JP3480614B2 - Construction method at the border between adjacent construction zones when constructing a dam body - Google Patents

Construction method at the border between adjacent construction zones when constructing a dam body

Info

Publication number
JP3480614B2
JP3480614B2 JP33602594A JP33602594A JP3480614B2 JP 3480614 B2 JP3480614 B2 JP 3480614B2 JP 33602594 A JP33602594 A JP 33602594A JP 33602594 A JP33602594 A JP 33602594A JP 3480614 B2 JP3480614 B2 JP 3480614B2
Authority
JP
Japan
Prior art keywords
concrete
construction
section
concrete layer
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP33602594A
Other languages
Japanese (ja)
Other versions
JPH08177033A (en
Inventor
信一 酒向
勝敏 倉谷
耕治 白井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP33602594A priority Critical patent/JP3480614B2/en
Publication of JPH08177033A publication Critical patent/JPH08177033A/en
Application granted granted Critical
Publication of JP3480614B2 publication Critical patent/JP3480614B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Road Paving Machines (AREA)

Description

【発明の詳細な説明】 【0001】 【産業上の利用分野】本発明はダム堤体を構築する際の
隣り合う工区の境の部分の施工方法に関する。 【0002】 【従来の技術】ダム堤体を構築するに際して、従来、ダ
ンプトラックによりコンクリートをダム堤体の構築箇所
に運搬し、該箇所にコンクリートを流し、次に、ブルド
ーザで所定の厚さに均し、次いで、ローラによりコンク
リートを締固める作業がなされる。 【0003】 【発明が解決しようとする課題】しかしながら、上述の
ような方式では、ダンプトラックにより構築箇所にコン
クリートを流す作業や、ブルドーザによる均し作業は、
その都度現場の状況に応じてダンプトラックやブルドー
ザを操作しなければコンクリート表面の平坦性を確保し
難く、締固め等の品質管理上無人化を図り難い。そのた
め、例えば、火砕流や土石流が発生する可能性がある地
域に砂防ダムを構築する場合には、短期間で工事を終了
することが望ましいが、従来の方式では多数の作業員を
配置しなければならない。しかしながら、多数の作業員
を配置したのでは、避難時に混乱し人命が危険にさらさ
れるため、結局、少人数の作業員しか配置できず、工期
の短縮化を図れない問題があった。本発明は前記事情に
鑑み案出されたものであって、本発明の目的は、無人化
を図る上で有利で、しかも工期の短縮化を図れるダム堤
体の構築方法を提供することにある。 【0004】 【課題を解決するための手段】前記目的を達成するため
本発明は、ダム堤体構築箇所の幅方向の両側においてダ
ム堤体の長さ方向に延在させて外壁を形成し、前記ダム
堤体構築箇所をその長手方向に沿って複数の工区に分割
し、各工区内をコンクリートフィニッシャによるコンク
リートの敷均しと、振動ローラによる締固めと、グリー
ンカットマシンによる散水、養生、グリーンカットとを
行って各工区毎に下側のコンクリート層と上側のコンク
リート層からなるコンクリート層を順次形成してダム堤
体を構築する際の隣り合う工区の境の部分の施工方法で
あって、現在施工中の工区からコンクリートフィニッシ
ャが次の工区に降りれるように、下側のコンクリート層
を隣接する次の工区との境の部分まで形成すると共に、
上側のコンクリート層を前記境の部分より手前の部分ま
で形成し、次に、コンクリートフィニッシャを次の工区
に移動させた後、下側のコンクリート層の端部に、次の
工区に配置したバックホウにより前記幅方向にわたりP
Cブロックを設置してPCブロック列を作り、次に、現
在施工中の工区において上側のコンクリート層の端部と
PCブロック列との間の下側のコンクリート層上に、バ
ックホウによりコンクリートを打設して掻き均し、上側
のコンクリート層をPCブロック列まで形成し、最後
に、PCブロック列まで形成した前記上側のコンクリー
ト層を振動ローラにより締固め、グリーンカットマシン
により散水、養生、グリーンカットが行われることを特
徴とする。 【0005】 【作用】隣り合う工区の境の部分の施工が効率良く行な
われ、隣の工区へのコンクリートフィニッシャ、振動ロ
ーラ、グリーンカットマシンの移動も簡単になされ、
割されたダム堤体構築箇所毎に順に効率良くコンクリー
ト層を形成でき、工期の短縮化を図れる。 【0006】 【実施例】以下、本発明の実施例を図面に基づいて説明
する。図1は本発明方法により構築される砂防ダム及び
その周辺の概略平面図、図2は砂防ダムの構築方法の説
明図を示す。1は砂防ダムで、砂防ダム1は、火砕流や
土石流が生じたときにこれら流れを受け止めると共に、
また、所定量以上の火砕流や土石流が越えて出ていく越
流部3と、越流部3のそれぞれ両端に設けられ火砕流や
土石流を前記越流部3に導く袖部5とから構成され、本
発明により越流部3が構築される。7はバッチャープラ
ントで、バッチャープラント7はダム構築箇所から離れ
た箇所に設置されている。9は中継ホッパーで、中継ホ
ッパー9はダム構築箇所の近傍に配置され、中継ホッパ
ーにはベルトコンベア11が接続され、また、中継ホッ
パー9の近傍には洗車設備13が配置されている。 【0007】砂防ダム1を構築するに際して、越流部構
築箇所へのコンクリートの供給は、まず、バッチャープ
ラント7において、温度管理されたRCD用コンクリー
トがダンプトラック15に投入される。次に、ダンプト
ラック15をベルトコンベア11の下流端に走行させて
コンクリートを投入する。これによりコンクリートはベ
ルトコンベア11を介して中継ホッパー9に投入され
る。そして、中継ホッパー9からクローラダンプ17に
コンクリートが投入され、クローラダンプ17によりダ
ム構築箇所に運搬される。尚、クローラダンプ17がダ
ム構築箇所に進入する前に洗車設備13において車両の
足廻り及び下部が洗浄される。 【0008】図3乃至図5はそれぞれ各工区毎にコンク
リート層を形成する説明図を示す。越流部構築箇所は、
その長手方向に間隔をおいて第1工区21と、第2工区
22と、第3工区23に分割される。そして、第1工区
21において、越流部3の幅方向両側箇所でそれぞれ越
流部3の長手方向に延在する外壁25が形成され、ま
た、第1工区21と第2工区22の境の部分に越流部3
の幅方向に延在する内壁27が形成される。前記外壁2
5及び内壁27は、図6に示すように、PCブロック2
9がクローラダンプ17により越流部3構築箇所に運搬
され、バックホウ31、スリップフォームペーパ33等
により直線状に並べられて構成される。また、越流部3
構築箇所には、コンクリートフィニッシャ35、振動ロ
ーラ37、グリーンカットマシン39が搬入される。図
3乃至図5において、41は越流部3構築箇所への車両
の進入退出路で、進入退出路41は、コンクリート層が
積み重なれていくに従い、次第に高く形成される。 【0009】そして、第1工区21の内壁27寄りにコ
ンクリートフィニッシャ35が配置され、コンクリート
フィニッシャ35のホッパー部にクローラダンプ17か
らコンクリートが投入され、コンクリートフィニッシャ
35とクローラダンプ17が第1工区21内を越流部3
の長手方向に沿って直線状に走行しつつ、図3に示すよ
うに、超硬練りのコンクリートが内壁27から所定の厚
み、幅で第1工区21に敷き均されていく。このように
して所定の厚み、幅のコンクリート層Cが第1工区21
に直線状に形成され、両側の外壁25の間で、前記作業
が複数回繰り返して行われ、第1工区21全体にコンク
リート層Cが形成される。 【0010】図3に示すように、第1工区21にコンク
リート層Cが形成されている間に、第2工区22におい
て外壁25が形成され、第1工区21全体にコンクリー
ト層Cが形成されたならば、図4に示すように、前記と
同様にして第2工区22においても内壁27からコンク
リート層Cが形成され、両側の外壁25の間で、前記作
業が複数回繰り返して行われ、第2工区22全体にコン
クリート層Cが形成される。そして、図4に示すよう
に、第2工区22にコンクリート層Cが形成されている
間に、第1工区21において、グリーンカットマシン3
9により締固められたコンクリート表面に散水されコン
クリートの養生がなされ、次いで、グリーンカット作業
が行われ、また、第3工区23では外壁25が形成され
る。 【0011】第2工区22全体にコンクリート層Cが形
成されたならば、図5に示すように、前記と同様にし
て、コンクリートフィニッシャ35によりコンクリート
層Cが形成され、両側の外壁25の間で、前記作業が複
数回繰り返して行われ、第3工区23全体にコンクリー
ト層Cが形成される。そして、第3工区23にコンクリ
ート層Cが形成されている間に、第2工区22におい
て、グリーンカットマシン39により締固められたコン
クリート表面に散水されコンクリートの養生がなされ、
グリーンカット作業が行われる。 【0012】尚、第2工区22と第3工区23との境の
部分は、この実施例では次のようにしてコンクリート層
Cを連続状に形成している。まず、図7(A)に示すよ
うに、下側のコンクリート層C1を第2工区22と第3
工区23との境の部分まで形成する。そして、コンクリ
ートフィニッシャ35が第3工区23側に降りれるよう
に、上側のコンクリート層C2を前記境の部分より手前
の部分まで形成する。次に、図7(B)に示すように、
コンクリートフィニッシャ35を第3工区23に移動さ
せた後、下側のコンクリート層C1の端部に、バックホ
ウ31により越流部3の幅方向にわたりPCブロック4
301を設置してPCブロック列43を作る。次に、図
7(C)に示すように、上側のコンクリート層C2の端
部とPCブロック列43との間の下側のコンクリート層
C1上に、バックホウ31によりコンクリートを打設し
て掻き均す。そして、図7(D)に示すように、振動ロ
ーラ37により締固め、グリーンカットマシン39によ
り散水、養生、グリーンカットが行われる。このように
して第2工区22と第3工区23との境の部分のコンク
リート層Cが形成される。従って、第3工区23でのコ
ンクリートフィニッシャ35によるコンクリート層Cの
形成は、図7(E)に示すように、PCブロック列43
を始点として行われる。 【0013】このようにして、第1工区21から第3工
区23の全体にわたりコンクリート層Cが形成されたな
らば、第1工区21のコンクリート層Cの上に前記と同
様にコンクリート層Cが形成されて積み重ねられ、第1
工区21にコンクリート層Cが積み重ねられている間
に、第3工区23において、グリーンカットマシン39
により締固められたコンクリート表面に散水されコンク
リートの養生がなされ、グリーンカット作業がなされ
る。 【0014】そして、第1工区21から第3工区23へ
順にコンクリート層Cが積み重ねられていき、コンクリ
ート層Cが所定の高さとなった時、図5に示すように、
第3工区23にコンクリート層Cを形成して積み重ねて
いる間に、次ぎに重ねるコンクリート層Cに対応させ、
第1工区21の外壁25及び内壁27にバックホウ31
によりPCブロック29を重ねこれら外壁25と内壁2
7を高くする。そして、第1工区21にコンクリートを
積み重ねている間に、前記と同様に、第2,第3工区2
3の外壁25にPCブロック29を重ねこれら外壁25
を高くしていく。また、第2工区22と第3工区23と
の境の部分では、コンクリート層Cが所定の高さになっ
た時に前記と同様にPCブロック列43を作って境の部
分のコンクリート層Cを形成していく。そして、このよ
うな作業の繰り返しにより所定の幅、高さ、長さの越流
部3が構築される。 【0015】 本実施例によれば、隣り合う工区の境の
部分の施工が効率良く行なわれ、隣の工区へのコンクリ
ートフィニッシャ35、振動ローラ33、グリーンカッ
トマシン39の移動も簡単になされ、分割されたダム堤
体構築箇所毎に順に効率良くコンクリート層を形成で
き、工期の短縮化を図れる。また、コンクリートフィニ
ッシャ35、振動ローラ33は直線的に移動するのみで
あり、また、コンクリートフィニッシャ35と振動ロー
ラ33によりコンクリート表面の平坦性も確保し易く、
更に、グリーンカットマシン39もコンクリート上にお
いて直線的に移動することで足り、従って、これら装置
の無人化を簡単に行うことが可能となる。そして、無人
操作で越流部3を構築できることから、火砕流や土石流
が発生する可能性がある地域に砂防ダム1の越流部3を
構築する場合であっても、人命を危険にさらすことなく
越流部3を構築できる。 【0016】また、越流部3を、その長手方向において
第1工区21と、第2工区22と、第3工区23に仕切
り、各工区毎にコンクリート層Cを形成するようにした
ので、第1工区21においてコンクリートを敷均し、締
固めている間に、第2工区22において外壁25を形成
し、また、第2工区22においてコンクリートを敷均
し、締固めている間に、第1工区21においてコンクリ
ートの養生やグリーンカット作業を行うと共に、第3工
区23において外壁25を形成する等、時間のロスをな
くし、工期の大幅な短縮化を図ることが可能となる。 【0017】 【発明の効果】以上の説明で明らかなように本発明によ
れば、隣り合う工区の境の部分の施工が効率良く行なわ
れ、隣の工区へのコンクリートフィニッシャ、振動ロー
ラ、グリーンカットマシンの移動も簡単になされ、分割
されたダム堤体構築箇所毎に順に効率良くコンクリート
層を形成でき、工期の短縮化を図れる。
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to the construction of a dam embankment.
The present invention relates to a construction method at the border between adjacent construction zones . 2. Description of the Related Art Conventionally, when constructing a dam embankment, concrete is transported to a construction site of the dam embankment by a dump truck, concrete is poured into the construction site, and then a predetermined thickness is applied by a bulldozer. Leveling and then compaction of the concrete by rollers. [0003] However, in the above-mentioned method, the work of flowing concrete to the construction site by the dump truck and the leveling work by the bulldozer are not performed.
Unless the dump truck or bulldozer is operated according to the situation at the site each time, it is difficult to secure the flatness of the concrete surface, and it is difficult to achieve unmanned quality control such as compaction. Therefore, for example, when constructing a sabo dam in an area where pyroclastic flow or debris flow may occur, it is desirable to finish construction in a short period of time, but in the conventional method it is necessary to arrange a large number of workers No. However, arranging a large number of workers is confusing at the time of evacuation, and endangers human lives. Therefore, only a small number of workers can be allocated, and the construction period cannot be shortened. The present invention has been devised in view of the above circumstances, and an object of the present invention is to provide a method of constructing a dam embankment body that is advantageous in achieving unmanned operation and that can shorten the construction period. . [0004] In order to achieve the above object, the present invention provides a dam embankment on both sides in the width direction of a dam embankment construction site.
