JP4327639B2 - Construction method of cast-in-place concrete pile - Google Patents

Construction method of cast-in-place concrete pile Download PDF

Info

Publication number
JP4327639B2
JP4327639B2 JP2004092396A JP2004092396A JP4327639B2 JP 4327639 B2 JP4327639 B2 JP 4327639B2 JP 2004092396 A JP2004092396 A JP 2004092396A JP 2004092396 A JP2004092396 A JP 2004092396A JP 4327639 B2 JP4327639 B2 JP 4327639B2
Authority
JP
Japan
Prior art keywords
concrete
pile
casing
top end
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2004092396A
Other languages
Japanese (ja)
Other versions
JP2005273412A (en
Inventor
重則 川西
隆 上西
孝徳 起橋
峰晴 中山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP2004092396A priority Critical patent/JP4327639B2/en
Publication of JP2005273412A publication Critical patent/JP2005273412A/en
Application granted granted Critical
Publication of JP4327639B2 publication Critical patent/JP4327639B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Description

本発明は、杭頭等にスライム等の不純分が殆ど混入していない品質のよい場所打ちコンクリート杭を能率よく造成することができる場所打ちコンクリートの造成方法に関するものである。   The present invention relates to a method for producing cast-in-place concrete capable of efficiently building a cast-in-place concrete pile having good quality in which impurities such as slime are hardly mixed in a pile head or the like.

従来から、場所打ちコンクリート杭を造成するには、地表面部分にケーシングを埋設状態に建て込み、このケーシング内を通じて該ケーシング下方の地盤をベントナイト液等の安定液によって孔壁の崩壊を防止しながら掘削して所定深さの杭孔を形成し、この杭孔内に鉄筋籠を建て込んだのち、トレミー管を杭孔内中心部に挿入して該トレミー管を通じて生コンクリート(以下、単にコンクリートという)を打設することにより造成しているが、打設コンクリートの上端部には杭の強度を低下させるスライム等の不純物が混在しているため、予め、計画杭の天端面よりも上方部分までコンクリートを打設して杭頭にコンクリートの余盛り部分を形成しておき、この余盛り部分を除去することによって杭頭処理を行っている。   Conventionally, in order to construct a cast-in-place concrete pile, a casing is embedded in the ground surface portion, and the ground below the casing is prevented from collapsing the hole wall with a stable liquid such as bentonite liquid through the casing. After digging to form a pile hole of a predetermined depth, and building a reinforcing bar in this pile hole, insert the tremy pipe into the center of the pile hole and through the treme pipe (hereinafter simply referred to as concrete) ), But the upper end of the cast concrete is mixed with impurities such as slime that reduce the strength of the pile. Pile head processing is performed by placing concrete and forming an extra portion of concrete on the pile head and removing this extra portion.

このような杭頭処理方法としては、従来から、打設コンクリートの硬化後に、スライム等の不純物を含むコンクリートの余盛り部分を斫りとって除去する方法や、コンクリート打設直後に未硬化の余盛り部分のコンクリートやバキュームホースによって吸引、除去する方法が採用されている。   Conventionally, such pile head treatment methods include a method of scraping off and removing the excess portion of concrete containing impurities such as slime after hardening of the cast concrete, or an uncured surplus immediately after casting of the concrete. A method of sucking and removing with a concrete or vacuum hose at the height is adopted.

一方、特許文献1には、杭孔内に計画杭頭の天端面の下方近傍部までコンクリートを打設したのち、一旦、バキューム装置によって打設したコンクリート上のスライム等の不純物を吸引除去し、しかるのち、着色コンクリートを計画杭の天端面よりも上方部分にまで打設して計画杭の天端面から上方におけるスライム等の不純物が混在する着色コンクリートの余盛り部分を着色した色相を確認しながら吸引除去し、次いで、打設コンクリートの天端を均すことが記載されている。
特開2003−64670号公報
On the other hand, in Patent Document 1, after placing concrete into the lower part of the top end face of the planned pile head in the pile hole, once the impurities such as slime on the concrete placed by the vacuum device are removed by suction, After that, colored concrete is placed up to the upper part of the top end of the planned pile, while checking the hue that colored the extra portion of the colored concrete mixed with impurities such as slime above the top end of the planned pile. It is described that it is removed by suction and then the top edge of the cast concrete is leveled.
JP 2003-64670 A

しかしながら、前者の杭頭処理方法では、杭の品質を確保するために、余盛り高さを1m以上にするので、斫り量が多くて斫り手間と処理費を多く必要とする上に、斫るための大掛かりな装置や機器類も必要し、さらに、斫り取り作業時に振動や大きな騒音が発生して環境を悪化させるという問題点がある。そのため、コンクリート打設直後に余盛り部分のコンクリートを吸引除去し、杭の天端を均すことによって杭頭の斫り取り作業を省略することができる後者の杭頭処理方法を採用しているが、この方法も同じく、杭の品質を確保するために、余盛り高さを1m以上にするので、吸引除去するコンクリートの量が多く、産業廃棄物として廃棄するための処理費用が高くなるといった問題点がある。   However, in the former pile head processing method, in order to ensure the quality of the pile, since the surplus height is 1 m or more, the amount of turning is large, and it requires a lot of trouble and processing costs. In addition, a large-scale device and equipment are required to beat, and further, there is a problem that vibration and loud noise are generated at the time of scraping work and the environment is deteriorated. Therefore, the latter pile head treatment method is adopted, which can eliminate the pile head scraping work by sucking and removing the concrete of the surplus portion immediately after placing the concrete and leveling the top of the pile. However, in this method as well, since the surplus height is set to 1 m or more in order to ensure the quality of the pile, the amount of concrete to be removed by suction is large, and the processing cost for disposal as industrial waste is high. There is a problem.

また、ベントナイト液やスライム等の不純物を含むコンクリート部分が完全に除去されたかどうかの確認を行うことができないので、コンクリートの硬化後、杭頭の一部から試料片となるコアを抜き取ってこのコアの圧縮強度等の試験を行うことにより、品質の確認を行っているのが現状である。そのため、多数の場所打ちコンクリート杭にこのようなコアの抜き取りから圧縮強度等の試験までの作業を行うには多大な手間と費用がかかると共に、試験結果が出るまで次の作業工程に移れないという問題があった。   In addition, since it is impossible to confirm whether or not the concrete portion containing impurities such as bentonite liquid and slime has been completely removed, after the concrete is hardened, the core as a sample piece is extracted from a part of the pile head. At present, quality is confirmed by performing tests such as compressive strength. For this reason, it takes a lot of time and effort to perform a number of cast-in-place concrete piles from the extraction of the core to the test such as compressive strength, and it is impossible to move to the next work process until the test results are obtained. There was a problem.

一方、上記特許文献1によれば、余盛り部分を吸引除去するので、振動や大きな騒音を発生させる斫り取り作業を省略することができるが、安定液とスライムを吸引除去する作業と、着色コンクリートを計画杭の天端面よりも上方部分にまで打設したのち、該着色コンクリートにおけるスライム等の不純物が混在する着色コンクリート部分を吸引除去する作業との2回の不純物除去作業を必要とするので、杭の造成作業が煩雑化すると共に作業時間が長くなるといった問題点があり、また、杭の品質を確認するためには、上記の杭頭処理方法と同様に、着色コンクリートの余盛り高さを1m以上にする必要があり、その上、この余盛り部分の着色コンクリートの吸引除去と先に打設したコンクリート上のスライム等の不純物の吸引除去とによるコンクリートの除去量が多量となって廃棄処理費用が高額になる。   On the other hand, according to the above-mentioned patent document 1, since the surplus portion is removed by suction, the scraping work that generates vibration and loud noise can be omitted, but the work of removing the stable liquid and slime by suction, and coloring After placing concrete up to the upper part of the top end of the planned pile, it is necessary to remove impurities twice by sucking and removing colored concrete parts mixed with impurities such as slime in the colored concrete. In addition, there is a problem that the construction work of the pile becomes complicated and the work time becomes long. Also, in order to check the quality of the pile, the height of the piled concrete of the colored concrete is the same as the above pile head treatment method. 1m or more, and in addition, suction removal of the colored concrete in the excess portion and suction removal of impurities such as slime on the previously placed concrete Disposal cost may become high removal amount of concrete is a large amount.

さらに、品質の確認を行うためにコンクリートを着色するので、着色のための染料等の材料費や染料をコンクリートに均一に混合するまでの時間等を必要として場所打ち杭の造成工事の作業能率を低下させることになり、その上、上述のように先に打設したコンクリート上のスライム等の不純物を吸引除去する際にはコンクリートの打設を中断し、不純物の吸引除去後、着色コンクリートを打設するものであるから、杭としての品質の確保が難しくなると共に杭の造成作業に時間をようするといった問題点がある。   In addition, since the concrete is colored to check the quality, it requires material costs such as dyes for coloring and time until the dye is uniformly mixed with the concrete. In addition, when removing impurities such as slime on the concrete previously placed as described above by suction, the concrete placement is interrupted, and after removing the impurities by suction, colored concrete is cast. Therefore, it is difficult to ensure the quality of the pile, and there is a problem that it takes time to build the pile.

本発明はこのような問題点に鑑みてなされたもので、その目的とするところは、多量の余盛り部分を設けることなく吸引除去すべき打設コンクリートの量を最小限度にして、且つ強度等の品質においても優れた場所打ちコンクリート杭を安定的に能率よく造成することができる場所打ちコンクリート杭の造成方法を提供するにある。   The present invention has been made in view of such problems, and the object of the present invention is to minimize the amount of cast concrete to be removed by suction without providing a large amount of surplus parts, and to improve the strength, etc. It is in providing the construction method of the cast-in-place concrete pile which can construct the cast-in-place concrete pile excellent also in the quality of the stable and efficiently.

上記目的を達成するために、本発明の場所打ちコンクリート杭の造成方法は、請求項1に記載したように、地盤の表層部にケーシングを、その下端部が計画杭の天端面よりも下方に位置するまで建て込んだのち、該ケーシング内から下方の地盤を所定深さまで安定液を満たしながら杭孔を掘削し、次いで、この杭孔内にコンクリートをケーシング内における該ケーシングの下端部から計画杭の天端面部分に達する間の高さ位置まで打設したのち、該打設コンクリート天端面上の安定液とスライム及び該スライム等の不純物が混在するコンクリート部分を除去し、しかるのち、計画杭の天端面より所定高さ高い位置に達するまでコンクリートを打設して余盛り部分を形成し、次いで、ケーシングを上昇させて打設コンクリートの天端面を計画杭の天端面の高さに合わすことを特徴とする。 In order to achieve the above object, the cast-in-place concrete pile manufacturing method according to the present invention includes, as described in claim 1, a casing on the surface layer portion of the ground, and a lower end portion thereof below the top end surface of the planned pile. After being built until it is located, a pile hole is excavated while filling the lower ground from the inside of the casing to a predetermined depth with a stable liquid, and then concrete is put into the pile hole from the lower end of the casing in the planned pile. After laying up to the height position while reaching the top end surface part of the concrete, remove the concrete part mixed with stabilizing liquid and slime and impurities such as the slime on the concrete top end face of the cast concrete. The concrete is cast to reach a position higher than the top end surface to form a surplus part, and then the casing is raised to plan the top end surface of the cast concrete. Wherein the match the height of the top end face.

上記請求項1に記載の場所打ちコンクリート杭の造成方法において、請求項に係る発明は、スライム等の不純物が混在するコンクリート部分の除去を、コンクリート天端にコンクリートの骨材が多く視認できるまで行うことを特徴とする。 In the method for forming a cast-in-place concrete pile according to claim 1, the invention according to claim 2 removes the concrete part mixed with impurities such as slime until a large amount of concrete aggregate is visible at the top of the concrete. It is characterized by performing.

さらに、請求項に係る発明は、上記バキュームホースを杭孔内に建て込んでいる鉄筋籠とケーシングの内周壁面との間の隙間に挿入して不純物が混在するコンクリート部分の除去を行うことを特徴とする。 Furthermore, the invention which concerns on Claim 3 inserts the said vacuum hose in the clearance gap between the reinforcement bar which has built in the pile hole, and the inner peripheral wall surface of a casing, and removes the concrete part in which an impurity is mixed. It is characterized by.

請求項1に係る発明によれば、ケーシングをその下端部が地盤の表層部における計画杭の天端面よりも深い位置に達するまで建て込んでおくので、このケーシングが土留作用を奏して打設コンクリートが該ケーシングの下端に達した後においては杭孔内のベントナイト等の安定液を除去しても、地盤が崩壊することはなく、従って、打設コンクリートの天端がケーシングの下端に達したのち、該ケーシング内の計画杭の天端面近傍部等の所定高さまでの適宜高さ位置において、打設コンクリートの天端面上の安定液とスライム及び該スライム等の不純物が混在するコンクリート部分を除去することによって殆ど全ての不純物を確実に除去することができる。   According to the first aspect of the invention, the casing is built until the lower end of the casing reaches a position deeper than the top end surface of the planned pile in the surface layer portion of the ground. After reaching the lower end of the casing, the ground will not collapse even if the stabilizing liquid such as bentonite in the pile hole is removed. Therefore, after the top of the cast concrete reaches the lower end of the casing Removing a portion of the concrete mixed with stable liquid, slime, and impurities such as slime on the top end surface of the cast concrete at an appropriate height position up to a predetermined height such as the vicinity of the top end surface of the planned pile in the casing. As a result, almost all impurities can be reliably removed.

このように、打設コンクリートがケーシング内における計画杭の天端面の位置までの適宜高さ位置において、該ケーシング内で安定液とスライム及び該スライム等の不純物が混在するコンクリート部分を一回の除去作業によって排除するので、不純物を短時間で集中的に除去することができると共にその処理量も少なくてすみ、産業廃棄物としての処理費用を低減させることができる上に、一度の除去作業によって効果的にスライム等の不純物や該不純物が混在するコンクリート部分を排除することができるので、杭の造成作業が円滑且つ能率よく行えると共に強度等の品質に優れた杭を造成することができる。その上、不純物の除去によって露呈したコンクリートの天端面の高さ位置が容易に観察することができて、その位置からの計画杭の天端面までの高さを確認することができ、該天端面までのコンクリートの打設作業が正確に且つ能率よく行うことができる。   In this way, at the appropriate height position of the cast concrete up to the position of the top end face of the planned pile in the casing, the concrete portion in which the stable liquid, slime, and impurities such as the slime are mixed is removed once in the casing. Since it is eliminated by the work, impurities can be removed intensively in a short time and the amount of treatment can be reduced, so that the processing cost as industrial waste can be reduced and the effect of the removal work once. In addition, impurities such as slime and the concrete portion in which the impurities are mixed can be eliminated, so that piles can be built smoothly and efficiently, and piles excellent in quality such as strength can be created. In addition, the height position of the concrete top face exposed by removing impurities can be easily observed, and the height from the position to the top face of the planned pile can be confirmed. The concrete placement work up to can be performed accurately and efficiently.

さらに、コンクリートをケーシング内における該ケーシング下端部から計画杭の天端面部分に達する間の高さ位置まで打設したのち、該打設コンクリート天端面上の安定液とスライム及び該スライム等の不純物が混在するコンクリート部分を除去し、しかるのち、計画杭の天端面より所定高さ高い位置に達するまでコンクリートを打設して余盛り部分を形成し、次いで、ケーシングを上昇させてその抜き取り跡に生じた該ケーシングの厚みに相当する隙間に上記余盛り部分に相当するコンクリートを流入充填させるので、計画杭の天端面から上方に打設する余盛り部分の量がケーシングの抜き取り跡の容積を充足できるだけの量であればよく、従って、打設コンクリートの量も必要最小限度にして簡単且つ正確にその天端面を計画杭の天端面に略一致させることができると共に材料費の節減を図ることができ、余分な打設コンクリートの除去作業や廃棄処理を不必要にして、或いは、少なくして造成工事の短縮を図ることができる。また、余盛り部分を硬化させることなく均すので爾後において斫り作業が不要となり、斫るための大型機械を使用することもないから騒音や振動が発生しない環境を実現することができる。 Furthermore, after pouring to a height position between the concrete reaches the top end surface portion of the planned pile from the casing bottom end of the casing, impurities such as stabilizing solution and slime and the slime on the ball striking setting concrete top end face Remove the mixed concrete part, and then cast concrete until it reaches a position higher than the top edge of the planned pile to form a surplus part, and then raise the casing to produce the removal trace. In addition, since the concrete corresponding to the surplus portion is filled and filled in the gap corresponding to the thickness of the casing, the amount of the surplus portion to be placed upward from the top end surface of the planned pile can satisfy the volume of the extraction trace of the casing. Therefore, the top end face of the planned pile can be easily and accurately made with the minimum amount of concrete placed. It is possible to save the material cost it is possible to substantially coincide, the removal operation and disposal of extra pouring concrete in unnecessary or can be shortened reclamation work with less. Further, since the surplus portion is leveled without being cured, no turning work is required after turning, and a large machine for turning is not used, so that an environment free from noise and vibration can be realized.

場所打ちコンクリート杭の品質の確認は、請求項に記載したように、スライム等の不純物が混在するコンクリート部分の吸引除去を、コンクリート天端にコンクリートの骨材が多く視認できるまで行うことによって確実に行うことができる。 Confirming the quality of cast-in-place concrete piles is assured by performing suction removal of concrete parts mixed with impurities such as slime until a large amount of concrete aggregate is visible at the top of the concrete as described in claim 2. Can be done.

また、上記杭孔内へのコンクリート打設作業を該杭孔の中心部等に挿入したトレミー管によって行った場合、打設コンクリートの天端においてコンクリートの流れがトレミー管側から杭孔の孔壁面に向かって流れてスライム等の不純物が混在したコンクリートがその孔壁面側に集中的に滞留することになるので、請求項に記載したように、バキュームホースを杭孔内に建て込んでいる鉄筋籠とケーシングの内周壁面との間の隙間に挿入することにより、不純物が混在したコンクリートを効率よく吸引除去することができる。 In addition, when the concrete placement work into the pile hole is performed with a tremey pipe inserted into the center of the pile hole, the concrete flow from the tremey pipe side to the hole wall surface of the pile hole at the top of the cast concrete Since concrete that flows toward the surface and mixed with impurities such as slime is concentrated on the hole wall surface side, the reinforcing bar in which the vacuum hose is built in the pile hole as described in claim 3 By inserting it into the gap between the ridge and the inner peripheral wall surface of the casing, the concrete in which impurities are mixed can be efficiently removed by suction.

次に、本発明の具体的な実施の形態を図面について説明する。まず、杭孔の掘削から杭頭処理前に至るまでの現場打ちコンクリート杭の施工手順を図1に基づいて簡単に説明する。この施工手順は公知のように、掘削機械10を使用して図1(イ)に示すように地盤に先行掘り1aを行ったのち、図1(ロ)に示すように表層ケーシング2をその下端が計画杭の天端面6よりも深い下方位置に達するように建て込んで掘削孔上部の孔壁の崩壊を防止する。次いで、掘削される孔内にベントナイト液等の孔壁安定液13を充満させた状態で上記掘削機械10によって図1(ハ)に示すように所定深さまで杭孔1を掘削する。この杭孔1の掘削後、孔底に沈澱しているスライムの一次処理を行い、しかるのち、図1(ニ)に示すように杭孔1内に鉄筋籠3を建て込む。   Next, specific embodiments of the present invention will be described with reference to the drawings. First, the construction procedure of the on-site concrete pile from the excavation of the pile hole to before the pile head processing will be briefly described based on FIG. As is well known in the art, after excavating the ground 1a as shown in FIG. 1 (a) using the excavating machine 10, the surface casing 2 is moved to its lower end as shown in FIG. 1 (b). Is built so as to reach a lower position deeper than the top end face 6 of the planned pile to prevent the collapse of the hole wall above the excavation hole. Next, the pile hole 1 is excavated to a predetermined depth as shown in FIG. 1C by the excavating machine 10 with the hole wall stabilizing liquid 13 such as bentonite liquid filled in the excavated hole. After excavation of the pile hole 1, primary processing of the slime settled on the bottom of the hole is performed, and then a reinforcing bar 3 is built in the pile hole 1 as shown in FIG.

次いで、図1(ホ)に示すように、トレミー管4を杭孔1内の中央部に位置させながらその開口下端が杭孔1の底面に達するまで吊り込んで、2次スライム処理を行ったのち、このトレミー管4を通じて図1(ヘ)に示すように、地上から杭孔1内にコンクリート5を打設する。   Next, as shown in FIG. 1 (e), while the tremy tube 4 is positioned at the center of the pile hole 1, it is suspended until the lower end of the opening reaches the bottom surface of the pile hole 1, and the secondary slime treatment is performed. After that, as shown in FIG. 1 (f), the concrete 5 is driven into the pile hole 1 from the ground through the tremy tube 4.

このコンクリート5の打設は、コンクリート5を杭孔1内に供給するトレミー管4の開口下端が常に打設したコンクリート5内に没入させた状態にしながら打設する。打設コンクリート5の上昇に従ってコンクリート5の打設天端面5aからの没入深さを一定範囲(2〜6m)に保ちながらトレミー管4を上方に引き上げる。コンクリート5の上端面5aからのトレミー管4の没入深さが浅すぎると、コンクリート5の材料分離やスライムの混入の原因となり、深すぎるとトレミー管4からのコンクリート5の流出停止やトレミー管4の引き上げ不能の原因となるので、上記のようにトレミー管4を2〜6mの深さに保持しながらコンクリート5の打設に従って引き上げていく。なお、コンクリート5の打設に伴って杭孔1内に供給した安定液13の液面が上昇するが、この安定液13を水中ポンプ9によって汲み出してその水位を一定高さに保つ。打設コンクリート5がケーシング2の下端部内に達すると、安定液を除去しても、該ケーシング2が土留作用を行うので、地盤が崩壊することはない。   The concrete 5 is placed while the lower end of the opening of the tremmy pipe 4 that supplies the concrete 5 into the pile hole 1 is always immersed in the concrete 5 that has been placed. The tremely pipe 4 is pulled upward while keeping the immersion depth of the concrete 5 from the casting top end surface 5a within a certain range (2 to 6 m) as the casting concrete 5 rises. If the immersion depth of the tremmy pipe 4 from the upper end surface 5a of the concrete 5 is too shallow, it will cause material separation of the concrete 5 and mixing of slime. If it is too deep, the outflow of the concrete 5 from the tremy pipe 4 will stop. 4 cannot be pulled up, so that the tremy tube 4 is pulled up according to the placement of the concrete 5 while holding the tremy tube 4 at a depth of 2 to 6 m as described above. In addition, although the liquid level of the stable liquid 13 supplied in the pile hole 1 rises with the placement of the concrete 5, the stable liquid 13 is pumped out by the submersible pump 9 and the water level is kept at a constant height. When the cast concrete 5 reaches the lower end of the casing 2, even if the stabilizing liquid is removed, the casing 2 performs a soil retaining action, so that the ground does not collapse.

こうして、コンクリート5の打設上端面5aがケーシング2の下端部内に達すると、一旦打設コンクリート5の打設を停止したのち、図1(ト)及び図2に示すように、予め杭孔1内の計画杭の高さ近くにまで下ろしておいた水中ポンプ9を始動して、上記打設コンクリート5上の全ての安定液13を地上に排出し、続いて、図3に示すように、予め、杭孔1内に挿入しておいたバキュームホース12により、該バキュームホース12が接続している地上の適所に配設したバキューム装置(バキューム車)11(図1(ト)に示す)を作動させることにより打設コンクリート5上のスライム14やスライムの混入したコンクリート部分15(コンクリート表層部分)等の不純物を吸引除去する。   In this way, when the placement upper end surface 5a of the concrete 5 reaches the lower end portion of the casing 2, the placement of the placement concrete 5 is once stopped, and thereafter, as shown in FIGS. The submersible pump 9 that has been lowered to the height of the planned pile inside is started, all the stabilizing liquid 13 on the cast concrete 5 is discharged to the ground, and then, as shown in FIG. A vacuum device (vacuum wheel) 11 (shown in FIG. 1 (G)) disposed in a proper place on the ground to which the vacuum hose 12 is connected by means of a vacuum hose 12 inserted in the pile hole 1 in advance. When activated, impurities such as slime 14 on the cast concrete 5 and concrete part 15 (concrete surface part) mixed with slime are sucked and removed.

この際、打設コンクリート5は、杭孔1の中心部にトレミー管4を挿入することによって行われているので、このトレミ管4により打設された時には、該コンクリート5はトレミー管4を伝って上昇してコンクリート天端部においては該トレミー管4の挿入部分が最も盛り上がり、その盛り上がりの中心部からケーシング2の内周壁面に向かって流れるので、該盛り上がり部分の天端面がケーシング2の内周壁面に向かって斜め下方に傾斜した傾斜端面となってスライム14もこの傾斜端面上を流動してケーシング2の内周壁面側に集められた状態となっている。   At this time, since the cast concrete 5 is performed by inserting the treme tube 4 into the center portion of the pile hole 1, the concrete 5 is transmitted along the treme tube 4 when it is cast by the tremi tube 4. In the top end of the concrete, the insertion portion of the tremely tube 4 is the most swelled and flows from the center of the swell toward the inner peripheral wall surface of the casing 2. The slime 14 also flows on the inclined end surface and gathers on the inner peripheral wall surface side of the casing 2 as an inclined end surface inclined obliquely downward toward the peripheral wall surface.

従って、バキュームホース12をケーシング2の内周壁面に沿って挿入した状態、即ち、杭孔1に建て込んでいる鉄筋籠3とケーシング2との間の隙間に挿入した状態にしてケーシング2の内周壁面に沿って周方向に移動させながらスライム14や該スライム等の不純物を混在したコンクリート部分15を吸引、除去すると、該スライム14やスライム等の不純物を混在したコンクリート部分15を集中的に能率よく吸引除去することができると共に、この吸引除去が進行するに従って打設コンクリート5の天端面5a上のスライム14や該スライム等の不純物を混在したコンクリート部分15が打設コンクリート5の上記傾斜天端面上をケーシング2の中心部側から内周壁面側に流動し、バキュームホース12をケーシング2の中央部に移動させることなく内周壁面に沿わした状態に周方向に移動させるのみで、打設コンクリート5上の全てのスライム14や該スライム等の不純物を混在したコンクリート部分15を確実に且つ能率よく吸引除去することができる。   Therefore, the vacuum hose 12 is inserted along the inner peripheral wall surface of the casing 2, that is, inserted into the gap between the reinforcing bar 3 built in the pile hole 1 and the casing 2. When the concrete part 15 mixed with impurities such as slime 14 and the slime is sucked and removed while moving in the circumferential direction along the peripheral wall surface, the concrete part 15 mixed with impurities such as slime 14 and slime is efficiently concentrated. As the suction and removal progresses, the sloping 14 on the top end surface 5a of the cast concrete 5 and the concrete portion 15 mixed with impurities such as the slime are formed on the inclined top end surface of the cast concrete 5. The upper wall flows from the center side of the casing 2 to the inner wall surface, and the inner wall surface without moving the vacuum hose 12 to the center of the casing 2 Only moved in along a state in the circumferential direction, all the slime 14 and concrete portion 15 which impurities are mixed, such as the slime on pouring concrete 5 can be reliably and efficiently sucked and removed.

なお、上記打設コンクリート5の天端面上の安定液13のポンプ除去やこの安定液13のポンプ除去に引き続いて行われるスライム14や不純物が混在したコンクリート部分15の吸引除去は、打設コンクリート5の天端面5aがケーシング2の下端部内に達した時に直ちに行う必要はなく、該打設コンクリートの天端面5aがケーシング2内における計画杭の天端面6の近傍部に達したのち行ってもよい。要するに、コンクリート5をケーシング2の下端部内から計画杭の天端面部分までの間の高さ位置まで打設したのち、スライム14や該スライム等の不純物を混在したコンクリート部分15の吸引除去を行えばよい。   It should be noted that the removal of the stabilizing liquid 13 on the top end surface of the cast concrete 5 and the suction removal of the concrete portion 15 mixed with the slime 14 and impurities, which is performed subsequent to the pump removal of the stable liquid 13, are carried out. It is not necessary to carry out immediately when the top end surface 5a of the concrete reaches the lower end of the casing 2, and may be performed after the top end surface 5a of the cast concrete reaches the vicinity of the top end surface 6 of the planned pile in the casing 2. . In short, after placing concrete 5 to the height position between the lower end of casing 2 and the top end surface of the planned pile, suction removal of slime 14 and concrete part 15 mixed with impurities such as slime can be performed. Good.

この際、スライム14や不純物の混在したコンクリート部分15の吸引除去を目視で観察することによって打設コンクリート5によって造成される杭Aの天端部の強度等の品質の良否を確認する。即ち、打設コンクリート5の天端上のスライム14や該スライム等の不純物を混在したコンクリート部分15の吸引開始時は安定液13が残っているので、打設コンクリート5の天端面上にはその安定液13の色が観察されるが、安定液13が吸引除去されると、コンクリート5の色が観察されることになる。しかしながら、このコンクリート5にはスライム等の不純物が混ざっている可能性がある。そこで、天端表面の打設コンクリート5の色が観察された状態からさらに該コンクリート中に骨材が観察されるまで打設コンクリート5の天端部を吸引除去することによって、強度等の品質の優れた杭天端部が造成されることを確認するものである。さらに、不純物の除去によって露呈したコンクリートの天端面の高さ位置が容易に観察することができて、その位置からの計画杭の天端面までの高さを確認することができ、該天端面までのコンクリートの打設作業が正確に且つ能率よく行うことができる。   At this time, quality of the top end portion of the pile A formed by the cast concrete 5 is confirmed to be good or bad by visually observing the suction removal of the slime 14 and the concrete portion 15 mixed with impurities. That is, when the suction of the slime 14 on the top edge of the cast concrete 5 and the concrete portion 15 mixed with impurities such as the slime is started, the stabilizing liquid 13 remains. Although the color of the stabilizing liquid 13 is observed, when the stabilizing liquid 13 is removed by suction, the color of the concrete 5 is observed. However, this concrete 5 may be mixed with impurities such as slime. Therefore, by removing the top end portion of the cast concrete 5 by suction until the aggregate is observed in the concrete from the state in which the color of the cast concrete 5 on the top end surface is observed, the quality such as strength is improved. It confirms that an excellent pile top end is created. Furthermore, the height position of the top end surface of the concrete exposed by removing impurities can be easily observed, and the height from that position to the top end surface of the planned pile can be confirmed. The concrete can be placed accurately and efficiently.

このように、打設コンクリート5中に骨材が観察されるまで打設コンクリート5の天端部を吸引除去すれば、強度等の品質の優れた杭天端部を造成することができることは、以下に示す実験結果から明らかになっている。即ち、上記場所打ちコンクリート杭の造成工事に先立って、該造成すべき場所打ちコンクリート杭と同一条件でもって造成した場所打ちコンクリート杭の杭天端部の圧縮強度やヤング係数、単位容積重量等の品質を実験的に確認したところ、表1に示す結果が得られた。   Thus, if the top end of the cast concrete 5 is removed by suction until aggregate is observed in the cast concrete 5, it is possible to create a pile top end having excellent quality such as strength as follows. It is clear from the experimental results shown. That is, prior to the above-mentioned cast-in-place concrete pile construction work, the quality such as compressive strength, Young's modulus, unit volume weight, etc. of the pile top end of the cast-in-place concrete pile created under the same conditions as the cast-in-place concrete pile to be built When experimentally confirmed, the results shown in Table 1 were obtained.

Figure 0004327639
Figure 0004327639

この表から明らかなように、天端表面の打設コンクリートの色が観察された状態からさらに該コンクリート中に骨材が観察されるまでコンクリート天端部の吸引除去を行うと、これによって造成された杭天端部の試供体の品質が極めて優れたものとなり、スライムや不純物の混ざったコンクリートが完全に除去されたことを示している。従って、上記場所打ちコンクリート杭の造成時には、スライム14や不純物が混在したコンクリート部分15を吸引除去する際に、コンクリート中に骨材が観察されるまでその吸引除去作業を行い、これによってスライムや不純物の混ざったコンクリートが完全に除去されたことを確認することができるのである。   As is clear from this table, if the concrete top end is removed by suction until the aggregate is observed in the concrete after the color of the cast concrete on the top end surface is observed, The quality of the specimen at the top of the pile was extremely excellent, indicating that the concrete mixed with slime and impurities was completely removed. Therefore, when the cast-in-place concrete pile is constructed, when removing the slime 14 and the concrete portion 15 mixed with impurities, the suction removal work is performed until aggregate is observed in the concrete, thereby reducing the slime and impurities. It can be confirmed that the mixed concrete is completely removed.

スライム14や該スライム等の不純物が混在したコンクリート部分15を吸引除去する上記バキュームホース12の吸引口としては、図8(イ)に示すように、その先端面を斜めに輪切り状に切断してなる傾斜吸引口12a に形成するか、或いは、図8(ロ)に示すように、先端部(下端部)を一側方に向かって直角に屈曲してなる屈曲吸引口12b に形成しているものであり、このように形成したことによって、傾斜吸引口12a や屈曲吸引口12b の開口部における上部をスライム等の不純物が混在したコンクリート部分15の天端面から上方に露出させた状態にして空気と共に該スライム等の不純物が混在するコンクリート部分15を吸引除去することができ、従って、作業員がケーシング2内に入ることなく、地上側でバキュームホース12を操作しながら、吸引力による空気の急速な流れによって上記スライム等の不純物が混在するコンクリート部分15を確実に且つ能率よく吸引除去することができる。   As the suction port of the vacuum hose 12 for sucking and removing the slime 14 and the concrete portion 15 mixed with impurities such as the slime, as shown in FIG. Or a bent suction port 12b formed by bending the tip (lower end) at a right angle toward one side as shown in FIG. 8 (b). As a result of this formation, the top of the opening of the inclined suction port 12a and the bent suction port 12b is exposed upward from the top end surface of the concrete portion 15 mixed with impurities such as slime. At the same time, the concrete portion 15 mixed with impurities such as slime can be removed by suction, so that the operator can operate the vacuum hose 12 on the ground side without entering the casing 2, and the suction force By the rapid flow of air, the concrete portion 15 in which impurities such as slime are mixed can be surely and efficiently removed by suction.

こうして、打設コンクリート5におけるスライム14や該スライム等の不純物を混在したコンクリート部分15を吸引除去したのち、再び、コンクリート5を打設してケーシング2内における計画杭の天端面6より10〜50cmに達する高さの余盛り部分5'(図4(イ)参照)を形成する。この余盛り部分5'の高さは、計画杭の杭頭の径やケーシング2の厚みの大小、及び、該ケーシング2の引き上げによって生じるケーシングの厚みに相当する隙間の長さの長短によって変わるが、要するに、この打設コンクリートによる余盛り部分5'の形成後、上記ケーシング2を引き上げた時に、その引き上げ跡に生じる上記隙間にその余盛り部分5'に相当するコンクリートを流入、充填することができる高さ(量)まで設けておく。この場合、該余盛り部分5'が隙間に流入、充填した時に、その天端面が計画杭の天端面6よりも著しく高くなることは好ましくなく、従って、同一面になるか少し低めになるように余盛り部分5'の高さ(量)を設定しておく。   Thus, after removing the slime 14 and the concrete portion 15 mixed with impurities such as the slime in the cast concrete 5 by suction, the concrete 5 is cast again and 10 to 50 cm from the top end face 6 of the planned pile in the casing 2. A surplus portion 5 ′ (see FIG. 4A) having a height that reaches the height is formed. The height of the surplus portion 5 ′ varies depending on the diameter of the pile head of the planned pile, the thickness of the casing 2, and the length of the gap corresponding to the thickness of the casing caused by lifting the casing 2. In short, when the casing 2 is lifted after the formation of the surplus portion 5 'by the cast concrete, the concrete corresponding to the surplus portion 5' can be filled and filled into the gap generated in the lifted trace. Provide as much as possible (amount). In this case, when the surplus portion 5 'flows into and fills the gap, it is not preferable that the top end surface is significantly higher than the top end surface 6 of the planned pile, and therefore, the top end surface is the same or slightly lower. The height (amount) of the extra portion 5 'is set in.

この余盛り部分5'の形成後、上述したようにケーシング2をその下端が計画杭の天端面6に達するまで引き上げてその引き上げにより生じた隙間に余盛り部分5'に相当するコンクリートを流入、充填させ(図4(ロ)参照)、計画杭の天端面6よりも上方に残った余盛り部分5'' を上記バキュームホース12によって吸引除去して打設コンクリート5の天端面5aを計画杭の天端面6に合わす。このバキュームホース12による2回目の吸引除去作業は、打設コンクリート5の天端面5aを計画杭の天端面6に正確に合致させるためであり、これによって杭天端の仕上げを行うものである。しかるのち、こうして造成された杭の杭頭Aの天端面A1の均し作業を行って杭頭部の仕上げを行う(図5参照)。なお、ケーシング2の引き上げによって余盛り部分5'が上記隙間内に流入、充填し、その天端面が計画杭の天端面6に一致した場合には、バキュームホース12による吸引除去は当然のことながら必要としない。   After the formation of the surplus portion 5 ′, as described above, the casing 2 is pulled up until the lower end reaches the top end surface 6 of the planned pile, and the concrete corresponding to the surplus portion 5 ′ flows into the gap generated by the lifting, Filled (see Fig. 4 (b)), the vacuum hose 12 sucks and removes the surplus portion 5 "remaining above the top end surface 6 of the planned pile, and the top end surface 5a of the cast concrete 5 is planned Align with the top face 6 of The second suction and removal operation by the vacuum hose 12 is for precisely matching the top end surface 5a of the cast concrete 5 with the top end surface 6 of the planned pile, thereby finishing the pile top end. After that, the pile head is finished by leveling the top end surface A1 of the pile head A of the pile thus created (see FIG. 5). In addition, when the surplus portion 5 ′ flows and fills into the gap by lifting the casing 2, and the top end face coincides with the top end face 6 of the planned pile, the suction hose removal with the vacuum hose 12 is natural. do not need.

ここで、本発明方法を採用して打設コンクリート5の天端面5a上のスライム14や該スライム等の不純物を混在したコンクリート部分15を除去したのち、上記余盛り部分5'の高さがケーシング2を引き上げた後においても80cmとなるように打設したことによって造成された杭において、該杭の中心部と外周部の複数個所における、杭頭から天端面以下80cmの深さまでのコア供試体(直径が10cm)を採取して圧縮強度試験を行い、品質の低下している範囲や高さ方向の強度の違いを確認したところ、図6に示すような結果が得られた。   Here, after adopting the method of the present invention to remove the slime 14 on the top end surface 5a of the cast concrete 5 and the concrete portion 15 mixed with impurities such as the slime, the height of the surplus portion 5 ′ is the casing. In piles constructed by placing them so as to be 80 cm even after pulling up 2, the core specimen from the pile head to a depth of 80 cm below the top end surface at the center and outer periphery of the pile A sample having a diameter of 10 cm was sampled and subjected to a compressive strength test to confirm the range in which the quality was deteriorated and the difference in strength in the height direction. The results shown in FIG. 6 were obtained.

この図6から明らかなように、杭天端より下方は勿論のこと、余盛り部分においても設計基準強度以上の強度を発現していることが理解できる。即ち、余盛り部分5'においてもスライムや不純物の混在するコンクリートがなくなっていることを示している。従って、該余盛り部分5'は上述したようにケーシング2の抜き取り跡の隙間を充足できる高さ(量)であればよい。   As is apparent from FIG. 6, it can be understood that the strength beyond the design reference strength is expressed not only below the pile top end but also in the extra portion. That is, it is shown that there is no concrete mixed with slime and impurities even in the extra portion 5 ′. Therefore, the surplus portion 5 ′ may be a height (amount) that can satisfy the clearance of the extracted trace of the casing 2 as described above.

上記のようにしてコンクリート杭を造成したのち、杭頭Aから上方の一定長さだけ引き上げられているケーシング2内に図7(イ)に示すように、砕石7を鉄筋籠3の上端に達するまで投入すると共に同図(ロ)に示すようにケーシング2を引き抜いて撤去し、同図(ハ)に示すように地表面まで土砂等の埋め戻し作業を行う。こうして、杭造成作業が全て終了したのち、杭周囲を掘削して杭の上部に建物の基礎を築造する前に、杭天端を高圧ジェット又はチッピング処理して、打設コンクリート5の硬化段階で発生するブリーディングを除去する。   After building the concrete pile as described above, the crushed stone 7 reaches the upper end of the reinforcing bar 3 as shown in FIG. And the casing 2 is pulled out and removed as shown in FIG. 5B, and backfilling work such as earth and sand is performed up to the ground surface as shown in FIG. Thus, after all the pile building work is finished, before excavating around the pile and building the foundation of the building on the top of the pile, the top of the pile is subjected to high-pressure jet or chipping treatment, and occurs in the hardening stage of the cast concrete 5 Remove bleeding.

なお、以上の実施の形態においては、杭孔1内にコンクリート5を打設するためのトレミー管4を杭断面の中央部、即ち、杭孔1の中心部に挿入している場合について説明したが、このトレミー管4の挿入位置を杭孔1の一側壁面側に片寄らせた状態でコンクリート5の打設を行ってもよく、この場合には、コンクリート5は天端面においてトレミー管4の周囲で盛り上がりながら杭孔1の他側壁面側に向かって流れ、スライム等の不純物もコンクリートと共に他側壁面側に流れてその部分に集中的に滞留することになる。従って、バキュームホース12をケーシング2の内周壁面に沿って周方向に移動させることなく、他側壁面側に配設しておくことにより、スライム等の不純物の吸引除去を効果的に行うことができる。また、上記実施の形態においては、スライム14やコンクリート15を除去する手段としてバキュームによる吸引除去について説明したが、除去手段をそれに限らず、バケット等による汲み取り手段、掬い取り手段を採用してもよい。   In addition, in the above embodiment, the case where the tremy tube 4 for placing concrete 5 in the pile hole 1 was inserted in the center part of the pile cross section, that is, the center part of the pile hole 1 was described. However, the concrete 5 may be placed in a state where the insertion position of the tremy tube 4 is shifted to the one side wall surface side of the pile hole 1, and in this case, the concrete 5 is placed on the top end surface of the tremy tube 4. Flowing toward the other side wall surface side of the pile hole 1 while rising around the periphery, impurities such as slime also flow to the other side wall surface side together with the concrete, and concentrate in that portion. Therefore, by removing the vacuum hose 12 on the other side wall surface side without moving in the circumferential direction along the inner peripheral wall surface of the casing 2, it is possible to effectively remove and remove impurities such as slime. it can. Further, in the above embodiment, suction removal by vacuum is described as means for removing slime 14 and concrete 15, but the removal means is not limited thereto, and pumping means and scooping means by a bucket or the like may be adopted. .

杭孔の掘削からコンクリートの打設までの施工手順を示す簡略縦断面図。The simplified longitudinal cross-sectional view which shows the construction procedure from excavation of a pile hole to concrete placement. 安定液を除去している状態の天端部分の縦断面図。The longitudinal cross-sectional view of the top end part in the state which has removed the stabilizer. スライム等の不純物を吸引除去している状態の天端部分の縦断面図。The longitudinal cross-sectional view of the top end part in the state which removes impurities, such as slime, by suction. (イ)はコンクリートの打設終了時の天端部分を、(ロ)はケーシングの引き上げによって降下した余盛り部分を示す縦断面図。(A) is a longitudinal cross-sectional view showing a top end portion at the end of concrete pouring, and (b) is a vertical cross-sectional view showing a surplus portion lowered by raising the casing. 杭頭部の仕上げを行った状態の縦断面図。The longitudinal cross-sectional view of the state which finished the pile head. 余盛り部分から杭天端下方部分に至る深さ方向の強度分布状態を示す線図。The diagram which shows the intensity distribution state of the depth direction from a surplus part to a pile top end lower part. 杭造成後の処理工程を示す簡略縦断面図。The simplified longitudinal cross-sectional view which shows the process after a pile creation. バキュームホースの吸引口の形状を示す簡略縦断面図。The simplified longitudinal cross-sectional view which shows the shape of the suction opening of a vacuum hose.

符号の説明Explanation of symbols

1 杭孔
2 ケーシング
4 トレミー管
5 打設コンクリート
5a その天端面
5' 余盛り部分
6 計画杭の天端面
12 バキュームホース
13 安定液
14 スライム
1 Pile hole 2 Casing 4 Tremy pipe 5 Casting concrete
5a The top edge
5 'Extra portion 6 Top edge of the planned pile
12 Vacuum hose
13 Stabilizer
14 Slime

Claims (3)

地盤の表層部にケーシングを、その下端部が計画杭の天端面よりも下方に位置するまで建て込んだのち、該ケーシング内から下方の地盤を所定深さまで安定液を満たしながら杭孔を掘削し、次いで、この杭孔内にコンクリートをケーシング内における該ケーシングの下端部から計画杭の天端面部分に達する間の高さ位置まで打設したのち、該打設コンクリート天端面上の安定液とスライム及び該スライム等の不純物が混在するコンクリート部分を除去し、しかるのち、計画杭の天端面より所定高さ高い位置に達するまでコンクリートを打設して余盛り部分を形成し、次いで、ケーシングを上昇させて打設コンクリートの天端面を計画杭の天端面の高さに合わすことを特徴とする場所打ちコンクリート杭の造成方法。 After building the casing on the surface layer of the ground until its lower end is located below the top end face of the planned pile , drill the pile hole while filling the ground below the casing to the specified depth from the inside of the casing. Then, after placing concrete in the pile hole up to a height position between the bottom end of the casing and the top end surface of the planned pile in the casing, the stabilizing liquid and slime on the top end surface of the cast concrete are placed. And the concrete part mixed with impurities such as the slime is removed, and then the concrete is cast to reach a position higher than the top end face of the planned pile to form a surplus part, and then the casing is raised A cast- in-place concrete pile construction method characterized in that the top end surface of the cast concrete is matched with the height of the top end surface of the planned pile . スライム等の不純物が混在するコンクリート部分の除去を、コンクリート天端にコンクリートの骨材が多く視認できるまで行うことを特徴とする請求項1に記載の場所打ちコンクリート杭の造成方法。 The method for constructing a cast-in-place concrete pile according to claim 1, wherein the concrete part mixed with impurities such as slime is removed until a large amount of concrete aggregate is visible at the top of the concrete. バキュームホースを杭孔内に建て込んでいる鉄筋籠とケーシングの内周壁面との間の隙間に挿入して不純物が混在するコンクリート部分の除去を行うことを特徴とする請求項1又は請求項2に記載の場所打ちコンクリート杭の造成方法。 Claim, characterized in that the removal of the insert into the gap concrete portions which impurities are mixed between the reinforcing bar cage and the inner peripheral wall surface of the casing that is built up a vacuum hose to the Kuiana 1 or claim 2 A method for constructing cast-in-place concrete piles as described in 1.
JP2004092396A 2004-03-26 2004-03-26 Construction method of cast-in-place concrete pile Expired - Lifetime JP4327639B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004092396A JP4327639B2 (en) 2004-03-26 2004-03-26 Construction method of cast-in-place concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004092396A JP4327639B2 (en) 2004-03-26 2004-03-26 Construction method of cast-in-place concrete pile

Publications (2)

Publication Number Publication Date
JP2005273412A JP2005273412A (en) 2005-10-06
JP4327639B2 true JP4327639B2 (en) 2009-09-09

Family

ID=35173373

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004092396A Expired - Lifetime JP4327639B2 (en) 2004-03-26 2004-03-26 Construction method of cast-in-place concrete pile

Country Status (1)

Country Link
JP (1) JP4327639B2 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4705663B2 (en) * 2008-05-27 2011-06-22 株式会社サンエイ Attachment for vacuum hose and pile head processing method using this attachment for vacuum hose
CN103485343B (en) * 2013-09-03 2015-10-21 深圳市金世纪工程实业有限公司 Filling pile head processing method
JP6470671B2 (en) * 2015-10-23 2019-02-13 鹿島建設株式会社 Tremy tube structure and pile construction method
CN105780762B (en) * 2016-03-09 2020-06-05 宇杰集团股份有限公司 Construction method for chiseling-free pile head
CN112030647A (en) * 2020-03-04 2020-12-04 河北鸿森公路工程技术有限公司 Repairing construction process for road of filling and digging boundary roadbed road section
CN112942324B (en) * 2021-01-29 2022-05-17 中建七局第二建筑有限公司 Auxiliary tool for building construction and use method thereof
CN113266004B (en) * 2021-06-30 2023-12-19 武汉城建建设工程有限公司 Device and method for pouring bridge underwater cast-in-place pile
CN114000500A (en) * 2021-11-16 2022-02-01 中铁十二局集团有限公司 Construction method for steel casing follow-up method of plateau composite geological bridge pile foundation

Also Published As

Publication number Publication date
JP2005273412A (en) 2005-10-06

Similar Documents

Publication Publication Date Title
CN109440762B (en) Construction method of filling pile for drainage pump station
JP4327638B2 (en) Construction method of cast-in-place concrete pile
JP4327639B2 (en) Construction method of cast-in-place concrete pile
KR100880439B1 (en) Apparatus and method for removing slime in a cast-in place pile construstion
CN110144887A (en) Vast sky stake bored pile construction method
KR100699359B1 (en) Underground diaphragm wall with post-tensioning equipment and construction method the same
KR100628511B1 (en) External reinforcement reverse circulation drill method
JP6645098B2 (en) Removal method of existing pile
JP2007224657A (en) Cast-in-place concrete pile construction method
JP4903016B2 (en) Improvement method of slime remaining in cast-in-place concrete pile.
KR100944284B1 (en) Pile construction methode for minimizing remaining volume of slime
JP3878772B2 (en) Construction method of cast-in-place concrete pile to put long steel frame
JP2640841B2 (en) Slime treatment method in cast-in-place pile method
JP7255072B2 (en) Infiltration well repair method
JP3913503B2 (en) Pile head treatment method for cast-in-place concrete piles
JP6634251B2 (en) Pile foundation structure, ready-made pile burying device, method of constructing pile foundation structure using said ready-made pile burying device
CN110872837B (en) Construction method for transforming empty pile section of rotary excavating cast-in-place pile into dewatering well
JP2006322190A (en) Pile head processing method of cast-in-place concrete pile and concrete processing agent mixing device
JP6116619B2 (en) Pile head processing equipment
JP2004263559A (en) Method for treating pile head of cast-in-place concrete pile
JP4137173B1 (en) Reinforcing bar construction in cast-in-place pile
JP2000273900A (en) Air suction type soil discharge device and construction method
JPH08209687A (en) Partial casing pile construction method
JP2004257065A (en) Pile head processing method for cast-in-place concrete pile and partition frame used therefor
JP4091939B2 (en) Pile head treatment method for cast-in-place concrete piles

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060908

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080312

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080507

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080703

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090512

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090611

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120619

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4327639

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150619

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250