JP4903016B2 - Improvement method of slime remaining in cast-in-place concrete pile. - Google Patents

Improvement method of slime remaining in cast-in-place concrete pile. Download PDF

Info

Publication number
JP4903016B2
JP4903016B2 JP2006168434A JP2006168434A JP4903016B2 JP 4903016 B2 JP4903016 B2 JP 4903016B2 JP 2006168434 A JP2006168434 A JP 2006168434A JP 2006168434 A JP2006168434 A JP 2006168434A JP 4903016 B2 JP4903016 B2 JP 4903016B2
Authority
JP
Japan
Prior art keywords
slime
pile hole
pile
tip
injected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2006168434A
Other languages
Japanese (ja)
Other versions
JP2007332722A (en
Inventor
伸一郎 野澤
明之 渡邊
敬一 西脇
貴史 玄順
精亮 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East Japan Railway Co
Original Assignee
East Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East Japan Railway Co filed Critical East Japan Railway Co
Priority to JP2006168434A priority Critical patent/JP4903016B2/en
Publication of JP2007332722A publication Critical patent/JP2007332722A/en
Application granted granted Critical
Publication of JP4903016B2 publication Critical patent/JP4903016B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Description

本発明は、場所打ちコンクリート杭の杭孔先端に残留するスライムの改良工法に関する。   The present invention relates to an improved construction method for slime remaining at a pile hole tip of a cast-in-place concrete pile.

場所打ちコンクリート杭は、地盤に掘削された杭孔に鉄筋籠を挿入し、次いで該杭孔にコンクリートを打設して形成される杭の総称である。場所打ちコンクリート杭の形成方法としては、アースドリル工法、リバースサーキュレーション工法、深礎工法が開発されている。これらの工法において、掘削土砂の搬出、掘削機の冷却、地下水等の噴出防止、孔壁の崩壊防止等のため、ベントナイト泥水等の安定液を孔内に満たして掘削作業を実施している。そのため杭孔の掘削後、杭孔底部に残留するスライム処理が実施されるが、残留するスライムを完全に除去するのは困難である。このように杭孔の底部にスライムが残存した状態でコンクリートを打設すると、杭先端の支持力度が低下し、打ち込み杭に比べて設計上の支持力が得られず、構造物が沈下するという問題が発生する。   A cast-in-place concrete pile is a general term for a pile formed by inserting a reinforcing bar into a pile hole excavated in the ground and then placing concrete in the pile hole. As methods for forming cast-in-place concrete piles, the earth drill method, reverse circulation method, and deep foundation method have been developed. In these methods, excavation work is carried out by filling the hole with a stable liquid such as bentonite mud water in order to carry out excavated earth and sand, cool the excavator, prevent ejection of groundwater, etc., and prevent collapse of the hole wall. Therefore, after excavation of the pile hole, slime treatment remaining at the bottom of the pile hole is carried out, but it is difficult to completely remove the remaining slime. In this way, when concrete is placed with the slime remaining at the bottom of the pile hole, the support strength at the tip of the pile is reduced, the design support force is not obtained compared to the driven pile, and the structure sinks. A problem occurs.

このような問題を解決するために、特開平10−131187号公報には、杭孔掘削後に固化材を封入したカプセルを杭孔に投入し、カプセルを衝撃等により破壊し、固化材を杭孔の底部に流出させ、杭孔の底部に残存するスライムと固化材を攪拌翼で攪拌混合して固化させる場所打ちコンクリート杭のスライム処理方法が開示されている。
特開平10−131187号公報
In order to solve such a problem, Japanese Patent Laid-Open No. 10-131187 discloses a capsule filled with a solidified material after excavation of a pile hole, destroys the capsule by impact or the like, and the solidified material is piled up in the pile hole. A cast-in-place concrete pile slime treatment method is disclosed in which the slime and the solidified material remaining in the bottom of the pile hole are mixed by agitating blades and solidified by agitation.
JP-A-10-131187

しかしながら、従来の杭孔の底部に残存するスライムと固化材を攪拌混合するスライム処理方法では、攪拌翼等の攪拌部材を必要とし、スライムの成分によっては固化材と攪拌混合して固化させても十分な支持強度を得ることができないという問題が発生する。   However, in the conventional slime treatment method of stirring and mixing the slime remaining in the bottom of the pile hole and the solidified material, a stirring member such as a stirring blade is required, and depending on the components of the slime, the solidified material may be stirred and mixed to be solidified. There arises a problem that sufficient support strength cannot be obtained.

本発明は、従来の杭孔に残存するスライム処理方法の持つ課題を解決する、攪拌翼等の機材を用いることなく、かつ、杭孔に残存するスライムの成分の相違にも関わらず、固化材の注入で杭先端の支持力度強度を得ることができる簡易な場所打ちコンクリート杭に残留するスライム改良工法を提供することを目的とする。   The present invention solves the problems of the conventional slime treatment method remaining in the pile hole, without using equipment such as a stirring blade, and despite the difference in the components of the slime remaining in the pile hole, the solidified material It aims at providing the slime improvement method which remains in the simple cast-in-place concrete pile which can obtain the bearing strength degree strength of a pile tip by pouring.

本発明の場所打ちコンクリート杭に残留するスライム改良工法は、前記課題を解決するために、地盤中に掘削された杭孔に固化材注入管を固定した鉄筋籠を挿入し、杭孔にコンクリートを打設する前或いはコンクリート打設後に前記固化材注入管から杭孔先端に固化材を注入し、注入する固化材の密度を杭孔の先端に残存するスライムの密度より大きくし、杭孔の先端に残存するスライムと注入される固化材とを置換し固化させることを特徴とする。 In order to solve the above-mentioned problem , the slime improvement method remaining on the cast-in-place concrete pile of the present invention inserts a reinforcing bar with a solidifying material injection pipe fixed into the pile hole excavated in the ground, and puts the concrete into the pile hole. Before or after pouring the concrete, the solidification material is injected from the solidification material injection pipe to the tip of the pile hole, the density of the solidification material to be injected is made larger than the density of the slime remaining at the tip of the pile hole, and the tip of the pile hole And the solidified material to be injected is replaced and solidified.

また、本発明の場所打ちコンクリート杭に残留するスライム改良工法は、地盤中に掘削された杭孔に固化材注入管を固定した鉄筋籠を挿入し、杭孔にコンクリートを打設する前或いはコンクリート打設後に前記固化材注入管から杭孔先端に固化材を注入し、杭孔先端に残存するスライムが粒径の大きな砂分を含む砂質土スライムの場合、注入する固化材の粒径を砂分の粒径より小さくし、スライム中の砂分を残し、砂分の周囲に存在する粒径の小さいスライムおよび水を押し出し固化材と置換させ、砂分の粒子間を固化材で固結させることを特徴とする。 In addition, the slime improvement method remaining in the cast-in-place concrete pile of the present invention is to insert a reinforcing bar with a solidifying material injection pipe fixed into the pile hole excavated in the ground, before placing concrete in the pile hole or in the concrete. After casting, the solidifying material is injected from the solidifying material injection pipe to the tip of the pile hole, and when the slime remaining at the tip of the pile hole is sandy soil slime containing sand having a large particle size, the particle size of the solidifying material to be injected is set. Smaller than the particle size of the sand, leaving the sand in the slime, extruding the small particle of slime and water around the sand and replacing it with the solidified material, and solidifying the sand particles with the solidified material. It is characterized by making it.

また、本発明の場所打ちコンクリート杭に残留するスライム改良工法は、前記鉄筋籠にスライム排出管を配置することを特徴とする。 Moreover, the slime improvement construction method remaining on the cast-in-place concrete pile of the present invention is characterized in that a slime discharge pipe is disposed on the reinforcing bar.

また、本発明の場所打ちコンクリート杭に残留するスライム改良工法は、杭孔先端に注入する固化材を、杭孔先端のスライム残留部分の上部、下部若しくは中部から加圧注入することを特徴とする。 The slime improvement method remaining in the cast-in-place concrete pile of the present invention is characterized in that the solidified material to be injected into the tip of the pile hole is injected under pressure from the upper, lower or middle portion of the remaining portion of the slime at the tip of the pile hole. .

また、本発明の場所打ちコンクリート杭に残留するスライム改良工法は、杭孔先端に注入する固化材のホモゲル強度を杭の支持力度以上とすることを特徴とする。 Moreover, the slime improvement method which remains in the cast-in-place concrete pile of this invention is characterized by making the homogel strength of the solidification material inject | poured into a pile-hole tip more than the supporting force degree of a pile.

また、本発明の場所打ちコンクリート杭に残留するスライム改良工法は、杭孔先端に注入する固化材に周囲地盤に固化材が浸透するのを抑制し、また、注入圧力で地盤を割裂破壊した割れ目に固化材が流入することを抑制する目地詰め材を混入することを特徴とする。 In addition, the slime improvement method remaining in the cast-in-place concrete pile of the present invention suppresses the penetration of the solidified material into the surrounding ground into the solidified material injected into the tip of the pile hole, and also cracks that fracture and break the ground with the injection pressure. It is characterized in that a joint filling material for suppressing the inflow of the solidifying material is mixed.

場所打ちコンクリート杭に残留するスライム改良工法において、地盤中に掘削された杭孔に固化材注入管を固定した鉄筋籠を挿入し、杭孔にコンクリートを打設する前或いはコンクリート打設後に前記固化材注入管から杭孔先端に固化材を注入し、注入する固化材の密度を杭孔の先端に残存するスライムの密度より大きくし、杭孔の先端に残存するスライムと注入される固化材とを置換し固化させる構成により、スライムを上方向に押しだし、スライムと注入固化材との置換を促進し、簡易な方法で杭先端の支持力を確保できる。
地盤中に掘削された杭孔に固化材注入管を固定した鉄筋籠を挿入し、杭孔にコンクリートを打設する前或いはコンクリート打設後に前記固化材注入管から杭孔先端に固化材を注入し、杭孔先端に残存するスライムが粒径の大きな砂分を含む砂質土スライムの場合、注入する固化材の粒径を砂分の粒径より小さくし、スライム中の砂分を残し、砂分の周囲に存在する粒径の小さいスライムおよび水を押し出し固化材と置換させ、砂分の粒子間を固化材で固結させる構成により、砂分を残し、他の粒径の小さいスライムのみを押し出して固化材と置換するので杭先端の支持力を確保することができる。
鉄筋籠の先端近傍にスライム排出管を配置する構成により、注入固化材の注入により押し出されるスライムを効率良く排出でき、スライムと注入固化材の置換を促進することができる。
杭孔先端に注入する固化材を、杭孔先端のスライム残留部分の上部、下部若しくは中部から加圧注入する構成により、スライムを上方向に押しだし、スライムと注入固化材との置換を促進することができる。
杭孔先端に注入する固化材のホモゲル強度を杭の支持力度以上とする構成により、固化材単体で固化しても杭支持力を得ることができる 。
杭孔先端に注入する固化材に周囲地盤に固化材が浸透するのを抑制し、また、注入圧力で地盤を割裂破壊した割れ目に固化材が流入することを抑制する目地詰め材を混入する構成により、注入固化材が周囲地盤に漏出するのを防止できるので、注入固化材の無駄を防止でき、改良効率を高めることができる。
In the slime improvement method remaining in the cast-in-place concrete pile, the solidification rod is inserted into the pile hole excavated in the ground, and the solidification is performed before or after placing concrete in the pile hole. Inject solidification material from the material injection pipe to the tip of the pile hole, make the density of the solidification material to be injected larger than the density of the slime remaining at the tip of the pile hole, and the slime remaining at the tip of the pile hole and the solidification material to be injected By replacing and solidifying the structure, the slime is pushed upward, the replacement of the slime with the injected solidified material is promoted, and the supporting force of the pile tip can be secured by a simple method.
Insert a reinforcing rod with a solidification material injection pipe fixed into the pile hole excavated in the ground, and inject the solidification material from the solidification material injection pipe to the tip of the pile hole before or after placing concrete in the pile hole. When the slime remaining at the tip of the pile hole is sandy soil slime containing sand with a large particle size, the particle size of the solidified material to be injected is made smaller than the particle size of the sand, leaving the sand in the slime, The slime and water with a small particle size around the sand are replaced with the solidified material by extruding, and the sand particles are solidified with the solidified material, leaving the sand and only other slime with a small particle size. Since it extrudes and replaces it with the solidified material, it is possible to secure the supporting force of the pile tip.
By arranging the slime discharge pipe in the vicinity of the tip of the reinforcing bar, the slime pushed out by the injection of the injected solidifying material can be efficiently discharged, and the replacement of the slime with the injected solidified material can be promoted.
By pushing the solidified material injected into the pile hole tip under pressure from the upper, lower or middle part of the slime residue at the pile hole tip, the slime is pushed upward to promote the replacement of the slime with the injected solidified material. Can do.
With a configuration in which the homogel strength of the solidified material injected into the pile hole tip is equal to or higher than the support strength of the pile, the pile support strength can be obtained even if the solidified material is solidified alone.
A composition that mixes the solidified material injected into the tip of the pile hole with the filling material that suppresses the penetration of the solidified material into the surrounding ground, and suppresses the inflow of the solidified material into the cracks that split and break the ground with the injection pressure. Thus, the injection solidified material can be prevented from leaking to the surrounding ground, so that the waste of the injection solidified material can be prevented and the improvement efficiency can be increased.

本発明の場所打ちコンクリート杭に残留するスライム改良工法の実施の形態を図により説明する。図1は、本発明の場所打ちコンクリート杭に残留するスライム改良工法の実施の形態の概要図である。   An embodiment of a slime improving method remaining in a cast-in-place concrete pile according to the present invention will be described with reference to the drawings. FIG. 1 is a schematic diagram of an embodiment of a slime improving method remaining in a cast-in-place concrete pile of the present invention.

地盤中に杭孔1を、アースドリル工法、リバースサーキュレーション工法、深礎工法等により形成する。杭孔1を形成するにあたって、掘削土砂の搬出、掘削機の冷却、地下水等の噴出防止、孔壁の崩壊防止等のため、ベントナイト泥水等の安定液2を孔内に満たして掘削作業を実施している。杭孔形成後の杭孔1の底部3には、掘削土の細粒分が安定液と懸濁したスライム4が沈殿する。スライム4の成分としては、掘削する地盤に応じて粘土質のものや、砂質のもの等様々である。しかし、スライムの4の性質がどのようなものであれ、杭孔1の底部3に沈殿したスライム4を処理しないで杭孔にコンクリートを打設した場合、杭支持力が十分に得ることができず、構造物の沈下を招くことになる。   The pile hole 1 is formed in the ground by an earth drill method, a reverse circulation method, a deep foundation method, or the like. When forming the pile hole 1, excavation work is carried out by filling the hole with a stable liquid 2 such as bentonite mud water to carry out excavated earth and sand, cool the excavator, prevent ejection of groundwater, etc., and prevent collapse of the hole wall. is doing. On the bottom 3 of the pile hole 1 after the formation of the pile hole, a slime 4 in which fine particles of excavated soil are suspended in a stable liquid is precipitated. As a component of the slime 4, there are various types such as clay and sand according to the ground to be excavated. However, whatever the nature of the slime 4 is, if the concrete is placed in the pile hole without treating the slime 4 settled on the bottom 3 of the pile hole 1, the pile supporting force can be sufficiently obtained. Therefore, the structure will sink.

そのため、本発明の場所打ちコンクリート杭に残留するスライム改良工法では、先ず、杭孔1に固化材注入管5を固定した鉄筋籠6を挿入する。固化材注入管5の数は、杭孔1の底部のスライム4の残留量に応じて1〜3、4本とする。固化材注入管5の先端部5’は、杭孔1の底部のスライム4の沈殿部に位置にするように配置する。固化材注入管5の先端5’は、スライム4の性状に応じて単管あるいはストレーナ管とする。杭孔1にコンクリートを打設する前或いはコンクリート打設後に、地表に設置した注入ポンプ7から固化材を杭孔1の底部に沈殿するスライム4中に注入する。固化材としては、微粒子セメントミルク、水中不分離性セメントミルク、水中不分離性モルタル等を用いる。   Therefore, in the slime improvement method remaining on the cast-in-place concrete pile of the present invention, first, the reinforcing bar 6 with the solidifying material injection pipe 5 fixed to the pile hole 1 is inserted. The number of the solidification material injection pipes 5 is 1 to 3 and 4 according to the residual amount of the slime 4 at the bottom of the pile hole 1. The distal end portion 5 ′ of the solidifying material injection pipe 5 is arranged so as to be located at the sedimentation portion of the slime 4 at the bottom of the pile hole 1. The tip 5 ′ of the solidifying material injection pipe 5 is a single pipe or a strainer pipe depending on the properties of the slime 4. Before or after placing concrete in the pile hole 1, the solidification material is injected into the slime 4 that settles at the bottom of the pile hole 1 from the injection pump 7 installed on the ground surface. As the solidifying material, fine particle cement milk, underwater inseparable cement milk, underwater inseparable mortar, or the like is used.

スライム4中に注入される固化材は、スライム4と混合するのではなく、沈殿するスライム4と置換するように注入される。そのため、スライム4の性状が粘土質の場合、注入する固化材の密度をスライム4の密度より大きくし、スライム4中に注入される固化材がスライム4を上方に押し上げ、スライム4が沈殿していた部分が固化材により置換されるようにする。上方に押し上げられたスライム4を排出するために鉄筋籠6にスライム排出管8を設置する。スライム4と固化材との置換を促進するために固化材の粘度、注入速度、注入圧力等を調節する。杭孔1の底部のスライム4と置換される固化材は、固化材単独で固化するので、固化材のホモゲル強度を杭支持力以上とするのが望ましい。また、杭孔1の底部に注入される固化材が杭孔1の底部周囲の土壌中に浸透し無駄になるのを防止し、改良効率を高めるため、固化材中に流動性を阻害せず単位体積重量が固化材と同程度かそれ以下の目地詰め材を混合しておくのが好ましい。   The solidified material injected into the slime 4 is not mixed with the slime 4 but injected to replace the precipitated slime 4. Therefore, when the property of the slime 4 is clayey, the density of the solidified material to be injected is made larger than the density of the slime 4, the solidified material injected into the slime 4 pushes the slime 4 upward, and the slime 4 is precipitated. The part is replaced with solidifying material. In order to discharge the slime 4 pushed upward, a slime discharge pipe 8 is installed in the reinforcing bar 6. In order to promote the replacement of the slime 4 with the solidified material, the viscosity, injection speed, injection pressure, etc. of the solidified material are adjusted. Since the solidified material to be replaced with the slime 4 at the bottom of the pile hole 1 is solidified by the solidified material alone, it is desirable that the homogel strength of the solidified material be equal to or higher than the pile supporting force. Moreover, in order to prevent the solidified material injected into the bottom of the pile hole 1 from penetrating into the soil around the bottom of the pile hole 1 and wasting waste, and improving the improvement efficiency, the fluidity is not hindered in the solidified material. It is preferable to mix joint fillers having a unit volume weight of the same level as or lower than that of the solidified material.

スライム4中に粒径の大きい砂分が多く存在する場合、スライム中に注入される固化材により粒径の大きな砂分を含むスライム4全体を置換するのは困難である。そのため、スライム4中に注入される固化材として、超微粒子セメントのセメントミルクを用い、スライム4中の粒径の大きな砂分の周囲に存在する粒径の小さなスライム分および水のみを固化材により押しだして置換する。押し出された粒径の小さいスライム4はスライム排出管8により排出される。砂分のまわりに固化材が満たされ砂分粒子同士は固結される。スライム4中に粒径の大きい砂分が多く存在する場合の固化材注入管5の先端部5’としては、単管よりストレーナ管の方が好ましい。   When there is a large amount of sand having a large particle size in the slime 4, it is difficult to replace the entire slime 4 including the sand having a large particle size by the solidified material injected into the slime. Therefore, the cement milk of ultrafine cement is used as the solidifying material injected into the slime 4, and only the slime component having a small particle size and water existing around the sand component having a large particle size in the slime 4 are solidified. Push to replace. The extruded slime 4 having a small particle diameter is discharged through a slime discharge pipe 8. The solidified material is filled around the sand and the sand particles are consolidated. As the tip portion 5 ′ of the solidifying material injection pipe 5 when a large amount of sand having a large particle size is present in the slime 4, a strainer pipe is preferable to a single pipe.

(実施例)
本発明の場所打ちコンクリート杭に残留するスライム改良工法を検証することを目的に次のような注入試験を実施した。
図2(a)(b)は、本試験に用いた試験装置を示す。図2(a)に示す試験装置は、ケース内の土壌中に杭孔の先端形状に模して形状を作成し、土壌の表面に注入材の浸透を抑制する不織布を配置し、杭孔形状の底部にスライム排出管を設置し、注入管としてストレーナ管を用いた。図2(b)に示す試験装置は、ケース内の土壌中に杭孔の先端形状に模して形状を作成し、土壌の表面に固化材の浸透を抑制する不織布を配置し、杭孔形状の底部のスライム残留部の直上にスライム排出管を設置し、注入管として単管を用いた。
(Example)
In order to verify the slime improvement method remaining in the cast-in-place concrete pile of the present invention, the following injection test was conducted.
2 (a) and 2 (b) show a test apparatus used for the test. The test device shown in FIG. 2 (a) creates a shape that mimics the shape of the tip of a pile hole in the soil in the case, and disposes a nonwoven fabric that suppresses the penetration of the injection material on the surface of the soil. A slime discharge pipe was installed at the bottom of the tube, and a strainer pipe was used as the injection pipe. The test apparatus shown in FIG. 2 (b) creates a shape that mimics the shape of the tip of the pile hole in the soil in the case, and disposes a nonwoven fabric that suppresses the penetration of the solidifying material on the surface of the soil. A slime discharge pipe was installed immediately above the slime residue part at the bottom of the tube, and a single pipe was used as the injection pipe.

図2(a)(b)に示される試験装置に、次の表1に示されるスライムの組成材料および注入材のパラメータをケース1〜ケース3として模擬スライムを充填して試験を実施した。   Tests were carried out by filling the test apparatus shown in FIGS. 2 (a) and 2 (b) with simulated slime using the slime composition material and the injection material parameters shown in Table 1 as cases 1 to 3.

Figure 0004903016
Figure 0004903016

図2(a)に示す試験装置で、ケース1のパラメータの模擬スライムおよび注入材の試験を実施し、図2(b)に示す試験装置で、ケース2、3のパラメータの模擬スライムおよび注入材の試験を実施した。注入速度は、5.0リットル/minで行った。注入量は、ケース1では、浸透注入による土粒子間の間隙容積である約91リットルとし、ケース2、3では全置換を目指してスライムの全容積である約155リットルとした。スライム処理状態は、所定の注入量を注入した後、直ちに試験装置の蓋を解体し目視で観察した。なお、ケース1では、図3(a)(b)に示す位置で供試体を採取し、JIS A1108「モルタルの圧縮強度試験方法」に準拠して一軸圧縮強度を材齢28日に測定した。   The test apparatus shown in FIG. 2A performs the test of the simulated slime and injection material of the parameters of case 1, and the test apparatus of FIG. 2B uses the simulated slime and injection material of the parameters of cases 2 and 3. The test was conducted. The injection rate was 5.0 liter / min. In the case 1, the injection volume was about 91 liters, which is the gap volume between the soil particles by osmotic injection, and in cases 2 and 3, the total volume of slime was about 155 liters aiming at total replacement. In the slime treatment state, after injecting a predetermined injection amount, the lid of the test apparatus was immediately disassembled and visually observed. In Case 1, specimens were collected at the positions shown in FIGS. 3A and 3B, and the uniaxial compressive strength was measured on the 28th day of the age in accordance with JIS A1108 “Compressive strength test method for mortar”.

(試験結果)
1.ケース1
注入後の断面状況は、上面では、間隙の水の中に僅かに注入材が溶けているような状態であった。しかし、深さ30cmになると注入材が全面に浸透し、深さ50cmおよび65cmでは、上方に比べてセメント濃度の高い注入材が土粒子間に浸透している状況が観察された。図3(a)(b)に示される位置で採取した強度試験用の供試体の外観は、断面1では、中央部の供試体3、4は固化したものの、断面の外側に位置する供試体1、2、5および6は固化せず、ばらばらに崩れる状態であった。しかし、断面2、断面3および断面4では、すべての供試体が完全に固化し表面も頑固な状態であった。一軸試験の結果を表2に示す。
(Test results)
1. Case 1
The cross-sectional condition after the injection was such that the injected material was slightly dissolved in the water in the gap on the upper surface. However, when the depth reached 30 cm, the injected material penetrated the entire surface, and at depths of 50 cm and 65 cm, the situation was observed where the injected material having a higher cement concentration than the upper portion penetrated between the soil particles. The external appearance of the specimen for strength test collected at the position shown in FIGS. 3 (a) and 3 (b) shows that in the cross section 1, the specimens 3 and 4 in the center are solidified, but the specimen is located outside the cross section. 1, 2, 5 and 6 were not solidified and were broken apart. However, in cross section 2, cross section 3 and cross section 4, all specimens were completely solidified and the surface was also stubborn. Table 2 shows the results of the uniaxial test.

Figure 0004903016
Figure 0004903016

表2に示される強度試験の結果、断面2〜4では、9.91〜19.2N/mm2の範囲となり高い強度を有していることが確認された。この結果、上方の一部を除いて、注入材が土粒子間に浸透し、砂質土スライムが注入材によって改良されたと判断される。 As a result of the strength test shown in Table 2, it was confirmed that the cross sections 2 to 4 had a high strength in the range of 9.91 to 19.2 N / mm 2 . As a result, except for the upper part, it is determined that the injecting material penetrates between the soil particles, and the sandy soil slime is improved by the injecting material.

2.ケース2
ケース2では、注入量が10リットル程度になった時点で、スライム排出管から注入材が漏出するのが確認され、その後は注入を終了するまでの間、注入材のみがスライム排出管から漏出する状況が続いた。注入後の断面形状は、上面では、注入材とスライムは、混合されず完全に分かれて存在していた。深さ10cmと20cmでも同様な状態であり、深さ40cm以深では注入材が全く存在しなかった。この結果、注入材は単管の注入口から下向きに吐出されるものの、密度および粘性の影響により上向きの流路を形成し、スライム排出管から漏出される状態になったと考えられる。
2. Case 2
In case 2, it is confirmed that the injection material leaks from the slime discharge pipe when the injection amount reaches about 10 liters, and thereafter, only the injection material leaks from the slime discharge pipe until the injection is finished. The situation continued. As for the cross-sectional shape after the injection, the injection material and the slime were not mixed but existed completely on the upper surface. The same condition was obtained at depths of 10 cm and 20 cm, and no injection material was present at a depth of 40 cm or more. As a result, although the injection material was discharged downward from the injection port of the single pipe, it is considered that the upward flow path was formed by the influence of density and viscosity, and the injection material was leaked from the slime discharge pipe.

3.ケース3
ケース2と同様に、上面より深さ20cmまでは、スライム排出管に向かう流路のみに注入材が存在していた。しかし、深さ40cmでは、スライムが注入材によってほぼ置換されていることが確認された。さらに、深さ65cmでは、内壁に僅かにスライムが付着している程度で、スライムが注入材によって完全に置換されている状況が観察された。これらの結果により、本発明の場所打ちコンクリート杭に残留するスライム改良工法によって粘性土スライムを改良するには、スライムに比べて密度の大きい注入材を用いること、また、注入過程で上方に向かう流路が形成されないように、注入材の粘性を設定する必要があると考えられる。
3. Case 3
Similar to Case 2, up to a depth of 20 cm from the upper surface, the injection material was present only in the flow path toward the slime discharge pipe. However, at a depth of 40 cm, it was confirmed that the slime was almost replaced by the injection material. Furthermore, at a depth of 65 cm, it was observed that the slime was completely replaced by the injection material with a slight amount of slime adhering to the inner wall. Based on these results, in order to improve the clay clay slime by the slime improvement method remaining in the cast-in-place concrete pile of the present invention, it is necessary to use an injection material having a density higher than that of the slime. It is considered necessary to set the viscosity of the injection material so that no path is formed.

これらの試験により、スライムの粒度組成により注入材および注入方法を選定することにより、杭孔先端に残留するスライムの改良が簡易に行えることが明らかになった。   These tests revealed that the slime remaining at the tip of the pile hole can be easily improved by selecting the injection material and the injection method according to the particle size composition of the slime.

本発明の実施の形態を示す図である。It is a figure which shows embodiment of this invention. (a)(b)本発明の効果を証明するための試験装置を示す図である。(A) (b) It is a figure which shows the test apparatus for demonstrating the effect of this invention. (a)(b)本発明の効果を示す供試体の採取一を示す図である。(A) (b) It is a figure which shows one collection of the test body which shows the effect of this invention.

符号の説明Explanation of symbols

1:杭孔、2:安定液、3:杭孔の底部、4:スライム、5:固化材注入管、5’:固化材注入管の先端部、6:鉄筋籠、7:注入ポンプ、8:スライム排出管   1: Pile hole, 2: Stabilizing liquid, 3: Bottom part of pile hole, 4: Slime, 5: Solidified material injection pipe, 5 ′: Tip of solidified material injection pipe, 6: Rebar rod, 7: Injection pump, 8 : Slime discharge pipe

Claims (6)

地盤中に掘削された杭孔に固化材注入管を固定した鉄筋籠を挿入し、杭孔にコンクリートを打設する前或いはコンクリート打設後に前記固化材注入管から杭孔先端に固化材を注入し、注入する固化材の密度を杭孔の先端に残存するスライムの密度より大きくし、杭孔の先端に残存するスライムと注入される固化材とを置換し固化させることを特徴とする場所打ちコンクリート杭に残留するスライム改良工法。 Insert a reinforcing rod with a solidification material injection pipe fixed into the pile hole excavated in the ground, and inject the solidification material from the solidification material injection pipe to the tip of the pile hole before or after placing concrete in the pile hole. And the density of the solidified material to be injected is larger than the density of the slime remaining at the tip of the pile hole, and the slime remaining at the tip of the pile hole is replaced with the solidified material to be injected and solidified. Improvement method of slime remaining on concrete piles. 地盤中に掘削された杭孔に固化材注入管を固定した鉄筋籠を挿入し、杭孔にコンクリートを打設する前或いはコンクリート打設後に前記固化材注入管から杭孔先端に固化材を注入し、杭孔先端に残存するスライムが粒径の大きな砂分を含む砂質土スライムの場合、注入する固化材の粒径を砂分の粒径より小さくし、スライム中の砂分を残し、砂分の周囲に存在する粒径の小さいスライムおよび水を押し出し固化材と置換させ、砂分の粒子間を固化材で固結させることを特徴とする場所打ちコンクリート杭に残留するスライム改良工法。 Insert a reinforcing rod with a solidification material injection pipe fixed into the pile hole excavated in the ground, and inject the solidification material from the solidification material injection pipe to the tip of the pile hole before or after placing concrete in the pile hole. When the slime remaining at the tip of the pile hole is sandy soil slime containing sand with a large particle size, the particle size of the solidified material to be injected is made smaller than the particle size of the sand, leaving the sand in the slime, A slime improvement method that remains in cast-in-place concrete piles, characterized in that slime and water with a small particle size existing around sand are replaced with extruded solidified material, and the particles of sand are consolidated with solidified material. 前記鉄筋籠にスライム排出管を配置することを特徴とする請求項1又は2に記載の場所打ちコンクリート杭に残留するスライム改良工法。 The slime improvement pipe | tube which remains on the cast-in-place concrete pile of Claim 1 or 2 characterized by arrange | positioning a slime discharge pipe to the said reinforcing bar. 杭孔先端に注入する固化材を、杭孔先端のスライム残留部分の上部、下部若しくは中部から加圧注入することを特徴とする請求項1〜3のいずれか1項に記載の場所打ちコンクリート杭に残留するスライム改良工法。 The cast-in-place concrete pile according to any one of claims 1 to 3 , wherein the solidified material to be injected into the tip of the pile hole is injected under pressure from the upper part, the lower part, or the middle part of the slime remaining part at the tip of the pile hole. Improvement method of slime remaining in the sea. 杭孔先端に注入する固化材のホモゲル強度を杭の支持力度以上とすることを特徴とする請求項1〜4のいずれか1項に記載の場所打ちコンクリート杭に残留するスライム改良工法。 The slime improvement method which remains in the cast-in-place concrete pile according to any one of claims 1 to 4 , wherein the homogel strength of the solidified material injected into the pile hole tip is equal to or higher than the support capacity of the pile. 杭孔先端に注入する固化材に周囲地盤に固化材が浸透するのを抑制し、また、注入圧力で地盤を割裂破壊した割れ目に固化材が流入することを抑制する目地詰め材を混入することを特徴とする請求項1〜5のいずれか1項に記載の場所打ちコンクリート杭に残留するスライム改良工法。 Incorporate joint filling material that suppresses the penetration of the solidified material into the surrounding ground into the solidified material injected into the tip of the pile hole, and suppresses the flow of the solidified material into the cracks that split and break the ground with the injection pressure. The slime improvement construction method which remains in the cast-in-place concrete pile of any one of Claims 1-5 characterized by these.
JP2006168434A 2006-06-19 2006-06-19 Improvement method of slime remaining in cast-in-place concrete pile. Active JP4903016B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006168434A JP4903016B2 (en) 2006-06-19 2006-06-19 Improvement method of slime remaining in cast-in-place concrete pile.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006168434A JP4903016B2 (en) 2006-06-19 2006-06-19 Improvement method of slime remaining in cast-in-place concrete pile.

Publications (2)

Publication Number Publication Date
JP2007332722A JP2007332722A (en) 2007-12-27
JP4903016B2 true JP4903016B2 (en) 2012-03-21

Family

ID=38932453

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006168434A Active JP4903016B2 (en) 2006-06-19 2006-06-19 Improvement method of slime remaining in cast-in-place concrete pile.

Country Status (1)

Country Link
JP (1) JP4903016B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5922960B2 (en) * 2012-03-16 2016-05-24 東日本旅客鉄道株式会社 Method for constructing cast-in-place piles and manufacturing method for cast-in-place piles
JP5973931B2 (en) * 2013-02-15 2016-08-23 鹿島建設株式会社 Construction method of high bearing capacity pile
CN103195064B (en) * 2013-04-10 2015-04-29 中铁大桥局集团第一工程有限公司 Grouting processing method for stopping water leakage of underwater concrete
CN108086325A (en) * 2018-01-26 2018-05-29 中国建筑第八工程局有限公司 Grouting Pipe and its construction method in pile foundation construction

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5918489B2 (en) * 1980-08-15 1984-04-27 三井建設株式会社 Slime processing method in stable liquid drilling method
JPS59206518A (en) * 1983-05-11 1984-11-22 Japanese National Railways<Jnr> Strengthening method of on-site concrete pile
JP3615073B2 (en) * 1999-01-22 2005-01-26 東日本旅客鉄道株式会社 On-site concrete pile construction method

Also Published As

Publication number Publication date
JP2007332722A (en) 2007-12-27

Similar Documents

Publication Publication Date Title
JP5302726B2 (en) Construction method of foundation pile, construction method of cement milk column
JP4903016B2 (en) Improvement method of slime remaining in cast-in-place concrete pile.
JP2008075266A (en) Method of constructing pile
JP5478386B2 (en) Improving method for ground with underground cavity
JP2008088746A (en) Replacing construction method of column
JP4905394B2 (en) Excavator
Ibragimov Characteristics of Soil Grouting by Hydro-Jet Technology.
JP4327638B2 (en) Construction method of cast-in-place concrete pile
KR101066587B1 (en) Construction method of inner filling structure using liquid ultrahigh viscosity and flowable grout material
JP5543628B2 (en) Cement milk solidification strength judgment method, foundation pile construction method, cement milk column construction method, sampling device
JP2012057407A (en) Slurry recycling method
JP6645098B2 (en) Removal method of existing pile
JP2004332431A (en) Method for constructing soil-cement composite pile
JP5055974B2 (en) Construction method of underground structure, ground excavation equipment
JP2021080789A (en) Ground backfilling method, and stirring blade
JP5317938B2 (en) Construction method of soil cement pillar and soil cement continuous wall
JP2008025330A (en) Construction method of impervious wall
JP6847176B1 (en) Pile construction method
JP3682554B2 (en) Underwater filling method
JP3874734B2 (en) Impermeable wall construction method
JP6854475B2 (en) Strength management method for solidified muddy water
JPS5820819A (en) Method and apparatus for injecting grout into ground
US11884860B2 (en) Fluidized sand and method of density control
JP2011184915A (en) Aseismatic reinforcing method for existing revetment
JP2008063916A (en) Ground improvement construction method and ground improvement device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090518

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20101129

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20111019

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20111118

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20111228

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120104

R150 Certificate of patent or registration of utility model

Ref document number: 4903016

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150113

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250