JP5007108B2 - How to make a steel structure - Google Patents

How to make a steel structure Download PDF

Info

Publication number
JP5007108B2
JP5007108B2 JP2006326871A JP2006326871A JP5007108B2 JP 5007108 B2 JP5007108 B2 JP 5007108B2 JP 2006326871 A JP2006326871 A JP 2006326871A JP 2006326871 A JP2006326871 A JP 2006326871A JP 5007108 B2 JP5007108 B2 JP 5007108B2
Authority
JP
Japan
Prior art keywords
steel
steel pipe
solid
steel material
solid steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2006326871A
Other languages
Japanese (ja)
Other versions
JP2008038586A (en
Inventor
昌克 内田
俊二 岩郷
速雄 岩郷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Arcreate KK
Original Assignee
Arcreate KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Arcreate KK filed Critical Arcreate KK
Priority to JP2006326871A priority Critical patent/JP5007108B2/en
Publication of JP2008038586A publication Critical patent/JP2008038586A/en
Application granted granted Critical
Publication of JP5007108B2 publication Critical patent/JP5007108B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Joining Of Building Structures In Genera (AREA)

Description

本発明は、鉄骨建築の上部構造物とその土木基礎構造物の接点を高強度で精度良く製作する方法に関するものである。 The present invention relates to how you manufacture accurately contacts superstructure and its civil substructure of the steel construction with high strength.

鉄骨建築は、図1に示すように、通常は角形鋼管・丸形鋼管・H形鋼による柱1とH形鋼による梁2からなっており、該柱と梁の接合部は仕口であり、図2に示すように、角形鋼管を使った柱1の場合、仕口部3はダイアフラム5と柱短管6の部品から構成され溶接7により製作され、該仕口部と柱1と梁2が溶接7で接合されている。   As shown in Fig. 1, a steel building is usually composed of a square steel pipe, a round steel pipe, a pillar 1 made of H-shaped steel and a beam 2 made of H-shaped steel, and the joint between the pillar and the beam is a joint. As shown in FIG. 2, in the case of a column 1 using a square steel pipe, the joint portion 3 is composed of parts of a diaphragm 5 and a short column tube 6 and is manufactured by welding 7, and the joint portion, the column 1 and the beam are formed. 2 are joined by welding 7.

鉄骨建築構造を支えているのが、図1で示す基礎4である。この基礎4は、独立基礎、一つの基礎で2本以上の柱を支える複合基礎、フーチングを連続して形成する布基礎がある。これらの基礎を作ってから柱1を基礎に接続して、建築物と基礎とが一体になるのである。   The foundation 4 shown in FIG. 1 supports the steel building structure. The foundation 4 includes an independent foundation, a composite foundation that supports two or more pillars with one foundation, and a fabric foundation that continuously forms footings. After these foundations are made, the pillar 1 is connected to the foundation, and the building and the foundation are united.

図4に、従来の独立基礎の上に構築した鉄骨建築模式図を示す。建築は、大略柱1,梁2、接合部即ち仕口部3からなっており、柱1を支持する基礎柱又は杭8を設置する地盤9を所定深さまで掘削して所定形状の穴を形成させ、穴の所に所定形状の型枠を製作して、コンクリート10を打設して、1週間ほどの養生期間を得て、固まらせる。また、水平材の基礎梁11で基礎間を連結し、建物全体の剛性を上げて不同沈下を押さえているのである。   FIG. 4 shows a schematic view of a steel building constructed on a conventional independent foundation. The building is generally composed of pillars 1, beams 2, and joints or joints 3. The foundation 9 that supports the pillars 1 or the ground 9 on which the piles 8 are installed is excavated to a prescribed depth to form holes of a prescribed shape. Then, a mold having a predetermined shape is produced at the hole, and the concrete 10 is placed, and a curing period of about one week is obtained and solidified. Moreover, the foundation beams 11 of horizontal members are used to connect the foundations to increase the rigidity of the entire building, thereby suppressing uneven settlement.

特願平9−348841(特開平11−181790号公報:引用文献1)の例を示す。図5に、従来型の基礎を改良した杭柱一体型工法の模式図を示す。該工法では、従来のような基礎は使わず、先端につけたスクリュー19で地盤9に鋼管杭18をねじ込んで、該鋼管杭18の地表部分で適当な寸法に上部を切断して一定の高さを確保して杭フランジ16を溶接して、該杭フランジ16と柱ベースプレート12とをスペーサ17を挟んでボルト15とナット14で固定する。 An example of Japanese Patent Application No. 9-348841 (Japanese Patent Laid-Open No. 11-181790: Cited Reference 1) is shown. In FIG. 5, the schematic diagram of the pile pillar integrated construction method which improved the foundation of the conventional type is shown. In this construction method, a conventional foundation is not used, and a steel pipe pile 18 is screwed into the ground 9 with a screw 19 attached to the tip, and the upper portion is cut to an appropriate dimension at the surface portion of the steel pipe pile 18 to a certain height. The pile flange 16 is welded, and the pile flange 16 and the column base plate 12 are fixed with bolts 15 and nuts 14 with a spacer 17 interposed therebetween.

特願2002−052860(特開2003−253758号公報:引用文献2)の例を示す。図3に、柱梁接合部を圧延鋼板等から採取した中実のサイコロ17に柱1及び梁2を溶接接合させるもので、図2に示すような複雑な構造をしていない。
特開平11−181790号公報 特開2003−253758号公報
An example of Japanese Patent Application No. 2002-052860 (Japanese Patent Laid-Open No. 2003-253758 : Cited Reference 2) will be shown. In FIG. 3, the column 1 and the beam 2 are welded and joined to a solid dice 17 whose column-beam joint is taken from a rolled steel plate or the like, and does not have a complicated structure as shown in FIG.
Japanese Patent Laid-Open No. 11-181790 JP 2003-253758 A

従来の基礎工事には、特許文献1にも記述があるように次のような問題がある。
(1)地盤を深く広く掘削する必要があり、掘削の作業量が大きく、残土が大量に出て、その処理に、費用と手間が掛かる。また、振動・騒音・砂埃が発生して環境問題が発生する恐れがある。
(2)コンクリート打設の手間と養生の期間が必要である。
(3)大きなフーチングと基礎梁と広い基礎が必要で、費用と養生期間の問題の他に、狭い箇所での施工が不都合になる場合が多い。
The conventional foundation work has the following problems as described in Patent Document 1.
(1) It is necessary to excavate the ground deeply and extensively, and the amount of excavation work is large, and a large amount of residual soil is produced, which requires cost and labor. In addition, vibration, noise, and dust are generated, which may cause environmental problems.
(2) It takes time for concrete placement and a period of curing .
(3) Large footings, foundation beams, and wide foundations are necessary, and in addition to the problems of cost and curing period, construction in narrow places is often inconvenient.

特許文献1では、次の問題がある。
(1)杭柱接合部の構造は従来の柱梁接合部に比べて構造が複雑である。高さ調整用のスペーサなど調整に手間が掛かる。
(2)柱の水平位置の調整が難しい
(3)杭フランジ部16の大きな剛性と強度を確保するのが難しい。
(4)表層地盤が弱いと単独鋼管杭では柱の曲げ耐力に対し弱い。
Patent Document 1 has the following problems.
(1) The structure of the pile-column joint is more complex than the conventional column-beam joint. It takes time to adjust the height adjustment spacer.
(2) It is difficult to adjust the horizontal position of the pillar .
(3) It is difficult to ensure the large rigidity and strength of the pile flange portion 16.
(4) If the surface ground is weak, the single steel pipe pile is weak against the bending strength of the column.

特許文献2では、次の問題がある。
(1)仕口部の構造が単純で、製作工数も少なく強度も高いが、土木基礎精度に対応した部材間の位置調整ができない。
(2)工場製作には良いが、固定した鋼板等中実鋼材の現場溶接性が悪い。
Patent Document 2 has the following problem.
(1) The structure of the joint is simple, the number of manufacturing steps is small and the strength is high, but the position adjustment between members corresponding to the civil engineering foundation accuracy cannot be performed.
(2) Good for factory production, but poor on-site weldability for solid steel such as fixed steel sheets.

このような諸課題は種々研究した結果、圧延・鍛造又は鋳造による鋼製の中実鋼材を用いて、該中実鋼材の形状及び接合方法を変えることによりこれらの問題が解決できることが明らかとなった。   As a result of various studies, it has become clear that these problems can be solved by changing the shape of the solid steel material and the joining method using a solid steel material produced by rolling, forging or casting. It was.

請求項1に係る発明は、建築鉄骨構造物において、圧延・鍛造又は鋳造による中実鋼材を介在させて、地盤に立設後に所定の高さで切断した複数の鋼管杭と、角形鋼管、丸形鋼管又はH形鋼の鉄骨柱とを建設地において溶接により接合させることにより、鉄骨構造物を製作する方法であって、
前記中実鋼材として、前記各鋼管杭の上端部の外径よりも大きな内径の複数の貫通孔を有する第1中実鋼材と、前記各鋼管杭の上端部の外側に嵌合可能な複数のリング状の第2中実鋼材とを準備する工程と、
地盤に立設後に所定の高さで切断した複数の前記鋼管杭の上端部に、第1中実鋼材を前記各貫通孔を前記各鋼管杭の外側に貫通させて配置する工程と、
各第2中実鋼材を前記各鋼管杭の上端部の外側に嵌合させて第1中実鋼材の上側に配置する工程と、
各第2中実鋼材と前記各鋼管杭とを溶接により固定する工程と、
各第2中実鋼材と第1中実鋼材とを溶接により固定する工程と、
前記鉄骨柱と第1中実鋼材とを溶接により固定する工程と、
を備えていることを特徴とする。
これにより、特許文献1及び特許文献2の諸問題を解決できる。即ち、強度の大きい平らな上面を有する単純な中実鋼材を用いて建設地における溶接接合により、諸問題が解決するのである。
The invention according to claim 1 is an architectural steel frame structure in which a solid steel material by rolling, forging or casting is interposed, and a plurality of steel pipe piles cut at a predetermined height after standing on the ground, a square steel pipe, A method of manufacturing a steel structure by joining a steel pipe or a steel column of H-shaped steel by welding in a construction site,
As the solid steel material, a first solid steel material having a plurality of through holes having an inner diameter larger than the outer diameter of the upper end portion of each steel pipe pile, and a plurality of pieces that can be fitted to the outside of the upper end portion of each steel pipe pile. Preparing a ring-shaped second solid steel material;
A step of disposing the first solid steel material by penetrating the through holes to the outside of the steel pipe piles at the upper ends of the steel pipe piles cut at a predetermined height after standing on the ground; and
Fitting each second solid steel material to the outside of the upper end of each steel pipe pile and placing it on the upper side of the first solid steel material;
Fixing each second solid steel material and each steel pipe pile by welding;
Fixing each second solid steel material and the first solid steel material by welding;
Fixing the steel column and the first solid steel material by welding;
It is characterized by having.
Thereby, the problems of Patent Document 1 and Patent Document 2 can be solved. That is, various problems are solved by welding and joining in a construction site using a simple solid steel material having a flat upper surface with high strength.

請求項2に係る発明は、建築鉄骨構造物において、圧延・鍛造又は鋳造による中実鋼材を介在させて、地盤に立設後に所定の高さで切断した複数の鋼管杭と、角形鋼管、丸形鋼管又はH形鋼の鉄骨柱とを建設地において溶接により接合させることにより、鉄骨構造物を製作する方法であって、
前記中実鋼材として、前記各鋼管杭の上端部の外径よりも大きな内径の複数の貫通孔を有する第1中実鋼材と、前記各鋼管杭の上端部の外側に嵌合可能な複数のリング状の第2中実鋼材とを準備する工程と、
地盤に立設後に所定の高さで切断した複数の前記鋼管杭の上端部に、各第2中実鋼材を前記各鋼管杭の上端部の外側に嵌合させて配置する工程と、
第1中実鋼材を前記各貫通孔を前記各鋼管杭の上側に位置させて各第2中実鋼材の上側に配置する工程と、
各第2中実鋼材と前記各鋼管杭とを溶接により固定する工程と、
各第2中実鋼材と第1中実鋼材とを溶接により固定する工程と、
前記鉄骨柱と第1中実鋼材とを溶接により固定する工程と、
を備えていることを特徴とする。
The invention according to claim 2 is a construction steel frame structure, in which a plurality of steel pipe piles cut at a predetermined height after standing on the ground with a solid steel material by rolling, forging or casting, a square steel pipe, a round A method of manufacturing a steel structure by joining a steel pipe or a steel column of H-shaped steel by welding in a construction site,
As the solid steel material, a first solid steel material having a plurality of through holes having an inner diameter larger than the outer diameter of the upper end portion of each steel pipe pile, and a plurality of pieces that can be fitted to the outside of the upper end portion of each steel pipe pile. Preparing a ring-shaped second solid steel material;
A step of fitting each second solid steel material to the outer side of the upper end of each of the steel pipe piles at the upper end of the plurality of steel pipe piles cut at a predetermined height after standing on the ground; and
Placing the first solid steel material on the upper side of each steel pipe pile with the respective through holes positioned on the upper side of each second steel pipe pile;
Fixing each second solid steel material and each steel pipe pile by welding;
Fixing each second solid steel material and the first solid steel material by welding;
Fixing the steel column and the first solid steel material by welding;
It is characterized by having.

請求項3に係る発明は、建築鉄骨構造物において、圧延・鍛造又は鋳造による中実鋼材を介在させて、地盤に立設後に所定の高さで切断した複数の鋼管杭と、角形鋼管、丸形鋼管又はH形鋼の鉄骨柱とを建設地において溶接により接合させることにより、鉄骨構造物を製作する方法であって、
前記中実鋼材として、前記各鋼管杭うちの1つの前記鋼管杭の上端部の外側に嵌合可能な嵌合孔と他の前記鋼管杭の上端部の外径よりも大きな内径の貫通孔を有する一方の中実鋼材および他方の中実鋼材とを準備する工程と、
地盤に立設後に所定の高さで切断した複数の前記鋼管杭の上端部に、一方の中実鋼材を、1つの前記鋼管杭の上端部の外側に前記嵌合孔を嵌合させる一方、他の前記各鋼管杭の上端部の外側に前記各貫通孔を貫通させかつ他の前記各鋼管杭の上端を一方の中実鋼材の上端よりも上方に突出させて配置する工程と、
他方の中実鋼材を、他の前記各鋼管杭のうちの1つの前記鋼管杭の上端部の外側に前記嵌合孔を嵌合させる一方、その他の前記各鋼管杭の上側に前記各貫通孔を位置させて一方の中実鋼材の上側に配置する工程と、
一方の中実鋼材と1つの前記鋼管杭とを溶接により固定しかつ他方の中実鋼材と他の前記各鋼管杭のうちの1つの前記鋼管杭とを溶接により固定する工程と、
一方の中実鋼材と他方の中実鋼材とを溶接により固定する工程と、
前記鉄骨柱と他方の中実鋼材とを溶接により固定する工程と、
を備えていることを特徴とする
According to a third aspect of the present invention, in a steel structure, a plurality of steel pipe piles cut at a predetermined height after standing on the ground with a solid steel material by rolling / forging or casting, a square steel pipe, a round A method of manufacturing a steel structure by joining a steel pipe or a steel column of H-shaped steel by welding in a construction site,
As the solid steel material, a fitting hole that can be fitted to the outside of the upper end portion of one of the steel pipe piles and a through hole having an inner diameter larger than the outer diameter of the upper end portion of the other steel pipe pile. Preparing one solid steel material and the other solid steel material having,
One solid steel material is fitted to the upper ends of the plurality of steel pipe piles cut at a predetermined height after standing on the ground, while the fitting hole is fitted to the outside of the upper end of one steel pipe pile, A step of penetrating each through hole outside the upper end portion of each other steel pipe pile and projecting the upper end of each other steel pipe pile above the upper end of one solid steel material; and
The other solid steel material is fitted into the fitting hole on the outer side of the upper end portion of one of the other steel pipe piles, while the through holes are formed on the upper side of the other steel pipe piles. And placing it on the upper side of one solid steel material,
Fixing one solid steel material and one steel pipe pile by welding and fixing the other solid steel material and one of the steel pipe piles by welding;
Fixing one solid steel material and the other solid steel material by welding;
Fixing the steel column and the other solid steel material by welding;
It is characterized by having .

請求項4に係る発明は、建築鉄骨構造物において、圧延・鍛造又は鋳造による中実鋼材を介在させて、地盤に立設後に所定の高さで切断した複数の鋼管杭と、角形鋼管、丸形鋼管又はH形鋼の鉄骨柱とを建設地において溶接により接合させることにより、鉄骨構造物を製作する方法であって、
前記中実鋼材として、前記各鋼管杭うちの1つの前記鋼管杭の上端部の外側に嵌合可能な嵌合孔と他の前記鋼管杭の上端部の外径よりも大きな内径の貫通孔を有する一方の中実鋼材と、他の前記各鋼管杭のうちの1つの前記鋼管杭の上端部の外側に嵌合可能な他方の中実鋼材とを準備する工程と、
複数の前記鋼管杭を地盤に立設後に、前記各鋼管杭うちの1つの前記鋼管杭の上端の高さを他の前記鋼管杭の上端の高さよりも低くなるように切断する工程と、
地盤に立設後に切断した複数の前記鋼管杭の上端部に、一方の中実鋼材を、1つの前記鋼管杭の上端部の外側に前記嵌合孔を嵌合させかつ当該鋼管杭の上端を一方の中実鋼材の下端以下に位置させる一方、他の前記各鋼管杭の上端部の外側に前記各貫通孔を貫通させかつ他の前記各鋼管杭の上端を一方の中実鋼材の上端よりも上方に突出させて配置する工程と、
他方の中実鋼材を、他の前記各鋼管杭のうちの1つの前記鋼管杭の上端部の外側に前記嵌合孔を嵌合させて一方の中実鋼材の上側に配置する工程と、
一方の中実鋼材と1つの前記鋼管杭とを溶接により固定しかつ他方の中実鋼材と他の前記各鋼管杭のうちの1つの前記鋼管杭とを溶接により固定する工程と、
一方の中実鋼材と他方の中実鋼材とを溶接により固定する工程と、
前記鉄骨柱と他方の中実鋼材とを溶接により固定する工程と、
を備えていることを特徴とする。
According to a fourth aspect of the present invention, there is provided a steel structure having a plurality of steel pipe piles that are cut at a predetermined height after standing on the ground through a solid steel material by rolling, forging or casting, a square steel pipe, a round A method of manufacturing a steel structure by joining a steel pipe or a steel column of H-shaped steel by welding in a construction site,
As the solid steel material, a fitting hole that can be fitted to the outside of the upper end portion of one of the steel pipe piles and a through hole having an inner diameter larger than the outer diameter of the upper end portion of the other steel pipe pile. Preparing one solid steel material having the other solid steel material that can be fitted to the outside of the upper end portion of one of the other steel pipe piles;
After standing a plurality of the steel pipe piles on the ground, cutting the height of the upper end of one of the steel pipe piles to be lower than the height of the upper ends of the other steel pipe piles;
One solid steel material is fitted to the upper ends of the plurality of steel pipe piles cut after standing on the ground, and the fitting hole is fitted to the outer side of the upper end of one steel pipe pile, and the upper ends of the steel pipe piles are While being positioned below the lower end of one solid steel material, the respective through holes are made to pass outside the upper end portions of the other steel pipe piles, and the upper ends of the other steel pipe piles are made higher than the upper ends of the one solid steel materials. And a step of projecting upward,
Placing the other solid steel material on the upper side of one solid steel material by fitting the fitting hole to the outside of the upper end portion of one of the other steel pipe piles;
Fixing one solid steel material and one steel pipe pile by welding and fixing the other solid steel material and one of the steel pipe piles by welding;
Fixing one solid steel material and the other solid steel material by welding;
Fixing the steel column and the other solid steel material by welding;
It is characterized by having.

請求項5に係る発明は、請求項2から請求項4のいずれか1項に記載の発明において、
第2の中実鋼材、一方の中実鋼材または他方の中実鋼材と前記鋼管とを溶接により固定する際に、
第2の中実鋼材の内周面と前記鋼管杭の上端とをすみ肉溶接するか、または、一方の中実鋼材の前記嵌合孔あるいは他の中実鋼材の前記嵌合孔と前記鋼管杭の上端とをすみ肉溶接するか、または、第2の中実鋼材の内周面と当該内周面の上端よりもその上端を下側に位置させた前記鋼管杭の上端面と当該鋼管杭の上端部の内側に嵌合され当該鋼管杭の上端よりも上側に位置させた鋼板の外周面とにより形成される環状溝を溶接するか、または、一方の中実鋼材の前記嵌合孔あるいは他の中実鋼材の前記嵌合孔の内周面と当該内周面の上端よりもその上端を下側に位置させた前記鋼管杭の上端と当該鋼管杭の上端部の内側に嵌合され当該鋼管杭の上端よりもその上面を上側に位置させた鋼板の外周面とにより形成される環状溝を溶接することを特徴とする。
The invention according to claim 5 is the invention according to any one of claims 2 to 4,
When fixing the second solid steel material, one solid steel material or the other solid steel material and the steel pipe by welding,
Fillet weld the inner peripheral surface of the second solid steel material and the upper end of the steel pipe pile, or the fitting hole of one solid steel material or the fitting hole of the other solid steel material and the steel pipe Fillet weld the upper end of the pile, or the upper end surface of the steel pipe pile and the steel pipe with the upper end located below the inner peripheral surface of the second solid steel material and the upper end of the inner peripheral surface An annular groove formed by the outer peripheral surface of the steel plate that is fitted inside the upper end of the pile and is located above the upper end of the steel pipe pile is welded, or the fitting hole of one solid steel material Or it fits into the inner peripheral surface of the fitting hole of the other solid steel material and the upper end of the steel pipe pile whose upper end is located below the upper end of the inner peripheral surface and the inner side of the upper end portion of the steel pipe pile. Welding the annular groove formed by the outer peripheral surface of the steel plate with its upper surface positioned above the upper end of the steel pipe pile. And butterflies.

請求項6に係る発明は、請求項2または請求項3に記載の発明において、
第2の中実鋼材と第1の中実鋼材とを、または、一方の中実鋼材と他方の中実鋼材とを溶接により固定する際に、
第1の中実鋼材の前記貫通孔の内周面、または、他方の中実鋼材の貫通孔の内周面と前記鋼管杭の上端とをすみ肉溶接することを特徴とする。
The invention according to claim 6 is the invention according to claim 2 or claim 3,
When fixing the second solid steel material and the first solid steel material, or one solid steel material and the other solid steel material by welding,
The inner peripheral surface of the through hole of the first solid steel material or the inner peripheral surface of the through hole of the other solid steel material and the upper end of the steel pipe pile are fillet welded.

請求項7に係る発明は、請求項1から請求項4のいずれか1項に記載の発明において、
地表又は地中において水平方向に隣り合った前記中実鋼材に梁を溶接接合させることを特徴とする。
The invention according to claim 7 is the invention according to any one of claims 1 to 4,
A beam is welded to the solid steel material that is adjacent in the horizontal direction on the ground surface or in the ground.

請求項8に係る発明は、請求項6に記載の発明において、
前記梁から建築柱を立ち上げることを特徴とする。
この構成は、水平方向に隣り合った該中実鋼材に対し梁を溶接接合させて該梁の中間から一本以上の間柱等の建築鉄骨柱を立ち上げることである。
The invention according to claim 8 is the invention according to claim 6,
An architectural column is raised from the beam.
In this configuration, a beam is welded and joined to the solid steel material adjacent in the horizontal direction, and an architectural steel column such as one or more studs is started up from the middle of the beam.

本発明では、
(1)地盤を深く広く掘削する必要がなく、掘削の作業量が少なく、残土が殆どなく、その処理に、費用と手間が殆ど掛からない。また、振動・騒音・砂埃が発生して環境問題が発生する恐れが殆どない。
(2)コンクリート打設の手間と養生の期間が必要ない。
(3)大きなフーチングと基礎梁と広い基礎が不必要で、その費用と養生期間の問題がなく、狭い箇所での施工が可能になる。
(4)従来の特許文献1の杭柱接合部に比べて構造が単純である。また、従来の特許文献1に比べて、高さ調整用のスペーサなど不要で、建設地での水平溶接の開先ギャップの調整により、柱の高さ調整ができて手間が掛からない。
(5)中実鋼材のトップ面が平滑であり、柱下端を中実鋼材のトップ面で容易に水平にずらすことができて、柱の水平位置の調整が容易である。
(6)中実鋼材の断面が大きくて、コンクリート製の柱脚や特願平9−348841の例よりも杭柱接合部の大きな剛性と強度が得られる。
(7)仕口部の構造が単純で、製作工数も少なく強度も高い上に、土木基礎精度に対応した部材間の位置調整ができる。
(8)中実鋼材と柱の現場溶接性は、柱の上下左右の位置調整が容易で姿勢が水平溶接であるため、良好である。
(9)中実鋼材を水平方向に合わせた2個の圧延・鍛造又は鋳造による中実鋼材から構成させると、中実鋼材の製造費が低減できる。
(10)杭芯と柱芯とが大きくずれた場合にも適用できる。特に、隣地が迫ったところで杭が打設できない場合にも柱を隣地近くに設置することができる。
In the present invention ,
(1) It is not necessary to excavate the ground deeply and widely, the amount of excavation work is small, there is almost no residual soil, and the cost and labor are hardly required for the processing. In addition, there is almost no risk of environmental problems due to vibration, noise and dust.
(2) There is no need for concrete placement and curing.
(3) Large footings, foundation beams, and wide foundations are unnecessary, and there is no problem with the cost and curing period, and construction in a narrow area is possible.
(4) The structure is simple compared to the conventional pile-column joint of Patent Document 1. Further, compared to the conventional Patent Document 1, a height adjusting spacer or the like is unnecessary, and the height of the column can be adjusted by adjusting the groove gap of the horizontal welding at the construction site, so that labor is not required.
(5) The top surface of the solid steel material is smooth, the lower end of the column can be easily shifted horizontally with the top surface of the solid steel material, and the horizontal position of the column can be easily adjusted.
(6) The cross section of the solid steel material is large, and greater rigidity and strength of the pile column joint can be obtained than the concrete column base and Japanese Patent Application No. 9-348841.
(7) The structure of the joint is simple, the number of manufacturing steps is small, the strength is high, and the position adjustment between members corresponding to the civil engineering foundation accuracy can be performed.
(8) The on-site weldability of the solid steel material and the column is good because the vertical and horizontal position adjustment of the column is easy and the posture is horizontal welding.
(9) If the solid steel material is constituted by two solid steel materials obtained by rolling, forging, or casting in the horizontal direction, the manufacturing cost of the solid steel material can be reduced.
(10) The present invention can also be applied when the pile core and the column core are greatly displaced. In particular, a pillar can be installed near the adjacent land even when a pile cannot be placed where the adjacent land approaches.

請求項5に係る発明では、さらに次の効果がある。即ち、このような構成にすれば、地盤が弱いところでも強固な地盤支持力が得られ、鉄骨柱の芯がずれていても該中実鋼材から該基礎杭と該鉄骨柱が共に外れることがなく、且つ、該基礎杭と該鉄骨柱との接合部が鋼材同士の溶接接合により大きな強度を保つことができる。即ち、杭柱接合部の大きな剛性と強度及び杭基礎により大きな地耐力が確保されるのである。
請求項5に係る発明では、杭柱継手の強度を確保しながら、該中実鋼材の上面の大きさ及び高さを最小にして、杭と柱の位置調整能力を最大に発揮させうる。
In the invention according to claim 5, there is further the following effects. That is, with such a configuration, a strong ground supporting force can be obtained even when the ground is weak, and even if the core of the steel column is misaligned, both the foundation pile and the steel column can be detached from the solid steel material. In addition, the joint portion between the foundation pile and the steel column can maintain a high strength by welding the steel materials. That is, a large ground strength is ensured by the large rigidity and strength of the pile column joint and the pile foundation.
In the invention which concerns on Claim 5 , while ensuring the intensity | strength of a pile pillar joint, the magnitude | size and height of the upper surface of this solid steel material can be minimized, and the position adjustment capability of a pile and a pillar can be exhibited to the maximum.

請求項6に係る発明では、さらに次の効果がある。即ち、請求項6に係る発明では、水平方向に隣り合った該中実鋼材に対し梁を溶接接合させて該梁の中間から一本以上の間柱等の建築柱を立ち上げることができる。間柱用の特別のコンクリート基礎が不要なので経済的である。 In the invention according to claim 6, there is further the following effects. That is, in the invention according to claim 6, it is possible to start up one or more building columns such as one or more studs from the middle of the beam by welding the beam to the solid steel materials adjacent in the horizontal direction. It is economical because it does not require a special concrete foundation for the studs.

実施の形態
本発明の実施の形態1について説明する。図6、図9及び図10は、円形鋼管杭と角形鋼管柱との間に、水平寸法よりも鉛直方向寸法が小さい6面体の圧延材・鍛造材又は鋳造材による鋼製中実鋼材を挟んで上下から該鋼管杭と該柱を接合した断面図を示し、図(イ)は、該中実鋼材17が一個の部品から構成されており、図6(ロ)は、中実鋼材17のそれぞれが水平寸法よりも鉛直方向寸法が小さくなるように水平方向に合わせた2個の中実鋼材17から構成されている。図6(イ)と(ロ)の中実鋼材17の水平方向の寸法は柱径以上即ち通常100〜1000mm望むらくは200〜500mmであり、垂直方向の寸法は16〜500mm望むらくは50〜400mmであり、水平寸法と垂直寸法の組合せでは水平寸法よりも垂直寸法が小さくなっている。通常は、柱1は角形鋼管・円形鋼管・H形鋼であり、鋼管杭18は円形鋼管杭である。該鋼管杭18は、地盤の浅いところに支持料がある場合に図5下部に示すように、必須ではないがその先端にスクリュー羽根19が単数又は複数取り付けられている。該鋼管杭18を地盤の中に立設し、その上部の余長分をガス切断して、所定の高さにした後、鋼管杭18側又は中実鋼材17側に開先加工を行い、中実鋼材17と鋼管杭18を溶接接合する。鋼管杭18の頂部に中実鋼材17を溶接接合した後、図7に示すように、上下又は水平位置調整が難しい場合に、鉄骨柱1用の裏当金20又は短管20を柱1及び中実鋼材17に仮付け溶接せずにルーズにしたまま、該柱用の裏当金又は短管20を柱1下端部内面及び中実鋼材上に置いて、柱1の高さ位置調整41及び水平位置調整42を行うことにより、柱1と中実鋼材17の継手開先ギャップGの調整を行い、柱1の高さを調整した後、柱1と裏当金20と中実鋼材17を仮付け溶接するか又は仮止めピース21を用いて柱1と中実鋼材17を仮付け溶接して固定し、それから継手溶接7を施工する。なお、水平方向に合わせた2個の圧延・鍛造又は鋳造による中実鋼材は、継手の強度要求により互いに上部・下部・側面を溶接接合することが可能であり、中実鋼材17の下端部に開先加工を行う場合は、一例として図8に示すように行い、建設現場でも可能であるが、鉄骨工場で予め実施しておく方が良い。更に、中実鋼材17の設置位置は、鋼管杭18の上部切断位置により、中実鋼材17を鋼管杭18及び柱1と接合した後に、地中、地中と地表の中間、地表又は地上のいずれでも可能である。尚、中いつ鋼材17の形状は、6面体に限らず8面体、球形、楕円体や円柱にもすることができる。図9は、図6の応用で、図6の場合よりも中実鋼材17を広く設けて、上部に柱1を一本、下部に鋼管杭18を一本取り付けたものである。この場合は、柱1の芯と鋼管杭18の芯とがずれても上部柱1と下部鋼管杭18が連続体として容易に取付られる。図10も、図6の応用で、図6の場合よりも中実鋼材17を広く設けて、上部に柱1を一本、下部に鋼管杭18を2本取り付けたものである。この場合も、柱1の芯と鋼管杭18の芯とがずれても上部柱1と下部鋼管杭18が連続対として容易に取付られる。
Embodiment 1
Embodiment 1 of the present invention will be described. 6, 9, and 10, a solid steel material made of a hexagonal rolled material, forged material, or cast material having a vertical dimension smaller than the horizontal dimension is sandwiched between a circular steel pipe pile and a square steel pipe column. And (b) shows that the solid steel material 17 is composed of one part, and FIG. 6 (b) shows the solid steel material 17 Each is composed of two solid steel members 17 aligned in the horizontal direction so that the vertical dimension is smaller than the horizontal dimension. 6 (a) and 6 (b), the horizontal dimension of the solid steel material 17 is equal to or greater than the column diameter, that is, usually 100 to 1000 mm, preferably 200 to 500 mm, and the vertical dimension is 16 to 500 mm, preferably 50 to 50 mm. The vertical dimension is smaller than the horizontal dimension in the combination of the horizontal dimension and the vertical dimension. Normally, the column 1 is a square steel pipe, a round steel pipe, and an H-shaped steel, and the steel pipe pile 18 is a round steel pipe pile. As shown in the lower part of FIG. 5, when the steel pipe pile 18 has a support material in a shallow place of the ground, one or more screw blades 19 are attached to the tip of the steel pipe pile 18, although it is not essential. The steel pipe pile 18 is erected in the ground, and the excess length of the upper part is gas cut to a predetermined height, and then groove processing is performed on the steel pipe pile 18 side or the solid steel material 17 side, The solid steel material 17 and the steel pipe pile 18 are joined by welding. After the solid steel material 17 is welded and joined to the top of the steel pipe pile 18, as shown in FIG. 7, when the vertical or horizontal position adjustment is difficult, the backing metal 20 or the short pipe 20 for the steel column 1 is connected to the column 1 and The back metal or short pipe 20 for the column is placed on the inner surface of the lower end of the column 1 and the solid steel material while being loosened without being tack welded to the solid steel material 17 to adjust the height position 41 of the column 1. And by adjusting the horizontal position adjustment 42, the joint groove gap G between the column 1 and the solid steel material 17 is adjusted, and after adjusting the height of the column 1, the column 1, the backing metal 20, and the solid steel material 17 are adjusted. Or the temporary fixing piece 21 is used to fix the column 1 and the solid steel material 17 by temporary welding, and then the joint weld 7 is applied. In addition, the two solid steel materials by rolling, forging, or casting that are aligned in the horizontal direction can be welded to each other at the upper, lower, and side surfaces depending on the strength requirements of the joint. When performing groove processing, it is performed as shown in FIG. 8 as an example, and it is also possible at a construction site, but it is better to carry out in advance at a steel factory. Furthermore, the installation position of the solid steel material 17 is determined by connecting the solid steel material 17 to the steel pipe pile 18 and the column 1 according to the upper cutting position of the steel pipe pile 18, and then in the ground, between the ground and the ground, on the ground surface, or on the ground. Either is possible. The shape of the steel material 17 is not limited to a hexahedron, but may be an octahedron, a sphere, an ellipsoid, or a cylinder. FIG. 9 shows an application of FIG. 6 in which a solid steel material 17 is provided wider than in the case of FIG. 6 and one column 1 is attached to the upper part and one steel pipe pile 18 is attached to the lower part. In this case, even if the core of the column 1 and the core of the steel pipe pile 18 are displaced, the upper column 1 and the lower steel pipe pile 18 are easily attached as a continuous body. FIG. 10 is also an application of FIG. 6, in which a solid steel material 17 is provided wider than in the case of FIG. 6, and one column 1 is attached to the upper part and two steel pipe piles 18 are attached to the lower part. Also in this case, even if the core of the column 1 and the core of the steel pipe pile 18 are displaced, the upper column 1 and the lower steel pipe pile 18 are easily attached as a continuous pair.

実施の形態
本発明の実施の形態2について説明する。図11は、鉛直方向に2つの孔を開けた1枚の圧延鋼板、鋳鋼材、又は鍛鋼材製の中実鋼材17の孔の上に、外形が四角・六角などの多角形・楕円又は円形のリング状の圧延鋼板、鋳鋼材、鍛鋼材製の中実鋼材17Aをそれぞれ1枚合計2枚載せて、中実鋼材17の中央孔17Hを通して、その2枚の中実鋼材17Aの中央開口部にそれぞれ2本の基礎杭上端を挿入して相互に溶接し、更に中実鋼材17と17Aを溶接接合7した場合の構造の断面図を示す。言い換えれば、2枚以上の厚板の圧延鋼板、鋳鋼材、又は鍛鋼材にそれぞれ内径の異なる孔を開けて重ね合わせ、2本以上の基礎杭上端をそれぞれの小さい方の孔に挿入してそれぞれ溶接し、更に2枚の圧延鋼板、鋳鋼材、鍛鋼材製の中実鋼板17A、17を溶接7した場合の断面図である。
この場合、鋼管杭本数が2本であるが、鋼管杭1本では鉛直支持力又は曲げモーメントが得られない場合に、鋼管杭本数を複数にしたものである。中実鋼板17の貫通孔の内径を大きめにすれば鋼管杭18の芯ずれにも対応ができる。中実鋼材17及び17Aの孔径が鋼管杭18より大きい分だけ鋼管杭の芯ずれの調整が代が大きくなる。
Embodiment 2
A second embodiment of the present invention will be described. FIG. 11 shows a polygon, an ellipse, or a circle such as a square or a hexagon on the hole of a solid steel material 17 made of one rolled steel plate, cast steel, or forged steel with two holes in the vertical direction. A ring-shaped rolled steel plate, cast steel material, and solid steel material 17A made of forged steel material, each of which is mounted in total 2 sheets, through the central hole 17H of the solid steel material 17 and the central opening of the two solid steel materials 17A Sectional drawing of the structure at the time of inserting two foundation pile upper ends, respectively, welding each other, and also welding the solid steel materials 17 and 17A 7 is shown. In other words , two or more thick rolled steel plates, cast steel materials, or forged steel materials are each stacked with holes having different inner diameters, and two or more foundation pile upper ends are inserted into the smaller holes, respectively. welding 7 is a cross-sectional view of a further two rolled steel, cast steel, welded 7 real steel 17 a, 17 in the forged steel material.
In this case, the number of steel pipe piles is two, but when the vertical support force or bending moment cannot be obtained with one steel pipe pile, the number of steel pipe piles is plural. If the inner diameter of the through hole of the solid steel plate 17 is made larger, the misalignment of the steel pipe pile 18 can be dealt with. The adjustment of the misalignment of the steel pipe pile is increased by the amount that the hole diameters of the solid steel materials 17 and 17A are larger than the steel pipe pile 18.

実施の形態
本発明の実施の形態3について説明する。図12は、孔17Hを開けた圧延鋼板、鋳鋼材、鍛鋼材製の中実鋼材17の上に、別の孔17Jを開けた外形が四角・六角又は円形の圧延鋼板、鋳鋼材、又は鍛鋼材製の中実鋼材17Aを上に重ねて載せて、それぞれの中実鋼板の開口部17H・17Jを合わせたうえに、1本の鋼管杭18を下側の中実鋼材17の孔17Hに挿入して中実鋼板17と鋼管杭18を溶接接合し、もう1本の鋼管杭を下側の中実鋼材17の孔17Hを通して上側の中実鋼材17Aの孔17Jに挿入して中実鋼板17Aと鋼管杭18を溶接接合する場合の構造の断面図を示す。鋼管杭18がそれぞれに接合され上下に重ねられた異なった2枚の中実鋼板17と17Aを互いに水平方向にずらすことにより、それぞれの鋼管杭が独立して芯位置調整が可能になっている。
Embodiment 3
Embodiment 3 of the present invention will be described. Figure 12 is a rolled steel plate, cast steel with a hole 17H, on the solid steel 17 in a forged steel member, another hole 17J of the open contour or square-hexagonal circular rolling steel, cast steel, or A solid steel material 17A made of forged steel is placed on top of each other, and the openings 17H and 17J of the respective solid steel plates are combined, and one steel pipe pile 18 is inserted into a hole 17H in the lower solid steel material 17 The solid steel plate 17 and the steel pipe pile 18 are welded and joined to each other, and the other steel pipe pile is inserted through the hole 17H of the lower solid steel material 17 into the hole 17J of the upper solid steel material 17A. Sectional drawing of the structure in the case of welding and joining the steel plate 17A and the steel pipe pile 18 is shown. By displacing two different solid steel plates 17 and 17A, which are joined to each other and stacked one above the other in the horizontal direction, the steel pipe piles can be independently adjusted in core position. .

実施の形態
本発明の実施の形態4について説明する。図13は、図12と穴明けを除いて同様であるが、下側の中実鋼材17の孔17Hに取り付けた鋼管杭位置には、上側の中実鋼材17Aには孔が開けてない。これは下側の中実鋼材17に鋼管杭18を溶接接合した後に上側の中実鋼材17Aを取り付けて別の鋼管杭を中実鋼材17A孔部分に溶接した場合である。
Embodiment 4
Embodiment 4 of the present invention will be described. FIG. 13 is the same as FIG. 12 except for drilling, but the upper solid steel material 17A is not perforated at the steel pipe pile position attached to the hole 17H of the lower solid steel material 17. This is a case where the steel pipe pile 18 is welded and joined to the lower solid steel material 17 and then the upper solid steel material 17A is attached and another steel pipe pile is welded to the hole portion of the solid steel material 17A.

実施の形態
本発明の実施の形態5について説明する。図14は、2枚の中実鋼材17と17Aの上下位置関係が図11と反対になっている。即ち、中央に孔を開けた外形が四角・六角又は円形のリング状の圧延鋼板、鋳鋼材、鍛鋼材製の中実鋼材17Aの2枚の上に、該リング状中実鋼材の中央孔位置に芯位置を合わせた貫通孔付きの中実鋼材17を載せて、その中実鋼材17Aの中央開口部にそれぞれ1本合計2本の鋼管杭上端を挿入して相互にすみ肉溶接又は突き合わせ溶接し、更に中実鋼材17と17Aを中実鋼材17の穴内ですみ肉溶接7F接合した場合の構造の断面図を示す。この場合、鋼管杭の上端部の接合は、中実鋼材17Aの内径と鋼管杭天端内面に入れた円板45と鋼管杭天端とでスロット溶接7Sするものである。この場合、中実鋼材17Aは先に鋼管杭18と溶接接合されて、その後で中実鋼材17が溶接接合7Fされるので、下向き姿勢で溶接施工が容易であるという利点がある。また、中実鋼材17の下側の鋼管杭18に中実鋼材17のストッパーを取り付けておけば、中実鋼材17の位置決めや溶接部17Sの補強になり、鉄骨柱1による鉛直荷重に対して耐力を増加させる。
Embodiment 5
Embodiment 5 of the present invention will be described. In FIG. 14, the vertical positional relationship between two solid steel materials 17 and 17A is opposite to that in FIG. That is, the center hole position of the ring-shaped solid steel material on two sheets of a solid steel material 17A made of a ring-shaped rolled steel plate, a cast steel material, or a forged steel material having a square, hexagonal or circular outer shape with a hole in the center. A solid steel material 17 with a through-hole aligned in the core position is placed on it, and the top ends of two steel pipe piles are inserted into the central opening of the solid steel material 17A, respectively, and fillet welding or butt welding each other. Further, a cross-sectional view of the structure when the solid steel materials 17 and 17A are joined by fillet welding 7F in the hole of the solid steel material 17 is shown. In this case, the upper end of the steel pipe pile is joined by slot welding 7S between the inner diameter of the solid steel material 17A and the disk 45 placed on the inner surface of the steel pipe pile top end and the steel pipe pile top end. In this case, since the solid steel material 17A is welded and joined to the steel pipe pile 18 first, and then the solid steel material 17 is welded and joined 7F, there is an advantage that welding work is easy in a downward posture. Moreover, if the stopper of the solid steel material 17 is attached to the steel pipe pile 18 of the lower side of the solid steel material 17, it will become positioning of the solid steel material 17 and reinforcement of the welding part 17S, and with respect to the vertical load by the steel column 1 Increase yield strength.

実施の形態
本発明の実施の形態6について説明する。図15に、中央に孔を開けた外形が四角・六角などの多角形又は円形のリング状の圧延鋼板、鋳鋼材、鍛鋼材製の中実鋼材17Aを2枚設置してその2枚の上に、該リング状中実鋼材17Aの中央孔位置に芯位置を合わせた貫通孔付きの中実鋼材17を載せて、その中実鋼材17Aの中央開口部にそれぞれ1本合計2本の基礎杭18の上端を挿入して、必要により、基礎杭18の上端部内径に円形鋼板45を挿入して相互にすみ肉溶接又は突き合わせ溶接し、更に中実鋼材17と17Aを中実鋼材17の穴内ですみ肉溶接7F接合し、更に地中梁又は地表梁11を溶接接合させた断面図を示す。該梁11は中実鋼材17の下側に該梁11の下フランジ11F及びウエブ11Wが延長されて任意の長さに設けることができる。該梁11が延長された結果、鋼管杭18に突き当たる場合は鋼管杭18に溶接接合することもできるし、鋼管杭18を避けて延長することもできるし、鋼管杭18を避けて延長し、上部柱1の下側に位置するように設けることができる。この梁11は通常H形鋼を用いるが、角形鋼管・円形鋼管・角鋼・丸鋼を用いることができる。また、本実施の形態では、該中実鋼材17Aを2枚設置して該中実鋼材17Aの中央開口部にそれぞれ1本合計2本の基礎杭上端を挿入して相互にすみ肉溶接又は突き合わせ溶接し、その後に、地中梁又は地表梁11を溶接接合させた貫通孔付きの中実鋼材17をその2枚の上に、該リング状中実鋼材17Aの中央孔位置に芯位置を合わせて載せて、その中実鋼材17の内径と中実鋼材17Aを穴内ですみ肉溶接7F接合することも可能である。
Embodiment 6
Embodiment 6 of the present invention will be described. In FIG. 15, two solid steel materials 17A made of a rolled steel plate, cast steel material, or forged steel material having a polygonal or circular shape such as a square or a hexagon or a round shape with a hole in the center are installed. A solid steel material 17 with a through hole whose core position is aligned with the center hole position of the ring-shaped solid steel material 17A is placed on the center opening portion of the solid steel material 17A, and two foundation piles, one each in total. 18 is inserted, and if necessary, a circular steel plate 45 is inserted into the inner diameter of the upper end of the foundation pile 18 to fillet or butt weld each other, and the solid steel members 17 and 17A are inserted into the holes of the solid steel member 17. The cross-sectional view in which the fillet weld 7F is joined and the underground beam or the ground beam 11 is further joined by welding is shown. The beam 11 can be provided at an arbitrary length by extending a lower flange 11F and a web 11W of the beam 11 below the solid steel material 17. As a result of the beam 11 being extended, when it hits the steel pipe pile 18, it can be welded to the steel pipe pile 18, it can be extended avoiding the steel pipe pile 18, and it can be extended avoiding the steel pipe pile 18, It can be provided so as to be located below the upper column 1. The beam 11 is usually made of H-shaped steel, but square steel pipe, round steel pipe, square steel, and round steel can be used. Further, in the present embodiment, two solid steel materials 17A are installed, and two foundation pile upper ends are inserted into the central opening of the solid steel material 17A, respectively, and fillet welding or butting is performed on each other. Welding, and then aligning the core position with the center hole position of the ring-shaped solid steel material 17A on the two solid steel materials 17 with through-holes to which the underground beam or the ground beam 11 is welded and joined It is also possible to join the inner diameter of the solid steel material 17 and the solid steel material 17A with the fillet weld 7F in the hole.

実施の形態
本発明の実施の形態7について説明する。図16に、中央に孔を開けた外形が四角の圧延鋼板、鋳鋼又は鍛鋼製の中実鋼材17Aを2枚設置してその中実鋼材17Aの中央開口部にそれぞれ1本合計2本の基礎杭上端を挿入して中実鋼材17Aと基礎杭上端とを相互にすみ肉溶接又は突き合わせ溶接し、その2枚の中実鋼材17Aの上に、該中実鋼材17Aよりも幅が狭くその中央孔位置に貫通孔なしの中実鋼材17を載せて、更に中実鋼材17Aの側面で17とすみ肉溶接7F接合し、更に2本の地中梁又は地表梁11を直角方向に溶接接合させた上面図を示す。該地中梁11の一つは、中実鋼材17の端部に接合されており、もう一つは中実鋼材17の端部から上部柱1の下側を通り中実鋼材17の他端部まで延長されている。鉄骨柱は両地中梁のほぼセンター位置で中実鋼材17の上面に溶接で取り付けられている。
Embodiment 7
Embodiment 7 of the present invention will be described. In FIG. 16, two solid steel materials 17A made of rolled steel, cast steel, or forged steel with a square outer perforation are installed, and two foundations are provided, one in each of the central openings of the solid steel materials 17A. The pile upper end is inserted and the solid steel material 17A and the foundation pile upper end are fillet welded or butt welded to each other. Solid steel material 17 without through-holes is placed at the hole position, and further, fillet weld 7F is joined to 17 on the side surface of solid steel material 17A, and two underground beams or surface beam 11 are welded in a perpendicular direction. A top view is shown. One of the underground beams 11 is joined to an end portion of the solid steel material 17, and the other is passed through the lower side of the upper column 1 from the end portion of the solid steel material 17 and the other end of the solid steel material 17. It is extended to the part. The steel column is attached to the upper surface of the solid steel material 17 by welding at approximately the center position between the two underground beams.

実施の形態
本発明の実施の形態8について説明する。図17に、中央に孔を開けた外形が多角形・楕円形又は円形のリング状の圧延鋼板、鋳鋼材、鍛鋼材製の中実鋼材17Aを3枚設置してその3枚の上に、該リング状中実鋼材17Aの中央孔位置に芯位置を合わせた貫通孔付きの中実鋼材17を載せて、その中実鋼材17と17Aの中央開口部にそれぞれ1本合計3本の基礎杭上端を挿入して相互にすみ肉溶接又は突き合わせ溶接し、更に中実鋼材17の孔の内径と中実鋼材17Aとを穴内ですみ肉溶接7F接合し、更に地中梁又は地表梁11を溶接接合させた上面図を示す。該梁11は中実鋼材17の下側に該梁11の下フランジ11F及びウエブ11Wが延長されて任意の長さに設けることができる。図17では、2本の梁11が中実鋼材17の下で延長され互いにT字形に溶接接合されている。この梁11は通常H形鋼を用いるが、角形鋼管・円形鋼管・角鋼・丸鋼を用いることができる。
Embodiment 8
Embodiment 8 of the present invention will be described. In FIG. 17, three solid steel materials 17A made of a ring-shaped rolled steel plate, cast steel material, or forged steel material having a polygonal, elliptical, or circular shape with a hole in the center are installed on the three pieces, A solid steel material 17 with a through-hole whose core position is aligned with the center hole position of the ring-shaped solid steel material 17A is placed, and a total of three foundation piles, one in each of the central openings of the solid steel materials 17 and 17A. Fillet welding or butt welding each other with the upper end inserted, and the inner diameter of the hole of the solid steel material 17 and the solid steel material 17A are joined in the fillet weld 7F in the hole, and the underground beam or the ground beam 11 is further welded. The top view joined is shown. The beam 11 can be provided at an arbitrary length by extending a lower flange 11F and a web 11W of the beam 11 below the solid steel material 17. In FIG. 17, two beams 11 are extended under the solid steel material 17 and welded together in a T-shape. The beam 11 is usually made of H-shaped steel, but square steel pipe, round steel pipe, square steel, and round steel can be used.

実施の形態
本発明の実施の形態9について説明する。図18に、水平方向に隣り合った該中実鋼材17に対し、地表又は地中に設置する梁11を溶接接合させて、該梁11から鉄骨柱29を立ち上げる実施の形態縦断面で示す。図18では、地盤に2本の鋼管杭18を貫入させて該鋼管杭18の上端のそれぞれに、中央に孔を開けた外形が多角形・楕円形又は円形のリング状の圧延鋼板、鋳鋼材、鍛鋼材製の中実鋼材17Aの孔に嵌合させて、更に、該鋼管杭18の上端内径に円形鋼板45を嵌合させて、中実鋼材17Aの孔の内径と鋼管杭18の上端面と円形鋼板45の外径とを相互にすみ肉溶接又は突き合わせ溶接して溝溶接部を形成させて、中実鋼材17Aと鋼管杭18と円形鋼板45とを接合させた後、地中梁又は地表梁11により溶接接合で互いに連結させた貫通孔付きの中実鋼材17の2枚をそれぞれ該2枚の中実鋼材17Aの上に、該リング状中実鋼材17Aの中央孔位置に芯位置を合わせて載せて、その中実鋼材17の内径と中実鋼材17Aを穴内ですみ肉溶接7F接合する。しかる後、該梁11の上フランジの任意の場所で鋼管柱29を接合させる。更に、中実鋼材17と17Aを穴内ですみ肉溶接7F接合し、更に地中梁又は地表梁11を溶接接合させた断面図を示す。
Embodiment 9
Embodiment 9 of the present invention will be described. FIG. 18 is a longitudinal sectional view of an embodiment in which a beam 11 installed on the ground surface or in the ground is welded to the solid steel material 17 adjacent in the horizontal direction and a steel column 29 is raised from the beam 11. Show. In FIG. 18, two steel pipe piles 18 are penetrated into the ground and a hole is formed in the center at each of the upper ends of the steel pipe piles 18. The steel plate pile 18 is fitted into the hole of the solid steel material 17A made of forged steel, and the circular steel plate 45 is fitted to the inner diameter of the upper end of the steel pipe pile 18, so that the inner diameter of the hole of the solid steel material 17A and the top of the steel pipe pile 18 are After the end face and the outer diameter of the circular steel plate 45 are fillet welded or butt welded to form a groove weld, the solid steel material 17A, the steel pipe pile 18 and the circular steel plate 45 are joined together, and then the underground beam Alternatively, two solid steel members 17 with through-holes connected to each other by welding with the ground beam 11 are placed on the two solid steel members 17A, respectively, at the center hole position of the ring-shaped solid steel member 17A. Place the same position and place the inner diameter of the solid steel material 17 and the solid steel material 17A in the hole. Joining fillet weld 7F. Thereafter, the steel pipe column 29 is joined at an arbitrary position of the upper flange of the beam 11. Further, a cross-sectional view in which solid steel materials 17 and 17A are joined by fillet welding 7F in a hole and an underground beam or a ground beam 11 is further joined by welding.

実施の形態10
図6から図19まで鋼管杭、中実鋼材、柱、間柱の取付施工順序を変えることができる。
Embodiment 10
From FIG. 6 to FIG. 19, the installation order of the steel pipe piles, solid steel materials, columns, and studs can be changed.

実施の形態11
本発明の実施の形態11について説明する。図19に、図18の実施の形態9に対し、地中に設置する中実鋼材17及び梁11の全体を、セメントモルタル・コンクリート又は鉄筋コンクリート48で覆うことを特徴とする鉄骨構造物を製作する方法の一例を断面図に示す。鋼管杭18を打設後、地盤9を掘削して中実鋼材17と17A及び梁11を設置して、セメントモルタル・コンクリート又は鉄筋コンクリート48で覆うのは、中実鋼材、地中梁、柱の防食及びこれらの材料の強度の補完に役立つからである。本実施の形態は、通常は、地中梁11や中実鋼材17は土間コンクリートスラブと共に地中に入るのだが、地下水の水位等が低い場合に中実鋼材17及び梁11の一部だけを地中に埋設したり、セメントモルタル・コンクリート又は鉄筋コンクリート48で覆ったりすることもできる。
Embodiment 11
An eleventh embodiment of the present invention will be described. FIG. 19 shows a steel structure characterized in that the solid steel material 17 and the beam 11 installed in the ground are covered with cement mortar / concrete or reinforced concrete 48 with respect to the ninth embodiment of FIG. An example of the method is shown in the cross-sectional view. After placing the steel pipe pile 18, the ground 9 is excavated and the solid steel materials 17 and 17A and the beam 11 are installed and covered with cement mortar / concrete or reinforced concrete 48. This is because it helps to prevent corrosion and supplement the strength of these materials. In the present embodiment, the underground beam 11 and the solid steel material 17 usually enter the ground together with the interstitial concrete slab. However, when the groundwater level is low, only the solid steel material 17 and a part of the beam 11 are used. It can also be buried in the ground or covered with cement mortar, concrete or reinforced concrete 48.

実施の形態12
本発明の実施の形態12ついて説明する。図20及び21に、鋼管杭18の地中埋設部分に水平の鋼板又は螺旋状の鋼板44を機械的又は溶接接合で取り付けて、該鋼板部分44を基礎定盤又は布基礎10の上側、下側、内部又はこれらを組み合わせた複数箇所に設けることを特徴とする鉄骨構造物を製作する方法を示す。図20は該鋼板部分44を基礎定盤又は布基礎10内部に単数設置した場合である。図21は基礎定盤又は布基礎10の上側、下側、内部の複数箇所に設けた場合である。本実施の形態は、従来のように杭頭の上に基礎を設けるよりも強固な鋼管杭と基礎との結合を得ることができる。また、本実施の形態は、既存の基礎を利用して、その既存の基礎の杭打設位置で孔を開けて、その孔に鋼管杭18と該鋼板部分44を設置した後に基礎定盤10を再構築することもできる。このようにすれば、基礎定盤の有効利用と土砂やコンクリート等の廃棄物の低減と基礎工事の短工期化に役立つ。
Embodiment 12
A twelfth embodiment of the present invention will be described. 20 and 21, a horizontal steel plate or a spiral steel plate 44 is attached to the underground buried portion of the steel pipe pile 18 by mechanical or welding joining, and the steel plate portion 44 is attached to the upper side and lower side of the foundation surface plate or the fabric foundation 10. The method of manufacturing the steel structure characterized by providing in the side, the inside, or several places which combined these is shown. FIG. 20 shows a case where a single steel plate portion 44 is installed inside the base surface plate or the fabric base 10. FIG. 21 shows a case where the foundation surface plate or the fabric foundation 10 is provided at a plurality of locations on the upper side, lower side, and inside. This embodiment can obtain a stronger bond between the steel pipe pile and the foundation than in the conventional case where the foundation is provided on the pile head. Further, in the present embodiment , the foundation surface plate 10 is formed after a hole is made at a position where the existing foundation is piled and a steel pipe pile 18 and the steel plate portion 44 are installed in the hole. Can also be rebuilt. In this way, it is useful for effective use of the foundation surface plate, reduction of waste such as earth and sand and concrete, and shortening of the foundation work.

実施の形態13
本発明の実施の形態13ついて説明する。図22に、図12のケースについて、角形鋼管、丸形鋼管、又はH形鋼の建築鉄骨柱1の1階部分を上部分と下部分に分割して、500〜2000mm程度の長さ、望むらくは溶接作業性から800〜1200mm程度の長さの該建築鉄骨柱1の下部分の下端を該中実鋼材上面に溶接接合7させて、しかる後、該建築鉄骨柱1の下部分の上端に該上部分の柱1Aを溶接7Cして鉄骨構造物を製作する方法を断面図で示す。本方法を用いれば、建物1階部分の床工事を鉄骨本体の建て方を行う前に行うことができて工事の工期短縮が可能になる。
Embodiment 13
A thirteenth embodiment of the present invention will be described. In FIG. 22, about the case of FIG. 12, the 1st floor part of the square steel pipe, the round steel pipe, or the H-steel building steel pillar 1 is divided into an upper part and a lower part, and a length of about 500 to 2000 mm is desired. From the viewpoint of welding workability, the lower end of the lower part of the architectural steel column 1 having a length of about 800 to 1,200 mm is welded 7 to the upper surface of the solid steel material, and then the upper end of the lower part of the architectural steel column 1 is obtained. A method of manufacturing a steel structure by welding the upper column 1A to 7C is shown in a sectional view. If this method is used, the floor construction of the first floor portion of the building can be performed before the construction of the steel frame body, and the construction period can be shortened.

実施の形態14
本発明の実施の形態14について説明する。図23に、鋼管杭の無い場合の本発明の実施の形態を示す。即ち、地盤の表層が弱くて比較的浅い所例えば0〜5m深さに十分な基礎耐力のある場合には、地盤を掘削し、コンクリート基礎定盤・布記基礎10又は捨てコンクリート10Aを敷設した後、掘削した所の地盤の上に、サイコロ又は中実鋼材17にH形鋼又は角形鋼管製の地中梁28を取り付けた鉄骨構造物を設置して、次に、H形鋼柱又は角形鋼管柱1をサイコロ又は中実鋼材17に溶接接合させる方法を断面図で示す。この場合に、図23の左側の中実鋼材17に示すように該中実鋼材1に梁せいよりも小さい板厚を用いた場合は地中梁28の下フランジ及びウエブを中実鋼材17の下側にまで延長して中実鋼材17の下側と地中梁の下側フランジとの間に補強用のスティフナー46を溶接で取り付ける。
Embodiment 14
Embodiment 14 of the present invention will be described. FIG. 23 shows an embodiment of the present invention when there is no steel pipe pile. That is, when the surface layer of the ground is weak and relatively shallow, for example, when there is sufficient foundation strength at a depth of 0 to 5 m, the ground is excavated and the concrete foundation surface plate / clothing foundation 10 or discarded concrete 10A is laid. After that, on the ground of the excavated place, a steel structure in which an underground beam 28 made of H-shaped steel or square steel pipe is attached to a dice or solid steel material 17 is installed, and then an H-shaped steel column or square A method of welding the steel pipe column 1 to a dice or solid steel material 17 by welding is shown in a sectional view. In this case, as shown in the solid steel material 17 on the left side of FIG. 23, when the solid steel material 1 has a thickness smaller than that of the beam, the lower flange and the web of the underground beam 28 are attached to the solid steel material 17. A stiffener 46 for reinforcement is attached by welding between the lower side of the solid steel material 17 and the lower flange of the underground beam.

実施の形態15
本発明の実施の形態15について説明する。図24に、図23と同様に鋼管杭の無い場合の本発明の実施の形態を示す。即ち、地盤の表層が弱くて比較的浅い所に十分な基礎耐力のある場合には、地盤を掘削し、コンクリート基礎定盤10又は捨てコンクリート10A敷設の有無によらず、掘削した所の地盤の上に、無筋のコンクリート即ちラップルコンクリート49を敷設した後、該ラップルコンクリート49の上にサイコロ又は中実鋼材17にH形鋼又は角形鋼管製の地中梁28を取り付けた鉄骨構造物を設置して、次に、H形鋼柱又は角形鋼管柱1をサイコロ又は中実鋼材17に溶接接合させる方法を示す。このラップルコンクリート49は強固な支持地盤と同様な効果を発揮し、支持地盤の支持高さレベルを上げる働きをする。本実施の形態では、該ラップルコンクリート49を中実鋼材17の下に配置しているが、該ラップルコンクリート49を地中梁28の任意の水平位置に配置することもできる。図23及び図24は、地盤支持層49が地表から浅い場合に、鋼管杭を用いずに、地盤の上に、又は、地盤の上に捨てコンクリートを置いた上に水平に置かれた単数の又は鉛直方向に重ね合わせて互いに溶接接合された複数の圧延材・鍛造材又は鋳造材による中実鋼材17を置き、更に、該中実鋼材17の上に、角形鋼管、丸形鋼管、又はH形鋼製の建築鉄骨柱の下端を建設地において溶接により接合させる方法を示す。本方法は、独立基礎又は布基礎の方式で、コンクリート定盤又は基礎の代わりに中実鋼材又はラップルコンクリートを用いる方法でもある。
Embodiment 15
A fifteenth embodiment of the present invention will be described. FIG. 24 shows an embodiment of the present invention in the case where there is no steel pipe pile as in FIG. That is, when the surface layer of the ground is weak and has a sufficient foundation strength in a relatively shallow place, the ground is excavated and the ground of the excavated place is irrelevant regardless of whether the concrete foundation surface plate 10 or the discarded concrete 10A is laid. On top of this, after laying unreinforced concrete, i.e., laple concrete 49, a steel structure in which an underground beam 28 made of H-shaped steel or square steel pipe is attached to the dice or solid steel material 17 is installed on the lapple concrete 49. Next, a method of welding the H-shaped steel column or the square steel pipe column 1 to the dice or the solid steel material 17 will be described. The wrinkle concrete 49 exhibits the same effect as a strong support ground, and works to increase the support height level of the support ground. In the present embodiment, the wrinkle concrete 49 is disposed under the solid steel material 17, but the wrinkle concrete 49 may be disposed at any horizontal position of the underground beam 28. FIG. 23 and FIG. 24 show that when the ground support layer 49 is shallow from the ground surface, without using steel pipe piles, a single unit placed horizontally on the ground or on the ground with abandoned concrete. Alternatively, a solid steel material 17 made of a plurality of rolled, forged or cast materials that are superposed in the vertical direction and welded to each other is placed, and on the solid steel material 17, a square steel pipe, a round steel pipe, or H The method of joining the lower end of a structural steel column made of section steel by welding in a construction site is shown. This method is a method of using an independent foundation or a cloth foundation, and using solid steel material or rapple concrete instead of a concrete surface plate or foundation.

実施の形態16
本発明の実施の形態16について説明する。図25、図26及び図27は、水平寸法よりも鉛直方向寸法が小さく、且つ、水平に置かれた単数の又は鉛直方向に合わせて互いに溶接接合された複数の圧延材・鍛造材又は鋳造材による中実鋼材17と、地盤に立設後に所定の高さで切断した単数又は複数の建築基礎鋼管杭18の上端を建設地において溶接により接合させた実施の形態で、図25は1柱1杭で杭18と上部柱1が平面視で同位置でない場合に1本の鋼管杭を下部に繋げた該中実鋼材17の上部にH形鋼地中梁を載せて溶接接合させた上面図(イ)と断面図(ロ)の例であり、図26は、1柱2杭で杭18と上部柱1が平面視で同位置でない場合に2本の鋼管杭を下部に繋げた該中実鋼材17の上部にH形鋼地中梁を載せて溶接接合させた上面図(イ)と断面図(ロ)の例であり、図27は1柱2杭で杭18と上部柱1が平面視で同位置でなく地中梁28の芯からもずれている場合に、2本の鋼管杭を下部に繋げた中実鋼材17の上部中央にH形鋼地中梁を載せて溶接接合させた上面図(イ)と断面図(ロ)の例である。図25及び図27共に、鉄骨柱1の下部に接続された中実鋼材17が鋼管杭18に接続された中実鋼材17とは別になっていて、2系列が組み合わさった形になっている。
Embodiment 16
A sixteenth embodiment of the present invention will be described. FIG. 25, FIG. 26 and FIG. 27 show a plurality of rolled materials, forged materials or cast materials that are smaller in the vertical dimension than the horizontal dimension and are welded and joined to each other in the vertical direction. 25 is an embodiment in which the upper ends of one or a plurality of building foundation steel pipe piles 18 cut at a predetermined height after standing on the ground are joined by welding in a construction site. Top view of the pile 18 and the upper column 1 when they are not in the same position in plan view, with an H-shaped steel underground beam placed on the upper part of the solid steel material 17 with one steel pipe pile connected to the lower part and welded FIG. 26 is an example of (a) and a cross-sectional view (b), and FIG. 26 shows a case in which two steel pipe piles are connected to the lower part when the pile 18 and the upper pillar 1 are not in the same position in plan view. An example of a top view (b) and a cross-sectional view (b) in which an H-shaped steel underground beam is placed on the upper part of the actual steel material 17 and welded. FIG. 27 shows a solid structure in which two steel pipe piles are connected to the lower part when the pile 18 and the upper pillar 1 are not in the same position in plan view but also deviated from the core of the underground beam 28. It is an example of a top view (I) and a cross-sectional view (B) in which an H-shaped steel underground beam is placed on the upper center of the steel material 17 and welded. 25 and 27, the solid steel material 17 connected to the lower part of the steel column 1 is different from the solid steel material 17 connected to the steel pipe pile 18, and the two series are combined. .

実施の形態17
本発明の実施の形態17について説明する。図28は、深さL=0〜5mの比較的浅い所に支持層がある地盤9において、支持層まで掘削した掘削溝9Bの底部に中実鋼材17を設置して鉄骨柱1を立設した断面図を示す。このように、施工すると鉄骨建て方で柱1を高くしても安定化するためには大きな径の中実鋼板17が必要になる。図29に示すように、円筒形又は多角形の鋼製容器50を製作して該円筒形又は多角形の鋼製容器の中に中実鋼材17及び鉄骨柱1を設置し、図30及び図31に示すように、地盤の深さL=0〜5mの浅いところに支持層がある地盤9Aまで掘削して、その底部に必要に応じて捨てコンクリートを敷設して、予め該中実鋼板17と鉄骨柱1の1階下部部分と溶接接合させて置いたものを該円筒形又は多角形の鋼製容器50の中に設置し溶接接合等で固定し、互いに一体化させて、掘削された地盤の底部に設置した後、コンクリート48をその容器50の中に充填してその容器50の重量を増加させて上部鉄骨柱1を安定的に建てる方法を断面図で示す。図29に示すように、鉄骨柱1の1階下部部分及び該円筒形又は多角形の鋼製容器50の高さは鉄骨レベルを測定して必要に応じた切断位置51でその上部1又は50を切断して高さを調整する。尚、該円筒形又は多角形の鋼製容器50の底板は中実鋼材17で代用させて、該円筒形又は多角形の鋼製容器50の側板と中実鋼材17で該鋼製容器50を構成させることも可能である。
Embodiment 17
Embodiment 17 of the present invention will be described. FIG. 28 shows that the steel column 1 is erected by installing the solid steel material 17 at the bottom of the excavation groove 9B excavated to the support layer in the ground 9 having the support layer at a relatively shallow depth L = 0 to 5 m. FIG. Thus, if it constructs, the solid steel plate 17 of a big diameter will be needed in order to stabilize even if it raises the pillar 1 by the steel frame construction method. As shown in FIG. 29, a cylindrical or polygonal steel container 50 is manufactured, and the solid steel material 17 and the steel column 1 are installed in the cylindrical or polygonal steel container. As shown in 31, the solid steel plate 17 is preliminarily excavated to the ground 9A having a support layer at a shallow depth of L = 0 to 5 m and laid with abandoned concrete as needed at the bottom. 1 and the lower part of the first floor of the steel column 1 are welded and placed in the cylindrical or polygonal steel container 50 and fixed by welding or the like, and integrated with each other and excavated. A method of stably building the upper steel column 1 by installing the concrete 48 in the container 50 and increasing the weight of the container 50 after being installed at the bottom of the ground is shown in a sectional view. As shown in FIG. 29, the height of the lower part of the first floor of the steel column 1 and the cylindrical or polygonal steel container 50 is measured at the cutting position 51 according to need by measuring the steel frame level. Cut the and adjust the height. The bottom plate of the cylindrical or polygonal steel container 50 is replaced with a solid steel material 17, and the steel container 50 is replaced with a side plate of the cylindrical or polygonal steel container 50 and the solid steel material 17. It is also possible to configure.

従来の建築鉄骨構造図の一例である。 It is an example of the conventional architectural steel structure diagram . 従来の角形鋼管柱を使った建築鉄骨柱梁接合部即ち仕口部の斜視図である。 It is a perspective view of a building steel beam-to-column connection part, that is, a joint part using a conventional square steel pipe column . 一体化工法を使った柱梁接合部の外観の斜視図である。 It is a perspective view of the appearance of a column beam joint using an integrated construction method . 従来の独立基礎の上に構築した鉄骨建築模式図である。 It is a steel-frame building schematic diagram built on the conventional independent foundation . 従来型の基礎を改良した杭柱一体型の模式図である。 It is a schematic diagram of the pile pillar integrated type which improved the conventional foundation . スクリュー羽根付き円形鋼管杭と角形鋼管柱との間に、6面体の鋼製中実鋼材を挟んで該鋼管杭と該柱を接合した部分断面図であって、(イ)は一個の中実鋼材使用、(ロ)は2枚合わせ中実鋼材使用の図である。 It is a partial cross-sectional view in which a hexagonal steel solid steel material is sandwiched between a circular steel pipe pile with screw blades and a square steel pipe column, and (a) is a solid piece (B) is a diagram of using two solid steel materials . 角形鋼管柱と6面体の鋼製中実鋼材の継手開先ギャップGの調整で、ルーズ裏当金を使って該柱の高さ調整を行う説明図(断面図)である。 It is explanatory drawing (sectional drawing) which adjusts the height of this pillar using a loose backing metal by adjustment of joint groove gap G of a square steel pipe pillar and hexagonal steel solid steel material . 円形鋼管杭と角形鋼管柱との間に、6面体の下端に開先加工した鋼製中実鋼材を挟んで該鋼管杭と該柱を接合した断面図であって、(イ)は一個の中実鋼材使用、(ロ)は2枚合わせ中実鋼材使用の図である。 It is sectional drawing which joined this steel pipe pile and this pillar on both sides of the steel solid steel material which carried out the groove processing at the lower end of a hexahedron between a circular steel pipe pile and a square steel pipe pillar, (B) is a diagram of using two solid steel materials . 円形鋼管杭と角形鋼管柱との間に、鋼製中実鋼材を挟んで1本の鋼管杭と該柱を接合した断面図である It is sectional drawing which joined one steel pipe pile and this pillar on both sides of steel solid steel materials between a circular steel pipe pile and a square steel pipe pillar. 円形鋼管杭と角形鋼管柱との間に、鋼製中実鋼材を挟んで2本の鋼管杭と該柱を接合した断面図である It is sectional drawing which joined two steel pipe piles and this pillar on both sides of steel solid steel materials between a circular steel pipe pile and a square steel pipe pillar. 鉛直方向に2つの孔を開けた1枚の中実鋼材17の孔の上に、中実鋼材17Aをそれぞれ1枚合計2枚載せて、中実鋼材17の中央孔17Hを通して、その2枚の中実鋼材17Aの中央開口部にそれぞれ2本の基礎杭上端を挿入して相互に溶接し、更に中実鋼材17と17Aを溶接接合7した場合の構造の断面図である。 Two solid steel members 17A are placed on each of the holes of one solid steel member 17 having two holes in the vertical direction, and the two pieces are passed through the central hole 17H of the solid steel member 17. It is sectional drawing of a structure at the time of inserting the two foundation pile upper ends in the center opening part of the solid steel material 17A, welding each other, and also welding the solid steel materials 17 and 17A further . 孔を開けた中実鋼材の上に、別の孔を開けた中実鋼材を上に重ねて載せて、1本の鋼管杭を下側の中実鋼材の孔に挿入して中実鋼板と鋼管杭を溶接接合し、もう1本の鋼管杭を下側の中実鋼材の孔を通して上側の中実鋼材の孔に挿入して中実鋼板と鋼管杭を溶接接合する場合の構造の断面図であるPlace a solid steel material with another hole on top of the solid steel material with a hole on it, insert one steel pipe pile into the hole in the lower solid steel material, Sectional view of the structure when a steel pipe pile is welded and another steel pipe pile is inserted into the hole of the upper solid steel through the hole of the lower solid steel and the solid steel plate and the steel pipe pile are welded It is . 図12の場合で、上側の中実鋼材には孔が開けてない場合を示す断面図である。FIG. 13 is a cross-sectional view showing the case where no hole is formed in the upper solid steel material in the case of FIG. 12. 2枚の中実鋼材の上下位置関係が図11と反対になっている断面図であるFIG. 12 is a cross-sectional view in which the vertical positional relationship between two solid steel materials is opposite to that in FIG. 11. 中実鋼材に地中梁を付けた断面図である。 It is sectional drawing which attached the underground beam to the solid steel material . 中実鋼材に地中梁を付けた上面図である。 It is the top view which attached the underground beam to the solid steel material . 中実鋼材に地中梁を付けた上面図である。 It is the top view which attached the underground beam to the solid steel material . 中実鋼材に地中梁を付け地中梁から鉄骨柱を建てる断面図である。 It is sectional drawing which attaches an underground beam to a solid steel material and builds a steel column from an underground beam . 中実鋼材に地中梁を付けモルタル、コンクリート等で掘削部を充填する断面図である。 It is sectional drawing which fills an excavation part with a mortar, concrete, etc. with an underground beam attached to a solid steel material . 基礎底盤に鋼管杭に固定した水平翼等を設置する断面図である。 It is sectional drawing which installs the horizontal wing | blade etc. which were fixed to the steel pipe pile in the foundation bottom board . 基礎底盤の上下中央に鋼管杭に固定した水平翼等を設置する断面図である。 It is sectional drawing which installs the horizontal wing | blade etc. which were fixed to the steel pipe pile in the center of the foundation bottom . 中実鋼板の上に建てた1階鉄骨柱のゼロ柱上部の溶接である。 It is welding of the upper part of the zero column of the 1st floor steel column built on the solid steel plate . 比較的浅いところに地盤の支持力があり、鋼管杭を無くして地中梁を設置する断面図である。 It is a cross-sectional view in which there is a ground supporting force at a relatively shallow place, and the underground beam is installed without the steel pipe pile . 比較的浅いところに地盤の支持力があり、鋼管杭を無くしてラップコンクリートと地中梁を設置する断面図である。 It is a cross-sectional view where there is a supporting force for the ground in a relatively shallow place, and steel pipe piles are eliminated and lap concrete and underground beams are installed . 1柱1杭で杭と上部柱が平面視で同位置でない場合に1本の鋼管杭を下部に繋げた該中実鋼材の上部にH形鋼地中梁を載せて溶接接合させた図である。 In Figure pile upper Columns 1 Column 1 pile is one of the steel pipe pile at the top of the middle actual steel obtained by connecting the bottom is welded by placing the H-shaped steel underground beams if not the same position in plan view is there. 1柱2杭で杭と上部柱1が平面視で同位置でない場合に2本の鋼管杭を下部に繋げた中実鋼材の上部にH形鋼地中梁を載せて溶接接合させた図である。 In Figure pile upper column 1 at 1 Poster 2 piles has the two steel pipe piles were welded by placing a H-shaped steel underground beam on top of the real steel in which lead to lower if not the same position in plan view is there. 1柱2杭で杭と上部柱が平面視で同位置でなく地中梁の芯からもずれている場合に、2本の鋼管杭を下部に繋げた中実鋼材の上部中央にH形鋼地中梁を載せて溶接接合させた図である。 When the pile and the upper column are not in the same position in plan view but are shifted from the core of the underground beam in one pillar and two piles, the H-section steel is in the upper center of the solid steel material with two steel pipe piles connected to the lower part. It is the figure which put the underground beam and was joined by welding . 比較的浅い所に支持層がある地盤において、支持層まで掘削した掘削溝の底部に中実鋼材を設置して鉄骨柱1を立設した断面図である。 FIG. 3 is a cross-sectional view of a steel column 1 erected by installing a solid steel material at the bottom of an excavation groove excavated to the support layer in a ground having a support layer in a relatively shallow place . 円筒形又は多角形の鋼製容器を製作して該円筒形又は多角形の鋼製容器の中に中実鋼材17及び鉄骨柱1を設置した断面図である。 It is sectional drawing which manufactured the cylindrical or polygonal steel container, and installed the solid steel material 17 and the steel column 1 in this cylindrical or polygonal steel container . 比較的浅い所に支持層がある地盤において、支持層まで掘削した掘削溝の底部に鋼製容器の中に中実鋼材を設置して鉄骨柱1を立設した断面図である。 It is sectional drawing which installed the solid steel material in the steel container in the bottom part of the excavation groove excavated to the support layer, and stood the steel column 1 in the ground which has a support layer in a comparatively shallow place . 比較的浅い所に支持層がある地盤において、支持層まで掘削した掘削溝の底部に鋼製容器の中に中実鋼材を設置して鉄骨柱1を立設し、更に、地中梁を設置した断面図である。 In a ground with a support layer in a relatively shallow place, a solid steel material is installed in a steel container at the bottom of the excavation groove drilled to the support layer, and a steel column 1 is installed, and an underground beam is installed. FIG .

1 建築鉄骨柱
1A 建築鉄骨1階上部柱
1B 建築鉄骨1階下部柱
2 建築鉄骨梁
3 建築鉄骨梁仕口部
4 鉄骨建築基礎
5 ダイアフラム
6 柱短管
7 溶接又は溶接部
7B 突合せ溶接部
7F すみ肉溶接部
7S スロット溶接
7C 1階柱同士の溶接
8 基礎柱又は基礎杭
9 地盤
9A 支持力のある地盤
9B 掘削部
10 コンクリート定盤又は基礎
10A 捨てコンクリート
11 基礎梁、地中梁、地表梁
11F 梁フランジ
11W 梁ウエブ
12 ベースプレート
12S スペーサ
13 アンカーボルト
14 ナット
15 ボルト
16 杭フランジ
17 サイコロ又は中実鋼材
17A リング状中実鋼材又はアウターリング
17H 貫通孔
17J 別の貫通孔
18 鋼管杭
19 スクリュー羽根
20 ルーズ裏当金又はルーズ短管又は水平ディスク
21 仮止めピース(ウマ)
22 テーパ
23 短管
24 プレビード(肉盛)
25 開先
26 柱1の中心線
27 杭18の中心線
28 H形鋼又は角形鋼管又は鋼板による梁
29 剛接合柱又はピン接合の間柱
30 中実鋼材の上面に溶接接合させたフランジ
31 柱の下面に溶接接合させたフランジ
32 鋼板製垂直翼
33 鋼板又はH形鋼又は角形鋼管製水平翼
34 垂直翼及び水平翼を取り付ける鋼管
35 鋼管杭に掛かる鉛直力
36 鋼管杭に掛かる曲げモーメント
37 ブレース
38 ルーズ裏当金又はルーズ短管又は水平ディスク
39 裏当金
40 仮付溶接
41 上下の高さ調整
42 左右の位置調整
43 インナーリング
44 鋼管杭側面に取り付けた鋼板又はらせん板
45 円板
46 スティフナー
47 組立用ストッパー
48 セメント又はコンクリート又は鉄琴コンクリート
49 ラップルコンクリート
50 円筒形又は多角形容器
51 切断位置又は高さ
1 Building Steel Column 1A Building Steel 1st Floor Upper Column 1B Building Steel 1st Floor Lower Column 2 Building Steel Beam 3 Building Steel Beam Joint 4 Steel Building Foundation 5 Diaphragm 6 Column Short Tube 7 Weld or Weld 7B Butt Weld 7F Meat welded portion 7S Slot welded 7C Welding between first-floor columns 8 Foundation column or foundation pile 9 Ground 9A Supporting ground 9B Excavated portion 10 Concrete surface plate or foundation 10A Abandoned concrete 11 Foundation beam, underground beam, ground beam 11F Beam flange 11W Beam web 12 Base plate 12S Spacer 13 Anchor bolt 14 Nut 15 Bolt 16 Pile flange 17 Dice or solid steel material 17A Ring-shaped solid steel material or outer ring 17H Through hole 17J Another through hole 18 Steel pipe pile 19 Screw blade 20 Loose Back metal or loose short tube or horizontal disk 21 Temporary fastening piece (horse)
22 Taper 23 Short tube 24 Pre-bead
25 Groove 26 Center line 27 of column 1 Center line 28 of pile 18 Beam made of H-shaped steel, square steel pipe or steel plate 29 Rigidly connected column or pin-connected intermediate column 30 Flange 31 welded to the upper surface of solid steel material 31 Flange 32 welded to the lower surface 33 Steel plate vertical blade 33 Horizontal plate 34 made of steel plate or H-shaped steel or rectangular steel pipe Steel pipe 35 to which the vertical blade and horizontal blade are attached 35 Vertical force applied to the steel pipe pile 36 Bending moment 37 applied to the steel pipe pile Loose backing metal or loose short pipe or horizontal disk 39 Backing metal 40 Temporary welding 41 Vertical height adjustment 42 Left and right position adjustment 43 Inner ring 44 Steel plate or spiral plate 45 attached to the side of steel pipe pile 45 Disc 46 Stiffener 47 Stopper for assembly 48 Cement or concrete or lyre concrete 49 Wrap concrete 50 Cylindrical or polygonal 51 cutting position or height

Claims (8)

建築鉄骨構造物において、圧延・鍛造又は鋳造による中実鋼材を介在させて、地盤に立設後に所定の高さで切断した複数の鋼管杭と、角形鋼管、丸形鋼管又はH形鋼の鉄骨柱とを建設地において溶接により接合させることにより、鉄骨構造物を製作する方法であって、
前記中実鋼材として、前記各鋼管杭の上端部の外径よりも大きな内径の複数の貫通孔を有する第1中実鋼材と、前記各鋼管杭の上端部の外側に嵌合可能な複数のリング状の第2中実鋼材とを準備する工程と、
地盤に立設後に所定の高さで切断した複数の前記鋼管杭の上端部に、第1中実鋼材を前記各貫通孔を前記各鋼管杭の外側に貫通させて配置する工程と、
各第2中実鋼材を前記各鋼管杭の上端部の外側に嵌合させて第1中実鋼材の上側に配置する工程と、
各第2中実鋼材と前記各鋼管杭とを溶接により固定する工程と、
各第2中実鋼材と第1中実鋼材とを溶接により固定する工程と、
前記鉄骨柱と第1中実鋼材とを溶接により固定する工程と、
を備えていることを特徴とする鉄骨構造物を製作する方法。
In building steel structures, a plurality of steel pipe piles that are cut at a predetermined height after standing on the ground with a solid steel material by rolling, forging or casting, and a steel pipe of square steel pipe, round steel pipe or H-shaped steel A method of manufacturing a steel structure by joining a pillar to a construction site by welding,
As the solid steel material, a first solid steel material having a plurality of through holes having an inner diameter larger than the outer diameter of the upper end portion of each steel pipe pile, and a plurality of pieces that can be fitted to the outside of the upper end portion of each steel pipe pile. Preparing a ring-shaped second solid steel material;
A step of disposing the first solid steel material by penetrating the through holes to the outside of the steel pipe piles at the upper ends of the steel pipe piles cut at a predetermined height after standing on the ground; and
Fitting each second solid steel material to the outside of the upper end of each steel pipe pile and placing it on the upper side of the first solid steel material;
Fixing each second solid steel material and each steel pipe pile by welding;
Fixing each second solid steel material and the first solid steel material by welding;
Fixing the steel column and the first solid steel material by welding;
A method of manufacturing a steel structure characterized by comprising:
建築鉄骨構造物において、圧延・鍛造又は鋳造による中実鋼材を介在させて、地盤に立設後に所定の高さで切断した複数の鋼管杭と、角形鋼管、丸形鋼管又はH形鋼の鉄骨柱とを建設地において溶接により接合させることにより、鉄骨構造物を製作する方法であって、In building steel structures, a plurality of steel pipe piles that are cut at a predetermined height after standing on the ground with a solid steel material by rolling, forging or casting, and a steel pipe of square steel pipe, round steel pipe or H-shaped steel A method of manufacturing a steel structure by joining a pillar to a construction site by welding,
前記中実鋼材として、前記各鋼管杭の上端部の外径よりも大きな内径の複数の貫通孔を有する第1中実鋼材と、前記各鋼管杭の上端部の外側に嵌合可能な複数のリング状の第2中実鋼材とを準備する工程と、As the solid steel material, a first solid steel material having a plurality of through holes having an inner diameter larger than the outer diameter of the upper end portion of each steel pipe pile, and a plurality of pieces that can be fitted to the outside of the upper end portion of each steel pipe pile. Preparing a ring-shaped second solid steel material;
地盤に立設後に所定の高さで切断した複数の前記鋼管杭の上端部に、各第2中実鋼材を前記各鋼管杭の上端部の外側に嵌合させて配置する工程と、A step of fitting each second solid steel material to the outer side of the upper end of each of the steel pipe piles at the upper end of the plurality of steel pipe piles cut at a predetermined height after standing on the ground; and
第1中実鋼材を前記各貫通孔を前記各鋼管杭の上側に位置させて各第2中実鋼材の上側に配置する工程と、Placing the first solid steel material on the upper side of each steel pipe pile with the respective through holes positioned on the upper side of each second steel pipe pile;
各第2中実鋼材と前記各鋼管杭とを溶接により固定する工程と、Fixing each second solid steel material and each steel pipe pile by welding;
各第2中実鋼材と第1中実鋼材とを溶接により固定する工程と、Fixing each second solid steel material and the first solid steel material by welding;
前記鉄骨柱と第1中実鋼材とを溶接により固定する工程と、Fixing the steel column and the first solid steel material by welding;
を備えていることを特徴とする鉄骨構造物を製作する方法。A method of manufacturing a steel structure characterized by comprising:
建築鉄骨構造物において、圧延・鍛造又は鋳造による中実鋼材を介在させて、地盤に立設後に所定の高さで切断した複数の鋼管杭と、角形鋼管、丸形鋼管又はH形鋼の鉄骨柱とを建設地において溶接により接合させることにより、鉄骨構造物を製作する方法であって、In building steel structures, a plurality of steel pipe piles that are cut at a predetermined height after standing on the ground with a solid steel material by rolling, forging or casting, and a steel pipe of square steel pipe, round steel pipe or H-shaped steel A method of manufacturing a steel structure by joining a pillar to a construction site by welding,
前記中実鋼材として、前記各鋼管杭うちの1つの前記鋼管杭の上端部の外側に嵌合可能な嵌合孔と他の前記鋼管杭の上端部の外径よりも大きな内径の貫通孔を有する一方の中実鋼材および他方の中実鋼材とを準備する工程と、As the solid steel material, a fitting hole that can be fitted to the outside of the upper end portion of one of the steel pipe piles and a through hole having an inner diameter larger than the outer diameter of the upper end portion of the other steel pipe pile. Preparing one solid steel material and the other solid steel material having,
地盤に立設後に所定の高さで切断した複数の前記鋼管杭の上端部に、一方の中実鋼材を、1つの前記鋼管杭の上端部の外側に前記嵌合孔を嵌合させる一方、他の前記各鋼管杭の上端部の外側に前記各貫通孔を貫通させかつ他の前記各鋼管杭の上端を一方の中実鋼材の上端よりも上方に突出させて配置する工程と、One solid steel material is fitted to the upper ends of the plurality of steel pipe piles cut at a predetermined height after standing on the ground, while the fitting hole is fitted to the outside of the upper end of one steel pipe pile, A step of penetrating each through hole outside the upper end portion of each other steel pipe pile and projecting the upper end of each other steel pipe pile above the upper end of one solid steel material; and
他方の中実鋼材を、他の前記各鋼管杭のうちの1つの前記鋼管杭の上端部の外側に前記嵌合孔を嵌合させる一方、その他の前記各鋼管杭の上側に前記各貫通孔を位置させて一方の中実鋼材の上側に配置する工程と、The other solid steel material is fitted into the fitting hole on the outer side of the upper end portion of one of the other steel pipe piles, while the through holes are formed on the upper side of the other steel pipe piles. And placing it on the upper side of one solid steel material,
一方の中実鋼材と1つの前記鋼管杭とを溶接により固定しかつ他方の中実鋼材と他の前記各鋼管杭のうちの1つの前記鋼管杭とを溶接により固定する工程と、Fixing one solid steel material and one steel pipe pile by welding and fixing the other solid steel material and one of the steel pipe piles by welding;
一方の中実鋼材と他方の中実鋼材とを溶接により固定する工程と、Fixing one solid steel material and the other solid steel material by welding;
前記鉄骨柱と他方の中実鋼材とを溶接により固定する工程と、Fixing the steel column and the other solid steel material by welding;
を備えていることを特徴とする鉄骨構造物を製作する方法。A method of manufacturing a steel structure characterized by comprising:
建築鉄骨構造物において、圧延・鍛造又は鋳造による中実鋼材を介在させて、地盤に立設後に所定の高さで切断した複数の鋼管杭と、角形鋼管、丸形鋼管又はH形鋼の鉄骨柱とを建設地において溶接により接合させることにより、鉄骨構造物を製作する方法であって、In building steel structures, a plurality of steel pipe piles that are cut at a predetermined height after standing on the ground with a solid steel material by rolling, forging or casting, and a steel pipe of square steel pipe, round steel pipe or H-shaped steel A method of manufacturing a steel structure by joining a pillar to a construction site by welding,
前記中実鋼材として、前記各鋼管杭うちの1つの前記鋼管杭の上端部の外側に嵌合可能な嵌合孔と他の前記鋼管杭の上端部の外径よりも大きな内径の貫通孔を有する一方の中実鋼材と、他の前記各鋼管杭のうちの1つの前記鋼管杭の上端部の外側に嵌合可能な他方の中実鋼材とを準備する工程と、As the solid steel material, a fitting hole that can be fitted to the outside of the upper end portion of one of the steel pipe piles and a through hole having an inner diameter larger than the outer diameter of the upper end portion of the other steel pipe pile. Preparing one solid steel material having the other solid steel material that can be fitted to the outside of the upper end portion of one of the other steel pipe piles;
複数の前記鋼管杭を地盤に立設後に、前記各鋼管杭うちの1つの前記鋼管杭の上端の高さを他の前記鋼管杭の上端の高さよりも低くなるように切断する工程と、After standing a plurality of the steel pipe piles on the ground, cutting the height of the upper end of one of the steel pipe piles to be lower than the height of the upper ends of the other steel pipe piles;
地盤に立設後に切断した複数の前記鋼管杭の上端部に、一方の中実鋼材を、1つの前記鋼管杭の上端部の外側に前記嵌合孔を嵌合させかつ当該鋼管杭の上端を一方の中実鋼材の下端以下に位置させる一方、他の前記各鋼管杭の上端部の外側に前記各貫通孔を貫通させかつ他の前記各鋼管杭の上端を一方の中実鋼材の上端よりも上方に突出させて配置する工程と、One solid steel material is fitted to the upper ends of the plurality of steel pipe piles cut after standing on the ground, and the fitting hole is fitted to the outer side of the upper end of one steel pipe pile, and the upper ends of the steel pipe piles are While being positioned below the lower end of one solid steel material, the respective through holes are made to pass outside the upper end portions of the other steel pipe piles, and the upper ends of the other steel pipe piles are made higher than the upper ends of the one solid steel materials. And a step of projecting upward,
他方の中実鋼材を、他の前記各鋼管杭のうちの1つの前記鋼管杭の上端部の外側に前記嵌合孔を嵌合させて一方の中実鋼材の上側に配置する工程と、Placing the other solid steel material on the upper side of one solid steel material by fitting the fitting hole to the outside of the upper end portion of one of the other steel pipe piles;
一方の中実鋼材と1つの前記鋼管杭とを溶接により固定しかつ他方の中実鋼材と他の前記各鋼管杭のうちの1つの前記鋼管杭とを溶接により固定する工程と、Fixing one solid steel material and one steel pipe pile by welding and fixing the other solid steel material and one of the steel pipe piles by welding;
一方の中実鋼材と他方の中実鋼材とを溶接により固定する工程と、Fixing one solid steel material and the other solid steel material by welding;
前記鉄骨柱と他方の中実鋼材とを溶接により固定する工程と、Fixing the steel column and the other solid steel material by welding;
を備えていることを特徴とする鉄骨構造物を製作する方法。A method of manufacturing a steel structure characterized by comprising:
請求項2から請求項4のいずれか1項に記載の発明において、In the invention according to any one of claims 2 to 4,
第2の中実鋼材、一方の中実鋼材または他方の中実鋼材と前記鋼管とを溶接により固定する際に、  When fixing the second solid steel material, one solid steel material or the other solid steel material and the steel pipe by welding,
第2の中実鋼材の内周面と前記鋼管杭の上端とをすみ肉溶接するか、または、一方の中実鋼材の前記嵌合孔あるいは他の中実鋼材の前記嵌合孔と前記鋼管杭の上端とをすみ肉溶接するか、または、第2の中実鋼材の内周面と当該内周面の上端よりもその上端を下側に位置させた前記鋼管杭の上端面と当該鋼管杭の上端部の内側に嵌合され当該鋼管杭の上端よりも上側に位置させた鋼板の外周面とにより形成される環状溝を溶接するか、または、一方の中実鋼材の前記嵌合孔あるいは他の中実鋼材の前記嵌合孔の内周面と当該内周面の上端よりもその上端を下側に位置させた前記鋼管杭の上端と当該鋼管杭の上端部の内側に嵌合され当該鋼管杭の上端よりもその上面を上側に位置させた鋼板の外周面とにより形成される環状溝を溶接することを特徴とする鉄骨構造物を製作する方法。Fillet weld the inner peripheral surface of the second solid steel material and the upper end of the steel pipe pile, or the fitting hole of one solid steel material or the fitting hole of the other solid steel material and the steel pipe Fillet weld the upper end of the pile, or the upper end surface of the steel pipe pile and the steel pipe with the upper end located below the inner peripheral surface of the second solid steel material and the upper end of the inner peripheral surface An annular groove formed by the outer peripheral surface of the steel plate that is fitted inside the upper end of the pile and is located above the upper end of the steel pipe pile is welded, or the fitting hole of one solid steel material Or it fits into the inner peripheral surface of the fitting hole of the other solid steel material and the upper end of the steel pipe pile whose upper end is located below the upper end of the inner peripheral surface and the inner side of the upper end portion of the steel pipe pile. Welding the annular groove formed by the outer peripheral surface of the steel plate with its upper surface positioned above the upper end of the steel pipe pile. Method of fabricating a steel structure to be butterflies.
請求項2または請求項3に記載の発明において、In the invention according to claim 2 or claim 3,
第2の中実鋼材と第1の中実鋼材とを、または、一方の中実鋼材と他方の中実鋼材とを溶接により固定する際に、When fixing the second solid steel material and the first solid steel material, or one solid steel material and the other solid steel material by welding,
第1の中実鋼材の前記貫通孔の内周面、または、他方の中実鋼材の貫通孔の内周面と前記鋼管杭の上端とをすみ肉溶接することを特徴とする鉄骨構造物を製作する方法。A steel structure characterized by fillet welding the inner peripheral surface of the through hole of the first solid steel material or the inner peripheral surface of the through hole of the other solid steel material and the upper end of the steel pipe pile. How to make.
請求項1から請求項6のいずれか1項に記載の発明において、In the invention according to any one of claims 1 to 6,
地表又は地中において水平方向に隣り合った前記中実鋼材に梁を溶接接合させることを特徴とする鉄骨構造物を製作する方法。A method of manufacturing a steel structure characterized by welding a beam to the solid steel material adjacent in the horizontal direction on the ground surface or in the ground.
請求項7に記載の発明において、
前記梁から建築柱を立ち上げることを特徴とする鉄骨構造物を製作する方法。
In the invention of claim 7,
A method of manufacturing a steel structure, wherein a building column is raised from the beam.
JP2006326871A 2006-07-12 2006-12-04 How to make a steel structure Expired - Fee Related JP5007108B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006326871A JP5007108B2 (en) 2006-07-12 2006-12-04 How to make a steel structure

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2006191911 2006-07-12
JP2006191911 2006-07-12
JP2006326871A JP5007108B2 (en) 2006-07-12 2006-12-04 How to make a steel structure

Publications (2)

Publication Number Publication Date
JP2008038586A JP2008038586A (en) 2008-02-21
JP5007108B2 true JP5007108B2 (en) 2012-08-22

Family

ID=39173935

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006326871A Expired - Fee Related JP5007108B2 (en) 2006-07-12 2006-12-04 How to make a steel structure

Country Status (1)

Country Link
JP (1) JP5007108B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103206010A (en) * 2013-03-23 2013-07-17 北京工业大学 Assembled steel structure prestress eccentric bracing frame system
CN103276796A (en) * 2013-06-10 2013-09-04 北京工业大学 Industrialized assembly type special-shaped column steel structure frame-eccentric support system
CN103882940A (en) * 2014-03-20 2014-06-25 北京工业大学 Modularized multi-story and high-rise assembly type steel structure meshed steel beam frame system

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100991341B1 (en) 2008-05-14 2010-11-01 주식회사 중앙씨앤씨 Precast Foundation and Pile Connection Structure between Precast Foundation and Pile
CN102979175B (en) * 2012-11-26 2015-01-14 北京工业大学 Industrialized multi-story high-rise assembled steel structure frame - prestressed eccentrically-braced system
JP6260906B2 (en) * 2013-09-27 2018-01-17 株式会社アークリエイト Steel structure pile pillar-to-base beam joint integrated method
CN105298139A (en) * 2015-09-22 2016-02-03 上海十三冶建设有限公司 Modular mounting method of large space division cooling box steel structure
CN109235640B (en) * 2018-06-05 2023-10-27 北京交通大学 Pin type connecting structure between modularized steel structural members for building
JP6988051B2 (en) * 2018-11-26 2022-01-05 株式会社竹中工務店 Pile head joint structure
JP2020165078A (en) * 2019-03-28 2020-10-08 日鉄建材株式会社 Rising member, foundation structure and construction method thereof
JP7377617B2 (en) * 2019-03-28 2023-11-10 日鉄建材株式会社 Connection structure, foundation structure, and construction method of foundation structure
JP7377616B2 (en) * 2019-03-28 2023-11-10 日鉄建材株式会社 Height adjustment member, foundation structure, and height adjustment method of rising member
CN110080558A (en) * 2019-04-29 2019-08-02 王少雄 The Anti-Typhoon house that can detachably repair more Dai Tongtang of multi-layer energy-saving antidetonation

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04315620A (en) * 1991-04-16 1992-11-06 Asahi Chem Ind Co Ltd Foundation structure for steel-framed building
JP2000034732A (en) * 1998-07-16 2000-02-02 High Frequency Heattreat Co Ltd Steel column mounting hardware, steel column mounting structure and steel column building method
JP2000282457A (en) * 1999-03-29 2000-10-10 Kawasaki Steel Corp Base for steel pipe pile
JP4748496B2 (en) * 2001-09-06 2011-08-17 旭化成建材株式会社 Joint structure of steel pipe pile and concrete foundation
JP2004324361A (en) * 2003-04-28 2004-11-18 Masakatsu Uchida Uneven beam field execution method of steel framed structure
JP3987470B2 (en) * 2003-09-02 2007-10-10 株式会社アークリエイト Integration method for steel beam-column joints
JP4144667B2 (en) * 2003-09-03 2008-09-03 大成建設株式会社 Joining method of jacket structure and pile

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103206010A (en) * 2013-03-23 2013-07-17 北京工业大学 Assembled steel structure prestress eccentric bracing frame system
CN103206010B (en) * 2013-03-23 2015-11-25 北京工业大学 A kind of assembling type steel structure prestressing force accentric support frame system
CN103276796A (en) * 2013-06-10 2013-09-04 北京工业大学 Industrialized assembly type special-shaped column steel structure frame-eccentric support system
CN103276796B (en) * 2013-06-10 2015-03-04 北京工业大学 Industrialized assembly type special-shaped column steel structure frame-eccentric support system
CN103882940A (en) * 2014-03-20 2014-06-25 北京工业大学 Modularized multi-story and high-rise assembly type steel structure meshed steel beam frame system

Also Published As

Publication number Publication date
JP2008038586A (en) 2008-02-21

Similar Documents

Publication Publication Date Title
JP5007108B2 (en) How to make a steel structure
JP6260906B2 (en) Steel structure pile pillar-to-base beam joint integrated method
JP5693140B2 (en) Artificial ground such as road and its construction method
JP4861640B2 (en) How to make a steel structure
KR101006411B1 (en) System and method for underground downward construction using concrete filled tube
KR100856723B1 (en) System and method for underground downward construction using cantilever type steel frame
JP5456627B2 (en) Connection structure and method of connection between pile and steel column
JP2006316495A (en) Foundation structure of bridge pier and its construction method
JP5607384B2 (en) Construction method for beam-column joints
JP4628838B2 (en) Steel foundation structure
JP3162264U (en) Support pile structure
JP2009013616A (en) Long span structure building
JP2021031926A (en) Steel structure pile/column joint integrated column base structure without underground beam
JP2002242302A (en) Beam-column connection structure of building steel frame and its connecting method
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JP4614159B2 (en) Joining structure and joining method of steel pipe pile and steel column
KR101762207B1 (en) The speed up construction method using hemispherical joint
KR102523155B1 (en) Connecting structure of middle girder and construction method thereof
JP2006188862A (en) Construction method of structure, and foundation structure used for the same
JP2007051500A (en) Joint structure of column and pile
JPH07268880A (en) Base footing and footing beam structure
JPS6026724A (en) Integration work of steel-framed building structure and composite underground beam
JP2017096087A (en) Structure of foundation and foundation structure
JP2000027291A (en) Structure of steel framed building
JP2967530B2 (en) Basement building construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090713

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110913

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20111011

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120515

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120528

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150601

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5007108

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

LAPS Cancellation because of no payment of annual fees
R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370