The outer wall is formed by extending in the length direction of the dam body,
Divide the embankment construction site into multiple sections along its length
And the inside of each section is concreted by a concrete finisher.
Leveling of REET, compaction by vibrating roller, and grease
Watering, curing and green cutting
Go to the lower concrete layer and upper concrete
A concrete layer consisting of a reed layer is formed sequentially to build a dam
In the construction method of the border part of the adjacent construction zone when building the body
There is a concrete finish from the construction area currently under construction.
Lower concrete layer so that the car can descend to the next section.
Up to the border with the next adjacent construction zone,
Apply the upper concrete layer to the part before the boundary.
And then add the concrete finisher to the next section
After moving to the end of the lower concrete layer,
P over the width direction by the backhoe placed in the construction section
Install the C block to create a PC block row, and then
In the construction area under construction,
On the lower concrete layer between the PC block rows,
Pour concrete with a hook and level it,
Of concrete layer up to PC block row
The upper concrete that has been formed up to the PC block row
Green cutting machine
Watering, curing and green cutting
Sign. [0005] [Effect] It is possible to efficiently perform the construction of the border between adjacent construction zones
And a concrete finisher to the next
And the green cutting machine can be moved easily, concrete layers can be formed efficiently in each of the divided dam embankment construction sites, and the construction period can be shortened. An embodiment of the present invention will be described below with reference to the drawings. FIG. 1 is a schematic plan view of a sabo dam constructed by the method of the present invention and its surroundings, and FIG. 2 is an explanatory view of a method of constructing a sabo dam. 1 is a sabo dam, which receives the pyroclastic flow and debris flow when they occur,
An overflow section 3 from which a pyroclastic flow or debris flow of a predetermined amount or more exits, and a sleeve portion 5 provided at each end of the overflow section 3 to guide the pyroclastic flow or debris flow to the overflow section 3 are provided. According to the invention, the overflow 3 is constructed. Reference numeral 7 denotes a batcher plant, and the batcher plant 7 is installed at a location away from the dam construction site. Reference numeral 9 denotes a relay hopper. The relay hopper 9 is disposed in the vicinity of a dam construction site, a belt conveyor 11 is connected to the relay hopper, and a car washing facility 13 is disposed in the vicinity of the relay hopper 9. When constructing the sabo dam 1, concrete is supplied to the overflow construction site at first. In the batcher plant 7, the RCD concrete whose temperature is controlled is put into the dump truck 15. Next, the dump truck 15 is moved to the downstream end of the belt conveyor 11 and concrete is charged. Thereby, the concrete is put into the relay hopper 9 via the belt conveyor 11. Then, concrete is put into the crawler dump 17 from the relay hopper 9 and transported to the dam construction site by the crawler dump 17. Before the crawler dump 17 enters the dam construction site, the undercarriage and the lower part of the vehicle are washed in the car wash facility 13. FIG. 3 to FIG. 5 are explanatory views showing the formation of a concrete layer in each section. Overflow part construction location,
The first section 21, the second section 22, and the third section 23 are divided at intervals in the longitudinal direction. Then, in the first section 21, outer walls 25 extending in the longitudinal direction of the overflow section 3 are formed at both sides in the width direction of the overflow section 3, respectively, and a boundary between the first section 21 and the second section 22 is formed. Overflow part 3 in part
An inner wall 27 extending in the width direction is formed. The outer wall 2
5 and the inner wall 27, as shown in FIG.
The crawler 9 is transported by the crawler dump 17 to the location where the overflow section 3 is constructed, and is linearly arranged by the backhoe 31, the slipform paper 33 and the like. In addition, overflow section 3
A concrete finisher 35, a vibrating roller 37, and a green cut machine 39 are carried into the construction location. In FIGS. 3 to 5, reference numeral 41 denotes an approach / exit path of the vehicle to the overflow portion 3 construction location, and the approach / exit path 41 is formed gradually higher as the concrete layers are stacked. Then, a concrete finisher 35 is disposed near the inner wall 27 of the first section 21, concrete is fed from the crawler dump 17 into a hopper portion of the concrete finisher 35, and the concrete finisher 35 and the crawler dump 17 are placed in the first section 21. Overflow part 3
As shown in FIG. 3, the ultra-hardened concrete is spread from the inner wall 27 to the first section 21 with a predetermined thickness and width while traveling in a straight line along the longitudinal direction. In this way, the concrete layer C having the predetermined thickness and width is
The above operation is repeated a plurality of times between the outer walls 25 on both sides, and the concrete layer C is formed on the entire first section 21. As shown in FIG. 3, while the concrete layer C is formed in the first section 21, the outer wall 25 is formed in the second section 22, and the concrete layer C is formed in the entire first section 21. Then, as shown in FIG. 4, the concrete layer C is formed from the inner wall 27 also in the second section 22 in the same manner as described above, and the above operation is repeated a plurality of times between the outer walls 25 on both sides. The concrete layer C is formed in the entire two sections 22. Then, as shown in FIG. 4, while the concrete layer C is formed in the second section 22, the green cutting machine 3 is placed in the first section 21.
Water is sprinkled on the surface of the concrete compacted by 9 to cure the concrete, then green cutting is performed, and an outer wall 25 is formed in the third section 23. When the concrete layer C is formed in the entire second section 22, as shown in FIG. 5, the concrete layer C is formed by the concrete finisher 35 in the same manner as described above, and between the outer walls 25 on both sides. The above operation is repeated a plurality of times, and the concrete layer C is formed in the entire third section 23. Then, while the concrete layer C is formed in the third section 23, in the second section 22, water is sprinkled on the concrete surface compacted by the green cut machine 39 to cure the concrete,
Green cut work is performed. In this embodiment, the concrete layer C is formed continuously at the boundary between the second section 22 and the third section 23 as follows. First, as shown in FIG. 7A, the lower concrete layer C1 is divided into the second section 22 and the third section.
It is formed up to the boundary with the construction zone 23. Then, the upper concrete layer C2 is formed up to the portion before the boundary so that the concrete finisher 35 can descend to the third section 23 side. Next, as shown in FIG.
After moving the concrete finisher 35 to the third section 23, the PC block 4 is attached to the end of the lower concrete layer C1 by the backhoe 31 over the width direction of the overflow section 3.
The PC block row 43 is made by installing the PC block 301. Next, as shown in FIG. 7 (C), the concrete is poured by the backhoe 31 on the lower concrete layer C1 between the end of the upper concrete layer C2 and the PC block row 43, and the concrete is scraped. You. Then, as shown in FIG. 7D, compaction is performed by the vibration roller 37, and watering, curing, and green cutting are performed by the green cutting machine 39. In this way, the concrete layer C at the boundary between the second section 22 and the third section 23 is formed. Therefore, the concrete layer C is formed by the concrete finisher 35 in the third section 23 as shown in FIG.
Is performed as a starting point. When the concrete layer C is formed in the entire first section 21 to the third section 23 as described above, the concrete layer C is formed on the concrete layer C in the first section 21 in the same manner as described above. And stacked, the first
While the concrete layer C is being stacked in the construction section 21, in the third construction section 23, the green cutting machine 39 is used.
Water is sprinkled on the compacted concrete surface to cure the concrete, and green cutting is performed. Then, concrete layers C are sequentially stacked from the first section 21 to the third section 23, and when the concrete layer C reaches a predetermined height, as shown in FIG.
While forming and stacking the concrete layer C in the third construction section 23, it is made to correspond to the concrete layer C to be stacked next,
The backhoe 31 is provided on the outer wall 25 and the inner wall 27 of the first construction section 21.
The outer wall 25 and the inner wall 2
Increase 7 Then, while the concrete is being stacked on the first construction section 21, the second and third construction sections 2
The PC block 29 is superimposed on the outer wall 25 of the third
To be higher. Also, at the boundary between the second section 22 and the third section 23, when the concrete layer C reaches a predetermined height, the PC block rows 43 are formed in the same manner as above to form the concrete layer C at the boundary. I will do it. Then, by repeating such operations, the overflow section 3 having a predetermined width, height, and length is constructed. According to the present embodiment , the boundary of the adjacent
The construction of the part is performed efficiently, and the concrete
Printer finisher 35, vibrating roller 33, green
The moving of the machine 39 is also easy, and the divided dam embankment
Efficient formation of concrete layers in order for each body construction site
The construction period can be shortened. Further, the concrete finisher 35 and the vibration roller 33 only move linearly, and the concrete finisher 35 and the vibration roller 33 easily ensure the flatness of the concrete surface,
Further, it is sufficient that the green cutting machine 39 also moves linearly on the concrete, so that it is possible to easily perform unmanned operation of these devices. And since the overflow section 3 can be constructed by unmanned operation, even if the overflow section 3 of the sabo dam 1 is constructed in an area where pyroclastic flow and debris flow may occur, without endangering human life The overflow section 3 can be constructed. The overflow section 3 is divided into a first section 21, a second section 22, and a third section 23 in the longitudinal direction, and the concrete layer C is formed for each section. The outer wall 25 is formed in the second section 22 while the concrete is spread and compacted in the first section 21. The first wall is formed while the concrete is spread and compacted in the second section 22. In addition to performing concrete curing and green cutting work in the construction section 21 and forming the outer wall 25 in the third construction section 23, it is possible to eliminate time loss and greatly reduce the construction period. As is apparent from the above description, according to the present invention, the construction at the boundary between adjacent construction sections can be performed efficiently.
Concrete finisher, vibrating row
La, green cutting machine can be easily moved and split
Concrete at each dam embankment construction site
A layer can be formed, and the construction period can be shortened.

【図面の簡単な説明】 【図1】本発明方法により構築される砂防ダム及びその
周辺の概略平面図である。 【図2】砂防ダムの構築方法の説明図である。 【図3】各工区毎にコンクリート層を形成する説明図で
ある。 【図4】各工区毎にコンクリート層を形成する説明図で
ある。 【図5】各工区毎にコンクリート層を形成する説明図で
ある。 【図6】外壁の構築方法の説明図である。 【図7】(A)乃至(E)はそれぞれ第2工区と第3工
区との境の部分でコンクリート層を形成する説明図であ
る。 【符号の説明】 1 砂防ダム 3 越流部 15 ダンプトラック 17 クローラダンプ 21 第1工区 22 第2工区 23 第3工区 35 コンクリートフィニッシャ 37 振動ローラ 39 グリーンカットマシン
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a schematic plan view of a sabo dam constructed by the method of the present invention and its periphery. FIG. 2 is an explanatory view of a method for constructing a sabo dam. FIG. 3 is an explanatory diagram for forming a concrete layer for each section. FIG. 4 is an explanatory view of forming a concrete layer for each section. FIG. 5 is an explanatory view of forming a concrete layer for each section. FIG. 6 is an explanatory diagram of a method of constructing an outer wall. FIGS. 7A to 7E are explanatory views of forming a concrete layer at a boundary between a second section and a third section. [Description of Signs] 1 Sabo dam 3 Overflow section 15 Dump truck 17 Crawler dump 21 First section 22 Second section 23 Third section 35 Concrete finisher 37 Vibration roller 39 Green cut machine

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平6−250590(JP,A) 特開 平5−33323(JP,A) 特開 平5−17923(JP,A) 特開 平5−118136(JP,A) 実公 平4−34172(JP,Y2) (58)調査した分野(Int.Cl.7,DB名) E02B 7/00 E04G 21/02 ────────────────────────────────────────────────── ─── Continuation of front page (56) References JP-A-6-250590 (JP, A) JP-A-5-33323 (JP, A) JP-A-5-17923 (JP, A) JP-A-5-17923 118136 (JP, A) Jingu 4-34172 (JP, Y2) (58) Fields investigated (Int. Cl. 7 , DB name) E02B 7/00 E04G 21/02

Claims (1)

(57)【特許請求の範囲】 【請求項1】 ダム堤体構築箇所の幅方向の両側におい
てダム堤体の長さ方向に延在させて外壁を形成し、前記
ダム堤体構築箇所をその長手方向に沿って複数の工区に
分割し、各工区内をコンクリートフィニッシャによるコ
ンクリートの敷均しと、振動ローラによる締固めと、グ
リーンカットマシンによる散水、養生、グリーンカット
とを行って各工区毎に下側のコンクリート層と上側のコ
ンクリート層からなるコンクリート層を順次形成してダ
ム堤体を構築する際の隣り合う工区の境の部分の施工方
法であって、 現在施工中の工区からコンクリートフィニッシャが次の
工区に降りれるように、下側のコンクリート層を隣接す
る次の工区との境の部分まで形成すると共に、上側のコ
ンクリート層を前記境の部分より手前の部分まで形成
し、 次に、コンクリートフィニッシャを次の工区に移動させ
た後、下側のコンクリート層の端部に、次の工区に配置
したバックホウにより前記幅方向にわたりPCブロック
を設置してPCブロック列を作り、 次に、現在施工中の工区において上側のコンクリート層
の端部とPCブロック列との間の下側のコンクリート層
上に、バックホウによりコンクリートを打設して掻き均
し、上側のコンクリート層をPCブロック列まで形成
し、 最後に、PCブロック列まで形成した前記上側のコンク
リート層を振動ローラにより締固め、グリーンカットマ
シンにより散水、養生、グリーンカットが行われる、 ことを特徴とするダム堤体を構築する際の隣り合う工区
の境の部分の施工方法。
(57) [Claims] [Claim 1] Both sides in the width direction of the dam embankment construction site
Extending in the length direction of the dam embankment to form an outer wall,
The dam embankment construction site is divided into multiple sections along its length.
Divide each section and use a concrete finisher to
Leveling of concrete, compaction by vibrating rollers, and
Watering, curing and green cutting by lean-cut machine
And the lower concrete layer and upper concrete
Concrete layers consisting of concrete layers are sequentially formed and
Construction method at the border between adjacent construction zones when constructing a bank
The concrete finisher from the construction area currently under construction
Adjoin the lower concrete layer so that you can get down to the construction section.
To the next construction zone, and
The concrete layer is formed up to the part before the boundary
And, then, move the concrete finisher to the next work area
After that, at the end of the lower concrete layer, place it in the next section
PC block over the width direction by the backhoe
To make a PC block row, then the upper concrete layer in the construction area currently under construction
Concrete layer between the edge of the PC and the row of PC blocks
Pour concrete with a backhoe on top
And form the upper concrete layer up to the PC block row
And, finally, the upper Conch formed to PC block row
The reed layer is compacted with a vibrating roller,
Adjacent construction area when constructing a dam embankment characterized by watering, curing, and green cutting by Shin
Construction method at the border.
JP33602594A 1994-12-21 1994-12-21 Construction method at the border between adjacent construction zones when constructing a dam body Expired - Fee Related JP3480614B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33602594A JP3480614B2 (en) 1994-12-21 1994-12-21 Construction method at the border between adjacent construction zones when constructing a dam body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33602594A JP3480614B2 (en) 1994-12-21 1994-12-21 Construction method at the border between adjacent construction zones when constructing a dam body

Publications (2)

Publication Number Publication Date
JPH08177033A JPH08177033A (en) 1996-07-09
JP3480614B2 true JP3480614B2 (en) 2003-12-22

Family

ID=18294925

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33602594A Expired - Fee Related JP3480614B2 (en) 1994-12-21 1994-12-21 Construction method at the border between adjacent construction zones when constructing a dam body

Country Status (1)

Country Link
JP (1) JP3480614B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005163283A (en) * 2003-11-28 2005-06-23 Okinawa General Bureau Cabinet Office Construction method for compacting top of slope, and top-of-slope compacting equipment for use in it

Also Published As

Publication number Publication date
JPH08177033A (en) 1996-07-09

Similar Documents

Publication Publication Date Title
CN110130641A (en) A kind of 3D printing assembled modular architectural method
CN106835992A (en) A kind of arcuate structure clear-water concrete construction of cast-in-situ box-beam method
JP3480614B2 (en) Construction method at the border between adjacent construction zones when constructing a dam body
EP3997270B1 (en) Ballast-plastic composite body
JP3851158B2 (en) Construction method of porous concrete slope
CN113306002A (en) Layout construction method and application of prefabricated bridge prefabricated part production base
JP5401124B2 (en) Concrete paving method
JP3454291B2 (en) Construction method of concrete structure
JP4000780B2 (en) Waste landfill method
WO1993008334A1 (en) Railway station platform edge
DE10358363B4 (en) Slipform paver for the production of surface coverings
JP4537343B2 (en) Form for shoulder
JP4056616B2 (en) Construction method for concrete structures
JPH08177032A (en) Constructing method of dam embankment body
CN113481771A (en) Permanent-temporary combined construction structure for municipal road and construction method thereof
JP3577581B2 (en) Sand formation method and mobile sand spreader on wide soft ground
JP4243419B2 (en) Concrete surface placement method for dams
JPH0827701A (en) Reinforced construction and ballast replacing method for ballast track bed
CN200943202Y (en) Lining carriage for large span integrated channel concrete pouring machine
CN220564977U (en) Site panel for petroleum and natural gas drilling site and assembled composite site
JPH08177035A (en) Forming method of wing section of checkdam
CN209759923U (en) Asphalt pavement cushion structure
JP4918378B2 (en) Construction method of trapezoidal CSG dam
JP2920613B2 (en) Acidic river water neutralization structure
WO2005038140A1 (en) Slip form paver for producing surfacings

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees