JP4918378B2 - Construction method of trapezoidal CSG dam - Google Patents

Construction method of trapezoidal CSG dam Download PDF

Info

Publication number
JP4918378B2
JP4918378B2 JP2007051759A JP2007051759A JP4918378B2 JP 4918378 B2 JP4918378 B2 JP 4918378B2 JP 2007051759 A JP2007051759 A JP 2007051759A JP 2007051759 A JP2007051759 A JP 2007051759A JP 4918378 B2 JP4918378 B2 JP 4918378B2
Authority
JP
Japan
Prior art keywords
csg
layer
layers
construction
dam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2007051759A
Other languages
Japanese (ja)
Other versions
JP2008214914A (en
Inventor
侃彦 藤澤
淳美 樋口
Original Assignee
財団法人ダム技術センター
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 財団法人ダム技術センター filed Critical 財団法人ダム技術センター
Priority to JP2007051759A priority Critical patent/JP4918378B2/en
Publication of JP2008214914A publication Critical patent/JP2008214914A/en
Application granted granted Critical
Publication of JP4918378B2 publication Critical patent/JP4918378B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

本発明は、CSGで築造される台形CSGダムの施工方法の改良に関する。   The present invention relates to an improvement in a method for constructing a trapezoidal CSG dam constructed by CSG.

CSGは、ダム建設現場(付近を含む。)で得られる天然の岩石を材料(現地発生材料)とし、この現地発生材料に少量のセメントを加えて混合したものを意味し、CSG(Cemented Sand and Gravel)と呼称される。   CSG means natural rocks obtained at the dam construction site (including the vicinity) as a material (locally generated material), a small amount of cement added to this locally generated material, and mixed. CSG (Cemented Sand and Gravel).

CSGでは、材料がダムサイト近傍で調達できて材料の調達コスト及び運搬コストを押さえることができるため、建設コストの削減が容易に図れる。また、セメントの量を最小限に抑えることで、セメントの調達費用を圧縮することができる。   In CSG, materials can be procured in the vicinity of the dam site, and the procurement cost and transportation cost of the material can be suppressed. Therefore, the construction cost can be easily reduced. In addition, cement procurement costs can be reduced by minimizing the amount of cement.

一方、ダムには多様の形式があるが、その中に、断面が台形形状を呈する、台形ダムが含まれる。この台形ダムをCSGで築造する施工方法が知られている(例えば、特許文献1参照。)。
特開2005−163283公報(図11、図12)
On the other hand, there are various types of dams, including trapezoidal dams having a trapezoidal cross section. A construction method for constructing this trapezoidal dam with CSG is known (for example, see Patent Document 1).
Japanese Patent Laying-Open No. 2005-163283 (FIGS. 11 and 12)

特許文献1を次図に基づいて説明する。
図7は従来の技術の基本原理を説明する図であり、先ず、(a)に示すように、CSGの第1層101を打設する。次に、(b)に示すようにプレキャスト型枠102を設置する。このプレキャスト型枠102は、第1層101の高さ(厚さ)の2倍の高さを有する。次に(c)に示すように、第1層101上にCSGの第2層103を打設する。この第2層103の上面とプレキャスト型枠102の上面とは同一高さになる。そこで、プレキャスト型枠102と第1・第2層101、103との間に保護コンクリート104を打設する。これで、1施工サイクルを終了する。
Patent document 1 is demonstrated based on the following figure.
FIG. 7 is a diagram for explaining the basic principle of the prior art. First, as shown in FIG. 7A, a first layer 101 of CSG is placed. Next, the precast formwork 102 is installed as shown in FIG. The precast formwork 102 has a height that is twice the height (thickness) of the first layer 101. Next, as shown in (c), a second layer 103 of CSG is placed on the first layer 101. The upper surface of the second layer 103 and the upper surface of the precast formwork 102 have the same height. Therefore, protective concrete 104 is placed between the precast formwork 102 and the first and second layers 101 and 103. This completes one construction cycle.

(a)、(b)に1日、(c)、(d)に1日掛ければ、1施工サイクルは、2日で完了する。このような施工サイクルを、繰り返すことで、必要な高さのダムが出来上がる。
例えば、第1・第2層101、103の合計高さが1mで、ダムの高さが50mであれば、50回施工サイクルを繰り返せばよく、計算上は100日でダムが完成することになる。
If (a) and (b) take one day and (c) and (d) take one day, one construction cycle is completed in two days. By repeating such a construction cycle, a dam with the required height is completed.
For example, if the total height of the first and second layers 101 and 103 is 1 m and the height of the dam is 50 m, the construction cycle may be repeated 50 times, and the dam will be completed in 100 days in calculation. Become.

従来の技術にはCSGで築造するため、ダムの建造コストを下げることができると共に、施工サイクルが明確であるため、工期の計算が容易になるという利点がある。しかし、現実に施工すると、次に述べる問題があることが判明した。   Since the conventional technique is constructed by CSG, it has the advantage that the construction cost of the dam can be reduced and the construction cycle is clear, so that the construction period can be easily calculated. However, when actually constructed, it was found that there were the following problems.

図8は台形CSGダムの正面図であり、台形CSGダム110は、谷川111をせき止める堰であるため、谷川111の上流側(又は下流側)から見ると、ほぼ逆三角形状を呈する。
図9は図8の9−9線断面図、すなわち、上流から下流へ切断した断面図であり、台形CSGダム110は、上部が狭く、下部が広い台形断面を呈する。
FIG. 8 is a front view of the trapezoidal CSG dam, and the trapezoidal CSG dam 110 is a weir that dams the Tanigawa 111, and thus has a substantially inverted triangular shape when viewed from the upstream side (or downstream side) of the Tanigawa 111.
FIG. 9 is a cross-sectional view taken along line 9-9 of FIG. 8, that is, a cross-sectional view cut from upstream to downstream. The trapezoidal CSG dam 110 has a trapezoidal cross section with a narrow upper part and a wide lower part.

図10は台形断面を簡略化した図であり、台形CSGダムは(a)に示されるように、上流側から見た形状は、底辺の長さがaで、高さがhである逆三角形113とみなすことができる。そして、(b)に示されるように、上流から下流へ切断した断面の形状は、底辺の長さがbで、高さがhである三角形114とみなすことことができる。   FIG. 10 is a simplified view of a trapezoidal cross section. As shown in FIG. 10A, the trapezoidal CSG dam has an inverted triangle with a base length a and a height h as seen from the upstream side. 113. As shown in (b), the shape of the cross section cut from the upstream to the downstream can be regarded as a triangle 114 having a base length of b and a height of h.

なお、三角形の頂点が上位で同底辺が下位である「三角形」に対して、「逆三角形」は底辺が上位で頂点が下位であって、「三角形」に対して上下が「逆」になっているものをいう。   In contrast to the “triangle” where the vertex of the triangle is higher and the base is lower, the “inverted triangle” is the upper base and the vertex is lower. Say what you are.

逆三角形113の頂点並びに三角形114の底辺を通る横線から直角に立ち上がる縦線をx軸としたときに、xは0からhまで変化する。任意のxを通る横線115で切断される線分の長さを各々a1、b1とする。横線115で切断された面の面積をyとすれば、この面積yは、(c)に示されるように、縦がa1で横がb1の長方形で表される。すなわちy=a1×b1となる。   When the vertical line rising perpendicularly from the horizontal line passing through the apex of the inverted triangle 113 and the base of the triangle 114 is taken as the x axis, x changes from 0 to h. The lengths of the line segments cut by the horizontal line 115 passing through arbitrary x are a1 and b1, respectively. Assuming that the area of the surface cut by the horizontal line 115 is y, the area y is represented by a rectangle with a1 in the vertical direction and b1 in the horizontal direction, as shown in (c). That is, y = a1 × b1.

(a)における逆三角形113では、a1:a=x:hの比例関係が成立し、a1=(ax/h)と整理することができる。
(b)における三角形114では、b1:b=(h−x):hの比例関係が成立し、b1=b(h−x)/hと整理することができる。
a1×b1は、(ax/h)・b(h−x)/h=x(h−x)・(ab/h)となる。(ab/h)は常数であるから、これを常数αに置き換える。
In the inverted triangle 113 in (a), a proportional relationship of a1: a = x: h is established, and can be arranged as a1 = (ax / h).
In the triangle 114 in (b), a proportional relationship of b1: b = (h−x): h is established, and can be arranged as b1 = b (h−x) / h.
a1 × b1 is (ax / h) · b (h−x) / h = x (h−x) · (ab / h 2 ). Since (ab / h 2 ) is a constant, it is replaced with a constant α.

以上の結果、面積yは、y=αx(h−x)=−αx+αhxで表される2次関数となる。この2次関数は、x=0とx=hでy=0となり、xの符号が負(−)であるため、図11に示すような、上に凸の2次関数曲線になる。 As a result, the area y is a quadratic function represented by y = αx (h−x) = − αx 2 + αhx. The secondary function, x = 0 and x = h at y = 0, and the sign of x 2 is negative (-) because it is, as shown in FIG. 11, the quadratic function curve convex upward.

図12は台形CSGダムの平断面の面積を説明する図であり、(a)に示される三角形114に、(b)に示されるグラフを添えた。このグラフは横軸がy軸で、縦軸がx軸であるため、2次関数曲線は右へ凸になっている。   FIG. 12 is a diagram for explaining the area of the flat cross section of the trapezoidal CSG dam. The triangle 114 shown in (a) is accompanied by the graph shown in (b). In this graph, since the horizontal axis is the y-axis and the vertical axis is the x-axis, the quadratic function curve is convex to the right.

この2次関数曲線は台形CSGダムを水平線で分割したときの各層の面積に相当し、各層に打設するCSGの打設量を表している。
縦軸でh/2の高さで、CSGの打設量が最大となる。
This quadratic function curve corresponds to the area of each layer when the trapezoidal CSG dam is divided by a horizontal line, and represents the amount of CSG to be placed on each layer.
The amount of CSG placement is maximized at a height of h / 2 on the vertical axis.

そこで、横軸に印したY/2の面積を賄うことができるCSG供給設備を、2基準備した。2基でYの面積を賄うことができるからである。
そして、縦軸で、高さ0〜P1の範囲では、1基のCSG供給設備だけを運転する。高さP1〜P2の範囲では、2基のCSG供給設備を運転する。高さP2〜hの範囲では、1基のCSG供給設備だけを運転する。1基のCSG供給設備を適宜休止させることで、設備の効率化を図ることができる。
Therefore, two CSG supply facilities that can cover the area of Y / 2 marked on the horizontal axis were prepared. This is because the area of Y can be covered with two units.
Then, on the vertical axis, only one CSG supply facility is operated in the range of height 0 to P1. In the range of the heights P1 to P2, two CSG supply facilities are operated. In the range of the heights P2 to h, only one CSG supply facility is operated. By efficiently suspending one CSG supply facility, the efficiency of the facility can be improved.

しかし、斜線部116、117、118及び119は、CSG供給設備が無駄に運転され、設備の稼働有効率が低下する。この結果、台形CSGダムの建造コストが嵩むことになる。
斜線部116、117、118及び119を圧縮又はゼロにすることができることが望まれる。
However, in the hatched portions 116, 117, 118, and 119, the CSG supply facility is wasted, and the operation efficiency rate of the facility is reduced. As a result, the construction cost of the trapezoidal CSG dam increases.
It is desirable that the shaded portions 116, 117, 118 and 119 can be compressed or made zero.

本発明は、台形CSGダムの築造において、CSG供給設備の稼働有効率を向上させることができるダムの施工方法を提供することを課題とする。   This invention makes it a subject to provide the construction method of the dam which can improve the operation | use effective rate of a CSG supply facility in construction of a trapezoidal CSG dam.

請求項1に係る発明は、上流側から見た形状が逆三角形に近似し、上流から下流へ切断した断面の形状が台形形状をしているダムを、CSGと呼ばれる材料で築造するときの施工方法であって、
1層の高さが500mm〜1000mmのCSG層を、順次打設してダムを築造するために、毎時間当たり一定量のCSGを供給するCSG供給設備を準備し、前記CSG層の2層分の高さのプレキャスト型枠を準備し、2層分のCSG層と前記プレキャスト型枠との間に流し込む保護コンクリート材を準備しておき、
任意のCSG層をn層、このn層の上に打設されるCSG層を(n+1)層、この(n+1)層の上に打設されるCSG層を(n+2)層のように多数層を順に呼び、前記n層が複数の工区で施工され、前記(n+1)層及び(n+2)層も同様に複数の工区で施工され、前記プレキャスト型枠及び前記保護コンクリート材の施工も複数の工区で施工されるときに、
前記プレキャスト型枠を、設置する型枠設置工程と、
この型枠設置工程の1区の施工が完了したときから、毎時間当たり一定量のCSGの供給を受けて前記n層のCSG層を連続して打設するn層CSG打設工程と、
このn層CSG打設工程に引き続いて、毎時間当たり一定量のCSGの供給を受けて前記(n+1)層のCSG層を連続して打設する(n+1)層CSG打設工程と、
この(n+1)層CSG打設工程の1区の施工が完了したときから、2層分のCSG層と前記プレキャスト型枠との間に前記保護コンクリート材を打設するコンクリート打設工程とを実施することで、前記CSG打設工程を連続して実施することを特徴とする。
The invention according to claim 1 is a construction for constructing a dam made of a material called CSG in which the shape viewed from the upstream side approximates an inverted triangle and the cross-sectional shape cut from the upstream to the downstream has a trapezoidal shape. A method,
In order to construct a dam by sequentially placing CSG layers with a height of 500 mm to 1000 mm, a CSG supply facility for supplying a constant amount of CSG per hour is prepared. Prepare a precast formwork of height, prepare a protective concrete material to be poured between the two CSG layers and the precast formwork,
Arbitrary CSG layers are n layers, CSG layers placed on the n layers are (n + 1) layers, and CSG layers placed on the (n + 1) layers are many layers such as (n + 2) layers. the turn call, the n layer is applied by a plurality of work area, the (n + 1) layer and (n + 2) layers are also applied by a plurality of work area as well, the construction also several of the precast mold and the protective concrete material When it is constructed in the work area ,
A mold installation step for installing the precast mold, and
When the construction of the first section of this formwork installation process is completed, an n-layer CSG placement process in which a constant amount of CSG is supplied per hour to continuously place the n-layer CSG layer;
Subsequent to the n-layer CSG placement step, the (n + 1) -layer CSG placement step is performed by receiving a constant amount of CSG per hour and continuously placing the (n + 1) -layer CSG layers;
After the completion of the first section of the (n + 1) layer CSG placing process, the concrete placing process for placing the protective concrete material between the two CSG layers and the precast formwork is performed. By applying, the CSG placing step is continuously performed.

請求項1に係る発明によれば、CSG打設工程の連続実施が可能となった。CSG打設工程は、毎時間当たり一定量のCSGの供給を受けて連続的に実施する。
CSGの供給が過剰になる心配はない。この結果、CSG供給設備を最大限有効に活用することができ、台形CSGダムの築造コストを下げることができる。
According to inventions described in claim 1, it enabled the continuous implementation of about C SG strokes設工. The CSG placement process is continuously performed with a constant amount of CSG supplied per hour.
There is no worry of excessive CSG supply. As a result, the CSG supply facility can be utilized to the maximum extent, and the construction cost of the trapezoidal CSG dam can be reduced.

本発明を実施するための最良の形態を添付図に基づいて以下に説明する。なお、図面は符号の向きに見るものとする。
図1はある層の平面断面図であり、台形CSGダムのある層(例えばn層)の平面断面形状を、縦がa1で横がb1である長方形に簡略化して示した図である。図の左から右へ施工を進めるものとして、1区〜4区の工区を定める。なお、工区の数は任意であるがここでは、便宜上4とした。
The best mode for carrying out the present invention will be described below with reference to the accompanying drawings. The drawings are viewed in the direction of the reference numerals.
FIG. 1 is a plan sectional view of a certain layer, and is a diagram showing the planar sectional shape of a certain layer (for example, n layer) of a trapezoidal CSG dam in a simplified form of a rectangle having a length of a1 and a width of b1. Establishing the 1st to 4th work zones as the work proceeding from left to right in the figure. In addition, although the number of construction zones is arbitrary, it was set to 4 here for convenience.

図2は本発明に係る台形CSGダムの施工工程図であり、横軸が時間軸である。この時間軸の下の第1行は型枠工(プレキャスト型枠設置工程)、第2行はCSG工(CSG打設工程)、第3行はコンクリート工(保護コンクリート打設工程)を示す。
時間軸に付したT1〜T8の時点における施工状態を、図3以降で詳しく説明する。
FIG. 2 is a construction process diagram of the trapezoidal CSG dam according to the present invention, and the horizontal axis is the time axis. The first line below the time axis shows the formwork (precast formwork installation process), the second line shows the CSG work (CSG placement process), and the third line shows the concrete work (protective concrete placement process).
The construction state at the time T1 to T8 attached to the time axis will be described in detail with reference to FIG.

CSG層のn層と(n+1)層とからなる2層分に対応する型枠の層をA層と定義し、(n+2)層と(n+3)層とからなる2層分に対応する型枠の層をB層と定義する。
第1行の型枠工において、時間軸のT0を始点として、A層での1区〜4区のプレキャスト型枠設置を実施する。
A formwork layer corresponding to two layers consisting of n layers and (n + 1) layers of the CSG layer is defined as A layer, and a formwork corresponding to two layers consisting of (n + 2) layers and (n + 3) layers Is defined as layer B.
In the first-line formwork, precast formwork installation in the 1st to 4th districts in the A layer is carried out starting from the time axis T0.

第1行のA層の1区(型枠工)が終了した時点で、第2行のCSG工程では、n層での1区〜4区のCSG打設を開始する。n層の4区の次に、アイドル時間Id1を置くことが望ましい。アイドル時間Id1は、4区から1区へブルドーザや振動ローラなどの重機を回送することや、1区〜4区の施工中に発生した遅れを吸収することを目的に決定される。ただし、アイドル時間Id1は、施工能率の低下に繋がるので、極力短い時間に設定する。同じ理由で、(n+1)層や(n+2)層の4区の次にもアイドル時間Id1を置くことが望ましい。   At the time when the first section (formwork) of the A layer in the first row is completed, in the CSG process in the second row, CSG placement in the first to fourth sections in the n layer is started. It is desirable to set idle time Id1 next to the 4th section of the n layer. The idle time Id1 is determined for the purpose of forwarding a heavy machine such as a bulldozer or a vibrating roller from the 4th ward to the 1st ward and absorbing a delay generated during construction in the 1st to 4th wards. However, the idle time Id1 is set to a time as short as possible because it leads to a decrease in construction efficiency. For the same reason, it is desirable to set the idle time Id1 next to the four sections of the (n + 1) layer and the (n + 2) layer.

アイドル時間Id1の後に、(n+1)層での1区〜4区のCSG打設を実施する。
なお、第2行のCSG工において、n層の打設は、T0から施工することは可能であるが、好ましくは、第1行のA層の1区が終了した時点で、開始する。工区が重複して隣接していると、重機同士の干渉や重機と作業者の干渉が問題となるが、この例のようにA層の工区とn層の工区が異なって離れていれば、重機の扱いが楽になり、労働安全上も好ましい。
After the idle time Id1, CSG placement in the 1st to 4th districts in the (n + 1) layer is performed.
In addition, in the CSG construction in the second row, it is possible to construct the n layer from T0, but preferably, it starts when the first section of the A layer in the first row is completed. If the work zones are overlapped and adjacent, interference between heavy machinery and heavy machinery and workers will be a problem, but if the A-layer work zone and the n-layer work zone are different as in this example, Handling of heavy machinery becomes easier and is preferable from the viewpoint of occupational safety.

第3行のコンクリート工では、第1行のA層に対応する保護コンクリート打設の層をa層と定義し、B層に対応する保護コンクリート打設の層をb層と定義する。
第3行のコンクリート工において、a層のコンクリート打設は、第2行の(n+1)層が始まれば、施工可能である。しかし、好ましくは、第2行の(n+1)層の1区が終了した時点で、開始する。工区が重複して隣接していると、重機同士の干渉や重機と作業者の干渉が問題となるが、この例のように(n+1)層の工区とa層の工区が異なって離れていれば、重機の扱いが楽になり、労働安全上も好ましい。
In the concrete work in the third row, the layer of protective concrete placement corresponding to the A layer in the first row is defined as a layer, and the layer of protection concrete placement corresponding to the B layer is defined as layer b.
In the concrete work in the third row, the concrete placement of the a layer can be performed if the (n + 1) layer in the second row starts. However, it preferably starts when the first section of the (n + 1) layer in the second row is completed. If the work zones overlap and are adjacent, the interference between heavy machinery and the interference between heavy machinery and workers will be a problem. However, as shown in this example, the (n + 1) -layer work zone and the a-layer work zone may be different. This makes it easier to handle heavy machinery and is favorable for occupational safety.

第2行のCSG工において、(n+1)層での1区〜4区のCSG打設を実施し、アイドル時間Id1の後に、(n+2)層での1区〜4区のCSG打設を実施するが、第1行のB層の1区の型枠工が、(n+2)層のCSG打設を実施する前に終了することができるよう、第1行のB層の1区の型枠設置を実施する。
そして、第2行で、(n+2)層での1区〜4区のCSG打設を実施し、アイドル時間Id1の後に、(n+3)層での1区〜4区のCSG打設を実施する。
In CSG construction in the second row, CSG placement for 1st to 4th districts at (n + 1) layer was carried out, and after 1st idle period Id1, CSG placement for 1st to 4th districts at (n + 2) layer was conducted However, the formwork of the 1st row of the B layer in the 1st row can be completed before the CSG placement of the (n + 2) layer is completed. Implement the installation.
Then, in the second row, CSG placement of 1st to 4th districts in the (n + 2) layer is performed, and after the idle time Id1, CSG placement of 1st to 4th districts in the (n + 3) layer is performed. .

第3行のコンクリート工において、b層のコンクリート打設は、第2行の(n+3)層の1区が終了した時点で、開始する。   In the concrete work in the third row, the concrete placement of the b layer starts when the first section of the (n + 3) layer in the second row is completed.

次に、図2のT1〜T8に対応する施工現場の状態を説明する。
図2において、T1では、型枠工のみが実施され、施工はA層の1区の途中まで進んでいる。このときの施工状態は、図3(a)に示されるとおりである。
図2において、T2では、型枠工はA層の2区の途中まで進んでいる。これに並行してCSG工はn層の1区の途中まで進んでいる。このときの施工状態は、図3(b)に示されるとおりである。図3(b)のC矢視図である、図3(c)によれば、n層(CSG層)の両側に所定の間隔L、Lを置いて、左右のA層(プレキャスト型枠)が設置されている。
Next, the state of the construction site corresponding to T1 to T8 in FIG. 2 will be described.
In FIG. 2, at T1, only the formwork is carried out, and the construction has progressed to the middle of the first section of the A layer. The construction state at this time is as shown in FIG.
In FIG. 2, at T2, the formwork has progressed to the middle of the second section of the A layer. In parallel with this, CSG is progressing to the middle of the 1st section of the n layer. The construction state at this time is as shown in FIG. According to FIG. 3 (c), which is a view taken in the direction of arrow C in FIG. 3 (b), left and right A layers (precast formwork) with predetermined intervals L and L on both sides of the n layer (CSG layer). Is installed.

図2において、T3では、CSG工はA層が終了し、CSG工はn層の4区まで進んでいる。このときの施工状態は、図4(a)に示されるとおりである。
図2において、T4では、CSG工は(n+1)層の2区の途中まで進んでいる。さらに、コンクリート工がa層の1区の途中まで進んでいる。このときの施工状態は、図4(b)に示されるとおりである。図4(b)のC矢視図である、図4(c)によれば、n層と(n+1)層とから2層分のCSG工と、左右のA層(プレキャスト型枠)との間に、a層(保護コンクリート)が打設されている。
In FIG. 2, at T3, the ASG layer of the CSG craft has finished, and the CSG craft has advanced to the 4th section of the n-layer. The construction state at this time is as shown in FIG.
In FIG. 2, at T4, the CSG process is progressing to the middle of the second section of the (n + 1) layer. In addition, the concrete work is progressing partway through the first section of the a layer. The construction state at this time is as shown in FIG. According to FIG. 4 (c), which is a C arrow view of FIG. 4 (b), the CSG process for two layers from the n layer and the (n + 1) layer, and the left and right A layers (precast formwork) A layer (protective concrete) is placed between them.

図2において、T5では、CSG工は(n+1)層の打設が終了し、型枠工はB層の1区の途中まで進んでいる。さらに、コンクリート工がa層の4区の途中まで進んでいる。このときの施工状態は、図5(a)に示されるとおりである。
図2において、T6では、型枠工はB層の2区の途中まで進んでいる。これに並行してCSG工は(n+2)層の1区の途中まで進んでいる。このときの施工状態は、図5(b)に示されるとおりである。図5(b)のC矢視図である、図5(c)によれば、(n+2)層(CSG層)の両側に所定の間隔L、Lを置いて、左右のB層(プレキャスト型枠)が設置されている。
In FIG. 2, at T5, the CSG craft has finished placing the (n + 1) layer, and the formwork has progressed partway through the first tier of the B layer. In addition, the concrete works are progressing halfway through the 4th section of the a layer. The construction state at this time is as shown in FIG.
In FIG. 2, at T6, the formwork is progressing to the middle of the second section of the B layer. In parallel with this, CSG is progressing to the middle of the first section of the (n + 2) layer. The construction state at this time is as shown in FIG. According to FIG. 5 (c), which is a view taken in the direction of arrow C in FIG. 5 (b), the left and right B layers (precast type) are placed at predetermined intervals L and L on both sides of the (n + 2) layer (CSG layer). Frame) is installed.

図2において、T7では、型枠工のB層が終了し、CSG工は(n+3)層の1区の途中まで進んでいる。このときの施工状態は、図6(a)に示されるとおりである。
図2において、T8では、CSG工は(n+3)層の2区の途中まで進んでいる。さらに、コンクリート工がb層の1区の途中まで進んでいる。このときの施工状態は、図6(b)に示されるとおりである。図6(b)のC矢視図である、図6(c)によれば、(n+2)層と(n+3)層とから2層分のCSG工と、左右のB層(プレキャスト型枠)との間に、b層(保護コンクリート)が打設されている。
In FIG. 2, at T7, the B layer of the formwork is finished, and the CSG method is progressing to the middle of the first section of the (n + 3) layer. The construction state at this time is as shown in FIG.
In FIG. 2, at T8, the CSG process has progressed to the middle of the second section of the (n + 3) layer. In addition, the concrete work is progressing to the middle of the 1st section of the b layer. The construction state at this time is as shown in FIG. According to FIG. 6 (c), which is a C arrow view of FIG. 6 (b), CSG work for two layers from the (n + 2) layer and the (n + 3) layer, and the left and right B layers (precast formwork) In between, a b layer (protective concrete) is placed.

図2では、CSGの第1層、第2層、第3層・・・第m層を、n層、(n+1)層、(n+2)層、(n+3)層の記載により一般化した。すなわち、CSG工は連続的に施工する。この結果、CSG供給設備を連続的に運転することができ、第1層、第2層、第3層・・・第m層を休み無く打設する。この結果、図12(b)に符号116〜119で示した斜線部、すなわち無駄部分を無くすことができる。したがって、CSGの供給が過剰になる心配はない。この結果、CSG供給設備を最大限有効に活用することができ、台形CSGダムの築造コストを下げることができる。   In FIG. 2, the first layer, the second layer, the third layer,... The mth layer of the CSG are generalized by describing the n layer, the (n + 1) layer, the (n + 2) layer, and the (n + 3) layer. In other words, CSG works continuously. As a result, the CSG supply facility can be operated continuously, and the first layer, the second layer, the third layer,. As a result, the hatched portions indicated by reference numerals 116 to 119 in FIG. Therefore, there is no worry of excessive CSG supply. As a result, the CSG supply facility can be utilized to the maximum extent, and the construction cost of the trapezoidal CSG dam can be reduced.

本発明は、CSGで築造される台形CSGダムに好適である。   The present invention is suitable for a trapezoidal CSG dam constructed by CSG.

ある層の平面断面図である。It is plane sectional drawing of a certain layer. 本発明に係る台形CSGダムの施工工程図である。It is a construction process figure of trapezoid CSG dam concerning the present invention. 図2でのT1、T2に対応する施工状態図である。FIG. 3 is a construction state diagram corresponding to T1 and T2 in FIG. 2. 図2でのT3、T4に対応する施工状態図である。FIG. 3 is a construction state diagram corresponding to T3 and T4 in FIG. 2. 図2でのT5、T6に対応する施工状態図である。FIG. 3 is a construction state diagram corresponding to T5 and T6 in FIG. 2. 図2でのT7、T8に対応する施工状態図である。FIG. 3 is a construction state diagram corresponding to T7 and T8 in FIG. 2. 従来の技術の基本原理を説明する図である。It is a figure explaining the basic principle of the prior art. 台形CSGダムの正面図である。It is a front view of a trapezoid CSG dam. 図8の9−9線断面図である。FIG. 9 is a sectional view taken along line 9-9 in FIG. 8. 台形断面を簡略化した図である。It is the figure which simplified the trapezoid cross section. 上に凸の2次関数曲線図である。It is an upward convex quadratic function curve diagram. 台形CSGダムの平断面の面積を説明する図である。It is a figure explaining the area of the plane cross section of a trapezoid CSG dam.

符号の説明Explanation of symbols

110…台形CSGダム、111…谷川、113…逆三角形、114…三角形、n層、(n+1)層、(n+2)層、(n+3)層…CGS層、A層〜B層…プレキャスト型枠、a層〜b層…保護コンクリート。   110 ... Trapezoid CSG dam, 111 ... Tanikawa, 113 ... Inverted triangle, 114 ... Triangle, n layer, (n + 1) layer, (n + 2) layer, (n + 3) layer ... CGS layer, A layer to B layer ... Precast formwork, Layers a to b ... Protective concrete.

Claims (1)

上流側から見た形状が逆三角形に近似し、上流から下流へ切断した断面の形状が台形形状をしているダムを、CSGと呼ばれる材料で築造するときの施工方法であって、
1層の高さが500mm〜1000mmのCSG層を、順次打設してダムを築造するために、毎時間当たり一定量のCSGを供給するCSG供給設備を準備し、前記CSG層の2層分の高さのプレキャスト型枠を準備し、2層分のCSG層と前記プレキャスト型枠との間に流し込む保護コンクリート材を準備しておき、
任意のCSG層をn層、このn層の上に打設されるCSG層を(n+1)層、この(n+1)層の上に打設されるCSG層を(n+2)層のように多数層を順に呼び、前記n層が複数の工区で施工され、前記(n+1)層及び(n+2)層も同様に複数の工区で施工され、前記プレキャスト型枠及び前記保護コンクリート材の施工も複数の工区で施工されるときに、
前記プレキャスト型枠を、設置する型枠設置工程と、
この型枠設置工程の1区の施工が完了したときから、毎時間当たり一定量のCSGの供給を受けて前記n層のCSG層を連続して打設するn層CSG打設工程と、
このn層CSG打設工程に引き続いて、毎時間当たり一定量のCSGの供給を受けて前記(n+1)層のCSG層を連続して打設する(n+1)層CSG打設工程と、
この(n+1)層CSG打設工程の1区の施工が完了したときから、2層分のCSG層と前記プレキャスト型枠との間に前記保護コンクリート材を打設するコンクリート打設工程とを実施することで、前記CSG打設工程を連続して実施することを特徴とする台形CSGダムの施工方法。
It is a construction method when building a dam with a shape viewed from the upstream side that approximates an inverted triangle and the shape of the cross section cut from the upstream to the downstream has a trapezoidal shape with a material called CSG,
In order to construct a dam by sequentially placing CSG layers with a height of 500 mm to 1000 mm, a CSG supply facility for supplying a constant amount of CSG per hour is prepared. Prepare a precast formwork of height, prepare a protective concrete material to be poured between the two CSG layers and the precast formwork,
Arbitrary CSG layers are n layers, CSG layers placed on the n layers are (n + 1) layers, and CSG layers placed on the (n + 1) layers are many layers such as (n + 2) layers. the turn call, the n layer is applied by a plurality of work area, the (n + 1) layer and (n + 2) layers are also applied by a plurality of work area as well, the construction also several of the precast mold and the protective concrete material When it is constructed in the work area ,
A mold installation step for installing the precast mold, and
When the construction of the first section of this formwork installation process is completed, an n-layer CSG placement process in which a constant amount of CSG is supplied per hour to continuously place the n-layer CSG layer;
Subsequent to the n-layer CSG placement step, the (n + 1) -layer CSG placement step is performed by receiving a constant amount of CSG per hour and continuously placing the (n + 1) -layer CSG layers;
After the construction of the first section of the (n + 1) layer CSG placing process is completed, a concrete placing process for placing the protective concrete material between the two CSG layers and the precast formwork is performed. Thus, the trapezoidal CSG dam construction method, wherein the CSG placing step is continuously performed.
JP2007051759A 2007-03-01 2007-03-01 Construction method of trapezoidal CSG dam Active JP4918378B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007051759A JP4918378B2 (en) 2007-03-01 2007-03-01 Construction method of trapezoidal CSG dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007051759A JP4918378B2 (en) 2007-03-01 2007-03-01 Construction method of trapezoidal CSG dam

Publications (2)

Publication Number Publication Date
JP2008214914A JP2008214914A (en) 2008-09-18
JP4918378B2 true JP4918378B2 (en) 2012-04-18

Family

ID=39835302

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007051759A Active JP4918378B2 (en) 2007-03-01 2007-03-01 Construction method of trapezoidal CSG dam

Country Status (1)

Country Link
JP (1) JP4918378B2 (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005163283A (en) * 2003-11-28 2005-06-23 Okinawa General Bureau Cabinet Office Construction method for compacting top of slope, and top-of-slope compacting equipment for use in it
JP4079435B2 (en) * 2004-03-31 2008-04-23 内閣府沖縄総合事務局長 Construction method of PC inclined formwork and dam body for dam construction

Also Published As

Publication number Publication date
JP2008214914A (en) 2008-09-18

Similar Documents

Publication Publication Date Title
CN103088942A (en) Building structure without form removal
JP2011184969A (en) Method for setting support spacer for continuous reinforced concrete pavement
CN202672335U (en) Pre-tensioned prestressing superposed beam building structural system
CN110284729B (en) Historical building wall block type cutting and dismantling method
JP2008308835A (en) Construction method for sidewall pilot tunnel type tunnel and its structure
JP4918378B2 (en) Construction method of trapezoidal CSG dam
CN103696437A (en) Construction method for cutting latticed column
JP4364816B2 (en) Construction method of the embankment and embankment
JP2009293331A (en) Structure of retaining wall formed of soil improvement object and its construction method
JP7453837B2 (en) Reinforcement structure and reinforcement construction method for concrete structures
JPH0611980B2 (en) Construction method of revetment using natural stone
CN214219934U (en) 3D prints reinforced concrete atress component
JPH08170311A (en) Floor slab with ct type steel
JP3133417U (en) Paving stone blocks
CN210013190U (en) Rock-fill concrete stacked structure and rock-fill concrete dam body
JP4929814B2 (en) Construction work and construction method
JP6882024B2 (en) Joining structure of precast concrete slab and construction method of precast concrete slab
Ivaniuk et al. Automated manufacturing of reinforced modules of segmented shells based on 3D printing with strain-hardening cementitious composites
CN217268169U (en) Cross wall body group building structure
CN111139832B (en) Pouring template system for concrete cushion layer of river dike and dyke and construction method
JP3480614B2 (en) Construction method at the border between adjacent construction zones when constructing a dam body
JP7350651B2 (en) slab
WO2006040845A1 (en) Concrete imitation rock block and mat with collected body of the imitation rock blocks
JP3454291B2 (en) Construction method of concrete structure
JP7051182B2 (en) Lining board

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20091009

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110729

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20111101

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20111221

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120124

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120130

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150203

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4918378

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150203

Year of fee payment: 3

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250