JP4057169B2 - Building construction method - Google Patents

Building construction method Download PDF

Info

Publication number
JP4057169B2
JP4057169B2 JP31596198A JP31596198A JP4057169B2 JP 4057169 B2 JP4057169 B2 JP 4057169B2 JP 31596198 A JP31596198 A JP 31596198A JP 31596198 A JP31596198 A JP 31596198A JP 4057169 B2 JP4057169 B2 JP 4057169B2
Authority
JP
Japan
Prior art keywords
floor
floors
construction
constructed
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP31596198A
Other languages
Japanese (ja)
Other versions
JP2000145153A (en
Inventor
勇次 時長
耕一 田中
久雄 小薄
道夫 田中
博 坂本
寛洋 湧川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP31596198A priority Critical patent/JP4057169B2/en
Publication of JP2000145153A publication Critical patent/JP2000145153A/en
Application granted granted Critical
Publication of JP4057169B2 publication Critical patent/JP4057169B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【0001】
【発明の属する技術分野】
この発明は、建築物を構築する方法に関し、特に、施工の仕方及び順序に関するものである。
【0002】
【従来の技術】
従来、例えば、6階建ての建築物を構築する場合は、図6の丸番号で示すように、最下階(地上1階)部分の床、柱、壁などのコンクリート躯体を施工した後、次に2階部分の躯体を、次に3階部分の躯体を、…というように、下から順番に階を構築していた。
【0003】
【発明が解決しようとする課題】
しかしながら、上述した従来の建築物の構築方法によれば、下から順番に階を構築していくので、工期を短縮できないという課題があった。
【0004】
本願発明は上述した課題を解消するためになされたもので、工期の短縮化が図れる建築物の構築方法を提供するものである。
【0005】
【課題を解決するための手段】
本願発明に係る建築物の構築方法は、少なくとも、ある階から、2つの階以上当該ある階より上方の他階までの鉄骨建て方を行い、上記ある階のある部分の床の構築工事と、上記他階における上記ある階のある部分に対応しない位置の部分の床の構築工事とを並行して行うことを繰り返して、上記ある階と他階の床を構築した後、上記ある階及びこのある階に続く階の構築工事と、上記他階及びこの他階に続く階の構築工事とを並行して行うようにした。
【0006】
【発明の実施の形態】
・実施の形態1
本発明の実施の形態1による建築物の構築方法は、まず、少なくとも、ある階から、2つの階以上当該ある階より上方の他階までの鉄骨建て方を行う。例えば地上4階建ての建築物を構築する場合において、まず、地上に、1階から他階としての3階の立ち上がり(鉄骨柱)までの鉄骨建て方を行う。この場合、上記ある階として1階部分の床を構築した後、上記他階として3階部分の床を構築し、その後、1階及び2階の構築工事と、3階及び4階の構築工事とを並行して行う。
尚、上記構築方法によれば、ある階と他階との間の工事が完了する前に、他階の工事を行うので、施工中の地震対策のため、本願では、ある階と他階との間の構造強度を考慮している。つまり、上記例では、3階の構築工事に先だって、1階と2階の鉄骨間柱間などに耐震補強ブレースを取り付けるようにする。さらに、他階の直下の階の壁構造が構築されていないうちに当該他階の床を構築するので、当該他階の床が垂れるおそれがある。従って、他階の床を引っ張りあげる床支持ブレースを取り付けるようにする。上記例では、床支持ブレースの両端を、3階の床を構成する例えば鉄骨大梁と3階の鉄骨柱に取り付けて、床支持ブレースで鉄骨大梁を引っ張り上げるようにしておく。
【0007】
以下、図1ないし図4に基づいて本発明の実施の形態1による建築物の構築方法を詳説する。
【0008】
まず、地下階を有しない構造の建築物、あるいはすでに建築物の地下階が完成していて、建築物の地上階のみを構築する場合について、6階建ての建築物を構築する場合を例にして図1に基づいて説明する。
まず、ある階としての1階から他階としての4階の立ち上がりまで(4階部分の鉄骨柱まで)の鉄骨建て方を行い鉄骨構造体1を構築する。次に、鉄骨構造体1の1階と2階と3階の部分の壁が構築される複数の個所のうちの少なくとも一部の個所に耐震補強ブレース2を取り付けておく。つまり、1階と2階と3階における鉄骨柱1aや鉄骨間柱1b間にターンバックルなどを用いて耐震補強ブレース2を取り付ける。この耐震補強ブレース2の取り付け個所は、耐震設計により任意に決めればよいが、例えば、建築物の外壁が構築される全個所と、建築物の内壁が構築される複数の個所のうちの一部の箇所に取り付けておく。
そして、1階部分の床3を構築した後、4階部分の床4を構築する。1階部分の床3は、例えば土間配筋した後にコンクリートを打設して完成する。4階部分の床4は、例えば鉄骨構造体1の4階部分の床4を構成する鉄骨大梁間にデッキプレートを敷設した後にコンクリートを打設したり、あるいは、型枠を設置して型枠内にコンクリートを打設したりすることで完成する。
型枠内にコンクリートを打設し構築した4階部分の床4の構造の一例を図2に示す。図2において、4aは大梁部、4bは小梁部、4cは柱部、1aは鉄骨柱、4dは柱の主筋(鉄筋)である。この例では、4階部分の床4は、鉄骨鉄筋で組んだ小梁を配置して小梁部4bが形成されたSRC(鉄骨鉄筋コンクリート)構造の床となる。
尚、3階部分の柱,壁などの躯体を構築しない前に、4階部分の床4を構築するので、床4が垂れるおそれがある。そこで、予め、床支持ブレース5を取り付けておいて4階部分の床4が垂れないようにしておく。
床支持ブレース5は、その両端を、ターンバックルなどを用いて4階の床を構成する鉄骨大梁と4階の鉄骨柱1a(立ち上がり鉄骨柱)とに取り付けておく。
尚、ブレース2,5は、一般には、鉄筋状のもの用いるが、強度を大きくするために、鉄板状のものや他の形状のものを用いてもよい。
また、4階部分の床4を1階部分の床3より先に施工してもよいが、1階部分の床3の施工と4階部分の床4の施工は時間をずらして行う。同時に行うと、4階部分から物が落下してくる可能性があり、1階部分の床3の施工者にとって危険だからである。
【0009】
そして、1階部分の床3の構築と4階部分の床4の構築が終了したら、1階部分の構築工事と、4階部分の構築工事とを並行して行う。尚、この時の構築工事とは、主に、柱や壁部分など床以外の部分の躯体構築工事を指す。
1階部分と4階部分の構築工事が完了したら、2階部分の構築工事と、5階部分の構築工事とを並行して行い、さらに、3階部分の構築工事と、6階部分の構築工事とを並行して行う。尚、この時の構築工事とは、主に、床や柱や壁部分などの躯体構築工事を指す。
以上により、6階建ての建築物の構築が完了する。なお、この場合、1階、2階、3階は、鉄骨鉄筋コンクリート構造(SRC構造)で構築され、4階(床を除いて)、5階、6階は、鉄筋コンクリート構造(RC構造)で構築される。尚、4階の床は、図2の場合はSRC構造となり、デッキプレート敷設の場合は鉄骨コンクリート構造(SC構造)となる。
【0010】
尚、従来、地下階の施工方法としては図3、図4に示すものがある。
図3は、まず、矢示▲1▼のように、地下のスペース分だけ地盤Sを掘削してから、その後、矢示▲2▼のように、下から順に、地下3階部分、地下2階部分、地下1階部分を構築していく方法を示している。
また、図4に示すように、地上1階部分の床を先に構築し、その後に、矢示▲1▼で示すように、地下1階のスペース分だけ地盤Sを掘削してから、地下1階を構築し、以下、順に、矢示▲2▼▲3▼のように、地下2階、地下3階を掘削して構築していく方法もある。
【0011】
図3,図4の工法で地下階を構築する場合、先に図3や図4の工法で地下階を構築してから、図1のように地上階を構築するようにしてもよい。
また、図3の工法で地下階を構築する場合、まず、地下3階から地上4階の立ち上がりまでの鉄骨建て方を行なってから、例えば、地下3階部分の床と1階部分の床3と4階部分の床4とを先に構築し、地下3階、1階、4階の3つの階から並行して構築工事を行うようにしてもよい。この場合、地下3階が、ある階に相当し、地上1階,4階が、他階に相当する。
また、図4の工法で地下階を構築する場合、まず、地上から地上4階の立ち上がりまでの鉄骨建て方を行って、地上1階部分の床3の構築と地上4階部分の床4の構築を行い、以後は、地上4階と上階の構築工事と、地下階の構築工事(掘削,地下階の躯体構築工事)とを並行して行って、最後に、地上1,2,3階部分の構築工事を行うようにしてもよい。掘削土は、予め地下上方階の床の一部に設けておいた排出口より排出される。この場合、掘削土の排出作業のため、地上1階,2階,3階の構築工事を最後に行うようにしているが、排出作業と、地上1階,2階,3階の構築工事とを並行して行える場合は、地下1,2,3階の構築工事と、地上4階,5,6階の構築工事と、地上1階,2,3階の構築工事とを並行して行うようにすればよい。この場合、ある階(1階)から他階(4階)まで(4階の立ち上がりまで)の鉄骨建て方を行い、上記ある階(1階)の床を構築した後、上記他階(4階)の床を構築し、その後、上記ある階(1階)及びこのある階より上方に続く階(2階,3階)及び下方に続く階(地下1階,2階,3階)の構築工事と、上記他階(4階)及びこの他階の上方に続く階(5階,6階)の構築工事とを並行して行うものである。
【0012】
実施の形態1によれば、ある階及びこのある階に続く階の構築工事と、他階及びこの他階に続く階の構築工事とを並行して行うので、工期の短縮化が図れるとともに、耐震補強ブレース2を取り付けるようにしたので、施工中の耐震性を向上でき、かつ、床支持ブレース5を取り付けるようにしたので、他階の床が垂れることなく品質の高い建築物を構築できるようになる。
【0013】
実施の形態2.
尚、ある階と他階の床の構築工事を、それぞれの階においても分割して行うようにしてもよい。
例えば、図1と同様な建築物を構築する場合において、図5のように、1階部分と4階部分の床部分を中央Cで区切って2分割し、分割した区域ごとに床を構築し、1階部分と4階部分の床の構築が完了したら、1階及び2階,3階の構築工事と、4階及び5階,6階の構築工事とを並行して行う場合を例にして説明する。
まず、図1と同様に鉄骨建て方を行う。そして、図5の4階部分の左側の区域の床の構築工事と、1階部分の右側の区域の床の構築工事とを並行して行う。次に、図5の4階部分の右側の区域の床の構築工事と、1階部分の左側の区域の床の構築工事とを並行して行う。以上で、ある階としての1階の床と他階としての4階の床の構築が完了する。この後は、上述のように、1階及び2階,3階の構築工事と、4階及び5階,6階の構築工事とを並行して行う。
尚、ある階と他階の床の構築工事の分割は、2分割以上であればよいが、あまり多く分割すると余計に作業が煩雑になるので、4分割ぐらいまでが妥当と思われる。
【0014】
尚、実施の形態2の方法は、地下階を有する建築物の構築にも同様に適用できることは言うまでもない。
【0015】
実施の形態2によれば、ある階と他階の床をより効率的に早く構築できるので、実施の形態1より、さらに工期を短縮化することが可能となる。
【0016】
尚、他階は、ある階に対して2つの階以上の間隔毎に上方に位置することになる2つ以上の階であってもよい。例えば、図1あるいは図3を前提にして、高層建築物を構築する場合を考えてみる。この場合、ある階を1階または地下最下階とし、当該ある階に対して2つの階以上の間隔毎に上方に位置する複数の他階を想定する。そして、これら、ある階と複数の他階を基準階にして、各基準階からの構築工事を並行して行うようにすれば、効率的に高層建築物を構築できる。尚、上記基準階と基準階との間隔は、上記実施の形態では、3階間隔としたが、2階間隔以上であれば、任意に決めればよい(階数にもよるが、高層建築物の場合は、実際には5〜7階間隔が妥当だと思われる)。また、図4の場合は、ある階を1階とし、当該ある階に対して2つの階以上の間隔毎に上方に位置する複数の他階を想定すればよい。
【0017】
また、上記実施の形態では、鉄骨部分はSRC構造で構築し、残りの上方の階はRC造で構築するようにした例を述べたが、構築する建築物の階数分だけの鉄骨建て方を行って、すべての階をSRC構造で構築したり、あるいはS構造またはSC構造で構築する場合でも本願発明を適用できることはいうまでもない。
また、実施の形態のように、鉄骨部分はSRC構造で構築し、残りの上方の階はRC造で構築するようにした構築方法によれば、上方の鉄骨建て方の手間を省けて、施工手間の省力化を図れるとともに、下層階の構造をSRC構造で構築できるので、構造的に安定な建築物を構築できるという効果がある。尚、このような構築方法は、下層階を商業スペース、上層階を住宅スペースとするような建築物に適している。
【0018】
なお、実施の形態では、鉄骨構造体1において壁が構築される複数の個所のうちの少なくとも一部の個所に耐震補強ブレース2を取り付けておくと説明したが、壁が構築される以外の個所に耐震補強ブレースを取り付けてもよく、要は、
鉄骨建て方で構築されるある階から他階との間の鉄骨構造体を耐震補強ブレースで補強するようにすればよい。
また、実施の形態では、床の鉄骨大梁を引っ張り上げるような態様の床支持ブレース5を説明したが、床の鉄骨大梁を下から支持するような床支持ブレースを用いても良い。
また、本願発明は、地上途中階(例えば2階)まで既に躯体工事が完了しているような場合でも、その上に鉄骨建て方を行って他階を設定することにより、実現できる。この場合、(地上途中階+1階)がある階となり、2つの階以上当該ある階より上方に離れた階(あるいは当該ある階に対して2つの階以上の間隔毎に上方に位置することになる2つ以上の階)が他階となる。
【0019】
【発明の効果】
本願発明によれば、少なくとも、ある階から、2つの階以上当該ある階より上方の他階までの鉄骨建て方を行い、上記ある階のある部分の床の構築工事と、上記他階における上記ある階のある部分に対応しない位置の部分の床の構築工事とを並行して行うことを繰り返して、上記ある階と他階の床を構築した後、上記ある階及びこのある階に続く階の構築工事と、上記他階及びこの他階に続く階の構築工事とを並行して行うようにしたので、ある階と他階の床をより効率的に早く構築でき、工期の短縮化を図ることが可能となる
【図面の簡単な説明】
【図1】 この発明の実施の形態1を説明するための工程説明図である。
【図2】 この発明の実施の形態1において施工された床部分の一例の詳細を説明するための平面図、正面図である。
【図3】 この発明に適用する地下階の施工方法を説明するための工程説明図である。
【図4】 この発明に適用する地下階の施工方法を説明するための工程説明図である。
【図5】 この発明の実施の形態2を説明するための工程説明図である。
【図6】 従来の建築物の構築方法を説明するための工程説明図である。
【符号の説明】
1 鉄骨構造体、2 耐震補強ブレース、3 1階(ある階)の床、4 4階(他階)の床、5 床支持ブレース。
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing a building, and more particularly to a construction method and order.
[0002]
[Prior art]
Conventionally, for example, when building a six-story building, as shown by the circle numbers in FIG. 6, after constructing concrete frames such as floors, pillars, walls, etc. of the lowest floor (first floor above ground), Next, the floors were constructed in order from the bottom, such as the second-floor frame, the third-floor frame, and so on.
[0003]
[Problems to be solved by the invention]
However, according to the conventional building construction method described above, since the floors are constructed in order from the bottom, there is a problem that the construction period cannot be shortened.
[0004]
This invention is made | formed in order to eliminate the subject mentioned above, and provides the construction method of the building which can aim at shortening of a construction period.
[0005]
[Means for Solving the Problems]
The building construction method according to the invention of the present application is to build a steel frame from at least one floor to two or more floors to the other floor above the floor, and the construction work of the floor of a certain floor, After constructing the floor of the other floor and the floor of the other floor by repeating in parallel with the construction of the floor of the part of the other floor not corresponding to the part of the certain floor, The construction work for the floor following a certain floor and the construction work for the other floor and the floor following this other floor were performed in parallel.
[0006]
DETAILED DESCRIPTION OF THE INVENTION
Embodiment 1
In the building construction method according to Embodiment 1 of the present invention, first, a steel frame is built from at least one floor to two or more floors to another floor above the floor. For example, when building a four-story building on the ground, first, a method of building a steel frame from the first floor to the rise of the third floor (steel column) as the other floor is performed on the ground. In this case, after constructing the floor of the first floor as the certain floor, construct the floor of the third floor as the other floor, and then constructing the first and second floors and constructing the third and fourth floors And in parallel.
In addition, according to the construction method described above, the construction of the other floor is performed before the construction between the certain floor and the other floor is completed. Consider the structural strength between. That is, in the above example, prior to the construction work on the third floor, the seismic reinforcement braces are attached between the steel inter-columns on the first floor and the second floor. Furthermore, since the floor of the other floor is constructed before the wall structure of the floor immediately below the other floor is constructed, there is a possibility that the floor of the other floor may hang down. Therefore, a floor support brace that pulls up the floor of another floor is attached. In the above example, both ends of the floor support brace are attached to, for example, a steel beam and a steel column of the third floor that constitute the floor of the third floor, and the steel beam is pulled up by the floor support brace.
[0007]
Hereinafter, a building construction method according to Embodiment 1 of the present invention will be described in detail with reference to FIGS.
[0008]
First, in the case of building a 6-story building as an example when building a structure with no basement, or when the basement of a building has already been completed and only the ground floor of the building is constructed. This will be described with reference to FIG.
First, the steel structure 1 is constructed by building a steel frame from the first floor as a certain floor to the rise of the fourth floor as the other floor (up to the steel column of the fourth floor). Next, the seismic reinforcement brace 2 is attached to at least some of the plurality of locations where the walls of the first, second, and third floor portions of the steel structure 1 are constructed. That is, the seismic reinforcement brace 2 is attached using a turnbuckle or the like between the steel column 1a and the steel inter-column 1b on the first, second and third floors. The location where the seismic reinforcement brace 2 is attached may be arbitrarily determined according to the seismic design. For example, all locations where the outer wall of the building is constructed and some of the locations where the inner wall of the building is constructed Attach it to the place.
And after constructing the floor 3 of the first floor part, the floor 4 of the fourth floor part is constructed. The floor 3 of the first floor portion is completed by placing concrete after placing the soil between, for example. For example, the floor 4 of the fourth floor is formed by placing concrete after placing a deck plate between the steel beams constituting the floor 4 of the fourth floor of the steel structure 1 or by installing a formwork to form the formwork. It is completed by placing concrete inside.
An example of the structure of the floor 4 of the fourth floor part constructed by placing concrete in the formwork is shown in FIG. In FIG. 2, 4a is a large beam portion, 4b is a small beam portion, 4c is a column portion, 1a is a steel column, and 4d is a main bar (rebar) of the column. In this example, the floor 4 of the fourth floor portion is a floor having an SRC (steel reinforced concrete) structure in which small beams 4b are formed by arranging small beams assembled with steel frames.
In addition, since the floor 4 of the 4th floor part is constructed before constructing the frame such as the pillar and wall of the 3rd floor part, the floor 4 may be drooped. Therefore, a floor support brace 5 is attached in advance so that the floor 4 of the fourth floor portion does not hang down.
The both ends of the floor support brace 5 are attached to the steel beam of the fourth floor and the steel column 1a (rise steel column) of the fourth floor by using a turnbuckle or the like.
The braces 2 and 5 are generally in the form of reinforcing bars, but in order to increase the strength, those in the form of iron plates or other shapes may be used.
Further, the floor 4 of the fourth floor portion may be constructed before the floor 3 of the first floor portion, but the construction of the floor 3 of the first floor portion and the construction of the floor 4 of the fourth floor portion are performed with a time lag. If it is performed at the same time, an object may fall from the fourth floor part, which is dangerous for the installer of the floor 3 of the first floor part.
[0009]
When the construction of the floor 3 of the first floor part and the construction of the floor 4 of the fourth floor part are completed, the construction work of the first floor part and the construction work of the fourth floor part are performed in parallel. In addition, the construction work at this time mainly refers to the construction work of the building other than the floor, such as pillars and walls.
When the construction work for the 1st floor and 4th floor is completed, the construction work for the 2nd floor and the 5th floor are performed in parallel, and further, the construction work for the 3rd floor and the 6th floor Perform the construction in parallel. The construction work at this time mainly refers to the construction work of the frame such as floors, pillars, and walls.
Thus, the construction of the 6-story building is completed. In this case, the 1st, 2nd and 3rd floors are constructed with a steel reinforced concrete structure (SRC structure), the 4th floor (excluding the floor), the 5th and 6th floors are constructed with a reinforced concrete structure (RC structure). Is done. The floor on the fourth floor has an SRC structure in the case of FIG. 2 and a steel-concrete structure (SC structure) in the case of laying the deck plate.
[0010]
Conventionally, construction methods for the underground floor include those shown in FIGS.
In FIG. 3, first, the ground S is excavated as much as the underground space, as shown by arrow (1), and then, as shown by arrow (2), in order from the bottom, the third basement part, the basement 2 This shows how to build the floor part and the first basement part.
In addition, as shown in FIG. 4, the floor of the first floor is constructed first, and then the ground S is excavated by the space of the first basement, as shown by arrow (1). There is also a method of constructing the first floor and then excavating and constructing the second basement floor and the third basement floor as shown by arrows (2) and (3).
[0011]
When the underground floor is constructed by the method shown in FIGS. 3 and 4, the underground floor may be constructed first as shown in FIG. 1 after the underground floor is constructed by the method shown in FIGS.
When constructing an underground floor by the method shown in FIG. 3, first, a steel frame is constructed from the third basement to the rise of the fourth floor, and then, for example, the basement 3 floor and the first floor 3 And the floor 4 of the fourth floor portion may be constructed first, and construction work may be performed in parallel from three floors of the third basement, the first floor, and the fourth floor. In this case, the third basement floor corresponds to a certain floor, and the first and fourth floors above correspond to other floors.
When constructing the basement floor by the method shown in FIG. 4, first, the steel frame is built from the ground up to the rise of the fourth floor, and the construction of the floor 3 of the first floor part and the floor 4 of the fourth floor part are performed. After that, the construction work on the 4th floor and the upper floor and the construction work on the basement floor (excavation, building construction on the basement floor) are performed in parallel. You may make it perform construction construction of a floor part. The excavated soil is discharged from a discharge port provided in advance on a part of the floor of the upper basement floor. In this case, the construction work on the 1st, 2nd, and 3rd floors is performed last for the excavation work of the excavated soil, but the construction work on the 1st, 2nd, and 3rd floors Can be performed in parallel, the construction work on the 1st, 2nd, 3rd floors, the construction work on the 4th, 5th, 6th floors, and the construction work on the 1st, 2nd, 3rd floors in parallel What should I do? In this case, after building a steel frame from one floor (1st floor) to the other floor (4th floor) (until the rise of the 4th floor) and constructing the floor of the certain floor (1st floor), the other floor (4 Of the above floor (the first floor), the floor (2nd floor, 3rd floor) that continues above this certain floor, and the floors (1st basement, 2nd floor, 3rd floor) that follow below The construction work is performed in parallel with the construction work on the other floor (4th floor) and the floors (5th floor and 6th floor) following the other floor.
[0012]
According to the first embodiment, the construction work of a certain floor and the floor following this certain floor and the construction work of the other floor and the floor following this other floor are performed in parallel, so that the construction period can be shortened, Since the seismic reinforcement brace 2 is attached, the earthquake resistance during construction can be improved, and the floor support brace 5 is attached, so that a high-quality building can be constructed without drooping the floors of other floors. become.
[0013]
Embodiment 2. FIG.
In addition, you may make it perform the construction construction of the floor of a certain floor and another floor also in each floor separately.
For example, when building a building similar to FIG. 1, as shown in FIG. 5, the floor portions of the first floor portion and the fourth floor portion are divided into two parts by dividing the center C, and a floor is constructed for each divided area. Once the construction of the floors of the 1st and 4th floors is completed, the construction work of the 1st, 2nd and 3rd floors and the construction work of the 4th, 5th and 6th floors are performed in parallel. I will explain.
First, the steel frame is built in the same manner as in FIG. Then, the floor construction work in the left area of the fourth floor portion in FIG. 5 and the floor construction work in the right area of the first floor portion are performed in parallel. Next, the construction work of the floor in the area on the right side of the fourth floor part in FIG. 5 and the construction work of the floor in the area on the left side of the first floor part are performed in parallel. This completes the construction of the first floor as a certain floor and the fourth floor as another floor. Thereafter, as described above, the construction work for the first, second, and third floors and the construction work for the fourth, fifth, and sixth floors are performed in parallel.
It should be noted that the division of construction work for a certain floor and other floors may be two or more, but if it is divided too much, the work becomes excessively complicated, so it seems that about four divisions are appropriate.
[0014]
Needless to say, the method of the second embodiment can be similarly applied to the construction of a building having an underground floor.
[0015]
According to the second embodiment, the floors of a certain floor and other floors can be constructed more efficiently and quickly, so that the construction period can be further shortened than in the first embodiment.
[0016]
The other floors may be two or more floors that are positioned above each floor at intervals of two or more floors. For example, consider the case where a high-rise building is constructed based on FIG. 1 or FIG. In this case, a certain floor is assumed to be the first floor or the lowest basement floor, and a plurality of other floors located above the certain floor at intervals of two or more floors are assumed. If a certain floor and a plurality of other floors are used as reference floors, and construction work from each reference floor is performed in parallel, a high-rise building can be efficiently constructed. In the above embodiment, the interval between the reference floor and the reference floor is set to be an interval of the third floor, but may be arbitrarily determined as long as it is equal to or more than the second floor (depending on the number of floors, In the case, it seems that the 5-7 floor interval is actually appropriate). In the case of FIG. 4, a certain floor may be defined as a first floor, and a plurality of other floors positioned above the certain floor at intervals of two or more floors may be assumed.
[0017]
Moreover, in the said embodiment, although the steel frame part was constructed | assembled with the SRC structure and the remaining upper floor was constructed with the RC structure, the method of constructing the steel frame for the number of floors of the building to be constructed was described. It goes without saying that the present invention can be applied even when all floors are constructed with an SRC structure, or with an S structure or an SC structure.
Moreover, according to the construction method in which the steel frame portion is constructed with the SRC structure and the remaining upper floor is constructed with the RC structure as in the embodiment, the construction of the upper steel frame can be saved and saved. In addition to saving labor, the structure of the lower floor can be constructed with the SRC structure, so that it is possible to construct a structurally stable building. Such a construction method is suitable for a building in which the lower floor is a commercial space and the upper floor is a residential space.
[0018]
In the embodiment, it has been described that the seismic reinforcement brace 2 is attached to at least some of the plurality of locations where the wall is constructed in the steel structure 1. However, locations other than the location where the wall is constructed are described. A seismic reinforcement brace may be attached to the
What is necessary is just to reinforce the steel structure between one floor and another floor constructed by the steel frame construction method with the earthquake-proof reinforcement brace.
Further, in the embodiment, the floor support brace 5 in such a manner that the floor steel beam is pulled up has been described, but a floor support brace that supports the steel beam beam from below may be used.
Further, the present invention can be realized even when the frame construction has already been completed up to the ground floor (for example, the second floor), by building a steel frame on that and setting another floor. In this case, (the ground intermediate floor + 1st floor) becomes a certain floor and is located above two floors above the certain floor (or above each certain floor at intervals of two or more floors). 2 or more floors) become other floors.
[0019]
【The invention's effect】
According to the invention of the present application, at least from one floor, two or more floors to the other floor above the certain floor are constructed, and the construction work of the floor of a certain floor of the certain floor, and the above in the other floor After constructing the floor of one floor and the other floor by repeating the construction work of the floor at the position not corresponding to a certain part of a certain floor, the floor following the certain floor and this certain floor building construction and, since to carry out in parallel the construction work of the floor following the aforementioned other floor and the other floor can be built more efficiently fast certain floors and other floors floors, shortening of Engineering period Can be achieved .
[Brief description of the drawings]
FIG. 1 is a process explanatory diagram for explaining Embodiment 1 of the present invention;
FIGS. 2A and 2B are a plan view and a front view for explaining details of an example of a floor portion constructed in Embodiment 1 of the present invention. FIGS.
FIG. 3 is a process explanatory diagram for explaining a basement construction method applied to the present invention.
FIG. 4 is a process explanatory diagram for explaining a basement construction method applied to the present invention.
FIG. 5 is a process explanatory diagram for explaining the second embodiment of the present invention.
FIG. 6 is a process explanatory diagram for explaining a conventional building construction method.
[Explanation of symbols]
1 Steel structure, 2 Seismic reinforcement brace, 3rd floor (one floor), 4th floor (other floor), 5 floor support brace.

Claims (1)

少なくとも、ある階から、2つの階以上当該ある階より上方の他階までの鉄骨建て方を行い、上記ある階のある部分の床の構築工事と、上記他階における上記ある階のある部分に対応しない位置の部分の床の構築工事とを並行して行うことを繰り返して、上記ある階と他階の床を構築した後、上記ある階及びこのある階に続く階の構築工事と、上記他階及びこの他階に続く階の構築工事とを並行して行うようにしたことを特徴とする建築物の構築方法 At least from one floor to two or more floors to the other floor above the floor, the construction of the floor of a certain part of the floor and the part of the certain floor of the certain floor After repeating the construction of the floor of the part of the position that does not correspond in parallel, constructing the floor of the certain floor and the other floor, then constructing the floor of the certain floor and the floor following this certain floor, and the above A construction method for a building, characterized in that construction work on another floor and a floor following this other floor is performed in parallel .
JP31596198A 1998-11-06 1998-11-06 Building construction method Expired - Fee Related JP4057169B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP31596198A JP4057169B2 (en) 1998-11-06 1998-11-06 Building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP31596198A JP4057169B2 (en) 1998-11-06 1998-11-06 Building construction method

Publications (2)

Publication Number Publication Date
JP2000145153A JP2000145153A (en) 2000-05-26
JP4057169B2 true JP4057169B2 (en) 2008-03-05

Family

ID=18071679

Family Applications (1)

Application Number Title Priority Date Filing Date
JP31596198A Expired - Fee Related JP4057169B2 (en) 1998-11-06 1998-11-06 Building construction method

Country Status (1)

Country Link
JP (1) JP4057169B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008255605A (en) * 2007-04-03 2008-10-23 Shimizu Corp Building construction method

Also Published As

Publication number Publication date
JP2000145153A (en) 2000-05-26

Similar Documents

Publication Publication Date Title
JP3180817U (en) Building structure without formwork removal
KR100927344B1 (en) Construction method for connecting underground structure and underground structure using connection structure for underground construction
KR100771144B1 (en) Extension work method by constructing multi-lavers synchronously
CN205329970U (en) Precast concrete wallboard and wall panel structure system of dark frame in area of structure thereof
JP4057169B2 (en) Building construction method
KR101908943B1 (en) RC WALL STRUCTURE FOR TOP-DOWN AND METHOD FOR CONSTRUCTING THE STRUCTUREa
JPH0684690B2 (en) Building basement extension method
JPH04161542A (en) Connecting work of column and beam and its structure
JP2000265479A (en) Foundation structure of structure
CN206769444U (en) A kind of seismic hardening system of frame structure filling tensility shock-resistant component
KR101045000B1 (en) Attachable wall-support device
RU87181U1 (en) REINFORCED CONCRETE FRAME OF MULTI-STOREY BUILDING OF ARKOS SYSTEM
JP2817591B2 (en) Construction method of steel reinforced concrete building
JPH06146309A (en) Construction method of underground structure
JP3830062B2 (en) Seismic reinforcement method for reinforced concrete buildings
JP6707872B2 (en) Reverse construction method
JP2877881B2 (en) How to build a reinforced concrete basement
JPH0657769A (en) Underground concrete structure and working method thereof
JPH08177068A (en) Construction of underground structure
JP2023022563A (en) Concrete wall construction method
JPH0816331B2 (en) Underground construction wall foundation method
JPH04131444A (en) Reinforcement arranging method for wall type rigid-frame construction
JP3069725B2 (en) How to build the basement frame
JPH03147926A (en) construction method for basement
JPH0657958B2 (en) Reverse floor construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051014

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070927

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20071009

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20071108

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071211

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071213

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101221

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111221

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111221

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121221

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121221

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131221

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees