JP4286265B2 - Temporary branch line extension method and temporary branch line retention tool in branch-type steel tower - Google Patents

Temporary branch line extension method and temporary branch line retention tool in branch-type steel tower Download PDF

Info

Publication number
JP4286265B2
JP4286265B2 JP2006093163A JP2006093163A JP4286265B2 JP 4286265 B2 JP4286265 B2 JP 4286265B2 JP 2006093163 A JP2006093163 A JP 2006093163A JP 2006093163 A JP2006093163 A JP 2006093163A JP 4286265 B2 JP4286265 B2 JP 4286265B2
Authority
JP
Japan
Prior art keywords
branch line
temporary
main
branch
attached
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2006093163A
Other languages
Japanese (ja)
Other versions
JP2007262860A (en
Inventor
和紀 野崎
俊郎 下東
茂 小谷
好弘 坂本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Denki Kogyo Co Ltd
Original Assignee
Denki Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Denki Kogyo Co Ltd filed Critical Denki Kogyo Co Ltd
Priority to JP2006093163A priority Critical patent/JP4286265B2/en
Publication of JP2007262860A publication Critical patent/JP2007262860A/en
Application granted granted Critical
Publication of JP4286265B2 publication Critical patent/JP4286265B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Description

本発明は、支線式鉄塔における仮支線の展張方法および仮支線引留用治工具に関する。   The present invention relates to a method for extending a temporary branch line in a branch-type steel tower and a jig for temporary branch line retention.

超長波送信用支線式鉄塔は、図8に示すように、鉄塔(本柱)100の周囲に、鉄塔100の頂部から順次一定間隔を置いて下方向にずらせた位置に、それぞれ3方向に展張する本支線(ロープ)101の一端部を取付け、これら本支線101の他端部を地面に引き留めるように構成されている。これらの本支線101の途中には、本支線101を流れる電流を絶縁する碍子装置102が介在されている。そして、3方向に展張する本支線(ロープ)101は、頂部から一定間隔で約4〜7段に亘って設けられている。   As shown in FIG. 8, the super-long-wave transmission branch towers are extended in three directions around the tower (main pillar) 100 at positions shifted downward from the top of the tower 100 in order at a certain interval. One end of the main branch line (rope) 101 is attached, and the other end of the main branch line 101 is secured to the ground. In the middle of the main branch line 101, an insulator device 102 for insulating a current flowing through the main branch line 101 is interposed. And the main branch line (rope) 101 extended in three directions is provided over about 4-7 steps | paragraphs from the top part with the fixed space | interval.

このような超長波送信用支線式鉄塔などでは、経年変化に伴って本支線交換および本支線を流れる電流を絶縁する碍子装置102の交換が必要である。そして、本支線101の交換および碍子装置102の交換に際して、図9に示すように、一時的に本支線101の取り外しを行い、あるいは交換する際に同一方向に当該本支線101の張力と同等の張力を確保するため、複数本の仮支線103が展張される。   In such a long-wave transmission branch tower, etc., it is necessary to replace the main line and the insulator device 102 that insulates the current flowing through the main line with the passage of time. When exchanging the main branch line 101 and the lever device 102, as shown in FIG. 9, the main branch line 101 is temporarily removed or replaced with the same tension as the main branch line 101 in the same direction. In order to ensure tension, a plurality of temporary branch lines 103 are extended.

この仮支線103を展張するために、図10および図11に示すような仮支線引留用治工具104が用いられている。この仮支線引留用治工具104は、通常、交換対象の本支線101の上部側の支柱100aに取付けられて用いられている。
この仮支線引留用治工具104は、略コ字状の仮支線アーム105の両端部と中間部に、固定具106が装着されており、この固定具106を鉄塔100の各支柱100aに固定して仮支線引留用治工具104を取付けている。そして、仮支線引留用治工具104の中間部のアーム105aの両端部の仮支線取付具107に仮支線103を1方向のみに展張して本支線101の張力を保ち、本支線101の交換、あるいは碍子装置102の交換を行っている。
特開平8−222923号公報 特開2003−9325号公報
In order to extend this temporary branch line 103, a temporary branch line retaining jig 104 as shown in FIGS. 10 and 11 is used. The temporary branch line retaining jig 104 is usually used by being attached to the upper column 100a of the main branch line 101 to be replaced.
The temporary branch line holding jig 104 has fixing tools 106 attached to both ends and an intermediate part of a substantially U-shaped temporary branch line arm 105, and the fixing tool 106 is fixed to each column 100 a of the tower 100. A temporary branch line retaining jig 104 is attached. Then, the temporary branch line 103 is stretched in only one direction on the temporary branch line attachments 107 at both ends of the intermediate arm 105a of the temporary branch line holding jig 104 to maintain the tension of the main branch line 101, and the main branch line 101 is replaced. Alternatively, the lever device 102 is replaced.
JP-A-8-222923 JP 2003-9325 A

しかしながら、前記先行技術によれば、仮支線引留用治工具104取付け位置の上部側には、空中線として利用する本支線101が展張されているため、数箇所の支線工事を同時に行う際に、本支線101と仮支線103が接触してしまい送信障害を引き起こす虞がある。また、仮支線引留用治工具104は、一方向の仮支線103のみに適用する構造であるため、他の方向の本支線101を同時に交換することはできなかった。そして、鉄塔100を垂直に支持するために本支線101が1鉄塔あたり12本から21本使用されている。これら本支線101は自然環境及び経年劣化等により、本支線101を構成する素線の断線等が予想されることから、本支線101の交換が必要となる。   However, according to the prior art, since the main branch line 101 used as an aerial line is extended on the upper side of the temporary branch line retaining jig 104 mounting position, the main branch line 101 used as an aerial line is extended. There is a possibility that the branch line 101 and the temporary branch line 103 come into contact with each other and cause a transmission failure. Further, since the temporary branch line holding jig 104 has a structure that is applied only to the temporary branch line 103 in one direction, the main branch line 101 in the other direction cannot be replaced at the same time. In order to support the steel tower 100 vertically, 12 to 21 main branch lines 101 are used per steel tower. Since these branch lines 101 are expected to break the strands of the main branch line 101 due to the natural environment and deterioration over time, the main branch line 101 needs to be replaced.

本発明は、上記課題を解決し、交換作業に際して本支線と仮支線の接触を防ぎ、かつ複数方向の交換作業を同時に行うことができる支線式鉄塔における仮支線の展張方法および仮支線引留用治工具を提供することを目的とする。   The present invention solves the above-described problems, prevents the contact between the main branch line and the temporary branch line during the replacement work, and simultaneously extends the temporary branch line in the branch-type steel tower capable of performing the replacement work in a plurality of directions, and the temporary branch line retention treatment. The purpose is to provide a tool.

本発明は、上記課題を解決するため、三角形の各頂点に本支柱が配置されるように構成され、かつ前記各本支柱から上下方向に複数段に亘って外方に展張された本支線により支持された支線式鉄塔における前記本支線および/または支線碍子を交換するために仮支線を展張する支線式鉄塔における仮支線の展張方法において、三角形を構成するように配置されたアームの各頂点に、前記本支柱を把持する把持具を取付けた仮支線引留用治工具を、前記把持具を介して前記支線式鉄塔の交換対象の本支線取付部近傍の支柱に取付け、前記各本支線の張力を保持する仮支線を交換対象の本支線および/または支線碍子が取り付けられた本支線の両側の支柱に取付けた前記把持具から、交換対象の本支線および/または支線碍子が取り付けられた本支線と平面視で同方向および側面視で略同方向に張力が近似するように展張して、交換対象の本支線および/または交換対象の支線碍子が取り付けられた本支線の張力を保持した状態で、交換作業を行うことにある。
また、本発明は、前記仮支線引留用治工具を、三角形を構成するように配置されたアームの各頂点に、前記本支柱を把持する把持具を取付けた上下複数段の治工具で構成し、これら上下複数段の治工具から上下複数段の仮支線を展張することにある。
さらに、本発明は、前記仮支線を各把持具から鉄塔の外側を通して交換対象の本支線および/または支線碍子が取り付けられた本支線と平面視で略平行に展張することで仮支線と交換対象の本支線および/または支線碍子が取り付けられた本支線の接触防止をすることにある。
またさらに、本発明は、三角形の各頂点に本支柱が配置されるように構成され、かつ前記各本支柱から上下方向に複数段に亘って外方に展張された本支線により支持された支線式鉄塔における前記本支線および/または支線碍子を交換するために仮支線を展張するための仮支線引留用治工具において、三角形を構成するように配置されたアームの各頂点に、前記本支柱を把持する把持具を装着し、これら把持具に、仮支線を展張する仮支線取付プレートを装着したことにある。
また、本発明は、前記本支柱を把持する把持具を二分割に構成するとともに、これら把持具の半割り部分をそれぞれ互いに隣り合うアームの先端部に装着し、これら半割り部分を互いに締結して前記本支柱に把持具を装着し、これら把持具に、隣り合う支柱に取付けられた本支線と同方向に向けて仮支線を展張する仮支線取付プレートを装着したことにある。
さらに、本発明は、前記三角形を構成するように配置されたアームの各頂点に、前記本支柱を把持する把持具を装着し、これら把持具に仮支線を展張する仮支線取付プレートを装着した上下複数段の治工具で構成したことにある。
In order to solve the above-mentioned problem, the present invention is configured such that a main support column is arranged at each vertex of a triangle, and a main branch line is extended outward from the main support column in multiple directions. In the method of extending a temporary branch line in a branch-type steel tower that extends the temporary branch line in order to replace the main branch line and / or the branch line insulator in the supported branch-line tower, at each vertex of the arm arranged to form a triangle The temporary branch line retaining jig attached with a gripping tool for gripping the main support is attached to the support in the vicinity of the main branch mounting part to be replaced of the branch tower via the gripping tool, and the tension of each main support line The main branch line to which the main branch line and / or branch insulator to be replaced is attached from the gripper attached to the support pillars on both sides of the main branch line and / or main branch line to which the temporary branch line is held. In a plan view and deployed as tension substantially in the same direction in the same direction and the side view is approximated, in a state where the branch line and / or branch line insulator to be replaced to be replaced holds the present branch line tension mounted, It is to perform exchange work.
In the present invention, the temporary branch line holding tool is constituted by a plurality of upper and lower stages of jigs in which a gripping tool for holding the main column is attached to each vertex of an arm arranged to form a triangle. Then, the temporary support lines of the upper and lower stages are extended from the upper and lower stages of jigs.
Furthermore, the present invention, the exchange and temporary branch tentative branch substantially be deployed in parallel with the branch line in plan view the branch line and / or branch line insulators is attached to be replaced through the outer tower from the gripper target The main branch line and / or the main branch line to which the branch line insulator is attached is prevented .
Still further, the present invention is configured such that a main column is arranged at each apex of a triangle, and a branch line supported by a main branch line that is extended outward from the main column in a plurality of vertical directions. In the temporary branch line holding jig for extending the temporary branch line in order to replace the main branch line and / or branch line insulator in the steel tower, the main column is placed at each vertex of the arm arranged to form a triangle. The gripping tool to be gripped is mounted, and the temporary support line mounting plate for extending the temporary support line is mounted to these gripping tools.
Further, the present invention is configured in such a manner that the gripping tool for gripping the main column is divided into two parts, and the halved portions of the gripping tools are respectively attached to the distal ends of the arms adjacent to each other, and the halved parts are fastened to each other. Thus, a gripping tool is attached to the main support column, and a temporary branch line mounting plate for extending the temporary support line in the same direction as the main support line attached to the adjacent support column is mounted on the gripping tool.
Further, in the present invention, a gripping tool for gripping the main column is attached to each apex of the arms arranged so as to constitute the triangle, and a temporary support line mounting plate for extending the temporary support line is attached to the gripping tool. It is composed of jigs with multiple upper and lower stages.

請求項1によれば、本支線から離れた位置から仮支線を展張することができるので、交換作業に際して本支線と仮支線の接触を防ぎ、送信障害を防止することができる。
請求項2によれば、支線径に応じて、支線径が太い場合は、上段、下段合わせて複数条の仮支線を使用し、支線径が細い場合は、下段のみ2条の仮支線の使用で施工することができる。
請求項3によれば、本支線から最も離れた位置に仮支線を展張することができるので、交換作業に際して本支線と仮支線の接触を防ぎ、送信障害を防止することができる。
請求項4によれば、本支線から離れた位置で、かつ本支線の下方側に仮支線を展張することができるので、交換作業に際して本支線と仮支線の接触を防ぎ、送信障害を防止することができる。また、仮支線引留用治工具を三角形に構成したので、三方向の本支線および支線碍子を同時に交換することができる。
請求項5によれば、仮支線引留用治工具は、各アームごとに分離できるので、組付けおよび搬送作業を容易に行うことができる。
請求項6によれば、仮支線引留用治工具は、上下複数段のアームで構成されていることから、本支線の太さに応じて仮支線の本数を2条、或いはそれ以上の複数条に設定することができる。
According to the first aspect, since the temporary branch line can be extended from a position away from the main branch line, the contact between the main branch line and the temporary branch line can be prevented at the time of replacement work, and transmission failure can be prevented.
According to claim 2, depending on the branch diameter, when the branch diameter is thick, the upper, by using the temporary branch of plural rows in accordance with the lower, when the branch diameter is thin, lower only tentative branch of Article 2 Can be constructed by use.
According to the third aspect, since the temporary branch line can be extended to the position farthest from the main branch line, the contact between the main branch line and the temporary branch line can be prevented during the replacement work, and the transmission failure can be prevented.
According to the fourth aspect, since the temporary branch line can be extended at a position away from the main branch line and below the main branch line, contact between the main branch line and the temporary branch line can be prevented during replacement work, and transmission failure can be prevented. be able to. Moreover, since the temporary branch line retaining jig is configured in a triangular shape, the main branch line and the branch line insulator in three directions can be exchanged at the same time.
According to the fifth aspect, since the temporary branch line holding jig can be separated for each arm, the assembly and the transport work can be easily performed.
According to claim 6, since the temporary branch line holding tool is composed of upper and lower arms, the number of temporary branch lines is two or more depending on the thickness of the main branch line. Can be set to

以下図示の実施の形態を図面を参照しながら詳細に説明する。   The embodiments shown in the drawings will be described in detail below with reference to the drawings.

図1は、超長波送信用支線式鉄塔に仮支線引留用治工具を装着した概念図で、図2は図1のA−A線断面図である。
図1および図2において、支線式鉄塔1は、3方向支線式鋼管トラス柱で、三角形の頂点に配置して立設した3本の各本支柱2を多数の連結材3で連結したものである。各本支柱2には、上下方向に沿って、一定間隔で、複数段の本支線4が平面視で、支線式鉄塔1を中心として3方向に放射状に、かつ、斜め下方向に向けて展張されている。本支線4の途中には、それぞれ大地と絶縁するための碍子装置(図示せず)が装着されている。
FIG. 1 is a conceptual diagram in which a temporary branch line holding tool is mounted on a branch tower for transmitting ultra-long waves, and FIG. 2 is a cross-sectional view taken along line AA in FIG.
1 and 2, a branch-type tower 1 is a three-way branch-type steel pipe truss column, which is formed by connecting three main columns 2 arranged upright at the apex of a triangle with a large number of connecting members 3. is there. Each main support column 2 is extended in a vertical direction at regular intervals, with a plurality of main branch lines 4 extending in a radial direction in three directions around the branch-type tower 1 in a plan view and obliquely downward. Has been. In the middle of the main branch line 4, an insulator device (not shown) for insulating from the ground is mounted.

仮支線引留用治工具10は、環状の把持具11を構成する半割り状のバンド11aをそれぞれ両端に装着した3本のアーム12を、半割り状のバンド11a相互を両端のフランジ部をボルトを介して締結して、三角形を構成するように組み立てたものである。図3および図5は上部側の環状の把持具11を示したもので、図4および図6は、下部側の環状の把持具11を示したものである。
この把持具11の半割り状のバンド11aには、水平のプレート13が装着されており、このプレート13の裏面には、間に配置された本支柱2に取付けられた本支線4と同方向に向けて垂設された一対の仮支線取付プレート14がそれぞれ装着されている。仮支線取付プレート14には、仮支線15を保持する取付穴16が設けられている。
The temporary branch line retaining tool 10 includes three arms 12 each having a half-shaped band 11a constituting an annular gripper 11 attached to both ends, and the half-shaped band 11a is bolted to the flanges at both ends. And are assembled so as to form a triangle. 3 and 5 show the upper annular gripping tool 11, and FIGS. 4 and 6 show the lower annular gripping tool 11.
A horizontal plate 13 is attached to the half-shaped band 11a of the gripping tool 11, and the back surface of the plate 13 is in the same direction as the main branch line 4 attached to the main column 2 disposed therebetween. A pair of provisional branch line attachment plates 14 that are vertically suspended are mounted respectively. The temporary branch line mounting plate 14 is provided with a mounting hole 16 for holding the temporary branch line 15.

上記半割り状のバンド11aをそれぞれ両端に装着した3本のアーム12は、垂直方向の連結部材17と、斜め方向の連結部材18によって、上下のアーム12相互間を互いに連結されて上下二段に構成されており、上下二段のアーム12の仮支線取付プレート14からそれぞれ仮支線15が展張できるように構成されている。   The three arms 12 mounted with the half-shaped band 11a on both ends are connected to each other between the upper and lower arms 12 by a vertical connecting member 17 and an oblique connecting member 18, respectively. The temporary branch lines 15 can be extended from the temporary branch line mounting plates 14 of the upper and lower two-stage arms 12.

次に、上記仮支線引留用治工具10を用いて仮支線を展張する方法を説明すると、3本の各本支柱2を把持するようにして半割り状のバンド11aを取り付け、この半割り状のバンド11aの両側のフランジ部11bをボルトおよびナットを介して互いに締結する。こうしてアーム12の両側の半割り状のバンド11aを隣のアーム12の半割り状のバンド11aと互いに締結することで、アーム12が三角形を構成するように配置される。上下二段のアーム12をそれぞれ半割り状のバンド11aを介して各本支柱2に装着する。 Next, a method for extending a temporary branch line using the temporary branch line holding jig 10 will be described. A half band 11a is attached so as to hold each of the three main struts 2, and this half line shape is attached. The flange portions 11b on both sides of the band 11a are fastened to each other via bolts and nuts. In this way, the halved bands 11a on both sides of the arm 12 are fastened together with the halved bands 11a of the adjacent arms 12, so that the arms 12 are arranged to form a triangle. The upper and lower two-stage arms 12 are respectively attached to the main columns 2 via the half-shaped bands 11a.

そして、図7(a)(b)に示すように、仮支線取付プレート14の取付穴16に仮支線15の一端を装着し、交換用本支線4が取付けられた本支柱2の両側の本支柱2に取付けられた把持具11の仮支線取付プレート14から交換用本支線4に沿って平面視で交換用本支線4と同方向に略平行に、かつ側面視で、交換用本支線4の下部側を略平行に斜め下方向に引き下ろす。仮支線15は、それぞれ1本の交換用本支線4に対して上下のアーム12の仮支線取付プレート14から4本または2本をそれぞれ三方の交換用本支線4ごとに引き降ろす。   Then, as shown in FIGS. 7A and 7B, one end of the temporary branch line 15 is mounted in the mounting hole 16 of the temporary branch line mounting plate 14, and the book on both sides of the main column 2 to which the replacement main branch line 4 is mounted. The replacement main branch line 4 is substantially parallel to the replacement main branch line 4 in a plan view along the replacement main branch line 4 from the temporary branch line mounting plate 14 of the gripper 11 attached to the support column 2 and in a side view. Pull the lower side of the slant downward in a substantially parallel manner. The temporary branch lines 15 are pulled down from the temporary branch line mounting plates 14 of the upper and lower arms 12 with respect to one replacement main branch line 4 for each of the three main replacement branch lines 4 respectively.

このように、三方の交換用本支線4あるいは交換用本支線4に接続された碍子装置を同時に交換することができるので、作業性が良好である。仮支線15は、平面視で交換用本支線4からの距離を最大限に大きくとることができるので、本支線4との距離を充分にとることができることから、本支線4との干渉を防ぐことができる。   In this way, since the three main replacement branch lines 4 or the lever device connected to the replacement main branch line 4 can be replaced at the same time, workability is good. Since the temporary branch line 15 can take the maximum distance from the replacement main branch line 4 in plan view, the temporary branch line 15 can have a sufficient distance from the main branch line 4, thereby preventing interference with the main branch line 4. be able to.

また、交換用本支線4の両側の後方から仮支線15を展張するので、交換用本支線4と上下方向の距離を大きく取ることができるので、空中線として利用されている交換用本支線4Aと接触する虞がない(図7(b)参照)。   In addition, since the temporary branch line 15 is extended from the rear of both sides of the replacement main branch line 4, a distance in the vertical direction from the replacement main branch line 4 can be increased, so that the replacement main branch line 4A used as an aerial line There is no risk of contact (see FIG. 7B).

こうして、上記仮支線引留用治工具10を上下方向に順次移動させながら、三方の交換用本支線4の交換および碍子装置の交換を行うことができる。   In this way, it is possible to replace the three-way replacement main branch line 4 and the lever device while sequentially moving the temporary branch line retaining jig 10 in the vertical direction.

なお、本発明は、上記実施の形態のみに限定されるものではなく、例えば、仮支線引留用治工具10は、上下二段に構成したが二段以上の複数段に構成することもできるなど、その他本発明の要旨を変更しない範囲内で適宜変更して実施し得ることは言うまでもない。   In addition, this invention is not limited only to the said embodiment, For example, although the temporary branch line holding jig 10 was comprised in the upper and lower two stages, it can also be comprised in two or more stages. Needless to say, the present invention can be appropriately modified and implemented without departing from the scope of the present invention.

本発明の実施の形態による支線式鉄塔における仮支線引留用治工具を示す概念図である。It is a conceptual diagram which shows the jig for temporary branch line retention in the branch type steel tower by embodiment of this invention. 図1の仮支線引留用治工具を示すA−A線矢視図である。It is an AA arrow directional view which shows the temporary branch line holding jig of FIG. 図2のB部拡大図である。It is the B section enlarged view of FIG. 図2のB部下段側の拡大図である。FIG. 3 is an enlarged view of the lower part of section B in FIG. 2. 図3のC−C線矢視図である。FIG. 4 is a view taken along the line CC in FIG. 3. 図4のD−D線矢視図である。FIG. 6 is a view taken along line DD in FIG. 4. 仮支線の展張方法を示し、(a)は平面図、(b)は(a)の側面図である。The method of extending a temporary branch line is shown, (a) is a plan view, (b) is a side view of (a). 支線式鉄塔を示す概念図である。It is a conceptual diagram which shows a branch line type steel tower. 支線式鉄塔における本支線の交換作業を示す概念図である。It is a key map showing exchange work of this branch line in a branch line type tower. 従来の支線式鉄塔における仮支線引留用治工具を示す概念図である。It is a conceptual diagram which shows the jig for temporary branch line retention in the conventional branch line type steel tower. 図10の仮支線引留用治工具を示す平面図である。It is a top view which shows the temporary branch line holding jig of FIG. 従来の仮支線の展張方法を示し、(a)は平面図、(b)は(a)の側面図である。The conventional temporary branch line extending method is shown, (a) is a plan view, (b) is a side view of (a).

符号の説明Explanation of symbols

1 支線式鉄塔
2 本支柱
3 連結材
4 本支線
10 仮支線引留用治工具
11 把持具
11a 半割り状のバンド
12 アーム
13 プレート
14 仮支線取付プレート
15 仮支線
16 取付穴
17,18 連結部材
DESCRIPTION OF SYMBOLS 1 Branch line type steel tower 2 Two support | pillars 3 Connecting material 4 Branch line 10 Temporary branch line retention jig 11 Grasping tool 11a Half-divided band 12 Arm 13 Plate 14 Temporary branch line mounting plate 15 Temporary branch line 16 Mounting hole 17, 18 Connecting member

Claims (6)

三角形の各頂点に本支柱が配置されるように構成され、かつ前記各本支柱から上下方向に複数段に亘って外方に展張された本支線により支持された支線式鉄塔における前記本支線および/または支線碍子を交換するために仮支線を展張する支線式鉄塔における仮支線の展張方法において、三角形を構成するように配置されたアームの各頂点に、前記本支柱を把持する把持具を取付けた仮支線引留用治工具を、前記把持具を介して前記支線式鉄塔の交換対象の本支線取付部近傍の支柱に取付け、前記各本支線の張力を保持する仮支線を交換対象の本支線および/または支線碍子が取り付けられた本支線の両側の支柱に取付けた前記把持具から、交換対象の本支線および/または支線碍子が取り付けられた本支線と平面視で同方向および側面視で略同方向に張力が近似するように展張して、交換対象の本支線および/または交換対象の支線碍子が取り付けられた本支線の張力を保持することを特徴とする支線式鉄塔における仮支線の展張方法。 The main branch line in the branch-type steel tower is configured so that the main pillar is arranged at each vertex of the triangle and supported by the main branch line that is extended outward from the main pillars in a plurality of vertical directions. In a method for extending temporary branch lines in a branch-line tower that extends temporary branch lines to replace branch line insulators, a gripping tool for holding the main column is attached to each vertex of the arm arranged to form a triangle. The temporary branch line holding jig is attached to the support column in the vicinity of the main branch attachment part to be replaced of the branch-type tower via the gripping tool, and the temporary branch line holding the tension of each main branch line is replaced with the main branch line to be replaced. From the gripping tool attached to the pillars on both sides of the main branch to which the branch line insulator is attached, the main branch line to be replaced and / or the main branch line to which the branch line insulator is attached are substantially the same in the same direction and side view. same And stretched so tension approximates countercurrent, temporary branch line stretched method in branch line type tower, characterized in that to hold the present branch line and / or replacement the branch line of tension branch insulator is attached to the object to be replaced . 前記仮支線引留用治工具を、三角形を構成するように配置されたアームの各頂点に、前記本支柱を把持する把持具を取付けた上下複数段の治工具で構成し、これら上下複数段の治工具から上下複数段の仮支線を展張することを特徴とする請求項1に記載の支線式鉄塔における仮支線の展張方法。 The temporary branch line holding tool is composed of a plurality of upper and lower stages of jigs each having a gripping tool for gripping the main column attached to each vertex of an arm arranged to form a triangle. The method of extending a temporary branch line in a branch-type steel tower according to claim 1, wherein a plurality of temporary branch lines are extended from a jig and tool. 前記仮支線を各把持具から鉄塔の外側を通して交換対象の本支線および/または支線碍子が取り付けられた本支線と平面視で略平行に展張することで仮支線と交換対象の本支線および/または支線碍子が取り付けられた本支線の接触防止を特徴とする請求項1または2に記載の支線式鉄塔における仮支線の展張方法。 The temporary branch line and the main branch line to be replaced and / or the main branch line to be replaced and / or the main branch line to be replaced through the outside of the steel tower and the main branch line to which the branch insulator is attached are extended in parallel in plan view. The method of extending a temporary branch line in a branch-type steel tower according to claim 1 or 2, wherein contact with the main branch line to which a branch line insulator is attached is prevented . 三角形の各頂点に本支柱が配置されるように構成され、かつ前記各本支柱から上下方向に複数段に亘って外方に展張された本支線により支持された支線式鉄塔における前記本支線および/または支線碍子を交換するために仮支線を展張するための仮支線引留用治工具において、三角形を構成するように配置されたアームの各頂点に、前記本支柱を把持する把持具を装着し、これら把持具に、仮支線を展張する仮支線取付プレートを装着したことを特徴とする支線式鉄塔における仮支線引留用治工具。 The main branch line in the branch-type steel tower is configured so that the main pillar is arranged at each vertex of the triangle and supported by the main branch line that is extended outward from the main pillars in a plurality of vertical directions. In the temporary branch line holding jig for extending the temporary branch line in order to replace the branch line insulator, a gripping tool for holding the main column is attached to each vertex of the arm arranged to form a triangle. A temporary branch line retaining jig in a branch type steel tower, wherein a temporary branch line mounting plate for extending the temporary branch line is attached to these gripping tools. 前記本支柱を把持する把持具を二分割に構成するとともに、これら把持具の半割り部分をそれぞれ互いに隣り合うアームの先端部に装着し、これら半割り部分を互いに締結して前記本支柱に把持具を装着し、これら把持具に、隣り合う支柱に取付けられた本支線と同方向に向けて仮支線を展張する仮支線取付プレートを装着したことを特徴とする請求項4に記載の支線式鉄塔における仮支線引留用治工具。 The gripping tool for gripping the main column is divided into two parts, and the halved parts of these gripping tools are respectively attached to the distal ends of adjacent arms, and the halved parts are fastened to each other and gripped by the main column. 6. A branch line type mounting plate according to claim 4 , wherein a temporary branch line mounting plate for extending the temporary branch line in the same direction as a main branch line mounted on an adjacent column is mounted on these gripping tools. A tool for temporary branch line retention in a steel tower. 前記三角形を構成するように配置されたアームの各頂点に、前記本支柱を把持する把持具を装着し、これら把持具に仮支線を展張する仮支線取付プレートを装着した上下複数段の治工具で構成したことを特徴とする請求項5に記載の支線式鉄塔における仮支線引留用治工具。 A jig having a plurality of upper and lower stages in which a gripping tool for gripping the main column is attached to each apex of the arms arranged so as to constitute the triangle, and a temporary support line mounting plate for extending the temporary support line is attached to the gripping tool. The jig for temporary branch line retention in the branch type steel tower according to claim 5, wherein
JP2006093163A 2006-03-30 2006-03-30 Temporary branch line extension method and temporary branch line retention tool in branch-type steel tower Active JP4286265B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006093163A JP4286265B2 (en) 2006-03-30 2006-03-30 Temporary branch line extension method and temporary branch line retention tool in branch-type steel tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006093163A JP4286265B2 (en) 2006-03-30 2006-03-30 Temporary branch line extension method and temporary branch line retention tool in branch-type steel tower

Publications (2)

Publication Number Publication Date
JP2007262860A JP2007262860A (en) 2007-10-11
JP4286265B2 true JP4286265B2 (en) 2009-06-24

Family

ID=38636105

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006093163A Active JP4286265B2 (en) 2006-03-30 2006-03-30 Temporary branch line extension method and temporary branch line retention tool in branch-type steel tower

Country Status (1)

Country Link
JP (1) JP4286265B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018222913A1 (en) * 2017-05-31 2018-12-06 Osmose Utilities Services, Inc. Temporary support structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018222913A1 (en) * 2017-05-31 2018-12-06 Osmose Utilities Services, Inc. Temporary support structure
US10385534B2 (en) 2017-05-31 2019-08-20 Osmose Utilities Servies, Inc. Temporary support structure
US10889957B2 (en) 2017-05-31 2021-01-12 Osmose Utilities Services, Inc. Temporary support structure

Also Published As

Publication number Publication date
JP2007262860A (en) 2007-10-11

Similar Documents

Publication Publication Date Title
JP5283716B2 (en) Suspension device for power lines
JP5855523B2 (en) 4 conductor transmission line insulator device replacement method and replacement device used for the method
CN207243238U (en) The hanging apparatus of vertical elongated set tube bank
JP2010043505A (en) Method of replacing main pole member of steel tower
JP2012244644A (en) Insulator replacement method for insulator chain
JP4286265B2 (en) Temporary branch line extension method and temporary branch line retention tool in branch-type steel tower
US20150316175A1 (en) Device of the tensioner type for the controlled clamping and moving of an elongated element
JP2007027090A (en) Tension insulator set
JP2016084662A (en) Lift-up method for roofing material
CN104003291A (en) Single-rail walking lifting device for mounting boiler equipment in power plant
JP5730674B2 (en) Steel tower maintenance work
JP5913908B2 (en) Construction method and structure of large roof
JP2009027314A (en) Antenna replacement apparatus
JP3115288U (en) Girder lifting tool for multi-house gardening
JP4421421B2 (en) Columnar structure construction method and suspension jig
KR200428655Y1 (en) Transmission Tower
JP3688655B2 (en) Method of dismantling tower structure
JP5688827B2 (en) Reconstruction method of existing steel tower
JP3914068B2 (en) Jumper device
CN206128606U (en) Platform is used in extra -large -size polygon coal bunker crowd's tied in a bundle cone steel coal scuttle installation
CN205346472U (en) External prestress wire finished product cable pay off rack
JP2021021232A (en) Roof structure
KR200407822Y1 (en) Device for supporting pipe
JP4719382B2 (en) Steel pipe tower gripping tool and apparatus equipped with the same
JP3362885B2 (en) Large bundle 6 conductors 3 stations tension device

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080401

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20081114

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090108

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090227

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090324

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120403

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4286265

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130403

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130403

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140403

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250