JP4191495B2 - Steel pipe pile method - Google Patents
Steel pipe pile method Download PDFInfo
- Publication number
- JP4191495B2 JP4191495B2 JP2003002308A JP2003002308A JP4191495B2 JP 4191495 B2 JP4191495 B2 JP 4191495B2 JP 2003002308 A JP2003002308 A JP 2003002308A JP 2003002308 A JP2003002308 A JP 2003002308A JP 4191495 B2 JP4191495 B2 JP 4191495B2
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- pipe
- muddy water
- pumped
- water pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、地中に鋼管を設置して杭体とする鋼管杭工法に関するものである。
【0002】
【従来の技術】
従来、地中に鋼管を設置して杭体とする鋼管杭工法として、特許第2935088号公報に記載されるように、回転圧入機で鋼管に回転力を与えて地中に回転圧入するものが知られている。この工法は、最下の鋼管に対し着脱可能なオーガを装着して掘削を行い、掘削終了時に鋼管を逆回転させて鋼管からオーガを取り外して回収するものである。
【0003】
【特許文献1】
特許第2935088号公報
【0004】
【発明が解決しようとする課題】
しかしながら、前述した工法にあっては、鋼管の押し込みが円滑に行えないおそれがある。すなわち、鋼管に取り付けられたオーガにより掘削が行われるが、その際、掘削土が発生する。この掘削土は、オーガ上方に設置される排出管により排出されるが、その排出管が掘削位置よりはるか上方に配置されるため、掘削土の排出が効率良く行えない。このため、鋼管の押し込みに支障を生じ、鋼管の圧入が円滑に行えないおそれがある。
【0005】
そこで、本発明は、このような問題点を解消するためになされたものであって、円滑に鋼管の圧入が行える鋼管杭工法を提供することを目的とする。
【0006】
【課題を解決するための手段】
このような目的を達成するために、本発明に係る鋼管杭工法は、地中に鋼管を設置して杭体とする鋼管杭工法であって、鋼管の内部の下端位置に掘削部材を取り付け、鋼管内に揚泥水管を挿通し掘削部材の中央に貫通させ、揚泥水管を鋼管及び掘削部材と共に回転しないように分離した状態で配置し、鋼管に回転力を与え鋼管と共に掘削部材を回転させ掘削部材により鋼管内部を掘削しつつ、揚泥水管により掘削土を吸引して鋼管内から排出することを特徴とする。
【0007】
また本発明に係る鋼管杭工法は、鋼管が回転圧入機により地盤に回転圧入されることを特徴とする。また本発明に係る鋼管杭工法は、掘削部材が鋼管に対し着脱可能に構成されていることを特徴とする。また本発明に係る鋼管杭工法は、揚泥水管の途中にポンプを設け、そのポンプの作動により揚泥水管を通じて泥水を上方へ排出することを特徴とする。
【0008】
これらの発明によれば、揚泥水管が掘削部材を貫通して設けられているため、揚泥水管の吸引口を掘削位置の近くに配置することができる。このため、掘削土を効率よく排出することが可能となる。その際、揚泥水管が掘削部材及び鋼管と分離しているため、揚泥水管を回転させる必要がなく、鋼管の回転に伴って揚泥水管がよじれるような不具合がなく、円滑な掘削が可能となる。また、揚泥水管が回転しないので、その途中にポンプを設置することができる。揚泥水管の途中にポンプを設けた場合には、揚泥水管による排土性能を向上させることができ、深度の深い杭体の構築が可能となる。また、揚泥水管が掘削部材の中央を貫通することにより、更に掘削土の排出が効率的に行える。
【0009】
【発明の実施の形態】
以下、添付図面に基づき、本発明における実施の形態について説明する。尚、各図において同一要素には同一符号を付して説明を省略する。また、図面の寸法比率は説明のものと必ずしも一致していない。
【0010】
(第一実施形態)
図1に本実施形態に係る鋼管杭工法の概要図を示す。本図に示すように、本実施形態に係る鋼管杭工法は、地中に鋼管1を押し込んで杭体とするものである。鋼管1は、複数の管体1aを連結して構成されている。鋼管1の打ち込み深度が増すに連れて、その上部に新たな管体1aが連結され、その連結数が増えていく。
【0011】
鋼管1内には揚泥水管2が挿通されている。揚泥水管2は、掘削により発生する掘削土を吸引して鋼管1内から排出するための管体である。揚泥水管2としては、例えばフランジ付きの管体2aを連結して構成される。この揚泥水管2も、鋼管1と同様に、鋼管1の打ち込み深度が増すに連れて、その上部に新たな管体2aが連結され、その連結数が増えていく。
【0012】
揚泥水管2の上部には、配管3を介してポンプ4が接続されている。ポンプ4の作動により、揚泥水管2の吸引口2bに吸引力が生じ、掘削土が吸引され鋼管1内から排出される。そして、掘削土は、ポンプ4からタンク5へ送られる。一方、タンク5内にはポンプ6が配置されている。ポンプ6は、鋼管1内に給水するためのものである。ポンプ6の作動により、タンク5内の水等が配管7を通じて鋼管1内に圧送される。
【0013】
鋼管1の上部位置には、回転圧入機8が設置されている。回転圧入機8は、例えば鋼管1の打ち込み位置の地表部に設置される。この回転圧入機8は、鋼管1に回転力を与える回転駆動手段として機能し、鋼管1を回転させると共に下方へ圧入させて鋼管1を地盤内へ押し込む。
【0014】
鋼管1の内部の下端位置には、掘削翼10が設置されている。掘削翼10は、鋼管1の内部を掘削する掘削部材であり、鋼管1内に取り付けられ、鋼管1と一体に回転するように設けられている。掘削翼10は、例えば中央位置から放射状に延びる複数の翼部11を備えて構成される。また、掘削翼10には、揚泥水管2の吸引口2bの前方に中央掘削部12を備えている。中央掘削部12は、吸引口2bの開口位置から突出して設けられている。
【0015】
掘削翼10には、揚泥水管2が貫通して設けられている。揚泥水管2は、掘削翼10の中央位置を貫通しており、掘削翼10の下方の掘削土を吸引できるようになっている。ここでいう「貫通」とは、揚泥水管2が掘削翼10の上方側から挿通され掘削翼10の下方側で開口していることを意味する。揚泥水管2が掘削翼10の中央部を貫通することにより、揚泥水管2の吸引口2bが掘削範囲の中央に位置するため、掘削土の吸引排除が効率良く行える。
【0016】
また、揚泥水管2は、回転する鋼管1及び掘削翼10と分離した状態で設けられている。すなわち、揚泥水管2は、鋼管1及び掘削翼10と共に回転しないように設けられている。揚泥水管2の最下位置の管体2aには、保持部材2cが設けられている。保持部材2cは、鋼管1内における揚泥水管2の位置を保持するための部材であり、管体2aの側部から水平方向に延びその先端が鋼管1の内壁近傍に位置している。この保持部材2cにより、揚泥水管2が鋼管1の中心位置に保持される。
【0017】
掘削翼10は、鋼管1に対し着脱可能に設けられている。掘削翼10には、例えば着脱装置20が設置され、この着脱装置20の作動により鋼管1に対し着脱可能とされる。
【0018】
図2、3に着脱装置の説明図を示す。
【0019】
図2に示すように、着脱装置20としては、例えば機械式のものが用いられる。この着脱装置20は、掛止部30と移動機構40を備えて構成されている。掛止部30は、掘削翼10に取り付けられ鋼管1に対し掛止及び掛止解除を行うものである。この掛止部30は、掘削翼1の上部に固着されるチューブ31と、そのチューブ31内を摺動するピストン32とを備えている。
【0020】
チューブ31は、鋼管1の内壁に向けて設けられる筒体であり、例えば掘削翼10の翼部11ごとに一つずつ設置される。ピストン32は、チューブ31を所定範囲で摺動自在に設置され、鋼管1の内壁面に向けて進退可能となっている。ピストン32が鋼管1の内壁側へ移動すると、ピストン32の先端が鋼管1の内壁を掛止する。この掛止により、鋼管1と掘削翼10が一体化され、鋼管1の回転とともに掘削翼10が回転する。
【0021】
移動機構40は、ピストン32を移動させる機構であり、例えば揚泥水管2の上下動に基づいてピストン32を水平移動させる機構が用いられる。この移動機構40は、揚泥水管2に外装され揚泥水管2の引き上げと共に上方へ移動する移動筒41と、その移動筒41の上方移動力をピストン32の後退力に変換するリンク機構42とを備えている。
【0022】
図2の状態から鋼管1に対して揚泥水管2を引き上げると、図3に示すように、移動筒41が上方へ引き上げられ、リンク機構42によりピストン32が後方へ引っ張られ後退する。これにより、着脱装置20が取り付け状態から取り外し状態へ切り換わり、掘削翼10が鋼管1から取り外される。
【0023】
一方、図3の状態から揚泥水管2を下方へ降ろすと、図2に示すように、移動筒41が下方へ移動し、リンク機構42によりピストン32が前方へ押し出されて前進する。これにより、着脱装置20が取り外し状態から取り付け状態へ切り換わり、掘削翼10が鋼管1に取り付けられる。
【0024】
次に、本実施形態に係る鋼管杭工法を施工手順に沿って詳述する。
【0025】
まず、図4に示すように、鋼管杭を施工する地表位置に口元管51が埋設される。この口元管51の埋設により、地表部の崩壊が防止される。そして、その口元管51の上方にやぐら52が設置される。そして、口元管51の上方位置に回転圧入機8が設置される。そして、口元管51内に最初の鋼管1が挿入される。この最初の鋼管1には、予め掘削翼10及び揚泥水管2が取り付けられる。これにより、鋼管1の挿入と同時に掘削翼10と揚泥水管2の設置が行える。また、掘削翼10は、着脱装置20により鋼管1に対して取り付けた状態とされる。
【0026】
そして、図5に示すように、回転圧入機8を作動させて鋼管1を回転させ下方へ押圧する。鋼管1の回転により、掘削翼10も一体となって回転する。これにより、鋼管1下方の地盤が掘削翼10によって掘削される。一方、鋼管1内は、配管7から注水されて水で満たされている。そして、揚泥水管2により掘削土が吸引される。
【0027】
このとき、揚泥水管2が掘削翼10を貫通して設けられているため、揚泥水管2の吸引口2bを掘削位置の近くに配設することができる。従って、掘削翼10の下方で発生する掘削土を効率良く吸引でき排出することができる。
【0028】
また、揚泥水管2が鋼管1及び掘削翼10と分離しているため、揚泥水管2を回転させる必要がなく、鋼管1の回転に伴って揚泥水管2がよじれるような不具合がなく、円滑な掘削が可能となる。また、揚泥水管2が回転しないので、揚泥水管2の途中にポンプを設置することができ、揚泥水管2による排土性能を向上させることができる。従って、深度の深い杭体の構築に適している。更に、揚泥水管2が掘削翼10の中央を貫通している。このため、さらに掘削土の排出が効率的に行える。
【0029】
そして、鋼管1の管体1a一つ分だけ掘り進んだら、揚泥水管2の上部に新たな管体2aを連結するとともに、鋼管1の上部に新たな管体1aを連結する。そして、再び鋼管1の回転圧入を行い、所定深度まで掘削していく。
【0030】
そして、鋼管1の下端が所定深度まで達したら掘削作業を終了し、掘削翼10を鋼管1内から回収する。すなわち、図3に示すように、揚泥水管2を上方に引き上げる。すると、移動筒41が上方へ引き上げられリンク機構42によりピストン32が後方へ引っ張られ後退する。これにより、着脱装置20が取り付け状態から取り外し状態へ切り換わり、掘削翼10が鋼管1から取り外され、揚泥水管2と共に上方へ引き上げられる。そして、鋼管1内から回収される。
【0031】
そして、図6に示すように、鋼管1の上方から回転圧入機8を移動する。そして、図7に示すように、鉄筋61を鋼管1内に建て込む。そして、図8に示すように、鋼管1内にコンクリートを打設して、鋼管杭の施工が完了する。
【0032】
以上のように、本実施形態に係る鋼管杭工法によれば、揚泥水管2が掘削翼10を貫通して設けられているため、掘削土を効率よく排出することができる。その際、揚泥水管2が掘削翼10及び鋼管1と分離しているため、揚泥水管2を回転させる必要がなく、鋼管1の回転に伴って揚泥水管2がよじれるような不具合がなく、円滑な掘削が可能である。
【0033】
また、揚泥水管2が回転しないので、その途中にポンプを設置することができ、揚泥水管による排土性能を向上させることができる。従って、深度の深い杭体の構築に適している。また、揚泥水管2が掘削翼10の中央を貫通することにより、更に掘削土の排出が効率的に行える。
【0034】
また、鋼管1を把持する回転圧入機8を傾けることにより、鋼管杭を垂直に対し傾いた状態で容易に構築することができる。このとき、揚泥水管2が鋼管1と分離しているので、鋼管1の回転時に揚泥水管2がよじれるという不具合を生じず、円滑に施工が行える。
【0035】
また、回転圧入機8の作動により、鋼管1及び掘削翼10を回転させて掘削できるので、回転駆動装置としてコンパクトなものを用いることができ、空頭制限のある施工が可能である。特に、アンダーピニングに有効である。
【0036】
また、掘削翼10で鋼管1の内部のみを掘削するので、掘削時の地山の崩壊のおそれがなく、施工が円滑に行える。
【0037】
また、鋼管1の圧入と鋼管1内の掘削が同時に行えるので、施工が迅速に行える。このため、工期短縮が可能となる。
【0038】
また、揚泥水管2を回転させる必要がないため、掘削に伴って、必ずしも管体2aをつなぐ必要がないため、施工の簡素化が可能となる。
【0039】
なお、本実施形態に係る鋼管杭工法にあっては、着脱装置として機械式の着脱装置20を用いる場合について説明したが、本発明に係る鋼管杭工法は必ずしもそのようなものに限られるものではなく、油圧によりピストンを進退させるタイプなどその他のものを用いてもよい。
【0040】
(第二実施形態)
次に第二実施形態に係る鋼管杭工法について説明する。
【0041】
第一実施形態では、地上に設置されるポンプ4により揚泥水管2を通じて掘削土を含む泥水をくみ上げる場合について説明したが、本実施形態に係る鋼管杭工法は、揚泥水管2の途中にポンプ60を設置して泥水を鋼管1から排出するものである。
【0042】
図9に本実施形態に係る鋼管杭工法の説明図を示す。本図に示すように、揚泥水管2の途中にはポンプ60が設置される。このポンプ60の設置は、掘削の進行に伴って行われる管体2aの連結と同様に行われる。このようにポンプ60を揚泥水管2の途中にポンプ60を設置することにより、揚泥水管2の揚程を大きくすることができ、大深度の掘削に対応することができる。従って、深度の深い杭体の構築が可能となる。
【0043】
【発明の効果】
以上説明したように本発明によれば、掘削土を効率よく排出して円滑に鋼管の圧入が行える鋼管杭工法を提供することができる。
【図面の簡単な説明】
【図1】本発明の実施形態に係る鋼管杭工法の概要説明図である。
【図2】図1の鋼管杭工法に用いられる着脱装置の説明図を示す。
【図3】図1の鋼管杭工法に用いられる着脱装置の説明図を示す。
【図4】図1の鋼管杭工法の施工説明図である。
【図5】図1の鋼管杭工法の施工説明図である。
【図6】図1の鋼管杭工法の施工説明図である。
【図7】図1の鋼管杭工法の施工説明図である。
【図8】図1の鋼管杭工法の施工説明図である。
【図9】第二実施形態に係る鋼管杭工法の説明図である。
【符号の説明】
1…鋼管
2…揚泥水管
2b…吸引口
8…回転圧入機
10…掘削翼[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a steel pipe pile construction method in which a steel pipe is installed in the ground to form a pile body.
[0002]
[Prior art]
Conventionally, as a steel pipe pile construction method in which a steel pipe is installed in the ground to form a pile body, as described in Japanese Patent No. 2935088, a rotary press is used to rotationally press the steel pipe into the ground by applying a rotational force. Are known. In this method, excavation is performed with a removable auger attached to the lowermost steel pipe, and when the excavation is completed, the steel pipe is reversely rotated to remove the auger from the steel pipe and collect it.
[0003]
[Patent Document 1]
Japanese Patent No. 2935088 [0004]
[Problems to be solved by the invention]
However, in the method described above, there is a possibility that the steel pipe cannot be pushed in smoothly. That is, excavation is performed by an auger attached to the steel pipe, and excavated soil is generated at that time. The excavated soil is discharged by a discharge pipe installed above the auger. However, since the discharge pipe is arranged far above the excavation position, the excavated soil cannot be discharged efficiently. For this reason, it may interfere with the pushing of the steel pipe, and there is a possibility that the steel pipe cannot be press-fitted smoothly.
[0005]
Then, this invention was made | formed in order to eliminate such a problem, Comprising: It aims at providing the steel pipe pile construction method which can press-fit a steel pipe smoothly.
[0006]
[Means for Solving the Problems]
In order to achieve such an object, the steel pipe pile construction method according to the present invention is a steel pipe pile construction method in which a steel pipe is installed in the ground to form a pile body, and a drilling member is attached to a lower end position inside the steel pipe, inserting the lift mud pipe within the steel pipe is passed through the center of the drilling member, lifting and placing the mud tubes in steel and a separated state so as not to rotate together with the drilling member, rotating the drilling member with steel gives rotational force to the steel tube While excavating the inside of the steel pipe with the excavating member, the excavated soil is sucked and discharged from the steel pipe with the pumped muddy water pipe.
[0007]
The steel pipe pile construction method according to the present invention is characterized in that the steel pipe is rotationally press-fitted into the ground by a rotary press-fitting machine. The steel pipe pile construction method according to the present invention is characterized in that the excavation member is configured to be detachable from the steel pipe. The steel pipe pile construction method according to the present invention is characterized in that a pump is provided in the middle of the pumped muddy water pipe, and the muddy water is discharged upward through the pumped muddy water pipe by the operation of the pump.
[0008]
According to these inventions, since the muddy water pipe is provided through the excavation member, the suction port of the muddy water pipe can be arranged near the excavation position. For this reason, it becomes possible to discharge excavated soil efficiently. At that time, because the pumped muddy water pipe is separated from the drilling member and the steel pipe, there is no need to rotate the muddy water pipe, and there is no problem that the muddy water pipe is twisted with the rotation of the steel pipe, enabling smooth drilling. It becomes. In addition, since the pumped muddy water pipe does not rotate, a pump can be installed on the way. When a pump is provided in the middle of the pumped muddy water pipe, the soil removal performance by the pumped muddy water pipe can be improved, and a deep pile body can be constructed. In addition, the pumped mud water pipe penetrates the center of the excavation member, so that the excavated soil can be discharged more efficiently.
[0009]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings. In addition, in each figure, the same code | symbol is attached | subjected to the same element and description is abbreviate | omitted. Further, the dimensional ratios in the drawings do not necessarily match those described.
[0010]
(First embodiment)
The schematic diagram of the steel pipe pile construction method concerning this embodiment is shown in FIG. As shown to this figure, the steel pipe pile construction method which concerns on this embodiment pushes the
[0011]
A pumped
[0012]
A pump 4 is connected to the upper part of the pumped
[0013]
A rotary press-
[0014]
A
[0015]
The
[0016]
Further, the pumped
[0017]
The
[0018]
2 and 3 are explanatory views of the attachment / detachment device.
[0019]
As shown in FIG. 2, as the attachment /
[0020]
The
[0021]
The moving
[0022]
When the pumped
[0023]
On the other hand, when the pumped
[0024]
Next, the steel pipe pile construction method according to the present embodiment will be described in detail along the construction procedure.
[0025]
First, as shown in FIG. 4, the
[0026]
Then, as shown in FIG. 5, the rotary press-fitting
[0027]
At this time, since the
[0028]
Moreover, since the pumped
[0029]
Then, after digging by one
[0030]
Then, when the lower end of the
[0031]
Then, as shown in FIG. 6, the
[0032]
As described above, according to the steel pipe pile method according to the present embodiment, since the pumped
[0033]
Moreover, since the pumped
[0034]
Further, by tilting the rotary press-fitting
[0035]
Moreover, since the
[0036]
Moreover, since only the inside of the
[0037]
Moreover, since the press fitting of the
[0038]
Moreover, since it is not necessary to rotate the pumped
[0039]
In the steel pipe pile construction method according to the present embodiment, the case where the mechanical attachment /
[0040]
(Second embodiment)
Next, the steel pipe pile construction method according to the second embodiment will be described.
[0041]
In 1st embodiment, although the case where the muddy water containing excavated soil was pumped up through the pumped
[0042]
FIG. 9 is an explanatory diagram of the steel pipe pile construction method according to the present embodiment. As shown in the figure, a
[0043]
【The invention's effect】
As described above, according to the present invention, it is possible to provide a steel pipe pile method that can efficiently excavate excavated soil and smoothly press-fit a steel pipe.
[Brief description of the drawings]
FIG. 1 is a schematic explanatory diagram of a steel pipe pile construction method according to an embodiment of the present invention.
FIG. 2 is an explanatory view of an attachment / detachment device used in the steel pipe pile construction method of FIG.
FIG. 3 is an explanatory view of an attachment / detachment device used in the steel pipe pile construction method of FIG. 1;
FIG. 4 is a construction explanatory diagram of the steel pipe pile construction method of FIG. 1;
FIG. 5 is a construction explanatory diagram of the steel pipe pile construction method of FIG. 1;
6 is a construction explanatory diagram of the steel pipe pile construction method of FIG. 1; FIG.
FIG. 7 is a construction explanatory diagram of the steel pipe pile construction method of FIG. 1;
8 is a construction explanatory diagram of the steel pipe pile construction method of FIG. 1; FIG.
FIG. 9 is an explanatory diagram of a steel pipe pile construction method according to a second embodiment.
[Explanation of symbols]
DESCRIPTION OF
Claims (4)
前記鋼管の内部の下端位置に掘削部材を取り付け、前記鋼管内に揚泥水管を挿通し前記掘削部材の中央に貫通させ、前記揚泥水管を前記鋼管及び掘削部材と共に回転しないように分離した状態で配置し、
前記鋼管に回転力を与え前記鋼管と共に前記掘削部材を回転させ前記掘削部材により前記鋼管内部を掘削しつつ、前記揚泥水管により掘削土を含む泥水を吸引して前記鋼管内から排出すること、
を特徴とする鋼管杭工法。In the steel pipe pile construction method to install a steel pipe in the ground and make it a pile body,
The wear member mounted within the lower end position of the steel pipe, by inserting the lifting mud pipe within said steel tube is penetrated through the center of the wear member, to separate the fried mud pipe so as not to rotate together with the steel pipe and the drilling member Placed in a state,
Applying a rotational force to the steel pipe, rotating the excavating member together with the steel pipe and excavating the inside of the steel pipe with the excavating member, sucking mud water containing excavated soil with the pumped muddy water pipe and discharging it from the steel pipe;
Steel pipe pile construction method characterized by
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003002308A JP4191495B2 (en) | 2003-01-08 | 2003-01-08 | Steel pipe pile method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003002308A JP4191495B2 (en) | 2003-01-08 | 2003-01-08 | Steel pipe pile method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004211500A JP2004211500A (en) | 2004-07-29 |
JP4191495B2 true JP4191495B2 (en) | 2008-12-03 |
Family
ID=32820094
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003002308A Expired - Fee Related JP4191495B2 (en) | 2003-01-08 | 2003-01-08 | Steel pipe pile method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4191495B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104762967A (en) * | 2015-04-14 | 2015-07-08 | 中天建设集团有限公司 | Improved anchor rod static pressure pile sealing device and construction method |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4635725B2 (en) * | 2005-05-31 | 2011-02-23 | 株式会社大林組 | Pile construction system |
CN106032668A (en) * | 2015-03-18 | 2016-10-19 | 中天建设集团有限公司 | Method and device for sealing piles without unloading static pressure piles of anchor rods |
-
2003
- 2003-01-08 JP JP2003002308A patent/JP4191495B2/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104762967A (en) * | 2015-04-14 | 2015-07-08 | 中天建设集团有限公司 | Improved anchor rod static pressure pile sealing device and construction method |
Also Published As
Publication number | Publication date |
---|---|
JP2004211500A (en) | 2004-07-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2006241919A (en) | Pile construction machine and pile construction method | |
JP3996012B2 (en) | Pile construction method and construction equipment | |
JP4191495B2 (en) | Steel pipe pile method | |
JP4881257B2 (en) | Spiral auger and method of attaching branch pipe to main buried in soil using spiral auger | |
JP4344762B2 (en) | Drilling method and drilling device | |
WO2008072950A2 (en) | Foundation system for the forming of a foundation pile in the ground | |
JP5885512B2 (en) | Construction method of heat collection tube | |
JP4635725B2 (en) | Pile construction system | |
JP3791644B2 (en) | Voltahead | |
JP2645545B2 (en) | Excavation press-fitting method and its equipment | |
JP3064258B2 (en) | Construction method of casing shaft | |
JP2007170087A (en) | Excavating device | |
JP3921299B2 (en) | Pile press-fitting device | |
JP3947304B2 (en) | Drilling rig | |
KR20050036084A (en) | Complex drill device and engineering method using that | |
JP3004267B1 (en) | Drilling rig | |
JP2005314871A (en) | Removing device for underground obstacle and removing method for underground obstacle | |
JP4507226B2 (en) | Vertical excavation method and apparatus | |
JP3123812U (en) | Attachment for boring equipment | |
JP3955792B2 (en) | Ground improvement device and ground improvement method | |
JP4485098B2 (en) | Drilling rig | |
JPH10266197A (en) | Molding method of foundation pile | |
JP3753530B2 (en) | Underground excavator and underground excavation method | |
JPH1122357A (en) | Excavation method | |
JPH06341143A (en) | Construction of foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20051128 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070925 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20071009 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20071206 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080129 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080328 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080603 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080725 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080916 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080918 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110926 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4191495 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110926 Year of fee payment: 3 |
|
R154 | Certificate of patent or utility model (reissue) |
Free format text: JAPANESE INTERMEDIATE CODE: R154 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140926 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |