KR101148272B1 - Downward Construction Method of Basement applying SCFSliding Channel Form - Google Patents

Downward Construction Method of Basement applying SCFSliding Channel Form Download PDF

Info

Publication number
KR101148272B1
KR101148272B1 KR1020090062000A KR20090062000A KR101148272B1 KR 101148272 B1 KR101148272 B1 KR 101148272B1 KR 1020090062000 A KR1020090062000 A KR 1020090062000A KR 20090062000 A KR20090062000 A KR 20090062000A KR 101148272 B1 KR101148272 B1 KR 101148272B1
Authority
KR
South Korea
Prior art keywords
floor
wall
basement
construction
cip
Prior art date
Application number
KR1020090062000A
Other languages
Korean (ko)
Other versions
KR20110004541A (en
Inventor
이창남
Original Assignee
이창남
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이창남 filed Critical 이창남
Priority to KR1020090062000A priority Critical patent/KR101148272B1/en
Publication of KR20110004541A publication Critical patent/KR20110004541A/en
Application granted granted Critical
Publication of KR101148272B1 publication Critical patent/KR101148272B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/13Geometrical or physical properties having at least a mesh portion
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

굴토 공사시 가설 흙막이의 기본 요소는 흙막이벽과 가로 버팀 부재인데 본 발명의 흙막이벽은 CIP(Cast In Place Pile, 주열식 흙막이, 이하 CIP) 연속벽을 사용하는 하향공사를 손쉽게 시공하는 미끄럼 골거푸집(Sliding Channel Form, 이하 SCF)에 관한 것이다.The basic elements of the temporary cladding at the time of the gulto construction are the cladding wall and the horizontal bracing member. The cladding wall of the present invention is a sliding rib formwork for easily constructing the downward construction using the CIP (Cast In Place Pile). (Sliding Channel Form, SCF).

가설 흙막이는 공사기간 동안 임시로 토압과 수압을 저항하도록 설치한 것이므로 기초공사 후 영구 벽체가 되는 합벽을 정상적인 상향 공법으로 시공하는 것이 작업효율과 공사품질을 높일 수 있어서 바람직하다. 그러나 지하실이 깊어지면서 지하공사를 마치고 순차적으로 상향공법을 적용하려면, 공사기간과 원가 상승, 공사중 토사붕괴위험 등의 부담 때문에 하향공법을 선호하고 있다. 하향공법은 지하 터파기를 하면서 본 건축물에 사용할 구조체를 동시에 축조하는 방법으로, 각층 지하외벽(합벽)과 바닥판을 한 층씩 동시에 완성해 내려가는 것이 바람직하나 위에 상층벽체가 있는 상태에서 그 아래 하층벽체를 시공하는 작업은 어렵다. 또한 하향공법 시 필수적인 작업용 장비에서 발생하는 매연 배출과 자연채광을 위해 외벽면에 개구부가 있으면 편리하다. 그러므로 지하실 합벽과 바닥 슬래브가 만나는 간섭부분을 슬기롭게 처리하면, 하향공법을 적용하는데 큰 효과가 있으며 이것이 본 발명의 핵심 기술이다.Temporary mudstones are installed to temporarily resist earth pressure and water pressure during the construction period. Therefore, it is desirable to construct the plywood wall, which becomes a permanent wall after the foundation work, by improving the work efficiency and construction quality. However, if the basement is deepened and the underground construction is to be applied sequentially, the downward construction method is preferred due to the burden of construction period, cost increase, and risk of soil collapse during construction. The downward method is a method of simultaneously constructing a structure to be used for this building while digging underground, and it is preferable to complete each floor's basement outer wall (plywood) and bottom plate at the same time. Construction work is difficult. In addition, it is convenient to have an opening on the outer wall surface for the emission of smoke and natural light generated from the work equipment essential for the downward construction method. Therefore, wisely treating the interference portion where the basement cladding and the floor slab meet, there is a great effect in applying the downward method, which is the core technology of the present invention.

CIP(10)와 바닥판(40) 사이의 지하외벽(30)은 가설 흙막이벽에 거푸집을 건물 내측에만 설치하고 콘크리트를 타설하는 합벽으로 공사한다. 지하외벽을 합벽으 로 후시공하기 위해 CIP와 바닥판 사이의 공간을 비어 놓고 슬래브를 타설하면, CIP가 받는 지하수압과 토압을 바닥판 슬래브에 이전하는 하중전달 경로가 끊어진다. 그렇다고 위 공간을 사전에 메우려면 바닥판 하부에 지하외벽 콘크리트를 부어넣기 위한 콘크리트 타설 구멍이 필요하다. 콘크리트 타설구멍을 이용한 하향공법은 공사가 완료된 후 바닥판 하부와 지하외벽 이음부의 콘크리트가 잘 충전되지 않아 균열 및 방수하자가 발생할 우려가 있다. 그러므로 바닥판과 합벽이 공유하는 간섭부분 일부를 후시공 하면서도 후에 합벽을 시공할 때까지 CIP에서 전달되는 큰 토압과 수압을 바닥판에 능히 전달하는 임시 매개체가 필요하다.The basement outer wall 30 between the CIP 10 and the bottom plate 40 is constructed with a plywood wall in which the formwork is installed only on the inside of the building, and the concrete is poured. If the space between the CIP and the bottom plate is emptied to post-construct the outer wall to the plywood wall, the slab is poured, and the load transfer path to transfer the groundwater pressure and earth pressure received by the CIP to the bottom plate slab is broken. However, in order to fill the above space in advance, a concrete pouring hole is needed to pour the basement wall concrete under the bottom plate. In the downward construction method using concrete pouring holes, the concrete is not well filled in the lower part of the bottom plate and the joint of the basement outer wall after the construction is completed, which may cause cracking and waterproofing. Therefore, it is necessary to temporarily construct a part of the interference part shared by the floorboard and the plywood, and to temporarily transmit the large earth pressure and water pressure transmitted from the CIP to the floorboard until the plywood is constructed later.

지하실이 깊어지면 외벽에서 전달되는 토압과 수압을 안전하게 지탱하기 위하여 바닥판 두께를 키워야 할 때도 있다. 그러므로 지하실 합벽과 바닥판의 간섭부분에 개구부를 설치한 재래식 공법은 도 4와 같이 개구부 주변과 콘크리트가 타설되는 부분을 보강하고 있으나 얇고 좁은 공간에 철근을 배근하고, 콘크리트를 부어 넣는 것은 어려운 작업이다. 따라서 도 9와 같이 바닥판 슬래브를 지지하는 철골 보로 '상부플랜지를 안쪽으로 접어 넣은 TSC보'(특허등록 10-0872959, 이하 TSC 보)를 사용하면 TSC 보 내부에 콘크리트를 타설할 수 있어 CIP에서 전달되는 토압과 수압에 효과적으로 저항할 수 있게 된다. 그러므로 CIP에서 전달되는 압축력에 효과적으로 저항할 수 있는 TSC 보를 벽보로 활용한다.As the basement deepens, it may be necessary to increase the thickness of the bottom plate to safely support the earth pressure and water pressure transmitted from the exterior walls. Therefore, the conventional method of installing the openings in the interference part of the basement plywood and the bottom plate reinforces the part around the opening and the concrete, as shown in Fig. 4, but it is difficult to reinforce the steel in the thin and narrow space and pour concrete into . Therefore, when using the TSC beam (folding the upper flange inward) (steel patent registration 10-0872959, hereinafter referred to as TSC beam) as a steel beam to support the slab slab as shown in Fig. 9 in the CIP Effectively resists earth pressure and hydraulic pressure delivered. Therefore, TSC beams are used as wall beams, which can effectively resist the compressive force transmitted from the CIP.

CIP는 지하천공 시 시공오차 등으로 정밀시공이 불가능하므로 합벽의 두께가 부위별로 달라진다. 따라서 위 CIP와 벽보 사이에 끼워 넣는 두꺼운 리브의 길이도 달라진다. 리브는 거푸집 공사 현장에서 하나하나 맞춤 제작하는 대신 미끄럼 골거 푸집(SCF)으로 해결한다. 미끄럼 골거푸집은 도 2b와 같이 A, B 한 쌍의 얇은 강판을 U형으로 접어 제작하여 B를 A에 끼워 넣으면 A안에서 길이 방향으로 이동이 가능하게 된다.Since the CIP cannot be precisely constructed due to construction errors in underground drilling, the thickness of the plywood wall varies for each part. Thus, the length of the thick ribs that fit between the upper CIP and the wall will also vary. Ribs are solved with sliding corrugated formwork (SCF) instead of custom-made at the formwork site. The sliding rib form is manufactured by folding a pair of thin steel sheets A and B in U shape as shown in FIG. 2B and inserting B into A to move in the longitudinal direction in A. FIG.

합벽은 큰 상층부 연직하중을 지지할 수 있어서 벽보 밑의 기둥을 생략하고 직접 합벽에 지지시키는 경우가 많다. 그런데 합벽을 후시공 하려면 그 때까지 벽보를 지지하는 별도 조치도 필요하며, 도 2의 3각브라켓이 그러한 기능을 수행한다. 3각브라켓(80)은 흙막이 H파일에 수직으로 용접 한 브라켓부착 띠강판(82)에 볼트 접합하여 바닥 콘크리트 양생이 끝난 후 회수하여 재활용할 수도 있다. 그러나 바닥콘크리트 양생이 끝났다고 해도 개구부를 제외한 리브가 임시로 바닥 연직하중을 CIP에 지지 시키는 것은 무리여서 바닥 콘크리트를 붓기 전에 경사버팀대인 밀대(90)를 별도로 추가한다. 3각브라켓은 바닥 콘크리트가 적어도 7일 강도를 발현된 후에 회수하여 재활용이 가능하다.The plywood walls can support large vertical vertical loads, so the pillars under the beams are often omitted and directly supported on the plywood walls. However, to post-install the plywood, it is necessary to take additional measures to support the wall until then, and the triangular bracket of FIG. 2 performs such a function. The triangular bracket 80 may be bolted to the bracket-coated strip steel plate 82 welded vertically to the soil barrier H pile, and then recovered and recycled after finishing the bottom concrete curing. However, even if the floor concrete curing is finished, the ribs except for the opening temporarily supports the vertical vertical load on the CIP, so it is impossible to add a push rod 90, which is an inclined brace, before pouring the floor concrete. The triangular bracket can be recovered by recycling the floor concrete after at least 7 days of strength.

Description

미끄럼 골거푸집(SCF)을 활용한 지하실 하향공법{Downward Construction Method of Basement applying SCF(Sliding Channel Form)}Downward Construction Method of Basement applying SCF (Sliding Channel Form)}

전 세계에서 지하실의 연면적이 가장 많고 또 깊은 곳은 우리나라일 것이며 지금도 전국 도처에서 지하실 공사를 계속하고 있다. 지하실 층수가 많은 건물 대지는 예외 없이 땅값이 비싸 지하외벽선이 대지 경계선과 인접한 것이 대부분이다. 그러므로 지하실 공사 중 주변 건물이나 시설물에 주는 피해를 최소한으로 줄이는 것이 필수적인데 지금까지 알려진 가장 안전한 방법은 지하실 하향공법이다. 땅 구덩이를 깊게 파면 지하수와 함께 주변의 흙이 밀려드는 과정에서 인접 건물이나 도로 및 각종 시설물에 변형, 변위를 유발할 수 있으므로 이를 최소한으로 줄이기 위하여서는 가설흙막이를 하여야 한다.The world's largest and deepest basement area in the world will be in Korea, and construction is still underway throughout the country. Building sites with a high basement floor are expensive without exception, and most of them are adjacent to the land boundary. Therefore, it is essential to minimize the damage to nearby buildings and facilities during the construction of the basement. Deep digging of the ground pit can cause deformation and displacement of adjacent buildings, roads, and various facilities in the process of pushing the surrounding soil along with groundwater, so to minimize this, temporary blockage should be done.

건물 본체 공사에 앞서 행하는 굴토 및 가설흙막이 공사의 존치기간이 길어지면 전체 공기가 길어질 뿐만 아니라 지하실 기초공사에 이어 1층 바닥골조를 완료할 때까지의 지하골조 공사기간은 마치 눈을 가리고 지뢰밭을 거니는 것과도 같은 토사붕괴위험에 처하게 된다. 이같은 불안감을 최소한으로 줄이기 위하여 적용하는 것이 지하실 하향공법이다. 도 8과 같이 가설 흙막이의 기본 요소는 흙과 직접 접하는 세로방향 흙막이벽과 이를 수평방향으로 구속하는 가로 버팀 부재인데 본 발명에서 다루는 흙막이벽은 CIP를 지하외벽 주변에 따라 연속적으로 배열한 것이다.If the length of the pit soil and temporary mudstone construction prior to the building body construction is longer, the overall air will not only be longer, but the underground frame construction period until the completion of the basement floor construction after the basement foundation construction is as if blindfolded and walked through the minefield. You will be in danger of earth and earth collapse. To reduce this anxiety to a minimum, the basement downhole is applied. As shown in FIG. 8, the basic elements of the temporary clamboard are vertical cladding walls directly contacting the soil and a horizontal support member constraining them in a horizontal direction. The cladding wall covered in the present invention is a CIP arranged continuously along the periphery of the basement outer wall.

CIP는 천공장비로 뚫은 구멍에 H형강이나 원통형 철근망을 삽입하고 나머지 빈 공간에 콘크리트를 채운 현장 콘크리트 말뚝인데 그 굵기와 H형강의 규격 및 삽입 간격은 흙의 종류, 지하수위, 지하실 깊이 및 이를 버텨주는 가로 버팀 부재의 상하 간격(여기서는 지하실 층고)에 따라 달라진다. 하향공법에서는 건물의 각층 영구 바닥판이 가설 버팀대(Strut)의 기능을 겸한다. 그런데 하향공법에서 각층 바닥판과 지하외벽(합벽)을 동시에 선 시공하는 것이 흙막이 안전상 바람직하나, 하층 벽체를 후 시공하면 필연적으로 콘크리트를 거꾸로 부어 넣는 작업이 쉽지 않다. 한편 선시공된 가설 흙막이가 공사중 단기하중에는 능히 토압과 수압을 저항할 수 있으므로 기초공사가 끝난 후 정상적인 상향 공법으로 합벽을 시공하는 것은 작업 효율과 공사의 품질을 높이는 첩경이 된다.CIP is a site concrete pile that inserts H-beam or cylindrical rebar network into the hole drilled by drilling equipment and fills the remaining empty space.The thickness, size and insertion interval of H-beam are the soil type, groundwater level, basement depth and The braces are dependent on the vertical spacing of the transverse brace members (in this case, the basement floor). In the downwork, permanent decks on each floor of the building function as a temporary strut. However, it is preferable for the earthquake to be installed at the same time with the bottom plate and the basement outer wall (plywood wall) in the downward construction method, but it is not easy to pour concrete upside down when the lower wall is constructed afterwards. On the other hand, since the pre-installed temporary block can resist earth pressure and water pressure during short-term load during construction, constructing the plywood wall by the normal upward construction method after finishing the foundation work is a shortcut to improve work efficiency and construction quality.

하향공법은 지하실 내부에서 작업하는 각종 장비들로 인해 발생하는 매연배출 및 최소한의 자연 채광을 위한 바닥판 개구부를 마련하는 것이 필요하다. 이러한 개구부가 외벽면에 연하여 있으면 매연배출과 자연채광 등에 활용 가능하다. 도 8에서 한 가지 어려우면서도 중요한 사항은 지하실 합벽과 바닥 슬래브가 만나는 부분 즉 단면이 겹쳐서 서로 간섭 되는 부분을 어떻게 처리하는가 하는 것이다. CIP와 바닥판 사이에 빈 공간이 있으면 CIP가 받은 지하수와 토압을 바닥판에 전달할 수 없으며, 공간이 없이 전부 메우면 후에 바닥판 아래 부분의 벽체 콘크리트를 부어넣을 구멍이 막히게 된다. 그러므로 CIP와 바닥판이 만나는 합벽 부분을 일부 후시공 하면서도 합벽을 시공할 때까지 CIP에 작용하는 토압과 수압을 바닥판에 용이하게 전달하는 임시 매개체가 필요하다.Downworking requires the provision of floorboard openings for minimal emissions and soot emissions resulting from various equipment working inside the basement. If the opening is connected to the outer wall surface, it can be utilized for soot emission and natural light. One difficult and important point in FIG. 8 is how to handle the areas where basement cladding and floor slabs meet, that is, where the cross sections overlap and interfere with each other. If there is an empty space between the CIP and the bottom plate, the groundwater and earth pressure received by the CIP cannot be transferred to the bottom plate, and if it is filled up without any space, the hole to pour the wall concrete below the bottom plate is blocked. Therefore, a temporary medium is needed to easily transfer the earth pressure and water pressure acting on the CIP to the bottom plate while constructing the part of the joint wall where the CIP and the bottom plate meet.

CIP와 바닥판이 만나는 합벽 부분을 일부 후 시공 하면서도 합벽을 시공할 때까지 CIP에 작용하는 토압과 수압을 바닥판에 전달하는 임시 매개체를 해결하기 위한 기존 기술은 도 4~도 7에 설명하는 바와 같다.Existing techniques for solving the temporary medium that delivers the earth pressure and water pressure acting on the CIP to the bottom plate while constructing a part of the joint wall where the CIP and the bottom plate meet, after the construction of the joint wall, are described in FIGS. 4 to 7. .

지하실이 깊어지면 바닥판 두께를 증가시켜야 할 정도로 토압과 수압이 커진다. 즉 도 8에서 지하실 합벽과 바닥판의 공유 간섭부분 중 일부만 선시공하여야 그 남은 개구부를 통해 합벽의 철근배근을 하고 콘크리트도 부어 넣을 수 있다. 그러나 이를 위해 특별한 조치를 하지 않고 바닥판 일부에 개구부를 남기고 바닥판과 같은 두께로 부분 시공하면, 구조 내력상 토압과 수압을 받을 수 없게 된다. 따라서 도 4와 같이 개구부 주변은 보강 철근이 많이 필요하게 된다. 그러나 지하실 바닥 슬래브는 두께가 고작 15~20cm 정도에 불과하여 도면에 표시된 대로 얇고 좁은 공간에 주근과 스터럽을 배근하고 또한 주변을 특수 보강하여 콘크리트를 부어 넣는 것은 쉬운 일이 아니며 더구나 이를 위한 거푸집 작업은 더 복잡하여 공사 기간과 인건비가 많이 드는 단점이 있다.As the basement deepens, the earth pressure and water pressure become large enough to increase the bottom plate thickness. That is, only a part of the shared interference portion of the basement plywood and the bottom plate in FIG. 8 needs to be pre-installed so that the reinforcement of the plywood is reinforced and the concrete can be poured through the remaining openings. However, if you do not take special measures to do this and leave an opening in a part of the bottom plate and partially install it with the same thickness as the bottom plate, it will not be able to receive earth pressure and water pressure in structural strength. Therefore, as shown in FIG. 4, the reinforcing bars are required around the opening. However, basement floor slabs are only 15-20cm thick, so it is not easy to pour the concrete by reinforcing the main stirrer and stirrup in a thin and narrow space as shown in the drawing, and also by specially strengthening the surroundings. It is more complicated, which requires a lot of construction time and labor costs.

도 5와 같이 재래식은 바닥에 ㄱ형강 장선을 걸고 그 위에 개구부를 피하여 리브라스를 오려 붙이고 나서 강판으로 만든 개구부 상자로 막은 후라야 각종 보강철근 배근이 가능하다. 또한 도 6과 같이 합벽 수직 철근도 불과 20cm 내외 폭의 개구부에 맞춰서 배근하여야 하므로 구조 내력에 따르는 자유로운 철근 간격 선택 이 불가능하며 합벽의 경제적인 설계를 포기하여야 한다. 도 7은 도 4~도 5의 방법 보다 더 오래된 초기 것으로 철골 보를 설치할 벽보를 선시공하는 것인데 이는 또 하나의 공정이 추가되며 벽보에 합벽 철근 토막을 사전 배근하고 미리 마련한 작은 원형파이프 슬리브를 통해 하부 벽체 콘크리트를 부어 넣어야 하므로 선시공한 띠장과 합벽 콘크리트 이음 부위에 균열이 발생하는 하자가 발생할 위험이 있다.As shown in Fig. 5, the conventional hanger is placed on the bottom of the a-beam and the openings are avoided to cut the ribs, and then closed with an opening box made of steel plate to reinforce various reinforcement bars. In addition, as shown in Figure 6, the vertical reinforcement of the plywood is also to be arranged in accordance with the opening of the width of only 20cm, it is not possible to select the free rebar spacing according to the structural strength and give up the economical design of the plywood wall. Figure 7 is earlier than the method of Figures 4 to 5 is to pre-install the wall to install the steel beams, which is another process is added to the lower wall through the pre-arranged small round pipe sleeve pre-arranged plywood reinforcement to the wall beam Since concrete needs to be poured, there is a risk that cracks will occur in the joints of the pre-constructed strip and the jointed concrete wall.

하향공법을 원활하게 적용하기 위해서는 촉박한 지하실 공사 기간에 별도 공종을 추가하지 않고, 합벽과 바닥판을 공유하는 간섭부분에 마련할 개구부의 폭을 최대한으로 넓히면서도 CIP에서 전달되는 토압과 수압을 바닥판에 안전하게 전달할 수 있는 새로운 방법을 모색하여야 한다. 또한 지하실 공사는 지루하고 비용이 많이 드는 3D 작업이므로 간단하며 공사기간이 짧고, 인건비를 포함한 공사비를 절감하는 신공법이 필요하다.In order to apply the downward method smoothly, it is necessary to increase the width of the opening to be provided in the interference part sharing the plywood and the floorboard, and to increase the width of the earth pressure and water pressure transmitted from the CIP without adding additional work during the tight basement construction period. Find new ways to communicate safely to the board. In addition, basement construction is a tedious and expensive 3D work, so it is simple, requires a short construction period, and requires a new construction method that reduces construction costs including labor costs.

지하외벽(30)은 연속적으로 시공한 두꺼운 벽체이므로 연직하중에 대한 부담능력도 크다. 따라서 외벽에 연하여 고층으로 올라가는 경우가 아니면 별도 기둥이 없어도 지하실 바닥하중은 물론 지상층 바닥하중을 지탱할 수 있다. 그러나 하향공법에서는 지하외벽을 시공하기 전에 가설 흙막이벽, 여기서는 CIP가 임시로 바닥 하중까지 받을 수 있도록 조치를 취해야 한다. 또한 그로인해 지하외벽공사를 마친 후 외관이 좋지 않아지거나 공사비가 많이 드는 것도 피해야 한다.Since the basement outer wall 30 is a thick wall continuously constructed, the burden capacity for vertical load is also large. Therefore, it is possible to support the basement floor load as well as the ground floor floor load without the need for a separate pillar unless it is connected to the outer wall to the high floor. However, in the downward process, measures must be taken to allow temporary temporary wall loads, here the CIP, to be temporarily loaded before installing the basement walls. Also, after finishing the underground exterior wall construction, it should be avoided that the appearance is not good or expensive.

도 9와 같이 바닥판 슬래브를 지지하는 철골 보로 일반 H형강 대신 '상부플랜지를 안쪽으로 접어 넣은 TSC보'(특허등록 10-0872959)를 사용하면 보 외관이 U형이고, 내부에 콘크리트를 채우므로 철근콘크리트 보와 동일한 형상의 단면이 된다. 따라서 CIP에서 전달되는 토압과 수압을 바닥 슬래브에 전달하는 매개체가 되는 간섭부분 중에서 개구부로 제거되는 단면 대신 나머지 슬래브 부분을 철근으로 보강할 것이 아니라 수직방향으로 두꺼운 리브가 형성되게 하면 벽보의 두께 중 점선으로 표시한 사선부분을 통하여 자연스럽게 바닥판으로 수압과 토압을 전달하게 된다. 벽보는 TSC 보(60)를 사용한다.As the steel beam to support the slab slab as shown in Figure 9 instead of the general H-shaped steel 'TSC beam fold the upper flange inward' (patent registration 10-0872959), the outer appearance of the beam is U-shaped, so as to fill the concrete inside It has a cross section of the same shape as the reinforced concrete beam. Therefore, instead of reinforcing the remaining slab portion with reinforcing bars instead of the cross section removed through the opening among the interfering parts that transmit the earth pressure and water pressure transmitted from the CIP to the floor slab, if a thick rib is formed in the vertical direction, Through the marked diagonal line, the water pressure and earth pressure are naturally transmitted to the bottom plate. The wall uses the TSC beam 60.

CIP는 천공 장비로 굴착한 구멍에 현장 콘크리트를 부어 넣은 것이어서 TSC 보와 정확하게 평행하기를 기대할 수 없다. 즉 지하외벽(30)의 두께가 부위별로 각각 다르며, CIP와 TSC 보 사이 지하외벽이 들어설 자리에 끼워 넣는 리브의 길이가 각각 달라진다. 이를 공사 현장에서 하나하나 측정해서 맞춤 제작하는 것은 공사 기간 지연의 원인이 되므로 도 2d와 같이 A, B 한 쌍의 얇은 강판을 U형으로 접어 채널을 제작하되 B의 외곽 크기는 A의 내부 치수와 맞게 성형하여 B를 A에 끼워 넣어 길이 방향으로 미끄러지게 하여 이를 리브용 영구거푸집으로 사용한다. 리브용 영구거푸집은 미끄럼 골거푸집(SCF)으로 한다.The CIP is the pouring of on-site concrete into the holes excavated with drilling equipment, so it cannot be expected to be exactly parallel to the TSC beams. That is, the thickness of the basement outer wall 30 is different for each part, and the length of the rib to be inserted into the place where the basement outer wall between the CIP and TSC beam will enter. Since measuring one by one at the construction site and making a customized one causes a delay in the construction period, as shown in FIG. 2d, a pair of thin steel sheets A and B can be folded into a U-shaped channel, but the outer size of B is equal to the inner dimension of A. Molded to fit B into A to slide it in the longitudinal direction and use it as a permanent mold for ribs. Permanent formwork for ribs is to be sliding rib formwork (SCF).

지하외벽(30)이 능히 큰 연직하중을 지지할 수 있어서 벽보 밑의 기둥을 생략하고 직접 합벽에 지지시키는 경우가 많다. 그런데 합벽을 후시공 하려면 그 때까지 벽보(60)를 지지하는 별도 조치가 필요하며 도 2의 3각브라켓(80)이 그것이 다. 이는 흙막이 H파일(20)에 수직으로 용접한 띠강판에 볼트접합 했다가 바닥 콘크리트 양생이 끝난 후 회수하여 재활용할 수도 있다. 그러나 바닥콘크리트 양생이 끝났다고 해도 개구부를 제외한 리브가 임시로 바닥 연직하중을 CIP에 지지시키는 것은 무리여서 바닥 콘크리트를 붓기 전에 경사버팀재인 밀대를 별도로 추가한다. 3각브라켓은 바닥 슬래브(40)의 콘크리트가 적어도 7일 강도를 발현된 후에 회수하여 재활용이 가능하다.Since the basement outer wall 30 can support large vertical loads, the pillars under the beams are often omitted and directly supported on the plywood walls. By the way, after the construction of the plywood is necessary until the separate measures to support the wall 60, the triangular bracket 80 of Figure 2 is it. This may be bolted to the band steel plate welded vertically to the soil pile H pile 20, and then recovered and recycled after the completion of the bottom concrete curing. However, even if the floor concrete curing is finished, it is impossible for the ribs except the opening to temporarily support the vertical vertical load on the CIP, so that a tilting rod, which is a slope support material, is added separately before pouring the floor concrete. The triangular bracket can be recovered by recycling the concrete of the floor slab 40 after at least 7 days of strength.

CIP에서 전달되는 횡력을 바닥판에 전달하는 리브를 마련하면 공사 방법이 간단하고, 인건비가 많이 드는 잡다한 작업이 생략되어 공사기간과 공사비가 절감된다. 가설 흙막이벽과 바닥판 사이의 가설 개구부 크기가 커서 합벽 시공이 쉽고 하향공법 중 필요한 환기, 채광용으로 활용하기에 편하다.The provision of ribs to transfer the lateral force transmitted from the CIP to the floorboards simplifies the construction method and eliminates the labor-intensive miscellaneous work, thus reducing the construction period and construction cost. It is easy to install the plywood wall because of the large size of the temporary opening between the temporary wall and the bottom plate, and it is convenient to use for ventilation and mining necessary during the down-construction method.

합벽 시공기간 중 바닥하중을 지탱할 3각브라켓은 재활용할 수도 있으므로 공사비가 절감된다. 밀대는 단일 ㄱ형강이며 리브 직하에 배치하므로 합벽 배근과 콘크리트를 붓는데 아무런 지장을 주지 않는다.Triangular brackets that will support the floor load during the construction of the plywood can be recycled, reducing construction costs. The push rod is a single a-beam and placed directly under the ribs, so it does not interfere with pouring the plywood and concrete.

재래식 방법으로 흙막이공사를 수행하고, 흙막이공사 중 주열식 흙막이공법(CIP 공법)으로 지반을 굴착하고, 여기에 H형강 또는 철근망을 삽입한다. 또한 건물 내부 기둥위치에 동일한 방법으로 시공하여 기둥을 설치하고, 하향공법으로 한 층씩 굴토한다. 각 층별로 굴토 중 도 2와 같이 CIP에 H파일(20)이 매입된 부분을 골라 콘크리트를 제거하여 H형강 플랜지를 노출시키고, 볼트구멍을 뚫은 브라켓부 착 띠강판(82)을 용접 후 볼트와 너트로 3각브라켓(80)을 조립한다. 이 때 3각브라켓의 ㄱ형강 규격은 2L-90×90×10이다.The earthquake works are performed by the conventional method, and the soil is excavated by the heat-stacking earthquake method (CIP method) during the earthwork, and the H-beam or reinforcing bar is inserted therein. In addition, the pillars should be installed in the same way as the pillars inside the building, and one layer will be excavated by the downward method. Select the part of the pile piled with H pile 20 in the CIP for each layer as shown in Fig. 2 to remove the concrete to expose the H-shaped steel flange, and weld the bracket-mounted strip steel plate 82 with the bolt holes, and then Assemble the triangular bracket (80) with a nut. At this time, the a-beam specification of the triangular bracket is 2L-90 × 90 × 10.

중간기둥(100)과 3각브라켓(80)에 슬래브용 철골 보를 조립한다. 철골 보는 H형강과 TSC 보, 비대칭 H형강 등 기존 제품을 적용한다. 3각브라켓을 부착하는 간격은 CIP 간격에 따라 2m 이내를 표준으로 하며, CIP 설계도와 구조계산으로 정한다. 도 9와 같이 합벽에 면한 TSC 보(벽보)는 합벽 내면에 철근 피복두께(4cm 정도) 걸치도록 배치시켜 합벽 공사가 끝나면 벽보(60)의 하중이 합벽에 원활히 전달되도록 한다.Assemble the steel beam for the slab to the intermediate column 100 and the triangular bracket (80). Steel beams are applied to existing products such as H-beams, TSC beams, and asymmetric H-beams. The spacing for attaching the triangular bracket is 2m or less according to the CIP spacing, and it is determined by the CIP blueprint and structural calculation. As shown in FIG. 9, the TSC beams (wall beams) facing the plywood wall are arranged to have a reinforcing coating thickness (about 4 cm) on the inner surface of the plywood wall so that the load of the wall beam 60 is smoothly transmitted to the plywood wall when the plywood construction is completed.

도 2와 같이 CIP 내측면에 미끄럼 골거푸집(이하 SCF)을 지지할 ㄱ형강(L-60×60×6)을 셋트앙카(Set Anchor)로 부착하고, 브라켓부착 띠강판(82)과 TSC 보의 합벽측 SCF(70)를 지지할 레벨에 맞춰서 대각선으로 밀대(90)를 용접한다. 밀대는 L-90×90×10 정도의 것이 적당하며 TSC 보와 만나는 상단측에는 L-125×75×7을 길이 150mm 정도로 잘라 용접한 것으로 한다. SCF를 지지할 ㄱ형강과 밀대의 상단에 용접한 150mm ㄱ형강 토막에 SCF를 얹는다.As shown in FIG. 2, the a-beam (L-60 × 60 × 6) to support the sliding rib form (hereinafter referred to as SCF) is attached to the inner surface of the CIP with a set anchor, and the bracket-attached band steel plate 82 and the TSC beam The push rod 90 is welded diagonally in accordance with the level to support the SCF 70 of the wall. The rod should be about L-90 × 90 × 10, and the L-125 × 75 × 7 should be cut to 150mm in length on the upper side where it meets the TSC beam. The SCF is placed on a 150 mm A piece welded to the top of the a-beam and the push rod to support the SCF.

SCF는 도 2b, 2c, 2d와 같은 Sliding Channel Form으로 A, B 한 쌍의 얇은 강판을 U형으로 접어 채널을 제작하되 B의 외곽 크기는 A의 내부 치수와 맞게 성형하여 B를 A에 끼워 넣어 길이 방향으로 미끄러지게 하여 이를 영구거푸집으로 사용한다. 그러므로 A는 외부채널(75), B는 내부채널(76)에 해당한다. 또한 SCF의 재질은 강판 이외에 콘크리트 패널, 각형강관 등으로 할 수 있다. SCF의 높이는 바닥 슬래브 두께의 1.5배 이상으로 하고 폭은 20cm 내외로 하며, SCF의 개수는 작용하 는 토압 및 수압의 수평력에 비례한다.SCF is a sliding channel form as shown in Figures 2b, 2c, 2d to form a channel by folding a pair of thin steel plates A, B in U shape, but the outer size of B is molded according to the internal dimensions of A to insert B into A It slides in the longitudinal direction and is used as permanent formwork. Therefore, A corresponds to the external channel 75, B corresponds to the internal channel 76. In addition, the SCF may be made of a concrete panel, a square steel pipe, or the like in addition to a steel sheet. The height of the SCF is not less than 1.5 times the thickness of the floor slab and the width is about 20cm. The number of SCFs is proportional to the horizontal force of the applied earth pressure and water pressure.

도 3d에서 A의 좌우 웨브 내면에는 상부에서 슬래브 두께만큼 아래에 철근토막 걸이쇠(71)를 용접하여 보에 걸쳐 용접한다. 도 3에서 A의 길이는 CIP와 철골 보의 간격 중 가장 좁은 폭보다 크지 않으면서 가깝게 하고 B는 당해 공사 현장에서 CIP와 철골 보 사이 간격 중 가장 넓은 폭에서 가장 좁은 폭을 뺀 값 보다 15cm 정도 더 길게 재단하여 제작한다. B를 A에 끼워 한 쪽 단부를 CIP로 밀어 밀착시켜 앞의 ㄱ형강 위에 고정시키되 사전에 CIP와 만나는 B의 플랜지가 CIP의 주열말뚝 외형 원호와 일치하도록 원호로 재단한다.In FIG. 3D, the left and right web inner surfaces of A are welded across the beam by welding the reinforcing bar latches 71 below the slab thickness from the top. In Figure 3, the length of A is closer than the narrowest of the gap between the CIP and the steel beams, and B is 15 cm more than the narrowest width minus the narrowest width of the gap between the CIP and the steel beams at the construction site. Make a long cut. Insert B into A and push one end to CIP to fix it on the front a-beam, and cut it with an arc so that the flange of B, which meets CIP in advance, coincides with the outer arc of the main pile pile of CIP.

도 3에서 보는 바와 같이 바닥 슬래브와 SCF 내에 콘크리트를 부어 넣으려면 TSC 보(60)의 내단면에 슬래브 두께만큼 거푸집으로 막아야 하므로 SCF에 걸쳐 와이어메쉬(72)를 세워서 배열한 슬래브 쪽에 메탈라스(73)를 붙여 콘크리트가 합벽쪽으로 새지 않고 후에 합벽 콘크리트와 부착이 용이하게 한다. 이때 필요하면 메탈라스와 와이어메쉬를 관통하여 철근을 배근할 수도 있으며 SCF 단부의 와이어메쉬에는 메탈라스를 붙이지 않는다. SCF의 간격은 지하실 층수가 더해감에 따라 좁아져서 매 CIP(보통 직경 50cm)마다 설치해야 할 경우도 있으며 1층 가까이에서는 CIP 중 H형강을 매입한 곳에만 설치할 수도 있는데 이는 구조계산으로 정한다. SCF 안과 기타 부분의 개구부 주변은 필요한 철근을 배근하고, 재래식 방법으로 설치한 트러스덱(도면 표시 생략)에 바닥 콘크리트를 부어 넣는다.As shown in Figure 3, to pour concrete into the floor slab and the SCF, the inner surface of the TSC beam 60 must be blocked with a form of slab as much as the slab thickness, so the metal mesh (73) on the side of the slab arranged by standing wire mesh 72 over the SCF. ) So that the concrete does not leak toward the wall and is easy to attach with the wall later. At this time, if necessary, reinforcing steel can be penetrated through metal lath and wire mesh, and metal lath is not attached to wire mesh at the end of SCF. The distance between the SCFs becomes narrower as the number of basements increases, so it may be necessary to install every CIP (usually 50cm in diameter). Inside the SCF and around the openings in the other parts, reinforce the required reinforcing bars and pour the floor concrete into the truss deck (not shown) installed in the conventional way.

바닥슬래브 콘크리트를 부어 넣을 때 TSC 보 내부에도 콘크리트가 쉽게 흘러 들어가지만 SCF는 폭이 좁으므로 조심스럽게 콘크리트를 채워야 한다. 하부 층 굴 토를 시작하고 상부 바닥 콘크리트의 강도가 7일 강도에 도달하면 3각브라켓(80)을 회수하여 다음 층 공사에 재활용할 수 있다. 기초공사를 완료하면 합벽 단면 중에서 층마다 SCF로 막힌 부분을 제외한 열린 공간에 합벽 배근을 하고 상향 공법으로 지하외벽(30)을 시공할 수 있다. 지하외벽은 H 파일에 용접한 브라켓부착 띠강판(82)의 볼트구멍에 철근 토막을 삽입하여 합벽 쪽으로 구부려 주면, H파일과 합벽을 합성으로 설계하여 합벽 단면을 줄일 수 있다. 이 공법은 별도로 특허 출원 중이다(가설흙막이 벽을 지하외벽의 일부로 영구 사용하는 합성 외벽공법 10-2007-0132010).When pouring the floor slab concrete, the concrete flows easily inside the TSC beam, but the SCF is narrow and must be filled carefully. When the lower floor oyster begins to stiffen and the strength of the upper floor concrete reaches 7 days of strength, the triangular bracket 80 can be recovered and recycled in the next floor construction. When the foundation work is completed, the plywood wall is reinforced in the open space except for the SCF block in each floor of the plywood section, and the underground outer wall 30 can be constructed by the upward method. When the basement outer wall is inserted into the bolt hole of the bracket-attached strip steel plate 82 welded to the H pile and bent toward the plywood wall, the H ply and the plywood wall are synthetically designed to reduce the ply wall cross section. This method is a separate patent pending (synthetic outer wall method 10-2007-0132010, which permanently uses the temporary mud wall as part of the basement outer wall).

도 1은 미끄럼 골거푸집(SCF)을 활용한 지하실 하향공법 평면도,1 is a plan view of the basement downward method using a sliding rib form (SCF),

도 2는 CIP, SCF, 밀대, 벽보 및 3각브라켓을 동시에 나타낸 합벽 단면도,2 is a sectional view of the plywood simultaneously showing the CIP, SCF, tack, wall and triangular bracket,

도 2a~도 2f는 합벽단면도의 부분상세도,2A to 2F are partial detail views of a sectional view of a sump wall,

도 3은 CIP, SCF, 합벽 구간 및 TSC 보(벽보)를 동시에 나타낸 부분 평면도,3 is a partial plan view simultaneously showing the CIP, SCF, plywood section and TSC beams (walls);

도 3a~도 3d는 SCF와 지하외벽의 부분상세도,3a to 3d are partial details of the SCF and the basement outer wall,

도 4는 재래식 합벽 하향공법 평면도,4 is a plan view of a conventional plywood downward method;

도 5는 위 4도의 단면도,5 is a cross-sectional view of the upper 4 degrees,

도 6은 위 4, 5도의 부분 상세도,6 is a partial detailed view of the above 4, 5 degrees,

도 7은 지하실 하향공법에서 초기 합벽 공법의 부분 단면도,7 is a partial cross-sectional view of the initial plywood method in the basement downhole method,

도 7a는 기초콘크리트 타설 후 지하와 지상 동시 공사에 대한 부분 단면도7a is a partial cross-sectional view of the simultaneous construction of underground and ground after foundation concrete

도 7b는 지하외벽과 철골보의 접합부인 스펜드럴 거더의 상세도Figure 7b is a detailed view of the suspended girder, the junction of the basement outer wall and cheolgolbo

도 8은 지하실 가설 흙막이벽과 바닥판의 일반적인 하중전달경로 설명도,8 is an explanatory diagram of a general load transfer path of a basement temporary wall and a base plate;

도 9는 본 발명의 지하실 가설 흙막이벽과 바닥판의 하중전달경로 설명도이다.9 is an explanatory view of the load transfer path of the basement temporary wall and the base plate of the present invention.

<도면의 부호에 대한 간단한 설명><Brief description of the symbols in the drawings>

10 ; CIP(주열식 흙막이공법) 20 ; H파일10; CIP (Soil Crushing Method) 20; H file

30 ; 지하외벽(합벽) 40 ; 슬래브(바닥판)30; Underground outer wall (plywood) 40; Slab (bottom plate)

42 ; 트러스데크 50 ; 철골 보42; Truss deck 50; Steel frame

60 ; TSC 보(벽보)60; TSC beams

70 ; 미끄럼 골거푸집(SCF) 71 ; 걸이쇠70; Sliding rib form (SCF) 71; Hook

72 ; 와이어메쉬 73 ; 메탈라스72; Wire mesh 73; Metal lath

75 ; 외부채널 76 ; 내부채널75; External channel 76; Internal channel

80 ; 3각브라켓 82 ; 브라켓부착 띠강판80; Triangular bracket 82; Steel strip with bracket

90 ; 밀대 100 ; 중간기둥90; Straw 100; Middle column

Claims (4)

1층 바닥 공사 → 지하1층 굴토 → 지하1층 바닥 공사 → 지하2층 굴토 → 지하2층 바닥 공사 등의 순서로 바닥 공사는 하층보다 상층 바닥부터 먼저 시공하는 역타공법을 적용하면서도 지하실 외벽(30)공사는 최하층 외벽에서 시작하여 지하1층 외벽까지 순차적인 상향공사를 시행하기 위한 공법에 있어서;Floor construction works in the order of 1st floor construction → 1st basement floor → 1st basement floor construction → 2nd floor underground construction → 2nd basement floor construction. ) The construction is a method for the sequential upward construction starting from the outermost outer wall to the outer one of the basement floor; a) 지반을 천공한 구멍에 H형강 또는 철근망을 삽입하여 CIP(10)공사를 수행하는 단계;a) inserting an H-beam or reinforcing bar into a hole drilled into the ground to perform a CIP (10) construction; b) 1층 바닥 공사를 위하여 CIP에 매입된 H파일(20)의 건물 내측 플렌지가 노출되도록 콘크리트 피복을 제거하고, 노출길이는 1층 TSC 보(60) 하부에서부터 3각브라켓(80)을 고정하기에 충분한 여유공간으로 하며;b) The concrete cover is removed so that the inner flange of the building of the H pile 20 embedded in the CIP is exposed for the ground floor construction, and the exposure length fixes the triangular bracket 80 from the lower part of the TSC beam 60 on the first floor. Sufficient free space for; c) 상기 H파일 플렌지에 1층용 3각브라켓을 접합하고 상기 3각브라켓의 단부인 건물내측에 1층 TSC 보(60)를 설치하며, 1층용 3각브라켓의 브라켓부착 띠강판(82)과 1층 TSC 보 상단부 사이에 1층용 밀대(90)를 사선방향으로 고정하여 1층 TSC 보를 고정시키는 단계;c) bonding the triangular bracket for the first floor to the H-pile flange, and installing the first-floor TSC beam 60 inside the building, which is the end of the triangular bracket, and with the bracket steel strip 82 of the triangular bracket for the first floor. Fixing the first floor TSC beam in an oblique direction between the first floor TSC beam upper ends; d) 상기 1층 TSC 보는 지하외벽(30) 두께에서 피복두께만큼 감소한 거리를 띄워 거치하고 1층 TSC 보 상부에 1층 슬래브(40)가 설치되도록 하는 단계;d) mounting the first floor slab 40 above the first floor TSC beam with a distance reduced from the thickness of the basement outer wall 30 by the coating thickness; e) 1층 TSC 보와 CIP 사이에 1층 미끄럼 골거푸집(70)을 설치하고, 1층 미끄럼 골거푸집 하부인 CIP와 1층 TSC 보 양측 단부에 1층용 ㄱ형강을 설치하여 1층 미끄럼 골거푸집을 지지하는 단계;e) 1st floor sliding formwork 70 is installed between 1st floor TSC beam and CIP, 1st floor sliding formwork is installed at both ends of CIP and 1st floor TSC beam at the bottom of 1st floor sliding formwork. Supporting the step; f) 상기 b) - e)과정이 종료된 1층 슬래브(40)와 1층 미끄럼 골거푸집(70) 내부에 콘크리트를 타설하고 나서, 지하1층을 굴토하는 단계;f) pouring concrete into the first-floor slab 40 and the first-floor sliding mold form 70 after the process b) -e) is completed, and then excavating the first-basement floor; g) 상기 b) - f)의 각 단계를 지하1층에서도 반복하여 지하1층 슬래브공사를 수행하고, 같은 방법으로 최하층 천장 슬래브까지 순차적으로 하향공사를 진행한 후, 기초공사를 수행하는 단계;g) performing the first-floor slab construction by repeating each step of b) -f) in the first-floor basement, and sequentially performing the downward construction to the lowest floor ceiling slab in the same manner, and then performing the foundation work; h)기초공사가 종료되면 최하층의 지하외벽 중 미끄럼 골거푸집을 제외한 열린 공간에 지하외벽(30) 철근을 배근하고 콘크리트를 타설하여 1층바닥까지 단계적으로 상향공사를 하는 단계;h) when the foundation work is completed, reinforcement of the reinforcement of the basement outer wall (30) in the open space except the sliding corrugated form among the basement walls of the lowermost floor and pouring concrete step by step up to the ground floor; 를 포함하는 것을 특징으로 하는 미끄럼 골거푸집을 활용한 지하실 하향공법.Basement downhole method using a sliding rib form, characterized in that it comprises a. 제1항에 있어서,The method of claim 1, 3각브라켓(80)은 CIP에 매입된 H파일(20)에 접합하는 브라켓부착 띠강판(82)과 여기에 수직으로 붙은 수평재, 수평재와 브라켓부착 띠강판 사이의 사재로 구성되며 ;The triangular bracket 80 is composed of a band between the bracket with a steel strip 82 to be bonded to the H pile 20 embedded in the CIP and a horizontal member attached to it vertically, a horizontal member and a band with a bracket steel sheet; 상기 H파일에 용접접합된 브라켓부착 띠강판은 양측면에 설치된 ㄱ형강을 볼트접합으로 고정하고 ; 및The bracket-attached band steel plate welded to the H-file is fixed to the a-beams installed on both sides with bolted joints; And TSC보와 슬래브(40) 및 미끄럼 골거푸집(70), 벽보(60)에 콘크리트를 타설하여 미끄럼 골거푸집과 벽보가 콘크리트와 합성작용으로 토압과 수직하중에 대한 저항성능(일반적으로 7일 이상)을 확보한 이후 3각브라켓을 회수하여 재사용하는 것도 가능한 것을 특징으로 하는 미끄럼 골거푸집을 활용한 지하실 하향공법Concrete is installed in TSC beams, slabs (40), sliding corrugated formwork (70), and wall (60) so that the sliding corrugated formwork and corrugate are combined with concrete to resist earth pressure and vertical load (generally 7 days or more). After securing the triangular bracket, it is also possible to recover the basement by using the sliding groove form 제1항에 있어서,The method of claim 1, 미끄럼 골거푸집(70)은 두 개의 강판을 U형으로 제작하여, 외부채널(75)과 내부채널(76)로 구성하고 ;The sliding rib formwork 70 is made of two steel plates in a U shape, and constitutes an outer channel 75 and an inner channel 76; 상기 외부채널은 TSC 보(60) 쪽에 오고, 내부채널은 외부채널 안에 겹쳐 CIP에 밀착하되 단부는 원형으로 제작하며 ; 및The outer channel comes to the TSC beam 60, the inner channel overlaps the outer channel and closely adheres to the CIP, but the end is manufactured in a circular shape; And 외부채널이 내부채널 보다 더 길고, 미끄럼 골거푸집의 춤은 해당층 슬래브 보다 두껍도록 하며 ;The outer channel is longer than the inner channel, and the sliding die dances thicker than the slab on the floor; 상기 TSC 보와 미끄럼 골거푸집이 만나는 TSC 보 상부플랜지에 걸이쇠(71)를 미끄럼 골거푸집 안쪽으로 양면에 용접하고 ;Welding the clasp 71 to both sides of the sliding ribs in the upper flange of the TSC beam where the TSC beams and the sliding ribs meet; 상기 걸이쇠 위에는 와이어메쉬(72)와 메탈라스(73)를 배치하는 것을 특징으로 하는 미끄럼 골거푸집을 활용한 지하실 하향공법The basement downward method using a sliding rib form, characterized in that the wire mesh 72 and the metal lath 73 is disposed on the hook. 제1항 또는 제3항에 있어서,The method according to claim 1 or 3, 미끄럼 골거푸집은 CIP에 작용하는 수평력에 비례하여 개소를 정하고, 재질은 강판 또는 콘크리트 패널, 각파이프 등으로 하며 ; 및Sliding rib form is determined in proportion to the horizontal force acting on the CIP, the material is made of steel sheet or concrete panel, square pipe or the like; And 상기 미끄럼 골거푸집 주변의 개구부에 벽체용 수직 철근을 배근하는 것을 특징으로 하는 미끄럼 골거푸집을 활용한 지하실 하향공법Basement downhole method using the sliding ribs, characterized in that the vertical reinforcement for the wall is placed in the opening around the sliding ribs
KR1020090062000A 2009-07-08 2009-07-08 Downward Construction Method of Basement applying SCFSliding Channel Form KR101148272B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090062000A KR101148272B1 (en) 2009-07-08 2009-07-08 Downward Construction Method of Basement applying SCFSliding Channel Form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090062000A KR101148272B1 (en) 2009-07-08 2009-07-08 Downward Construction Method of Basement applying SCFSliding Channel Form

Publications (2)

Publication Number Publication Date
KR20110004541A KR20110004541A (en) 2011-01-14
KR101148272B1 true KR101148272B1 (en) 2012-07-09

Family

ID=43611989

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090062000A KR101148272B1 (en) 2009-07-08 2009-07-08 Downward Construction Method of Basement applying SCFSliding Channel Form

Country Status (1)

Country Link
KR (1) KR101148272B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797637A (en) * 2017-04-26 2018-11-13 杭州南联土木工程科技有限公司 Prefabricated board combined cast-in-situ concrete considers the underground pipe gallery construction method of structure and ground

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2653911B1 (en) 2010-10-28 2016-04-27 LG Electronics, Inc. Display apparatus
US8416361B2 (en) 2011-01-12 2013-04-09 Lg Electronics Inc. Display apparatus
KR101726836B1 (en) * 2014-08-22 2017-04-14 이기환 Reinforcement member and reinforcement structure for wale using the same
KR101880014B1 (en) * 2018-01-27 2018-07-18 양병진 Variable filler for supporting column-type wall
CN109025281A (en) * 2018-05-30 2018-12-18 中建三局第三建设工程有限责任公司 A kind of construction system and method suitable for business superelevation super-span Atrium Structure
CN114908797B (en) * 2022-04-29 2024-01-30 中国建筑第五工程局有限公司 Construction method for underground room of dangerous old building

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100694762B1 (en) 2004-09-11 2007-03-14 (주)엠씨에스공법 Method for constructing underground slabs and walls without preliminary wall-attached supports
KR100767953B1 (en) 2005-09-27 2007-10-17 이창남 Separating method of Monowall with spandrel girders

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100694762B1 (en) 2004-09-11 2007-03-14 (주)엠씨에스공법 Method for constructing underground slabs and walls without preliminary wall-attached supports
KR100767953B1 (en) 2005-09-27 2007-10-17 이창남 Separating method of Monowall with spandrel girders

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797637A (en) * 2017-04-26 2018-11-13 杭州南联土木工程科技有限公司 Prefabricated board combined cast-in-situ concrete considers the underground pipe gallery construction method of structure and ground

Also Published As

Publication number Publication date
KR20110004541A (en) 2011-01-14

Similar Documents

Publication Publication Date Title
KR100951097B1 (en) Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR101148272B1 (en) Downward Construction Method of Basement applying SCFSliding Channel Form
KR101274974B1 (en) Earth retaining wall and construction method thereof
KR100927344B1 (en) Construction method for connecting underground structure and underground structure using connection structure for underground construction
KR100982827B1 (en) Construction method of basement exterior wall applying the floor slab as the strut against the earth pressure from the temporary earth wall = TSW(Thrusting slabbed wall) method
KR101344063B1 (en) The construction method of steel-concrete underpass
KR102208793B1 (en) Under ground structure using column wall and construction method thereof
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
KR101687495B1 (en) Partial top-down construction method for building underground structures
KR20090094971A (en) Under ground top-down method
KR20090114863A (en) Parallelly connected iron tube and construction method for underground structure using the same
JP4881555B2 (en) Construction method of underground structure
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR101182704B1 (en) Construction method of undergroud structure using PHC pile
KR101051978B1 (en) Basement structure construction method using PC member
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR100383268B1 (en) method for underground construction of building by using permanent structural member as strut for support retaining wall
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR101631447B1 (en) Top-Down method of underground structure using the CFT and the Composite Beam
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR200370107Y1 (en) Forms for edge girder construction
KR20090043625A (en) Method for constructing underground slabs using asymmetric girder
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
KR100640244B1 (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
KR102482690B1 (en) Bridge foundation construction method using formwork integrated PC panels

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150430

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160510

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee