JP4526625B2 - Method for producing precast concrete member - Google Patents
Method for producing precast concrete member Download PDFInfo
- Publication number
- JP4526625B2 JP4526625B2 JP34685199A JP34685199A JP4526625B2 JP 4526625 B2 JP4526625 B2 JP 4526625B2 JP 34685199 A JP34685199 A JP 34685199A JP 34685199 A JP34685199 A JP 34685199A JP 4526625 B2 JP4526625 B2 JP 4526625B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- heat insulating
- insulating material
- top end
- precast concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Description
【0001】
【発明の属する技術分野】
本発明は、例えば建築現場などでプレキャストコンクリート柱を短期間に製造する場合などに好適なプレキャストコンクリート部材の製造方法に関する。
【0002】
【従来の技術】
従来、例えばプレキャストコンクリート柱を工場内で製造する場合、一日程度の短期間に完成させる必要があるときには、次に説明するように蒸気養生又は発熱体を使用した養生を行って、コンクリートを加熱することにより強制的に乾燥させるようにしていた。
【0003】
すなわち、蒸気養生では、例えば鋼板製の型枠内にコンクリートを打設した後、型枠ごとシートで覆い、これを蒸気雰囲気中に運び込んで加熱することによりコンクリートを強制的に乾燥させる。
【0004】
また、発熱体を使用した養生では、鋼板製の型枠の外周面に板状ヒータなどの発熱体を取り付け、この発熱体によりコンクリートを加熱することによって、コンクリートを強制的に乾燥させる。
【0005】
一方、プレキャストコンクリート柱を、例えば建築現場などで短期間に製造する場合には、蒸気養生のための設備がないのが普通であり、例えば板状ヒータなどの発熱体を用いて養生するのが一般的であった。
【0006】
【発明が解決しようとする課題】
しかしながら、従来の蒸気養生又は発熱体による養生では、いずれにしても設備が大型化或いは複雑化してコストアップになるという問題があった。
【0007】
すなわち、蒸気養生では、蒸気を発生させるためのボイラーが必要であり、また、蒸気雰囲気を作るため密閉された部屋が必要であり、更にこの密閉された部屋もプレキャスト柱を収納できるだけの相当大きな部屋が必要になるため、設備が大型になる。
【0008】
また、発熱体を使用する場合には、これを型枠の外周面に取り付けてコンクリートを加熱するが、そのまま通電したのでは発熱体の温度が非常に高くななるので、コンクリートの養生に使用するには無理がある。そこで、発熱体の温度をコンクリートの養生に適した温度になるようにコントロールし、しかも時間の経過と共に温度を変化させる必要がある。これを実行するのには、一般にはコンピュータ制御等が必要になるため、設備が複雑になる。特に、発熱体から離れたコンクリート天端はしばしば初期効果による表面クラックが発生するという問題があった。
【0009】
このような問題は、プレキャストコンクリート柱に限らず各種のプレキャストコンクリート部材を製造するときに発生することがあった。
そこで、本発明は、建築現場などのように蒸気養生の設備がない場合に、発熱体のように複雑な設備を使用することなく、クラックの発生を防ぐと共に、簡単な構成で短期間にプレキャストコンクリート部材を製造することが可能なプレキャストコンクリート部材の製造方法を提供することを目的とする。
【0010】
【課題を解決するための手段】
上記の課題を解決するために、本発明は次のような構成としている。すなわち、本発明は、型枠の外周が断熱材で覆われているプレキャストコンクリート部材の型枠を形成した後、前記型枠内にコンクリートを打設し、前記型枠内に打設したコンクリートの天端部上を断熱材で覆い、前記型枠の外周及び前記天端部上を前記断熱材で覆った状態で前記コンクリートを養生することを特徴とする。
【0011】
次に、各部の構成について説明する。
(型枠)
型枠は、特に限定されないが、例えば鋼板などで構成することができる。この型枠の一部を開閉可能にすることにより、内部のプレキャストコンクリート部材を簡単に取り出すことが可能になる。
(断熱材)
型枠の外周面及びコンクリートの天端部から外部に水和熱が逃げるのを防止するものであり、材質は特に限定されないが、発泡材のように軽量で剛性のあるものが、取り扱いが容易であり望ましい。グラスウールなども使用できる。
【0012】
発泡材を使用する場合には、天端部上の水分がほぼなくなったときに発泡材を載せるようにする。これは、天端部上に水分があるときに発泡材を載せると、水分内に含まれているセメント成分が発泡材の気泡中に侵入し、コンクリートが乾燥したときに発泡材が天端部に付着してしまうからである。
(カバー部材)
カバー部材は、断熱材がコンクリートの天端部に付着したり、断熱材の表面の凹凸が天端部に影響を与えたりしないようにするものであり、シートや板部材などを使用することができる。
【0013】
本発明によれば、コンクリート内のセメント成分が水と反応するときに発生する水和熱が、型枠の外周面及びコンクリートの天端部を覆っている断熱材によって外部に放出されなくなり、コンクリート内に蓄積される。これによって、コンクリートが水和熱で加熱されて強制的に乾燥され、短期間に養生が終了する。
【0014】
また、天端部を断熱材で覆うことにより、天端部を含めてコンクリートが全体的に均一の速度で乾燥するため、コンクリートの表面側と内部の乾燥速度が異なるときに発生する表面クラックを防止できる。
【0015】
【発明の実施の形態】
以下、本発明に係るプレキャストコンクリート部材の製造方法の実施の形態について、図面を参照して詳細に説明する。
【0016】
図1は、本発明をプレキャストコンクリート柱に適用した場合について説明する断面図であり、コンクリートの養生中の状態を示す。
このプレキャスト部材の製造方法は、プレキャストコンクリート柱などを例えば建築現場などのように蒸気養生設備や発熱体による養生設備がない場所で、短期間、例えば1日程度で製造するときに好適である。
【0017】
このプレキャスト部材の製造方法では、例えば鋼板製の型枠11の外周が断熱材13で覆われ、組み立てられた型枠11内にコンクリート12が打設される。断熱材13は、押さえ板14によって脱落防止が行われる。コンクリート12には、複数の鉄筋15が埋設される。この鉄筋15は、コンクリート12の天端部12aより上に突出しており、この突出部分はプレキャストコンクリート柱を現地に設置したときに、その上に乗せられる梁部材(図示せず)などの主筋に結合される。
【0018】
また、鉄筋15の突出部分には、鉄筋15の位置ずれを防ぐため、鉄筋拘束用の型板16が嵌め込まれる。更に、コンクリート12の天端部12aには、鉄筋15を避けて断熱材17が載置される。なお、図中の符号18は、型枠11のベースである。
【0019】
次に各部の構成を詳細に説明する。型枠11は、プレキャストコンクリート柱を実際の設置形態と同様に立てた状態で製造するように組み立てられる。この型枠11は、高さが例えば約2.3mと非常に高いので、複数のブロック11a〜11eに分けて製造されている。各ブロック11a〜11eは、鋼板などの板部材で形成され、その上端には補強用のリブ19が設けられている。これらのブロック11a〜11eは、積み上げられて固定される。
【0020】
各ブロック11a〜11eは、図2に示すように断面が4角形の枠状に形成されている。そして、これらのブロック11a〜11eの4面を構成する板部材20a〜20dの両端部に側板部21が設けられている。
【0021】
また、各ブロック11a〜11eの4面を構成する板部材20a〜20dのうち、隣接する2面、本実施の形態では図2中の左側と下側の面を形成する板部材20a、20dが、次に説明するようにそれぞれ隣接する他の板部材20b,20cに開閉自在に取り付けられている。
【0022】
すなわち、板部材20a、20dの片方の側板部21が、この側板部21に設けられたブラケット22、隣接する板部材20b,20cの側板部21に設けられたブラケット23、及びこれらのブラケット22、23を連結するピン24を介して、隣接する板部材20b,20cに取り付けられており、これによって開閉自在になっている。
【0023】
型枠11の外周面に貼り付けられた断熱材13は、型枠11内でコンクリート12を養生中に、セメント中の成分が水と化合して発生する水和熱を外部に逃がさないようにし、この水和熱でコンクリート12を加熱して強制的に乾燥させるためのものであり、そのために必要な断熱材13の厚さは材質によって異なるが、いずれにしても上述の目的を達成できるような厚さとする。
【0024】
本実施の形態では、断熱材13として発泡材を使用する。この発泡材は、軽量で剛性があるため取り扱いやすく、また、断熱効果も大きいので厚さを小さくできて好都合である。
【0025】
コンクリート12の天端部12a上に載置する断熱材17(図1)も、上述の断熱材13と同様に発泡材を使用するが、ここでは、発泡材を露出した状態で天端部12a上に載置する。これにより、天端部12aが全面的に断熱材(発泡材)17で覆われる。
【0026】
天端部12a上に断熱材17を載置するときには、天端部12aを「こて」で均して平坦にする。この後、天端部12a上に浮き出ている水分が、コンクリート12内に滲み込んだり或いは蒸発してほぼなくなったことを確認してから、断熱材17を載せる。
【0027】
これは、天端部12a上に水分があるときに断熱材17を載せると、水分に含まれるモルタルが水分と一緒に断熱材17の気泡や隙間内に侵入し、これが乾燥したときに断熱材17がコンクリート12に付着してしまって剥がし難くなるからである。なお、天端部12a上の水分がほぼなくなる時間は、5分〜10分くらいであり、あまり時間が経過すると表面硬化が始まるので、水分がなくなったらすぐに断熱材17を載せるようにする。
【0028】
この断熱材17は、図3に示すように天端部12aの鉄筋15に囲まれた部分を覆う矩形ブロック17aと、鉄筋15の外側の部分を覆う2種類の大きさの長方形ブロック17b,17cとに分割されている。このように断熱材17をブロック分けすることによって、鉄筋15があっても簡単に着脱することができる。
【0029】
鉄筋15を拘束する型板16は、図4に示すように、例えば木材で4角形に形成し、その内側に全ての鉄筋15の位置に合わせて貫通孔27を設け、これらの貫通孔27に鉄筋15を通すようになっている。この型板16は、鉄筋15又は近くにある適宜な部材に固定する。
【0030】
次に、このプレキャストコンクリート部材の製造方法の施工手順を説明する。
ここでは、まず、図5に示すように建築現場の適宜な場所にベース18を配置し、その上に型枠11を組み立てる。型枠11には、予め断熱材13及び押さえ板14を取り付けておくが、型枠11を組み立てた後、断熱材13及び押さえ板14を取り付けることもできる。
【0031】
型枠11を組み立てた後、型枠11内に鉄筋15を配置し、この鉄筋15の適宜な部分を支持部材(図示せず)によって型枠11に固定する。
次に、図6に示すように、コンクリート供給ホース27によって型枠11内にコンクリート12を打設する。そして、コンクリート12が型枠11内の所定の高さまで打設された後、コンクリート12の天端部12aを「こて」で均して平坦に仕上げる。
【0032】
この状態で、天端部12a上に浮き出ている水分がほぼなくなるまで少しの時間待機する。そして、天端部12a上の水分がほぼなくなったとき直ぐに、図7に示すように天端部12上に断熱材17の各ブロック17a〜17cを載置する。断熱材17は、室内においては風によって吹き飛ばされるおそれがないので、単に載置するだけでよいが、風がある場合には断熱材17の上に錘を乗せるなどして固定する。次に、鉄筋15の上部側に型板16を嵌合して固定する。
【0033】
この状態でコンクリート12を養生すると、コンクリート12中のセメント成分と水とが反応して水和熱が発生する。この水和熱は、型枠11の外周を覆っている断熱材13と、天端部12aを覆っている断熱材17によって、外部に放出されることなくコンクリート12内に蓄積される。
【0034】
この蓄積された水和熱によって、コンクリート12が加熱されて強制的に乾燥され、1日程度の短期間でコンクリート12の養生が終了し、コンクリート12が所定の硬さまで硬化する。ここで、型枠11を取り外し、例えば鉄筋15を吊り上げて設置場所まで搬送することができる。
【0035】
なお、当初、型枠11の外周を断熱材13で覆うものの、天端部12a上を断熱材17で覆わずにシートを載せただけでコンクリート12を養生したところ、図8に示すように鉄筋15からコンクリート12の側端面にかけて、初期硬化による表面クラック28が発生した。この表面クラック28は、図9に示すように天端部12aからほぼ一定の深さまで続いていた。
【0036】
このように、鉄筋15の周囲に表面クラック28が発生した理由は、天端部12aを断熱材17で覆わない場合には、コンクリート12の養生中に、天端部12aの空気にさらされている部分が最初に乾燥硬化して収縮が始まるが、内部が硬化前なので表面に引張り応力が発生し、この引張応力によって鉄筋15の周囲のコンクリート12が外側に引っ張られるためと考えられる。表面クラック28は、水分が少なく強度の高いコンクリートほど発生しやすくなる。
【0037】
これに対して、本発明では、上述のように型枠11の外周と、天端部12a上の両方をそれぞれ断熱材13、17で覆っているので、天端部12aと内部の乾燥速度がほぼ均一となるため、表面クラック28の発生が見られなかった。このように、天端部12aは必ず断熱材17で覆う必要があることが分かる。
【0038】
このように、本発明のプレキャストコンクリート柱の製造方法によれば、型枠11の外周及びコンクリート12の天端部12a上を発泡材などの断熱材13、17で覆った状態で養生するので、コンクリート12の水和熱が内部に蓄積され、この水和熱によってコンクリート12が加熱されて強制的に乾燥される。
【0039】
これにより、プレキャストコンクリート柱を1日程度の短期間で製造することができる。また、蒸気養生や発熱板による養生などのように大型の設備や複雑な設備が不要であり、大幅なコスト低減が可能になる。
【0040】
更に、本実施の形態では、プレキャストコンクリート柱を立てた状態で製造するようにしたので、完成時にはそのまま設置位置に横移動するだけであり、重量の大きなプレキャストコンクリート柱を立てる必要がないため、クレーンなどの大型機械を使用する回数が少なくなる。
【0041】
なお、上述の実施の形態では、天端部12a上の水分がほぼなくなったときに、断熱材17を直接載置するようにしたが、天端部12a上に水分が残っている状態で断熱材17を載せる必要がある場合には、図10に示すように、天端部12a上にシートや鋼板(いずれも図示せず)などの表面が滑らかなカバー部材26を載置し、このカバー部材26の上に断熱材17を載置することができる。これにより、断熱材17がコンクリート12に付着するのを防止できる。
【0042】
また、断熱材17として例えばグラスウールなどのように天端部12aとの当接面が平坦でない部材を使用するときにも、天端部12a上にカバー部材26を敷いて、その上に断熱材17を載せることにより、天端部12aを平坦に仕上げることができる。
【0043】
更に、上述の実施の形態では、断熱材17又はカバー部材26を天端部12a上に直接載置したが、コンクリート12で発生した水和熱によってコンクリート12を強制的に乾燥するという目的を達成できれば、断熱材17又はカバー部材26と天端部12aとの間にある程度の隙間があってもよい。
【0044】
また、上述の実施の形態では、プレキャストコンクリート柱を実際の使用形態と同様に立てた状態で製造する場合について説明したが、図11に示すようにプレキャストコンクリート柱を横にした状態で製造する場合にも、本発明を適用することができる。
【0045】
この場合も、横長に組み立てた型枠31の外周を断熱材32で覆うと共に、型枠31内に打設したコンクリート33の天端部33a上を断熱材34で覆うことにより、短期間にプレキャストコンクリート柱を製造できる。なお、図11中の符号35は鉄筋、36は押さえ板、37は鉄筋拘束用の型板、38はベースである。
【0046】
上述の実施形態では、本発明をプレキャストコンクリート柱に適用した場合について説明したが、本発明はこれに限らず各種のプレキャストコンクリート部材に適用することができる。
【0047】
【発明の効果】
以上説明したように、本発明によれば、コンクリート内のセメント成分が水と反応するときに発生する水和熱が、断熱材によってコンクリート内部に蓄積され、この水和熱によってコンクリートが強制的に乾燥されるので、プレキャストコンクリート部材を短期間で製造することができる。
【0048】
また、コンクリートの天端部上を断熱材で覆うことにより、天端部と内部がほぼ均一の速度で乾燥するので、天端部に初期硬化による表面クラックが発生するのを防止できる。
【0049】
更に、断熱材を発泡材とした場合には、軽量で且つ剛性が高いので取り扱い易く、また、断熱効果が高いので厚さを小さくできる。
【図面の簡単な説明】
【図1】本発明のプレキャストコンクリート部材の製造方法を説明する縦断面図である。
【図2】図1のA−A断面図である。
【図3】図1のB−B断面図である。
【図4】本発明の鉄筋拘束用の型板を示す平面図である。
【図5】本発明の施工手順を示す図である。
【図6】本発明の施工手順を示す図である。
【図7】本発明の施工手順を示す図である。
【図8】コンクリートの天端部に発生する表面クラックを示す平面図である。
【図9】図8のC矢視図である。
【図10】本発明の別の実施形態を示す断面図である。
【図11】本発明の別の実施形態を示す断面図である。
【符号の説明】
11、31 型枠
12、33 コンクリート
12a、33a 天端部
13、17、32、34 断熱材
26 カバー部材[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for producing a precast concrete member suitable for producing a precast concrete column in a short period of time, for example, at a construction site.
[0002]
[Prior art]
Conventionally, for example, when precast concrete pillars are manufactured in a factory, when it is necessary to complete them in a short time of about a day, the concrete is heated by steam curing or curing using a heating element as described below. By doing so, it was forced to dry.
[0003]
That is, in steam curing, for example, concrete is placed in a mold made of steel, and then the mold is covered with a sheet, and the concrete is forcedly dried by carrying it in a steam atmosphere and heating it.
[0004]
In curing using a heating element, a heating element such as a plate heater is attached to the outer peripheral surface of a steel plate mold, and the concrete is forcibly dried by heating the concrete with the heating element.
[0005]
On the other hand, when precast concrete pillars are manufactured in a short period of time, for example, at a construction site, it is normal that there is no equipment for steam curing, for example, curing using a heating element such as a plate heater. It was general.
[0006]
[Problems to be solved by the invention]
However, in the conventional steam curing or curing with a heating element, there is a problem in that the equipment is enlarged or complicated in any case and the cost is increased.
[0007]
That is, in steam curing, a boiler for generating steam is necessary, and a sealed room is required to create a steam atmosphere, and this sealed room is also a considerably large room that can accommodate a precast pillar. Will be necessary, resulting in large equipment.
[0008]
If a heating element is used, the concrete is heated by attaching it to the outer peripheral surface of the formwork. However, if the current is applied as it is, the temperature of the heating element becomes very high, so it is used for curing concrete. Is impossible. Therefore, it is necessary to control the temperature of the heating element so as to be suitable for curing the concrete, and to change the temperature with time. In order to execute this, generally, computer control or the like is required, so that the facilities become complicated. In particular, the concrete top edge away from the heating element often suffers from surface cracks due to initial effects.
[0009]
Such a problem may occur when manufacturing various types of precast concrete members as well as precast concrete columns.
Therefore, the present invention prevents the occurrence of cracks without using complex equipment such as a heating element when there is no steam curing equipment as in a construction site, etc., and precasts in a short time with a simple configuration. It aims at providing the manufacturing method of the precast concrete member which can manufacture a concrete member.
[0010]
[Means for Solving the Problems]
In order to solve the above problems, the present invention has the following configuration. That is, according to the present invention, after forming a form of a precast concrete member in which the outer periphery of the form is covered with a heat insulating material, concrete is placed in the form, and the concrete placed in the form is The top is covered with a heat insulating material, and the concrete is cured in a state where the outer periphery of the mold and the top end are covered with the heat insulating material.
[0011]
Next, the configuration of each unit will be described.
(Formwork)
Although a formwork is not specifically limited, For example, it can comprise with a steel plate etc. By making a part of this mold form openable and closable, the internal precast concrete member can be easily taken out.
(Insulation material)
It prevents the heat of hydration from escaping from the outer peripheral surface of the formwork and the top edge of the concrete to the outside. The material is not particularly limited, but it is lightweight and rigid, such as foam, which is easy to handle. It is desirable. Glass wool can also be used.
[0012]
When a foam material is used, the foam material is placed when the water on the top end is almost gone. This is because if the foam is placed when there is moisture on the top edge, the cement component contained in the moisture will penetrate into the foam bubbles and the foam will be It is because it will adhere to.
(Cover member)
The cover member prevents the heat insulating material from adhering to the top edge of the concrete or the unevenness of the surface of the heat insulating material from affecting the top edge, and it is possible to use a sheet or plate member, etc. it can.
[0013]
According to the present invention, the heat of hydration generated when the cement component in the concrete reacts with water is not released to the outside by the heat insulating material covering the outer peripheral surface of the mold and the top end of the concrete. Accumulated within. As a result, the concrete is heated with heat of hydration and forced to dry, and curing is completed in a short period of time.
[0014]
In addition, by covering the top end with a heat insulating material, the concrete including the top end is dried at a uniform speed as a whole, so surface cracks that occur when the drying speed on the surface side and inside of the concrete are different. Can be prevented.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of a method for producing a precast concrete member according to the present invention will be described in detail with reference to the drawings.
[0016]
FIG. 1 is a cross-sectional view illustrating a case where the present invention is applied to a precast concrete column, and shows a state during curing of concrete.
This method for producing a precast member is suitable for producing a precast concrete column or the like in a short period of time, for example, about one day, in a place where there is no steam curing equipment or curing equipment such as a heating element such as a construction site.
[0017]
In this method of manufacturing a precast member, for example, the outer periphery of a steel plate mold 11 is covered with a
[0018]
Further, in order to prevent the position of the reinforcing
[0019]
Next, the configuration of each unit will be described in detail. The formwork 11 is assembled so that the precast concrete pillar is manufactured in a standing state in the same manner as the actual installation form. The mold 11 has a very high height of about 2.3 m, for example, and is thus divided into a plurality of blocks 11a to 11e. Each of the blocks 11a to 11e is formed of a plate member such as a steel plate, and a reinforcing
[0020]
Each of the blocks 11a to 11e is formed in a frame shape having a quadrangular cross section as shown in FIG. And the side-
[0021]
In addition, among the
[0022]
That is, one
[0023]
The
[0024]
In the present embodiment, a foam material is used as the
[0025]
The heat insulating material 17 (FIG. 1) placed on the
[0026]
When the
[0027]
This is because when the
[0028]
As shown in FIG. 3, the
[0029]
As shown in FIG. 4, the
[0030]
Next, the construction procedure of this precast concrete member manufacturing method will be described.
Here, first, as shown in FIG. 5, the
[0031]
After assembling the mold 11, the reinforcing
Next, as shown in FIG. 6, concrete 12 is placed in the mold 11 by the
[0032]
In this state, the apparatus waits for a short time until there is almost no moisture floating on the
[0033]
When the concrete 12 is cured in this state, the cement component in the concrete 12 reacts with water to generate heat of hydration. The heat of hydration is accumulated in the concrete 12 without being released to the outside by the
[0034]
With the accumulated heat of hydration, the concrete 12 is heated and forcibly dried, and the curing of the concrete 12 is completed in a short period of about one day, and the concrete 12 is cured to a predetermined hardness. Here, the formwork 11 can be removed and, for example, the reinforcing
[0035]
In addition, although the outer periphery of the mold 11 was initially covered with the
[0036]
As described above, the reason why the
[0037]
In contrast, in the present invention, both the outer periphery of the mold 11 and the
[0038]
Thus, according to the method for producing a precast concrete column of the present invention, the outer periphery of the mold 11 and the
[0039]
Thereby, a precast concrete pillar can be manufactured in a short period of about one day. In addition, large-scale facilities and complicated facilities such as steam curing and heat plate curing are not required, and a significant cost reduction is possible.
[0040]
Furthermore, in the present embodiment, since the precast concrete pillar is manufactured in an upright state, when it is completed, it only moves to the installation position as it is, and it is not necessary to stand a heavy precast concrete pillar. The number of times of using large machines such as is reduced.
[0041]
In the above-described embodiment, the
[0042]
In addition, when using a member whose contact surface with the
[0043]
Furthermore, in the above-described embodiment, the
[0044]
Moreover, in the above-mentioned embodiment, although the case where it manufactures in the state which stood the precast concrete pillar like the actual usage form was demonstrated, the case where it manufactures with the precast concrete pillar lying down as shown in FIG. Also, the present invention can be applied.
[0045]
Also in this case, the outer periphery of the horizontally assembled
[0046]
In the above-described embodiment, the case where the present invention is applied to a precast concrete column has been described. However, the present invention is not limited to this and can be applied to various precast concrete members.
[0047]
【The invention's effect】
As described above, according to the present invention, the heat of hydration generated when the cement component in the concrete reacts with water is accumulated in the concrete by the heat insulating material, and the concrete is forced by the heat of hydration. Since it is dried, the precast concrete member can be manufactured in a short period of time.
[0048]
In addition, by covering the top end portion of the concrete with a heat insulating material, the top end portion and the inside are dried at a substantially uniform speed, so that it is possible to prevent surface cracks due to initial hardening from occurring at the top end portion.
[0049]
Further, when the heat insulating material is a foam material, it is easy to handle because it is lightweight and has high rigidity, and the thickness can be reduced because the heat insulating effect is high.
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional view for explaining a method for producing a precast concrete member of the present invention.
FIG. 2 is a cross-sectional view taken along the line AA of FIG.
3 is a cross-sectional view taken along the line BB in FIG.
FIG. 4 is a plan view showing a rebar constraining template according to the present invention.
FIG. 5 is a diagram showing a construction procedure of the present invention.
FIG. 6 is a diagram showing a construction procedure of the present invention.
FIG. 7 is a diagram showing a construction procedure of the present invention.
FIG. 8 is a plan view showing surface cracks occurring at the top edge of concrete.
9 is a view taken in the direction of arrow C in FIG.
FIG. 10 is a cross-sectional view showing another embodiment of the present invention.
FIG. 11 is a cross-sectional view showing another embodiment of the present invention.
[Explanation of symbols]
11, 31
Claims (3)
前記天端部上の水分がなくなったときに、前記天端部上を前記断熱材で覆うことを特徴とするプレキャストコンクリート部材の製造方法。After forming the formwork of the precast concrete member whose outer periphery is covered with a heat insulating material, concrete is placed in the formwork and foamed on the top edge of the concrete placed in the formwork It is a method for producing a precast concrete member that is covered with a heat insulating material made of a material, and that cures the concrete in a state where the outer periphery of the formwork and the top end portion are covered with the heat insulating material,
A method for producing a precast concrete member, characterized in that when the water on the top end is exhausted, the top end is covered with the heat insulating material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP34685199A JP4526625B2 (en) | 1999-12-06 | 1999-12-06 | Method for producing precast concrete member |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP34685199A JP4526625B2 (en) | 1999-12-06 | 1999-12-06 | Method for producing precast concrete member |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001162609A JP2001162609A (en) | 2001-06-19 |
JP4526625B2 true JP4526625B2 (en) | 2010-08-18 |
Family
ID=18386244
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP34685199A Expired - Fee Related JP4526625B2 (en) | 1999-12-06 | 1999-12-06 | Method for producing precast concrete member |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4526625B2 (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5065797B2 (en) * | 2007-08-03 | 2012-11-07 | 小柳建設株式会社 | Block manufacturing formwork |
JP5382399B2 (en) * | 2007-10-03 | 2014-01-08 | 清水建設株式会社 | Thermal insulation and curing method for mass concrete |
JP4852018B2 (en) * | 2007-10-30 | 2012-01-11 | 大成建設株式会社 | How to build concrete columns |
CN107520947A (en) * | 2016-06-21 | 2017-12-29 | 中国十七冶集团有限公司 | A kind of prefabricated column joint production mould and its application method |
CN112497445B (en) * | 2020-11-30 | 2022-04-01 | 铭际建筑科技(泰兴)有限公司 | Quick-drying pouring device for concrete prefabricated wall panel |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01282171A (en) * | 1988-05-10 | 1989-11-14 | Toshiro Suzuki | Production of precast concrete member |
JPH11170240A (en) * | 1997-12-05 | 1999-06-29 | Oriental Construction Co Ltd | Production of pc member by adiabatic curing |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0354127Y2 (en) * | 1984-09-20 | 1991-11-28 | ||
JPS61183610U (en) * | 1986-04-25 | 1986-11-15 | ||
JPH0196051A (en) * | 1987-10-08 | 1989-04-14 | Toshiro Suzuki | Method for casting concrete in cold season |
JPH01282170A (en) * | 1988-05-09 | 1989-11-14 | Sekisui Chem Co Ltd | Production of inorganic sheet |
JPH0721725Y2 (en) * | 1992-05-13 | 1995-05-17 | 戸田建設株式会社 | Concrete member curing sheet |
-
1999
- 1999-12-06 JP JP34685199A patent/JP4526625B2/en not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01282171A (en) * | 1988-05-10 | 1989-11-14 | Toshiro Suzuki | Production of precast concrete member |
JPH11170240A (en) * | 1997-12-05 | 1999-06-29 | Oriental Construction Co Ltd | Production of pc member by adiabatic curing |
Also Published As
Publication number | Publication date |
---|---|
JP2001162609A (en) | 2001-06-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4526625B2 (en) | Method for producing precast concrete member | |
JP2005508465A (en) | Architectural components | |
CN114000646A (en) | Reverse-beating integrated wallboard of precast concrete composite heat-insulation template and preparation method | |
JPH11229402A (en) | Foundation and construction for steel frame structure | |
US5894704A (en) | Wall construction process | |
KR20120069263A (en) | Half slab providing hollow material construction method and half slab using the same | |
JP3264933B2 (en) | Manufacturing method of thermal insulation panel for large panel structure | |
JPH11193533A (en) | Execution method of foundation part | |
JP2000104392A (en) | Floor panel and its manufacture | |
JP3612108B2 (en) | RC wall construction method | |
JP4746781B2 (en) | Exterior insulation construction method for buildings | |
JP3611119B2 (en) | Building soundproofing structure and building soundproofing construction method | |
JP2862952B2 (en) | Manufacturing method of precast concrete board | |
JPH08302710A (en) | Machine base for installation equipment and constructing method thereof | |
JPH0825338A (en) | Manufacture of hollow pc beam | |
KR100297426B1 (en) | Glass block panel and manufacturing method of glass block panel | |
JP2863995B2 (en) | Concrete formwork | |
JPH05208411A (en) | Construction of foundation plate for hollow concrete slab and manufacture thereof | |
KR200209618Y1 (en) | A sheeting panel of a transparency for inspected a construction | |
GB2582688A (en) | Wall panels | |
JP3020071U (en) | Plate formwork | |
JPH0673840A (en) | Manufacture of decorative laminated column | |
JPS6243086Y2 (en) | ||
JP3829891B2 (en) | Block panel manufacturing method | |
JPH08151724A (en) | Unit structure and production thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050404 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20080213 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080507 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080701 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090714 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090914 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20100511 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20100602 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130611 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313532 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |