KR100840190B1 - I-beam segment connection method equipped with prestress steel synthetic concrete upper flange for continuous bridge - Google Patents

I-beam segment connection method equipped with prestress steel synthetic concrete upper flange for continuous bridge Download PDF

Info

Publication number
KR100840190B1
KR100840190B1 KR1020070127394A KR20070127394A KR100840190B1 KR 100840190 B1 KR100840190 B1 KR 100840190B1 KR 1020070127394 A KR1020070127394 A KR 1020070127394A KR 20070127394 A KR20070127394 A KR 20070127394A KR 100840190 B1 KR100840190 B1 KR 100840190B1
Authority
KR
South Korea
Prior art keywords
beam segment
upper flange
steel
parent
concrete
Prior art date
Application number
KR1020070127394A
Other languages
Korean (ko)
Inventor
노윤근
노옥근
노실근
Original Assignee
노윤근
노옥근
노실근
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 노윤근, 노옥근, 노실근 filed Critical 노윤근
Priority to KR1020070127394A priority Critical patent/KR100840190B1/en
Application granted granted Critical
Publication of KR100840190B1 publication Critical patent/KR100840190B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Abstract

A connection method for an I-beam segment equipped with prestressed steel-combined concrete upper flange for a continuous bridge is provided to increase rigidity reinforcement and sectional rigidity by interconnecting the I-beam segment divided into main and sub moment units. A connection method for an I-beam segment equipped with prestressed steel-combined concrete upper flange for a continuous bridge includes the steps of: processing the I-beam segment to manufacture a main moment unit I-beam segment(10a) with prestressed steel-combined concrete upper flange; processing the I-beam segment to manufacture a sub moment unit I-beam segment(10b) with prestressed steel-combined concrete upper flange; and connecting the main moment unit I-beam segment with the sub moment unit I-beam segment.

Description

연속교용 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 아이빔 세그멘트 연결방법{I-beam segment connection method equipped with prestress steel synthetic concrete upper flange for continuous bridge }I-beam segment connection method equipped with prestress steel synthetic concrete upper flange for continuous bridge}

본 발명은 연속교용 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 세그멘트 연결방법에 관한 것이다.The present invention relates to a method for connecting an I beam segment having a prestressed steel composite concrete flange for continuous bridges.

종래에는 압연강재 I형 강재빔을 이용하여 교량을 설치할 때 강성증대를 위하여 강재 하부에 강선을 설치하고, 상기 강선에 인장력을 도입하여 상기 I형 강재빔에 프리스트레스를 도입하여 작용하는 하중에 저항하도록 한 교량을 시공하여 왔다.Conventionally, when installing a bridge using a rolled steel I-type steel beam, a steel wire is installed in the lower part of the steel for increasing rigidity, and a tensile force is introduced to the steel wire to introduce a prestress into the I-type steel beam to resist a load acting. A bridge has been constructed.

그러나 상기의 강선의 부식 및 풀리는 것을 막기 위한 유지관리의 필요성과 주기적으로 상기 강선에 인장력을 도입하여 상기 I빔에 일정한 프리스트레스력이 계속 유지되도록 하는 유지보수관리를 하여야 하는 문제점과 압연 강재 I형 강재빔을 그대로 사용하는 경우는 강성저하로 이를 극복하기 위하여 압연 강재 빔의 사용량이 많아져 경제성이 불리하고, 장경간의 교량건설이 불가한 측면이 있으며, 전 구간을 압연 강재 I형 강재빔의 상부 또는 하부플랜지나 상, 하부플랜지의 고강도 강판을 부착하여 프리스트레스를 가하여 사용하는 경우는 경제적이기는 하나, 기존 압연 강재 I형 강재빔의 형고 제약으로 장경간의 교량 건설이 불가한 면이 있었다. However, there is a need for maintenance to prevent corrosion and unwinding of the steel wire and a problem of maintaining maintenance to maintain a constant prestress force on the I beam by periodically introducing a tensile force to the steel wire and a rolled steel I type steel. If the beam is used as it is, the rigidity is reduced, so that the use of the rolled steel beam is increased to overcome this, which is disadvantageous in economic efficiency, and there is a side that is impossible to construct a bridge between long spans. Although it is economical to apply prestress by attaching high strength steel plate of lower flange or upper and lower flange, it is impossible to construct bridge between long diameter due to the limitation of shape of existing rolled steel I-type steel beam.

이에, 본 발명은 상기한 바와 같은 제문제점을 해결하기 위해 안출된 것으로서, 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 세그멘트를 정모멘트부와 부모멘트부로 각각 분리 제작한 후, 정, 부모멘트부 I빔 세그멘트를 연결하여, 프리스트레스 강합성 콘크리트 상부플랜지가 없는 기존의 정, 부모멘트부 I빔 세그멘트 보다 저형고, 장지간이 가능하고, 경제적이면서도 강성보강과 단면 강성을 증대시킨 연속교용 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 세그멘트 연결방법을 제공하는데 그 목적이 있다.Thus, the present invention was devised to solve the problems described above, after separately manufacturing the I-beam segment having a pre-stressed rigid composite concrete upper flange into the constant moment portion and the parent portion portion, the positive, parent portion portion I By connecting the beam segment, the upper part of the prestressed composite concrete for the continuous bridge that is lower than the conventional static and parental section I beam segment without the prestressed rigid concrete upper flange, and can be longer and more economically, but also increases the rigidity reinforcement and the stiffness of the cross section. It is an object of the present invention to provide a method for connecting an I beam segment having a flange.

상기한 목적을 달성하기 위한 본 발명에 따른 연속교용 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 세그멘트 연결방법은 I빔 세그멘트를 가공하여 프리스트레스가 도입된 강합성 콘크리트 상부플랜지를 가지는 정모멘트부 I빔 세그멘트를 제작하고, I빔 세그멘트를 가공하여 프리스트레스가 도입된 강합성 콘크리트 상부플랜지를 가지는 부모멘트부 I빔 세그멘트를 제작하는 한편, 상기 제작된 정, 부모멘트부 I빔 세그멘트를 상호 연결함을 특징으로 한다.In order to achieve the above object, a method for connecting an I beam segment having a prestressed rigid composite concrete upper flange for continuous bridges according to the present invention is a positive moment portion having a rigid composite concrete upper flange in which a prestress is introduced by processing an I beam segment. To fabricate the I beam segment, and to fabricate the parent cement portion I beam segment having the pre-stressed reinforced concrete upper flange, while interconnecting the fabricated positive and parent cement segments I beam segments. do.

이상에서 설명한 바와 같이, 본 발명에 따른 연속교용 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 세그멘트 연결방법은 저형고 및 장경간의 교량 건설을 가능하게 함과 동시에 경제적이면서도 강성보강과 단면 강성이 증대되는 장점이 있다. As described above, the I-beam segment connecting method having the prestressed steel composite concrete flange for continuous bridges according to the present invention enables the construction of bridges between low heights and long diameters, and at the same time, economical rigidity and cross-sectional rigidity are increased. There is this.

이하, 본 발명을 첨부한 예시도면을 참조하여 상세히 설명한다.Hereinafter, with reference to the accompanying drawings, the present invention will be described in detail.

도 1은 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량을 도시한 측면도이며, 도 2는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 정모멘트부 I빔을 도시한 측면도이며, 도 3은 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 정모멘트부 I빔을 도시한 단면도이며, 도 4는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 부모멘트부 I빔을 도시한 측면도이며, 도 5는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 부모멘트부 I빔을 도시한 단면도이다.1 is a side view showing an I-beam bridge having a pre-stressed composite concrete upper flange according to the present invention, Figure 2 is a moment of the I beam bridge having a pre-stressed composite concrete upper flange according to the present invention I beam One side view, Figure 3 is a cross-sectional view showing a constant moment I beam of the I-beam bridge having a pre-stressed composite concrete upper flange according to the present invention, Figure 4 is a pre-stressed composite concrete upper flange according to the present invention I Fig. 5 is a sectional view showing the parent portion portion I beam of the beam bridge, and Fig. 5 is a sectional view showing the parent portion portion I beam of the I beam bridge having the prestressed composite concrete upper flange according to the present invention.

이들 도면에 도시된 바와 같이, 본 발명에 따른 연속교용 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 세그멘트 연결방법은 I빔 세그멘트(10)를 가공하여 프리스트레스가 도입된 강합성 콘크리트 상부플랜지를 가지는 정모멘트부 I빔 세그멘트(10a)를 제작하고, I빔 세그멘트(10)를 가공하여 프리스트레스가 도입된 강합성 콘크리트 상부플랜지를 가지는 부모멘트부 I빔 세그멘트(10b)를 제작하는 한편, 상기 제작된 정, 부모멘트부 I빔 세그멘트(10a, 10b)를 상호 연결한다.As shown in these drawings, the I-beam segment connecting method having a continuous bridge prestressed rigid concrete upper flange according to the present invention is a static moment having a rigid composite concrete upper flange in which prestress is introduced by processing the I-beam segment 10 The secondary I beam segment 10a is fabricated, and the I beam segment 10 is fabricated to produce the parent cement portion I beam segment 10b having a rigid synthetic upper flange into which prestress is introduced. The parent cement portion I beam segments 10a and 10b are interconnected.

여기서, 상기 정모멘트부 I빔 세그멘트(10a)는 도 6a 내지 6d에 도시된 바와 같이, I빔 세그멘트(10)를 사용하중과 반대되는 방향으로 솟음 가공하여 I빔 세그멘트(10)의 하부플랜지(12)에는 고강도 강판(14)을 덧대고, 상부플랜지(16)에는 철근(18)을 배근하고, L형 거푸집(20)을 설치한 후, 수직 상향으로 프리플랙션 하중을 재하한 후, 하부플랜지(12)에는 고강도 강판(14)을 용접으로 접합하고, 상부플랜지(16)에는 고강도 콘크리트(22)를 타설하여 양생한 후 프리플랙션 하중을 제거하여 프리스트레스가 도입된 강합성 콘크리트 상부플랜지를 가지는 정모멘트부 I빔 세그멘트(10a)를 제작한다.6A through 6D, the bottom flange of the I beam segment 10 may be formed by raising the I beam segment 10 in a direction opposite to the load. 12) a high-strength steel plate 14 is padded, the upper flange 16 is reinforced with a reinforcing bar 18, the L-shaped formwork 20 is installed, and after loading the pre-fraction load vertically upwards, The high strength steel plate 14 is welded to the flange 12, and the high flange 16 is poured into the high flange 22, and the high strength concrete 22 is cast and cured, and then the pre-stress is removed. The branches have a constant moment portion I beam segment 10a.

또한, 상기 부모멘트부 I빔 세그멘트(10b)는 도 7a 내지 7e에 도시된 바와 같이, I빔 세그멘트(10)를 사용하중과 반대되는 방향으로 솟음 가공하여 I빔 세그멘트(10)의 상, 하부플랜지(16, 12)에 고강도 강판(14)을 덧대고, 수직 하향으로 프리플랙션 하중을 재하한 후, I빔 세그멘트(10)의 상, 하부플랜지(16, 12)에 고강도 강판(14)을 용접으로 접합한 후, 프리플랙션 하중을 제거하고, 상부플랜지(16) 양단부에 PS강재(24)를 정착 긴장할 강재정착구(26a, 26b)를 설치하고, 쉬스(28) 및 철근(18)을 설치한 후, L형 거푸집(20)을 조립하여 고강도 콘크리트(22)를 타설 및 양생한 후 상기 강재정착구(26a, 26b)에 PS강재(24)를 삽입 설치하고 긴장하여 프리스트레스가 도입된 강합성 콘크리트 상부플랜지를 가지는 부모멘트부 I빔 세그멘트(10b)를 제작한다.Also, as shown in FIGS. 7A to 7E, the parent cement portion I beam segment 10b is formed by raising the I beam segment 10 in a direction opposite to the load, and thus, the upper and lower portions of the I beam segment 10. The high strength steel sheet 14 is attached to the flanges 16 and 12, and the pre-fraction load is loaded vertically downward, and then the high strength steel sheet 14 is applied to the upper and lower flanges 16 and 12 of the I beam segment 10. After welding, the pre-fraction load is removed, and steel fixing holes 26a and 26b for fixing and fixing the PS steel 24 at both ends of the upper flange 16 are installed, and the sheath 28 and the reinforcing bar 18 are provided. After the installation, the L-form formwork 20 to pour and cure the high-strength concrete (22), and then install the PS steel material 24 into the steel fixing holes (26a, 26b) and the tension is introduced into the steel A parent cement portion I beam segment 10b having a synthetic concrete upper flange is fabricated.

그리고 상기 정, 부모멘트부 I빔 세그멘트(10a, 10b)의 연결은 정, 부모멘트부 I빔 세그멘트(10a, 10b)의 거치 후 처짐 방지를 위해 연결부 상단 유간부(33) 양단에 ㄱ형 강재브라켓(34)을 설치하고, 유압잭(36)으로 수평하중을 가한 후, 무수축 콘크리트(38)를 타설하여 연결한다.And the connection between the positive and the parent portion I beam segment (10a, 10b) is a-shaped steel brackets at both ends of the connecting portion upper clearance 33 to prevent sagging after mounting of the positive, parent portion I beam segment (10a, 10b) (34) is installed, horizontal load is applied by the hydraulic jack (36), and the non-contraction concrete 38 is poured and connected.

여기서, 상기 부모멘트부 I빔 세그멘트(10b)의 상부플랜지(16) 양단부에 부착되는 PS강재(24)를 정착 긴장하는 강재정착구(26a, 26b)를 설치하되, 상기 강재정착구((26a, 26b)는 평판형 정착판(28)에 삼각형 버팀판(30)이 중앙부에 부착된 형태로 상부플랜지(16)에만 프리스트레스를 도입하는 단순 강재정착구(26a)와, 상부플랜지(16)와 바닥판 슬래브(32)에 프리스트레스를 도입하는 복합 강재정착구(26b)로 구성된다.Here, the steel fixtures (26a, 26b) for fixing the PS steel material 24 attached to both ends of the upper flange (16) of the parent cement portion I beam segment (10b) is provided, the steel fixtures (26a, 26b In the form of a triangular bracing plate 30 attached to the center of the plate-shaped fixing plate 28, the simple steel fixing hole 26a for introducing prestress only to the upper flange 16, and the upper flange 16 and the bottom plate slab. It consists of a composite steel anchoring hole 26b which introduces prestress into 32.

이하, 상기한 바와 같은 구성으로 이루어진 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 세그멘트 연결 시공에 대해 설명한다.Hereinafter, an I beam segment connection construction having a prestressed rigid concrete upper flange according to the present invention having the above configuration will be described.

도 15는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 I빔 연결부를 도시한 측면도이며, 도 16은 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 I빔 연결부를 도시한 평면도이다.15 is a side view illustrating an I beam bridge of an I beam bridge having a prestressed composite concrete upper flange according to the present invention, and FIG. 16 is an I beam bridge of an I beam bridge having a prestressed composite concrete upper flange according to the present invention. It is a top view showing the.

이들 도면에 도시된 바와 같이, 본 발명에 따른 연속교용 프리스트레스 강합 성 콘크리트 상부플랜지를 가지는 I빔 세그멘트 연결방법은 정모멘트부 I빔 세그멘트(10a)를 제작하되, 사용하중과 반대되는 방향으로 솟음을 도입한 I빔 세그멘트(10)를 제작하여 I빔 세그멘트(10)의 하부플랜지(12)에 고강도 강판(14)을 덧대고, 유압잭(36)으로 상향력을 도입한 후, 하부플랜지(12)에 고강도 강판(14)을 용접 부착하고, 상부플랜지(16)에는 고강도 콘크리트(22)를 타설 및 양생한 다음, 유압잭(36)의 상향력을 해제하여 강재 I빔 세그멘트(10)에 프리스트레스를 도입하여 정모멘트부 I빔 세그멘트(10a)를 제작한 후, As shown in these drawings, the I-beam segment connecting method having a continuous bridge pre-stressed composite concrete upper flange according to the present invention while producing a constant moment portion I beam segment (10a), but rises in the direction opposite to the working load After manufacturing the introduced I-beam segment 10, the high-strength steel plate 14 is applied to the lower flange 12 of the I-beam segment 10, and after introducing an upward force into the hydraulic jack 36, the lower flange 12 The high strength steel sheet 14 is welded to the upper flange 16, the high strength concrete 22 is poured and cured on the upper flange 16, and the prestress is introduced into the steel I beam segment 10 by releasing the upward force of the hydraulic jack 36. After manufacturing the constant moment portion I beam segment (10a),

이어서, 부모멘트부 I빔 세그멘트(10b)를 제작하되, 사용하중과 반대되는 방향으로 솟음을 도입한 I빔 세그멘트(10)를 제작하여 I빔 세그멘트(10)의 상, 하부플랜지(16, 12)에 고강도 강판(14)을 덧대어 유압잭(36)으로 하향력을 도입하여 상, 하부플랜지(16, 12)에 고강도 강판(14)을 용접 부착한 후, I빔 세그멘트(10)의 상부플랜지(16)에 프리스트레스 도입을 위한 강재정착구(26a, 26b)를 설치한 다음, 고강도 콘크리트(22)를 타설 및 양생한 후, PS강재(24)로 긴장하여 강재 I빔 세그멘트(10)에 프리스트레스를 도입하여 부모멘트부 I빔 세그멘트(10b)를 제작한 후, Subsequently, the parent beam portion I beam segment 10b is fabricated, but the I beam segment 10 is introduced into the direction opposite to the working load so as to produce upper and lower flanges 16 and 12 of the I beam segment 10. A high strength steel sheet 14 is applied to the upper and lower flanges 16 and 12 to weld the high strength steel sheet 14 to the upper and lower flanges 16 and 12. Steel fittings 26a and 26b for introducing prestress are installed at 16, and after the high-strength concrete 22 is poured and cured, it is tensioned with PS steel 24 to prestress the steel I beam segment 10. After introduction to produce the parent portion I beam segment 10b,

상기 정, 부모멘트부 I빔 세그멘트(10a, 10b)를 연결강판에 의해 연결 조립하되, 제작된 프리스트레스 강합성 콘크리트 상부플랜지(16)를 가지는 정, 부모멘트 I빔 세그멘트(10a, 10b)를 현장에서 연결 조립함에 있어서, 상기 정, 부모멘트 I빔 세그멘트(10a, 10b)의 상부플랜지(16)의 콘크리트 미타설부의 유간으로 인한 처짐 발생을 방지하기 위해 유간부(33)에 ㄱ형 강재브라켓(34)을 한 쌍으로 설치하고, 그 위에 유압잭(36)을 설치하여 수평하중을 가한 상태에서 유간부(33)에 무수 축콘크리트(38)를 타설 양생하여 연결 조립을 완료한 후, 크레인으로 연결조립된 정, 부모멘트부 I빔 세그멘트(10a, 10b)를 교각(40), 교대(42)에 거치한 후, 바닥판 슬래브 철근(18)을 배근하고, 콘크리트(22)를 타설 및 양생한다.The positive and parent portion I beam segment (10a, 10b) is connected and assembled by a connecting steel plate, but the positive and parent cement I beam segment (10a, 10b) having a pre-stressed rigid composite concrete upper flange (16) on-site In assembling in the connection, the a-shaped steel bracket (34) to the stem portion 33 to prevent the sagging caused by the clearance between the concrete ridge portion of the upper flange 16 of the positive, parent cement I beam segment (10a, 10b) ) And a hydraulic jack 36 is installed on it, and the axial concrete (38) is poured into the spacing part 33 in the state where the horizontal load is applied. After mounting the fixed and parent cement portion I beam segments 10a and 10b to the pier 40 and the alternating 42, the bottom slab slab 18 is placed and the concrete 22 is poured and cured.

여기서, 선택적으로 부모멘트부 I빔 세그멘트(10b)의 바닥판 슬래브(32)에 프리스트레스를 도입할 경우에는 바닥판 슬래브(32) 타설시 복합 강재정착구(26b)에 쉬스(19)를 배치하고, 콘크리트 양생 후 상기 쉬스(19)에 PS강재(24)를 삽입하여 프리스트레스를 도입한 후, 교량 상부구조물의 시공을 완료한다.Here, when the prestress is selectively introduced into the bottom plate slab 32 of the parent portion I beam segment 10b, the sheath 19 is disposed at the composite steel anchoring hole 26b when the bottom plate slab 32 is placed. After curing the concrete, the PS steel 24 is inserted into the sheath 19 to introduce the prestress, and then complete the construction of the bridge upper structure.

또한, 상기 L형 거푸집(20)의 내측에 탄성고무(46)를 고장력볼트(44)로 고정 설치하여, 콘크리트 타설시 콘크리트가 흘러내리지 않도록 하면서 시공한다.In addition, by installing the elastic rubber 46 fixed to the inner side of the L-shaped formwork 20 with a high-tensile bolt 44, it is installed while preventing the concrete from flowing down during concrete pouring.

도 1은 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량을 도시한 측면도,1 is a side view showing an I-beam bridge having a prestressed rigid concrete upper flange according to the present invention,

도 2는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 정모멘트부 I빔을 도시한 측면도,Figure 2 is a side view showing a constant moment portion I beam of the I-beam bridge having a prestressed steel composite concrete upper flange according to the present invention,

도 3은 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 정모멘트부 I빔을 도시한 단면도,3 is a cross-sectional view showing a constant moment portion I beam of the I-beam bridge having a prestressed steel composite concrete upper flange according to the present invention,

도 4는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 부모멘트부 I빔을 도시한 측면도,Figure 4 is a side view showing the parent portion portion I beam of the I-beam bridge having a prestressed steel composite concrete upper flange according to the present invention,

도 5는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 부모멘트부 I빔을 도시한 단면도,5 is a cross-sectional view showing the parent beam portion I beam of the I-beam bridge having a prestressed steel composite concrete upper flange according to the present invention,

도 6a 내지 6d는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 정모멘트부 I빔 제작과정을 도시한 공정도,6a to 6d is a process diagram showing a process for producing a constant moment portion I beam of the I-beam bridge having a pre-stressed composite concrete upper flange according to the present invention,

도 7a 내지 7e는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 부모멘트부 I빔 제작과정을 도시한 공정도,7a to 7e is a process chart showing the process of manufacturing the I-beam of the parent portion of the I-beam bridge having a pre-stressed composite concrete upper flange according to the present invention,

도 8은 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 L형 거푸집을 도시한 단면 상세도,8 is a cross-sectional detail view showing an L-shaped formwork of an I-beam bridge having a prestressed rigid concrete upper flange according to the present invention;

도 9는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 단순 강재정착구를 도시한 사시도,9 is a perspective view showing a simple steel fixture of the I-beam bridge having a pre-stressed steel composite concrete upper flange according to the present invention,

도 10은 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 단순 강재정착구를 도시한 정면도,10 is a front view showing a simple steel anchoring hole of an I-beam bridge having a prestressed steel composite concrete upper flange according to the present invention,

도 11은 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 단순 강재정착구를 도시한 평면도,11 is a plan view showing a simple steel anchoring hole of an I-beam bridge having a prestressed steel composite concrete upper flange according to the present invention,

도 12는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 복합 강재정착구를 도시한 사시도,12 is a perspective view showing a composite steel anchorage of the I-beam bridge having a prestressed steel composite concrete upper flange according to the present invention,

도 13은 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 복합 강재정착구를 도시한 정면도,13 is a front view showing a composite steel anchorage of the I-beam bridge having a pre-stressed steel composite concrete upper flange according to the present invention,

도 14는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 복합 강재정착구를 도시한 평면도,14 is a plan view showing a composite steel anchorage of the I-beam bridge having a prestressed steel composite concrete upper flange according to the present invention,

도 15는 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 I빔 연결부를 도시한 측면도,15 is a side view showing an I beam connecting portion of an I beam bridge having a prestressed rigid concrete upper flange according to the present invention;

도 16은 본 발명에 따른 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 교량의 I빔 연결부를 도시한 평면도.16 is a plan view showing an I beam connecting portion of an I beam bridge having a prestressed rigid concrete upper flange according to the present invention;

-도면의 주요부분에 대한 부호의 설명-Explanation of symbols on the main parts of the drawing

10: I빔 세그멘트 10: I beam segment

10a: 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 정모멘트부 I빔 세그멘트10a: constant moment portion I beam segment with prestressed rigid concrete upper flange

10b: 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 부모멘트부 I빔 세그멘트 10b: parent portion I beam segment with prestressed rigid concrete upper flange

12: 하부플랜지 14: 고강도 강판12: lower flange 14: high strength steel sheet

16: 상부플랜지 18: 철근16: upper flange 18: rebar

19: 쉬스 20: L형 거푸집19: sheath 20: L formwork

22: 고강도 콘크리트, 콘크리트 24: PS강재22: high strength concrete, concrete 24: PS steel

26a: 단순 강재정착구 26b: 복합 강재정착구26a: Simple Steel Fittings 26b: Composite Steel Fittings

28: 정착판 30: 버팀판28: fixing plate 30: brace plate

32: 바닥판 슬래브 33: 유간부32: bottom plate slab 33: clearance part

34: ㄱ형 강재브라켓 36: 유압잭34: A type steel bracket 36: Hydraulic jack

38: 무수축 콘크리트 40: 교각38: non-contraction concrete 40: pier

42: 교대 44: 고장력볼트42: Shift 44: High tension bolt

46: 탄성고무 B: I빔 교량46: elastic rubber B: I-beam bridge

Claims (6)

I빔 세그멘트(10)를 가공하여 프리스트레스가 도입된 강합성 콘크리트 상부플랜지를 가지는 정모멘트부 I빔 세그멘트(10a)를 제작하고, I beam segment 10 is fabricated to produce a constant moment portion I beam segment 10a having a steel composite upper flange with prestress introduced thereto, I빔 세그멘트(10)를 가공하여 프리스트레스가 도입된 강합성 콘크리트 상부플랜지를 가지는 부모멘트부 I빔 세그멘트(10b)를 제작하는 한편, While processing the I beam segment 10 to produce a parent cement portion I beam segment (10b) having a steel composite upper flange of the pre-stress introduced, 상기 제작된 정, 부모멘트부 I빔 세그멘트(10a, 10b)를 상호 연결함을 특징으로 하는 연속교용 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 세그멘트 연결방법.I-beam segment connection method having a pre-strength rigid composite concrete upper flange for continuous bridges, characterized in that for interconnecting the produced positive, parent portion I beam segment (10a, 10b). 제 1항에 있어서,The method of claim 1, 상기 정모멘트부 I빔 세그멘트(10a)은 I빔 세그멘트(10)를 사용하중과 반대되는 방향으로 솟음 가공하여 I빔 세그멘트(10)의 하부플랜지(12)에는 고강도 강판(14)을 덧대고, 상부플랜지(16)에는 철근(18)을 배근하고, L형 거푸집(20)을 설치한 후, 수직 상향으로 프리플랙션 하중을 재하한 후, 하부플랜지(12)에는 고강도 강판(14)을 용접으로 접합하고, 상부플랜지(16)에는 고강도 콘크리트(22)를 타설하여 양생한 후 프리플랙션 하중을 제거하여 프리스트레스가 도입된 강합성 콘크리트 상부플랜지를 가지는 정모멘트부 I빔 세그멘트(10a)를 제작함을 특징으로 하는 연속교용 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 세그멘트 연결방법.The constant moment I beam segment 10a is formed by rising the I beam segment 10 in a direction opposite to the load, and attaching a high strength steel plate 14 to the lower flange 12 of the I beam segment 10. After reinforcing bars 18 are installed in the upper flange 16, the L-shaped formwork 20 is installed, and the pre-fraction load is loaded vertically upward, the high strength steel plate 14 is welded to the lower flange 12. To the upper flange 16, the high-strength concrete 22 is poured and cured, and then the pre-fraction load is removed to produce the positive moment part I beam segment 10a having the rigid composite upper flange with prestress. I-beam segment connection method having a pre-stressed rigid composite concrete upper flange for continuous bridges. 제 1항에 있어서,The method of claim 1, 상기 부모멘트부 I빔 세그멘트(10b)는 I빔 세그멘트(10)를 사용하중과 반대되는 방향으로 솟음 가공하여 I빔 세그멘트(10)의 상, 하부플랜지(16, 12)에 고강도 강판(14)을 덧대고, 수직 하향으로 프리플랙션 하중을 재하한 후, I빔 세그멘트(10)의 상, 하부플랜지(16, 12)에 고강도 강판(14)을 용접으로 접합한 후, 프리플랙션 하중을 제거하고, 상부플랜지(16) 양단부에 PS강재(24)를 정착 긴장할 강재정착구(26a, 26b)를 설치하고, 쉬스(28) 및 철근(18)을 설치한 후, L형 거푸집(20)을 조립하여 고강도 콘크리트(22)를 타설 및 양생한 후 상기 강재정착구(26a, 26b)에 PS강재(24)를 삽입 설치하고 긴장하여 프리스트레스가 도입된 강합성 콘크리트 상부플랜지를 가지는 부모멘트부 I빔 세그멘트(10b)를 제작함을 특징으로 하는 연속교용 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 세그멘트 연결방법.The parent portion I beam segment 10b is formed by high-strength steel sheet 14 on the upper and lower flanges 16 and 12 of the I beam segment 10 by raising the I beam segment 10 in a direction opposite to the load. And load the high strength steel plate 14 to the upper and lower flanges 16 and 12 of the I-beam segment 10 by welding after preloading the load vertically downward. After removing the steel fittings 26a and 26b to fix the PS steel 24 at both ends of the upper flange 16, and installing the sheath 28 and the reinforcing bars 18, the L-shaped formwork 20 is removed. After mounting and curing high-strength concrete 22, inserting and reinforcing the PS steel 24 into the steel fitting holes 26a and 26b and tensioning the parent cement portion I beam segment having a steel composite concrete upper flange in which prestress is introduced. Prestressed steel composite flange for continuous bridges characterized in that the manufacturing 10b I-beam segment connections that. 제 1항에 있어서,The method of claim 1, 상기 정, 부모멘트부 I빔 세그멘트(10a, 10b)의 연결은 정, 부모멘트부 I빔 세그멘트(10a, 10b)의 거치 후 처짐방지를 위해 연결부 상단 유간부(33) 양단에 ㄱ형 강재브라켓(34)을 설치하고, 유압잭(36)으로 수평하중을 가한 후, 무수축 콘크리트(38)를 타설함을 특징으로 하는 연속교용 프리스트레스 강합성 콘크리트 상부플랜지를 가지는 I빔 세그멘트 연결방법.The connection between the positive and the parent part I beam segments 10a and 10b is a-shaped steel bracket at both ends of the upper part of the connecting part 33 to prevent sagging after the mounting of the positive and parent part I beam segments 10a and 10b. 34), I-beam segment connection method having a pre-stressed rigid composite concrete upper flange for continuous bridges, characterized in that after placing a horizontal load with a hydraulic jack (36), pour non-contraction concrete (38). 삭제delete 삭제delete
KR1020070127394A 2007-12-10 2007-12-10 I-beam segment connection method equipped with prestress steel synthetic concrete upper flange for continuous bridge KR100840190B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020070127394A KR100840190B1 (en) 2007-12-10 2007-12-10 I-beam segment connection method equipped with prestress steel synthetic concrete upper flange for continuous bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020070127394A KR100840190B1 (en) 2007-12-10 2007-12-10 I-beam segment connection method equipped with prestress steel synthetic concrete upper flange for continuous bridge

Publications (1)

Publication Number Publication Date
KR100840190B1 true KR100840190B1 (en) 2008-06-23

Family

ID=39772057

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070127394A KR100840190B1 (en) 2007-12-10 2007-12-10 I-beam segment connection method equipped with prestress steel synthetic concrete upper flange for continuous bridge

Country Status (1)

Country Link
KR (1) KR100840190B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839510A (en) * 2016-05-23 2016-08-10 西安公路研究院 Steel-ultra-high-performance concrete combined continuous beam bridge structure and construction method thereof
CN109024271A (en) * 2018-06-20 2018-12-18 广西交通科学研究院有限公司 Limit the construction method of the built-in concrete beam bridge steel reinforced concrete anchoring piece of Local Cracking
CN110258340A (en) * 2019-06-11 2019-09-20 中铁一局集团有限公司 A kind of segmented efficient construction method of groove profile continuous beam
CN113308995A (en) * 2021-04-23 2021-08-27 浙江交工集团股份有限公司 Prefabricated bent cap subsection wet joint method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS584006A (en) 1981-06-26 1983-01-11 川田工業株式会社 Continuous type bridge using prestressed steel beam
KR20060046873A (en) * 2004-11-12 2006-05-18 천진욱 Preflex comopsite bridges and method for constructing thereof
KR20070082435A (en) * 2006-02-16 2007-08-21 김선기 Temporary bridge consruction method using composite slab girder
KR100773385B1 (en) 2007-07-31 2007-11-05 우경건설 주식회사 Precise prestress introduction method which high-strength steel against i beam again and used the bolt hole perforation part for connection assembly at the time of prestress introduction

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS584006A (en) 1981-06-26 1983-01-11 川田工業株式会社 Continuous type bridge using prestressed steel beam
KR20060046873A (en) * 2004-11-12 2006-05-18 천진욱 Preflex comopsite bridges and method for constructing thereof
KR20070082435A (en) * 2006-02-16 2007-08-21 김선기 Temporary bridge consruction method using composite slab girder
KR100773385B1 (en) 2007-07-31 2007-11-05 우경건설 주식회사 Precise prestress introduction method which high-strength steel against i beam again and used the bolt hole perforation part for connection assembly at the time of prestress introduction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839510A (en) * 2016-05-23 2016-08-10 西安公路研究院 Steel-ultra-high-performance concrete combined continuous beam bridge structure and construction method thereof
CN109024271A (en) * 2018-06-20 2018-12-18 广西交通科学研究院有限公司 Limit the construction method of the built-in concrete beam bridge steel reinforced concrete anchoring piece of Local Cracking
CN110258340A (en) * 2019-06-11 2019-09-20 中铁一局集团有限公司 A kind of segmented efficient construction method of groove profile continuous beam
CN113308995A (en) * 2021-04-23 2021-08-27 浙江交工集团股份有限公司 Prefabricated bent cap subsection wet joint method

Similar Documents

Publication Publication Date Title
KR100837608B1 (en) J.K Bracket Method
KR101170922B1 (en) The rahmen bridge construction technique for which tendon and the connection support stand was used
KR101242395B1 (en) Construction method for rhamen bridge
KR100840190B1 (en) I-beam segment connection method equipped with prestress steel synthetic concrete upper flange for continuous bridge
KR20100025161A (en) Girder bridge connected to abutment and the construction method thereof
KR101264577B1 (en) Steel frame concrete beam and manufacturing method of the same
KR101658390B1 (en) Reinforcement method of culvert
KR200397213Y1 (en) Mounting structure of Steel Cross-beam in Multi-girder concrete bridge and its construction method
KR100720067B1 (en) Construction method of composition beam for using arched plate
KR100522298B1 (en) Improved prestressed steel reinforced concrete beam and bridge construction method using the same beam
KR100860796B1 (en) Continuationization method by which psc which used upper and lower symmetry or asymmetric fixed bracket
KR100592196B1 (en) large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket and its installation method
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
KR20130005928A (en) A composite steel box girder using prestressed concrete for a positive moment area of a bridge
KR20070001410A (en) Mounting structure of steel cross-beam in multi-girder concrete bridge and its construction method
KR101157607B1 (en) Prestressed steel composite girder with prestressed non-introducing portions provided at both ends of lower flange casing concrete, manufacturing method thereof, and Rahmen structure and construction method thereof
KR20080111973A (en) Prestressed steel composite beam and a manufacturing method thereof
KR102066355B1 (en) The method of composite girder to minimize side buckling
KR20040091350A (en) Prestressed steel girder
KR100989153B1 (en) Psc girder connection structure with strength connector detail for substitution of rebar placement in deck and bridge construction method using the same
KR100696646B1 (en) External prestressing method of ps concrete composite girder bridge by tendon anchored/supported to prefabricated cross beam
KR20040102391A (en) Composite Beam Stiffened with In-Situ Concrete Panel Having Embedded Lower Flange and Constructing Method thereof
KR200291793Y1 (en) Pssc complex girder
KR100926137B1 (en) Composite girder form-system with cross support beam and composite girder construction method using the same
KR20210077874A (en) method of uniting the longitudinal steel on the lower flange of steel box girder bridge with tension introduced

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee