し、この後、プレート12を降ろして、上側の柱鉄筋篭Bの外筋1を下降させ、上下の外筋1同士を接続する。」が記載される実施例を示す「先組柱鉄筋籠の建て込み方法」がある。(例えば、特許文献1参照)  Therefore, as a prior art related to the construction of the reinforcing bar rod, “using the coupler nut 10 and the lock nut 11, the core bar 2 of the upper column reinforcing bar rod B is changed to the core bar 2 of the lower column reinforcing bar rod A. After connecting, the plate 12 is lowered, the outer reinforcement 1 of the upper column reinforcement bar B is lowered, and the upper and lower outer reinforcements 1 are connected to each other. There is a "how to build a kite". (For example, see Patent Document 1)

また、関連する先行技術として、上板2、中板3及び下板4の三板1の長孔7の構成の複数板の内一板を一方向に移動させて、該長孔7に挿通される既設鉄筋篭及び新設鉄筋篭の両主筋を、前記複数板の協働により圧着したのち、該複数板をロックして前記両主筋を接続するとする、その複数板の一板を一方向に移動して圧着する接続に関する実施例を示す「鉄筋籠の接続方法及びその装置」がある。(例えば、特許文献2参照)  Further, as a related prior art, an inner plate of a plurality of plates in the configuration of the long hole 7 of the three plates 1 of the upper plate 2, the middle plate 3 and the lower plate 4 is moved in one direction and inserted into the long hole 7. After the main bars of the existing reinforcing bar rod and the newly installed reinforcing bar rod are pressure-bonded by the cooperation of the plurality of plates, the plurality of plates are locked and connected to the main bars. Then, there is a “rebar rod connection method and apparatus” showing an embodiment relating to the connection to be crimped. (For example, see Patent Document 2)

特開平8−319694号公報Japanese Patent Laid-Open No. 8-319694 特開平7−97863号公報JP-A-7-97863

従来の場所打ち杭に用いられる鉄筋篭の建込み方法は、鉄筋篭を複数段、連結接続して一体の鉄筋篭とする施工方法で、その連結接続に関して、主筋同士の溶接による連結が規制対象となるに至り、その溶接に変わる連結接続法に多くの課題とその課題解決が求められている。  The conventional method of building reinforcing bar used for cast-in-place piles is a construction method in which reinforcing bar is connected in multiple stages to make an integrated reinforcing bar. As a result, many problems and solutions to the connection method that replaces the welding are required.

つまり、主筋の溶接方法が認められなくなった今、鉄筋篭に使用する主筋の連結接続には、最も簡易でコストも低く抑えられるUボルト、結束線等で並設接続する部分を保持固定する連結方法が従来から行われているが、保持力が弱く、連結接続して建込みするときの高重量に耐えられず、接続部が擦れて、当初設計した所定の長さより長くなり、またその位置擦れにより連結が外れることもあることから大きな課題となり、簡易で安価な保持力のある連結建込み方法の提案が求められていた。  In other words, now that the main bar welding method is no longer accepted, the main bar connection used for rebar rods is the simplest and most cost-effective connection that holds and fixes the parts that are connected side by side with U-bolts, cable ties, etc. Although the method has been conventionally used, the holding force is weak, it cannot withstand the high weight when erected and connected, and the connection part is rubbed, becoming longer than the originally designed predetermined length, and its position Since the connection may be disengaged due to rubbing, it has been a big problem, and a proposal for a simple and inexpensive connection and building method with a holding force has been demanded.

また、上述した並設接続する部分を保持固定する連結方法の保持力の弱さは、鉄筋篭(分割鉄筋籠)をクレ−ン等で吊り起こし搬送して設置するその吊り起こす時に最も多く生じ、よってその時の主筋の捻れ、各係止部の位置擦れなど変形を防止し、また分割鉄筋篭に留まらず連結接続された連結鉄筋籠全体の変形防止することにより、鉄筋籠の崩壊を防ぐことができることから上記変形を防止することが求められている。  In addition, the weakness of the holding force of the connecting method for holding and fixing the above-described parallel connection portions occurs most frequently when the reinforcing bar rod (divided reinforcing bar rod) is lifted by a crane or the like and transported and installed. Therefore, it prevents deformation of the reinforcing bars by preventing the main bars from twisting, the position of each locking part from rubbing at that time, and preventing the deformation of the whole connected reinforcing bars instead of the split reinforcing bars. Therefore, it is required to prevent the above deformation.

そしてまた、上述した鉄筋籠の高重量化は、近年耐震化の要求により、使用する鉄筋を太くし、当然、該鉄筋籠も高重量となり、しかし上記鉄筋篭の主筋の連結接続には、特に高重量に対応するように変更されることなく従来の取付金具などが一般的に使用され、上述したように接続部の擦れ等により課題が多く発生し、よってその従来の取付金具などを使用しても高重量に対応できるものが求められていた。  In addition, the above-described increase in the weight of the reinforcing bar has recently increased the thickness of the reinforcing bar to be used in response to the demand for seismic resistance. Naturally, the reinforcing bar has also increased in weight. Conventional mounting brackets and the like are generally used without changing to correspond to the high weight, and as described above, there are many problems due to rubbing of the connection portion, etc. However, the thing which can respond to high weight was calculated | required.

さらに、上述した他の背景技術には、連結接続する接続部をスリーブにより圧着し、又はスリーブ状のネジ部材で該接続部を螺着接続は、接続保持力は確保できるとされているが、接続部の擦れによる長さの変化に不安が残り、さらにそのコストと作業性の改善が求められ、スリーブによる圧着は、油圧など圧着装置とその作業手順で時間を要し、またネジ部材での接続は、そのネジ部材と螺着作業及びその接続部の隙間にグラウトを注入するなど多くの手間を要し、コストと作業性の改善が求められる。  Furthermore, in the other background art described above, it is said that the connection holding force can be secured by crimping the connecting portion to be connected and connected by a sleeve, or screwing the connecting portion with a sleeve-like screw member. Anxiety remains in the length change due to the friction of the connecting part, and further improvement in cost and workability is required. Crimping with a sleeve takes time with a crimping device such as a hydraulic pressure and its work procedure, and also with a screw member The connection requires a lot of work such as screwing work with the screw member and injecting grout into the gap between the connection parts, and improvement in cost and workability is required.

しかして、先行技術で開示される特許文献1の「先組柱鉄筋籠の建て込み方法」は、カプラーナット10とロックナット11を用いることから、上述したネジ部材と同様の課題があり、コストと作業性の改善が求められる。  Therefore, the “method of erection of the pre-assembled column reinforcing bar” disclosed in Patent Document 1 disclosed in the prior art uses the coupler nut 10 and the lock nut 11, and thus has the same problem as the screw member described above, and costs Improvement of workability is required.

また、特許文献2の「鉄筋籠の接続方法及びその装置」は、複数板の内一板を一方向に移動して既設鉄筋篭及び新設鉄筋篭の両主筋を前記複数板に設けられる長穴7の逆方向の擦れによる協働する圧着と記載されていることから、この圧着作用は、従来使用されるUボルトと同様の接続作用で、その保持力では擦れのおそれがあり、またそのような締め付けによる保持力は、締め付け方向に対する保持力は強力でも、保持方向と直角方向である擦れ方向の保持力は弱く、従来の課題であるUボルトの保持力と同様、擦れ方向に対する保持力は弱く、保持力のある接続法の提案が求められる。  In addition, the “rebar rod connection method and apparatus” of Patent Document 2 is an elongated hole in which one main plate of a plurality of plates is moved in one direction and both main bars of an existing reinforcing rod and a new reinforcing rod are provided in the plurality of plates. 7 is described as cooperative crimping by rubbing in the reverse direction, and this crimping action is a connection action similar to a U-bolt used in the past, and there is a risk of rubbing with its holding force. Although the holding force by the tightening is strong in the tightening direction, the holding force in the rubbing direction perpendicular to the holding direction is weak, and the holding force in the rubbing direction is the same as the conventional U-bolt holding force. A proposal for a weak and holding connection method is required.

このような課題に鑑み本発明は、鉄筋籠の一段目と二段目の接続部を跨ぐように連結部材又は係止連結部材で補強枠同士を橋架するように橋設保持固定すること、また鉄筋籠両端側の補強枠を延伸連結部材で橋設保持固定すると共に一段目と二段目の接続部を跨ぐように該延伸連結部材を次段目の接続部直近の補強枠まで延設させて該次段目の補強枠に橋設保持固定することで、分割鉄筋籠の接続部である主筋同士を溶接することなく強固に連結接続させて一体の連結鉄筋籠体として建込みし、その簡易な構成の連結部材の接続方法及び鉄筋篭接続構造体により、求められる主筋の無溶接での低コストの接続を可能とし、また該連結鉄筋籠全体の歪みを延伸連結部材で防止することで、上述した課題の解決を図ることを目的とする。  In view of such a problem, the present invention is to hold and fix the bridge so that the reinforcing frames are bridged with a connecting member or a locking connecting member so as to straddle the first and second connecting portions of the reinforcing bar. Reinforcement frames on both ends of the reinforcing steel bar are bridged and held by extension connection members, and the extension connection members are extended to the reinforcement frame closest to the connection part of the next stage so as to straddle the connection parts of the first and second stages. By holding and fixing the bridge to the reinforcement frame at the next stage, the main reinforcing bars that are the connecting parts of the divided reinforcing bar rods are firmly connected without welding and built as an integral connecting reinforcing bar frame, By connecting the connecting member with a simple structure and the reinforcing bar rod connection structure, it is possible to connect the required main bars without welding at low cost, and by preventing the entire connecting reinforcing bar rod from being distorted by the elongated connecting member. The object is to solve the above-mentioned problems.

本発明は、上記課題を解決するために、第1の解決手段として、掘削した地盤の中に分割鉄筋籠の一段目を建込みすると共に該分割鉄筋籠の接続部を地盤より所定量突出した状態で保持し、次に、二段目の分割鉄筋籠の接続部に、前記一段目の主筋の接続部を並設させると共に該並設する双方の接続部同士をUボルト金具または結束線等で保持固定し、また該一段目と二段目の直近の補強枠同士に所定長さの連結部材を複数箇所、該接続部を跨いで橋架するように取付金具または結束線等の固定手段で橋設保持固定し、各分割鉄筋籠の各段を同様に、順次、連結接続しながら一体の連結鉄筋籠体とする連結建込み方法により、
該所定長さの連結部材で、接続部の並設量を設定させると共にその位置擦れ及び連結外れが生じないように、補強枠同士を橋架するように橋設保持固定することで該分割鉄筋籠を連結接続して一体の連結鉄筋籠体として建込みするとしている。
In order to solve the above-mentioned problem, the present invention provides a first solution means that the first stage of the split reinforcing bar is built in the excavated ground and the connecting portion of the split reinforcing bar is protruded by a predetermined amount from the ground. Next, the connecting portion of the first-stage main reinforcing bar is juxtaposed to the connecting portion of the second-stage split reinforcing bar rod, and the connecting portions of the two juxtaposed bars are U-bolt fittings or binding wires, etc. And fixing means such as mounting brackets or binding wires so as to bridge a plurality of connecting members of a predetermined length between the first and second reinforcing frames closest to each other and across the connecting portion. By holding and fixing the bridge, by connecting and building each integrated reinforcing bar frame in the same way, connecting and connecting each step of the reinforcing bar frame in turn,
The split reinforcing bar is fixed by bridging the reinforcing frames so as to bridge the reinforcing frames so that the connecting portions of the predetermined length are set in parallel and the position frames are not rubbed and disconnected. It is supposed that it will be built as an integral connecting rebar frame.

また、第2の解決手段として、該連結部材の両端に掛止部を形成した係止連結部材とし、上記並設連結された接続部直近の補強枠同士を橋架すると共に該補強枠に掛止する連結建込み方法により、
連結鉄筋籠体の上記接続部の長さを設定させると共にその位置擦れ及び連結外れが生じないように、該係止連結部材で、補強枠同士を掛止すると共に橋設保持固定させて該分割鉄筋籠を連結接続して、一体の連結鉄筋籠体として建込みするとしている。
Further, as a second solution, a latching coupling member having latching portions formed at both ends of the coupling member is used, and the reinforcing frames immediately adjacent to the connecting portions connected in parallel are bridged and latched on the reinforcing frame. Depending on the consolidated construction method
In order to set the length of the connecting portion of the connecting reinforcing bar frame and prevent the position rubbing and disconnection from occurring, the locking connecting member hooks the reinforcing frames together and holds and fixes the bridge. Reinforcing rods are connected and connected to form an integrated connecting rod frame.

また、第3の解決手段として、分割鉄筋篭の両端近傍の補強枠間を橋架すると共に上記並設連結する接続部を超えて次段の分割鉄筋篭の補強枠まで延設して橋架する延伸連結部材とし、該延伸連結部材を、該各補強枠に橋設保持固定すると共に次段の分割鉄筋篭の上記接続部直近の該補強枠に取付金具などの固定手段で保持固定する連結建込み方法により、
連結鉄筋籠体の長さを設定すると共に分割鉄筋篭及び一体の連結鉄筋籠体の全体の歪と、その位置擦れ及び連結外れが生じないように、該延伸連結部材で、各補強枠同士を連結保持させて各分割鉄筋籠を連結接続して、一体の連結鉄筋籠体として建込みするとしている。
In addition, as a third solution, the bridge between the reinforcing frames near both ends of the divided reinforcing bar rod is extended to extend to the reinforcing frame of the divided reinforcing rod of the next stage beyond the connecting portion connected in parallel. As a connecting member, the stretched connecting member is bridged and held and fixed to each reinforcing frame, and is held and fixed to the reinforcing frame in the immediate vicinity of the connecting portion of the divided reinforcing bar by a fixing means such as a mounting bracket. Depending on the method
Set the length of the connecting reinforcing bar frame, and prevent the entire reinforcing frame of the split reinforcing bar rod and the integral connecting reinforcing bar frame from being distorted and rubbed and disconnected. It is assumed that the divided reinforcing bar rods are connected and connected to be connected and built as an integral connecting reinforcing bar frame.

また、第4の解決手段として、分割鉄筋篭を複数連結接続して一体の連結鉄筋篭体が形成できるように、該分割鉄筋籠の主筋端部近傍を所定長さの接続部として設け、連結接続する該双方の接続部同士を突き合わせ状に並設すると共に該並設する双方の接続部同士をUボルト金具または結束線等の固定手段で保持固定すると共にさらに所定の長さの連結部材で、該並設連結された接続部直近の上記補強枠同士を複数箇所橋架すると共に取付金具または結束線等の固定手段で橋設保持固定して連結形成したことにより、
連結鉄筋籠体の長さを設定すると共にその位置擦れ及び連結外れが生じないように、分割鉄筋籠の補強枠同士を該連結部材で連結保持させて、該一体の連結鉄筋籠体として形成するとしている。
Further, as a fourth solving means, the vicinity of the main reinforcing bar end portion of the divided reinforcing bar rod is provided as a connecting portion having a predetermined length so that a plurality of divided reinforcing bar rods can be connected and connected to form an integral connecting reinforcing bar rod. The connecting portions of the two to be connected are arranged side by side in abutting manner, and the connecting portions of the two juxtaposed portions are held and fixed by a fixing means such as a U-bolt fitting or a binding wire, and a connecting member having a predetermined length is used. In addition, the reinforcing frames in the vicinity of the juxtaposed and connected portions are bridged at a plurality of locations and are formed by holding and fixing with a fixing means such as a mounting bracket or a binding wire.
The length of the connecting reinforcing bar frame is set, and the reinforcing frames of the divided reinforcing bar rods are connected and held by the connecting member so that the position rubbing and disconnection do not occur, thereby forming the integrated connecting reinforcing bar frame. It is said.

また、第5の解決手段として、並設連結された接続部直近の補強枠同士を橋架すると共に該補強枠に掛止できるように、該連結部材の両端に掛止部を形成した係止連結部材とするとしたことにより、
連結鉄筋籠体の長さを設定すると共にその位置擦れ及び連結外れが生じないように、分割鉄筋籠の補強枠同士を該係止連結部材で掛止すると共に橋設保持固定させて、該一体の連結鉄筋籠体として形成するとしている。
Further, as a fifth solving means, a locking connection in which the reinforcing frames in the vicinity of the connecting parts connected in parallel are bridged and hooked portions are formed at both ends of the connecting member so as to be hooked to the reinforcing frames. By making it a member,
The length of the connecting reinforcing bar frame is set, and the reinforcing frames of the divided reinforcing bar rods are hooked by the locking connecting members and bridged and held and fixed so that the position rubbing and disconnection do not occur. It is supposed to be formed as a connecting rebar frame.

また、第6の解決手段として、分割鉄筋篭の両端近傍の補強枠間を橋架すると共に上記並設連結する接続部を超えて次段の分割鉄筋篭の補強枠まで延設して橋架する延伸連結部材としたことにより、
連結鉄筋籠体の長さを設定すると共に分割鉄筋篭及び一体の連結鉄筋籠体の歪と、その位置擦れ及び連結外れが生じないように、該延伸連結部材で、各補強枠同士を該延伸連結部材で連結保持させて、該一体の連結鉄筋籠体として形成するとしている。
Further, as a sixth solution, the extension between the reinforcing frames in the vicinity of both ends of the divided reinforcing bar rod and the bridge extending by extending to the reinforcing frame of the divided reinforcing rod in the next stage beyond the connecting portion connected in parallel. By making it a connecting member,
Set the length of the connecting reinforcing bar frame and stretch the reinforcing frames with the extended connecting member so that the split reinforcing bar rod and the integral connecting reinforcing bar frame are not distorted, and the position rubbing and disconnection do not occur. It is assumed that it is formed by connecting and holding with a connecting member to form the integrally connected reinforcing bar frame.

本発明は、上述した手段によって課題を解決して有効な効果が得られるようにしたもので、特に、第1の解決手段の、縦方向の主筋に対し環状のフープ筋及び補強枠の内側または外側に所定本数それぞれ格子状に配置すると共に取付金具又は結束線などの固定手段で交差保持固定して所定形状の鉄筋籠を形成し、該分割鉄筋籠に連結接続する所定長さの接続部を該主筋端部に設け、該接続部で各段の該分割鉄筋篭同士を複数段連結接続しながら掘削した地盤の縦坑に場所打ち杭として落とし込む一体の連結鉄筋篭体として建込みする連結鉄筋篭体の連結建込み方法において、
掘削した地盤の縦坑に前記分割鉄筋籠の一段目を建込み挿入すると共に該分割鉄筋籠の接続部を地盤より所定量突出した状態で支持し、次に建込み挿入する二段目の分割鉄筋籠の接続部と、前記一段目の突出した主筋の接続部を突き合わせ状に並設させると共に該並設する双方の接続部同士をUボルト金具または結束線等の固定手段で保持固定し、次に、上記保持固定された該一段目と二段目の接続部直近の補強枠同士に、所定長さの連結部材を複数箇所、該接続部を跨いで橋架するように設けると共に取付金具または結束線等の固定手段で橋設保持固定して、該分割鉄筋籠を連結接続し、以後、各段の分割鉄筋籠を同様に連結接続しながら一体の連結鉄筋籠体として建込みする連結鉄筋篭体の連結建込み方法により、
分割鉄筋籠を連結接続しながら建込みする一体の連結鉄筋籠体は、接続部同士をUボルト金具または結束線等の固定手段で保持固定すると共に連結部材で補強枠同士を橋架するように取付金具または結束線等の固定手段で保持固定して連結接続させるので、連結鉄筋籠体の連結接続に位置擦れが生じないため全長が変形することなく、また建て込みによるその連結外れが生じず、よってその変形の修復などの無駄な作業も発生せず安全に作業が進められ、建て込み作業時間及びその建て込みコスト削減が実現できる。
The present invention solves the problem by the above-described means so that an effective effect can be obtained. In particular, the first solving means has an inner hoop line and a reinforcing frame inside the longitudinal main bar or the reinforcing frame. A predetermined number of connecting portions, which are arranged in a lattice shape on the outside and are held in a crossing manner by fixing means such as mounting brackets or binding wires to form a reinforcing bar rod having a predetermined shape, and are connected to the divided reinforcing rod rods. A connecting reinforcing bar that is provided at the end of the main reinforcing bar and is built as an integral connecting reinforcing bar frame that is dropped as a cast-in-place pile into the vertical shaft of the ground excavated while connecting the divided reinforcing bar rods at each stage in a plurality of stages at the connecting portion. In the consolidated construction method of the frame,
The first stage of the divided reinforcing bar is inserted and inserted into the vertical shaft of the excavated ground, and the connecting part of the divided reinforcing bar is supported in a state protruding by a predetermined amount from the ground, and then inserted into the second stage. The connecting portion of the reinforcing bar rod and the connecting portion of the protruding main reinforcing bar in the first stage are arranged side by side in abutting manner, and the two connecting portions arranged side by side are held and fixed by fixing means such as a U-bolt fitting or a binding wire, Next, a plurality of connecting members of a predetermined length are provided between the reinforcing frames adjacent to the first-stage and second-stage connecting parts held and fixed so as to bridge across the connecting parts and mounting brackets or A connecting rebar that is constructed by holding and fixing the bridge with a fixing means such as a binding wire, and connecting and connecting the divided reinforcing bar rods as a united connecting reinforcing bar frame. Depending on the method of connecting the housing,
The integrated rebar frame that is built while connecting and connecting the divided rebars is fixed so that the connecting parts are held and fixed by fixing means such as U-bolt fittings or binding wires, and the reinforcing frames are bridged by the connecting members. Since it is held and fixed with a fixing means such as a metal fitting or a binding wire, it is connected and connected, so there is no position rubbing in the connecting connection of the connecting reinforcing bar frame, and the total length does not deform, and the connection is not released due to the installation, Therefore, a wasteful work such as the repair of the deformation does not occur, and the work can be safely carried out, and the erection work time and the erection cost can be reduced.

また、建込みの連結作業で、補強枠同士を連結部材で連結接続するとき、取付金具または結束線等の固定手段で保持固定し、またボルト止めすることで変形に対する強度を増すことができ、さらに補強枠と連結部材を溶着でも可能で簡易な溶接作業で早く連結接続ができる。  In addition, when connecting and connecting reinforcement frames with a connecting member in a built-in connection operation, the strength against deformation can be increased by holding and fixing with a fixing means such as a mounting bracket or a binding wire, and bolting, Further, the reinforcing frame and the connecting member can be welded, and can be connected and connected quickly by a simple welding operation.

なお、この溶接については上述したような規制はあるが、主筋に対して直接溶接してはならない規制であって、補強枠については対象となっておらず、その補強枠と本願発明の連結部材との溶接には、何ら問題なく使用できるので、上述した簡易な手順で連結接続ができ、連結強度と作業時間の短縮及びそのコスト削減が実現できた。  In addition, although there are the above-mentioned regulations for this welding, it is a regulation that should not be welded directly to the main bar, and is not a target for the reinforcing frame, and the reinforcing frame and the connecting member of the present invention The welding can be used without any problem, so that the connecting connection can be made by the above-described simple procedure, and the connecting strength and working time can be shortened and the cost can be reduced.

また、連結部材の長さを所定長さに設定していることから、分割鉄筋籠同士の接続部の並設量を予め設定することなく、該連結部材の長さで補強枠同士を橋架するように設けると共に該連結部材と補強枠を取付金具または結束線等の固定手段で保持固定して連結接続することで、その一体の連結鉄筋籠の全長が正確に設定でき、よって連結作業が容易となり、その作業時間及びそのコスト削減が実現できた。  In addition, since the length of the connecting member is set to a predetermined length, the reinforcing frames are bridged with the length of the connecting member without setting in advance the amount of connection of the connecting portions between the divided reinforcing bar rods. By connecting and connecting the connecting member and the reinforcing frame with a fixing means such as a mounting bracket or a binding wire, the total length of the integral connecting rebar rod can be accurately set, and thus the connecting operation is easy. As a result, the working time and the cost were reduced.

しかして、第2の解決手段の、上記連結部材を、該連結部材の両端に掛止部を形成した係止連結部材とし、上記並設連結された接続部直近の補強枠同士を橋架すると共に該補強枠に掛止する連結鉄筋篭体の連結建込み方法により、
補強枠同士を該係止連結部材で橋架して連結接続するとき、該所定長さの係止連結部材の掛止部を該補強枠同士に掛止して連結できるので、予め主筋同士の接続部を並設する該並設量をその係止連結部材の所定長さで設定することにより、連結接続する並設量を調整することなく、連結接続する量を正確に早く設定でき、よって連結接続の作業が捗り、作業上の大きな効果となり、その作業時間及びそのコスト削減が実現できた。
Thus, in the second solving means, the connecting member is a locking connecting member in which a hooking portion is formed at both ends of the connecting member, and the reinforcing frames immediately adjacent to the connecting portions connected in parallel are bridged together. According to the connecting construction method of the connecting rebar frame that is hooked to the reinforcing frame,
When the reinforcing frames are bridged and connected by the locking connecting members, the locking portions of the predetermined length of the locking connecting members can be hooked and connected to the reinforcing frames, so the main bars are connected in advance. By setting the juxtaposition amount for juxtaposing the parts with the predetermined length of the locking connecting member, the amount of connecting and connecting can be set accurately and quickly without adjusting the amount of juxtaposing connection and connection. The work of connection progressed, and it became a big effect on work, and the work time and the cost reduction were realized.

しかして、第3の解決手段の、上記連結部材を、分割鉄筋篭の両端近傍の補強枠間を橋架すると共に上記並設連結する接続部を超えて次段の分割鉄筋篭の補強枠まで延設して橋架する延伸連結部材とし、該延伸連結部材を、該各補強枠に橋設保持固定すると共に次段の分割鉄筋篭の上記接続部直近の該補強枠に取付金具などの固定手段で保持固定する連結鉄筋篭体の連結建込み方法により、
分割鉄筋篭の両端部近傍の補強枠間を延伸連結部材で橋設保持するので、建込みするために該鉄筋籠を吊り上げたときの変形を該延伸連結部材が防ぎ、さらに該延伸連結部材で分割鉄筋篭を連結接続させると共にその連結接続部の変形及び一体の連結鉄筋籠の全体が歪まないように連結保持でき、よってその連結接続の強度を増し、さらに位置擦れ及び該外れを防止する大きな効果となり、上述第2の解決手段と同様、連結接続する量を正確に早く設定できるので連結接続の作業が捗る。
Thus, in the third solution means, the connecting member is bridged between the reinforcing frames in the vicinity of both ends of the divided reinforcing bar rod and extends to the reinforcing frame of the divided reinforcing bar rod of the next stage beyond the connecting portion to be connected in parallel. The extension connecting member is installed and bridged, and the extension connecting member is bridged and fixed to each reinforcing frame and fixed to the reinforcing frame in the vicinity of the connecting portion of the divided reinforcing bar in the next stage by fixing means such as a mounting bracket. By connecting and building the connecting rebar frame to hold and fix,
The stretched connecting member bridges and holds the reinforcing frames in the vicinity of both ends of the divided reinforcing bar so that the stretched connecting member prevents deformation when the reinforcing bar is lifted for building, and the extended connecting member further It is possible to connect the divided reinforcing bar rods together and to keep the connecting connecting portion deformed and the whole connecting reinforcing rod rods so as not to be distorted, thereby increasing the strength of the connecting connection and further preventing positional rubbing and disconnection. As in the case of the above-described second solving means, the amount of connection and connection can be set quickly and accurately, and the operation of connection and connection progresses.

しかして、第4の解決手段の、縦方向の主筋に対し環状のフープ筋及び補強枠の内側または外側に所定本数それぞれ格子状に配置すると共に取付金具又は結束線などの固定手段で交差保持固定して所定形状の鉄筋籠を形成し、該鉄筋籠を掘削した地盤の縦坑に複数段連結接続しながら落とし込む場所打ち杭に用いる円筒状の分割鉄筋籠であって、該分割鉄筋籠同士を連結接続して連結鉄筋篭体を形成する該連結接続する接続部において、
該分割鉄筋篭を複数連結接続して一体の連結鉄筋篭体が形成できるように、該分割鉄筋籠の主筋端部近傍を所定長さの接続部として設け、連結接続する該双方の接続部同士を突き合わせ状に並設すると共に該並設する双方の接続部同士をUボルト金具または結束線等の固定手段で保持固定すると共にさらに所定の長さの連結部材で、該並設連結された接続部直近の上記補強枠同士を複数箇所橋架すると共に取付金具または結束線等の固定手段で橋設保持固定して連結形成したことにより、
連結部材で補強枠同士を取付金具または結束線等の固定手段で橋設保持固定して連結保持させるので、連結鉄筋籠体の連結接続に位置擦れ及びその外れが生じず、その位置擦れ又はその外れたときの修復などの無駄な作業が発生せず、安全に建て込み作業が進められ、作業時間及びそのコスト削減ができる連結鉄筋籠体が得られた。
Thus, in the fourth solution means, a predetermined number of hoop bars and a reinforcing frame are arranged inside or outside the longitudinal main bars in a grid pattern, and fixed by crossing with fixing means such as mounting brackets or binding wires. Forming a rebar rod of a predetermined shape, and a cylindrical divided rebar rod used for a cast-in-place pile that is dropped while connecting and connecting to a vertical shaft of the ground where the rebar rod is excavated, In the connecting part for connecting and connecting to form a connecting rebar frame by connecting and connecting,
In order to form an integrally connected reinforcing bar frame by connecting and connecting a plurality of the divided reinforcing bar rods, the vicinity of the main reinforcing bar ends of the divided reinforcing bar rods are provided as connecting portions of a predetermined length, and the two connecting portions to be connected to each other Are connected in parallel with each other, and the connecting portions of the two side-by-side connections are held and fixed by fixing means such as a U-bolt fitting or a binding wire, and the connection members connected in parallel are connected by a connecting member having a predetermined length. By bridging the above-mentioned reinforcement frames in the immediate vicinity of a plurality of locations and forming a bridge by holding and fixing with a fixing means such as a mounting bracket or a binding wire,
Since the reinforcing frames are bridged, held and fixed by fixing means such as mounting brackets or binding wires, etc. with the connecting member, the position of the connecting rebar frame is not rubbed or detached, and the position rub or There was no wasteful work such as repairing when it came off, and it was possible to safely carry out the erection work and to obtain a connected reinforcing bar frame that can reduce the work time and cost.

また、連結部材の長さを所定の長さに設定することから、分割鉄筋籠同士の接続部の並設量を調整しながら連結接続することなく、該連結部材の長さで補強枠同士を橋設して連結接続できるので、その一体の連結鉄筋籠の全長が正確に早く設定でき、よって連結作業が容易で早くでき、その作業時間及びそのコスト削減が実現できた。  In addition, since the length of the connecting member is set to a predetermined length, the reinforcing frames are connected to each other with the length of the connecting member without connecting and connecting while adjusting the parallel arrangement amount of the connecting portions of the divided reinforcing bar rods. Since the bridges can be connected and connected, the total length of the integral connecting bar can be set accurately and quickly, so that the connecting work can be done easily and quickly, and the working time and cost can be reduced.

なお、分割鉄筋籠を組立てるとき、上記第4の解決手段の該分割鉄筋籠の格子状に配置される補強枠の取付位置において、該分割鉄筋篭の両端近傍に設けられるそれぞれの補強枠の交差取付位置を、予め正確に位置決めして組み立てることで、該鉄筋籠を吊り上げ建込みで該補強枠の取付位置に擦れが生じると、予定された連結接続する補強枠間の距離と、所定長さの連結部材との長さに差が生じることで補強枠の位置擦れを確認でき、またその位置擦れの対応策として、連結部材を補強枠に取付けるときその取付位置を調整することで対応できるので、その修正作業が容易で、連結鉄筋籠の長さがその場で修正でき、作業時間の短縮及びそのコスト削減が実現できる。  In addition, when assembling the divided reinforcing bar rods, the crossing points of the reinforcing frames provided in the vicinity of both ends of the divided reinforcing bar rods at the mounting positions of the reinforcing frame arranged in the lattice form of the divided reinforcing bar rods of the fourth solving means. When the mounting position is accurately positioned and assembled in advance, if the reinforcing bar is lifted and rubbed and the mounting position of the reinforcing frame is rubbed, a predetermined distance between the reinforcing frames to be connected and connected and a predetermined length Because the difference in length with the connecting member can be confirmed the position rubbing of the reinforcing frame, and as a countermeasure for the position rubbing, it can be handled by adjusting the mounting position when attaching the connecting member to the reinforcing frame. The correction work is easy, the length of the connecting reinforcing bar can be corrected on the spot, and the work time and the cost can be reduced.

また、建込みの連結作業の補強枠同士を連結部材で連結接続するとき、上述したように、取付金具または結束線等の固定手段で橋設保持固定して連結保持させるほか、補強枠と連結部材を溶着することで、連結作業が早く、また変形に対する強度を増すことができる保持固定としても良いが、具体的図示は省略した。  In addition, when connecting and connecting reinforcement frames for erection work with a connecting member, as described above, the bridge is held and fixed by fixing means such as mounting brackets or binding wires, and connected to the reinforcement frame. By welding the members, the connecting operation can be performed quickly and the strength against deformation can be increased, but the specific illustration is omitted.

しかして、第5の解決手段の、上記連結部材を、上記並設連結された接続部直近の補強枠同士を橋架すると共に該補強枠に掛止できるように、該連結部材の両端に掛止部を形成した係止連結部材とすることにより、
該所定長さの係止連結部材の掛止部を該補強枠同士に掛止させることで、主筋同士の接続部を並設する該並設量をその係止連結部材の所定長さで設定できると共に建込みする一体の連結鉄筋籠体の全長が容易に設定できることにより連結接続する長さが正確に早く設定でき、連結接続の作業が捗り、作業上の大きな効果となる。
Thus, in the fifth solution means, the connecting member is hooked at both ends of the connecting member so that the reinforcing frames in the vicinity of the connecting portions connected in parallel can be bridged and hooked to the reinforcing frame. By making the locking connecting member formed part,
By hooking the latching portions of the locking connection member of the predetermined length between the reinforcing frames, the juxtaposition amount for connecting the connecting portions of the main bars is set by the predetermined length of the locking connection member In addition, since the total length of the integrally connected reinforcing bar frame to be built can be easily set, the length of connecting and connecting can be set accurately and quickly, and the connecting and connecting work progresses, which is a great work effect.

しかして、第6の解決手段の、上記連結部材を、分割鉄筋篭の両端近傍の補強枠間を橋架すると共に上記並設連結する接続部を超えて次段の分割鉄筋篭の補強枠まで延設して橋架する延伸連結部材とすることにより、
該分割鉄筋篭の両端部近傍の補強枠間を延伸連結部材で橋設保持するので、建込みするために該鉄筋籠を吊り上げたときの変形を該延伸連結部材が防ぎ、また掘削した地盤の縦杭に落とし込むとき、該延伸連結部材で分割鉄筋篭を連結接続させると共にその連結接続部の変形及び一体の連結鉄筋籠体の全体が歪まないように連結保持させているので、連結接続の強度を増し、位置擦れ及びその外れを防止する大きな効果となり、上述の解決手段と同様、連結接続する量を正確に早く設定できるので連結接続の作業が捗る。
Thus, in the sixth solving means, the connecting member is bridged between the reinforcing frames in the vicinity of both ends of the divided reinforcing bar rod and extends to the reinforcing frame of the divided reinforcing bar rod of the next stage beyond the connecting portion to be connected in parallel. By setting it as an extended connecting member that is installed and bridged,
The stretched connecting member bridges and holds between the reinforcing frames in the vicinity of both ends of the split reinforcing bar, so that the extended connecting member prevents deformation when the reinforcing bar is lifted for building, and the excavated ground When dropping into a vertical pile, the split connecting rods are connected and connected by the extended connecting members, and the connecting and connecting portions are deformed and held together so as not to be distorted. This is a great effect of preventing positional rubbing and disengagement. Like the above-described solution, the amount of connection and connection can be set accurately and quickly, so that the operation of connection and connection progresses.

なお、第3及び第6の解決手段の延伸連結部材を設けた実施例のものに、係止連結部材同様の掛止部を形成して同様に橋設保持固定することで、連結接続の作業が捗る効果が得られる。
よって、これらの構成、作用から本発明は、実用上著大な効果を奏する。
It should be noted that, in the third and sixth solving means in which the extended connecting member is provided, a hooking portion similar to the locking connecting member is formed and similarly held and fixed by the bridge so that the connection connection work is performed. Can improve the effect.
Therefore, from these configurations and functions, the present invention has a practically significant effect.

本発明の実施例の分割鉄筋篭1の建込み状態を示す正面部分断面図である。It is a front fragmentary sectional view which shows the erection state of the division rebar 1 of the Example of this invention. 本発明の主筋7と補強枠8及びフープ筋10による分割鉄筋篭1の組立状態を示す要部の正面図である。It is a front view of the principal part which shows the assembly state of the split reinforcing bar rod 1 by the main reinforcement 7, the reinforcement frame 8, and the hoop reinforcement 10 of this invention. 本発明の主筋7と補強枠8及びフープ筋10の接続状態を示す要部の斜視図である。It is a perspective view of the principal part which shows the connection state of the main reinforcement 7, the reinforcement frame 8, and the hoop reinforcement 10 of this invention. 本発明の主筋7とフープ筋10の接続状態を示す要部の側面図である。It is a side view of the principal part which shows the connection state of the main reinforcement 7 and the hoop reinforcement 10 of this invention. 本発明の分割鉄筋篭1の連結接続状態を示す要部の正面図である。It is a front view of the principal part which shows the connection state of the division | segmentation reinforcing bar rod 1 of this invention. 本発明の連結部材19と補強枠8の固着状態を示す要部の側面図である。It is a side view of the principal part which shows the adhering state of the connection member 19 and the reinforcement frame 8 of this invention. 本発明の主筋7の接続状態を示す要部の正面図である。It is a front view of the principal part which shows the connection state of the main reinforcement 7 of this invention. 本発明の主筋7の接続状態を示す要部の平面図である。It is a top view of the principal part which shows the connection state of the main reinforcement 7 of this invention. 本発明の係止連結部材21と補強枠8の取付状態を示す要部の側面図である。It is a side view of the principal part which shows the attachment state of the latching connection member 21 and the reinforcement frame 8 of this invention. 本発明の係止連結部材21と補強枠8の取付状態を示す要部の拡大側面図である。It is an enlarged side view of the principal part which shows the attachment state of the latching connection member 21 and the reinforcement frame 8 of this invention. 本発明の延伸連結部材22の連結接続状態を示す連結鉄筋籠1aの要部の正面図である。It is a front view of the principal part of the connection reinforcement rod 1a which shows the connection connection state of the extending | stretching connection member 22 of this invention.

しかして、第1の実施形態は、掘削した地盤の縦杭に分割鉄筋籠の一段目を建込みすると共に鉄筋籠の接続部を地盤より所定量突出した状態で保持し、次に、二段目の分割鉄筋籠の接続部に、前記一段目の接続部を並設させると共に該並設部を固定手段で保持固定し、次に、該一段目と二段目の直近の補強枠同士に所定長さの連結部材を複数箇所、該接続部を跨いで橋架するように設けると共に固定手段で橋設保持固定し、各段の分割鉄筋籠を同様に連結接続しながら一体の連結鉄筋籠体として連結建込み方法と、
次に、第2の実施形態は、上記連結部材を、該連結部材の両端に掛止部を形成した係止連結部材とし、上記並設連結された接続部直近の補強枠同士を橋架すると共に該補強枠に掛止する連結建込み方法と、
次に、第3の実施形態は、上記連結部材を、分割鉄筋篭の両端近傍の補強枠間を橋架すると共に上記並設連結する接続部を超えて次段の分割鉄筋篭の補強枠まで延設して橋架する延伸連結部材とし、該延伸連結部材を、該各補強枠に橋設保持固定すると共に次段の分割鉄筋篭の上記接続部直近の該補強枠に取付金具などの固定手段で保持固定する連結建込み方法により
該連結部材又は係止連結部材で、連結部の長さを設定すると共に補強枠同士を連結保持し、また延伸連結部材で、分割鉄筋篭及び一体の連結鉄筋籠の全体が歪まないようにすると共に連結部の長さを設定することで分割鉄筋籠を連結接続して一体の連結鉄筋籠体として建込みする方法を実現させている。
Thus, in the first embodiment, the first stage of the split reinforcing bar is built in the vertical pile of the excavated ground and the connecting part of the reinforcing bar is protruded from the ground by a predetermined amount, and then the two steps. The connecting portion of the first stage is juxtaposed to the connecting part of the split rebar rod of the eye and the juxtaposed part is held and fixed by a fixing means, and then the nearest reinforcing frames of the first and second stages A connecting member of a predetermined length is provided so as to be bridged across a plurality of locations and the connecting portion, and is held and fixed by a fixing means. As a consolidated erection method,
Next, in the second embodiment, the connecting member is a locking connecting member in which a latching portion is formed at both ends of the connecting member, and bridges the reinforcing frames immediately adjacent to the juxtaposed and connected connecting portions. A connection erection method for hanging on the reinforcing frame;
Next, in the third embodiment, the connecting member is bridged between the reinforcing frames in the vicinity of both ends of the divided reinforcing bar rod and extends to the reinforcing frame of the divided reinforcing bar rod of the next stage beyond the connecting portion to be connected in parallel. The extension connecting member is installed and bridged, and the extension connecting member is bridged and fixed to each reinforcing frame and fixed to the reinforcing frame in the vicinity of the connecting portion of the divided reinforcing bar in the next stage by fixing means such as a mounting bracket. With the connecting construction method for holding and fixing, the length of the connecting portion is set and the reinforcing frames are connected and held by the connecting member or the locking connecting member, and the divided reinforcing bar rod and the integral connecting reinforcing rod rod are connected by the extended connecting member. As a result, it is possible to realize a method of connecting the divided reinforcing bar rods so as to be built as an integral connecting reinforcing bar frame by setting the length of the connecting portion.

