JP5062418B2 - Plane frame structure with precast concrete girder - Google Patents
Plane frame structure with precast concrete girder Download PDFInfo
- Publication number
- JP5062418B2 JP5062418B2 JP2007339808A JP2007339808A JP5062418B2 JP 5062418 B2 JP5062418 B2 JP 5062418B2 JP 2007339808 A JP2007339808 A JP 2007339808A JP 2007339808 A JP2007339808 A JP 2007339808A JP 5062418 B2 JP5062418 B2 JP 5062418B2
- Authority
- JP
- Japan
- Prior art keywords
- precast concrete
- socket
- pile
- girders
- precast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
- Bridges Or Land Bridges (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Lining And Supports For Tunnels (AREA)
Description
本発明は、主として道路や鉄道のため地盤内を横切る道路や河川等の通路を構築するためのアンダーパスや橋梁床版その他の平版状物を、アンダーパスの土留側壁、橋梁の橋脚・橋台、或いは家屋における等の支持構造物間に複数のプレキャストコンクリート桁を掛け渡して構成させたプレキャストコンクリート桁による平版状物架構構造に関する。 The present invention mainly uses underpass, bridge floor slabs and other lithographic materials for constructing passages such as roads and rivers crossing the ground for roads and railways, underpass retaining walls, bridge piers / abutments, Alternatively, the present invention relates to a lithographic frame structure made of precast concrete girders constructed by spanning a plurality of precast concrete girders between support structures such as houses.
従来、橋梁の床版等のような平版状物を架設する方法として、プレキャストコンクリート桁を幅方向に並べて各両端を橋脚や橋台上に架設し、各プレキャストコンクリート桁間に目地コンクリートを打設するとともに、幅方向に跨らせて挿通した鋼棒等の連結材にて各桁間を幅方向に一体化させることにより平版状の床版を架設する方法が知られている(例えば特許文献1)。 Conventionally, as a method of laying flat plates such as bridge slabs, precast concrete girders are arranged in the width direction, each end is erected on a pier or abutment, and joint concrete is placed between each precast concrete girder. In addition, a method of constructing a slab-like floor slab is known by integrating each girder in the width direction with a connecting material such as a steel rod inserted across the width direction (for example, Patent Document 1). ).
また、主として道路や鉄道のため地盤内を横切る道路や河川等の通路を構築するためのアンダーパスとしては、所謂ボックスカルバートがある。これには工場生産による角筒型をした一体型コンクリートブロック又はこれを複数分割した形状の分割型コンクリートブロックを現場に搬入し、地盤を横切る配置に埋設するものもあるが、ブロックによる構築にはその大きさに限界があり、頂版幅が一定以上となる場合には、場所打ちコンクリートによって土留め壁、頂版、底版を形成せざるを得ないものであり、その本体工の構築に先立って、ボックスカルバートの躯体より大きい作業空間を形成するために仮設土留めを行う必要があり、工期が長くなるという問題がある。 In addition, as an underpass for constructing a road such as a road or a river crossing the ground mainly for a road or a railway, there is a so-called box culvert. In this, there are some concrete concrete blocks in the form of square tubes produced by factory production or divided concrete blocks that are divided into multiple pieces, and are embedded in an arrangement across the ground. If there is a limit on the size and the top plate width exceeds a certain level, cast-in-place concrete, top plate, and bottom plate must be formed, and prior to the construction of the main body In order to form a working space larger than the box culvert housing, it is necessary to perform temporary earth retaining, which causes a problem that the construction period becomes long.
この問題を解決するものとして、一対の側壁を構築し、その側壁の上端に頂版を掛け渡した構造のものが知られている。上記側壁は、場所打ちコンクリートによって構築する方法の他、コンクリート杭を多数並べて立設することによって構築する方法がある。また頂版は、場所打ちコンクリートによって構築するものの他、多数のプレキャストコンクリート桁を並べて架設し、その桁間の隙間に間詰めコンクリートを打設すると桁幅方向に貫通させたPC緊張材の緊張によってプレキャストコンクリート桁間を一体化する方法がある。 In order to solve this problem, a structure in which a pair of side walls is constructed and a top plate is stretched over the upper ends of the side walls is known. In addition to a method of constructing the side wall by cast-in-place concrete, there is a method of constructing a side wall by standing a large number of concrete piles. The top plate is constructed with cast-in-place concrete, and a number of precast concrete girders are laid side by side, and when concrete is placed in the gap between the girders, the tension of the PC tension material penetrated in the width direction of the girders There is a method to integrate the precast concrete girders.
この種の従来のアンダーパスの頂版等の平版状物の架設は、図12に示すように、上述した各種方法によって構築された側壁などの支持構造物1,1の上端に、段状に頂版支承部2,2を形成し、その支承部2,2上に頂版3の両端を載せ、その頂版3の両端部と支承部2,2とをボルト等の締結具によって一体化させている(例えば特許文献2)。
As shown in FIG. 12, this type of conventional underpass top plate such as a top plate is constructed in a stepped manner on the upper ends of
また、
上述した従来の平版状物架構構造は、土留側壁等の支持構造物の上端に、現場にて頂版支持部を段状配置に形成し、その頂版支持部に支持させて場所打ちコンクリートにより頂版を形成しているため、工期が長くなり、また現場によるコンクリート成型によるものであるため、活荷重が絶えず作用している頂版コンクリートを高強度・高品質のものとすることが困難であるという問題がある。また、アンダーパスの場合には、工期が長くなると交通規制の期間も長くなるという問題がある。 The conventional planographic frame structure described above has a top plate support part formed in a step-like arrangement at the upper end of a support structure such as a retaining wall side wall, and is supported by the top plate support part by cast-in-place concrete. Because the top plate is formed, the construction period is long, and because it is due to concrete molding at the site, it is difficult to make the top plate concrete where the live load constantly acts high strength and high quality. There is a problem that there is. Further, in the case of underpass, there is a problem that the traffic regulation period becomes longer as the construction period becomes longer.
また、このような問題を解決する方法として、前記特許文献1にあるようなプレキャストコンクリート桁を工場にて製造し、現場に搬入して架設する方法が考えられ、支持部間のスパンが大きい場合にはプレストレストコンクリート(以下PCと記す)桁の使用が考えられるが、プレキャストコンクリート桁を使用する場合においても、支持部のメンテナンスを軽減し、背面土の地下水を遮断できる剛構造とするために、鉄筋継手、PC鋼材の緊張定着・グラウト作業、モルタルの充填、コンクリート打設等多くの現場作業が必要となるという問題があった。
Moreover, as a method of solving such a problem, a method of manufacturing a precast concrete girder as in
本発明は、このような従来の問題に鑑み、アンダーパスの頂版、橋梁や建築物の床版等の平版状物として、工場にて高品質に製造できるプレキャストコンクリート製品を使用し、しかも現場における支持構造物との連結固定作業が少ない工数で短時間に行われ、且つ支持構造物と平版状物との連結部が、現場作業の優劣に左右されることなく所要強度の剛結合構造とすることができるプレキャストコンクリート桁による平版状物架構構造の提供を目的としてなされたものである。 In view of such a conventional problem, the present invention uses a precast concrete product that can be manufactured at a factory with high quality as a flat plate such as an underpass top plate, a bridge or a floor slab of a building, The connecting and fixing work with the supporting structure in the work is performed in a short time with a small number of man-hours, and the connecting portion between the supporting structure and the lithographic material has a rigid joint structure with the required strength without being affected by the superiority or inferiority of the field work. It was made for the purpose of providing a planographic structure with precast concrete girders that can be used.
上述の如き従来の問題を解決し、所期の目的を達成するための請求項1に記載する発明の特徴は、互いに間隔を隔てて立設した支持構造物間に、複数のプレキャストコンクリート桁を平行配置に掛け渡して支持させ、該プレキャストコンクリート桁間を一体化させて平版状物とするプレキャストコンクリート桁による平版状物架構構造において、前記支持構造物の上端に、上向きに開口した多数のソケットを、該支持構造物の水平長さ方向に並べて一体に備えるとともに、前記各プレキャストコンクリート桁の両端下面に前記ソケット内にその内面との間に間隙を設けて挿入可能な下向きのソケット挿入用凸部を一体に備え、該ソケット挿入用凸部を前記支持構造物部上の各ソケットに挿入し、該ソケットとソケット挿入用凸部間の間隙に充填材を充填して互いに一体化させたことにある。
In order to solve the above-mentioned conventional problems and achieve the intended object, the feature of the invention described in
請求項2に記載する発明の特徴は、前記請求項1の構成に加え、前記平版状物が、アンダーパスを構成する頂版であり、前記支持構造物が、該アンダーパスを構成する土留側壁であることにある。 According to a second aspect of the present invention, in addition to the structure of the first aspect, the lithographic material is a top plate constituting an underpass, and the support structure is a retaining wall constituting the underpass. It is to be.
請求項3に記載する発明の特徴は、前記請求項1の構成に加え、前記平版状物が、橋梁の床版であり、前記支持構造物が、前記床版を支持する橋脚又は橋台であることにある。 According to a third aspect of the present invention, in addition to the configuration of the first aspect, the lithographic material is a bridge floor slab, and the support structure is a pier or abutment that supports the floor slab. There is.
請求項4に記載する発明の特徴は、前記請求項1〜3のいずれかに請求項の構成に加え、前記支持構造物は、地中に多数並べて打設したプレキャストコンクリート杭であり、各杭の上端にそれぞれ前記ソケットを一体に備えていることにある。 According to a fourth aspect of the present invention, in addition to the structure of any one of the first to third aspects, the support structure is a precast concrete pile that is placed side by side in the ground. The sockets are integrally provided at the upper ends of the two.
請求項5に記載する発明の特徴は請求項4の構成に加え、前記ソケットは、前記プレキャストコンクリート杭の上端に設置した鋼製の筒状部材であることにある。
The feature of the invention described in
請求項6に記載する発明の特徴は、請求項4又は3のいずれか1の請求項の構成に加え、前記プレキャストコンクリート杭は、断面がH型のプレキャストコンクリート杭であることにある。
The feature of the invention described in
請求項7に記載する発明の特徴は、請求項6の請求項の構成に加え、断面H型のプレキャストコンクリート杭の上端部のウエブ部分を前記ソケットの深さ分だけ除去し、該ウエブ部除去部分の前後のフランジ部縁部間に鋼製の側面板を固定することによって、前記前後のフランジ部と両側面板に囲まれたソケットを杭上端に一体に備えたことにある。 According to a seventh aspect of the present invention, in addition to the configuration of the sixth aspect, the web portion at the upper end of the H-shaped precast concrete pile is removed by the depth of the socket, and the web portion is removed. By fixing a steel side plate between the front and rear flange edges of the portion, a socket surrounded by the front and rear flange portions and both side plates is integrally provided at the upper end of the pile.
請求項8に記載する発明の特徴は、請求項6の請求項の構成に加え、断面H型のプレキャストコンクリート杭の上端部のウエブ部分と、一方のフランジ部とを前記ソケットの深さ分だけ除去し、他方のフランジ部の両縁部に断面がコ字状の鋼製金具の両縁を一体化させ、前記ウエブ部及び一方のフランジ部除去部分に他方のフランジ部と前記コ字状の鋼製金具に囲まれたソケットを杭上端に一体に備えたことにある。 According to an eighth aspect of the present invention, in addition to the configuration of the sixth aspect of the invention, the web portion at the upper end portion of the precast concrete pile having an H-shaped section and one flange portion are provided by the depth of the socket. The two flanges of the other flange portion are integrated with both edges of the steel bracket having a U-shaped cross section, and the other flange portion and the U-shaped flange are integrated into the web portion and one flange portion removal portion. A socket surrounded by steel fittings is integrated with the top of the pile.
請求項9に記載する発明の特徴は、請求項6の請求項の構成に加え、断面がH型のプレキャストコンクリート杭の上端部の両フランジ部外面に鋼製のソケット前面側板及びソケット背面側板を設置し、互いに隣り合う前記プレキャストコンクリート杭の前記ソケット前面板間及びソケット背面板間を一体に連結させるとともに、該前面板と背面板との間を、仕切り用連結材にて連結することにより複数のソケットを形成したことにある。
The feature of the invention described in claim 9 is that, in addition to the configuration of
請求項10に記載する発明の特徴は、請求項1〜9のいずれか1の請求項の構成に加え、前記プレキャストコンクリート桁間を一体化させる締結具として、該各プレキャストコンクリート桁に跨らせて幅方向に挿通したPC緊張材を使用し、前記平版状物全体に幅方向のプレストレスを導入していることにある。
A feature of the invention described in
上述の如き構成の本発明は、以下の如き効果がある。 The present invention configured as described above has the following effects.
平版状部を、多数のプレキャストコンクリート桁を平行に並べ、各桁間の隙間に目地材を充填した状態でその各桁間を幅方向の締結具により平版状に一体化させて構成していることにより、各プレキャストコンクリート桁は、工場にて一定品質に製造することができることとなり、活荷重の影響の大きい頂版を高強度・高品質なものとすることが容易となる。 The lithographic part is composed of a large number of precast concrete girdles arranged in parallel, and the gaps between the girders are filled with joint material, and the gaps between the girders are integrated into a lithographic shape with a fastener in the width direction. Thus, each precast concrete girder can be manufactured with a constant quality at the factory, and it becomes easy to make the top plate having a large influence of the live load with high strength and high quality.
支持構造物の上端に、上向きに開口した多数のソケットを一体に備えるとともに、頂版を構成させる各プレキャストコンクリート桁の両端下面に前記ソケット内にその内面との間に間隙を設けて挿入可能な下向きのソケット挿入用凸部を一体に備え、該ソケット挿入用凸部を前記支持構造物部上の各ソケットに挿入し、該ソケットとソケット挿入用凸部間の間隙に充填材を充填して互いに一体化させたことにより、プレキャストコンクリート桁の架設作業は、予め形成されている支持構造物のソケットにプレキャストコンクリート桁のソケット挿入用凸部を嵌め合せ、両者の隙間に無収縮性モルタル等からなる充填材を充填するだけで完了するため、現場での作業が熟練を要しない単純作業となるとともに作業工数が少なく、工期を短縮できる。 A large number of sockets opened upward are integrally provided at the upper end of the support structure, and can be inserted into the socket with gaps between the inner surfaces of the precast concrete girders constituting the top slab. A downward socket insertion convex portion is integrally provided, the socket insertion convex portion is inserted into each socket on the support structure portion, and a filler is filled in the gap between the socket and the socket insertion convex portion. By integrating each other, the precast concrete girder erection work is done by fitting the socket for the precast concrete girder into the socket of the pre-formed support structure, and using a non-shrinkable mortar or the like in the gap between them. Since the work is completed simply by filling the filler, the work at the site becomes a simple work that does not require skill, and the work man-hours are small and the work period can be shortened. .
支持構造物のソケットにプレキャストコンクリート桁のソケット挿入用凸部の製造誤差があっても、その誤差を想定して、両者の嵌合部分の隙間を設定しておくことにより問題なく両者間を固定することができる。 Even if there is a manufacturing error of the projection for inserting the socket of the precast concrete girder in the socket of the support structure, it is possible to fix the gap between the two without any problem by setting the gap between the two fitting parts. can do.
前記支持構造物を、地中に多数並べて打設したプレキャストコンクリート杭をもって構成し、各プレキャストコンクリート杭の上端にそれぞれ前記ソケットを一体に備えるようにすることにより、プレキャストコンクリート杭の製造時にソケットを形成しておくことができ、現場における作業が少なくなると同時にソケットの品質を安定化することができる。 The support structure is composed of precast concrete piles arranged side by side in the ground, and the sockets are integrally formed at the upper end of each precast concrete pile, so that sockets are formed during the production of precast concrete piles. This reduces the amount of work on site and stabilizes the quality of the socket.
前記ソケットを、杭の上端に設置された鋼製の筒状部材としたことにより、結合部は鋼管によって外周が被覆された鋼コンクリート合成構造となって高い曲げ及びせん断応力を有する構造とできる。 By making the said socket into the cylindrical member made from steel installed in the upper end of a pile, it can be set as the structure which has a high bending and shear stress as a joint part becomes the steel concrete composite structure by which the outer periphery was coat | covered with the steel pipe.
前記プレキャストコンクリート杭を、断面がH型のプレキャストコンクリート杭とすることにより、土留側壁の構築に際し、隣り合うH型のプレキャストコンクリート杭のフランジ部間に形成される空間に間詰めコンクリートを打設することが可能となり、杭間の応力の伝達性が良くなるとともに止水性に優れた構造とすることができる。 By setting the precast concrete pile as a precast concrete pile having an H-shaped cross section, when constructing the retaining wall, the compacted concrete is placed in a space formed between the flange portions of adjacent H-shaped precast concrete piles. It becomes possible, and it can be set as the structure which was excellent in the water stop while improving the transmissibility of the stress between piles.
断面H型のプレキャストコンクリート杭の上端部のウエブ部分を前記ソケットの深さ分だけ除去し、該ウエブ部除去部分の前後のフランジ部縁部間に鋼製の側面板を固定することによって、前記前後のフランジ部と両側面板に囲まれたソケットを杭上端に一体に備えることにより、ソケットを構成する部材の殆どをプレキャストコンクリート杭構成部分にて構成させることとなり、経済的であるとともに、プレキャストコンクリート杭とソケットとの一体性が高くなり、安定した強度が得られる。 By removing the web portion of the upper end portion of the precast concrete pile having an H-shaped section by the depth of the socket, and fixing the steel side plate between the front and rear flange edge portions of the web portion removal portion, By providing a socket surrounded by the front and rear flanges and both side plates integrally on the top of the pile, most of the members that make up the socket are made up of precast concrete pile components, which is economical and precast concrete. The unity between the pile and the socket is increased, and a stable strength can be obtained.
断面H型のプレキャストコンクリート杭の上端部のウエブ部分と、一方のフランジ部とを前記ソケットの深さ分だけ除去し、他方のフランジ部の両縁部に断面がコ字状の鋼製金具の両縁を一体化させ、前記ウエブ部及び一方のフランジ部除去部分に他方のフランジ部と前記コ字状の鋼製金具に囲まれたソケットを杭上端に一体に備えたことにより、ソケットを構成する部材の一部をプレキャストコンクリート杭構成部分にて構成させることとなり、経済的であるとともに、プレキャストコンクリート杭とソケットとの一体性が高くなり、安定した強度が得られる。 The web part at the upper end of the H-shaped precast concrete pile and one flange part are removed by the depth of the socket, and a steel fitting having a U-shaped cross section is formed at both edges of the other flange part. Both edges are integrated, and a socket surrounded by the other flange part and the U-shaped steel fitting is integrally provided at the upper end of the pile at the web part and one flange part removal part to constitute a socket. A part of the member to be made is constituted by the precast concrete pile constituent portion, which is economical and the unity between the precast concrete pile and the socket becomes high, and a stable strength can be obtained.
断面がH型のプレキャストコンクリート杭の上端部の両フランジ部外面に鋼製のソケット前面側板及びソケット背面側板を設置し、互いに隣り合う前記プレキャストコンクリート杭の前記ソケット前面板間及びソケット背面板間を一体に連結させるとともに、該前面板と背面板との間を、仕切り用連結材にて連結することにより複数のソケットを形成することにより、H型のプレキャストコンクリート杭と、プレキャストコンクリート桁の幅が、使用できるクレーンの幅や、道路輸送上の問題によってことなる場合、プレキャストコンクリートくいを並べて構成させた支持構造物上に、プレキャストコンクリート桁の幅に対応させた幅のソケットを簡単に設置することができる。 A steel socket front side plate and a socket rear side plate are installed on the outer surface of both flanges at the upper end of the H-shaped precast concrete pile, and between the socket front plate and the socket back plate of the precast concrete pile adjacent to each other. By connecting together and forming a plurality of sockets by connecting the front plate and the back plate with a connecting member for partitioning, the width of the H-type precast concrete pile and the precast concrete girder is reduced. If there is a difference in the width of the crane that can be used and road transportation problems, a socket with a width corresponding to the width of the precast concrete girder can be easily installed on the support structure in which precast concrete piles are arranged side by side. Can do.
前記プレキャストコンクリート桁間を一体化させる締結具として、該各プレキャストコンクリート桁に跨らせて幅方向に挿通したPC緊張材を使用し、前記平版状物全体に幅方向のプレストレスを導入することにより、1のプレキャストコンクリート桁に掛かる活荷重が、他のプレキャストコンクリート桁分散されることとなり、桁1本あたりの負担を小さいものとできる。 As a fastener for integrating the spaces between the precast concrete girders, using a PC tension material that is inserted in the width direction across the precast concrete girders, and introducing a prestress in the width direction to the entire lithographic material. Thus, the live load applied to one precast concrete girder is distributed to other precast concrete girders, and the load per girder can be reduced.
次に本発明の好適な実施形態を図面に基づいて具体的に説明する。 Next, preferred embodiments of the present invention will be specifically described with reference to the drawings.
図1本発明をアンダーパスに応用した実施例を示しており、図において符号10はアンダーパスが設けられる道路等の地盤であり、11は本発明における支持構造物であって、地盤10を横切る配置に形成した一対の土留側壁、12は、本発明における平版状物であって、両土留側壁11の頂部間に掛け渡して一体に連結した頂版、13は側壁11間に、これと一体的に形成した底版である。
1 shows an embodiment in which the present invention is applied to an underpass. In the figure,
土留側壁11は、図2に示すように、断面がH型をした多数のプレキャストPC杭14,14……を幅方向に並べて土中に打設することによって構成されている。即ち、この土留側壁11は、それぞれH形断面を有するプレキャストPC杭14を、そのH型のフランジ部14b,14cを連接させて地盤10中に沈設することによって構成されている。尚、この沈設は、フランジ部14b,14c間にオーガスクリュー式の削孔機(図示せず)を挿入し、この削孔機によって排土させながら沈設することができる。
As shown in FIG. 2, the
プレキャストPC杭14の下端側は地盤底部の地中に沈設されており、底版13から上側が、アンダーパスの土留側壁を構成している。土留側壁11,11の形成は、地盤10上から各杭14,14……を土中に沈設して所定の深さの土留側壁11,11を形成し、しかる後互いに対向する杭14,14間に切り梁を仮設し、両土留側壁11,11間の土砂を掘削し、所望のアンダーパス空間15を形成する。
The lower end side of the
アンダーパス空間15を形成した後、底版13を場所打ちコンクリートによって形成する。底版の形成に際しては、例えば、土留側壁を構成するプレキャストPC杭14に予め設置しておいた底版連結用の鉄筋を底版13内に埋め込むことにより土留側壁と一体化させる。
After the
また、各土留側壁11,11において、土留側壁の所定幅毎にPC緊張材17を挿通するとともに、互いに隣り合うプレキャストPC杭14,14のフランジ部14b,14cとウエブ部14aに囲まれる空間18内に間詰めコンクリート19を打設し、前記PC緊張材17を緊張することによって杭間が埋められて互いに一体化された土留側壁となす。
Further, in each retaining
各プレキャストPC杭14は、その上端に鋼製のソケット20が予め一体に設置されている。このソケット20は、図3に示すように、角筒状に形成され、その下端側の略半分がプレキャストPC杭14の上端外に嵌め込まれ、残りの上端側部分が杭14の上端延長方向に突出している。
Each
このようにしてプレキャストPC杭14を並べて沈設することによって土留側壁11,11を形成することにより、図6に示すように各土留側壁11,11の上端に、杭14の数だけのソケット20が土留側水平長さ方向に並べて設置させる。
As shown in FIG. 6,
頂版12は、図4〜図8に示すように多数のプレキャストPC桁25をアンダーパスの軸方向に並べ、それぞれの両端を土留側壁11,11上端間に掛け渡し、互いに隣り合うプレキャストPC桁25,25間の隙間に後述する間詰め材及び目地材であるモルタル33を介在させて平版状に形成されている。また該プレキャストPC桁25,25……の幅方向に跨らせて後述するPC緊張材35,35……が挿通され、これを緊張して平版状の頂版全体に、プレキャストPC桁25の幅方向、即ちアンダーパスのトンネル軸方向に向けたプレストレスを導入することにより全体が一体化されている。
As shown in FIGS. 4 to 8, the
尚、図4〜図6は、間詰め材及び目地材であるモルタル33を充填する前の状態を示しており、図7、図8は同充填後の状態を示している。
4 to 6 show the state before filling the
各プレキャストPC桁25は、工場にて形成されたものを使用し、その長さ方向には予めプレストレスが導入されている。このプレキャストPC桁25の両端下面には、それぞれ前述したソケット20内に間隙を持たせて嵌まり合う大きさのソケット嵌合用凸部25a,25aが一体成型されているとともに、プレキャストPC桁25の両側面には、互いに対称な位置に、上縁から下縁近くにまで達する間詰め材充填用凹部30が一定間隔毎に形成されており、上縁には両端に亘って浅い目地用凹部31が形成されている。更に、各プレキャストPC桁25には、両側面の前記間詰め材充填用凹部30,30に連通開口させたPC緊張材挿通孔32が形成されている。
Each
頂版12の構築は、施工現場へプレキャストPC桁25を搬入し、先に構築した土留側壁11,11の上端のソケット20,20にプレキャストPC桁25の両端のソケット嵌合凸部25a,25aを挿入することにより、幅方向に隣り合わせた多数のプレキャストPC桁25,25……を架設する。
The
しかる後、各プレキャストPC桁25,25間にて互いに向かい合う間詰め材充填用凹部30,30によって構成される間詰め部空間に、隣り合うプレキャストPC桁25,25間において互いに向かい合うPC緊張材挿通孔32,32に跨らせてシース(図示せず)を設置して該間詰め分空間内に充填材であるモルタル33を充填する。これと同時に目地用凹部31,31によって構成される目地溝内に目地材であるモルタル33を充填する。
After that, the PC tension material is inserted between the adjacent
このようにして多数のプレキャストPC桁25を並べて架設して平版状となした後、水平方向に属したPC緊張材挿通孔32,32……にPC緊張材35を挿通し、これを緊張して頂版12全体に桁幅方向のプレストレスを付与することにより、各プレキャストPC桁25を力学的に一体化させた頂版12となす。次いで、ソケット20の内面と凸部25aの外周面との間隙に無収縮モルタルからなる充填材36を充填する。
In this way, a large number of
上述の実施例では、断面H型のプレキャストPC杭14の上端に筒状をした構成の金具を一体に突設することによってソケット20を構成させているが、この他、図11(a)〜(c)に示すように、断面H型のプレキャストPC杭14の上端部のウエブ部14a部分を、ソケットの深さ分だけ除去し、そのウエブ部除去部分の前後のフランジ部14b,14cの縁部間に鋼製の側面板50,50を固定することによって、前後のフランジ部14b,14cと両側面板50,50に囲まれたソケット51を杭上端に一体に備えることができる。
In the above-described embodiment, the
このように構成することによりソケットを構成する部材の殆どをプレキャストPC杭構成部分にて構成させることとなり、経済的であるとともに、プレキャストPC杭とソケットとの一体性が高くなり、安定した強度が得られる。 By constituting in this way, most of the members constituting the socket will be constituted by the precast PC pile component, which is economical and the integrity of the precast PC pile and the socket is increased, and the stable strength is increased. can get.
またこの他、図12(a)〜(c)に示すように、断面H型のプレキャストPC杭14の上端部のウエブ部14a部分と、一方のフランジ部14b部分とをソケットの深さ分だけ除去し、他方のフランジ部14cの両縁部に断面がコ字状の鋼製金具52の両縁を一体化させ、前記ウエブ部及び一方のフランジ部除去部分に他方のフランジ部14cと前記コ字状の鋼製金具52に囲まれたソケット53を杭上端に一体に備えることができる。
In addition, as shown in FIGS. 12 (a) to 12 (c), the
このように構成することにより、ソケットを構成する部材の一部をプレキャストPC杭構成部分にて構成させることとなり、経済的であるとともに、プレキャストPC杭とソケットとの一体性が高くなり、安定した強度が得られる。 By constituting in this way, a part of the member constituting the socket will be constituted by the precast PC pile constituent part, and it is economical and the integrity of the precast PC pile and the socket becomes high and stable. Strength is obtained.
更に、図13(a)〜(c)に示すように、断面がH型のプレキャストPC杭14の上端部の両フランジ部14b,14cの外面に鋼製板状をしたソケット前面側板54a及びソケット背面側板54bを設置し、その両板54a,54bの両縁間に仮止め板55,55をボルトにより仮止めしておく。
Further, as shown in FIGS. 13A to 13C, a socket
この各プレキャストPC杭14,14……を並べて打設することによって支持構造物とした後、図14に示すように、各仮止め板55,55……を取り外し、互いに隣り合うプレキャストPC杭14,14間におけるソケット前面板54a,54a間及びソケット背面板54b,54b間を溶接またはボルト止めなどの連結手段によって連結する。
After the precast PC piles 14, 14... Are placed side by side to form a supporting structure, the
しかる後、互いに複数枚ずつ連結されたソケット前面板54aとソケット背面板54bとの間に、複数の仕切り用連結板56,56……を一定間隔毎に溶接またはネジ止めによって連結する。このようにしてソケツト前面板54a、ソケット背面板54b及び一対の仕切り用連結板56,56によって囲まれて構成された任意数のソケット57を形成することができる。
After that, a plurality of
このようにしてソケット57を構成させることにより、H型のプレキャストPC杭14と、プレキャストPC桁25の幅が、使用できるクレーンの幅や、道路輸送上の問題によってことなる場合、プレキャストPC杭を並べて構成させた支持構造物上に、プレキャストコンクリート桁の幅に対応させた幅のソケットを簡単に設置することができる。
By configuring the
尚、上述の実施例では、H型のプレキャストPC杭を使用して土留側壁を構築した場合を示しているが、H型の他、連続地中壁を構築するための各種のプレキャストコンクリート杭や鋼管杭、場所打ちコンクリート杭を用いて土留側壁を構築しても良い。 In addition, although the above-mentioned Example has shown the case where the retaining wall is constructed using the H type precast PC pile, various precast concrete piles for constructing the continuous underground wall in addition to the H type The retaining wall may be constructed using steel pipe piles and cast-in-place concrete piles.
また、土留側壁上端のソケットは上述した鋼製の筒状部材のものの他、図13、図14に示すように、土留側壁11の上端に凹部40を一体成型してソケット20としたものであっても良い。尚、前述した実施例と同一部分には同一符号を付している。
In addition to the steel tubular member described above, the socket at the upper end of the retaining wall is a
更に、土留側壁はプレキャストコンクリート杭の他、底版と一体成型した又は底版に一体化される縦(鉛直)壁状のコンクリートブロックを設置すること、或いは場所打ちコンクリートのコンクリートによって構築されたものであっても良い。これらの場合においてその上端のソケットは、鋼管を埋設することによって設置しても良く、周壁がコンクリート製の凹部であっても良い。 In addition to the precast concrete piles, the retaining wall is constructed by installing vertical (vertical) wall-shaped concrete blocks that are molded integrally with the bottom plate or integrated with the bottom plate, or by cast-in-place concrete. May be. In these cases, the upper end socket may be installed by embedding a steel pipe, and the peripheral wall may be a concave portion made of concrete.
更に、本発明は、上述したアンダーパスの頂版架構構造の他、図15に示すように橋梁に実施しても良く、この例では、河川の対岸に、支持構造物である橋台(又は橋脚)45,45を構築し、その橋台(又は橋脚)45,45の上端間に平版状物である床版46を剛結合構造で架設する場合にも同様に実施することができる。この場合の橋台(又は橋脚)45は前述と同様のコンクリートPC杭を使用したもの、場所打ちコンクリートによるもの等、各種構造であっても良い。
Further, the present invention may be applied to a bridge as shown in FIG. 15 in addition to the above-described underpass top plate frame structure. In this example, on the opposite bank of the river, an abutment (or pier) as a support structure is provided. ) 45, 45 is constructed, and the
更に図には示してないが、本発明は適宜の建築物の壁と床との結合にも同様に適用することができる。 Further, although not shown in the drawings, the present invention can be similarly applied to the connection of an appropriate building wall and floor.
10 地盤
11 土留側壁
12 頂版
13 底版
14 プレキャストPC杭
14a ウエブ部
14b,14c フランジ部
15 アンダーパス空間
16 底版連結用の鉄筋
17 PC緊張材
18 空間
19 間詰めコンクリート
20 ソケット
21 開口
25 プレキャストPC桁
25a ソケット嵌合用凸部
30 間詰め材充填用凹部
31 目地用凹部
32 PC緊張材挿通孔
33 モルタル
35 PC緊張材
36 充填材
40 凹部
45 橋台
46 床版
50 側面板
51 ソケット
52 鋼製金具
53 ソケット
54a ソケット前面側板
54b ソケット背面側板
55 仮止め板
56 仕切り用連結板
57 ソケット
DESCRIPTION OF
Claims (10)
前記支持構造物の上端に、上向きに開口した多数のソケットを、該支持構造物の水平長さ方向に並べて一体に備えるとともに、
前記各プレキャストコンクリート桁の両端下面に前記ソケット内にその内面との間に間隙を設けて挿入可能な下向きのソケット挿入用凸部を一体に備え、
該ソケット挿入用凸部を前記支持構造物部上の各ソケットに挿入し、該ソケットとソケット挿入用凸部間の間隙に充填材を充填して互いに一体化させたことを特徴としてなるプレキャストコンクリート桁による平版状物架構構造。 A lithographic shape by a precast concrete girder that supports a plurality of precast concrete girders supported in a parallel arrangement between support structures standing upright apart from each other, and integrating the precast concrete girders into a lithographic material. In the frame structure,
At the upper end of the support structure, a large number of sockets opened upward are arranged in a row in the horizontal length direction of the support structure, and are integrally provided.
Provided integrally with a downward socket insertion convex portion that can be inserted into the socket with a gap between the inner surfaces of both pre-cast concrete girders on the lower surface of both ends,
Precast concrete characterized in that the projection for inserting the socket is inserted into each socket on the support structure portion, and a filler is filled in the gap between the socket and the projection for insertion of the socket so as to be integrated with each other. A planographic frame structure with girders.
As a fastener for integrating the space between the precast concrete girders, using a PC tension material that is inserted in the width direction across the precast concrete girders, introducing prestress in the width direction to the whole lithographic material The planographic structure of a precast concrete girder according to any one of claims 1 to 6.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007339808A JP5062418B2 (en) | 2007-12-28 | 2007-12-28 | Plane frame structure with precast concrete girder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007339808A JP5062418B2 (en) | 2007-12-28 | 2007-12-28 | Plane frame structure with precast concrete girder |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2009161932A JP2009161932A (en) | 2009-07-23 |
JP5062418B2 true JP5062418B2 (en) | 2012-10-31 |
Family
ID=40964854
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2007339808A Expired - Fee Related JP5062418B2 (en) | 2007-12-28 | 2007-12-28 | Plane frame structure with precast concrete girder |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5062418B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105780809B (en) * | 2016-03-24 | 2018-06-29 | 上海市机械施工集团有限公司 | A kind of multi-functional sinking equipment and its construction method |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3896351B2 (en) * | 2003-06-30 | 2007-03-22 | 株式会社ピーエス三菱 | Construction method of underground wall and construction method of underpass |
JP4361839B2 (en) * | 2004-06-16 | 2009-11-11 | 前田建設工業株式会社 | Construction method and structure of underpass road at intersection |
JP4464216B2 (en) * | 2004-07-07 | 2010-05-19 | 東日本旅客鉄道株式会社 | Bridge structure and its construction method |
JP4641257B2 (en) * | 2005-12-27 | 2011-03-02 | 株式会社ピーエス三菱 | Construction method of concrete |
JP4647544B2 (en) * | 2006-05-19 | 2011-03-09 | 鹿島建設株式会社 | Underpass construction method and underpass |
-
2007
- 2007-12-28 JP JP2007339808A patent/JP5062418B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2009161932A (en) | 2009-07-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20160340855A1 (en) | Modular construction mold apparatus and method for constructing concrete buildings and structures | |
KR102208793B1 (en) | Under ground structure using column wall and construction method thereof | |
KR101278687B1 (en) | Box-type thrust tube structure, and method of building underground structure using the box-type thrust tube structure | |
KR101263370B1 (en) | Precast end-block with girder connection member and bridge construction method using ths same | |
KR101288601B1 (en) | Underpass using precast concrete pile and bottom slab and method for constructing the same | |
JP3844743B2 (en) | Box girder bridge structure and its construction method | |
KR101148272B1 (en) | Downward Construction Method of Basement applying SCFSliding Channel Form | |
KR20090117860A (en) | The construction method of underpass using steel-concrete composite wall pile | |
KR101167511B1 (en) | Underpass using precast concrete pile and method for constructing the same | |
KR101013235B1 (en) | Manufacturing method of rainwater storage bath | |
KR20070052109A (en) | Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor | |
KR101356724B1 (en) | Retaining walls and construction method thereof | |
KR101054718B1 (en) | Rahmen bridge using butress and enlarged tendon and rahmen bridge construction method thterefor | |
JP4865300B2 (en) | Semi-underground road construction method | |
JP5062418B2 (en) | Plane frame structure with precast concrete girder | |
KR20060117746A (en) | A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof | |
KR101271290B1 (en) | Underground reclamation type water storage tank having a assembling structure | |
KR102482690B1 (en) | Bridge foundation construction method using formwork integrated PC panels | |
JP5280150B2 (en) | Yamadome retaining wall and method of forming Yamadome retaining wall | |
JP2004346729A (en) | Widened road | |
KR101439400B1 (en) | A hinged base structure of arch-shaped composite structure with the precast concrete pannel and the steel frame using the open trench tunnel and method for constructing arch-shaped open trench tunnel | |
KR20210098162A (en) | Under ground structure using column steel pipe wall and construction method thereof | |
JP2008274567A (en) | Circular steel pipe prefabricated bridge and its construction method | |
JP2005282115A (en) | Construction method of steel element concrete type underground structure | |
KR102503888B1 (en) | Underground space structure with pretension PSC wall of stepped variable section structure and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20101111 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20120125 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20120307 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20120424 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20120704 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20120724 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5062418 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20150817 Year of fee payment: 3 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |