Repair method for damaged vertical wall tiles in the tunnel inspector passage Download PDF

Info

Publication number
JP4880075B1
JP4880075B1 JP2011002484A JP2011002484A JP4880075B1 JP 4880075 B1 JP4880075 B1 JP 4880075B1 JP 2011002484 A JP2011002484 A JP 2011002484A JP 2011002484 A JP2011002484 A JP 2011002484A JP 4880075 B1 JP4880075 B1 JP 4880075B1
Authority
JP
Japan
Prior art keywords
tile
repair
passage
concrete
vertical wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2011002484A
Other languages
Japanese (ja)
Other versions
JP2012144869A (en
Inventor
佳顕 山本
敬 三山
Original Assignee
ケイコン株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ケイコン株式会社 filed Critical ケイコン株式会社
Priority to JP2011002484A priority Critical patent/JP4880075B1/en
Application granted granted Critical
Publication of JP4880075B1 publication Critical patent/JP4880075B1/en
Publication of JP2012144869A publication Critical patent/JP2012144869A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

【課題】 自動車道のトンネル側壁際の監視員通路の欠損した縦壁のタイル表面の全面を一括して張り直して補修する方法を提供する。
【解決手段】 トンネル1内の監視員通路4の手摺りの支柱6aのベースプレート6b及び縦壁5のタイルの剥離箇所などの欠損部をステンレス製L字型タイル補修板9の上面補修枠11とタイル模様補修板10により補修する方法で、補修する箇所にアンカーを打込み、保守箇所の縦壁5にタイル模様補修板10を、監視員通路の欠損した部分に上面補修枠11をそれぞれ当接してタイル模様補修板10をパネル材で覆い、これらを支保材14で支持した後、面補修枠11の開口部にモルタルを注入固化し、モルタルの固化後に支保材を取り去りパネルを除去して縦壁5のタイル模様を補修する。
【選択図】 図5
PROBLEM TO BE SOLVED: To provide a method of repairing a whole tile surface of a vertical wall where a supervisor passage is missing at the side wall of a tunnel on a motorway by repairing the entire surface.
A defect portion such as a base plate 6b of a handrail post 6a of a guard rail passage 4 in a tunnel 1 and a tile peeling portion of a vertical wall 5 is repaired with an upper surface repair frame 11 of a stainless steel L-shaped tile repair plate 9. In the method of repairing with the tile pattern repair plate 10, the anchor is driven into the repaired portion, the tile pattern repair plate 10 is brought into contact with the vertical wall 5 of the maintenance portion, and the upper surface repair frame 11 is brought into contact with the missing part of the supervisor passage. After covering the tile pattern repair plate 10 with a panel material and supporting them with the support material 14, the mortar is injected and solidified into the opening of the surface repair frame 11, and after the mortar is solidified, the support material is removed and the panel is removed to remove the vertical wall. Repair the 5 tile pattern.
[Selection] Figure 5

Description

自動車専用道路のトンネルでは、長期間の使用によりトンネル側壁ぎわに設けられた監視員通路の手摺りの下部の監視員通路の内部が劣化して損壊し、この内部の損壊が監視員通路の縦壁のタイル壁まで及んで破損する。この発明は損壊した箇所の補修方法に関し、特に監視員通路の内部の補修に加えて縦壁表面の破損したタイル壁をステンレス製L字型タイル補修板により補修する方法に関する。   In a tunnel on an automobile road, the interior of the supervisor passage below the handrail of the supervisor passage provided on the side wall of the tunnel is deteriorated and damaged due to long-term use, and this internal damage is the vertical wall of the supervisor passage. The tile wall is damaged. The present invention relates to a repair method for a damaged portion, and more particularly to a method for repairing a damaged tile wall on the surface of a vertical wall with a stainless steel L-shaped tile repair plate in addition to repairing the inside of a supervisor passage.

自動車専用道路の長大なトンネルにおけるトンネル側壁ぎわに設けられた監視員通路はその路側帯に面したコンクリート製の縦壁を有しており、この縦壁の上に監視員の安全をはかる鉄パイプ製の手摺りが立設されている。ところで、長大なトンネルの側壁は、運転者から見たトンネルの内視環境の改善のために、コンクリート壁からなるトンネル側壁にタイルを張りめぐらしてタイル内装としている。このトンネル側壁のタイル内装に合わせて、監視員通路の手摺りの下部の走行車線がわのコンクリート製の縦壁にも、通常はタイルを張りめぐらし、縦壁の壁面をコンクリート表面とした場合に受ける無味乾燥な感じを解消して、トンネル内を走行する自動車の運転者の心を整ったタイル壁面により和ませて安全運転をはかっている。   The observer passage provided on the side wall of the tunnel in the long tunnel of the exclusive road for automobiles has a concrete vertical wall facing the roadside belt, and on this vertical wall is made of iron pipe for safety of the observer The handrail is erected. By the way, the side walls of the long tunnel are tiled in order to improve the internal environment of the tunnel as seen from the driver by laying tiles around the tunnel side wall made of concrete. In accordance with the tile interior of the tunnel side wall, when the lane under the railing of the guard's passage is usually laid around the vertical wall made of concrete and the wall of the vertical wall is the concrete surface, It eliminates the dry and dry feeling that it receives and softens the driver's mind inside the tunnel with a tile wall that has been prepared for safe driving.

ところで、寒冷地の自動車道路では、路面が凍結して滑り易くなるので、走行中にスリップする危険が極めて高い。そこで、このような路面凍結を防止するために、路面に凍結防止剤、例えば塩化ナトリウムや塩化カルシウムなどの塩分を散布している。このため、これらの凍結防止剤の散布された道路を走行してきた自動車がトンネル内に進入してくると、トンネル外でタイヤに付着した凍結防止剤の塩分をそのままトンネル内に持ち込み、トンネル内の路面に落とす。さらに、落下した凍結材をタイヤで跳ね飛ばし、トンネル側壁ぎわの監視員通路の下部の路側帯側の縦壁やその縦壁の上に立てられている鉄パイプ製の手摺りに凍結防止剤を付着させる。この付着した凍結防止剤にトンネル内の湧水が掛かると、凍結防止剤が徐々に溶解されて手摺りの付け根のベースプレートの部分から監視員通路の中に浸透する。このように凍結防止剤が監視員通路の中に浸透すると、監視員通路下部を構成するコンクリートに埋設の鉄筋が腐蝕され、この腐蝕された部分とその周囲が膨潤して劣化して損壊し、さらに縦壁を劣化し損壊する。このように監視員通路下部のコンクリートの断面破壊が起こって縦壁に及び、終にはコンクリート壁の表面に張りめぐらしたタイル面に剥離が生じ、タイルが脱落する。   By the way, on a motorway in a cold region, since the road surface freezes and becomes slippery, the risk of slipping during traveling is extremely high. Therefore, in order to prevent such road surface freezing, an antifreezing agent, for example, salt such as sodium chloride or calcium chloride is sprayed on the road surface. For this reason, when a car traveling on a road where these antifreeze agents are applied enters the tunnel, the antifreeze salt attached to the tires outside the tunnel is brought into the tunnel as it is, Drop it on the road. Furthermore, the fallen frozen material is spun off with tires, and antifreezing agent is attached to the vertical wall on the side of the roadside belt at the bottom of the tunnel passage side of the tunnel side wall and the iron pipe handrail standing on the vertical wall. Let When spring water in the tunnel is applied to the adhering antifreeze agent, the antifreeze agent is gradually dissolved and permeates from the base plate portion at the base of the handrail into the supervisor passage. When the antifreezing agent penetrates into the supervisor passage in this way, the rebar embedded in the concrete that forms the lower part of the supervisor passage is corroded, and the corroded portion and its surroundings are swollen and deteriorated and damaged, Furthermore, the vertical wall is deteriorated and damaged. In this way, the cross-section of the concrete below the supervisor passage breaks down, extends over the vertical wall, and finally peels off the tile surface spread around the surface of the concrete wall, and the tile falls off.

一方、トンネルの側壁面にクラックや欠損が生じ、あるいは監視員通路に不陸が生じると、これらに起因してトンネル内に湧水を生じ、上記したように凍結防止剤が徐々に溶解されて監視員通路に浸透して内部のコンクリートを損壊し、監視員通路の縦壁のタイル壁も損壊する。これらの損壊した部分の修復方法としては、表面の汚れを除去し、その上にプライマーを塗布し、プライマーの硬化後に不陸調整剤を塗布し、その表面に炭素繊維などの繊維シートを貼り付け、仕上げ剤を塗布するなどの修復工事が行われる。この方法は、不陸調整剤の塗布技術に高度な熟練を要とし、また繊維シートの貼り付けは、迅速な作業を必要とする。さらに、繊維シート内には貼り付け時に気泡を内包し易く、このため繊維シートの強度が低下して、再び漏水する事故も発生し易く、再度の補修が行う必要がある。これらの繰返しで、トンネル内壁や監視員通路の縦壁のコンクリート壁の強度は脆弱化されていた。このようになると、トンネル内壁の漏水した部分のコンクリート壁体をしゃくり取って、その内部に漏水を導く流下水路を形成した後に下地処理を行い、その表面をモルタルで平滑化し、その上にタイルプレートを貼り付け、タイルの目地部を充填することにより、トンネル内壁面を修復する方法が提案されている(例えば、特許文献1参照。)。しかし、この方法では、修復後は、漏水が壁面を修復したタイル内装の表面を流れることはなくなり、従前のタイル内装したタイルの景観を回復することができるが、しかし、この方法による監視員通路の路側帯側の縦壁では、縦壁のタイル面のコンクリート下地すなわちタイルを表面に張りめぐらしているコンクリート下地の部分であるタイル内装部分損壊箇所の削り取りなどの作業を路側帯側から行う必要がある。このため、長期の工事期間にわたって、路側帯に最も近い車道の一車線を安全のために規制しなければならず、長期間にわたって交通渋滞を引き起し、また費用もかかる問題があった。   On the other hand, if cracks or defects occur on the side wall surface of the tunnel, or if the land of the observer passage is uneven, spring water is generated in the tunnel due to these, and the antifreezing agent is gradually dissolved as described above. It penetrates into the observer passage and destroys the concrete inside, and the tile wall of the vertical wall of the observer passage is also damaged. As a method for repairing these damaged parts, remove the dirt on the surface, apply a primer on it, apply a non-landing conditioner after curing the primer, and paste a fiber sheet such as carbon fiber on the surface Restoration work such as applying a finishing agent is performed. This method requires a high level of skill in the application technique of the unevenness adjusting agent, and the application of the fiber sheet requires a quick operation. Furthermore, it is easy to enclose bubbles in the fiber sheet at the time of sticking, so that the strength of the fiber sheet is reduced and an accident of water leakage is likely to occur again, and it is necessary to perform repair again. These repetitions weakened the strength of the concrete walls of the inner walls of the tunnel and the vertical walls of the guard passage. In this case, the concrete wall body of the leaked part of the inner wall of the tunnel is scraped, and a downflow channel that guides the water leakage is formed inside, and then the ground treatment is performed, and the surface is smoothed with mortar. A method of repairing the inner wall surface of the tunnel by pasting and filling the joints of the tile has been proposed (see, for example, Patent Document 1). However, with this method, after the restoration, water leakage does not flow on the surface of the tile interior that has repaired the wall surface, and the landscape of the tile with the previous tile interior can be restored. For the vertical wall on the roadside belt side, it is necessary to work from the roadside belt side, such as scraping the damaged part of the tile interior, which is the concrete foundation of the tile surface of the vertical wall, that is, the portion of the concrete foundation where the tiles are spread over the surface. is there. For this reason, the road lane closest to the roadside zone must be regulated for safety over a long period of construction, causing a traffic jam for a long period of time and cost.

さらに、凍結防止剤による塩害を受けたコンクリート構造物の補修方法として、コンクリート構造物の劣化した部分を取り除き、その箇所に型枠を配設して亜硫酸塩を含むグラウトまたはモルタルを流し込んで、コンクリートと型枠を一体化させる補修方法が提案されている(例えば、特許文献2参照。)。ところで、この補修方法では、型枠は撤去しないので、モルタルの養生および型枠撤去のための工事期間を設ける必要はないが、この方法はタイル壁の補修方法に係る方法ではないので、この方法をトンネル内壁面にタイルを張ってタイル内装の壁面としている箇所に適用しても、元のタイル壁面や監視員通路の縦壁のタイル面を得ることはできない。そこで、タイル内装の景観を回復させるために、この補修方法で劣化した部分にモルタルを流し込んで型枠と一体化しても、現場の路側帯において、一体化した型枠の表面にさらにタイルを張りめぐらすか、あるいはタイルの色彩形状を描くなどの余分の工程を行う必要がある。このためにトンネル内での交通規制の必要な工事期間を延長しなければならない問題があった。   Furthermore, as a method of repairing a concrete structure that has been damaged by the antifreeze agent, the deteriorated portion of the concrete structure is removed, a mold is placed at that location, and a grout or mortar containing sulfite is poured into the concrete structure. And a repair method for integrating the formwork with each other has been proposed (see, for example, Patent Document 2). By the way, in this repair method, since the formwork is not removed, it is not necessary to provide a work period for curing the mortar and removing the formwork, but this method is not a method related to the tile wall repair method. Even if it is applied to a place where a tile is stretched on the inner wall surface of the tunnel to form a wall surface of the tile interior, the original tile wall surface or the tile surface of the vertical wall of the observer passage cannot be obtained. Therefore, to restore the landscape of the tile interior, even if mortar is poured into the part deteriorated by this repair method and integrated with the formwork, tiles are further applied to the surface of the integrated formwork on the roadside belt at the site. It is necessary to perform an extra process such as turning around or drawing the color shape of the tile. For this reason, there has been a problem that the construction period requiring traffic regulation in the tunnel has to be extended.

特開平11−343796号公報JP-A-11-343796 特開2004−52413号公報JP 2004-52413 A

本発明が解決しようとする課題は、自動車用道路のトンネル内の走行車線の路面の状況やトンネル内壁などの状況を監視するために、トンネル内壁ぎわに設けられた監視員通路において、監視員通路の路側帯側の手摺りの下部の縦壁のタイル壁面に生じたタイルの剥がれや監視員通路のコンクリートの断面破壊の損壊による欠損部分の縦壁表面に張りめぐらしたタイルを個々に貼り直すことなく、その欠損部分のタイルの全面を一括して張り直して補修することで、元のタイル壁面と変わらないタイル壁の景観を付与する方法を提供することである。   The problem to be solved by the present invention is that, in order to monitor the condition of the road surface of the traveling lane in the tunnel of the automobile road and the situation of the inner wall of the tunnel, in the observer path provided on the inner wall of the tunnel, Without re-sticking the tiles stretched around the vertical wall surface of the defective part due to the peeling of the tile on the wall surface of the vertical wall under the handrail on the roadside belt side or the damage of the cross section of the concrete in the observer passage It is to provide a method of giving a tile wall landscape that is not different from the original tile wall surface by repairing and repairing the entire surface of the tile of the defective portion at once.

監視員通路の路側帯側の手摺りの下部のコンクリートの縦壁の壁面である縦壁の表面に貼られたタイル壁の経年変化による剥落を起こした部分や、あるいは、トンネル外の走行車線の路面に冬期に散布した凍結防止剤の塩化ナトリウムや塩化カルシウムなどの塩分が走行車両のタイヤなどによってトンネル内に持ち込まれ、タイヤから凍結防止剤の塩分が監視員通路側に跳ね飛ばされ、トンネル内の漏水と合わさって溶解され、この塩分を含む水が監視員通路の手摺りのベースプレートの部分から、下部のコンクリートの縦壁内に浸透する。このコンクリートの縦壁内に浸透した塩分を含む水がコンクリートの縦壁内に埋設された鉄筋を腐蝕し、さらに腐蝕した鉄筋とその周囲の部分が膨潤してコンクリートの縦壁を劣化する。この結果、監視員通路の縦壁内部のコンクリートの断面破壊やコンクリートの縦壁表面のタイル壁の剥離を引き起こす。そこで、このようにコンクリートの断面破壊あるいはコンクリートの縦壁表面のタイル壁の剥離の起こった部分をステンレス製L字型タイル補修板で被覆し、この被覆したステンレス製L字型タイル補修板の中にモルタルを埋め戻し、さらに埋め戻した部分の監視員通路のコンクリートの縦壁の表面を元のタイル壁面と変わらない色彩からなるタイル模様の壁面に補修し、走行車線を走行する車両の運転手から見た監視員通路の縦壁の景観を良好なものとする。さらに、この補修したタイル壁面を凍結防止剤の塩分による腐蝕に耐え得るものとする方法を発明者は鋭意研究して見出した。この方法として、コンクリートの縦壁の表面の当初のタイル壁面の色彩模様を模して描いたタイル模様を有するステンレス製の前面タイル補修板と監視員通路の手摺りのベースプレートの部分の上面に載置するステンレス製の上面補修枠からなるステンレス製L字型タイル補修板を補修箇所の縦壁の最外部の壁面及びその縦壁の上面に載置し、この前面タイル模様補数板である縦壁の部分にパネル材を被せ、これらを断面C字型の支保材で支持し、上面に当接した上面補修枠に設けた開口部からコンクリートの縦壁内の欠損部にモルタルを流し込んでこのステンレス製L字型タイル補修板を監視員通路のコンクリート路盤と一体化する。この一体化の方法により監視員通路の路側帯側の手摺りの下部のコンクリートの縦壁の断面破壊した部分とそのタイルの剥離や損壊したタイル部分を当初のタイル模様と見た目に変わらない状態に補修する方法である。   The part of the tile wall affixed to the surface of the vertical wall, which is the wall of the vertical wall of the concrete below the handrail on the roadside belt side of the observer passage, or the traveling lane outside the tunnel Salts such as sodium chloride and calcium chloride of antifreeze sprayed on the road surface in the winter are brought into the tunnel by the tires of the traveling vehicle, and the salt of antifreeze agent jumps off from the tires to the side of the guard's aisle. The salt-containing water penetrates into the concrete vertical wall of the lower part from the base plate part of the handrail of the observer passage. The salt-containing water that has permeated into the vertical wall of the concrete corrodes the reinforcing bars embedded in the vertical wall of the concrete, and the corroded reinforcing bars and the surrounding portions swell to deteriorate the vertical wall of the concrete. As a result, the cross section of the concrete inside the vertical wall of the observer passage and the separation of the tile wall on the vertical wall surface of the concrete are caused. Therefore, the part where the concrete cross-section fracture or the separation of the tile wall on the surface of the concrete vertical wall is covered with the stainless steel L-shaped tile repair plate, and the covered stainless steel L-shaped tile repair plate is covered. The driver of the vehicle traveling in the driving lane repairs the surface of the vertical wall of the concrete in the observer passage in the backfilled part to the tiled wall surface that has the same color as the original tile wall surface. The landscape of the vertical wall of the guards passage seen from above shall be good. Further, the inventor has intensively researched and found out a method for making the repaired tile wall surface resistant to corrosion by the salt of the antifreeze agent. This is done by placing a stainless steel front tile repair plate with a tile pattern imitating the original tile wall color pattern on the surface of the concrete vertical wall and the base plate part of the handrail of the guard passage. A stainless steel L-shaped tile repair plate made of a stainless steel upper surface repair frame is placed on the outermost wall of the vertical wall at the repair location and the upper surface of the vertical wall, and the vertical wall is the front tile pattern complement plate This part is covered with a panel material, supported by a support material with a C-shaped cross section, and mortar is poured into the defect in the vertical wall of the concrete from the opening provided in the upper surface repair frame in contact with the upper surface. The made L-shaped tile repair plate is integrated with the concrete roadbed of the observer passage. By this integration method, the section of the vertical wall of the concrete below the handrail on the roadside belt side of the guard's passage is broken and the tiles peeled and damaged are not changed to the original tile pattern. It is a repair method.

すなわち、上記の課題を解決するための本発明の手段は、請求項1の手段では、監視員通路の路側帯側の手摺り支柱のベースプレートの下部のコンクリートからなる監視員通路の欠損した通路面の部分およびこの通路面の路側帯側の欠損したコンクリートの縦壁の部分およびこの縦壁表面のタイル剥離面の部分や損壊タイル面の部分の補修方法である。この補修方法としては、これらの補修を必要とする部分に前面タイル模様補修板および上面補修枠からなるステンレス製L字型タイル補修板を当接し、さらに該ステンレス製L字型タイル補修板の前面タイル模様補修板の表面をパネル材で覆い、該パネル材および該上面補修枠を断面C字型の支保材により監視員通路面およびコンクリートの縦壁に取り付け支持した後、上面補修枠に有する開口部から下部の監視員通路のコンクリート欠損部およびその側面の縦壁欠損部に無収縮性モルタルを流し込み、該監視員通路のコンクリート路盤の欠損部およびその縦壁面のタイル剥離面あるいはタイル損壊面に、上面補修枠および前面タイル模様補修板を該無収縮性モルタルで固着し、固着後に該支保材を解体し、さらにパネル材を取り外す方法からなる、トンネル側壁ぎわの監視員通路の通路面の欠損部並びに縦壁およびタイル壁面の欠損部のステンレス製L字型タイル補修板による補修方法である。   That is, according to the means of the present invention for solving the above-mentioned problems, in the means of claim 1, the passage surface lacking the supervisor passage made of concrete below the base plate of the handrail support column on the roadside belt side of the supervisor passage. And a part of the vertical wall of the missing concrete on the road side belt side of the passage surface, and a part of the tile peeling surface and a part of the damaged tile surface on the surface of the vertical wall. As this repair method, a stainless steel L-shaped tile repair plate made of a front tile pattern repair plate and an upper surface repair frame is brought into contact with the portions requiring repair, and the front surface of the stainless steel L-shaped tile repair plate is further contacted. The surface of the tile pattern repair plate is covered with a panel material, and the panel material and the upper surface repair frame are attached to and supported by the monitoring staff passage surface and the vertical wall of the concrete by a support member having a C-shaped cross section, and then the opening provided in the upper surface repair frame Pour the non-shrinkable mortar into the concrete defect part and the vertical wall defect part on the side of the observer passage from the bottom to the crack part of the concrete roadbed in the observer passage and the tile peeling surface or tile damage surface of the vertical wall surface. , A method of fixing the upper surface repair frame and the front tile pattern repair plate with the non-shrinkable mortar, dismantling the support material after fixing, and further removing the panel material It becomes a repair method according to a stainless steel L-shaped tile repair plate of defects of the defect as well as vertical walls and tile wall surface of the passage surface of the wardens passage of the tunnel side walls Sai.

請求項2の手段では、前面タイル模様補修板および上面補修枠からなるステンレス製L字型タイル補修板を当接し、さらに該前面タイル模様補修板の表面にパネル材で覆い、該パネル材および該上面補修枠を断面C字型の支保材により監視員通路面およびコンクリートの縦壁に取り付けて支持する方法である。この方法は、前面タイル模様補修板の表面を覆ったパネル材の表面に断面C字型の支保材を縦方向に当接し、該支保材の下端部の内面のコンクリートにコンクリートアンカーを打ち込み、該支保材の下端部の表面から固定ボルトを該コンクリートアンカーに結合してパネル材の下端部を支持する。さらに、上面補修枠の後端側の監視員通路の上面にコンクリートアンカーを打ち込み、L字型受け材の横部材の表面から固定ボルトを該コンクリートアンカーに結合し、該支保材の上端部の表面から長尺の固定ボルトをL字型受け材の縦部材の上部に挿通してナットで固定してパネル材の上端部を支持し、前面タイル模様補修板および上面補修枠からなるステンレス製L字型タイル補修板を支持する方法からなる、請求項1の手段のトンネル側壁ぎわの監視員通路の通路面の欠損部並びに縦壁およびタイル壁面の欠損部のステンレス製L字型タイル補修板による補修方法である。   In the means of claim 2, a stainless steel L-shaped tile repair plate made of a front tile pattern repair plate and an upper surface repair frame is brought into contact, and the surface of the front tile pattern repair plate is covered with a panel material. In this method, the upper surface repair frame is attached to and supported by a monitoring member passage surface and a vertical wall of concrete by a support member having a C-shaped cross section. In this method, a support material having a C-shaped cross section is vertically contacted to the surface of the panel material covering the surface of the front tile pattern repair plate, and a concrete anchor is driven into the concrete on the inner surface of the lower end portion of the support material, A fixing bolt is coupled to the concrete anchor from the surface of the lower end portion of the support material to support the lower end portion of the panel material. Further, a concrete anchor is driven into the upper surface of the observer passage on the rear end side of the upper surface repair frame, and a fixing bolt is coupled to the concrete anchor from the surface of the transverse member of the L-shaped receiving member, and the surface of the upper end portion of the support member A long fixing bolt is inserted into the upper part of the vertical member of the L-shaped receiving material and fixed with nuts to support the upper end of the panel material, and it is made of stainless steel made of a front tile pattern repair plate and an upper surface repair frame A repair method using a stainless steel L-shaped tile repair plate for a passage surface defect portion and a vertical wall and tile wall defect portion of a guard wall of a tunnel side wall in the means of claim 1 comprising a method of supporting a tile repair plate It is.

本発明の手段の自動車道のトンネルの監視員通路の縦壁の走行車線側の前面壁であるタイル壁面の欠損部の補修方法により、従来の補修のように欠損部分をモルタルで補修して縦壁表面のタイルを1枚ずつ貼り直す必要がなく、一挙に短時間でタイル模様の壁面に補修できる。しかも、補修期間であるトンネル内の走行車線の通行規制期間も短期日ででき従来の工法に比して大幅に通行規制の期間を短縮することができる。   According to the method of the present invention, the defect portion is repaired with mortar as in the conventional repair by the repair method of the defect portion of the tile wall surface which is the front wall on the traveling lane side of the vertical wall of the surveillance passage of the tunnel of the motorway. There is no need to reattach tiles on the wall surface one by one, and repair can be made to the tiled wall surface in a short time. In addition, the traffic regulation period of the traveling lane in the tunnel, which is a repair period, can also be a short day, and the period of traffic regulation can be greatly shortened compared to the conventional construction method.

さらに、本発明の支保材の使用により、ステンレス製L字型タイル補修板の上面補修枠内にモルタルを流入する作業では、上面補修枠から流入したモルタルによってステンレス製L字型タイル補修板を部分的に縦壁前面に膨出することなく、しかも、ステンレス製L字型タイル補修板で補修されているので、冬期に凍結防止材の塩分がタイヤで撥ね飛ばされて縦壁表面に付着しても塩害によって再び腐蝕されることが無く、かつ、ステンレス板の表面に描かれたタイル模様による修復で、元の縦壁の走行車線側の壁面のタイル壁面の模様と一体的に見えるので、走行車線を走る車両の運転手は違和感なく安心して走行できる。   Furthermore, in the work of flowing mortar into the upper surface repair frame of the stainless steel L-shaped tile repair plate by using the support material of the present invention, the stainless steel L-shaped tile repair plate is partially made by the mortar flowing from the upper surface repair frame. Since it is repaired with a stainless steel L-shaped tile repair plate, it does not bulge to the front of the vertical wall, and the salt of anti-freezing material is splashed off by the tire in the winter and adheres to the vertical wall surface. It will not corrode again due to salt damage, and it can be seen as a tile wall pattern on the driving lane side of the original vertical wall by repairing with the tile pattern drawn on the surface of the stainless steel plate. The driver of the vehicle running in the lane can travel with peace of mind without any discomfort.

一般的なトンネル側壁ぎわの監視員通路と手摺りと手摺りの下部の縦壁と円形水路を下部に有する路側帯および走行車線を示す斜視図である。It is a perspective view which shows the roadside belt | band | zone and driving lane which have a general tunnel side wall wagging supervisor passage, a handrail, the vertical wall of the lower part of a handrail, and a circular water channel in the lower part. トンネル側壁ぎわの監視員通路の手摺りの下部の縦壁に塩害により生じた欠損部を示す斜視図である。It is a perspective view which shows the defect | deletion part which arose due to salt damage to the vertical wall of the lower part of the handrail of the guard passage of a tunnel side wall. ステンレス製L字型タイル補修板の立面図で、(a)は正面図、(b)は側面図である。It is an elevation view of a stainless steel L-shaped tile repair plate, (a) is a front view, (b) is a side view. ステンレス製L字型タイル補修板の上面補修板で、(a)は支柱開口部カバーの無い上面補修板、(b)は支柱開口部カバーを示す。It is an upper surface repair board of stainless steel L-shaped tile repair board, (a) is an upper surface repair board without a support | pillar opening part cover, (b) shows a support | pillar opening part cover. 監視員通路の欠損した縦壁にステンレス製L字型タイル補修板を適用する補修状況を示す斜視図である。It is a perspective view which shows the repair condition which applies a stainless steel L-shaped tile repair board to the vertical wall which the supervisor channel | path lost. 監視員通路の欠損した縦壁の補修箇所に設けたステンレス製L字型タイル補修板を部分的に示し、(a)は側面図、(b)は平面図である。The stainless steel L-shaped tile repair board provided in the repair location of the vertical wall where the monitoring person passage was missing is partially shown, (a) is a side view, (b) is a plan view. 監視員通路の縦壁に支保材を取付けた上面補修枠を示す平面図である。It is a top view which shows the upper surface repair frame which attached the supporting material to the vertical wall of the supervisor channel | path. 監視員通路の縦壁にステンレス製L字型タイル補修板を支保材で支持した図で、(a)は正面図、(b)は側面図である。It is the figure which supported the stainless steel L-shaped tile repair board on the vertical wall of the supervisor channel | path with the support material, (a) is a front view, (b) is a side view. トンネル内の監視員通路の縦壁にステンレス製L字型タイル補修板を支保材で取り付けた斜視図である。It is the perspective view which attached the stainless steel L-shaped tile repair board to the vertical wall of the monitoring channel | path in a tunnel with the support material. トンネル内の縦壁を補修した監視員通路と走行車線の路側帯を示す側面図である。It is a side view which shows the roadside belt | band | zone of the monitoring staff channel | path and driving lane which repaired the vertical wall in a tunnel.

本発明を実施するための形態について、図面を参照して以下に説明する。図1に示すように、一般的な自動車専用道路のトンネル1のトンネル側壁1aぎわに設けたコンクリート路盤4aにより一段と高くなって車の衝突の際の安全をはかった監視員通路4がある。この監視員通路4のトンネル側壁1aぎわには細い溝4bがあり、トンネル側壁1aや監視員通路4に溜まった水を流すようになっている。さらに、この監視員通路4を形成するコンクリート路盤4aの走行車線2及びその路側帯3の側部には縦壁5があり、走行車線2に対面して設けられている。通常、この縦壁5には、トンネル側壁1aと共にタイルが貼られてタイル壁面となっている。監視員通路4の縦壁5の近辺の上には手摺り6が設けられており、この手摺り6は手摺支柱6aに支持され、手摺支柱6aの下部はベースプレート6bにより監視員通路4のコンクリート路盤4aに固定されている。この縦壁5の下端きわには路面下に埋設した円形水路3aがあり、この円形水路3aの上面が路側帯3の一部となっており走行車線に持ち込まれた雨水などを円形水路3aで流下する。   EMBODIMENT OF THE INVENTION The form for implementing this invention is demonstrated below with reference to drawings. As shown in FIG. 1, there is a supervisor passage 4 which is further raised by a concrete roadbed 4a provided on the side wall 1a of a tunnel 1 of a general automobile-only road 1 to increase safety in the event of a car collision. A narrow groove 4b is formed in the tunnel side wall 1a of the monitoring member passage 4 so that water accumulated in the tunnel side wall 1a and the monitoring member passage 4 flows. Furthermore, a vertical wall 5 is provided on the side of the road lane 2 of the concrete roadbed 4 a and the roadside belt 3 that form the supervisor passage 4, and is provided facing the road lane 2. Usually, a tile is stuck to the vertical wall 5 together with the tunnel side wall 1a to form a tile wall surface. A handrail 6 is provided on the vicinity of the vertical wall 5 of the supervisor passage 4, and this handrail 6 is supported by the handrail support 6a. The lower portion of the handrail support 6a is supported by the base plate 6b in the concrete of the supervisor passage 4. It is fixed to the roadbed 4a. At the lower end of the vertical wall 5, there is a circular water channel 3a buried under the road surface. The upper surface of the circular water channel 3a is a part of the roadside belt 3, and rainwater brought into the driving lane is passed through the circular water channel 3a. Flow down.

このような、自動車専用道路のトンネル1は、開通してから長期間にわたって使用された結果、トンネル内の車の通る走行車線2の路面や、トンネル側壁1aや、トンネル側壁1aぎわに設けられている監視員通路4が傷んでくる。そこで、走行車線2の路面やトンネル側壁1aや上面のトンネル壁は、走行車の安全のために、頻繁に補修されている。ところで、上記したように、走行車線2の路側帯3とトンネル側壁1aの間の路側帯3よりも一段と高い位置には、この位置から走行車線2の路面やトンネル内の状況を監視する監視員が通る監視員通路4が設けられている。ところで、この監視員通路4も長年の間に監視員通路4のコンクリート路盤4aの内部に、冬期にトンネル内を走行する車のタイヤに付着した凍結防止剤が撥ね飛ばされ、トンネル内の漏水と共にその塩分が浸入する。すなわち、トンネル内の漏水と共に凍結防止剤の塩分が路側帯3がわの監視員通路4のコンクリート路盤4a上にかかり、コンクリート路盤4aに立設された手摺6の支柱6aの監視員通路面のベースプレート6bの部分から下部の監視員通路4のコンクリート路盤4aの中に浸潤する。この浸潤した凍結防止剤の塩分によりコンクリート路盤4aを形成する鉄筋コンクリートの鉄筋4cが、図2に示すように、腐蝕されて膨潤し、膨潤部4dとなり、さらにコンクリート路盤4aの内部構造が損壊されて欠損7となる。このようにコンクリート路盤4aの内部構造が損壊されると、路側帯3との間を形成する監視員通路4のコンクリート路盤4aの側部の縦壁5にも欠損を生し、これらの縦壁5にタイル壁面5aが形成されていると、このタイル壁面5aも破損される。そこで、これらの欠損した監視員通路4のコンクリート路盤4aおよび監視員通路4の側部のタイル壁面5aを有する縦壁5を補修する必要が生じる。   As a result of being used over a long period of time after opening, such a tunnel 1 for an automobile road is provided on the road surface of the traveling lane 2 through which the cars in the tunnel pass, the tunnel side wall 1a, and the tunnel side wall 1a. Surveillance passage 4 is damaged. Therefore, the road surface of the traveling lane 2, the tunnel side wall 1a, and the upper tunnel wall are frequently repaired for the safety of the traveling vehicle. By the way, as described above, there is a supervisor who monitors the road surface of the traveling lane 2 and the situation in the tunnel from this position at a position higher than the roadside belt 3 between the roadside belt 3 and the tunnel side wall 1a. A supervisor passage 4 through which is passed is provided. By the way, for a long time, the anti-freezing agent adhering to the tires of the car traveling in the tunnel in the winter season is splashed off inside the concrete roadbed 4a of the observer passage 4 for a long time. The salt infiltrates. That is, the salt content of the antifreezing agent is applied to the concrete roadbed 4a of the roadway 4 of the roadside belt 3 along with water leakage in the tunnel, and the surface of the roadway of the supervisor 6a of the column 6a of the handrail 6 erected on the concrete roadbed 4a. The base plate 6b infiltrates into the concrete roadbed 4a of the lower supervisor passage 4. As shown in FIG. 2, the reinforced concrete rebar 4c that forms the concrete roadbed 4a by the infiltrated antifreeze salt is corroded and swollen to become a swollen portion 4d, and the internal structure of the concrete roadbed 4a is further damaged. It becomes defect 7. When the internal structure of the concrete roadbed 4a is thus damaged, the vertical wall 5 on the side of the concrete roadbed 4a of the supervisor passage 4 formed between the roadside belt 3 is also damaged, and these vertical walls If the tile wall surface 5a is formed on 5, the tile wall surface 5a is also damaged. Therefore, it is necessary to repair the vertical wall 5 having the concrete roadbed 4a of the missing supervisor passage 4 and the tile wall surface 5a on the side of the supervisor passage 4.

ところで、上記の監視員通路4のコンクリート路盤4aの縦壁5には、タイルが全面に張られて縦壁5の前面がタイル壁面5aとなっている。そこで、上記した凍結防止剤による塩分で欠損した部分は、これら縦壁5の前面のタイル壁面5aにも及び、タイルが割れたり剥落したりしている。そこで、監視員通路4のコンクリート路盤4aの中およびその表面である縦壁5の前面のタイル壁面5aの補修に当たっては、トンネル内を走行する車の走行規制の期間を短くして、できる限り影響を及ぼさないようにする必要がある。このため、補修する際にタイルを1枚ずつ貼り替える手間を省略して、一定の面積の多数のタイル面を一挙に補修することが出来る、前面タイル模様補修板10と上面補修枠11からなるステンレス製L字型タイル補修板9と、このステンレス製L字型タイル補修板9を用いて補修する際に、ステンレス製L字型タイル補修板9がモルタルで固着するまで固定するために支持する断面C字型の鉄製の支保材14を用いて補修する。この支保材14は断面形状がC字型に形成されているので支保材の剛性が向上し、ステンレス製L字型タイル補修板9及びパネル材12をコンクリート路盤4a及び縦壁5に堅固に支持できる。   By the way, tiles are stretched over the entire surface of the vertical wall 5 of the concrete roadbed 4a of the supervisor passage 4 and the front surface of the vertical wall 5 is a tile wall surface 5a. Therefore, the portion lacking due to the salt caused by the antifreezing agent described above also extends to the tile wall surface 5a on the front surface of the vertical wall 5, and the tile is cracked or peeled off. Therefore, when repairing the tile wall surface 5a in the front surface of the vertical wall 5 which is the surface of the concrete roadbed 4a of the supervisor passage 4, the travel regulation period of the vehicle traveling in the tunnel is shortened, and the influence is exerted as much as possible. Must be avoided. For this reason, it consists of a front tile pattern repair plate 10 and an upper surface repair frame 11 that can repair a large number of tile surfaces of a certain area at once, eliminating the trouble of replacing tiles one by one when repairing. When repairing using the stainless steel L-shaped tile repair plate 9 and the stainless steel L-shaped tile repair plate 9, the stainless steel L-shaped tile repair plate 9 is supported for fixing until it is fixed with mortar. Repair is performed using a steel support member 14 having a C-shaped cross section. Since the support member 14 has a C-shaped cross section, the rigidity of the support member is improved, and the stainless steel L-shaped tile repair plate 9 and the panel material 12 are firmly supported on the concrete roadbed 4a and the vertical wall 5. it can.

このために使用するステンレス製L字型タイル補修板9の大きさは、その前面タイル模様補修板10では、図3の(a)の正面図では、縦横共に略900mmで、縦の右側サイドは幅20mmの挿入重ね部9bは、2枚以上のステンレス製L字型タイル補修板9を横に並べて補修する際に使用する。また、前面タイル模様補修板10の下側は縦幅20mmの傾斜面9cとなっており、さらに幅50mmの縦方向の取付け面9dを有し、さらにステンレス製L字型タイル補修板9の上面は上面補修枠11であり、上面補修枠11の横幅は図3の(a)の正面図に示す横幅と同じ900mmで、その奥行きは、図3の(b)の側面図の上部に示すように、200mmからなっている。この上面補修枠11は、監視員通路4の面であるコンクリート路盤4aの上面よりも略50mm高い位置に水平に配設されその後端は50mmの傾斜面9cとなってコンクリート路盤4aに当接し、さらに40mmの水平方向の取付け面9dでコンクリート路盤4aに載っている。このように50mm高い位置に上面補修枠11を位置させる理由は、コンクリート路盤4aよりも略10mm高い位置に上面補修枠11を設けた場合、図4に示す上面補修枠11のモルタル注入孔11cからモルタルを注入した時に十分にモルタルが補修箇所の欠損部7に十分に流れ込みにくい。しかしながら、上面補修枠11が略50mm高い位置に設けられていると、欠損部7までモルタルが良好に流入できるからである。なお、略50mm高い位置に設けた上面補修枠11の側端部から注入したモルタルを流出させないために、補修箇所の最端部となるステンレス製L字型タイル補修板9の部分は、上面補修枠11の側端部を50mm下部の監視員通路4の上面に当接するように下方に曲げて側端部を閉じるようにする。   The size of the stainless steel L-shaped tile repair plate 9 used for this purpose is approximately 900 mm both vertically and horizontally in the front tile pattern repair plate 10 in the front tile pattern repair plate 10, and the vertical right side is The insertion overlap portion 9b having a width of 20 mm is used when repairing two or more stainless steel L-shaped tile repair plates 9 arranged side by side. Further, the lower side of the front tile pattern repair plate 10 is an inclined surface 9c having a vertical width of 20 mm, and further has a vertical mounting surface 9d having a width of 50 mm, and the upper surface of the stainless steel L-shaped tile repair plate 9. Is the upper surface repair frame 11, the horizontal width of the upper surface repair frame 11 is 900 mm which is the same as the lateral width shown in the front view of FIG. 3A, and the depth is as shown in the upper part of the side view of FIG. And 200 mm. The upper surface repair frame 11 is horizontally disposed at a position approximately 50 mm higher than the upper surface of the concrete roadbed 4a, which is the surface of the supervisor passage 4, and the rear end thereof is an inclined surface 9c of 50 mm and comes into contact with the concrete roadbed 4a. Furthermore, it is mounted on the concrete roadbed 4a with a horizontal mounting surface 9d of 40 mm. The reason for positioning the upper surface repair frame 11 at a position 50 mm higher in this way is that when the upper surface repair frame 11 is provided at a position approximately 10 mm higher than the concrete roadbed 4a, from the mortar injection hole 11c of the upper surface repair frame 11 shown in FIG. When the mortar is injected, the mortar is not sufficiently flown into the defect portion 7 at the repair location. However, if the upper surface repair frame 11 is provided at a position that is approximately 50 mm higher, the mortar can flow into the defect portion 7 satisfactorily. In order to prevent the mortar injected from the side end of the upper surface repair frame 11 provided at a position approximately 50 mm higher from flowing out, the portion of the stainless steel L-shaped tile repair plate 9 that is the outermost end of the repair location is the upper surface repair. The side end portion of the frame 11 is bent downward so as to abut on the upper surface of the supervisor passage 4 below 50 mm so as to close the side end portion.

以上に説明した、前面タイル模様補修板10と上面補修枠11からなるステンレス製L字型タイル補修板9による自動車専用道路のトンネル内のトンネル側壁際に設けられた監視員通路の縦壁の補修方法について、そのフローの概略を簡単に示すと、1.事前調査による施工位置の決定→2.前処理→3.マーキング→4.アンカーの削孔及び打込み→5.ステンレス製補修板、パネル材、支保材の取り付け→6.充填材(モルタル)注入→7.充填材の固化→8.支保材解体→9.片付け撤収となる。   Repair of the vertical wall of the observer passage provided on the side wall of the tunnel in the tunnel of the automobile road by the stainless steel L-shaped tile repair plate 9 made of the front tile pattern repair plate 10 and the upper surface repair frame 11 described above. The outline of the flow of the method is as follows. Determining the construction position by prior survey → 2. Pretreatment → 3. Marking → 4. Anchor drilling and driving → 5. Installation of stainless steel repair plate, panel material, support material → 6. Filler (mortar) injection → 7. Solidification of filler → 8. Support material dismantling → 9. It will be cleaned up.

これらについて、さらに詳細に説明する。先ず、補修の施工前に事前調査を実施する。すなわち、自動車専用道路のトンネル1内の状況を把握するために、事前調査として監視員通路4の走行車線2の側に安全のために設けられている手摺り6の支柱6aの下部のベースプレート6bの周辺の監視員通路4の通路面や走行路線2のがわの監視員通路4の縦壁5の壁面などの補修箇所の状況を記録して、補修を必要とする箇所の施工場所を決定する。この決定した監視員通路4の補修箇所に対して前処理を実施する。この前処理では、事前調査で見出した監視員通路4の手摺り6の支柱6aの下部のベースプレート6bの周辺の監視員通路4の通路面や走行路線2のがわの監視員通路4の縦壁5の壁面に長年の使用による劣化による表面のコンクリートやタイルの剥離や浮きに対し、あるいは、凍結防止剤の塩分によってコンクリート路盤4aを形成する鉄筋コンクリートの鉄筋4cが、図2に示すように、腐蝕されて膨潤した膨潤部4dに対し、それらの剥離や浮きあるいは膨潤部4dをハンマーなどでハツリ取り、あるいは鉄筋4cに錆を生じている場合、錆の部分をワイヤーブラシなどをかけて錆を除去するなどの補修の予備処理を行う。この予備処理を終えると、本処理のために、トンネル1における補修箇所の端部を決定し、その部分の監視員通路4の縦壁5に通路方向と直角向きのマーキングをダイヤモンドホイールで行う。   These will be described in more detail. First, a preliminary survey will be conducted before repair work. That is, in order to grasp the situation in the tunnel 1 of the automobile exclusive road, as a preliminary survey, the base plate 6b below the column 6a of the handrail 6 provided for safety on the side of the traveling lane 2 of the supervisor passage 4 is provided. Record the situation of the repaired parts such as the passage surface of the supervisory passage 4 around the road and the wall surface of the vertical wall 5 of the riverside supervisory passage 4 of the traveling route 2, and determine the construction site of the place requiring repair To do. Pre-processing is performed on the repaired part of the determined supervisor passage 4. In this pre-processing, the path surface of the supervisor path 4 around the base plate 6b below the column 6a of the handrail 6 of the handrail 6 of the supervisor path 4 found in the preliminary survey and the vertical length of the guard path 4 of the traveling route 2 are detected. As shown in FIG. 2, a reinforced concrete reinforcing bar 4c that forms a concrete roadbed 4a with respect to peeling or floating of concrete and tiles on the wall due to deterioration due to long-term use on the wall of the wall 5, or by the salt content of the antifreeze agent, If the swollen portion 4d that has been corroded and swollen is peeled off or lifted off, or the swollen portion 4d is scraped off with a hammer or the like, or rust is formed on the reinforcing bar 4c, the rust portion is covered with a wire brush or the like. Perform preparatory repairs such as removal. When this preliminary process is completed, the end of the repair location in the tunnel 1 is determined for this process, and the vertical wall 5 of the supervisor path 4 of that portion is marked with a diamond wheel in a direction perpendicular to the path direction.

補修箇所の端部が決定すると、走行車線の補修箇所に近接の1車線を走行規制し、この走行車線を規制した箇所に資機材を持ち込み、補修作業を開始する。補修作業の手始めとして、監視員通路4の補修用のステンレス製L字型タイル補修板9あるいはその上に被せるパネル材12を支持するための支保材14の取り付けに必要なコンクリートアンカー17を打ち込む位置にマーキングを行う。このマーキングでは、監視員通路4のコンクリート路盤4a及び手摺り6の下部の走行車線2のがわの縦壁5の下部のそれぞれのコンクリートアンカー17の打ち込み位置に、ステンレス製L字型タイル補修板9及びその上に重ねるパネル材12に合わせて、マーキング用の所定の位置に振動ドリルで先導孔をあけ、その後に指定太さのハンマードリルで削孔を行って穿孔する。この場合穿孔の深さが所定のものとなるように、ドリルビットにビニールテープでマーキングして深さを確認して穿孔する。さらに上記で決定した補修箇所の端部に、非補修箇所のタイル模様と連続させるための、タイル模様となる幅のL字型端部止め型枠を、幅900mmのステンレス製L字型タイル補修板9から重ね合わせ部を設けて切り出す。この切り出したL字型端部止め型枠を取り付けるために、監視員通路4と縦壁5の下部に通路方向と鉛直向きのマーキングを行ない、そのマーキング位置に上記と同様の方法で穿孔する。これらの穿孔した箇所にコンクリートアンカー17を打ち込む際には、必ずアンカー打ち込み棒を使用し、壁面に直角になるように打ち込む。   When the end of the repair location is determined, the travel restriction of one lane in the vicinity of the repair lane of the travel lane is restricted, and the equipment is brought to the location where the travel lane is restricted, and the repair work is started. As a start of repair work, a position where a concrete anchor 17 necessary for mounting a support member 14 for supporting a stainless steel L-shaped tile repair plate 9 for repairing the monitoring passage 4 or a panel material 12 placed thereon is driven. Mark on. In this marking, a stainless steel L-shaped tile repair plate is placed at each concrete anchor 17 driving position at the lower part of the vertical wall 5 of the concrete roadbed 4a of the monitoring person passage 4 and the traveling lane 2 below the handrail 6. 9 and the panel material 12 stacked thereon, a leading hole is drilled with a vibration drill at a predetermined position for marking, and then drilled with a hammer drill of a specified thickness. In this case, the drill bit is marked with a vinyl tape so that the perforation depth becomes a predetermined depth, and the depth is confirmed to perforate. In addition, an L-shaped end-stop formwork with a width of a tile pattern to be connected to the tile pattern of the non-repaired area at the end of the repaired area determined above is repaired with a 900 mm-wide stainless steel L-shaped tile. An overlapping portion is provided from the plate 9 and cut out. In order to attach the cut-out L-shaped end portion stop form, markings in the direction of the passage and the vertical direction are made at the lower part of the supervisor passage 4 and the vertical wall 5, and the marking position is punched in the same manner as described above. When the concrete anchor 17 is driven into these drilled portions, an anchor driving rod is always used, and the concrete anchor 17 is driven so as to be perpendicular to the wall surface.

以上のコンクリートアンカー17の打込みが終わると、先ず、ステンレス製L字型タイル補修板9、パネル材12及び支保材14の取り付け位置のコンクリート面の凹凸を確認しながら、先ずステンレス製L字型タイル補修板9を監視員通路4とその縦壁5に当接する。すなわち前面タイル模様補修板10を縦壁5に当接し上面補修枠11を監視員通路4に当接する。さらに当接した上面補修枠11の端部の傾斜面11a及び取付け面11b並びにこれらの両側の傾斜面11a及び水平な取付け面11bの間の下側に傾斜面11aおよび水平な取付け面11bの形状をした支柱開口部カバー11fを差し入れて設ける。これらの傾斜面11a及び取付け面11b並びに支柱開口部カバー11fの下部のコンクリート面に、図5に示すように、シールゴム13からなるパッキンを貼り付ける。ステンレス製L字型タイル補修板9の前面タイル模様補修板10及び上面補修枠11と、前面タイル模様補修板10に重ねたパネル材12は支保材14で表面から支持し、図8の(b)に示すように、上部は長い固定ボルト15でL字型受け材16にワッシャー15aで締め付けてコンクリートアンカー17に取り付け、下部は短い固定ボルト15でコンクリートアンカー17に取り付けて、それぞれゆるみの無いように固定する。この場合、上記したように、シールゴム13を取付け面11bの下部のコンクリート面の上に敷いているので、監視員通路4の部分に溜まった湧き水などが補修した箇所に浸入することは無い。またステンレス製L字型タイル補修板9、と隣接のステンレス製L字型タイル補修板9の継目の挿入重ね部9b及び11eは図示しないビスで固定し、継目の間に段差が生じたり、注入したモルタルが漏れないようにする。さらに、ステンレス製L字型タイル補修板9の上面補修枠11のモルタル注入孔11cからモルタルを注入した際に、監視員通路4のコンクリート路盤4aの前面に設けた前面タイル模様補修板10が注入されたモルタルによる面圧2t/m2の圧力で前面の路側帯3の側へ膨れ出ることを防止する必要がある。このため前面タイル模様補修板10の表面を厚さ略20mmの木質のパネル材12で覆って、パネル材12を支保材14で支持する。 When the concrete anchor 17 is driven in, the stainless steel L-shaped tile is first checked while confirming the unevenness of the concrete surface at the mounting position of the stainless steel L-shaped tile repair plate 9, the panel material 12 and the support material 14. The repair plate 9 is brought into contact with the supervisor passage 4 and its vertical wall 5. That is, the front tile pattern repair plate 10 is brought into contact with the vertical wall 5 and the upper surface repair frame 11 is brought into contact with the supervisor passage 4. Further, the shape of the inclined surface 11a and the horizontal mounting surface 11b on the lower side between the inclined surface 11a and the mounting surface 11b at the end of the upper surface repair frame 11 and the inclined surfaces 11a and the horizontal mounting surfaces 11b on both sides thereof. The column opening cover 11f that has been subjected to is inserted and provided. As shown in FIG. 5, a packing made of a seal rubber 13 is attached to the inclined concrete surface 11a, the attachment surface 11b, and the concrete surface below the support opening cover 11f. The front tile pattern repair plate 10 and the upper surface repair frame 11 of the stainless steel L-shaped tile repair plate 9 and the panel material 12 overlaid on the front tile pattern repair plate 10 are supported from the surface by a support material 14, and FIG. ), The upper part is attached to the concrete anchor 17 by tightening the L-shaped receiving member 16 with a long fixing bolt 15 with a washer 15a, and the lower part is attached to the concrete anchor 17 with a short fixing bolt 15 so that there is no looseness. Secure to. In this case, as described above, since the seal rubber 13 is laid on the concrete surface below the mounting surface 11b, the spring water accumulated in the portion of the supervisor passage 4 does not enter the repaired portion. The stainless steel L-shaped tile repair plate 9 and the adjacent overlapped portions 9b and 11e of the stainless steel L-shaped tile repair plate 9 are fixed with screws (not shown) so that a step is formed between the joints or injected. Prevent mortar from leaking. Further, when the mortar is injected from the mortar injection hole 11c of the upper surface repair frame 11 of the stainless steel L-shaped tile repair plate 9, the front tile pattern repair plate 10 provided on the front surface of the concrete roadbed 4a of the supervisor passage 4 is injected. It is necessary to prevent the mortar from bulging out to the roadside belt 3 side at the front pressure of 2 t / m 2 . For this reason, the surface of the front tile pattern repair plate 10 is covered with a wooden panel material 12 having a thickness of about 20 mm, and the panel material 12 is supported by the support material 14.

上記の支保材の取付けが完了すると、充填材であるモルタルと練り混ぜて準備する。この準備では、モルタル(商品名:デンカハイプレタスコン)に対し、モルタル25kg当たり水4.5kgとなるように計量した水を容器の中に入れ、ハンドミキサーで十分に練り混ぜる。この十分に混練したモルタルを上面補修枠11のモルタル注入孔11cへ練り混ぜた容器から直接に注入する。この注入した部分の天端は注入したモルタルが落ち着いてから2回手作業により平滑化する仕上げ行う。次いで、充填したモルタルは凡そ1時間余りで固化するので、モルタルの注入完了から2時間後にモルタル注入孔11cから充填したモルタルの硬さを確認してから、固定ボルト15を外して支保材14を解体し、前面タイル模様補修板10の前面のパネル材12を取り外す。この後、解体した支保材14を撤去した後、コンクリートアンカー17の部分に解体の際にボルトを抜いて生じたボルト孔に、再びステンレス製ボルトを挿着して固定して、ボルト孔から水などが浸入しないものとする。これらの一連の作業が終了すると、作業箇所とした走行車線の片付けを行なってすべての資機材を回収し、さらに注入材であるモルタルの付着した箇所を清掃して、片付け撤収した後、走行車線の走行規制を解除し、次の補修箇所に移動して補修の準備及び補修作業を実施する。   When the attachment of the support material is completed, the mortar as a filler is mixed and prepared. In this preparation, water weighed in a mortar (trade name: DENKA HIGH PRETUSCON) so that the amount of water is 4.5 kg per 25 kg of mortar is put in a container and sufficiently mixed with a hand mixer. This fully kneaded mortar is poured directly into the mortar injection hole 11c of the upper surface repair frame 11 from a kneaded container. The top end of the injected portion is finished by smoothing by hand twice after the injected mortar settles. Next, since the filled mortar solidifies in about one hour, after confirming the hardness of the mortar filled from the mortar injection hole 11c two hours after the completion of the mortar injection, the fixing bolt 15 is removed and the support material 14 is removed. The panel material 12 of the front surface of the front tile pattern repair board 10 is removed. Thereafter, after the dismantled support material 14 is removed, a stainless steel bolt is again inserted into and fixed to the bolt hole formed by removing the bolt at the time of dismantling in the concrete anchor 17, and water is removed from the bolt hole. Etc. shall not enter. When these series of operations are completed, the traveling lane as the work location is cleaned up, all materials and equipment are collected, and the mortar, which is the injection material, is cleaned, cleaned up and removed, then the driving lane The travel regulations are canceled, and the next repair location is moved to prepare for repair and repair work.

1 トンネル
1a トンネル側壁
2 走行車線
3 路側帯
3a 円形水路
4 監視員通路
4a コンクリート路盤
4b 溝
4c 鉄筋
4d 膨潤部
5 縦壁
5a タイル壁面
6 手摺り
6a 支柱
6b ベースプレート
7 欠損部
8 補修箇所
9 ステンレス製L字型タイル補修板
9a 前面タイル模様
9b 挿入重ね部
9c 傾斜面
9d 取付け面
10 前面タイル模様補修板
11 上面補修枠
11a 傾斜面
11b 取付け面
11c モルタル注入孔
11d 支柱開口部
11e 挿入重ね部
11f 支柱開口部カバー
12 パネル(コンパネ)材
13 シールゴム
14 支保材(C字型の)
15 固定ボルト
16 L字型受け材
17 コンクリートアンカー
DESCRIPTION OF SYMBOLS 1 Tunnel 1a Tunnel side wall 2 Driving lane 3 Roadside zone 3a Circular water channel 4 Surveillance passage 4a Concrete roadbed 4b Groove 4c Reinforcement 4d Swelling part 5 Vertical wall 5a Tile wall 6 Handrail 6a Post 6b Base plate 7 Defect part 8 Stainless steel repair part 9 L-shaped tile repair plate 9a Front tile pattern 9b Insertion overlap portion 9c Inclined surface 9d Mounting surface 10 Front tile pattern repair plate 11 Upper surface repair frame 11a Inclined surface 11b Mounting surface 11c Mortar injection hole 11d Post opening 11e Insertion overlap portion 11f Post Opening cover 12 Panel (company) material 13 Seal rubber 14 Support material (C-shaped)
15 Fixing bolt 16 L-shaped receiving material 17 Concrete anchor

Claims (2)

監視員通路の路側帯側の手摺り支柱のベースプレートの下部のコンクリートからなる監視員通路の欠損した通路面の部分およびこの通路面の路側帯側の欠損したコンクリートの縦壁の部分やこの縦壁表面のタイル剥離面の部分や損壊タイル面の部分に前面タイル模様補修板および上面補修枠からなるステンレス製L字型タイル補修板を当接し、該前面タイル模様補修板の表面をパネル材で覆い、該パネル材および該上面補修枠を監視員通路面およびコンクリートの縦壁に断面C字型の支保材で取り付け支持した後、上面補修枠に有する開口部から下部の監視員通路のコンクリート欠損部およびその側面の縦壁欠損部に無収縮性モルタルを流し込み該欠損部を充填固化して、該監視員通路のコンクリート欠損部およびその側面のタイル剥離面あるいはタイル損壊面に、上面補修枠および前面タイル模様補修板を固着し、この固着後に該支保材を解体してパネル材を取り外す方法からなることを特徴とするトンネル側壁ぎわの監視員通路の通路面の欠損部並びに縦壁およびタイル壁面の欠損部のステンレス製L字型タイル補修板による補修方法。   The part of the missing passage surface of the guard's passage made of concrete below the base plate of the handrail post on the roadside belt side of the guard's passage and the part of the vertical wall of the missing concrete on the roadside belt side of this passage surface and this vertical wall The front tile pattern repair plate and the stainless steel L-shaped tile repair plate made of the upper surface repair frame are brought into contact with the surface of the tile peeling surface and the damaged tile surface, and the surface of the front tile pattern repair plate is covered with a panel material. After the panel material and the upper surface repair frame are attached to and supported by the monitoring member passage surface and the vertical wall of the concrete with a support member having a C-shaped cross section, the concrete missing portion of the lower monitoring member passage from the opening provided in the upper surface repair frame Then, non-shrinkable mortar is poured into the vertical wall defect on the side surface and the defect part is filled and solidified, so that the concrete defect part of the observer passage and the tile peeling surface on the side surface are aligned. Or, the upper surface repair frame and the front tile pattern repair plate are fixed to the damaged surface of the tile, and after the fixing, the support material is disassembled and the panel material is removed. Repair method using a stainless steel L-shaped tile repair plate for road surface defects and vertical wall and tile wall defects. 前面タイル模様補修板および上面補修枠からなるステンレス製L字型タイル補修板を当接し、該前面タイル模様補修板の表面にパネル材で覆い、該パネル材および該上面補修枠を監視員通路面およびコンクリートの縦壁に断面C字型の支保材で取り付け支持する方法は、前面タイル模様補修板の表面を覆ったパネル材の表面に断面C字型の支保材を縦方向に当接し、該支保材の下端部の内面のコンクリートにコンクリートアンカーを打ち込み、該支保材の下端部の表面から固定ボルトを該コンクリートアンカーにねじ結合してパネル材の下端部を支持し、上面補修枠の後端側の監視員通路の上面にコンクリートアンカーを打ち込み、L字型受け材の横部材の表面から固定ボルトを該コンクリートアンカーにねじ結合し、該支保材の上端部の表面から長尺の固定ボルトをL字型受け材の縦部材の上部に挿通してナットで固定してパネル材の上端部を支持して、前面タイル模様補修板および上面補修枠からなるステンレス製L字型タイル補修板を支持する方法からなることを特徴とする請求項1に記載のトンネル側壁ぎわの監視員通路の通路面の欠損部並びに縦壁およびタイル壁面の欠損部のステンレス製L字型タイル補修板による補修方法。   A stainless steel L-shaped tile repair plate made of a front tile pattern repair plate and an upper surface repair frame is contacted, and the surface of the front tile pattern repair plate is covered with a panel material, and the panel material and the upper surface repair frame are covered with a supervisor passage And a method of attaching and supporting to a vertical wall of concrete with a support member having a C-shaped cross section, a support material having a C-shaped cross section is brought into contact with the surface of the panel material covering the surface of the front tile pattern repair plate in the vertical direction, A concrete anchor is driven into the concrete on the inner surface of the lower end portion of the support material, and a fixing bolt is screwed to the concrete anchor from the surface of the lower end portion of the support material to support the lower end portion of the panel material. A concrete anchor is driven into the upper surface of the side observer's passage, and a fixing bolt is screwed to the concrete anchor from the surface of the transverse member of the L-shaped receiving member. A long fixing bolt is inserted into the upper part of the vertical member of the L-shaped receiving material and fixed with a nut to support the upper end of the panel material, and is made of stainless steel L consisting of a front tile pattern repair plate and an upper surface repair frame 2. The stainless-steel L-shaped tile of a passage surface of a tunnel side wall guard passage and a defect of a vertical wall and a tile wall surface according to claim 1, characterized by comprising a method of supporting a letter-shaped tile repair plate. Repair method with repair plate.
JP2011002484A 2011-01-07 2011-01-07 Repair method for damaged vertical wall tiles in the tunnel inspector passage Active JP4880075B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011002484A JP4880075B1 (en) 2011-01-07 2011-01-07 Repair method for damaged vertical wall tiles in the tunnel inspector passage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011002484A JP4880075B1 (en) 2011-01-07 2011-01-07 Repair method for damaged vertical wall tiles in the tunnel inspector passage

Publications (2)

Publication Number Publication Date
JP4880075B1 true JP4880075B1 (en) 2012-02-22
JP2012144869A JP2012144869A (en) 2012-08-02

Family

ID=45851213

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011002484A Active JP4880075B1 (en) 2011-01-07 2011-01-07 Repair method for damaged vertical wall tiles in the tunnel inspector passage

Country Status (1)

Country Link
JP (1) JP4880075B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112983550A (en) * 2021-03-30 2021-06-18 广东华隧建设集团股份有限公司 Multidimensional temperature sensing monitoring system for freezing soft and hard strata of subway communication channel

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5761701B1 (en) * 2015-02-09 2015-08-12 株式会社ヒロコーポレーション How to repair the wall that raises the observer passage in the tunnel
JP7037782B2 (en) * 2017-12-20 2022-03-17 Jfe建材株式会社 Arched structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0392202U (en) * 1990-01-10 1991-09-19
JPH07189486A (en) * 1993-12-27 1995-07-28 Shoei Kensou Kk Molding method by cement slurry form impregnation onto existing concrete surface
JP2004263376A (en) * 2003-02-28 2004-09-24 Fuji Ultrasonic Engineering Co Ltd Repair construction method for existing structure
JP2010007424A (en) * 2008-06-30 2010-01-14 Milcon:Kk Wall surface board for construction of tunnel passage
JP2011127422A (en) * 2009-11-18 2011-06-30 Furukawa Electric Co Ltd:The Method for repairing concrete structure, and resin panel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0392202U (en) * 1990-01-10 1991-09-19
JPH07189486A (en) * 1993-12-27 1995-07-28 Shoei Kensou Kk Molding method by cement slurry form impregnation onto existing concrete surface
JP2004263376A (en) * 2003-02-28 2004-09-24 Fuji Ultrasonic Engineering Co Ltd Repair construction method for existing structure
JP2010007424A (en) * 2008-06-30 2010-01-14 Milcon:Kk Wall surface board for construction of tunnel passage
JP2011127422A (en) * 2009-11-18 2011-06-30 Furukawa Electric Co Ltd:The Method for repairing concrete structure, and resin panel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112983550A (en) * 2021-03-30 2021-06-18 广东华隧建设集团股份有限公司 Multidimensional temperature sensing monitoring system for freezing soft and hard strata of subway communication channel

Also Published As

Publication number Publication date
JP2012144869A (en) 2012-08-02

Similar Documents

Publication Publication Date Title
CN108677758A (en) The antidumping anti-fall girder apparatus and its construction method that existing bridge is added
CN102296546A (en) Treatment scheme of hollow slab bridge hinge joint defects and construction process thereof
JP2015224478A (en) Abutted-type expansion/contraction device for road bridge, and construction and repair methods therefor
JP2008121374A (en) Structure for embedding expansion joint in highway bridge
CN111455776B (en) Construction method of ground anchor type steel structure overhanging sidewalk
JP4880075B1 (en) Repair method for damaged vertical wall tiles in the tunnel inspector passage
CN107178031A (en) A kind of unit assembled prestressing force Multidirectional displacement bridge expansion device and installation method
JP6393556B2 (en) Method for repairing drain gutter and cover block for repair
CN208346657U (en) The antidumping anti-fall girder apparatus that existing bridge is added
CN113202142B (en) Composite asphalt pavement inspection well protection device and pavement construction method
CN202194081U (en) Hinge joint disease treatment structure of hollow slab bridge
JP5958907B2 (en) Partial restoration method for existing concrete slabs
JP7239423B2 (en) Floor slab reinforcement method for horizontal tightening PC bridge
JP6810472B2 (en) Repair method for drainage lids for bridges
EP1865109A2 (en) Method for improving a steel bridge, as well as a steel bridge improved in this manner
JP6360769B2 (en) Widening method of existing road bridge
KR100786357B1 (en) Reinforcement equipment and method for joint of concrete paved road
JPH0538086Y2 (en)
JP6504838B2 (en) Repair method for concrete deck top
JP2022158643A (en) Repair construction method and repair structure using stainless steel repair panel for wall of expressway tunnel watchman passage
KR101335606B1 (en) Metallic saw concrete type expansion joint installation method
JP4954934B2 (en) Gutter block
JP2020190091A (en) Drainage ditch forming members and road bridge drainage ditch replacement and repair method
JP5090292B2 (en) Reinforcement structure and reinforcement method for box-shaped diagonal members of lower steel truss bridge
JP2022078456A (en) Countermeasure construction method for damage on tunnel monitoring passage wall and countermeasure structure for damage

Legal Events

Date Code Title Description
A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20111124

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20111129

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20111130

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4880075

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141209

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250