JP4896084B2 - 発電機運用計画作成方法 - Google Patents
発電機運用計画作成方法 Download PDFInfo
- Publication number
- JP4896084B2 JP4896084B2 JP2008169778A JP2008169778A JP4896084B2 JP 4896084 B2 JP4896084 B2 JP 4896084B2 JP 2008169778 A JP2008169778 A JP 2008169778A JP 2008169778 A JP2008169778 A JP 2008169778A JP 4896084 B2 JP4896084 B2 JP 4896084B2
- Authority
- JP
- Japan
- Prior art keywords
- stop
- demand
- generator
- operation plan
- fluctuation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 104
- 238000009826 distribution Methods 0.000 claims abstract description 48
- 238000012545 processing Methods 0.000 claims abstract description 45
- 230000007613 environmental effect Effects 0.000 claims abstract description 12
- 230000008569 process Effects 0.000 claims description 65
- 238000011156 evaluation Methods 0.000 claims description 41
- 238000010248 power generation Methods 0.000 claims description 36
- 239000000446 fuel Substances 0.000 claims description 15
- 230000008859 change Effects 0.000 claims description 7
- 239000005431 greenhouse gas Substances 0.000 claims description 6
- 238000012804 iterative process Methods 0.000 claims description 6
- 239000006185 dispersion Substances 0.000 claims description 4
- 238000002360 preparation method Methods 0.000 abstract description 2
- 239000000243 solution Substances 0.000 description 62
- 238000004364 calculation method Methods 0.000 description 26
- 238000007726 management method Methods 0.000 description 12
- 230000009467 reduction Effects 0.000 description 12
- 230000000694 effects Effects 0.000 description 9
- 230000007246 mechanism Effects 0.000 description 5
- 230000004044 response Effects 0.000 description 5
- 230000004913 activation Effects 0.000 description 4
- 230000006870 function Effects 0.000 description 4
- 238000003860 storage Methods 0.000 description 4
- 230000007704 transition Effects 0.000 description 4
- 238000000342 Monte Carlo simulation Methods 0.000 description 3
- 230000008901 benefit Effects 0.000 description 3
- 238000012854 evaluation process Methods 0.000 description 3
- 230000014509 gene expression Effects 0.000 description 3
- 238000004088 simulation Methods 0.000 description 3
- 239000007858 starting material Substances 0.000 description 3
- 230000009471 action Effects 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 2
- 230000009849 deactivation Effects 0.000 description 2
- 230000005012 migration Effects 0.000 description 2
- 238000013508 migration Methods 0.000 description 2
- 238000003825 pressing Methods 0.000 description 2
- 238000009825 accumulation Methods 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 230000015556 catabolic process Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- NUHSROFQTUXZQQ-UHFFFAOYSA-N isopentenyl diphosphate Chemical compound CC(=C)CCO[P@](O)(=O)OP(O)(O)=O NUHSROFQTUXZQQ-UHFFFAOYSA-N 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 238000012887 quadratic function Methods 0.000 description 1
- 238000012216 screening Methods 0.000 description 1
- 230000001932 seasonal effect Effects 0.000 description 1
- 239000012089 stop solution Substances 0.000 description 1
- 230000002194 synthesizing effect Effects 0.000 description 1
Images
Classifications
-
- Y04S10/54—
-
- Y04S10/60—
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
このような一般的な計算機システム上で、運用計画作成のための処理フローが実行される。
このほかにも、起動停止コストや最小運転時間制約などに関する諸特性についても、データテーブル0102に格納されている。処理0101では、必要な発電機特性データを全てこのデータテーブル0102より読み込む。
ここに、ln()は自然対数関数を表す。nd()は時間tに依存せずに、一日で一つの値を採用する。このような処理によって、期待需要を一日全体として上下に変動させた想定需要量dn(t)を確率的に生成することができる。このように求めた想定需要量を電力需要モデル0202の出力として扱うこともできる。
Claims (8)
- 発電機運用計画作成方法において、
起動停止計画処理に必要な想定条件を変動させながら各発電機の起動停止計画作成手段を繰り返す第一の反復処理と、
前記第一の反復処理で得られた複数の起動停止計画の各々について、経済負荷配分処理に必要な想定条件を変動させながら各発電機の経済負荷配分決定手段を繰り返す第二の反復処理とで構成されており、
前記起動停止計画の各々について想定条件が変動した場合の費用評価もしくは環境評価に関する確率的な統計情報を算出することを特徴とする発電機運用計画作成方法。 - 請求項1において、前記起動停止計画処理および前記経済負荷配分決定に必要な想定条件として電力需要変動要因を採用し、電力需要変動の確率変動モデルを用いて乱数処理によって想定条件を作成することを特徴とする発電機運用計画作成方法。
- 請求項1において、前記起動停止計画処理および前記経済負荷配分決定に必要な想定条件として自然エネルギーを利用する発電装置の発電出力変動要因を採用し、発電出力変動の確率変動モデルを用いて乱数処理によって想定条件を作成することを特徴とする発電機運用計画作成方法。
- 請求項1において、前記起動停止計画処理および前記経済負荷配分決定に必要な想定条件として電力料金契約内容変更に対する需要家の電力消費行動変動要因を採用し、電力需要変動の確率変動モデルを用いて乱数処理によって想定条件を作成することを特徴とする発電機運用計画作成方法。
- 請求項2〜4のいずれかにおいて、前記起動停止計画処理に必要な想定条件を乱数処理によって作成する際に、起動停止計画の発電機構成が変化する需給バランス上の境界点について統計情報を保持しており、その統計情報から得られる確率分布と想定条件項目個別に規定される確率分布を合成した確率分布を用いることを特徴とする発電機運用計画作成方法。
- 請求項1において、前記費用評価に関する確率的な統計情報として、発電コストもしくは燃料コスト・起動停止コストについて、期待値・分散値および所定の信頼区間におけるVaR値を用いることを特徴とする発電機運用計画作成方法。
- 請求項1において、前記環境評価に関する確率的な統計情報として、温暖化ガス排出量もしくはCO2排出量について、期待値・分散値および所定の信頼区間におけるVaR値を用いることを特徴とする発電機運用計画作成方法。
- 請求項1において、前記費用評価もしくは環境評価に関する確率的な統計情報を算出する際に、別途指定された統計情報内のデータ項目に関する選択条件選択に従って、起動停止計画を選別することを特徴とする発電機運用計画作成方法。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008169778A JP4896084B2 (ja) | 2008-06-30 | 2008-06-30 | 発電機運用計画作成方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008169778A JP4896084B2 (ja) | 2008-06-30 | 2008-06-30 | 発電機運用計画作成方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2010011670A JP2010011670A (ja) | 2010-01-14 |
JP4896084B2 true JP4896084B2 (ja) | 2012-03-14 |
Family
ID=41591463
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2008169778A Active JP4896084B2 (ja) | 2008-06-30 | 2008-06-30 | 発電機運用計画作成方法 |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4896084B2 (ja) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10937112B2 (en) | 2018-08-17 | 2021-03-02 | Kabushiki Kaisha Toshiba | System, method and device for creating a power generation plan in a power generation system |
US11054798B2 (en) | 2018-06-04 | 2021-07-06 | Kabushiki Kaisha Toshiba | Operation planning system, method and device for generating an operation plan using multiple planning devices |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8972074B2 (en) * | 2011-03-30 | 2015-03-03 | General Electric Company | System and method for optimal load planning of electric vehicle charging |
CN103559582B (zh) * | 2013-11-08 | 2016-09-28 | 国家电网公司 | 调度计划安全校核方法及系统 |
JP6237321B2 (ja) * | 2014-02-21 | 2017-11-29 | 富士通株式会社 | 運転計画作成プログラム、運転計画作成方法および運転計画作成装置 |
JP6816949B2 (ja) * | 2014-11-26 | 2021-01-20 | ゼネラル・エレクトリック・カンパニイ | 発電プラント発電ユニットの制御を強化するための方法 |
JP6725406B2 (ja) * | 2016-12-12 | 2020-07-15 | 株式会社東芝 | 発電計画策定装置、発電計画策定方法、および発電計画策定プログラム |
JP7240862B2 (ja) * | 2018-11-29 | 2023-03-16 | 株式会社日立製作所 | 周波数制御装置および周波数制御方法 |
JP7240156B2 (ja) * | 2018-12-06 | 2023-03-15 | 株式会社日立製作所 | 電力需給計画装置 |
CN112949924B (zh) * | 2021-03-09 | 2023-03-03 | 中国南方电网有限责任公司 | 考虑电量执行与调峰匹配的机组组合优化方法和控制器 |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4327325B2 (ja) * | 2000-03-27 | 2009-09-09 | 大阪瓦斯株式会社 | 熱電併給プラントの最適運転制御システム |
JP2002064935A (ja) * | 2000-08-18 | 2002-02-28 | Toshiba Corp | 自動給電システム、自動給電方法、および自動給電プログラムを記憶したコンピュータ読み取り可能な記憶媒体 |
JP2003016374A (ja) * | 2001-06-28 | 2003-01-17 | Toshiba Corp | 発電設備計画の評価方法、発電設備計画の策定方法及びプログラム |
JP3791503B2 (ja) * | 2003-03-12 | 2006-06-28 | 株式会社日立製作所 | 発電計画・電力売買計画作成方法,装置及びプログラム |
JP2006180673A (ja) * | 2004-12-24 | 2006-07-06 | Mitsubishi Electric Corp | 発電機の運用計画作成装置 |
JP4577232B2 (ja) * | 2006-02-22 | 2010-11-10 | 株式会社日立製作所 | 発電所運用計画作成装置およびその方法 |
JP4745148B2 (ja) * | 2006-06-29 | 2011-08-10 | 株式会社東芝 | 電力系統の需給計画作成装置および需給計画作成方法 |
-
2008
- 2008-06-30 JP JP2008169778A patent/JP4896084B2/ja active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11054798B2 (en) | 2018-06-04 | 2021-07-06 | Kabushiki Kaisha Toshiba | Operation planning system, method and device for generating an operation plan using multiple planning devices |
US10937112B2 (en) | 2018-08-17 | 2021-03-02 | Kabushiki Kaisha Toshiba | System, method and device for creating a power generation plan in a power generation system |
Also Published As
Publication number | Publication date |
---|---|
JP2010011670A (ja) | 2010-01-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4896084B2 (ja) | 発電機運用計画作成方法 | |
Ogunmodede et al. | Optimizing design and dispatch of a renewable energy system | |
Kuosmanen et al. | What is the best practice for benchmark regulation of electricity distribution? Comparison of DEA, SFA and StoNED methods | |
JP5248372B2 (ja) | 発電計画作成方法、装置、プログラムおよび記憶装置 | |
Rouhani et al. | Cost-benefit analysis of various California renewable portfolio standard targets: Is a 33% RPS optimal? | |
CA2859833A1 (en) | Capital asset investment planning apparatus, systems and methods | |
JP2019082935A (ja) | 管理装置および管理方法 | |
Schwarz et al. | Two-stage stochastic, large-scale optimization of a decentralized energy system: a case study focusing on solar PV, heat pumps and storage in a residential quarter | |
Czupryna et al. | An agent-based approach to integrated assessment modelling of climate change | |
US20190066235A1 (en) | Systems and methods for energy management | |
US20150363732A1 (en) | Device for assisting determination of supply group and program for assisting determination of supply group | |
Vrionis et al. | A Generation Expansion Planning model for integrating high shares of renewable energy: A Meta-Model Assisted Evolutionary Algorithm approach | |
Beuse et al. | Comparing CO2 emissions impacts of electricity storage across applications and energy systems | |
Pickering et al. | Quantifying resilience in energy systems with out-of-sample testing | |
Vespucci et al. | Two-stage stochastic mixed integer optimization models for power generation capacity expansion with risk measures | |
JP2022015383A (ja) | 発電と送電の最適組合せの決定方法及び支援システム | |
Culaba et al. | Optimal design of an integrated renewable‐storage energy system in a mixed‐use building | |
Fischer et al. | Understanding errors in EIA projections of energy demand | |
Azcárate et al. | Peaking strategies for the management of wind-H2 energy systems | |
CN110956318A (zh) | 一种基于预先构建的预测模型进行预测的方法及装置 | |
Sturt et al. | Value of stochastic reserve policies in low-carbon power systems | |
Newham | Power system investment planning using stochastic dual dynamic programming | |
Bischoff et al. | Economic objectives, uncertainties and decision making in the energy sector | |
JP2022090134A (ja) | 管理装置および管理方法 | |
JP7154244B2 (ja) | 電力需給計画作成装置及び電力需給計画作成方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20100325 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20111104 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20111122 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20111220 |
|
R151 | Written notification of patent or utility model registration |
Ref document number: 4896084 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R151 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20150106 Year of fee payment: 3 |