JP4449875B2 - Large-section tunnel structure and its construction method - Google Patents

Large-section tunnel structure and its construction method Download PDF

Info

Publication number
JP4449875B2
JP4449875B2 JP2005281872A JP2005281872A JP4449875B2 JP 4449875 B2 JP4449875 B2 JP 4449875B2 JP 2005281872 A JP2005281872 A JP 2005281872A JP 2005281872 A JP2005281872 A JP 2005281872A JP 4449875 B2 JP4449875 B2 JP 4449875B2
Authority
JP
Japan
Prior art keywords
tunnel
arch
arch member
shaped
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2005281872A
Other languages
Japanese (ja)
Other versions
JP2007092355A (en
Inventor
則雄 浅見
伴行 後藤
隆夫 奥田
雄介 前田
Original Assignee
羽田コンクリート工業株式会社
ケイコン株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 羽田コンクリート工業株式会社, ケイコン株式会社 filed Critical 羽田コンクリート工業株式会社
Priority to JP2005281872A priority Critical patent/JP4449875B2/en
Publication of JP2007092355A publication Critical patent/JP2007092355A/en
Application granted granted Critical
Publication of JP4449875B2 publication Critical patent/JP4449875B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

本発明は、主に開削工法によって形成されるトンネルに用いられるものであって、特に大断面のトンネル構造及びその構築方法に関するものである。 The present invention is mainly used for a tunnel formed by a cutting method, and particularly relates to a tunnel structure having a large cross section and a method for constructing the tunnel structure.

従来、この種の大断面のトンネルは、地盤上に型枠を組み、前記型枠内にコンクリートを現場打ちして構築する方法が一般的であった。ところが、現場打ちコンクリートによりトンネルを構築するには作業工数が増大し、コストがかかるという問題があった。このような問題に対して、トンネル長さ方向に延びる底版の幅方向両端間に、左右一対の円弧版状のプレキャストコンクリート版がアーチ状に架け渡されるとともにトンネル長さ方向に連結され、底版の幅方向両端には、各プレキャストコンクリート版の脚部の外側において脚部の外面と適宜の間隔をあけて上方に膨出しトンネル長さ方向に延びる側帯が一体に設けられ、この側帯と前記脚部の間に受圧部材が介在されるとともに、脚部が側帯にボルト等の締結部材で締結され、前記コンクリート版を覆って盛土が施されて構成されるものが開示されている(例えば特許文献1)。
特開平7−216917号公報
Conventionally, this type of large-section tunnel is generally constructed by assembling a formwork on the ground and placing concrete in the formwork on-site. However, the construction of a tunnel using cast-in-place concrete has the problem that the number of work steps increases and costs increase. For such a problem, a pair of left and right arc plate-shaped precast concrete plates are arched between both ends in the width direction of the bottom plate extending in the tunnel length direction and connected in the tunnel length direction. At both ends in the width direction, side bands that bulge upward at an appropriate distance from the outer surface of the leg part and extend in the tunnel length direction on the outside of the leg part of each precast concrete plate are integrally provided. A pressure receiving member is interposed therebetween, and a leg portion is fastened to a side band by a fastening member such as a bolt, and a bank is applied to cover the concrete plate (for example, Patent Document 1). ).
JP 7-21617 A

しかしながら、上記したトンネル構造においては、円弧版をプレキャストコンクリート版により構成しコストの低減を図れるものの、トンネルの長さ方向に延びる底版を現場打ちコンクリートで形成する必要があり、この作業が煩雑で、低減できるコストに限界があった。 However, in the tunnel structure described above, although the arc plate can be constituted by a precast concrete plate and the cost can be reduced, it is necessary to form the bottom plate extending in the length direction of the tunnel with the cast-in-place concrete, and this work is complicated. There was a limit to the cost that could be reduced.

そこで、本発明は上記した問題点に鑑み、現場作業の工数を低減することによって、コストを削減できる大断面のトンネル構造及びその構築方法を提供することを目的とする。 In view of the above-described problems, an object of the present invention is to provide a tunnel structure having a large cross section that can reduce the cost by reducing the number of man-hours for field work and a construction method thereof.

上記目的を達成するために、請求項1に係る発明は、トンネル底側部からトンネル高さ方向に延びる左右一対のプレキャストコンクリート製のL形部材と、前記L形部材間に横架されるプレキャストコンクリート製のアーチ部材とにより形成され、前記L形部材は、底部と、前記底部の一端から垂直に延びる側壁部とからなり、前記側壁部は、上方が内側に湾曲しており、前記側壁部の上端面に接続継手が突設され、前記接続継手は前記アーチ部材に設けられた継手受部に挿入されてなることを特徴とする。 In order to achieve the above-mentioned object, the invention according to claim 1 is directed to a pair of left and right precast concrete L-shaped members extending in the tunnel height direction from the bottom side of the tunnel, and a precast horizontally mounted between the L-shaped members. The L-shaped member includes a bottom portion and a side wall portion extending vertically from one end of the bottom portion, and the side wall portion is curved inward at the upper side, and the side wall portion A connection joint projects from the upper end surface of the arch member, and the connection joint is inserted into a joint receiving portion provided in the arch member .

また、請求項に係る発明は、請求項1において、前記アーチ部材は、頂部で左右に分割して構成されることを特徴とする。 The invention according to claim 2 is characterized in that, in claim 1, the arch member is divided into left and right at the top.

また、請求項に係る発明は、請求項1又は2において、前記アーチ部材は、埋込体を備えることを特徴とする。 The invention according to claim 3, Oite to claim 1 or 2, wherein the arch member is characterized in that it comprises an embedded member.

また、請求項に係る発明は、請求項1〜いずれか1項において、前記L形部材間に中央底版部を設けることを特徴とする。 The invention according to claim 4 is characterized in that, in any one of claims 1 to 3 , a central bottom plate portion is provided between the L-shaped members.

また、請求項に係る発明は、請求項1〜いずれか1項において、前記L形部材の背面に背面底版部を設けることを特徴とする。 The invention according to claim 5 is characterized in that, in any one of claims 1 to 3 , a back bottom plate portion is provided on the back surface of the L-shaped member.

また、請求項に係る発明は、トンネル底側部からトンネル高さ方向に延びる左右一対のプレキャストトンネル製のL形部材を設置し、前記一対のL形部材同士を間隔保持部材で連結し、アーチ部材を横架し、前記L形部材と前記アーチ部材とを接続した後、前記間隔保持部材を撤去することを特徴とする。 Further, the invention according to claim 6 is provided by installing a pair of left and right precast tunnel L-shaped members extending in the tunnel height direction from the tunnel bottom side, and connecting the pair of L-shaped members with a spacing member. An arch member is horizontally mounted, and after the L-shaped member and the arch member are connected , the spacing member is removed.

本発明の請求項1に記載の大断面のトンネル構造によれば、複数に分割されたプレキャストコンクリート製の部材で構成することにより、大断面であっても現場作業の工数を低減し、コストを削減することができる。また、側壁をL形部材で構成したことにより、側壁が自立することができるので、容易に設置でき作業工数を低減できる。 According to the tunnel structure having a large cross section according to claim 1 of the present invention, the construction of the member made of precast concrete divided into a plurality of parts reduces the man-hours for on-site work even with a large cross section, and reduces the cost. Can be reduced. Further, since the side wall is made of an L-shaped member, the side wall can stand on its own, so that it can be easily installed and the number of work steps can be reduced.

また、請求項に記載の大断面のトンネル構造によれば、アーチ部材を分割して構成したことにより、輸送が容易となり、大きな断面を有するトンネルであっても、プレキャストコンクリート製の部材により構築することができるので、コストをより低減できる。 Further, according to the tunnel structure with a large cross section according to claim 2 , the arch member is divided and configured to facilitate transportation, and even a tunnel having a large cross section is constructed with a precast concrete member. Cost can be further reduced.

また、請求項に記載の大断面のトンネル構造によれば、埋込体を埋設することにより、アーチ部材を軽量化して、材料費、輸送費を削減できると共に、現場における作業を容易に行なうことができるので、さらにコストを削減することができる。 According to the tunnel structure having a large cross section according to claim 3 , by embedding the embedded body, the arch member can be reduced in weight, and the material cost and the transportation cost can be reduced, and the work on the site can be easily performed. Therefore, the cost can be further reduced.

また、請求項に記載の大断面のトンネル構造によれば、中央底版部を設けることにより、軟弱な地盤においても確実に構築することができる。 Moreover, according to the tunnel structure of the large cross section of Claim 4 , it can construct | assemble reliably in a soft ground by providing a center bottom slab part.

また、請求項に記載の大断面のトンネル構造によれば、背面底版部を設けることにより、少ない材料で構築できるので、コストを削減できる。 Further, according to the tunnel structure having a large cross section according to the fifth aspect , by providing the back bottom plate portion, the construction can be made with a small amount of material, so that the cost can be reduced.

また、請求項に記載の大断面のトンネル構築方法によれば、左右一対のL形部材同士を保持部材により連結するので、構築途中においてL形部材が転倒するのを防止できる。また、L型部材を所定間隔に保持することもできるので、安全かつ容易に大断面のトンネルを構築することができるので、コストを低減できる。 Moreover, according to the tunnel construction method of the large cross section of Claim 6 , since a pair of left and right L-shaped members are connected by the holding member, the L-shaped member can be prevented from falling during the construction. In addition, since the L-shaped members can be held at a predetermined interval, a tunnel with a large cross section can be constructed safely and easily, so that the cost can be reduced.

以下図面を参照して、本発明の第1実施例について説明する。 A first embodiment of the present invention will be described below with reference to the drawings.

図1に示すトンネル構造1は、トンネル底側部からトンネル高さ方向に延びる左右一対のプレキャストコンクリート製のL形部材2と、前記L形部材2の上方に横架されるプレキャストコンクリート製のアーチ部材3とにより形成される。また、L形部材2の間には底版部である中央底版部4が現場打ちコンクリートにより形成される。 A tunnel structure 1 shown in FIG. 1 includes a pair of left and right precast concrete L-shaped members 2 extending in the tunnel height direction from a tunnel bottom side, and a precast concrete arch that is horizontally mounted above the L-shaped members 2. And the member 3. Further, between the L-shaped members 2, a central bottom slab portion 4 which is a bottom slab portion is formed of cast-in-place concrete.

L形部材2は、地盤Gに当接する底部5と、前記底部5の一端から垂直に延びる側壁部6とからなり、予め工場で形成されたものである。前記側壁部6は、内側すなわち底部5の他端側へ上方が緩やかに湾曲しており、トンネルの高さの略中間の高さに形成される。また、L形部材2には、トンネルの長さ方向における縦締めを行うための縦締用挿通孔7が設けられる。 The L-shaped member 2 includes a bottom portion 5 that contacts the ground G and a side wall portion 6 that extends perpendicularly from one end of the bottom portion 5 and is formed in advance at a factory. The side wall portion 6 is gently curved upward on the inner side, that is, toward the other end side of the bottom portion 5, and is formed at a height approximately in the middle of the height of the tunnel. Further, the L-shaped member 2 is provided with a vertical fastening insertion hole 7 for performing vertical fastening in the length direction of the tunnel.

アーチ部材3は、上方に凸となるようにトンネルの幅方向に湾曲して形成された前記側壁部6と略同じ厚さを有する矩形の版部材であって、予め工場で形成されたものである。このアーチ部材3は、周方向の一端に設けられた接合部8と、他端に設けられた頂部9とを備える。また、アーチ部材3には、トンネルの長さ方向における縦締めを行うための縦締用挿通孔7が外周面に設けられる。 The arch member 3 is a rectangular plate member having substantially the same thickness as the side wall portion 6 which is curved in the width direction of the tunnel so as to protrude upward, and is formed in advance at a factory. is there. The arch member 3 includes a joint portion 8 provided at one end in the circumferential direction and a top portion 9 provided at the other end. Further, the arch member 3 is provided with a vertical fastening insertion hole 7 on the outer peripheral surface for vertical fastening in the length direction of the tunnel.

L形部材2及びアーチ部材3には、埋込体17が埋設されており、これによりL形部材2及びアーチ部材3を軽量化することができる。埋込体17は種々のものが考えられ、例えば、紙、段ボール、発泡スチロール等により管や円柱を形成してもよいし、また、塩ビ管で構成してもよい。また、埋込体17を鋼管で構成することにより、L形部材2及びアーチ部材3に配筋される鉄筋に置き換えることとしてもよい。アーチ部材3に埋設される埋込体17は、周方向に複数連設されることによって、湾曲している周方向の略全体に渡って埋設することができる。 An embedded body 17 is embedded in the L-shaped member 2 and the arch member 3, whereby the L-shaped member 2 and the arch member 3 can be reduced in weight. Various types of the embedded body 17 are conceivable. For example, a tube or a cylinder may be formed of paper, cardboard, polystyrene foam, or the like, or a polyvinyl chloride tube may be used. Moreover, it is good also as replacing with the reinforcing bar arranged by the L-shaped member 2 and the arch member 3 by comprising the embedded body 17 with a steel pipe. A plurality of the embedded bodies 17 embedded in the arch member 3 can be embedded over substantially the entire curved circumferential direction by providing a plurality of embedded bodies 17 in the circumferential direction.

図2に示すように、側壁部6の上端には、接続継手10と、ガイド部材11とが設けられている。接続継手10は、側壁部6の上端面6aに垂直に突設されている。また、ガイド部材11は、鋼鉄製の版部材であって、側壁部6の内側に固定され、上端面6aに直行する方向に突出している。アーチ部材3の周方向の一端に設けられた接合部8の接合面8aには、前記L形部材2の側壁部6の上端面6aに設けられた接続継手10が係合する継手受部12が内設されている。 As shown in FIG. 2, a connection joint 10 and a guide member 11 are provided at the upper end of the side wall portion 6. The connection joint 10 protrudes perpendicularly to the upper end surface 6 a of the side wall portion 6. The guide member 11 is a steel plate member, is fixed to the inside of the side wall portion 6, and protrudes in a direction perpendicular to the upper end surface 6a. A joint receiving portion 12 with which a joint 10 provided on the upper end surface 6a of the side wall portion 6 of the L-shaped member 2 engages with a joint surface 8a of the joint portion 8 provided at one end in the circumferential direction of the arch member 3. Is installed.

アーチ部材3の周方向の他端に設けられた頂部9には、図3に示すように、頂部端面9aに直交して貫通する挿通孔15が形成されている。この挿通孔15によりアーチ部材3の表面側に形成される開口には、座面16が設けられる。このアーチ部材3は、左右一対として構成され、前記頂部端面9aで互いに突き合わされてトンネルの天井部分に配置される。 As shown in FIG. 3, an insertion hole 15 penetrating perpendicularly to the top end face 9a is formed in the top 9 provided at the other end in the circumferential direction of the arch member 3. A seat surface 16 is provided in an opening formed on the surface side of the arch member 3 by the insertion hole 15. The arch members 3 are configured as a pair of left and right, and are arranged to face each other at the top end face 9a and are arranged on the ceiling portion of the tunnel.

次に、上記したトンネル構造1の構築方法について図を参照して説明する。 Next, a method for constructing the tunnel structure 1 will be described with reference to the drawings.

まず、プレキャストコンクリート製のL形部材2及びアーチ部材3を設置する場合について説明する。図4(A)に示すように、開削した地盤G上に、均しコンクリートにより基礎20を敷設する。次いで、この基礎20の上に、図示しない敷きモルタルを施工した後、前記L形部材2を左右一対として設置する。L形部材2は、底部5と一体化されているので、自立することができ、作業性を向上することができる。 First, the case where the L-shaped member 2 and the arch member 3 made of precast concrete are installed will be described. As shown in FIG. 4 (A), a foundation 20 is laid on the ground G that has been cut by using leveled concrete. Next, after constructing a mortar (not shown) on the foundation 20, the L-shaped member 2 is installed as a pair of left and right. Since the L-shaped member 2 is integrated with the bottom portion 5, it can stand on its own and workability can be improved.

このようにトンネルの長さ方向に同様の作業を繰り返し行ない、左右一対の前記L形部材2を、間隔保持部材27で連結する。前記間隔保持部材27は、両端に雄ネジが形成された一対の横杆28aで構成される。それぞれの横杆28aの一端はL形部材の側壁に予め形成された貫通穴に挿通し、プレート29を介してナット26bに固定される。また、それぞれの間隔保持部材27の他端は、一対のL形部材2の略中央で連結手段28b、例えば、ターンバックルによって他端同士が連結される。これにより、構築途中においてL形部材2が転倒するのを防止できると共に、所定間隔に保持することができる。尚、上記のように横架された間隔保持部材27は、L形部材2及びアーチ部材3を後述する方法により締結した後、撤去される。 In this way, the same operation is repeated in the length direction of the tunnel, and the pair of left and right L-shaped members 2 are connected by the spacing member 27. The spacing member 27 is composed of a pair of horizontal rods 28a having male screws formed at both ends. One end of each horizontal rod 28a is inserted into a through-hole formed in advance in the side wall of the L-shaped member, and fixed to the nut 26b via the plate 29. The other ends of the spacing members 27 are connected to each other by a connecting means 28b, for example, a turnbuckle, at the approximate center of the pair of L-shaped members 2. As a result, the L-shaped member 2 can be prevented from falling down during the construction, and can be held at a predetermined interval. In addition, the space | interval holding member 27 horizontally mounted as mentioned above is removed after fastening the L-shaped member 2 and the arch member 3 by the method mentioned later.

次に、図4(B)に示すように、移動自在の架台21を一対の前記L形部材2の略中間に設置する。この架台21の上端には、ジャッキ22が備えられる。また、図示しないが、L形部材2の背面側に転倒防止用の枠組みを、L形部材2の内側にアーチ部材3を架設するための足場をそれぞれ設ける。 Next, as shown in FIG. 4 (B), a movable base 21 is installed approximately in the middle of the pair of L-shaped members 2. A jack 22 is provided at the upper end of the gantry 21. Although not shown, a frame for preventing overturning is provided on the back side of the L-shaped member 2, and a scaffold for constructing the arch member 3 is provided on the inner side of the L-shaped member 2.

次に、L形部材2の側壁部6に一方のアーチ部材3を横架する。L形部材2の側壁部6にアーチ部材3を横架するには、図5に示すように、アーチ部材3の両端近傍にワイヤ23を係止する。アーチ部材3の頂部9側に係止した頂部側ワイヤ23aには予めチェーンブロック24が接続されている。このワイヤ23を図示しないクレーンに接続し、クレーンでアーチ部材3を引き上げる。次いで、前記チェーンブロック24により頂部側ワイヤ23aを巻き上げ、アーチ部材3の頂部9を持ち上げる。アーチ部材3の頂部9を持ち上げることによって、図2に示すように、継手受部12が設けられたアーチ部材3の接合面8aの角度を側壁部6の上端面6aの角度に合わせる。継手受部12が設けられたアーチ部材3の接合面8aと、側壁部6の上端面6aとの角度を合わせた後、接続継手10を継手受部12に挿入し、アーチ部材3を架台21に設置する。このとき、側壁部6の上端には、ガイド部材11が設けられていることにより、容易に接続継手10を挿入することができる。尚、継手受部12にはモルタルが充填され、接合部8においてアーチ部材3と側壁部6とが固定される。同様にして他方のアーチ部材3の接合部8をL形部材2の側壁部6の上端6aに接続し、架台21に設置する(図4(C))。 Next, one arch member 3 is horizontally mounted on the side wall portion 6 of the L-shaped member 2. In order to horizontally mount the arch member 3 on the side wall portion 6 of the L-shaped member 2, the wires 23 are locked in the vicinity of both ends of the arch member 3 as shown in FIG. 5. A chain block 24 is connected in advance to the top side wire 23a locked to the top 9 side of the arch member 3. The wire 23 is connected to a crane (not shown), and the arch member 3 is pulled up by the crane. Next, the top wire 23a is wound up by the chain block 24, and the top 9 of the arch member 3 is lifted. By lifting the top portion 9 of the arch member 3, the angle of the joint surface 8a of the arch member 3 provided with the joint receiving portion 12 is matched with the angle of the upper end surface 6a of the side wall portion 6 as shown in FIG. After matching the angle between the joint surface 8a of the arch member 3 provided with the joint receiving portion 12 and the upper end surface 6a of the side wall portion 6, the connecting joint 10 is inserted into the joint receiving portion 12, and the arch member 3 is attached to the base 21. Install in. At this time, since the guide member 11 is provided at the upper end of the side wall portion 6, the connection joint 10 can be easily inserted. The joint receiving portion 12 is filled with mortar, and the arch member 3 and the side wall portion 6 are fixed at the joint portion 8. Similarly, the joint portion 8 of the other arch member 3 is connected to the upper end 6a of the side wall portion 6 of the L-shaped member 2 and installed on the mount 21 (FIG. 4C).

次に、左右一対のアーチ部材3を、頂部9で接合する場合について説明する。まず、架台21に備えられたジャッキ22を昇降させ一方のアーチ部材3の頂部9の高さを調節し、他方のアーチ部材3の頂部9の高さに合わせる。両方のアーチ部材3の頂部9の高さが位置決めできたら、図3に示すように、頂部端面9aに直交して貫通する挿通孔15にPC鋼棒25を挿通する。挿通孔15に挿通したPC鋼棒25の両端にナット26aを螺合し、ナット26aを締め上げ、PC鋼棒25に緊張力を導入する。これにより、左右のアーチ部材3の頂部9に左右方向の緊張力であるプレストレスを導入する。このプレストレスの反力は、アーチ部材3の外表面に形成された座面16で吸収される。 Next, a case where the pair of left and right arch members 3 are joined at the top 9 will be described. First, the jack 22 provided on the gantry 21 is moved up and down to adjust the height of the top portion 9 of one arch member 3, and is adjusted to the height of the top portion 9 of the other arch member 3. When the heights of the top portions 9 of both arch members 3 can be positioned, the PC steel rod 25 is inserted into the insertion hole 15 penetrating perpendicularly to the top end surface 9a, as shown in FIG. A nut 26 a is screwed to both ends of the PC steel rod 25 inserted through the insertion hole 15, the nut 26 a is tightened, and a tension force is introduced into the PC steel rod 25. Thereby, prestress which is tension in the left-right direction is introduced into the top portions 9 of the left and right arch members 3. This prestress reaction force is absorbed by the seating surface 16 formed on the outer surface of the arch member 3.

また、トンネルの長さ方向に同様の作業を繰り返し行ない、所定数、例えばアーチ部材3を10セット設置した段階で、トンネルの長さ方向に対し縦締めをし、一体化される。縦締めは、図示しないが、アーチ部材3及びL形部材2の外周表面に形成された縦締用挿通孔7にPC鋼棒を挿通し、PC鋼棒の両端にナットを螺合し、ナットを締め上げ、PC鋼棒に緊張力を導入して行われる。 Further, the same operation is repeated in the length direction of the tunnel, and when a predetermined number, for example, 10 sets of the arch members 3 are installed, they are vertically tightened in the length direction of the tunnel and integrated. Although the vertical tightening is not shown, a PC steel rod is inserted into the vertical tightening insertion hole 7 formed on the outer peripheral surface of the arch member 3 and the L-shaped member 2, and nuts are screwed into both ends of the PC steel rod. This is done by introducing tension to the PC steel bar.

次に、現場に設置された上記トンネル部材に中央底版部4を打設する場合について説明する。中央底版部4は、前記L形部材2の底部5の間に配筋された図示しない鉄筋と、現場打ちコンクリートとにより構成され、前記鉄筋と、前記底部5に予め張り出し形成された鉄筋とが図示しない機械式継手で接続される。機械式継手は、種々のものが考えられる。例えば、図示しないが、L形部材2の底部5に設けられた鉄筋に埋込側スリーブを固設し、中央底版部4を構成する端部の鉄筋に接続側スリーブを固設して、それぞれのスリーブに対となるように右雌ネジと左雌ネジのいずれかを形成し、一端に右ネジを他端に左ネジを備えた接続ボルトで固定する方法によって接続することができる。こうして、鉄筋を接合したL形部材2の底部5の間にコンクリートを打設して中央底版部4を形成する(図4(D))。上記作業終了後、枠組み、足場が解体され、撤去される。 Next, the case where the center bottom slab part 4 is driven in the said tunnel member installed in the field is demonstrated. The center bottom plate portion 4 is composed of a reinforcing bar (not shown) arranged between the bottom portions 5 of the L-shaped member 2 and a cast-in-place concrete, and the reinforcing bars and the reinforcing bars formed in advance on the bottom portion 5 are formed. They are connected by a mechanical joint (not shown). Various mechanical joints are conceivable. For example, although not shown in the drawings, the embedding sleeve is fixed to the reinforcing bar provided on the bottom 5 of the L-shaped member 2, and the connecting sleeve is fixed to the reinforcing bar at the end constituting the central bottom plate portion 4. Either a right female screw or a left female screw is formed so as to be paired with the sleeve, and the connection can be established by fixing with a connection bolt having a right screw at one end and a left screw at the other end. In this way, the concrete is cast between the bottom portions 5 of the L-shaped member 2 to which the reinforcing bars are joined to form the central bottom plate portion 4 (FIG. 4D). After the above work is completed, the framework and scaffolding are dismantled and removed.

このように、本実施形態に係るトンネル構造1が、複数の分割されたプレキャストコンクリート製の部材により構成されることにより、現場打ちコンクリートで構築した場合に比べ、型枠の設置、解体が不要になるなど、大幅に作業工数を低減でき、コストを大幅に低減できる。また、トンネル構造1が、4分割により構成されることにより、工場で容易に形成できると共に、容易に輸送することができる。 As described above, the tunnel structure 1 according to the present embodiment is constituted by a plurality of divided precast concrete members, so that installation and dismantling of the formwork are unnecessary as compared with a case where the tunnel structure 1 is constructed by on-site concrete. The work man-hours can be greatly reduced and the cost can be greatly reduced. In addition, since the tunnel structure 1 is constituted by four parts, it can be easily formed in a factory and can be easily transported.

尚、地盤Gが軟弱である場合には、上記のようにL形部材2の底部5の間に中央底版部4を設ける必要があるが、強固な地盤Gに対しては、図6に示すような底版部として背面底版部30を適用することができる。背面底版部30は、L形部材2の背面に現場打ちコンクリートによって形成される。これにより、中央底版部4に比べ、使用する部材量を少なくすることができるので、十分な強度を保持しながら、コストを低減することができる。 In addition, when the ground G is soft, it is necessary to provide the center bottom plate | board part 4 between the bottom parts 5 of the L-shaped member 2 as mentioned above, but for the strong ground G, it shows in FIG. The back bottom plate portion 30 can be applied as such a bottom plate portion. The back bottom plate portion 30 is formed on the back surface of the L-shaped member 2 by cast-in-place concrete. Thereby, since the amount of members to be used can be reduced as compared with the central bottom plate portion 4, the cost can be reduced while maintaining a sufficient strength.

上記のように構築された大断面のトンネル構造1は、アーチ部材3及び側壁部6に土圧等によるモーメントが発生すると、プレストレスを導入したPC鋼棒25で吸収する。また、本実施形態に係るトンネル構造1では、L形部材2の側壁部6と底部5とを接続する箇所に応力が集中するが、上記の通り、L形部材2は側壁部6と底部5とを一体化して形成しているので、応力に対し十分な強度を確保することができる。このようにトンネル構造1では、各応力を吸収し得る構造となっているため、大断面であって、かつ、複数のプレキャストコンクリート製の部材からなるものでありながら、十分な強度を確保することができる。 The tunnel structure 1 having a large cross section constructed as described above absorbs the arch member 3 and the side wall 6 with a PC steel rod 25 into which prestress is introduced when a moment due to earth pressure or the like is generated. Further, in the tunnel structure 1 according to the present embodiment, stress concentrates on a location where the side wall portion 6 and the bottom portion 5 of the L-shaped member 2 are connected. As described above, the L-shaped member 2 has the side wall portion 6 and the bottom portion 5. Can be ensured sufficient strength against stress. As described above, the tunnel structure 1 has a structure capable of absorbing each stress. Therefore, the tunnel structure 1 has a large cross section and is made of a plurality of precast concrete members, but ensures sufficient strength. Can do.

上記のように本実施形態においては、トンネル底側部からトンネル高さ方向に延びる左右一対のプレキャストコンクリート製のL形部材2と、前記L形部材2間に横架されるプレキャストコンクリート製のアーチ部材3とにより形成されることにより、大断面であっても現場作業の工数を低減することによって、コストを削減することができる。また、側壁をL形部材2で構成したことにより、側壁が自立することができるので、容易に設置でき作業工数を低減できる。 As described above, in the present embodiment, a pair of left and right precast concrete L-shaped members 2 extending in the tunnel height direction from the bottom side of the tunnel, and a precast concrete arch horizontally mounted between the L-shaped members 2 By forming with the member 3, even if it is a large cross section, cost can be reduced by reducing the man-hour of field work. Further, since the side wall is made of the L-shaped member 2, the side wall can stand on its own, so that it can be easily installed and the number of work steps can be reduced.

また、前記アーチ部材3は、頂部9で左右に分割して構成されることにより、輸送が容易となり大きな断面を有するトンネルであっても、プレキャストコンクリート製の部材により構築することができるので、コストを低減できる。 Further, since the arch member 3 is divided into left and right at the top portion 9, it is easy to transport and can be constructed with a precast concrete member even if it is a tunnel having a large cross section. Can be reduced.

また、前記アーチ部材3は、埋込体17を備えることにより、アーチ部材3を軽量化して、材料費、輸送費を削減できると共に、現場作業を容易に行なえるので、さらにコストの低減を図ることができる。 Further, since the arch member 3 includes the embedded body 17, the arch member 3 can be reduced in weight to reduce the material cost and the transportation cost, and the field work can be easily performed, so that the cost can be further reduced. be able to.

また、前記L形部材2の間に中央底版部4を設けることにより、軟弱な地盤Gにおいても確実に構築することができる。 In addition, by providing the central bottom plate portion 4 between the L-shaped members 2, the soft ground G can be reliably constructed.

また、前記L形部材2の背面に背面底版部30を設けることにより、少ない材料で構築できるので、コストを削減できる。 Moreover, since the back bottom plate portion 30 is provided on the back surface of the L-shaped member 2, it can be constructed with a small amount of material, so that the cost can be reduced.

また、トンネル底側部からトンネル高さ方向に延びる左右一対のプレキャストコンクリート製のL形部材2を設置し、頂部で左右に分割して構成されるアーチ部材3を横架し、前記L形部材2と前記アーチ部材3とを締結すると共にアーチ部材3同士を頂部9において緊張力を導入したPC鋼棒により締結することにより、より大きな内空を有するトンネルであっても、プレキャストコンクリート製の部材により構築することができるので、コストを低減できる。 Also, a pair of left and right precast concrete L-shaped members 2 extending in the tunnel height direction from the tunnel bottom side are installed, and an arch member 3 divided into left and right at the top is horizontally mounted, and the L-shaped member 2 and the arch member 3 and the arch members 3 are fastened to each other with a PC steel rod introduced with a tension force at the top portion 9, so that even a tunnel having a larger inner space can be made of a precast concrete member. Therefore, the cost can be reduced.

また、トンネル底側部からトンネル高さ方向に延びる左右一対のプレキャストコンクリート製のL形部材2を設置し、前記一対のL形部材同士2を間隔保持部材27で連結し、頂部で左右に分割して構成されるアーチ部材3を横架し、前記L形部材2と前記アーチ部材3とを締結すると共にアーチ部材3同士を頂部9において緊張力を導入したPC鋼棒により締結した後、前記間隔保持部材27を撤去することにより、左右一対のL形部材同士2を間隔保持部材27により連結するので、構築途中においてL形部材2が転倒するのを防止できる。また、L形部材2を所定間隔に保持することができ、安全かつ容易に大断面のトンネルを構築することができるので、コストを低減できる。 Also, a pair of left and right precast concrete L-shaped members 2 extending from the tunnel bottom side in the tunnel height direction are installed, the pair of L-shaped members 2 are connected by a spacing member 27, and divided into left and right at the top. The arch member 3 constructed as above is horizontally mounted, the L-shaped member 2 and the arch member 3 are fastened, and the arch members 3 are fastened to each other by a PC steel rod introduced with a tension force at the top portion 9. By removing the spacing member 27, the pair of left and right L-shaped members 2 are connected to each other by the spacing member 27, so that the L-shaped member 2 can be prevented from falling during the construction. Further, since the L-shaped member 2 can be held at a predetermined interval, and a tunnel with a large cross section can be constructed safely and easily, the cost can be reduced.

また、本実施形態ではトンネルの天井をアーチ部材3で閉塞する場合について説明したが、本発明はこれに限らず、図7に示すように斜めに切り込み31を設けたアーチ部材32をL形部材2に接続することとしてもよい。こうすることにより、トンネル出口における明かりとりを形成することもできる。 Further, in the present embodiment, the case where the ceiling of the tunnel is closed with the arch member 3 has been described. However, the present invention is not limited to this, and the arch member 32 provided with the oblique cuts 31 as shown in FIG. 2 may be connected. By doing so, it is also possible to form a light source at the tunnel exit.

次に本発明の第2実施例について説明する。尚、上記した第1実施例に係る構成と同様の構成については同様の符号を付し、簡単のため、説明を省略する。 Next, a second embodiment of the present invention will be described. In addition, the same code | symbol is attached | subjected about the structure similar to the structure which concerns on the above-mentioned 1st Example, and description is abbreviate | omitted for simplicity.

図8に示す本実施例に係るトンネル構造35は、第1実施例に係るトンネル構造1に対し、アーチ部材3のみが異なり、一対のL形部材2と、前記L形部材2間に横架される一体型アーチ部材36とにより構成される。すなわち、本実施例に係る一体型アーチ部材36は、上方に凸となるようにトンネルの幅方向に湾曲して形成された前記側壁部6と略同じ厚さを有する矩形の版部材であって、予め工場で形成されたものである。この一体型アーチ部材36とL形部材2の当接部37には、当接面に直交して貫通する図示しない挿通孔が形成されている。 The tunnel structure 35 according to this embodiment shown in FIG. 8 is different from the tunnel structure 1 according to the first embodiment only in the arch member 3, and is horizontally mounted between a pair of L-shaped members 2 and the L-shaped members 2. And the integrated arch member 36. That is, the integrated arch member 36 according to the present embodiment is a rectangular plate member having substantially the same thickness as the side wall portion 6 that is curved in the width direction of the tunnel so as to protrude upward. , Previously formed at the factory. In the contact portion 37 between the integral arch member 36 and the L-shaped member 2, an insertion hole (not shown) penetrating perpendicularly to the contact surface is formed.

次に、上記したトンネル構造1の構築方法について図9を参照して説明する。まず、図9(A)に示すように、開削した地盤G上に、均しコンクリートにより基礎20を敷設する。次いで、この基礎20の上に、図示しない敷きモルタルを施工した後、前記L形部材2を左右一対として設置する(図9(B))。 Next, a method for constructing the tunnel structure 1 will be described with reference to FIG. First, as shown in FIG. 9 (A), a foundation 20 is laid on the ground G that has been cut by using leveled concrete. Next, after laying mortar (not shown) on the foundation 20, the L-shaped member 2 is installed as a pair of left and right (FIG. 9B).

次に、図9(C)に示すように、移動自在の架台21を一対の前記L形部材2の略中間に設置する。また、図示しないが、L形部材2の背面側に転倒防止用の枠組みを、L形部材2の内側にアーチ部材3を架設するための足場をそれぞれ設ける。また、現場に設置された上記トンネル部材に中央底版部4を打設する。中央底版部4は、前記L形部材2の底部5の間に配筋された図示しない鉄筋と、現場打ちコンクリートとにより構成され、前記鉄筋と、前記底部5に予め張り出し形成された鉄筋とが図示しない機械式継手で接続される。 Next, as shown in FIG. 9 (C), a movable base 21 is installed approximately in the middle of the pair of L-shaped members 2. Although not shown, a frame for preventing overturning is provided on the back side of the L-shaped member 2, and a scaffold for constructing the arch member 3 is provided on the inner side of the L-shaped member 2. Moreover, the center bottom plate | version | printing part 4 is driven in the said tunnel member installed in the field. The center bottom plate portion 4 is composed of a reinforcing bar (not shown) arranged between the bottom portions 5 of the L-shaped member 2 and a cast-in-place concrete, and the reinforcing bars and the reinforcing bars formed in advance on the bottom portion 5 are formed. They are connected by a mechanical joint (not shown).

次に、L形部材2の側壁部6に一体型アーチ部材36を横架する。すなわち、図9(D)に示すように、一体型アーチ部材36の両端近傍にワイヤ23を係止する。ワイヤ23には予めチェーンブロック24が接続されている。このワイヤ23を図示しないクレーンに接続し、クレーンで一体型アーチ部材36を引き上げる。次いで、前記チェーンブロック24によりワイヤ23の長さを調節することによって一体型アーチ部材36の位置を微調整し、前記挿通孔に挿通した締結用PC鋼棒により一体型アーチ部材36をL形部材2に連結する。尚、一体型アーチ部材36を1セット設置するごとに目地部にはモルタルが充填され、一体型アーチ部材36と側壁部6とが固定される。 Next, the integral arch member 36 is horizontally mounted on the side wall portion 6 of the L-shaped member 2. That is, as shown in FIG. 9D, the wire 23 is locked in the vicinity of both ends of the integrated arch member 36. A chain block 24 is connected to the wire 23 in advance. The wire 23 is connected to a crane (not shown), and the integrated arch member 36 is pulled up by the crane. Next, the position of the integrated arch member 36 is finely adjusted by adjusting the length of the wire 23 by the chain block 24, and the integrated arch member 36 is formed into an L-shaped member by the fastening PC steel rod inserted through the insertion hole. Connect to 2. Each time one set of the integrated arch member 36 is installed, the joint portion is filled with mortar, and the integrated arch member 36 and the side wall portion 6 are fixed.

このようにトンネルの長さ方向に同様の作業を繰り返し行ない、所定数、例えば一体型アーチ部材36を2セット設置した段階で、トンネルの長さ方向に対し縦締めをし、一体化される。上記作業終了後、枠組み及び足場を解体し撤去する。 In this way, the same operation is repeated in the tunnel length direction, and when a predetermined number, for example, two sets of the integrated arch members 36 are installed, they are vertically tightened in the tunnel length direction and integrated. After completion of the above work, dismantle and remove the framework and scaffolding.

尚、L形部材2を間隔保持部材27で連結することとしてもよいことはもちろんである。 Needless to say, the L-shaped member 2 may be connected by the spacing member 27.

上記のように、本実施例に係るトンネル構造は、一体型アーチ部材3で構築したから、部材数を低減できるので、作業工数を削減することができ、コストダウンを図れる。 As described above, since the tunnel structure according to the present embodiment is constructed with the integrated arch member 3, the number of members can be reduced, so that the number of work steps can be reduced and the cost can be reduced.

本発明は、本実施形態に限定されるものではなく、本発明の要旨の範囲内で種々の変形実施が可能である。例えば、本実施形態では開削工法におけるトンネル構造について説明したが、本発明はこれに限らず、アーチ橋として適用することもできる。 The present invention is not limited to this embodiment, and various modifications can be made within the scope of the gist of the present invention. For example, in the present embodiment, the tunnel structure in the open-cut method has been described, but the present invention is not limited to this and can be applied as an arch bridge.

本実施形態に係る大断面のトンネル構造を示す縦断面図である。It is a longitudinal cross-sectional view which shows the tunnel structure of the large cross section based on this embodiment. 同上、側壁部とアーチ部材との接合部を示す縦断面図である。It is a longitudinal cross-sectional view which shows the junction part of a side wall part and an arch member same as the above. 同上、頂部の縦断面図である。It is a longitudinal cross-sectional view of the top part as above. 本実施形態に係る大断面のトンネルの構築方法を段階的に示す図である。It is a figure which shows the construction method of the tunnel of a large section concerning this embodiment in steps. 同上、アーチ部材を設置する状態を示す図である。It is a figure which shows the state which installs an arch member same as the above. 本実施形態の変形例を示す縦断面図である。It is a longitudinal cross-sectional view which shows the modification of this embodiment. 本実施形態の別の変形例を示す外観図である。It is an external view which shows another modification of this embodiment. 本発明の第2実施例に係るトンネル構造を示す縦断面図である。It is a longitudinal cross-sectional view which shows the tunnel structure based on 2nd Example of this invention. 同上、トンネルの構築方法を段階的に示す図である。It is a figure which shows the construction method of a tunnel step by step same as the above.

1 トンネル構造
2 L形部材
3 アーチ部材
4 中央底版部
9 頂部
17 埋込体
DESCRIPTION OF SYMBOLS 1 Tunnel structure 2 L-shaped member 3 Arch member 4 Center bottom plate part 9 Top part
17 Embedded

Claims (6)

トンネル底側部からトンネル高さ方向に延びる左右一対のプレキャストコンクリート製のL形部材と、前記L形部材間に横架されるプレキャストコンクリート製のアーチ部材とにより形成され、前記L形部材は、底部と、前記底部の一端から垂直に延びる側壁部とからなり、前記側壁部は、上方が内側に湾曲しており、前記側壁部の上端面に接続継手が突設され、前記接続継手は前記アーチ部材に設けられた継手受部に挿入されてなることを特徴とする大断面のトンネル構造。 A pair of left and right precast concrete L-shaped members extending in the tunnel height direction from the bottom side of the tunnel, and an arch member made of precast concrete horizontally placed between the L-shaped members, the L-shaped member, A bottom portion and a side wall portion extending perpendicularly from one end of the bottom portion, the side wall portion being curved inward on the upper side, a connection joint projecting from the upper end surface of the side wall portion, A tunnel structure having a large cross section, which is inserted into a joint receiving portion provided on an arch member . 前記アーチ部材は、頂部で左右に分割して構成されることを特徴とする請求項1記載の大断面のトンネル構造。 The arch member is large section of the tunnel structure according to claim 1 Symbol mounting, characterized in that it is constituted by being divided into right and left at the top. 前記アーチ部材は、埋込体を備えることを特徴とする請求項1又は2記載の大断面のトンネル構造。 The arch member is large section of the tunnel structure according to claim 1 or 2 Symbol mounting, characterized in that it comprises an embedded member. 前記L形部材間に中央底版部を設けることを特徴とする請求項1〜3のうちいずれか1項に記載の大断面のトンネル構造。 The tunnel structure with a large cross section according to any one of claims 1 to 3, wherein a central bottom plate portion is provided between the L-shaped members. 前記L形部材の背面に背面底版部を設けることを特徴とする請求項1〜3のうちいずれか1項に記載の大断面のトンネル構造。 The large-section tunnel structure according to any one of claims 1 to 3, wherein a back bottom plate portion is provided on a back surface of the L-shaped member. トンネル底側部からトンネル高さ方向に延びる左右一対のプレキャストコンクリート製のL形部材を設置し、前記一対のL形部材同士を間隔保持部材で連結し、アーチ部材を横架し、前記L形部材と前記アーチ部材とを接続した後、前記間隔保持部材を撤去することを特徴とする大断面のトンネルの構築方法。
A pair of left and right precast concrete L-shaped members extending in the tunnel height direction from the tunnel bottom side are installed, the pair of L-shaped members are connected to each other by a spacing member, an arch member is horizontally mounted, and the L-shaped After connecting a member and the said arch member, the said space holding member is removed, The construction method of the tunnel of a large cross section characterized by the above-mentioned.
JP2005281872A 2005-09-28 2005-09-28 Large-section tunnel structure and its construction method Active JP4449875B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005281872A JP4449875B2 (en) 2005-09-28 2005-09-28 Large-section tunnel structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005281872A JP4449875B2 (en) 2005-09-28 2005-09-28 Large-section tunnel structure and its construction method

Publications (2)

Publication Number Publication Date
JP2007092355A JP2007092355A (en) 2007-04-12
JP4449875B2 true JP4449875B2 (en) 2010-04-14

Family

ID=37978381

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005281872A Active JP4449875B2 (en) 2005-09-28 2005-09-28 Large-section tunnel structure and its construction method

Country Status (1)

Country Link
JP (1) JP4449875B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5055249B2 (en) * 2008-11-21 2012-10-24 西日本高速道路株式会社 Multiple tunnel construction method and multiple tunnel structure
CN102937025A (en) * 2012-11-25 2013-02-20 中铁隧道集团有限公司 Large-diameter shield tunnel structure provided with tension chord member
JP6243147B2 (en) * 2013-06-18 2017-12-06 日本スプライススリーブ株式会社 Method for connecting curved precast members and connecting structure thereof
JP7205893B2 (en) 2019-04-18 2023-01-17 日本サミコン株式会社 Mounting device for construction of arch-shaped member and construction method using the same
CN113586086B (en) * 2021-07-12 2024-02-20 山西工程技术学院 Method for reinforcing weak broken bottom plate of semi-closed large-section roadway

Also Published As

Publication number Publication date
JP2007092355A (en) 2007-04-12

Similar Documents

Publication Publication Date Title
JP4449876B2 (en) Large-section tunnel structure and its construction method
JP5594987B2 (en) Method for manufacturing concrete mount, concrete mount, and connecting material
JP4739175B2 (en) Pier structure and pier construction method
JP4738886B2 (en) Equipment foundation
JP4449875B2 (en) Large-section tunnel structure and its construction method
JP4524800B2 (en) Arch material for tunnel
JP2008150947A (en) Wall structure in which permanent anchor is executed, and construction method of wall structure in which permanent anchor is executed
JP6543077B2 (en) Construction method of structure
JP2008285952A (en) Base-isolated building structure
KR101726068B1 (en) Precast panel structure and construction method thereof
JP2010265689A (en) Floor formation method
JP4842093B2 (en) Flat plate construction method
JP2006299660A (en) Temporary receiving construction method and temporary receiving structure
JP6918613B2 (en) Wall structure and wall construction method
JP5028323B2 (en) Ground anchor method
KR101258330B1 (en) Temporary supporting system of steel beam and construstion method thereof
JP2007002606A (en) Supporting device for anchor bolt
KR20140126883A (en) A construction method of a slab and an outer wall of an underground structure
JP4460357B2 (en) Construction method of underground concrete structure
JP2009299419A (en) Construction method for preventing displacement of form, and installment tool
KR101215764B1 (en) A burial slab structure of an outer wall of an underground construction
JP2005299265A (en) Installation method of underwater structure, and underwater structure
JP5322214B2 (en) Foundation reinforcement method for existing wooden houses
JP2019124061A (en) Prefabricated structure and construction method of concrete structure
KR20190123408A (en) Mounting Apparatus For Supporting Frames

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070501

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090527

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090914

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20091110

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100105

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100118

R150 Certificate of patent or registration of utility model

Ref document number: 4449875

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130205

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130205

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140205

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250