JP4407543B2 - Steelmaking process operation schedule creation system, steelmaking process operation schedule creation method, and computer program - Google Patents

Steelmaking process operation schedule creation system, steelmaking process operation schedule creation method, and computer program Download PDF

Info

Publication number
JP4407543B2
JP4407543B2 JP2005068141A JP2005068141A JP4407543B2 JP 4407543 B2 JP4407543 B2 JP 4407543B2 JP 2005068141 A JP2005068141 A JP 2005068141A JP 2005068141 A JP2005068141 A JP 2005068141A JP 4407543 B2 JP4407543 B2 JP 4407543B2
Authority
JP
Japan
Prior art keywords
molten steel
continuous casting
transport unit
secondary refining
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2005068141A
Other languages
Japanese (ja)
Other versions
JP2006247703A (en
Inventor
健 岩村
昌 三浦
元良 小原
慎吾 武内
亨治 植松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Metal Industries Ltd
Original Assignee
Sumitomo Metal Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Industries Ltd filed Critical Sumitomo Metal Industries Ltd
Priority to JP2005068141A priority Critical patent/JP4407543B2/en
Publication of JP2006247703A publication Critical patent/JP2006247703A/en
Application granted granted Critical
Publication of JP4407543B2 publication Critical patent/JP4407543B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Continuous Casting (AREA)
  • Treatment Of Steel In Its Molten State (AREA)
  • Carbon Steel Or Casting Steel Manufacturing (AREA)

Description

本発明は、転炉、二次精錬設備、連続鋳造機が複数存在する製鋼プロセスで、連続鋳造機での連連鋳造の遅れ、いわゆる連連鋳造切れが生じることを回避することができ、溶鋼の滞留時間を短縮することができる製鋼プロセスの操業スケジュール作成システム、製鋼プロセスの操業スケジュール作成方法、及びコンピュータプログラムに関する。   The present invention is a steelmaking process in which there are a plurality of converters, secondary refining equipment, and continuous casting machines, and it is possible to avoid the delay of continuous casting in continuous casting machines, so-called continuous casting breakage, and the stay of molten steel The present invention relates to an operation schedule creation system for a steelmaking process capable of reducing time, an operation schedule creation method for a steelmaking process, and a computer program.

鉄鋼業における製鋼プロセスにおいて、転炉から後、連続鋳造機で鋳造するまでは、溶鋼は注文を取り合わせたチャージという単位で専用の取鍋(以下、取鍋という)に収容して搬送される。したがって、物流という観点から見ると、工場内では取鍋を搬送手段として移動していることになる。   In the steelmaking process in the steel industry, molten steel is housed in a dedicated ladle (hereinafter referred to as a ladle) and transported in units of charge, which is a combination of orders, from the converter to casting with a continuous casting machine. Therefore, from the viewpoint of physical distribution, the ladle is moved as a transport means in the factory.

転炉、二次精錬設備、連続鋳造機が複数存在する製鋼プロセスでは、連続鋳造機での連連鋳造の遅れ(以下、連連鋳造切れという)を生じることなく、上工程より取鍋に入った溶鋼を供給するよう制御することで、鋳造プロセスが非常に効率的になる。そのために、特に多段階の二次精錬を必要とする場合、複数の取鍋を同時に複数の設備にて処理する必要がある。複数の取鍋を同時に複数の設備にて処理する場合、例えば搬送設備である複数のクレーンが干渉し、どちらか一方の作業を優先しなければならない等、非能率的な作業を強いられることも多い。   In a steelmaking process with multiple converters, secondary refining facilities, and continuous casters, molten steel enters the ladle from the upper process without causing delays in continuous casting with the continuous casters (hereinafter referred to as continuous cast out). By controlling to supply, the casting process becomes very efficient. Therefore, especially when multi-stage secondary refining is required, it is necessary to treat a plurality of ladles with a plurality of facilities at the same time. When processing multiple ladles at multiple facilities at the same time, for example, multiple cranes that are transport facilities may interfere, and it may be forced to perform inefficient work such as priority must be given to either work. Many.

一方、製鋼プロセスにおいて、温度低下による品質低下を最小限に食い止めるためには、次工程における処理の終了待ち、クレーン干渉による搬送待ち等の、工程間での物流停滞を最小限に押さえる必要がある。   On the other hand, in the steelmaking process, it is necessary to minimize the stagnation of logistics between processes, such as waiting for the end of processing in the next process and waiting for conveyance due to crane interference, in order to minimize quality deterioration due to temperature drop. .

斯かる課題を解決すべく、例えば特許文献1では、生産予測により指定された鋳造順序に従って連続鋳造を行うことを前提として溶鋼の出鋼順位を決定し、チャージ単位で各設備での処理時刻を変数とする線形計画を算出し、最適な操業スケジュールを策定する方法が開示されている。   In order to solve such a problem, for example, in Patent Document 1, the steelmaking rank of molten steel is determined on the premise that continuous casting is performed in accordance with the casting order specified by the production prediction, and the processing time in each facility is determined in charge units. A method for calculating an optimal operation schedule by calculating a linear program as a variable is disclosed.

また、特許文献2では、連続鋳造機の鋳造スケジュールに基づき、遡りシミュレーション及び下りシミュレーションによる検証により物流停滞を回避し、いわゆる連連鋳造切れを回避する操業スケジュールの生成方法が開示されている。   Further, Patent Document 2 discloses a method for generating an operation schedule that avoids a stagnation of physical distribution by verification based on a backward simulation and a downward simulation based on a casting schedule of a continuous casting machine, and avoids so-called continuous casting failure.

さらに、特許文献3では、実際の操業チャージとの整合性を考慮し、生産ラインへの注文の投入時刻が事前に決定している場合であっても、注文ごとの優先度をシミュレーション計算し、優先度に応じて待ち時間を調整することにより、納期を考慮した現実的な生産計画を立案することができる生産計画作成装置が開示されている。
特開昭62−164811号公報 特許第3166822号公報 特開2000−254838号公報
Furthermore, in Patent Document 3, considering the consistency with the actual operation charge, even if the order entry time to the production line is determined in advance, the priority for each order is calculated by simulation, There has been disclosed a production plan creation device capable of formulating a realistic production plan in consideration of a delivery date by adjusting a waiting time according to priority.
JP-A-62-164811 Japanese Patent No. 3166822 JP 2000-254838 A

しかし、特許文献1に開示されている操業スケジュールを策定する方法では、製鋼プロセスへのチャージ単位の出鋼順序の決定に二次精錬設備での干渉を考慮しておらず、線形計画法を用いた操業スケジュール算出において制約条件として考慮するのみである。したがって、最終的に算出された操業スケジュールで特定されている出鋼順序が、そのまま実現可能である保証が無く、算出された操業スケジュールを実行することができないおそれが残されているという問題点があった。また、連連鋳造切れの有無は、線形計画法を用いた操業スケジュール算出において用いる評価関数でのみ考慮されており、算出された操業スケジュールを実行することができないおそれがある以上、連連鋳造切れを完全に回避することができるという保証も無い。   However, in the method of formulating the operation schedule disclosed in Patent Document 1, interference in the secondary refining equipment is not taken into account in determining the order of steel production in charge units in the steelmaking process, and linear programming is used. It is only considered as a constraint condition in calculating the operation schedule. Therefore, there is no guarantee that the steel production order specified in the finally calculated operation schedule can be realized as it is, and there is a possibility that the calculated operation schedule cannot be executed. there were. In addition, the presence or absence of continuous casting is considered only by the evaluation function used in the operation schedule calculation using the linear programming method, and as long as there is a possibility that the calculated operation schedule cannot be executed, the continuous casting is completely eliminated. There is no guarantee that it can be avoided.

また、特許文献2に開示されている操業スケジュールの生成方法では、次工程の処理の終了待ち、クレーン干渉による搬送待ち等の、工程間での物流停滞を最小化することができず、温度低下による品質低下を回避することが困難であるという問題点があった。   In addition, in the operation schedule generation method disclosed in Patent Document 2, the stagnation of physical distribution between processes such as waiting for the end of processing of the next process or waiting for conveyance due to crane interference cannot be minimized, and the temperature decreases. There is a problem that it is difficult to avoid the quality degradation due to.

さらに、特許文献3に開示されている生産計画作成装置では、実操業のチャージとの整合性を考慮して生産計画を策定しているものの、遡りシミュレーションによる各工程での処理の開始時刻と、チャージ単位の溶鋼の投入予定時刻との間に差異が生じた場合、生じた差異は、次工程に均等に配分することにより吸収している。したがって、他のチャージへ及ぼす影響を無視することができず、次工程の処理終了待ち、クレーン干渉による搬送待ち等の、工程間での物流停滞を最小化することが困難であるという問題点があった。   Furthermore, in the production plan creation device disclosed in Patent Document 3, although the production plan is formulated in consideration of the consistency with the charge of the actual operation, the processing start time in each process by the retroactive simulation, If there is a difference between the scheduled charging time of molten steel in the charge unit, the generated difference is absorbed by evenly distributing it to the next process. Therefore, the effect on other charges cannot be ignored, and it is difficult to minimize the stagnation of logistics between processes, such as waiting for the end of processing of the next process, waiting for conveyance due to crane interference, etc. there were.

本発明は斯かる事情に鑑みてなされたものであり、実操業の整合性を考慮しつつ、いわゆる連連鋳造切れを回避することができ、工程間での物流停滞を最小化することができる製鋼プロセスの操業スケジュール作成システム及び方法、コンピュータプログラムを提供することを目的とする。   The present invention has been made in view of such circumstances, and steelmaking capable of avoiding so-called continuous casting while considering the consistency of actual operation and minimizing the stagnation of logistics between processes. It is an object of the present invention to provide a process operation schedule creation system and method, and a computer program.

上記目的を達成するために第1発明に係る製鋼プロセスの操業スケジュール作成システムは、溶鋼を複数の転炉で精錬し、複数の二次精錬設備で二次精錬した後、複数の連続鋳造機で連連鋳造するよう、複数の搬送設備により溶鋼を搬送する製鋼プロセスの操業スケジュール作成システムにおいて、連続鋳造機の溶鋼搬送単位ごとの鋳造スケジュールを記憶しておき、記憶してある鋳造スケジュールに基づいて、時間軸を遡り、溶鋼搬送単位ごとに各設備での処理開始時刻及び終了時刻を特定する操業スケジュールを仮算出する手段と、該手段で仮算出した操業スケジュールから複数の転炉、二次精錬設備で処理する順序情報を溶鋼搬送単位ごとに抽出する手段と、溶鋼搬送単位ごとに、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報を受付ける手段と、連続鋳造機における溶鋼搬送単位ごとの連連鋳造の順位に関する情報を受付ける手段と、溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、線形計画法を用いて溶鋼搬送単位ごとの操業スケジュールを算出する手段とを備えることを特徴とする。 Operation scheduling system steelmaking process according to the first invention to achieve the above object, the molten steel refined in a converter furnace multiple, after secondary refining in multiple secondary refining facility, continuous multiple In the operation schedule creation system of the steelmaking process that transports molten steel with multiple transport equipment so as to continuously cast with a casting machine, the casting schedule for each molten steel transport unit of the continuous casting machine is stored, and the stored casting schedule is stored Based on the time axis, provisionally calculating an operation schedule for specifying the processing start time and end time at each facility for each molten steel transport unit, and a plurality of converters, two from the operation schedule temporarily calculated by the means A means for extracting the order information to be processed in the secondary refining equipment for each molten steel transport unit, and a plurality of converters, secondary refining equipment, and continuous casting machines for each molten steel transport unit, respectively. It means for receiving the lower information on top of the elapsed time between, and means for receiving information about Renren casting ranking of each molten steel conveying unit in a continuous casting machine, a plurality of the converter for each molten steel transport units, and secondary refining facility Linear, based on the order information processed in the process, multiple converters, secondary refining equipment, and continuous casters, information on the upper and lower limits of the elapsed time between them, and information on the rank of continuous casting for each steel transport unit And a means for calculating an operation schedule for each molten steel transport unit using a planning method.

また、第2発明に係る製鋼プロセスの操業スケジュール作成システムは、第1発明において、溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、複数の転炉、及び二次精錬設備での溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を算出する手段と、算出した溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を評価関数として操業スケジュールを算出する手段とを備えることを特徴とする。 Moreover, the operation schedule creation system of the steelmaking process which concerns on 2nd invention in the 1st invention WHEREIN: The several converters for every molten steel conveyance unit, the order information processed with secondary refining equipment, several converters, secondary refining Based on information on the upper and lower limits of the elapsed time between the equipment and continuous casting machine, and information on the rank of continuous casting for each molten steel transport unit, molten steel transport units in multiple converters and secondary refining equipment And a means for calculating a dwell time for each continuous casting machine and a stop time for the continuous casting machine, and a means for calculating an operation schedule using the calculated dwell time for each molten steel transport unit and the stop time for the continuous casting machine as an evaluation function. To do.

また、第3発明に係る製鋼プロセスの操業スケジュール作成方法は、溶鋼を複数の転炉で精錬し、複数の二次精錬設備で二次精錬した後、複数の連続鋳造機で連連鋳造するよう、複数の搬送設備により溶鋼を搬送する製鋼プロセスの操業スケジュール作成方法において、連続鋳造機の溶鋼搬送単位ごとの鋳造スケジュールを記憶し、記憶してある鋳造スケジュールに基づいて、時間軸を遡り、溶鋼搬送単位ごとに各設備での処理開始時刻及び終了時刻を特定する操業スケジュールを仮算出し、仮算出した操業スケジュールから複数の転炉、及び二次精錬設備で処理する順序情報を溶鋼搬送単位ごとに抽出し、溶鋼搬送単位ごとに、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報を受け付け、連続鋳造機における溶鋼搬送単位ごとの連連鋳造の順位に関する情報を受け付け、溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、線形計画法を用いて溶鋼搬送単位ごとの操業スケジュールを算出することを特徴とする。 Further, operation scheduling method of steelmaking process according to the third invention, the molten steel refined in a converter furnace multiple, after secondary refining in multiple secondary refining facility, communicating communicating cast multiple continuous casting machine In a method for creating an operation schedule for a steelmaking process in which molten steel is conveyed by a plurality of conveying facilities, the casting schedule for each molten steel conveying unit of the continuous casting machine is stored, and the time axis is traced back based on the stored casting schedule. , Tentatively calculate the operation schedule to specify the processing start time and end time in each facility for each molten steel transport unit, and transfer the steel processing order information to be processed in multiple converters and secondary refining facilities from the temporarily calculated operation schedule extracted for each unit, each molten steel transport unit receives a plurality of the converter, secondary refining equipment, and the continuous casting machine, the information about the lower limit on the elapsed time between each successive Receiving information on the order of continuous casting for each molten steel transport unit in the machine, order information processed by multiple converters and secondary refining equipment for each molten steel transport unit, multiple converters, secondary refining equipment, and continuous casting The operation schedule for each molten steel transport unit is calculated using linear programming based on the machine, the information on the upper and lower limits of the elapsed time between them, and the information on the rank of continuous casting for each molten steel transport unit To do.

また、第4発明に係る製鋼プロセスの操業スケジュール作成方法は、第3発明において、溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、複数の転炉、二次精錬設備での溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を算出し、算出した溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を評価関数として操業スケジュールを算出することを特徴とする。 Moreover, the operation schedule creation method of the steelmaking process which concerns on 4th invention is the 3rd invention. The several converters for every molten steel conveyance unit, the order information processed with secondary refining equipment, several converters, secondary refining Each unit of molten steel in multiple converters and secondary refining facilities based on information on the upper and lower limits of the elapsed time between the equipment and continuous casting machine, and information on the rank of continuous casting for each molten steel transport unit And a stop time of the continuous casting machine are calculated, and an operation schedule is calculated using the calculated residence time and stop time of the continuous casting machine for each molten steel transport unit as evaluation functions.

また、第5発明に係るコンピュータプログラムは、溶鋼を複数の転炉で精錬し、複数の二次精錬設備で二次精錬した後、複数の連続鋳造機で連連鋳造するよう、複数の搬送設備により溶鋼を搬送する製鋼プロセスの操業スケジュールを作成するコンピュータで実行可能なコンピュータプログラムにおいて、記憶手段に溶鋼搬送単位ごとの連続鋳造機の鋳造スケジュールを記憶しておき、前記コンピュータを、記憶してある鋳造スケジュールに基づいて、時間軸を遡り、溶鋼搬送単位ごとに各設備での処理開始時刻及び終了時刻を特定する操業スケジュールを仮算出する手段、該手段で仮算出した操業スケジュールから複数の転炉、及び二次精錬設備で処理する順序情報を溶鋼搬送単位ごとに抽出する手段、溶鋼搬送単位ごとに、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報を受付ける手段、連続鋳造機における溶鋼搬送単位ごとの連連鋳造の順位に関する情報を受付ける手段、及び溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、線形計画法を用いて溶鋼搬送単位ごとの操業スケジュールを算出する手段として機能させることを特徴とする。 The computer program according to the fifth aspect of the present invention is to refine the molten steel in the converter of multiple, after secondary refining in multiple secondary refining facility, so as to communicate communicating cast multiple continuous casting machine, a plurality of In a computer program executable by a computer for creating an operation schedule of a steelmaking process for conveying molten steel by a conveying facility, a casting schedule of a continuous casting machine for each molten steel conveying unit is stored in a storage means, and the computer is stored. Based on the casting schedule, the means goes back the time axis, provisionally calculates an operation schedule that specifies the processing start time and end time in each facility for each molten steel transport unit, and a plurality of operation schedules temporarily calculated by the means Means for extracting the order information to be processed in the converter and the secondary refining equipment for each molten steel transport unit, a plurality of converters for each molten steel transport unit, Next refining facilities, and continuous casting machine, means for receiving the lower information on top of the elapsed time between each means for receiving information about Renren casting ranking of each molten steel conveying unit in a continuous casting machine, and a plurality of each molten steel conveying unit Information on the order of processing in the converter and secondary refining equipment, information on multiple converters, secondary refining equipment, and continuous casting machines, the upper and lower limits of the elapsed time between them, and continuous casting for each molten steel transport unit It is made to function as a means which calculates the operation schedule for every molten steel conveyance unit using a linear programming based on the information regarding the order | rank of this.

また、第6発明に係るコンピュータプログラムは、第5発明において、前記コンピュータを、溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、複数の転炉、二次精錬設備での溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を算出する手段、及び算出した溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を評価関数として操業スケジュールを算出する手段として機能させることを特徴とする。 Further, the computer program according to a sixth invention is the computer program according to the fifth invention, wherein the computer is processed by a plurality of converters and secondary refining equipment for each molten steel transport unit, order information, a plurality of converters, and a secondary refining equipment. , And continuous casting machines, information on the upper and lower limits of the elapsed time between them, and information on the rank of continuous casting for each molten steel transport unit, for each of the molten steel transport units in a plurality of converters and secondary refining equipment It is characterized by functioning as a means for calculating a residence time and a continuous casting machine stop time, and a means for calculating an operation schedule using the calculated residence time and continuous casting machine stop time for each molten steel transport unit as an evaluation function.

第1発明、第3発明、及び第5発明では、溶鋼搬送単位ごとの連続鋳造機の鋳造スケジュールに基づいて、鋳造工程から時間軸を遡り、溶鋼搬送単位ごとの操業スケジュールを仮算出する、いわゆるバックワードシミュレーションを行う。バックワードシミュレーションにより算出された操業スケジュールから溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する処理順序情報を抽出する。複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び連続鋳造機における連連鋳造の処理順位に関する情報を受付け、線形計画法を用いて操業スケジュールを算出する。これにより、いわゆる連連鋳造切れを回避しつつ、線形計画法により実操業との整合性を保持しつつ工程の滞留時間を最小化することができ、製鋼プロセスにおける温度低下による品質低下を最小限に食い止めることができる。また、工程間での物流停滞を最小限に押さえることができ、製造コストを最小限に抑制することが可能となる。 In 1st invention, 3rd invention, and 5th invention, based on the casting schedule of the continuous casting machine for every molten steel conveyance unit, a time axis is traced back from a casting process, and the operation schedule for every molten steel conveyance unit is tentatively calculated. Perform backward simulation. Processing order information to be processed in a plurality of converters and secondary refining equipment for each molten steel transport unit is extracted from the operation schedule calculated by the backward simulation. Accepting information on multiple converters, secondary refining equipment, and continuous casters, information on the upper and lower limits of the elapsed time between them, and processing order of continuous casting in continuous casters, operation schedule using linear programming Is calculated. This avoids so-called continuous casting breakage, minimizes the residence time of the process while maintaining consistency with the actual operation by linear programming, and minimizes quality degradation due to temperature drop in the steelmaking process. I can stop. In addition, the stagnation of logistics between processes can be minimized, and the manufacturing cost can be minimized.

また、第2発明、第4発明、及び第6発明では、複数の転炉、及び二次精錬設備の処理順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限各設備間の経過時間の上下限に関する情報、及び連連鋳造の処理順位に関する情報に基づいて算出した、工程の滞留時間及び連続鋳造機の停止時間を評価関数として、線形計画法を用いて操業スケジュールを算出する。これにより、いわゆる連連鋳造切れを回避しつつ、線形計画法により実操業との整合性を保持しつつ工程の滞留時間を最小化することができ、製鋼プロセスにおける温度低下による品質低下を最小限に食い止めることができる。また、工程間での物流停滞を最小限に押さえることができ、製造コストを最小限に抑制することが可能となる。 Further, in the second invention, the fourth invention, and the sixth invention, the processing order information of the plurality of converters and the secondary refining equipment, the plurality of converters, the secondary refining equipment, and the continuous casting machine, the lower limit information on top of the elapsed time between on the elapsed time limit each facility, and were calculated on the basis of the information on the processing order of the communicating communication casting, as an evaluation function downtime residence time and continuous caster process, linear programming Is used to calculate the operation schedule. This avoids so-called continuous casting breakage, minimizes the residence time of the process while maintaining consistency with the actual operation by linear programming, and minimizes quality degradation due to temperature drop in the steelmaking process. I can stop. In addition, the stagnation of logistics between processes can be minimized, and the manufacturing cost can be minimized.

本発明によれば、いわゆる連連鋳造切れを回避しつつ、線形計画法により実操業との整合性を保持しつつ工程の滞留時間を最小化することができ、製鋼プロセスにおける温度低下による品質低下を最小限に食い止めることができる。また、工程間での物流停滞を最小限に押さえることができ、製造コストを最小限に抑制することが可能となる。   According to the present invention, it is possible to minimize the residence time of the process while maintaining consistency with the actual operation by the linear programming method while avoiding so-called continuous casting breakage, and reducing the quality due to the temperature decrease in the steelmaking process. Can be kept to a minimum. In addition, the stagnation of logistics between processes can be minimized, and the manufacturing cost can be minimized.

以下、本発明の実施の形態について、図面を参照して説明する。図1は、本発明の実施の形態に係る製鋼プロセスの操業スケジュール作成システムを具現化するコンピュータのブロック図である。図1に示すように、製鋼プロセスの操業スケジュール作成システムを具現化するコンピュータ1は、少なくとも、CPU(中央演算装置)11、記憶手段12、RAM(メモリ)13、外部の通信手段と接続する通信手段14、マウス、キーボード等の入力手段15、モニタ、プリンタ等の出力手段16、及び補助記憶手段17で構成される。   Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a block diagram of a computer that embodies an operation schedule creation system for a steelmaking process according to an embodiment of the present invention. As shown in FIG. 1, a computer 1 that embodies an operation schedule creation system for a steelmaking process includes at least a CPU (central processing unit) 11, a storage unit 12, a RAM (memory) 13, and a communication connected to an external communication unit. It comprises means 14, input means 15 such as a mouse and keyboard, output means 16 such as a monitor and printer, and auxiliary storage means 17.

CPU11は、内部バス19を介して上述したようなハードウェア各部と接続されており、上述したハードウェア各部を制御するとともに、記憶手段12に格納されたプログラムに従って、種々のソフトウェア的機能を実行する。RAM(メモリ)13は、SRAM、フラッシュメモリ等からなり、プログラム処理において一時的に発生したデータを一時記憶する。   The CPU 11 is connected to each hardware unit as described above via the internal bus 19, and controls each hardware unit described above and executes various software functions in accordance with programs stored in the storage unit 12. . A RAM (memory) 13 includes an SRAM, a flash memory, and the like, and temporarily stores data temporarily generated in the program processing.

出力手段16は、液晶表示装置、CRTディスプレイ等の表示装置、又はプリンタ等の印刷装置であり、演算結果を表示し、又は印刷して出力する。   The output means 16 is a display device such as a liquid crystal display device, a CRT display, or a printing device such as a printer, and displays or prints out the calculation result.

補助記憶手段17は、製鋼プロセスの操業スケジュールを作成するコンピュータ1で使用するプログラムを記録した可搬型記録媒体18であり、DVD、CD−ROM等が該当する。また、使用するデータを記録する可搬型記録媒体18等も含む。   The auxiliary storage means 17 is a portable recording medium 18 in which a program used by the computer 1 for creating an operation schedule for the steelmaking process is recorded, and corresponds to a DVD, a CD-ROM, or the like. Moreover, the portable recording medium 18 etc. which record the data to be used are also included.

コンピュータ1の記憶手段12は、鋳造計画データを格納した鋳造計画データベース121、材質コードごとの進捗状況を示すデータを格納した材質データベース122、チャージごとの各設備における操業実績を格納した操業実績データベース123、及び生成した操業スケジュールを格納する操業スケジュールデータベース124を備えている。図2は、鋳造計画データベース121のデータ構成の例示図である。   The storage means 12 of the computer 1 includes a casting plan database 121 that stores casting plan data, a material database 122 that stores data indicating the progress of each material code, and an operation results database 123 that stores operation results in each facility for each charge. And an operation schedule database 124 for storing the generated operation schedule. FIG. 2 is an exemplary diagram of a data structure of the casting plan database 121.

鋳造計画データベース121は、連続鋳造機ごとにチャージ単位での鋳込順序、連続鋳造機で連連鋳造を行う連連回数、連連鋳造を行う順序である連連順位、段取り時間、及び鋳込量を記憶している。また、各チャージで用いる溶鋼の材質を、材質コードで記憶してある。   The casting plan database 121 stores the casting order in charge units for each continuous casting machine, the number of continuous castings in which continuous casting is performed by the continuous casting machine, the continuous rank in which the continuous casting is performed, the setup time, and the casting amount. ing. The material of the molten steel used for each charge is stored as a material code.

図3は、材質データベース122のデータ構成の例示図である。材質データベース122は、材質を識別する材質コードごとに、プロセスコードに対応付けて、各設備(工程)での処理時間、設備間(工程間)の搬送時間を記憶している。ここで、プロセスコードは材質コードにより特定されるコードであり、対象プロセス中での通過工程を識別する情報である。   FIG. 3 is an exemplary diagram of a data structure of the material database 122. The material database 122 stores the processing time in each facility (process) and the transport time between facilities (between processes) in association with the process code for each material code for identifying the material. Here, the process code is a code specified by the material code, and is information for identifying a passing process in the target process.

図4は、操業実績データベース123のデータ構成の例示図である。操業実績データベース123は、チャージごとに各設備(工程)での開始時刻及び終了時刻を実績データとして記憶してある。   FIG. 4 is an exemplary diagram of a data configuration of the operation performance database 123. The operation result database 123 stores the start time and end time of each facility (process) as result data for each charge.

CPU11は、鋳造計画データベース121から、操業スケジュールを作成する対象期間のデータを読出し、材質コードに対応するデータを材質データベース122から読出し、既に所定の設備での処理が開始されている場合には、操業実績データベース123から、開始されている処理の開始時刻及び終了(予定)時刻を読出し、RAM13に展開する。CPU11は、RAM13に展開された情報に基づいて、バックワードシミュレーション及び線形計画法によるスケジューリングを実行し、操業スケジュールデータベース124に、実行結果を格納する。図5は、操業スケジュールデータベース124のデータ構成の例示図であり、チャージごとの各設備(工程)での開始時刻及び終了時刻とともに、スケジューリングされたチャージごとの各設備(工程)での開始予定時刻及び終了予定時刻を記憶してある。   CPU11 reads the data of the target period which produces an operation schedule from the casting plan database 121, reads the data corresponding to a material code from the material database 122, and when processing with a predetermined facility has already started, The start time and end (scheduled) time of the started process are read from the operation result database 123 and developed in the RAM 13. The CPU 11 executes scheduling based on backward simulation and linear programming based on the information developed in the RAM 13, and stores the execution result in the operation schedule database 124. FIG. 5 is a view showing an example of the data structure of the operation schedule database 124. The scheduled start time at each facility (process) for each scheduled charge is shown together with the start time and end time at each facility (process) for each charge. And the scheduled end time are stored.

図6は、本発明の実施の形態に係る製鋼プロセスの操業スケジュール作成システムのコンピュータ1のCPU11での操業スケジュール作成処理の手順を示すフローチャートである。コンピュータ1のCPU11は、鋳造計画データベース121から計画対象期間、例えば1シフトや1日に該当する鋳込計画データを読出し、RAM13へ展開する(ステップS601)。CPU11は、材質データベース122及び操業実績データベース123を、それぞれ材質コード及びチャージNoをキー情報として参照して材質データ及び実績データを読出し、RAM13へ展開する(ステップS602)。   FIG. 6 is a flowchart showing a procedure of an operation schedule creation process in the CPU 11 of the computer 1 of the operation schedule creation system of the steelmaking process according to the embodiment of the present invention. The CPU 11 of the computer 1 reads casting plan data corresponding to a planning target period, for example, one shift or one day, from the casting plan database 121 and develops it in the RAM 13 (step S601). The CPU 11 reads out the material data and the actual data from the material database 122 and the operation result database 123 by referring to the material code and the charge No as the key information, respectively, and develops them in the RAM 13 (step S602).

CPU11は、鋳込順序、段取り時間、設備の修理スケジュール等の入力を受け付け(ステップS603)、バックワードシミュレーションによるスケジューリングを行う(ステップS604)。図7は、バックワードシミュレーションの例示図である。   The CPU 11 accepts inputs such as casting sequence, setup time, equipment repair schedule, etc. (step S603), and performs scheduling by backward simulation (step S604). FIG. 7 is an exemplary diagram of backward simulation.

CPU11は、RAM13に展開されている鋳造計画データに基づいて、図7(a)のように、複数の連続鋳造機ごとのスケジュール(予定される鋳込開始時刻及び終了時刻)を算出する。図7(a)では、15時から順次、チャージごとの鋳込予定開始時刻及び予定終了時刻を算出している。チャージごとの鋳込予定開始時刻は、RAM13に実績データが展開されている場合には、展開されている実績データに係る鋳込開始時刻を用い、展開されていない場合には、入力手段15で受け付けた鋳込開始時刻を用いる。また、鋳造計画データベース121において連連順位が‘1’であるチャージについては、入力手段15で受け付けた段取り時間に基づいて鋳込開始予定時刻及び終了予定時刻を算出する。   The CPU 11 calculates a schedule (scheduled casting start time and end time) for each of a plurality of continuous casting machines based on the casting plan data developed in the RAM 13 as shown in FIG. In Fig.7 (a), the casting start time and schedule end time for every charge are calculated sequentially from 15:00. The scheduled casting start time for each charge is determined by using the casting start time related to the developed result data when the record data is developed in the RAM 13, and the input means 15 if not developed. The received casting start time is used. In addition, for a charge whose consecutive rank is “1” in the casting plan database 121, the estimated casting start time and the scheduled end time are calculated based on the setup time received by the input unit 15.

CPU11は、図7(b)に示すように、算出したスケジュールのうち、現在時刻から最も離れている鋳込開始時刻を起点として、現実の時間流れと逆方向に処理時間、搬送時間、設備干渉等を考慮したシミュレーション(バックワードシミュレーション)を行い、二次精錬設備、転炉の処理開始時刻及び終了時刻を算出する。CPU11は、算出したスケジュールに基づいて各設備の処理順序を算出して、各設備の処理開始時刻及び終了時刻とともに操業スケジュールデータベース124へ格納する。   As shown in FIG. 7B, the CPU 11 starts the casting start time that is farthest from the current time in the calculated schedule and starts processing time, transport time, and equipment interference in the direction opposite to the actual time flow. A simulation (backward simulation) is performed in consideration of the above, and the processing start time and end time of the secondary refining equipment and the converter are calculated. The CPU 11 calculates the processing order of each facility based on the calculated schedule and stores it in the operation schedule database 124 together with the processing start time and end time of each facility.

なお、プロセスコードごとに連続鋳造機から転炉までの通過工程及び搬送設備は特定されているものとし、待ち時間の発生が予想される搬送設備が存在する場合、経過時間をやや長めに設定することで対応する。 In addition, the passage process from the continuous casting machine to the converter and the transfer equipment are specified for each process code, and if there is a transfer equipment that is expected to generate a waiting time, set the elapsed time slightly longer. I will respond.

上述した方法で算出したスケジュールは、連続鋳造機の連連鋳造切れは回避している。しかし、例えば転炉の操業実績が存在するチャージの場合、実績データに基づく転炉の処理終了時刻と、算出したスケジュールでの転炉の処理終了時刻とが整合していないおそれが残る。また、チャージの滞留時間を最小化することができない。   The schedule calculated by the above-described method avoids continuous casting of the continuous casting machine. However, for example, in the case of a charge in which converter operation results exist, there is a possibility that the converter process end time based on the result data and the converter process end time in the calculated schedule do not match. In addition, the charge residence time cannot be minimized.

そこでCPU11は、ステップS604で算出された仮のスケジュールに基づいて、線形計画法を用いたスケジューリングを行う(ステップS605)。図8は、転炉1基、二次精錬設備1基、及び連続鋳造機1基の場合の製鋼プロセスにおける線形計画問題の制約条件を示す図である。   Therefore, the CPU 11 performs scheduling using linear programming based on the temporary schedule calculated in step S604 (step S605). FIG. 8 is a diagram showing constraints on the linear programming problem in the steel making process in the case of one converter, one secondary refining facility, and one continuous casting machine.

図8で、Xi,j は、転炉処理順序がi 番目のチャージにおける区分j における経過時間(分)を示している。区分j は、j=1の場合が、所定の基点から転炉処理の開始まで、j=2の場合が、転炉処理の終了から二次精錬処理の開始まで、j=3の場合が、二次精錬処理の終了から鋳込処理の開始まで、j=4の場合が、直前のチャージ(i−1)の鋳込処理の終了から本チャージ(i)の鋳込処理の開始まで、のそれぞれを示している。   In FIG. 8, Xi, j represents the elapsed time (minutes) in the section j in the i-th charge in the converter processing sequence. In the case of j = 1, when j = 1, from the predetermined base point to the start of the converter process, when j = 2, from the end of the converter process to the start of the secondary refining process, when j = 3, From the end of the secondary refining process to the start of the casting process, the case of j = 4 is from the end of the casting process of the immediately preceding charge (i-1) to the start of the casting process of the main charge (i). Each is shown.

CPU11は、バックワードシミュレーションを実行したことにより定まっている各設備の処理順序を操業スケジュールデータベース124から読出し、各設備の処理順序を調整する制約条件(数1)〜(数3)を抽出する。なお、(数1)は転炉の制約条件を、(数2)は二次精錬の制約条件を、(数3)は連続鋳造機の制約条件を、それぞれ示している。   The CPU 11 reads out the processing order of each facility determined by executing the backward simulation from the operation schedule database 124 and extracts the constraint conditions (Equation 1) to (Equation 3) for adjusting the processing order of each facility. In addition, (Equation 1) shows the constraints of the converter, (Equation 2) shows the constraints of secondary refining, and (Equation 3) shows the constraints of the continuous casting machine.

Figure 0004407543
Figure 0004407543

Figure 0004407543
Figure 0004407543

Figure 0004407543
Figure 0004407543

なお、(数1)〜(数3)において、span_CViは転炉処理時間(分)を、min_CViは転炉準備時間(分)を、span_RHiは二次精錬処理時間(分)を、min_RHiは二次精錬準備時間(分)を、span_CCiは鋳込時間(分)を、それぞれ示している。   In (Expression 1) to (Expression 3), span_CVi is the converter processing time (minutes), min_CVi is the converter preparation time (minutes), span_RHi is the secondary refining processing time (minutes), and min_RHi is 2 The next refining preparation time (minute) and span_CCi indicate the casting time (minute), respectively.

CPU11は、各設備間の経過時間に関する変数Xi,2、Xi,3の制約条件として、(数4)、(数5)により上限値及び下限値として、入力手段15を介して受け付ける。なお、上限値としては、品質管理、操業制約等により規定される値を、下限値としては、搬送時間を設定する。   The CPU 11 accepts the upper limit value and the lower limit value through the input means 15 as the constraint conditions of the variables Xi, 2, Xi, 3 related to the elapsed time between the facilities, using (Equation 4) and (Equation 5). The upper limit value is a value defined by quality control, operation restrictions, etc., and the lower limit value is a conveyance time.

Figure 0004407543
Figure 0004407543

Figure 0004407543
Figure 0004407543

なお、(数4)、(数5)において、MaeKill_minは変数Xi,2の下限値を、MaeKill_maxは変数Xi,2の上限値を、AtoKill_minは変数Xi,3の下限値を、AtoKill_maxは変数Xi,3の上限値を、それぞれ示している。   In (Equation 4) and (Equation 5), MaeKill_min is the lower limit value of the variable Xi, 2, MaeKill_max is the upper limit value of the variable Xi, 2, AtoKill_min is the lower limit value of the variable Xi, 3, and AtoKill_max is the variable Xi , 3 respectively.

さらに、CPU11は、連続鋳造機の連連鋳造切れを回避する制約条件を、変数Xi,4の制約条件として、(数6)に示す上限値及び下限値を、入力手段15を介して受け付ける。なお、上限値としては、品質管理、操業制約等により規定される値を、下限値としては、段取り時間を設定する。また、変数Xi,4が過度に大きくなった場合、連続鋳造機の生産量が低下することは言うまでもない。   Further, the CPU 11 accepts the upper limit value and the lower limit value shown in (Equation 6) via the input unit 15 with the constraint condition for avoiding continuous casting break of the continuous casting machine as the constraint condition for the variable Xi, 4. As the upper limit value, a value defined by quality control, operation restrictions, etc. is set, and as the lower limit value, a setup time is set. Needless to say, when the variable Xi, 4 becomes excessively large, the production amount of the continuous casting machine decreases.

Figure 0004407543
Figure 0004407543

なお、(数6)において、Trykan_minは変数Xi,4の下限値を、Trykan_maxは変数Xi,4の上限値を、それぞれ示している。そして、CPU11は、各設備の実績データが存在する場合には、実績データとの整合性を保持する制約条件(数7)〜(数9)を、入力手段15を介して受け付ける。図9は、転炉1基、二次精錬設備1基、及び連続鋳造機1基のときの製鋼プロセスにおける線形計画問題の制約条件であって、実績転炉終了迄経過時間end_CVi、実績二次精錬終了迄経過時間end_RHi、及び実績鋳込開始迄経過時間st_CCiを追加したときの制約条件を示す図である。図9に基づいて、転炉の制約条件(数7)、二次精錬の制約条件(数8)、及び連続鋳造機の制約条件(数9)を、それぞれ求めることができる。   In (Equation 6), Trykan_min indicates the lower limit value of the variable Xi, 4, and Trykan_max indicates the upper limit value of the variable Xi, 4. And when the performance data of each equipment exists, CPU11 receives the constraint conditions (Equation 7)-(Equation 9) holding consistency with performance data via the input means 15. FIG. FIG. 9 is a constraint condition of the linear programming problem in the steel making process with one converter, one secondary refining equipment, and one continuous casting machine, and the elapsed time end_CVi, the actual secondary It is a figure which shows the restriction | limiting conditions when adding elapsed time end_RHi until completion | finish of refining, and elapsed time st_CCi until the start of performance casting. Based on FIG. 9, the converter restrictive condition (Expression 7), the secondary refining restrictive condition (Expression 8), and the continuous casting machine restrictive condition (Expression 9) can be respectively obtained.

Figure 0004407543
Figure 0004407543

Figure 0004407543
Figure 0004407543

Figure 0004407543
Figure 0004407543

スケジュール作成対象となるチャージ全体の滞留時間を最小化するためには、チャージごとの滞留時間、すなわち変数Xi,2と変数Xi,3との総和を最小とすれば足りる。しかし、(数10)に示すように、評価関数として、連続鋳造機の停止時間に相当する変数Xi,4の総和を重み係数αとともに導入することにより、生産量を考慮したスケジュール作成が可能となる。   In order to minimize the residence time of the entire charge to be scheduled, it is sufficient to minimize the residence time for each charge, that is, the sum of the variables Xi, 2 and Xi, 3. However, as shown in (Equation 10), by introducing the sum of variables Xi, 4 corresponding to the stop time of the continuous casting machine together with the weighting factor α as an evaluation function, it is possible to create a schedule in consideration of the production volume. Become.

Figure 0004407543
Figure 0004407543

以上、(数1)〜(数10)からなる線形計画問題を、CPU11は、例えば一解法であるシンプレックス法を用いて解Xi,j を算出し、解Xi,j を時刻情報に変換することにより操業スケジュールを求めることができる。   As described above, the CPU 11 calculates the solution Xi, j using, for example, the simplex method, which is one solution, and converts the solution Xi, j into time information for the linear programming problem consisting of (Equation 1) to (Equation 10). The operation schedule can be obtained.

CPU11は、線形計画問題を解くことにより求めた操業スケジュールについて、出力手段16を介して表示出力し、整合性を具備しているか否かを確認することができる(ステップS606)。確認事項は、設備の稼動状況、各チャージの操業状況等であり、より具体的には転炉での処理が終了した後、連続鋳造機で鋳造を開始するまでの時間等を確認する。CPU11は、整合性に問題が生じている旨の入力を受付けた場合(ステップS606:NO)、上述した制約条件を変更する、又は鋳造計画そのものを変更して(ステップS607)、ステップS604へ戻る。   The CPU 11 can display and output the operation schedule obtained by solving the linear programming problem via the output unit 16 to confirm whether or not the operation schedule has consistency (step S606). The confirmation items are the operation status of the equipment, the operation status of each charge, and more specifically, the time until the casting is started by the continuous casting machine after the processing in the converter is completed. When the CPU 11 receives an input indicating that there is a problem in consistency (step S606: NO), the CPU 11 changes the above-described constraint condition or changes the casting plan itself (step S607), and returns to step S604. .

CPU11は、整合性に問題が生じていない旨の入力を受付けた場合(ステップS606:YES)、CPU11は、算出した操業スケジュールを、記憶手段12の操業スケジュールデータベース124へ登録して(ステップS608)、処理を終了する。   When the CPU 11 accepts an input indicating that there is no problem in consistency (step S606: YES), the CPU 11 registers the calculated operation schedule in the operation schedule database 124 of the storage unit 12 (step S608). The process is terminated.

以上のように本実施の形態によれば、溶鋼搬送単位ごとの連続鋳造機の鋳造スケジュールに基づいて、鋳造工程から時間軸を遡り、溶鋼搬送単位ごとの操業スケジュールを仮算出する、いわゆるバックワードシミュレーションを行い、バックワードシミュレーションにより算出された溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する処理順序情報と、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報と、連続鋳造機における連連鋳造の処理順位に関する情報とに基づいて、線形計画法を用いて操業スケジュールを算出する。これにより、バックワードシミュレーションにより、いわゆる連連鋳造切れを回避しつつ、線形計画法により実操業との整合性を保持しつつ工程の滞留時間を最小化することができ、製鋼プロセスにおける温度低下による品質低下を最小限に食い止めることができる。また、工程間での物流停滞を最小限に押さえることができ、製造コストを最小限に抑制することが可能となる。 As described above, according to the present embodiment, based on the casting schedule of the continuous casting machine for each molten steel conveyance unit, the time axis is traced back from the casting process, and the operation schedule for each molten steel conveyance unit is temporarily calculated, so-called backward Performing simulation, processing order information processed by multiple converters and secondary refining equipment for each molten steel transport unit calculated by backward simulation, multiple converters, secondary refining equipment, and continuous casting machine, respectively The operation schedule is calculated using linear programming based on information on the upper and lower limits of the elapsed time during the period and information on the processing order of continuous casting in the continuous casting machine. As a result, backward simulation avoids so-called continuous casting breakage, while linear programming keeps consistency with actual operation and minimizes the residence time of the process. The decline can be minimized. In addition, the stagnation of logistics between processes can be minimized, and the manufacturing cost can be minimized.

本発明の実施の形態に係る製鋼プロセスの操業スケジュール作成システムを具現化するコンピュータのブロック図である。It is a block diagram of a computer which embodies the operation schedule creation system of the steelmaking process concerning an embodiment of the invention. 鋳造計画データベースのデータ構成の例示図である。It is an illustration figure of the data structure of a casting plan database. 材質データベースのデータ構成の例示図である。It is an illustration figure of the data structure of a material database. 操業実績データベースのデータ構成の例示図である。It is an illustration figure of the data structure of the operation performance database. 操業スケジュールデータベースのデータ構成の例示図である。It is an illustration figure of the data structure of the operation schedule database. 本発明の実施の形態に係る製鋼プロセスの操業スケジュール作成システムのコンピュータのCPUでの操業スケジュール作成処理の手順を示すフローチャートである。It is a flowchart which shows the procedure of the operation schedule creation process in CPU of the computer of the operation schedule creation system of the steelmaking process which concerns on embodiment of this invention. バックワードシミュレーションの例示図である。It is an illustration figure of a backward simulation. 転炉1基、二次精錬設備1基、及び連続鋳造機1基の場合の製鋼プロセスにおける線形計画問題の制約条件を示す図である。It is a figure which shows the constraint conditions of the linear programming problem in the steelmaking process in the case of 1 converter, 1 secondary refining equipment, and 1 continuous casting machine. 転炉1基、二次精錬設備1基、及び連続鋳造機1基のときの製鋼プロセスにおける線形計画問題の制約条件であって、実績転炉終了迄経過時間、実績二次精錬終了迄経過時間、及び実績鋳込開始迄経過時間を追加したときの制約条件を示す図である。It is a constraint condition of the linear programming problem in the steelmaking process with one converter, one secondary refining equipment, and one continuous casting machine, the elapsed time until the end of the actual converter, the elapsed time until the end of the actual secondary refining It is a figure which shows a constraint condition when adding elapsed time until the start of performance casting.

符号の説明Explanation of symbols

1 コンピュータ
11 CPU
12 記憶手段
13 RAM
14 通信手段
15 入力手段
16 出力手段
17 補助記憶手段
18 可搬型記録媒体
121 鋳造計画データベース
122 材質データベース
123 操業実績データベース
124 操業スケジュールデータベース
1 Computer 11 CPU
12 storage means 13 RAM
DESCRIPTION OF SYMBOLS 14 Communication means 15 Input means 16 Output means 17 Auxiliary storage means 18 Portable recording medium 121 Casting plan database 122 Material database 123 Operation performance database 124 Operation schedule database

Claims (6)

溶鋼を複数の転炉で精錬し、複数の二次精錬設備で二次精錬した後、複数の連続鋳造機で連連鋳造するよう、複数の搬送設備により溶鋼を搬送する製鋼プロセスの操業スケジュール作成システムにおいて、
連続鋳造機の溶鋼搬送単位ごとの鋳造スケジュールを記憶しておき、
記憶してある鋳造スケジュールに基づいて、時間軸を遡り、溶鋼搬送単位ごとに各設備での処理開始時刻及び終了時刻を特定する操業スケジュールを仮算出する手段と、
該手段で仮算出した操業スケジュールから複数の転炉、二次精錬設備で処理する順序情報を溶鋼搬送単位ごとに抽出する手段と、
溶鋼搬送単位ごとに、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報を受付ける手段と、
連続鋳造機における溶鋼搬送単位ごとの連連鋳造の順位に関する情報を受付ける手段と、
溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、線形計画法を用いて溶鋼搬送単位ごとの操業スケジュールを算出する手段と
を備えることを特徴とする製鋼プロセスの操業スケジュール作成システム。
Refining the molten steel in the converter of multiple, after secondary refining in multiple secondary refining facility, so as to communicate communicating cast multiple continuous casting machine, operation of steelmaking process for conveying the molten steel by a plurality of transport equipment In the schedule creation system,
Remember the casting schedule for each molten steel transport unit of the continuous casting machine,
Based on the stored casting schedule, going back the time axis, provisionally calculating an operation schedule for specifying the processing start time and end time in each facility for each molten steel transport unit;
Means for extracting from the operation schedule temporarily calculated by the means a plurality of converters, order information to be processed in the secondary refining equipment for each molten steel transport unit;
Means for receiving information on the upper and lower limits of the elapsed time between each of a plurality of converters, secondary refining equipment, and continuous casting machines for each molten steel transport unit;
Means for receiving information on the rank of continuous casting for each molten steel conveyance unit in a continuous casting machine;
Multiple converters for each molten steel transport unit and order information processed by secondary refining equipment, multiple converters, secondary refining equipment, and continuous casting machine, information on upper and lower limits of elapsed time between each, and molten steel An operation schedule creation system for a steelmaking process, comprising: means for calculating an operation schedule for each molten steel conveyance unit using a linear programming method based on information relating to the order of continuous casting for each conveyance unit.
溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、複数の転炉、及び二次精錬設備での溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を算出する手段と、
算出した溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を評価関数として操業スケジュールを算出する手段と
を備えることを特徴とする請求項1記載の製鋼プロセスの操業スケジュール作成システム。
Multiple converters for each molten steel transport unit and order information processed by secondary refining equipment, multiple converters, secondary refining equipment, and continuous casting machine, information on upper and lower limits of elapsed time between each, and molten steel Based on the information regarding the rank of continuous casting for each transport unit, a plurality of converters, a means for calculating the residence time for each molten steel transport unit in the secondary refining equipment and the stop time of the continuous casting machine,
The operation schedule creation system for a steelmaking process according to claim 1, further comprising means for calculating an operation schedule using the calculated residence time for each molten steel transport unit and stop time of the continuous casting machine as an evaluation function.
溶鋼を複数の転炉で精錬し、複数の二次精錬設備で二次精錬した後、複数の連続鋳造機で連連鋳造するよう、複数の搬送設備により溶鋼を搬送する製鋼プロセスの操業スケジュール作成方法において、
連続鋳造機の溶鋼搬送単位ごとの鋳造スケジュールを記憶し、
記憶してある鋳造スケジュールに基づいて、時間軸を遡り、溶鋼搬送単位ごとに各設備での処理開始時刻及び終了時刻を特定する操業スケジュールを仮算出し、
仮算出した操業スケジュールから複数の転炉、及び二次精錬設備で処理する順序情報を溶鋼搬送単位ごとに抽出し、
溶鋼搬送単位ごとに、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報を受け付け、
連続鋳造機における溶鋼搬送単位ごとの連連鋳造の順位に関する情報を受け付け、
溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、線形計画法を用いて溶鋼搬送単位ごとの操業スケジュールを算出することを特徴とする製鋼プロセスの操業スケジュール作成方法。
Refining the molten steel in the converter of multiple, after secondary refining in multiple secondary refining facility, so as to communicate communicating cast multiple continuous casting machine, operation of steelmaking process for conveying the molten steel by a plurality of transport equipment In the schedule creation method,
Stores the casting schedule for each molten steel transfer unit of the continuous casting machine,
Based on the stored casting schedule, go back the time axis, provisionally calculate the operation schedule that specifies the processing start time and end time at each facility for each molten steel transport unit,
Extract the order information to be processed in the multiple converters and secondary refining equipment from the temporarily calculated operation schedule for each molten steel transport unit
Receive information on the upper and lower limits of elapsed time between multiple converters, secondary refining equipment, and continuous casting machines for each molten steel transport unit,
Receives information on the rank of continuous casting for each molten steel transport unit in a continuous casting machine,
Multiple converters for each molten steel transport unit and order information processed by secondary refining equipment, multiple converters, secondary refining equipment, and continuous casting machine, information on upper and lower limits of elapsed time between each, and molten steel An operation schedule creation method for a steelmaking process, wherein an operation schedule for each molten steel conveyance unit is calculated using linear programming based on information relating to the rank of continuous casting for each conveyance unit.
溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、複数の転炉、二次精錬設備での溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を算出し、
算出した溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を評価関数として操業スケジュールを算出することを特徴とする請求項3記載の製鋼プロセスの操業スケジュール作成方法。
Multiple converters for each molten steel transport unit and order information processed by secondary refining equipment, multiple converters, secondary refining equipment, and continuous casting machine, information on upper and lower limits of elapsed time between each, and molten steel Based on the information on the rank of continuous casting for each transport unit, calculate the residence time for each molten steel transport unit and the stop time of the continuous casting machine in multiple converters, secondary refining equipment,
The method for creating an operation schedule for a steelmaking process according to claim 3, wherein the operation schedule is calculated using the calculated residence time for each molten steel transport unit and stop time of the continuous casting machine as an evaluation function.
溶鋼を複数の転炉で精錬し、複数の二次精錬設備で二次精錬した後、複数の連続鋳造機で連連鋳造するよう、複数の搬送設備により溶鋼を搬送する製鋼プロセスの操業スケジュールを作成するコンピュータで実行可能なコンピュータプログラムにおいて、
記憶手段に溶鋼搬送単位ごとの連続鋳造機の鋳造スケジュールを記憶しておき、
前記コンピュータを、
記憶してある鋳造スケジュールに基づいて、時間軸を遡り、溶鋼搬送単位ごとに各設備での処理開始時刻及び終了時刻を特定する操業スケジュールを仮算出する手段、
該手段で仮算出した操業スケジュールから複数の転炉、及び二次精錬設備で処理する順序情報を溶鋼搬送単位ごとに抽出する手段、
溶鋼搬送単位ごとに、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報を受付ける手段、
連続鋳造機における溶鋼搬送単位ごとの連連鋳造の順位に関する情報を受付ける手段、及び
溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、線形計画法を用いて溶鋼搬送単位ごとの操業スケジュールを算出する手段
として機能させることを特徴とするコンピュータプログラム。
Refining the molten steel in the converter of multiple, after secondary refining in multiple secondary refining facility, so as to communicate communicating cast multiple continuous casting machine, operation of steelmaking process for conveying the molten steel by a plurality of transport equipment In a computer program executable on a computer for creating a schedule,
Store the casting schedule of the continuous casting machine for each molten steel transport unit in the storage means,
The computer,
Based on the stored casting schedule, means for temporarily calculating an operation schedule that goes back the time axis and specifies the processing start time and end time in each facility for each molten steel transport unit;
Means for extracting order information to be processed in a plurality of converters and secondary refining equipment from the operation schedule temporarily calculated by the means for each molten steel transport unit;
Means for receiving information on the upper and lower limits of the elapsed time between each of a plurality of converters, secondary refining equipment, and continuous casting machines for each molten steel transport unit;
Means for receiving information on the order of continuous casting for each molten steel transport unit in a continuous casting machine, multiple converters for each molten steel transport unit, and order information processed by secondary refining equipment, multiple converters, secondary refining equipment Based on the information about the upper and lower limits of the elapsed time between the continuous casting machine and the continuous casting machine, and the information about the rank of the continuous casting for each molten steel conveying unit, the operation schedule for each molten steel conveying unit is calculated using linear programming. A computer program that functions as means.
前記コンピュータを、
溶鋼搬送単位ごとの複数の転炉、及び二次精錬設備で処理する順序情報、複数の転炉、二次精錬設備、及び連続鋳造機、それぞれの間の経過時間の上下限に関する情報、及び溶鋼搬送単位ごとの連連鋳造の順位に関する情報に基づいて、複数の転炉、二次精錬設備での溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を算出する手段、及び
算出した溶鋼搬送単位ごとの滞留時間及び連続鋳造機の停止時間を評価関数として操業スケジュールを算出する手段
として機能させることを特徴とする請求項5記載のコンピュータプログラム。
The computer,
Multiple converters for each molten steel transport unit and order information processed by secondary refining equipment, multiple converters, secondary refining equipment, and continuous casting machine, information on upper and lower limits of elapsed time between each, and molten steel Based on the information regarding the rank of continuous casting for each transport unit, means for calculating the dwell time for each molten steel transport unit in the secondary refining equipment, the stop time of the continuous casting machine, and the calculated molten steel transport unit 6. The computer program according to claim 5, wherein the computer program is caused to function as means for calculating an operation schedule using the residence time for each time and the stop time of the continuous casting machine as evaluation functions.
JP2005068141A 2005-03-10 2005-03-10 Steelmaking process operation schedule creation system, steelmaking process operation schedule creation method, and computer program Active JP4407543B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005068141A JP4407543B2 (en) 2005-03-10 2005-03-10 Steelmaking process operation schedule creation system, steelmaking process operation schedule creation method, and computer program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005068141A JP4407543B2 (en) 2005-03-10 2005-03-10 Steelmaking process operation schedule creation system, steelmaking process operation schedule creation method, and computer program

Publications (2)

Publication Number Publication Date
JP2006247703A JP2006247703A (en) 2006-09-21
JP4407543B2 true JP4407543B2 (en) 2010-02-03

Family

ID=37088715

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005068141A Active JP4407543B2 (en) 2005-03-10 2005-03-10 Steelmaking process operation schedule creation system, steelmaking process operation schedule creation method, and computer program

Country Status (1)

Country Link
JP (1) JP4407543B2 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5786724B2 (en) * 2012-01-11 2015-09-30 新日鐵住金株式会社 Steelmaking process operation schedule creation method, steelmaking process operation schedule creation system, steelmaking process operation method, and steel manufacturing method
JP5880347B2 (en) * 2012-08-14 2016-03-09 新日鐵住金株式会社 Method and apparatus for creating operation schedule in steelmaking process
KR101550667B1 (en) 2013-11-25 2015-09-07 주식회사 포스코 Method for manufacturing molten steel
JP6398579B2 (en) * 2013-12-06 2018-10-03 新日鐵住金株式会社 Operation schedule creation device, operation schedule creation method, and program
CN103984324B (en) * 2014-05-26 2017-01-18 中冶南方工程技术有限公司 Method for steel-making continuous casting dynamic dispatching based on heuristic algorithm cluster
JP6375741B2 (en) * 2014-07-10 2018-08-22 新日鐵住金株式会社 Control method of molten steel temperature in steelmaking factory
JP6394208B2 (en) * 2014-09-08 2018-09-26 新日鐵住金株式会社 Operation schedule preparation method and preparation apparatus in a steelmaking factory
JP6582582B2 (en) * 2015-06-15 2019-10-02 日本製鉄株式会社 Operation schedule creation device, operation schedule creation method, and program
JP6477309B2 (en) * 2015-07-08 2019-03-06 Jfeスチール株式会社 Steelmaking production schedule creation device, steelmaking production schedule creation method, operation method, and steelmaking product manufacturing method

Also Published As

Publication number Publication date
JP2006247703A (en) 2006-09-21

Similar Documents

Publication Publication Date Title
JP4407543B2 (en) Steelmaking process operation schedule creation system, steelmaking process operation schedule creation method, and computer program
JP4734024B2 (en) Hot rolling mill heating / rolling schedule creation apparatus, creation method, computer program, and computer-readable recording medium
JP4501740B2 (en) Steelmaking process operation schedule creation system, steelmaking process operation schedule creation method, and computer program
CN103631243A (en) Rescheduling method and rescheduling system of steel making and continuous casting on basis of genetic algorithm
Fanti et al. An integrated system for production scheduling in steelmaking and casting plants
Ouelhadj A multi-agent system for the integrated dynamic scheduling of steel production
CN112699524A (en) Simulation optimization scheduling model applied to high-speed tool steel steelmaking process of special steel mill
JP2011159230A (en) Scheduling support system, scheduling support method, and scheduling support program
JP2007061870A (en) Device and method for preparing rolling schedule, computer program and computer readable storage medium
JP3166822B2 (en) Operation schedule creation system for steelmaking process
JP5318651B2 (en) Scheduling method, scheduling program, and scheduling system
JP2001034672A (en) Operation plan adjusting method and operation plan adjusting system
JP2009258881A (en) System, method, and program for editing production schedule
JP5652069B2 (en) Optimal charge knitting device and optimal charge knitting method
JP4746334B2 (en) Production planning method, apparatus, and computer program for manufacturing process
JP6248223B2 (en) Formwork supply support system
JP5488184B2 (en) Scheduling parameter correcting method and correcting apparatus, schedule generating method and generating apparatus, and steel material manufacturing method
JP6191629B2 (en) Hot metal logistics planning method and hot metal logistics planning device
JPS62164811A (en) Method for making operation plan for tapping and casting
JP3154397B2 (en) Hot metal supply and demand management scheduling method
JP4959125B2 (en) Processing plan creation device, operation control device, processing plan creation method, operation control method, computer program, and recording medium
JP2005208891A (en) Control apparatus and processing system
JPH06218659A (en) Preparation replacing instruction device and manufacturing system
JP5494194B2 (en) Production target range setting device and production target range setting method
JPH10143567A (en) Scheduling device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070322

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090714

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090721

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090909

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20091020

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20091102

R150 Certificate of patent or registration of utility model

Ref document number: 4407543

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121120

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131120

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131120

Year of fee payment: 4

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131120

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350