また、第4の実施形態は、該分割鉄筋籠の主筋端部近傍を所定長さの接続部として設けると共に隣接するそれぞれの接続部を並設し、該並設する接続部をUボルトまたは結束線等で保持固定すると共に該接続する分割鉄筋篭の直近の補強枠同士を複数の連結部材で橋架するように固定手段で橋設保持固定した連結鉄筋篭体と、
また、第5の、連結部材の両端に掛止部を設けた所定長さの係止連結部材とした連結鉄筋篭体と、
また、第6の実施形態は、分割鉄筋篭の両端側近傍に設けられる補強枠間に延伸連結部材で橋架して設けると共に連結接続する次段の分割鉄筋篭の接続部直近の補強枠まで該延伸連結部材を延設させて設けた連結鉄筋篭体により、
連結鉄筋籠の全長を正確に設定すると共にその位置擦れ及び連結外れが生じないように、分割鉄筋籠の補強枠同士を該連結部材で連結保持させ、また係止連結部材で掛止すると共に連結保持させ、さらに分割鉄筋篭及び一体の連結鉄筋籠の全体が歪まないように、また連結部の長さを設定すると共にその位置擦れ及び連結外れが生じないように、補強枠同士を該延伸連結部材で連結保持させて、該一体の連結鉄筋籠体として形成することが実現できた。
Further, in the fourth embodiment, the vicinity of the main bar end portion of the split reinforcing bar rod is provided as a connection portion having a predetermined length, and adjacent connection portions are provided side by side, and the connection portions provided in parallel are provided with U bolts or bundling. A connecting reinforcing bar frame that is held and fixed by fixing means so as to bridge and fix the nearest reinforcing frames of the divided reinforcing bar rods to be connected by a plurality of connecting members while holding and fixing with a wire or the like;
In addition, a fifth connecting reinforcing bar frame as a locking connecting member having a predetermined length provided with a latching portion at both ends of the connecting member;
In the sixth embodiment, the reinforcement frame provided near the both ends of the divided reinforcing bar rod is provided with a stretched connecting member between the reinforcing frames and connected to the reinforcing frame immediately adjacent to the connecting portion of the divided reinforcing bar rod of the next stage. By the connecting rebar frame provided by extending the extended connecting member,
In order to accurately set the total length of the connecting reinforcing bar rods and prevent the position rubbing and disconnection from occurring, the reinforcing frames of the divided reinforcing bar rods are connected and held by the connecting members, and are latched by the locking connecting members and connected. Reinforced frames are stretched and connected so that the split rebar bar and the whole connecting bar bar are not distorted, and the length of the connecting part is set and the position is not rubbed or disconnected. It was possible to realize formation of the integrally connected reinforcing bar frame by connecting and holding the members.

本発明の実施例を図面に基づいて詳細に説明すると、図1において、1は分割鉄筋篭で、該分割鉄筋篭1を掘削した地盤の縦坑2の中に建込みする状態を示し、そこで先ず、一段目の分割鉄筋篭1を掘削した地盤の縦坑2の中に落とし込むと共に該縦坑2の落込み口3より分割鉄筋篭1の接続部4を突出させた状態で、該一段目の分割鉄筋篭1を鉄筋籠落込支持体5で仮支持させ、次に、クレーン6で二段目の分割鉄筋篭1を吊り移設して、該一段目の分割鉄筋篭1と連結接続して、後述する連結鉄筋籠体1aとして形成する。  An embodiment of the present invention will be described in detail with reference to the drawings. In FIG. 1, reference numeral 1 denotes a divided reinforcing bar rod, which shows a state in which the divided reinforcing rod rod 1 is installed in a vertical shaft 2 excavated. First, the first-stage split rebar rod 1 is dropped into the excavated vertical shaft 2 and the connection portion 4 of the divided rebar rod 1 is projected from the drop port 3 of the vertical shaft 2. Are temporarily supported by the reinforcing bar drop-in support 5, and then the second-stage divided reinforcing bar 1 is suspended and transferred by the crane 6 to be connected to the first-stage divided reinforcing bar 1 and connected. The connecting rebar frame 1a, which will be described later, is formed.

そこで、該分割鉄筋篭1は、両端部近傍と略中央寄りの各所定位置に、図2に示すように、主筋7と補強枠8を格子状にそれぞれ交差するように配置し、つまり環状の補強枠8の内側に主筋7を縦方向に所定本数格子状に配置すると共に取付金具9で該補強枠8を交差取付け保持固定し、その保持固定された該補強枠8,8間にフープ筋10を多数並列させて、上述同様の格子状に配置すると共に結束線11又は取付金具9aで取付け保持固定して所定形状の分割鉄筋篭1を形成する。
なお、取付金具9は、分割鉄筋篭1の外側から補強枠8と共に取付ける外締め用の取付金具9を示し、図中の取付金具9aは、分割鉄筋篭1の内側からフープ筋10と共に取付ける内締め用の取付金具9aを示す一実施例である。
Therefore, as shown in FIG. 2, the split reinforcing bar rods 1 are arranged so that the main bars 7 and the reinforcing frames 8 intersect each other in a lattice shape at predetermined positions near both ends and near the center. The main bars 7 are arranged in a grid pattern in the vertical direction inside the reinforcing frame 8 and the reinforcing frame 8 is cross-mounted and fixed by a mounting bracket 9, and a hoop bar between the holding and fixed reinforcing frames 8 and 8. A large number of 10 are arranged in parallel and arranged in the same lattice pattern as described above, and are attached and held and fixed by the binding wires 11 or the attachment fittings 9a to form the divided reinforcing bar rod 1 having a predetermined shape.
In addition, the attachment metal fitting 9 shows the attachment metal fitting 9 for external fastening attached with the reinforcement frame 8 from the outer side of the division | segmentation reinforcing bar rod 1, The attachment metal fitting 9a in a figure is the inside attached with the hoop reinforcement 10 from the division | segmentation reinforcing bar rod 1 inside. It is one Example which shows the attachment metal fitting 9a for fastening.

また、該取付金具9は、図3に示すように市販の略Uボルト形状を示す側面略コの字形状で、その両先端側のネジ部と、他端の基端側が補強枠8の幅に対応する該側面略コの字形状で、その両端部双方からそれぞれ起立状に屈曲させると共にその屈曲中央部近傍を主筋径に対応するように略U字形状に屈曲させて、両先部側のネジ部12,12と略U字形状の交差掛止部13,13がそれぞれ起立屈曲して形成され、またその基端側の側面略コの字形状は補強枠8を係止する取付掛止部14として形成し、そして該取付金具9の取付け固定に使用する取付座金15は板状で該ネジ部12,12に対応する挿通穴部16,16を開設している。  Further, as shown in FIG. 3, the mounting bracket 9 has a substantially U-shaped side surface showing a commercially available substantially U-bolt shape, and the screw portion on both ends and the base end on the other end are the width of the reinforcing frame 8. The side surface is substantially U-shaped and is bent upright from both ends thereof, and the vicinity of the bent central portion is bent into a substantially U shape so as to correspond to the main muscle diameter. Screw portions 12 and 12 and substantially U-shaped crossing latching portions 13 and 13 are formed by standing and bending, respectively, and a substantially U-shaped side surface on the base end side is an attachment hook for locking the reinforcing frame 8. A mounting washer 15 formed as a stop 14 and used for mounting and fixing the mounting bracket 9 is plate-shaped and has insertion holes 16 and 16 corresponding to the screw portions 12 and 12.

そして、主筋7と交差する補強枠8の交差部の取付状態は、図3に示すように、まず、主筋7を内側と補強枠8を外側の交差状態で、取付金具9の取付掛止部14を補強枠8の外側から係止し、次に交差する主筋7に交差掛止部13,13を内側から係止させると共に該補強枠8を挟むようにネジ部12,12の先端を該補強枠8から外側に突出させ、そして取付座金15の挿通穴部16,16に、その突出する該ネジ部12,12を挿通して補強枠8を押圧するように取付座金15を取付けて、図4で示す他の実施例と同様にナット17,17を螺着して、主筋7と補強枠8を交差状に保持させている。  Then, as shown in FIG. 3, the attachment state of the intersection of the reinforcing frame 8 intersecting with the main reinforcement 7 is as follows. First, the attachment latching portion of the attachment fitting 9 with the main reinforcement 7 crossing the inside and the reinforcement frame 8 outside. 14 is locked from the outside of the reinforcing frame 8, the cross-hatch portions 13, 13 are locked from the inner side to the intersecting main muscle 7, and the ends of the screw portions 12, 12 are sandwiched between the reinforcing frames 8. The mounting washer 15 is attached so as to protrude outward from the reinforcing frame 8 and to insert the protruding screw portions 12 and 12 into the insertion holes 16 and 16 of the mounting washer 15 and press the reinforcing frame 8. As in the other embodiments shown in FIG. 4, nuts 17 and 17 are screwed to hold the main reinforcement 7 and the reinforcing frame 8 in a cross shape.

また、主筋7と交差するフープ筋10の結束線11での取付けは、主筋7を内側と補強枠8を外側の交差状態で、結束線11を交差状に巻付けて取付け、また上述図2の取付金具9aでの取付けは、上述補強枠8の交差部の取付状態と略同様で、その相違において、図4に示すように、主筋7の径に対応した略U字形状の取付掛止部14aで、主筋7に係止すると共に交差掛止部13a,13aでフープ筋10を係止して、分割鉄筋篭1の内側から主筋7と交差するフープ筋10と共に該取付金具9aで取付けて図2に示すように、所定形状の分割鉄筋篭1を形成する。  In addition, the hoop muscle 10 that intersects the main bar 7 is attached to the binding line 11 by winding the main line 7 in the crossing state of the inner side and the reinforcing frame 8 and winding the binding line 11 in a crossing manner. The mounting bracket 9a is mounted in substantially the same manner as the mounting state of the intersecting portion of the reinforcing frame 8. In this difference, as shown in FIG. 4, a substantially U-shaped mounting latch corresponding to the diameter of the main bar 7 is provided. The hook 14 is locked to the main bar 7 by the portion 14a and the hoop bar 10 is locked to the cross hooking parts 13a and 13a. As shown in FIG. 2, the split reinforcing bar rod 1 having a predetermined shape is formed.

なお、主筋7と交差する補強枠8及びフープ筋10の取付位置で、各実施例は主筋7が内側とし、補強枠8及びフープ筋10が外側に配置されているが、適宜、逆に設けられても良く、また鉄筋籠の内側から取付け締め付けを行う、上記外締め用の取付金具9及び内締め用の取付金具9aも、それぞれ外側取付け、内側取付けとして適宜変更しても良いが図示は省略した。  In addition, in the attachment position of the reinforcement frame 8 and the hoop muscle 10 intersecting with the main reinforcement 7, in each embodiment, the main reinforcement 7 is on the inner side, and the reinforcement frame 8 and the hoop reinforcement 10 are arranged on the outer side. The mounting bracket 9 for external tightening and the mounting bracket 9a for internal tightening that are mounted and tightened from the inside of the reinforcing bar may be appropriately changed as outer mounting and inner mounting, respectively. Omitted.

しかして、上述したように組み立てられた分割鉄筋篭1を、図1に示す掘削した地盤の縦坑2の中に建込みするときの連結接続は、図5に示すように隣接する上下段の分割鉄筋篭1,1の各主筋7,7,…同士の各端部側を、図7及び図8に示すように並設させると共に該主筋7,7の接続部4,4をUボルト18,18(一般市販品)で仮止め螺着し、その状態で、図5及び図6に示すように補強枠8,8を平板(又はLアングル等も使用可能)の連結部材19,19で橋架するように橋設溶着し、該仮止め螺着を本締めして該分割鉄筋篭1,1を連結接続して連結鉄筋籠体1aとして建て込み形成する。  Thus, when the divided reinforcing bar 1 assembled as described above is installed in the vertical shaft 2 of the excavated ground shown in FIG. 1, the connecting connection is as shown in FIG. As shown in FIGS. 7 and 8, the end portions of the main reinforcing bars 7, 7,... Of the split reinforcing bar rods 1, 1 are arranged side by side and the connecting portions 4, 4 of the main reinforcing bars 7, 7 are connected to the U-bolt 18. , 18 (general commercial product), and in this state, the reinforcing frames 8 and 8 are connected by flat plate (or L angle or the like) connecting members 19 and 19 as shown in FIGS. The bridges are welded so as to be bridged, and the temporary fastening screws are tightened to connect the divided reinforcing bar rods 1 and 1 to form a connecting reinforcing bar frame 1a.

また、他の実施例として示す図9及び図10の連結接続は、平板又は棒状の両端に掛止部20,20を形成した係止連結部材21で連結接続し、その連結接続は、掛止部20,20を補強枠8,8の上下から掛止して、上述同様、図7及び図8に示すように、並設する主筋7,7同士の接続部4,4をUボルト18,18で螺着すると共に該補強枠8,8に係止連結部材21,21を溶着して該分割鉄筋篭1,1を連結接続して連結鉄筋籠体1aとして建て込み形成する。  9 and 10 shown as another embodiment is connected by a locking connecting member 21 having hooking portions 20 and 20 formed at both ends of a flat plate or a rod, and the connecting connection is the hooking. As shown in FIGS. 7 and 8, the connecting portions 4, 4 between the main bars 7, 7 arranged side by side are hooked on the U bolts 18, respectively. At the same time, the connecting members 21 and 21 are welded to the reinforcing frames 8 and 8 and the divided reinforcing bar rods 1 and 1 are connected and connected to form the connecting reinforcing bar frame 1a.

なお、その補強枠8,8に係止連結部材21,21を溶着することに換えて、補強枠8,8と係止連結部材21,21を貫通するボルト止めとして、溶着不可の場合に置き換え製作でき、また本実施例の隣接する上下段の分割鉄筋篭1,1の連結接続に、係止連結部材21の掛止部20,20を掛止させているので、連結する接続部4に直接重量が掛からないため、使用しているUボルト18,18に代えて、安価な結束線11の使用が可能となり、それによりコストダウンとなるが、その図示は省略した。  Instead of welding the locking connecting members 21 and 21 to the reinforcing frames 8 and 8, the bolts passing through the reinforcing frames 8 and 8 and the locking connecting members 21 and 21 are replaced when the welding is impossible. Since the latching portions 20 and 20 of the latching coupling member 21 are latched to the coupling connection of the adjacent upper and lower divided reinforcing bar rods 1 and 1 of this embodiment, the coupling portion 4 to be coupled is connected to the coupling portion 4 to be coupled. Since the weight is not directly applied, it is possible to use an inexpensive binding wire 11 in place of the U bolts 18 and 18 used, thereby reducing the cost, but the illustration thereof is omitted.

しかして、分割鉄筋篭1,1の他の実施例の延伸連結部材22を使用する連結接続は、図11に示すように、隣接する上下段の該分割鉄筋篭1の両端側近傍の補強枠8,8の間に延伸連結部材22で橋架して、交差する主筋7と共に上述したように外締め用の取付金具9で保持固定すると共に延伸連結部材22を、次段の分割鉄筋篭1の接続部4直近の補強枠8まで延設させて、同様に交差する主筋7と共に上述したように外締め用の取付金具9で保持固定した状態にする。  Thus, as shown in FIG. 11, the connecting connection using the extended connecting member 22 of another embodiment of the divided reinforcing bar rods 1, 1 is a reinforcing frame in the vicinity of both ends of the divided reinforcing bar rod 1 in the adjacent upper and lower stages. 8 and 8 is bridged by the extending connecting member 22 and is held and fixed by the mounting bracket 9 for outer fastening as described above together with the intersecting main reinforcing bars 7 and the extending connecting member 22 is connected to the divided reinforcing bar 1 of the next stage. It extends to the reinforcing frame 8 closest to the connecting portion 4 and is in a state of being held and fixed by the external fastening fitting 9 as described above together with the intersecting main reinforcing bars 7.

そして、二段目を上記一段目に連結接続するとき、連結する主筋7,7の接続部4,4同士を並設すると共に延設された該延伸連結部材22の先端を、該二段目の補強枠8に主筋7と共に上述したように外締め用の取付金具9で保持固定して、該分割鉄筋篭1,1を連結接続して連結鉄筋籠体1aとして建て込み形成する。  When the second stage is connected and connected to the first stage, the connecting portions 4 and 4 of the main bars 7 and 7 to be connected are juxtaposed and the tip of the extended connecting member 22 extended is connected to the second stage. As described above, the reinforcing frame 8 is held and fixed together with the main reinforcement 7 by the mounting bracket 9 for external fastening, and the divided reinforcing bar rods 1 and 1 are connected and connected to form a connecting reinforcing bar frame 1a.

なお、延伸連結部材22は、平板、棒状又はLアングル等で形成し、また分割鉄筋篭1の大きさに合わせて、該周面に略均等に数カ所配置すると共に各補強枠8,8のそれぞれに主筋7と共に上述したように外締め用の取付金具9で保持固定して分割鉄筋篭1が、捻れなど歪まないように保持させる。  In addition, the extending | stretching connection member 22 is formed in a flat plate, rod shape, L angle, etc., and according to the magnitude | size of the division | segmentation rebar bar | burr 1, arrange | positions several places on this peripheral surface substantially equally, and each of each reinforcement frame 8 and 8 is each. In addition, as described above, together with the main reinforcing bar 7, it is held and fixed by the mounting bracket 9 for external tightening, and the split reinforcing bar 1 is held so as not to be distorted such as torsion.

また、上述延伸連結部材22の実施例に合わせて、上記実施例の該接続部4を橋設する連結部材19又は係止連結部材21を、延伸連結部材22,22,…との間に設けて併用しても良いが、図示は省略した。  Further, a connecting member 19 or a locking connecting member 21 for bridging the connecting portion 4 of the above embodiment is provided between the extending connecting members 22, 22,. However, the illustration is omitted.

しかして、分割鉄筋篭1をクレーン6で縦坑2の落込み口3に落とし込んで建て込みをすることにおいて、先ず一段目の分割鉄筋篭1を建て込みするとき、上述したように予め補強枠8に連結部材19,19,…を保持固定した分割鉄筋篭1、
または予め延伸連結部材22,22,…を、補強枠8と交差する主筋7と共に外締め用の取付金具9で保持固定した該一段目の分割鉄筋篭1を、掘削した地盤の縦坑2に建込み挿入すると共に該分割鉄筋籠1の接続部4を地盤より所定量突出した状態で、該分割鉄筋籠1を鉄筋籠落込支持体5で仮支持させる。
Therefore, when the divided rebar bar 1 is dropped into the drop port 3 of the vertical shaft 2 by the crane 6 and built, when the first-stage divided bar bar 1 is first built, as described above, a reinforcing frame is previously provided. .. Reinforcing bar 1 having the connecting members 19, 19,.
Alternatively, the first-stage split rebar rod 1 in which the extension connecting members 22, 22,... Are held and fixed together with the main reinforcement 7 crossing the reinforcement frame 8 together with the external fastening fitting 9 is applied to the vertical shaft 2 of the excavated ground. The split reinforcing bar 1 is temporarily supported by the reinforcing bar drop support 5 in a state where the connecting part 4 of the split reinforcing bar 1 is projected by a predetermined amount from the ground.

そして次に、二段目の分割鉄筋籠1を、仮支持された一段目の分割鉄筋篭1の接続部4近傍まで該クレーン6で移送し、該一段目の突出した主筋7の接続部4を突き合わせ状に並設させると共に予め設けられた連結部材19,19,…、または延伸連結部材22,22,…の先端側を二段目の分割鉄筋籠1の補強枠8と位置あわせして、該補強枠8と連結部材19,19,…、または延伸連結部材22,22,…を保持固定すると共に該主筋7,7の接続部4,4をUボルト18,18で螺着して保持固定することで連結鉄筋籠体1aが形成される。  Then, the second-stage split rebar rod 1 is transported by the crane 6 to the vicinity of the connection portion 4 of the first-stage divided rebar rod 1 temporarily supported, and the first-stage protruding main reinforcement 7 connection portion 4 is transferred. Are arranged side by side in abutting fashion, and the tip ends of the connecting members 19, 19,... Or the extended connecting members 22, 22,. The reinforcing frame 8 and the connecting members 19, 19,... Or the extended connecting members 22, 22,... Are held and fixed, and the connecting portions 4, 4 of the main bars 7, 7 are screwed with U bolts 18, 18. The connecting reinforcing bar frame 1a is formed by holding and fixing.

なお、連結接続して形成される該連結鉄筋籠体1aの全長が、正確に設定できるように、予め連結部材19、または延伸連結部材22の長さを設定して、一段目の分割鉄筋篭1の補強枠8に保持固定すると共に該連結部材19、または延伸連結部材22の先端を、二段目の分割鉄筋籠1の補強枠8に保持固定することで該連結鉄筋籠体1aの全長が、正確に設定できる。  In addition, the length of the connecting member 19 or the extended connecting member 22 is set in advance so that the total length of the connecting reinforcing bar frame 1a formed by connecting and connecting can be accurately set, and the divided reinforcing bar rods at the first stage are set. The full length of the connecting reinforcing bar frame 1a is fixed to the reinforcing frame 8 by holding and fixing the tip of the connecting member 19 or the extended connecting member 22 to the reinforcing frame 8 of the split reinforcing bar 1 of the second stage. Can be set accurately.

そして、上述したように分割鉄筋篭1を、連結部材19、または延伸連結部材22で、それぞれ連結接続した後、二段目の分割鉄筋篭1を該クレーン6で若干吊り上げて該縦坑2の落込み口3で仮支持する該鉄筋籠落込支持体5を抜き取り、該一段目の分割鉄筋篭1の支持を解除し、次に吊り上げられた状態の二段目の分割鉄筋篭1を縦坑2の中に落とし込み、そして次に、該二段目の分割鉄筋篭1を、上述したように鉄筋籠落込支持体5で、該分割鉄筋籠1の接続部4を地盤より所定量突出した状態で再び仮支持し、次段以後、該分割鉄筋篭1を同様に繰り返して連結接続することで、場所打ち杭に用いられる連結鉄筋籠体1aとして建込みをする。  Then, as described above, the divided reinforcing bar rod 1 is connected and connected by the connecting member 19 or the extending connecting member 22, and then the second-stage divided reinforcing rod rod 1 is slightly lifted by the crane 6. The rebar drop support 5 that is temporarily supported by the drop opening 3 is extracted, the support of the first split rebar bar 1 is released, and then the second split rebar bar 1 in the lifted state is used as a vertical shaft. 2 and then, the second-stage split rebar rod 1 is protruded from the ground by a predetermined amount with the reinforcing bar drop-in support 5 as described above. Then, after the next stage, the divided reinforcing bar rods 1 are repeatedly connected and connected in the same manner, so that the connecting reinforcing bar frame 1a used for the cast-in-place pile is built.

また、係止連結部材21は、上述の連結部材19、延伸連結部材22と略同様に建て込み実施され、その相違において、二段目の分割鉄筋籠1を、該仮支持された一段目の分割鉄筋篭1の接続部4近傍まで移送すると共に該一段目の突出した主筋7の接続部4と移送された該接続部4を突き合わせ状に並設させ後に、一段目と二段目の補強枠8,8に該係止連結部材21の掛止部20,20を掛止させると共に該クレーン6で二段目の分割鉄筋籠1を若干吊り上げ若干の張力を掛けて所定長さに設定し、その状態で係止連結部材21の掛止部20,20と補強枠8,8を保持固定することとし、該連結鉄筋籠体1aとして建込みをする。  In addition, the locking connecting member 21 is built in substantially the same manner as the connecting member 19 and the extending connecting member 22 described above, and in the difference, the second-stage split rebar rod 1 is attached to the first-stage temporarily supported. After the transfer to the vicinity of the connection part 4 of the split reinforcing bar rod 1, the connection part 4 of the main bar 7 protruding from the first stage and the transferred connection part 4 are arranged side by side in abutment, and then the first and second stage reinforcement The hooks 20, 20 of the locking connection member 21 are hooked on the frames 8, 8, and the second-stage split rebar bar 1 is slightly lifted by the crane 6 and set to a predetermined length by applying a slight tension. In this state, the latching portions 20 and 20 of the locking connecting member 21 and the reinforcing frames 8 and 8 are held and fixed, and the connecting reinforcing bar frame 1a is built.

なお、該係止連結部材21の掛止部20,20を補強枠8,8に掛止させて若干の張力を掛けて保持固定することで、連結接続して形成される該連結鉄筋籠体1aの全長が正確に設定できるように、予め係止連結部材21の長さ及びその掛止部20,20の位置を設定する。  It should be noted that the connecting rebar frame formed by connecting and connecting the engaging portions 20 and 20 of the engaging connecting member 21 by engaging with the reinforcing frames 8 and 8 and holding and fixing them with some tension. The length of the locking connecting member 21 and the positions of the latching portions 20 and 20 are set in advance so that the total length of 1a can be set accurately.

また、補強枠8と、それぞれ連結部材19、係止連結部材21又は延伸連結部材22との保持固定手段に、取付金具9,9aまたは結束線11を用いるとしているが、補強枠8と、連結部材19、係止連結部材21又は延伸連結部材22のそれぞれに穴を開設すると共に該穴を介してボルト止めとしても良く、また上述したように溶着としても良いが、図は省略した。  In addition, the mounting brackets 9 and 9a or the binding wires 11 are used as the holding and fixing means for the reinforcing frame 8 and the connecting member 19, the locking connecting member 21 or the extended connecting member 22, respectively. A hole is formed in each of the member 19, the locking connecting member 21, or the extended connecting member 22 and may be bolted through the hole, or may be welded as described above, but the illustration is omitted.

本発明の鉄筋篭の連結建込み方法及びその連結鉄筋篭体は、場所打ち抗に用いられる分割鉄筋篭を連結して建込みする連結鉄筋籠体に使用できる。  The method for connecting and building the reinforcing bar rods according to the present invention and the connecting reinforcing bar frame can be used for the connecting reinforcing bar rods that are constructed by connecting the divided reinforcing bar rods that are used for place fighting.

1 分割鉄筋篭
1a 連結鉄筋籠体
2 縦坑
4 接続部
5 鉄筋籠落込支持体
7 主筋
8 補強枠
9,9a 取付金具
10 フープ筋
11 結束線
18 Uボルト
19 連結部材
20 掛止部
21 係止連結部材
22 延伸連結部材。
DESCRIPTION OF SYMBOLS 1 Reinforcement rod 1a Connection reinforcement rod body 2 Vertical shaft 4 Connection part 5 Reinforcement rod fall support body 7 Main reinforcement 8 Reinforcement frame 9, 9a Mounting bracket 10 Hoop reinforcement 11 Binding wire 18 U bolt 19 Connection member 20 Latching part 21 Locking Connecting member 22 Stretched connecting member.

Claims (6)

縦方向の主筋に対し環状のフープ筋及び補強枠の内側または外側に所定本数それぞれ格子状に配置すると共に取付金具又は結束線などの固定手段で交差保持固定して所定形状の鉄筋籠を形成し、該分割鉄筋籠に連結接続する所定長さの接続部を該主筋端部に設け、該接続部で各段の該分割鉄筋篭同士を複数段連結接続しながら掘削した地盤の縦坑に場所打ち杭として落とし込む一体の連結鉄筋篭体として建込みする鉄筋篭の連結建込み方法において、
掘削した地盤の縦坑に前記分割鉄筋籠の一段目を建込み挿入すると共に該分割鉄筋籠の接続部を地盤より所定量突出した状態で支持し、次に建込み挿入する二段目の分割鉄筋籠の接続部と、前記一段目の突出した主筋の接続部を突き合わせ状に並設させると共に該並設する双方の接続部同士をUボルト金具または結束線等の固定手段で保持固定し、次に、上記保持固定された該一段目と二段目の接続部直近の補強枠同士に、所定長さの連結部材を複数箇所、該接続部を跨いで橋架するように設けると共に取付金具または結束線等の固定手段で橋設保持固定して、該分割鉄筋籠を連結接続し、以後、各段の分割鉄筋籠を同様に連結接続しながら一体の連結鉄筋籠体として建込みすることを特徴とした連結鉄筋篭の連結建込み方法。
Predetermined numbers of bars are arranged inside or outside of the hoop bars and reinforcement frames in the form of a lattice with respect to the main bars in the vertical direction, and fixed and held by fixing means such as mounting brackets or binding wires to form reinforcing bar rods of a predetermined shape. A connecting portion having a predetermined length to be connected to the divided reinforcing bar rod is provided at the end of the main reinforcing bar, and is located in the vertical shaft of the ground excavated while connecting the divided reinforcing rod rods of each stage in a plurality of stages at the connecting portion. In the method of connecting and building reinforcing bars to be built as an integrated connecting reinforcing bar to be dropped as a pile,
The first stage of the divided reinforcing bar is inserted and inserted into the vertical shaft of the excavated ground, and the connecting part of the divided reinforcing bar is supported in a state protruding by a predetermined amount from the ground, and then inserted into the second stage. The connecting portion of the reinforcing bar rod and the connecting portion of the protruding main reinforcing bar in the first stage are arranged side by side in abutting manner, and the two connecting portions arranged side by side are held and fixed by fixing means such as a U-bolt fitting or a binding wire, Next, a plurality of connecting members of a predetermined length are provided between the reinforcing frames adjacent to the first-stage and second-stage connecting parts held and fixed so as to bridge across the connecting parts and mounting brackets or Fixing and fixing the bridge with a fixing means such as a tie wire, and connecting and connecting the divided reinforcing bar rods, and then building the integrated reinforcing bar frame as a single unit while connecting and connecting the divided reinforcing bar rods of each stage in the same manner. A method for erection of the connected reinforcing bar rod.
上記連結部材が、該連結部材の両端に掛止部を形成した係止連結部材とし、上記並設連結された接続部直近の補強枠同士を橋架すると共に該補強枠に掛止する請求項1記載の連結鉄筋篭の連結建込み方法。  The connecting member is a locking connecting member in which a latching portion is formed at both ends of the coupling member, and bridges the reinforcing frames in the vicinity of the juxtaposed and connected connecting portions and latches on the reinforcing frame. The method of linking and building up the connecting reinforcing bar rod as described. 上記連結部材が、分割鉄筋篭の両端近傍の補強枠間を橋架すると共に上記並設連結する接続部を超えて次段の分割鉄筋篭の補強枠まで延設して橋架する延伸連結部材とし、該延伸連結部材を、該各補強枠に橋設保持固定すると共に次段の分割鉄筋篭の上記接続部直近の該補強枠に取付金具などの固定手段で保持固定する請求項1記載の連結鉄筋篭の連結建込み方法。  The connecting member bridges between the reinforcing frames in the vicinity of both ends of the divided reinforcing bar rods and extends to the reinforcing frame of the divided reinforcing bar rod of the next stage beyond the connecting portion to be connected side by side as an extended connecting member to bridge. 2. The connecting reinforcing bar according to claim 1, wherein the extending connecting member is bridged and fixed to each reinforcing frame, and is held and fixed to the reinforcing frame in the immediate vicinity of the connecting portion of the divided reinforcing bar by a fixing means such as a mounting bracket. Consolidation method for firewood. 縦方向の主筋に対し環状のフープ筋及び補強枠の内側または外側に所定本数それぞれ格子状に配置すると共に取付金具又は結束線などの固定手段で交差保持固定して所定形状の鉄筋籠を形成し、該鉄筋籠を掘削した地盤の縦坑に複数段連結接続しながら落とし込む場所打ち杭に用いる円筒状の分割鉄筋籠であって、該分割鉄筋籠同士を連結接続して連結鉄筋篭体を形成する該連結接続する接続部において、
該分割鉄筋篭を複数連結接続して一体の連結鉄筋篭体が形成できるように、該分割鉄筋籠の主筋端部近傍を所定長さの接続部として設け、連結接続する該双方の接続部同士を突き合わせ状に並設すると共に該並設する双方の接続部同士をUボルト金具または結束線等の固定手段で保持固定すると共にさらに所定の長さの連結部材で、該並設連結された接続部直近の上記補強枠同士を複数箇所橋架すると共に取付金具または結束線等の固定手段で橋設保持固定して連結形成したことを特徴とする連結鉄筋篭体。
Predetermined numbers of bars are arranged inside or outside of the hoop bars and reinforcement frames in the form of a lattice with respect to the main bars in the vertical direction, and fixed and held by fixing means such as mounting brackets or binding wires to form reinforcing bar rods of a predetermined shape. , A cylindrical divided rebar rod used for cast-in-place piles that are dropped while connecting and connecting to the vertical shaft of the ground where the rebar rod is excavated, and connecting the divided rebar rods together to form a connected rebar frame In the connecting part for connecting and connecting,
In order to form an integrally connected reinforcing bar frame by connecting and connecting a plurality of the divided reinforcing bar rods, the vicinity of the main reinforcing bar ends of the divided reinforcing bar rods are provided as connecting portions of a predetermined length, and the two connecting portions to be connected to each other Are connected in parallel with each other, and the connecting portions of the two side-by-side connections are held and fixed by fixing means such as a U-bolt fitting or a binding wire, and the connection members connected in parallel are connected by a connecting member having a predetermined length. A connecting rebar frame characterized in that the reinforcing frames immediately adjacent to each other are bridged at a plurality of locations and are formed by holding and fixing with a fixing means such as a mounting bracket or a binding wire.
上記連結部材が、上記並設連結された接続部直近の補強枠同士を橋架すると共に該補強枠に掛止できるように、該連結部材の両端に掛止部を形成した係止連結部材とする請求項4記載の連結鉄筋篭体。  The connecting member is a locking connecting member in which hooking portions are formed at both ends of the connecting member so that the reinforcing frames in the vicinity of the connecting portions connected in parallel can be bridged and hooked to the reinforcing frame. The connection reinforcing bar frame according to claim 4. 上記連結部材が、分割鉄筋篭の両端近傍の補強枠間を橋架すると共に上記並設連結する接続部を超えて次段の分割鉄筋篭の補強枠まで延設して橋架する延伸連結部材とした請求項4記載の連結鉄筋篭体。  The connecting member bridges between the reinforcing frames in the vicinity of both ends of the divided reinforcing bar rods, and extends to the reinforcing frame of the divided reinforcing bar rod of the next stage beyond the connecting portion to be connected in parallel. The connection reinforcing bar frame according to claim 4.
JP2013070250A 2013-03-11 2013-03-11 A method for linking and installing a reinforced steel bar and a reinforced steel frame for the same. Expired - Fee Related JP5382394B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013070250A JP5382394B1 (en) 2013-03-11 2013-03-11 A method for linking and installing a reinforced steel bar and a reinforced steel frame for the same.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013070250A JP5382394B1 (en) 2013-03-11 2013-03-11 A method for linking and installing a reinforced steel bar and a reinforced steel frame for the same.

Publications (2)

Publication Number Publication Date
JP5382394B1 true JP5382394B1 (en) 2014-01-08
JP2014173418A JP2014173418A (en) 2014-09-22

Family

ID=50036555

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013070250A Expired - Fee Related JP5382394B1 (en) 2013-03-11 2013-03-11 A method for linking and installing a reinforced steel bar and a reinforced steel frame for the same.

Country Status (1)

Country Link
JP (1) JP5382394B1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107964944A (en) * 2017-12-29 2018-04-27 上海三凯建设管理咨询有限公司 A kind of filling pile cage of reinforcement component and its construction method
CN110029663A (en) * 2019-03-20 2019-07-19 中铁四局集团有限公司 A kind of ultra-deep Mud Ground rotary jet strengthening method
CN110562838A (en) * 2019-08-28 2019-12-13 武汉市汉阳市政建设集团有限公司 Connection method of reinforcement cage
CN112520577A (en) * 2020-11-30 2021-03-19 成都悦鉴科技有限公司 Hoisting device for prefabricated reinforcement cage
CN112681309A (en) * 2020-12-26 2021-04-20 天津武清建总建设工程集团有限公司 Cast-in-place pile reinforcement cage hoisting and fixing device and construction method thereof
CN113266008A (en) * 2021-06-24 2021-08-17 朱小齐 High-rise building pile foundation construction method
CN113502807A (en) * 2021-06-15 2021-10-15 浙江省建筑设计研究院 Slow-setting prestressed filling pile reinforcement cage structure and sectional construction method thereof
CN114941321A (en) * 2022-06-22 2022-08-26 中煤长江基础建设有限公司 Cast-in-place pile reinforcement cage construction device and construction method
CN115419053A (en) * 2022-09-14 2022-12-02 中铁隧道局集团路桥工程有限公司 Occlusive pile structure of complex stratum below river channel and construction method of occlusive pile structure

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6434349B2 (en) * 2015-03-25 2018-12-05 東京鐵鋼株式会社 Pile reinforcement bar and its holding member
US10041252B1 (en) * 2016-07-28 2018-08-07 Steven James Bongiorno Bar sleeve
CN109914393B (en) * 2019-02-28 2021-01-05 温州国宁建设有限公司 Cast-in-place pile convenient to transport and construction process thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001055733A (en) * 1999-08-19 2001-02-27 Ohbayashi Corp Construction method for underground wall and underground wall structure thereof
JP2008214990A (en) * 2007-03-06 2008-09-18 Kajima Corp Basket body and manufacturing method for basket body

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001055733A (en) * 1999-08-19 2001-02-27 Ohbayashi Corp Construction method for underground wall and underground wall structure thereof
JP2008214990A (en) * 2007-03-06 2008-09-18 Kajima Corp Basket body and manufacturing method for basket body

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107964944A (en) * 2017-12-29 2018-04-27 上海三凯建设管理咨询有限公司 A kind of filling pile cage of reinforcement component and its construction method
CN107964944B (en) * 2017-12-29 2023-06-02 上海三凯工程咨询有限公司 Bored concrete pile reinforcement cage assembly and construction method thereof
CN110029663A (en) * 2019-03-20 2019-07-19 中铁四局集团有限公司 A kind of ultra-deep Mud Ground rotary jet strengthening method
CN110562838A (en) * 2019-08-28 2019-12-13 武汉市汉阳市政建设集团有限公司 Connection method of reinforcement cage
CN110562838B (en) * 2019-08-28 2024-03-15 武汉市汉阳市政建设集团有限公司 Connecting method of reinforcement cage
CN112520577A (en) * 2020-11-30 2021-03-19 成都悦鉴科技有限公司 Hoisting device for prefabricated reinforcement cage
CN112520577B (en) * 2020-11-30 2022-10-21 湖北才汇投资咨询有限公司 Hoisting device for prefabricated reinforcement cage
CN112681309A (en) * 2020-12-26 2021-04-20 天津武清建总建设工程集团有限公司 Cast-in-place pile reinforcement cage hoisting and fixing device and construction method thereof
CN113502807A (en) * 2021-06-15 2021-10-15 浙江省建筑设计研究院 Slow-setting prestressed filling pile reinforcement cage structure and sectional construction method thereof
CN113266008A (en) * 2021-06-24 2021-08-17 朱小齐 High-rise building pile foundation construction method
CN114941321A (en) * 2022-06-22 2022-08-26 中煤长江基础建设有限公司 Cast-in-place pile reinforcement cage construction device and construction method
CN115419053A (en) * 2022-09-14 2022-12-02 中铁隧道局集团路桥工程有限公司 Occlusive pile structure of complex stratum below river channel and construction method of occlusive pile structure

Also Published As

Publication number Publication date
JP2014173418A (en) 2014-09-22

Similar Documents

Publication Publication Date Title
JP5382394B1 (en) A method for linking and installing a reinforced steel bar and a reinforced steel frame for the same.
KR100909839B1 (en) Curve type preflexion steel beam frame using preflexion for installing reinforcing material at curved steel material of a curved steel frame and method for manufacturing the same
WO2017013694A1 (en) Framework structure and construction method for same
KR100662811B1 (en) Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof
WO2009011516A2 (en) Form with reinforcing bars, non-support form system and non-support construction method using the same
KR101440434B1 (en) Construction Method for Composite Type Rahmen Bridge
KR102075165B1 (en) Concrete filled tubular column and connecting structure of the same and construction method thereof
KR100783256B1 (en) Composite girder having connection structure of inclined members in composite girder with steel truss web using embedded t-type perfobond and such connection structure
CN103072906B (en) Connecting device of inner climbing type tower crane and building structure and construction method utilizing same
KR20150144398A (en) Reinforced Concrete Walls by Triangular Reinforcing Bar Details and Construction Method Thereof
KR101211691B1 (en) Hybrd-structure beam using gusset connection plate
JP4888915B2 (en) Building structure using composite structural beams with beam ends made of PC
KR200397213Y1 (en) Mounting structure of Steel Cross-beam in Multi-girder concrete bridge and its construction method
WO2008100026A1 (en) Composite girder with steel truss web having hinge connecting, and connection structure thereof
KR20070001410A (en) Mounting structure of steel cross-beam in multi-girder concrete bridge and its construction method
KR100840190B1 (en) I-beam segment connection method equipped with prestress steel synthetic concrete upper flange for continuous bridge
KR20100000385A (en) Pipe rack as constructed using precast concrete members
KR200417902Y1 (en) Anchor frame assembly of tower crane
KR101126131B1 (en) Structure for reinforcing head of a steel pipe pile for a construction
KR20120036614A (en) Method of longitudinal connection for double steel box girder using tendon and connection plate and method steel box girder bridge using the same
KR101257752B1 (en) Non-welding type seismic reinforcing structure and method for column using cft
KR102465099B1 (en) construction method and structure for TG beam form
JP2015045202A (en) Arch culvert and manufacturing method thereof
JP6349732B2 (en) Method and structure for joining reinforced concrete beam to steel column or column with steel frame
CN108756012B (en) Tensioning rope connection assembly for connecting concrete wall panels and method of use thereof

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130917

R150 Certificate of patent or registration of utility model

Ref document number: 5382394

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees