JP4351081B2 - Construction management system and construction management method - Google Patents
Construction management system and construction management method Download PDFInfo
- Publication number
- JP4351081B2 JP4351081B2 JP2004025326A JP2004025326A JP4351081B2 JP 4351081 B2 JP4351081 B2 JP 4351081B2 JP 2004025326 A JP2004025326 A JP 2004025326A JP 2004025326 A JP2004025326 A JP 2004025326A JP 4351081 B2 JP4351081 B2 JP 4351081B2
- Authority
- JP
- Japan
- Prior art keywords
- dimensional
- building
- construction
- data
- construction management
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000009430 construction management Methods 0.000 title claims description 40
- 238000000034 method Methods 0.000 title claims description 25
- 238000010276 construction Methods 0.000 claims description 50
- 230000003014 reinforcing effect Effects 0.000 claims description 16
- 238000005259 measurement Methods 0.000 claims description 13
- 238000009415 formwork Methods 0.000 claims description 9
- 238000004364 calculation method Methods 0.000 claims description 8
- 230000002787 reinforcement Effects 0.000 claims description 5
- 238000009418 renovation Methods 0.000 claims description 5
- 238000006243 chemical reaction Methods 0.000 claims description 4
- 238000009419 refurbishment Methods 0.000 claims description 4
- 238000004088 simulation Methods 0.000 claims description 2
- 238000007726 management method Methods 0.000 description 10
- 238000009435 building construction Methods 0.000 description 4
- 238000013461 design Methods 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 238000012937 correction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000006870 function Effects 0.000 description 2
- 230000005856 abnormality Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 238000007634 remodeling Methods 0.000 description 1
Images
Description
本発明は、建築施工中の建築物の精度管理を行う施工管理システム及び施工管理方法に関する。 The present invention relates to a construction management system and construction management method for managing the accuracy of a building under construction.
建築施工中の建築物の精度を把握するために、従来から、建築施工におけるさまざまなプロセスにおいて、予め選定した特定ポイントにおいてその都度実際の寸法を測定し、躯体図との照合を行っている。この方法によれば、測定ポイントを増やすことによって精度を向上することが図れるものの、それらの照合に手間がかかるという問題が生じる。一方で、測定ポイントを減らすことによって照合の手間を少なくすることができるが、精度・品質が低下するという問題が生じる。また、トランシットやレベル等の測量器械を用いた測量では、測量する者の測量技術によって、実際に測量された寸法に大きな誤差を生じる場合もあり、測量の精度にも限度がある。 Conventionally, in order to grasp the accuracy of a building under construction, actual dimensions are measured each time at specific points selected in advance in various processes in construction, and collated with a structural drawing. According to this method, although the accuracy can be improved by increasing the number of measurement points, there is a problem that it takes time to collate them. On the other hand, it is possible to reduce the time and effort of collation by reducing the measurement points, but there arises a problem that accuracy and quality are lowered. Further, in surveying using a surveying instrument such as transit or level, the surveying technique of the surveyor may cause a large error in the actually measured dimensions, and the accuracy of surveying is also limited.
これに対し、鉄骨建て方時にトータルステーションを用いて測定した測定ポイントの3次元座標を計算し、3次元CADデータとの照合を行う技術が知られている(例えば、特許文献1参照。)。当該特許文献1に記載の発明は、鉄骨工事を対象として、トータルステーションと受光機を利用して、ある限られた数の測量点に対して鉛直角、水平角及び距離から当該測量点の3次元座標を計算し、CADデータとの照合を行うものである。
しかしながら、上記特許文献1に記載の発明によれば、特定の測量点のみ3次元座標を算出するだけであって、測定ポイント数を増加して建物空間の全体に渡って3次元座標を測定することは、作業手間がその分だけ増えることから現実的ではない。また、上記特許文献1に記載の発明は、予め3次元CADデータが存在する鉄骨の建て方時における精度管理しか行うことができず、予め3次元CADデータが存在しないような建物のリニューアル作業(改装作業)に対しては対応することができない。 However, according to the invention described in Patent Document 1, only three-dimensional coordinates are calculated only for specific survey points, and the three-dimensional coordinates are measured over the entire building space by increasing the number of measurement points. This is not realistic because the labor is increased accordingly. In addition, the invention described in the above-mentioned Patent Document 1 can only perform accuracy control at the time of building a steel frame in which three-dimensional CAD data exists in advance, and renewal work for a building in which three-dimensional CAD data does not exist in advance ( (Remodeling work) cannot be handled.
本発明は、このような事情を考慮してなされたものであり、3次元レーザスキャナを用いて高速・高精度で計測した建物空間の3次元データに基づいて、建築施工中の建築物の精度管理を好適に実施することができる施工管理システム及び施工管理方法を提供することを目的とする。 The present invention has been made in consideration of such circumstances, and based on the three-dimensional data of the building space measured at high speed and with high accuracy using a three-dimensional laser scanner, the accuracy of the building under construction is determined. It is an object of the present invention to provide a construction management system and a construction management method capable of suitably performing management.
上記課題を解決するために、本発明は、建築施工中の建築物の精度管理を行う施工管理システムであって、
前記建築物の3次元CADデータを記憶する記憶手段と、
3次元レーザスキャナを用いて、建築施工中の前記建築物の3次元形状を示す3次元データを計測する計測手段と、
前記記憶手段に記憶された前記3次元CADデータと前記計測手段で計測された前記3次元データとを照合する照合手段と、
前記照合手段による照合結果から、前記建築物の建築施工において発生した誤差を算出する算出手段と、
前記誤差が許容範囲内か否かを判定する判定手段と、
3次元レーザスキャナを用いて、改装施工前の建築物の3次元形状を示す3次元データを計測する第2の計測手段と、
前記3次元データを前記建築物の3次元CADデータに変換する変換手段と、
を備え、
前記記憶手段が、前記変換手段で変換された前記建築物の3次元CADデータを初期値として記憶し、
前記記憶手段に記憶された前記3次元CADデータに基づいて改装施工後の建築物の3次元CADデータをシミュレートするシミュレート手段をさらに備えることを特徴とする。
In order to solve the above-mentioned problem, the present invention is a construction management system for performing accuracy management of a building under construction construction,
Storage means for storing three-dimensional CAD data of the building;
Measuring means for measuring three-dimensional data indicating the three-dimensional shape of the building under construction using a three-dimensional laser scanner;
Collation means for collating the three-dimensional CAD data stored in the storage means with the three-dimensional data measured by the measurement means;
From the collation result by the collation means, a calculation means for calculating an error generated in the construction of the building,
Determining means for determining whether the error is within an allowable range ;
A second measuring means for measuring three-dimensional data indicating a three-dimensional shape of the building before the refurbishment using a three-dimensional laser scanner;
Conversion means for converting the three-dimensional data into three-dimensional CAD data of the building;
With
The storage means stores the three-dimensional CAD data of the building converted by the conversion means as an initial value,
The apparatus further comprises simulation means for simulating the three-dimensional CAD data of the building after renovation based on the three-dimensional CAD data stored in the storage means .
また、上記施工管理システムは、前記判定手段によって判定された誤差が許容範囲を超えている場合、施工管理者に警告する警告手段をさらに備えることを特徴とする。 The construction management system further includes warning means for warning the construction manager when the error determined by the determination means exceeds an allowable range.
さらにまた、本発明は、建築施工中の建築物の精度管理を行う施工管理方法であって、
3次元レーザスキャナを用いて、配筋が施された前記建築物の3次元形状を示す3次元データを計測する第1の計測工程と、
前記3次元データから、前記配筋のピッチ及び該配筋の直径を含む該配筋の状態を算出する第1の算出工程と、
3次元レーザスキャナを用いて、前記配筋が施され、さらに型枠が取り付けられた前記建築物の3次元形状を示す3次元データを計測する第2の計測工程と、
前記3次元データから前記型枠の厚みを取り除いた3次元データと、算出された前記配筋の状態とから、該鉄筋を覆うコンクリート部材の被り厚さを算出する第2の算出工程と
を有することを特徴とする。
Furthermore, the present invention is a construction management method for performing accuracy management of a building under construction construction,
Using a three-dimensional laser scanner, a first measurement step of measuring three-dimensional data indicating a three- dimensional shape of the building to which reinforcement is applied;
A first calculation step of calculating a state of the bar arrangement including a pitch of the bar arrangement and a diameter of the bar arrangement from the three-dimensional data;
Using a three-dimensional laser scanner, a second measurement step of measuring three-dimensional data indicating a three- dimensional shape of the building to which the bar arrangement is performed and a formwork is attached;
A second calculation step of calculating the covering thickness of the concrete member covering the reinforcing bar from the three-dimensional data obtained by removing the thickness of the formwork from the three-dimensional data and the calculated state of the reinforcement. It is characterized by that.
さらにまた、上記施工管理方法は、前記第2の算出工程によって算出された前記被り厚さについて最小被り厚さに達していない部分があるか否かを判定する判定工程と、
前記判定工程によって、前記被り厚さが前記最小被り厚さに達していない部分がある場合、施工管理者に警告する警告工程をさらに有することを特徴とする。
Furthermore, the construction management method includes a determination step of determining whether or not there is a portion that has not reached the minimum cover thickness for the cover thickness calculated by the second calculation step;
If there is a portion where the covering thickness does not reach the minimum covering thickness by the determining step, the method further includes a warning step of warning a construction manager.
本発明によれば、3次元レーザスキャナを用いて高速・高精度で計測した建物空間の3次元データに基づいて、建築施工中の建築物の精度管理を好適に実施することができる。 ADVANTAGE OF THE INVENTION According to this invention, based on the three-dimensional data of the building space measured with high-speed and high precision using the three-dimensional laser scanner, the precision management of the building under construction construction can be implemented suitably.
以下、図面を参照して、本発明の一実施形態に係る建築施工前後の建物の精度管理を好適に実施することができる施工管理システム及び施工管理方法の詳細について説明する。 Hereinafter, with reference to drawings, the detail of the construction management system and construction management method which can carry out suitably the accuracy control of the building before and after building construction concerning one embodiment of the present invention is explained.
図1は、本発明の一実施形態に係る建物の精度管理を行う施工管理システムの構成を示す概要図である。 FIG. 1 is a schematic diagram illustrating a configuration of a construction management system that performs accuracy management of a building according to an embodiment of the present invention.
図1においては、建築施工現場10において、3次元レーザスキャナ12を用いて建物空間の3次元データを測定し、事務所(又は、会社等)20のコンピュータ21を用いて当該建物の設計図面に相当する3次元CADデータとの照合を行い、異常等があれば建築施工現場10等に位置する施工管理者等に報知する施工管理システムが示されている。
In FIG. 1, at a
図1では、一例として、実際に建物の建築施工現場10におけるコンピュータ11と、事務所(或いは、会社等)20におけるコンピュータ21とがLANや電話回線等のネットワーク30を介して接続されている様子が示されている。
In FIG. 1, as an example, a
建築施工現場10のコンピュータ11には、建物空間の全体に渡って3次元座標を測定することができる3次元レーザスキャナ12と、その測定された3次元座標データを記憶する記憶装置13とが接続されている。尚、測定された3次元座標データは、記憶装置13ではなくコンピュータ11に内蔵のハードディスクに格納するようにしてもよい。ここで、本実施形態で使用する3次元レーザスキャナ13の詳細について説明する。
Connected to the
3次元レーザスキャナ13は、レーザ光を測定対象物に照射し、対象物の正確な3次元位置座標(X,Y,Z)、輝度及びカラーを計測することができる。例えば、本実施形態では、Z+F社のIMAGER5003を用いて建物空間の3次元座標を計測する。この機器によれば、水平360度、垂直310度で最大625,000点/秒のスキャンレートで建物内を計測することができる。また、約50メートルの距離から数ミリメートルの誤差といった高精度で測定点の3次元座標を測定することができるので、従来用いられていたトータルスキャン等よりもより迅速に、かつ精度よく、建築物内の各種測量点の3次元座標を取得することができる。
The three-
一方、事務所(又は、会社等)20のコンピュータ21には、建築施工現場10で建築施工される建築物の3次元CADデータを記憶する記憶装置22が接続されている。尚、記憶装置22が記憶する3次元CADデータは、コンピュータ21で作成されたデータであってもよいが、その他の3次元CADを用いて作成したデータを当該記憶装置22に記憶させたものであってもよい。また、後述するように、改装時等であって、3次元CADデータが見当たらないような場合においては、建築施工現場10で施工前の状態にある建物空間に3次元レーザスキャナ12を用いて3次元データを測定し、それから再構成された3次元CADデータを記憶させたものであってもよい。尚、建築物の3次元CADデータは、記憶装置22ではなくコンピュータ21に内蔵のハードディスクに格納するようにしてもよい。また、コンピュータ21は3次元CAD装置であってもよい。
On the other hand, a
図2は、本発明の一実施形態に係る施工管理システムを用いた建築物の施工管理手続を説明するためのフローチャートである。ここで、建築施工の対象となる建築物が新設される場合、通常設計図や施工図等の図面は3次元CADデータとして予め作成される。そして、前述したように、これらのデータは記憶装置22内に格納される。
FIG. 2 is a flowchart for explaining a construction management procedure for a building using the construction management system according to the embodiment of the present invention. Here, when a building to be constructed is newly established, drawings such as normal design drawings and construction drawings are created in advance as three-dimensional CAD data. As described above, these data are stored in the
これに対し、既設の建築物のリニューアル(改装)施工のような場合において当該建築物の3次元CADデータが存在する場合は、新設の場合と同様にして施工管理を行うことが可能であるが、一般的には図面がないような場合が多い。また、存在してもその内容が現実とは大きく異なっているような場合も多い。このような場合には、施工前の状態において、3次元レーザスキャナ12を用いて建物空間をスキャニングし(ステップS11)、コンピュータ11又は他のCADシステム等を用いてスキャンされたデータを初期データとして記憶する。そして、コンピュータ11やコンピュータ21等にインストールされている、3次元データから3次元CADデータ(3次元モデル)を構築するためのソフトウェア等を用いて、記憶された初期値の3次元CADデータから改装終了後の「出来上がり」の状態の3次元CADデータをシミュレートする(ステップS12)。そして、シミュレートされた3次元CADデータを(改装)設計や施工のための図面データとして記憶装置22内に記憶する。このように改装終了後の状態をシミュレートすることで、施工計画等の予備調査を好適に行うことができる。
On the other hand, in the case of renewal (renovation) construction of an existing building, when 3D CAD data of the building exists, construction management can be performed in the same manner as in the case of new construction. In general, there are often no drawings. Moreover, even if it exists, there are many cases where the content is very different from the actual situation. In such a case, in the state before construction, the building space is scanned using the three-dimensional laser scanner 12 (step S11), and the data scanned using the
そして、これらの3次元CADデータに基づいて建築における設計や施工が行われる(ステップS20)。ある程度建築施工(或いは、改装等)が進むと、施工管理者が定めるタイミングでステップS21以降の建築施工中の建築物の精度管理を行う施工管理手続を行う。施工管理者は、通常、任意のタイミングや各プロセスの終了時に精度管理を行うための施工管理手続を行う。 Based on these three-dimensional CAD data, design and construction in the building are performed (step S20). When building construction (or refurbishment or the like) proceeds to some extent, a construction management procedure is performed for managing the accuracy of the building under construction after step S21 at a timing determined by the construction manager. The construction manager usually performs a construction management procedure for performing precision management at an arbitrary timing or at the end of each process.
前述したように、当該施工管理手続を行う前提として、記憶装置22には、施工管理の対象となる建築物の3次元CADデータが記憶されている。そして、3次元レーザスキャナ12を用いて、建築施工中の建築物の3次元データを計測する(ステップS21)。3次元レーザスキャナ12で計測された3次元データは記憶装置13に記憶され、コンピュータ21又はコンピュータ11において、記憶装置22に記憶されている3次元CADデータとの照合が行われる(ステップS22)。尚、3次元レーザスキャナ12を使用するに当たり、当該建築物の3次元CADデータの座標と、3次元レーザスキャナ12のスキャン時の座標を同一座標系にしておくか、データ取得後コンピュータ11又は12内で同一座標系に変換するようにする。
As described above, as a premise for performing the construction management procedure, the
そして、その照合結果から、建築物の建築施工において発生した誤差を算出し(ステップS23)、その誤差が許容範囲内か否かを予め設定されたしきい値と比較することによって判定する(ステップS24)。そして、判定された誤差が許容範囲を超えている場合、施工管理者に対して誤差が許容範囲外である旨を警告する(ステップS25)。本実施形態における警告要領の一例として、建築現場10のコンピュータ11に警告メッセージを送信したり、施工管理者が所持する携帯電話に音声や文字(メール)を用いた警告メッセージを通信したりすることができる。また、施工管理者以外の各種関係者等にも同様にして警告したり、或いはホームページ等に当該判定の結果等をアップロードし、各種関係者が社内イントラネットを用いてそれらの判定結果や3次元データの照合結果等を閲覧できるようにしてもよい。
And the error which generate | occur | produced in the construction construction of a building is calculated from the collation result (step S23), and it determines by comparing with the threshold value set beforehand whether the error is in an allowable range (step). S24). If the determined error exceeds the allowable range, the construction manager is warned that the error is outside the allowable range (step S25). As an example of the warning procedure in the present embodiment, a warning message is transmitted to the
また、単に警告するだけではなく、或いは当該警告に代えて、例えば、どの程度修正することによって許容範囲になるといった内容の改善要求メッセージ等を送信するようにしてもよい。もちろん、判定された誤差が許容範囲内であっても、同様にして、許容範囲内である旨を示すメッセージ等を送信するようにしてもよい。 Further, instead of merely giving a warning, instead of the warning, for example, an improvement request message or the like indicating that the correction is made to the allowable range may be transmitted. Of course, even if the determined error is within the allowable range, a message indicating that it is within the allowable range may be transmitted in the same manner.
そして、ステップS24における誤差の判定の結果、許容範囲内であれば本施工管理手続はそのまま終了し、許容範囲外であれば上述したようにステップS25で警告を行った後、当該施工管理手続を終了する。そして、以降の施工管理手続は、上記警告の結果から問題点を改善するための建築施工(ステップS20)或いは他の施工箇所の建築施工(ステップS20)が終了した段階であって、施工管理者が示したタイミングにおいてステップS21から同様にして行われる。 And as a result of the error determination in step S24, if it is within the allowable range, the construction management procedure is terminated as it is. If it is out of the allowable range, the warning is given in step S25 as described above, and then the construction management procedure is performed. finish. The subsequent construction management procedure is the stage at which the construction work (step S20) for improving the problem from the result of the warning or the construction work (step S20) at another construction point has been completed. Is performed in the same manner from step S21 at the timing indicated by.
また、遠隔から当該施工管理の様子をモニタリングするような場合には、例えば、ある一定期間「待ち状態」に設定しておき、設定期間経過後に自動的に上記手続を行うようにしてもよい。 Further, when monitoring the state of the construction management from a remote location, for example, it may be set in a “waiting state” for a certain period, and the above procedure may be automatically performed after the set period has elapsed.
上記施工管理が行われる場面の一つとして鉄筋の配筋段階がある。すなわち、鉄筋を組み立てた後(ステップS20)、3次元レーザスキャナ12を用いて配筋された鉄筋をスキャニングする(ステップS21)。これにより、配筋された鉄筋のピッチや鉄筋径といった配筋された鉄筋の位置等の現在の状態を高精度かつ高速で把握することが可能となる。
One of the scenes where the construction management is performed is the reinforcing bar placement stage. That is, after assembling the reinforcing bars (step S20), the reinforcing bars arranged using the three-
その後、前述したように、予め図面として記憶していた3次元CADデータと計測された3次元データとを照合し(ステップS22)、誤差を算出して(ステプS23)、その誤差が許容範囲内であるか否かを判定する(ステップS24)。尚、本実施形態に係る施工管理によれば、従来のような数点のみの計測ではなく、より多数の測量点を用いて誤差の判定を行うことが可能であるため、より精度のよい施工管理を行うことが可能となる。 Thereafter, as described above, the three-dimensional CAD data stored in advance as a drawing is compared with the measured three-dimensional data (step S22), an error is calculated (step S23), and the error is within an allowable range. It is determined whether or not (step S24). In addition, according to the construction management according to the present embodiment, since it is possible to perform error determination using a larger number of survey points instead of measurement of only a few points as in the past, construction with higher accuracy is possible. Management can be performed.
また、本実施形態に係る施工管理システムでは、従来の方法では達成することができなかった鉄筋のコンクリート被り厚さを好適に計測することも可能である。図3は、配筋された鉄筋上に型枠を取り付けする前後の状態を説明するための概要図である。図3において、(a)は鉄筋31が配筋された状態を示す図である。また、(b)は配筋された鉄筋31上にコンクリートを流し込むための型枠32を取り付けた状態を示す図である。
Further, in the construction management system according to the present embodiment, it is also possible to suitably measure the concrete covering thickness of the reinforcing bars that could not be achieved by the conventional method. Drawing 3 is an outline figure for explaining the state before and behind attaching a formwork on the arranged reinforcing bar. In FIG. 3, (a) is a figure which shows the state by which the reinforcing
まず、3次元レーザスキャナ12を用いて、図3(a)に示すように鉄筋31の配筋が施された建築物の3次元データを計測する。そして、計測された3次元データから、配筋のピッチ及び鉄筋径を含む配筋の状態を算出する。次いで、図3(b)に示すように、配筋が施された上からコンクリートを流し込むための型枠32を取り付ける。そして、3次元レーザスキャナ12を用いて型枠が取り付けられた建築物の3次元データを計測する。
First, using the three-
そして、型枠32を取り付けた後に計測された3次元データから型枠32の厚みdを取り除いた3次元データと、鉄筋31が配筋された状態での3次元データとの差分から、鉄筋31を覆うコンクリート部材の被り厚さを算出する。これによって、従来は計測することができなかったコンクリートを被り厚さをコンクリートを流し込む前に知ることができるので、コンクリート躯体の品質状態の調査をより十分に行うことが可能となる。
Then, from the difference between the three-dimensional data obtained by removing the thickness d of the
また、単にコンクリートの被り厚さを算出するだけでなく、算出された被り厚さに最小被り厚さに達していない部分があるか否かを判定するようにし、被り厚さが最小被り厚さに達していない部分がある場合、施工管理者にその旨を警告するようにしてもよい。さらに、単に警告するだけではなく、或いは当該警告に代えて、例えば、どの程度修正することによって許容範囲になるといった内容の改善要求メッセージ等を送信するようにしてもよい。 In addition to simply calculating the concrete cover thickness, it is also determined whether there is a portion where the calculated cover thickness does not reach the minimum cover thickness. If there is a part that has not reached, it may be warned to the construction manager. Further, instead of merely warning, for example, an improvement request message or the like having a content such that the amount of correction is within an allowable range may be transmitted instead of the warning.
同様にして、鉄筋だけでなく配管の段階での施工管理状態を調査するために上記施工管理システムを用いてもよい。その他、本実施形態に係る施工管理システムは、スラブの不陸管理や各種機器の据付精度の管理にも適用することが可能である。 Similarly, the construction management system may be used to investigate the construction management state at the piping stage as well as the reinforcing bars. In addition, the construction management system according to the present embodiment can be applied to slab unevenness management and management of installation accuracy of various devices.
尚、本発明は、前述した実施形態の機能をコンピュータで実現するためのプログラムを、コンピュータ読み取り可能な記録媒体(記憶媒体)に記録して、当該記録媒体に記録されたプログラムを上記システム内のコンピュータ等が読み出して実行するようにしてもよい。また、コンピュータ読み取り可能な記録媒体には、フレキシブルディスク、CD−ROM、DVD−ROM、CD−R及びDVD−R等の可搬記録媒体、システム又はコンピュータに内蔵されているハードディスク、揮発性メモリ(RAM)等の記憶装置(記録装置)を含む。また、上記プログラムは、インターネット等のネットワークや電話回線等の通信回線を介して上記システムやコンピュータ等にダウンロードするようにしてもよい。 In the present invention, a program for realizing the functions of the above-described embodiments by a computer is recorded on a computer-readable recording medium (storage medium), and the program recorded on the recording medium is stored in the system. A computer or the like may read and execute. Computer-readable recording media include portable recording media such as flexible disks, CD-ROMs, DVD-ROMs, CD-Rs, and DVD-Rs, hard disks built into the system or computer, and volatile memory ( A storage device (recording device) such as a RAM). The program may be downloaded to the system, computer, or the like via a network such as the Internet or a communication line such as a telephone line.
そして、上記システムやコンピュータにおいて、読み出されたプログラムを実行することにより、前述した実施形態の機能が実現されることとなる。この場合、上記記録媒体等は、前述したフローチャートに対応するプログラムを格納している。 Then, the functions of the above-described embodiments are realized by executing the read program in the system or the computer. In this case, the recording medium or the like stores a program corresponding to the flowchart described above.
10 建築施工現場
11、21 コンピュータ
12 3次元レーザスキャナ
13、22 記憶装置
20 事務所(又は、会社等)
30 ネットワーク
10
30 network
Claims (4)
前記建築物の3次元CADデータを記憶する記憶手段と、
3次元レーザスキャナを用いて、建築施工中の前記建築物の3次元形状を示す3次元データを計測する計測手段と、
前記記憶手段に記憶された前記3次元CADデータと前記計測手段で計測された前記3次元データとを照合する照合手段と、
前記照合手段による照合結果から、前記建築物の建築施工において発生した誤差を算出する算出手段と、
前記誤差が許容範囲内か否かを判定する判定手段と、
3次元レーザスキャナを用いて、改装施工前の建築物の3次元形状を示す3次元データを計測する第2の計測手段と、
前記3次元データを前記建築物の3次元CADデータに変換する変換手段と、
を備え、
前記記憶手段が、前記変換手段で変換された前記建築物の3次元CADデータを初期値として記憶し、
前記記憶手段に記憶された前記3次元CADデータに基づいて改装施工後の建築物の3次元CADデータをシミュレートするシミュレート手段をさらに備えることを特徴とする施工管理システム。 A construction management system for managing the accuracy of buildings under construction,
Storage means for storing three-dimensional CAD data of the building;
Measuring means for measuring three-dimensional data indicating the three-dimensional shape of the building under construction using a three-dimensional laser scanner;
Collation means for collating the three-dimensional CAD data stored in the storage means with the three-dimensional data measured by the measurement means;
From the collation result by the collation means, a calculation means for calculating an error generated in the construction of the building,
Determining means for determining whether the error is within an allowable range ;
A second measuring means for measuring three-dimensional data indicating a three-dimensional shape of the building before the refurbishment using a three-dimensional laser scanner;
Conversion means for converting the three-dimensional data into three-dimensional CAD data of the building;
With
The storage means stores the three-dimensional CAD data of the building converted by the conversion means as an initial value,
A construction management system further comprising simulation means for simulating three-dimensional CAD data of a building after renovation based on the three-dimensional CAD data stored in the storage means .
3次元レーザスキャナを用いて、配筋が施された前記建築物の3次元形状を示す3次元データを計測する第1の計測工程と、
前記3次元データから、前記配筋のピッチ及び該配筋の直径を含む該配筋の状態を算出する第1の算出工程と、
3次元レーザスキャナを用いて、前記配筋が施され、さらに型枠が取り付けられた前記建築物の3次元形状を示す3次元データを計測する第2の計測工程と、
前記3次元データから前記型枠の厚みを取り除いた3次元データと、算出された前記配筋の状態とから、該鉄筋を覆うコンクリート部材の被り厚さを算出する第2の算出工程と
を有することを特徴とする施工管理方法。 A construction management method for managing the accuracy of a building under construction,
Using a three-dimensional laser scanner, a first measurement step of measuring three-dimensional data indicating a three-dimensional shape of the building to which reinforcement is applied;
A first calculation step of calculating a state of the bar arrangement including a pitch of the bar arrangement and a diameter of the bar arrangement from the three-dimensional data;
Using a three-dimensional laser scanner, a second measurement step of measuring three-dimensional data indicating a three-dimensional shape of the building to which the bar arrangement is performed and a formwork is attached;
A second calculation step of calculating the covering thickness of the concrete member covering the reinforcing bar from the three-dimensional data obtained by removing the thickness of the formwork from the three-dimensional data and the calculated state of the reinforcement. A construction management method characterized by that.
前記判定工程によって、前記被り厚さが前記最小被り厚さに達していない部分がある場合、施工管理者に警告する警告工程をさらに有することを特徴とする請求項3に記載の施工管理方法。 A determination step of determining whether or not there is a portion that has not reached the minimum cover thickness with respect to the cover thickness calculated by the second calculation step;
The construction management method according to claim 3 , further comprising a warning step of warning a construction manager when there is a portion where the covering thickness does not reach the minimum covering thickness by the determination step.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004025326A JP4351081B2 (en) | 2004-02-02 | 2004-02-02 | Construction management system and construction management method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004025326A JP4351081B2 (en) | 2004-02-02 | 2004-02-02 | Construction management system and construction management method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2005213972A JP2005213972A (en) | 2005-08-11 |
JP4351081B2 true JP4351081B2 (en) | 2009-10-28 |
Family
ID=34907743
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2004025326A Expired - Lifetime JP4351081B2 (en) | 2004-02-02 | 2004-02-02 | Construction management system and construction management method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4351081B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20220131581A (en) * | 2021-03-22 | 2022-09-29 | 충북대학교 산학협력단 | Dimensional quality inspection method for reinforced concrete structures |
Families Citing this family (25)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5048962B2 (en) * | 2006-04-03 | 2012-10-17 | 大成建設株式会社 | Architectural plan change method and architectural plan change device using three-dimensional laser scanner |
US9858712B2 (en) * | 2007-04-09 | 2018-01-02 | Sam Stathis | System and method capable of navigating and/or mapping any multi-dimensional space |
JP5350729B2 (en) * | 2008-09-30 | 2013-11-27 | 大成建設株式会社 | Work type confirmation system, work form confirmation program, and work form confirmation method |
JP2010151577A (en) * | 2008-12-25 | 2010-07-08 | Shimizu Corp | Device and method for inspecting arrangement of reinforcing bar |
KR101081937B1 (en) | 2009-06-11 | 2011-11-09 | 연세대학교 산학협력단 | A Method for Assessing the Possibility of Joining Structures Using Terrestrial Laser Scanner |
JP5557609B2 (en) * | 2010-06-15 | 2014-07-23 | 株式会社新世測量 | 3D data management system |
JP5235235B1 (en) * | 2012-01-20 | 2013-07-10 | 新菱冷熱工業株式会社 | Building production system |
JP6024964B2 (en) * | 2012-11-21 | 2016-11-16 | 清水建設株式会社 | Cover thickness inspection system |
KR101392566B1 (en) * | 2012-11-23 | 2014-05-27 | 성균관대학교산학협력단 | Quality managing method for construction material using reverse modeling and reconstruction determing method using reverse modeling |
JP6264601B2 (en) * | 2013-08-30 | 2018-01-24 | 清水建設株式会社 | Rebar positioning system |
CN104864806A (en) * | 2014-02-24 | 2015-08-26 | 顺富科技实业有限公司 | Stereo-space measuring instrument and space measuring method thereof |
JP2014112957A (en) * | 2014-03-10 | 2014-06-19 | Shinsei Sokuryo Co Ltd | Three-dimensional data management system |
JP6500351B2 (en) * | 2014-06-09 | 2019-04-17 | 株式会社大林組 | Construction management system for construction work, program for construction management of construction work, and construction management method for construction work |
JP6468962B2 (en) * | 2015-07-03 | 2019-02-13 | 日立造船株式会社 | Crane interference check system, bridge erection simulation system, and 3D construction planning system equipped with them |
JP6463235B2 (en) * | 2015-08-31 | 2019-01-30 | 三菱電機ビルテクノサービス株式会社 | Dimensional measuring device |
JP6680628B2 (en) * | 2016-06-15 | 2020-04-15 | 株式会社トプコン | Laser scanner |
JP6946164B2 (en) * | 2017-12-19 | 2021-10-06 | 大和ハウス工業株式会社 | Building construction system |
JP7332015B2 (en) * | 2018-10-04 | 2023-08-23 | 株式会社大林組 | Construction work device and construction work method |
CN109470222B (en) * | 2018-12-13 | 2021-08-10 | 潍坊科技学院 | Supervision control method for super high-rise building engineering measurement |
JP7288769B2 (en) * | 2019-03-05 | 2023-06-08 | 倉敷紡績株式会社 | Insulation thickness control system and server |
JP7311225B2 (en) | 2019-05-15 | 2023-07-19 | 株式会社トプコン | Measuring system, measuring method and measuring program |
JP7390956B2 (en) | 2020-03-27 | 2023-12-04 | 株式会社フジタ | Construction work support system and construction work support method |
JP7411930B2 (en) | 2020-03-30 | 2024-01-12 | 株式会社イクシス | inspection system |
JP2020101573A (en) * | 2020-04-03 | 2020-07-02 | 株式会社トプコン | Position specifying device |
LU102102B1 (en) | 2020-09-30 | 2022-03-30 | Space Time S A | Data management of a building construction over time |
-
2004
- 2004-02-02 JP JP2004025326A patent/JP4351081B2/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20220131581A (en) * | 2021-03-22 | 2022-09-29 | 충북대학교 산학협력단 | Dimensional quality inspection method for reinforced concrete structures |
KR102613835B1 (en) * | 2021-03-22 | 2023-12-14 | 충북대학교 산학협력단 | Dimensional quality inspection method for reinforced concrete structures |
Also Published As
Publication number | Publication date |
---|---|
JP2005213972A (en) | 2005-08-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4351081B2 (en) | Construction management system and construction management method | |
CN111627099B (en) | Steel structure non-contact actual measurement real quantity method and system based on three-dimensional scanning technology | |
CN106370670A (en) | 3D laser scanning based building prefabricated part quality detection system and method | |
CN109146711A (en) | A method of comprehensive utilization BIM technology and 3D laser scanning system Optimizing construction | |
CN109025319B (en) | Quality detection and disposal method for prefabricated part butt joint interface | |
JP5248550B2 (en) | On-site bar arrangement support method using 3D bar arrangement system | |
Gordon et al. | Combining reality capture technologies for construction defect detection: A case study | |
CN108663029B (en) | Method for acquiring underwater cylindrical foundation pile information, storage medium and terminal | |
CN110646159A (en) | Construction method for high-precision control and measurement of cast-in-place bare concrete wind tunnel | |
CN106779476A (en) | A kind of Construction Schedule management platform and method based on BIM IFC technologies | |
JP4602844B2 (en) | Displacement information measuring system, method and program | |
Tapponi et al. | Renovation of heritage assets using BIM: A case study of the Durham Cathedral | |
CN108253193B (en) | Wall pipeline pre-embedding construction method | |
KR101081937B1 (en) | A Method for Assessing the Possibility of Joining Structures Using Terrestrial Laser Scanner | |
JP2023547784A (en) | Data management of building construction over time | |
CN109680961B (en) | Automatic generation method and device for stair embedded part based on assembly type building | |
CN116703127A (en) | Building construction supervision method and system based on BIM | |
CN109885975B (en) | Continuous beam prestressed pipeline model processing method and system | |
JP7104912B2 (en) | Information processing device, information processing method, and program | |
Akula et al. | Augmenting BIM with 3D imaging data to control drilling for embeds into reinforced concrete bridge decks | |
KR101511522B1 (en) | 3-dimensional coordinate converting method of precision measuring drawing and storage medium | |
JP2021085745A (en) | Concrete surface evaluation system | |
JP2003104650A (en) | System and terminal for preparing elevator installation drawing | |
JP2006057396A (en) | Plumbing accuracy control method and plumbing method | |
JP2002049656A (en) | Site measurement support system for wall material |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20061117 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20090216 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090227 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090310 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090406 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090424 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20090626 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20090723 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120731 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4351081 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120731 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20150731 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20150731 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20150731 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |