JP4011269B2 - Work result management apparatus, work plan support apparatus, and storage medium storing a program for causing a computer to perform processing in these apparatuses - Google Patents

Work result management apparatus, work plan support apparatus, and storage medium storing a program for causing a computer to perform processing in these apparatuses Download PDF

Info

Publication number
JP4011269B2
JP4011269B2 JP2000215088A JP2000215088A JP4011269B2 JP 4011269 B2 JP4011269 B2 JP 4011269B2 JP 2000215088 A JP2000215088 A JP 2000215088A JP 2000215088 A JP2000215088 A JP 2000215088A JP 4011269 B2 JP4011269 B2 JP 4011269B2
Authority
JP
Japan
Prior art keywords
information
project
work
schedule
work process
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000215088A
Other languages
Japanese (ja)
Other versions
JP2002032225A (en
Inventor
守克 ▲廣▼瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP2000215088A priority Critical patent/JP4011269B2/en
Publication of JP2002032225A publication Critical patent/JP2002032225A/en
Application granted granted Critical
Publication of JP4011269B2 publication Critical patent/JP4011269B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Stored Programmes (AREA)
  • User Interface Of Digital Computer (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、プロジェクトを管理する作業実績管理装置および既存プロジェクトを参照しつつ新規プロジェクトの計画を支援する作業計画支援装置に係り、詳しくは、プロジェクトを構成する作業工程に関する情報と、各作業工程の予定と実績との差を示す乖離情報とを関連付けして管理する作業実績管理装置、および、既存プロジェクトを参照しつつ、既存プロジェクトを構成する各作業工程に応じた乖離情報に基づいて、新規プロジェクトの予定計画策定を支援する作業計画支援装置を提供するものである。
【0002】
また、本発明は、それらの装置での処理をコンピュータに行なわせるためのプログラムを格納した記憶媒体に関する。
【0003】
【従来の技術】
情報処理システムの開発プロジェクトにおいて、ドキュメントとプログラムは、プロジェクトの中心的な開発対象成果物である。従って、一般的に、プロジェクトの開始時期や各工程でのスケジュール見直し時期に、プロジェクトの計画(スケジュール、必要リソースなど)を立案または変更し、立案または変更した作業計画に基づいてドキュメントやプログラムの作成が行なわれる。
【0004】
この際に用いられるスケジュール管理ツール(例えば、市販のMS-Project98等)は、タスク名、必要資源(人、物、日数)、開始終了日等で構成され、タスク間の関連について管理することができた。
【0005】
また、表計算ソフトやワープロで作成した一覧表で、成果物の名称、担当者、成果物の量等を管理することも行なわれている。
【0006】
【発明が解決しようとする課題】
一般に、プロジェクトを推進する際に、作業スケジュールが当初計画どおりに進むことは稀であり、そのため、予定と実績は乖離(実績値が遅延しがち)する場合がある。
【0007】
しかし、従来の上記管理方法は、あるタスクの開始日と終了日の予定/実績や担当者名、ページ数やステップ数等の成果物の量の予定/実績に関する情報を管理しているが、予定と実績との乖離(主に、遅延理由)を、その都度記録する手段がないため、後でプロジェクトの評価をする際、作業担当者の記憶に頼るか、作業担当者が作成したメモや作業記録に頼るという不都合があった。そのため、プロジェクトの評価が曖昧になるという問題があった。
【0008】
また、従来の上記管理方法は、作業タスク毎の予定と実績に関する情報と、先行タスクと後続タスク間で受け渡される『オブジェクト』(=成果物)との関係を定義しているが、先行プロジェクトの事例を、そのまま、後続プロジェクトのスケジュール作成時に参考にする場合、そのプロジェクトの成果物を精査して、参考となるかを判断しなければならなかった。
【0009】
さらに、具体的な成果物(設計書、プログラム又はロードモジュール)については、作業スケジュールとは別にライブラリ管理されており、ある作業タスクで作成した成果物がどれであるかを特定することは困難であった。たとえ成果物名が判っていたとしても、膨大な量のライブラリ中より、容易に特定する手段がなかった。
【0010】
このような管理方法において、過去の事例としてスケジュールの予定と実績を示しても、そのスケジュール上のあるタスクで作成する具体的な成果物を、その成果物の名称のみから予測するのは困難であり、作業の乖離理由(遅延理由)が明確でないため、どの程度の工数を投入するのが妥当であるかを見積ることが困難である等の問題があった。
【0011】
よって、特にプロジェクト管理の初心者が、過去の事例として提示されたスケジュールを元にして、自分の担当するプロジェクトのスケジュールを独力で作成することは不可能に近く、プロジェクト管理の経験者が逐一指導しながらスケジュールを作成していく必要があり、スケジュール作成のノウハウを伝授するのに時間を要していた。
【0012】
よって、プロジェクトに関する各タスクの予定と実績との乖離理由を容易に参照できるとともに、各タスクに関する実際の成果物の取得を容易に行なえることが望まれている。
【0013】
そこで、本発明の課題は、プロジェクトを構成する作業工程に関する情報と、各作業工程の予定と実績との差を示す乖離情報とを関連付けして管理し、既存プロジェクトを参照しつつ、既存プロジェクトを構成する各作業工程に応じた乖離情報に基づいて、新規プロジェクトの予定計画策定を支援する作業実績管理装置を提供することである。
【0015】
【課題を解決するための手段】
上記課題を解決するため、本発明は、複数の作業工程情報で構成される既存プロジェクト情報を参照し、該複数の作業工程情報内の予定情報と実績情報とに基づいて、新規プロジェクト情報の生成支援を行う作業実績管理装置において、存プロジェクト作業工程に予定情報と予定情報に応じて入力された実績情報とを管理する作業工程情報と、該予定情報と該実績情報とに差を生じさせた理由を示す乖離情報とを関連付けて既存プロジェクト情報として第一データベースに記憶することによって管理する第一の管理手段と、上記新規プロジェクト情報を特定する新規プロジェクトコードと、該新規プロジェクト参照される上記既存プロジェクト情報を特定する参照プロジェクトコードとを入力するための入力域を備えた画面を表示手段に表示させる表示制御手段と、上記画面より入力された参照プロジェクトコードを用いて上記第一データベースから上記参照される既存プロジェクト情報を検索する既存プロジェクト検索手段と、上記検索された既存プロジェクト情報に含まれる上記乖離情報に基づいて、当該既存プロジェクト情報の上記作業工程情報に含まれる上記予定情報または上記実績情報のいずれかを新規プロジェクト情報の作業工程情報の予定情報とするかを判断する判断手段と、上記判断手段によって判断された上記既存プロジェクト情報の上記各作業工程情報に含まれる上記予定情報または上記実績情報のいずれかに基づいて、入力された新規プロジェクトの開始日を起点日として、上記新規プロジェクト情報の各作業工程情報の予定情報を決定する予定情報決定手段とを有するように構成される。
【0017】
【発明の実施の形態】
以下、本発明の実施の形態を図面に基づいて説明する。
【0018】
本発明の実施の一形態に係る作業実績管理装置及び作業計画支援装置が構成されるコンピュータシステムのハードウェア構成は、例えば、図1に示すようになっている。
【0019】
図1において、この作業実績管理装置100及び作業計画支援装置200は、CPU(中央演算処理ユニット)11、メモリユニット12、出力ユニット13、入力ユニット14、表示ユニット15、補助記憶装置16及びCD−ROMドライブユニット17を有している。これらの各ユニット11、12、13、14、15、16及びCD−ROMドライブユニット17は、バスBに接続されている。
【0020】
CPU11は、メモリユニット12に格納されたプログラムに従って当該作業実績管理装置を制御すると共に、後述するような作業実績管理装置での処理を行う。メモリユニット12は、RAM及びROMにて構成され、CPU11にて実行されるプログラム、CPU11での処理に必要なデータ、CPU11での処理にて得られたデータ等を格納する。また、メモリユニット12の一部の領域が、CPU11での処理に利用されるワークエリアとして割り付けられている。
【0021】
入力ユニット14は、マウス、キーボード等を有し、利用者が後述するような作業実績管理処理を行なうためのデータ入力や入力したデータの変更等、必要な各種情報を入力するために用いられる。表示ユニット16は、CPU11の制御のもとに利用者に必要な各種情報を表示する。
【0022】
補助記憶装置16は、例えば、ハードディスクユニットにて構成され、各種ファイル、テーブル、プログラムを格納する。
【0023】
作業実績管理処理に係るプログラムは、例えば、CD−ROM20によって当該システムに提供される。即ち、作業実績管理処理に係るプログラムが保存されたCD−ROM20がCD−ROMドライブユニット17にセットされると、CD−ROMドライブユニット17がCD−ROM20から当該プログラムを読み出し、その読み出されたプログラムがバスBを介して補助記憶装置16にインストールされる。そして、この作業実績管理処理が起動されると、補助記憶装置16にインストールされた当該プログラムに従ってCPU11がその処理を開始する。尚、当該プログラムを格納する媒体としてCD−ROM20に限定するものではなく、コンピュータが読み取り可能な媒体であればよい。
【0024】
図2は、データの関連構成を示す図である。
【0025】
図2より、作業実績管理装置100及び作業計画支援装置200で管理されるデータの中核部分の関連構成は、8個のエンティティで構成され、プロジェクト30と、組織31と、人32と、工程33と、プロセス34と、タスク35と、オブジェクト36と、乖離理由37とを有する。
【0026】
1つのプロジェクト30は、複数の組織に割り当てられる。
【0027】
1つの組織31は、複数の組織を構成し、また、1つの組織32に複数の人32が所属する。
【0028】
上記1つのプロジェクト30は複数の工程33に分割され、1つの工程33は複数のプロセス34分割される。さらに、1つのプロセス34は複数のタスクに分割される。複数のタスク35は複数のタスク35と関連する。
【0029】
乖離理由37はタスク35を分類し、1つの乖離理由37は複数のタスク35に対応する。
【0030】
1つのタスク35は、複数のオブジェクト36を入力、又は、複数のオブジェクト36を出力する。また、複数のタスク35は、複数の人32が担当し、複数の人32によって管理される。
【0031】
1人の人32は、複数のオブジェクト36を作成する。
【0032】
次に、上記各エンティティに対応するテーブルについて、図3から図8で説明する。図3から図8で示されるテーブルは、図1の補助記憶装置16に格納される。
【0033】
図3から図8に示されるテーブルにおいて、実線付き項目は、そのテーブル内のキーを示し、点線付き項目は、そのテーブル内の外部キー(他テーブルを参照するためのキー)を示す。
【0034】
図3(A)に示されるプロジェクトテーブルT30は、図2のプロジェクト30に対応し、レコードの連番を示すSEQ.、プロジェクト毎に一意に与えられるプロジェクトコード、プロジェクト名を示すプロジェクト名及びプロジェクトのオーダ番号を示すオーダ番号等とで構成される。
【0035】
図3(A)より、例えば、SEQ.「0001」のプロジェクトコードは「PJ0010」、プロジェクト名は「Aシステム開発」、オーダ番号は「AA92050」となる。
【0036】
図3(B)に示される組織テーブルT31は、図2の組織31に対応し、レコードの連番を示すSEQ.、組織毎に一意に与えられる組織コード、プロジェクト毎に一意に与えられプロジェクトテーブルT30で管理されるプロジェクトコード、組織名、親組織の組織コードを示す親組織コード等とで構成される。
【0037】
図3(B)より、例えば、SEQ.「0001」の組織コードは「2929」、プロジェクトコードは「PJ0010」、組織名は「第一事業部」、親組織コードは「(空欄)」(自分が親組織の場合は空欄)となる。
【0038】
図4(A)に示される人テーブルT32は、図2の人32に対応し、レコードの連番を示すSEQ.、担当者に一意に与えられた担当者コード、担当者名、担当者のSE経験年数、担当者が保有する保有資格等とで構成される。
【0039】
図4(A)より、例えば、SEQ.「0001」の担当者コードは「19900256」、担当者名は「○山 □男」、SE経験年数は「10年」、保有資格は「情報処理1種」となる。
【0040】
図4(B)に示される工程テーブルT33は、図2の工程32に対応し、レコードの連番を示すSEQ.、工程毎に一意に与えられた工程コード、プロジェクト毎に一意に与えられプロジェクトテーブルT30で管理されるプロジェクトコード、工程名称等とで構成される。
【0041】
図4(B)より、例えば、SEQ.「0001」の工程コードは「SP」、プロジェクトコードは「PJ0010」、工程名称は「システム企画工程」となる。
【0042】
図5に示されるプロセステーブルT34は、図2のプロセス34に対応し、レコードの連番を示すSEQ.、各プロセスに一意に与えられたプロセスコード、工程毎に一意に与えられた工程テーブルT33で管理される工程コード、プロセス名等とで構成される。
【0043】
図5より、例えば、SEQ.「0001」のプロセスコードは「A1SA」、工程コードは「SA」、プロセス名は「業務方式設計」となる。
【0044】
図6に示されるタスクテーブルT35は、図2のタスク35に対応し、レコードの連番を示すSEQ.、各タスクに一意に与えられたタスクコード、各プロセスに一意に与えられ上記プロセステーブルT34で管理されるプロセスコード、親タスクを示す親タスクコード、先行するタスクを示す先行タスクコード、後続するタスクを示す後続タスクコード、タスク名、予定開始日、予定終了日、実績開始日、実績終了日、レビュー完了日、予定工数、実績工数、予定金額、実績金額、担当者コード、乖離理由テーブルT37(後述)で管理される乖離理由コード、担当者によって入力された乖離理由、進捗率(分母)、進捗率(分子)等とで構成される。
【0045】
上記乖離理由は、予定の人月工数、予定のプログラム工数、又は、予定の金額に対する実績との乖離が起きた理由を示す。
【0046】
図6より、例えば、SEQ.「0001」のタスクコードは「A1SA2」、プロセスコードは「SA」、親タスクコード及び先行タスクコードは「(空欄)」(親タスク及び先行タスクが存在しない場合はそれぞれ空欄)、後続タスクコードは「A1SA3」、タスク名は「現行業務の調査」、予定開始日は「1999.08.01」、予定終了日は「1999.08.31」、実績開始日は「1999.08.01」、実績終了日は「1999.09.10」、レビュー完了日は「1999.09.24」、予定工数は「300h」、実績工数は「350h」、予定金額は「300万円」、実績金額は「320万円」、担当者コードは「19900256」、乖離理由コードは「70890」、乖離理由は「見積りミス」、進捗率(分母)は「100」、進捗率(分子)は「100」となる。
【0047】
図7に示されるオブジェクトテーブルT36は、図2のオブジェクト36に対応し、レコードの連番を示すSEQ.、各オブジェクトに一意に与えられたオブジェクトコード、入力タスクコード、出力タスクコード、オブジェクト名称、実体ファイル名、実体格納先、オブジェクトサイズ、版数等とで構成される。
【0048】
上記実体格納先は、例えば、URLアドレス、または、ディレクトリ情報でオブジェクトの格納先を示す。
【0049】
図7より、例えば、SEQ.「1000」のオブジェクトコードは「CUD00100」、入力タスクコードは「(空欄)」(該当するタスクコードが無い場合は空欄)、出力タスクコード「C1PS」、オブジェクト名称は「チェック更新定義」、実体ファイル名は「PGM00100.CUD」、実体格納先は「http://dicserv.〜.〜.co.jp」、オブジェクトサイズは「267800byte」、版数は「3」となる。
【0050】
図8に示される乖離理由テーブルT37は、図2の乖離理由37に対応し、レコードの連番を示すSEQ.、乖離理由分類に応じて一意に与えられた乖離理由コード、乖離理由分類名称、乖離理由分類区分等とで構成される。
【0051】
図8より、例えば、SEQ.「0010」の乖離理由コードは「00100」、乖離理由分類名称は「誤差範囲(許容範囲)」、乖離理由分類区分は「0」となる。
【0052】
次に、作業実績管理装置100のCPU11によって実行される作業実績管理処理について、図9、図10及び図11で説明する。
【0053】
図9は、予定情報入力画面の例を示す図である。
【0054】
図9において、作業実績管理処理によって図1に示す表示ユニット15に表示される予定情報入力画面110は、タスクの予定情報と実績情報を管理するため、タスク情報を入力する画面であり、主に、工程管理情報域120と文書管理情報域130とで構成される。
【0055】
さらに、工程管理情報域120は、タスクテーブルT35と関連付けて構成される工程管理情報テーブルから、タスク名121に応じたレコードに基づいて情報を入力または表示する領域である。
【0056】
工程管理情報テーブルは、タスクコード、タスク名、担当者コード、進捗率(分母)、進捗率(分子)、予定開始日、予定終了日、実績開始日、実績終了日、乖離理由コード、乖離理由等とで構成される。人テーブルT32と関連付けすることによって、担当者コードに担当者名が対応付けられる。
【0057】
また、文書管理情報域130は、オブジェクトテーブルT36と関連付けて構成される文書管理情報テーブルから、上記工程管理情報域120のタスク名121に応じたレコードに基づいて情報を入力または表示する領域である。
【0058】
上記より、乖離理由コード140と乖離理由141がタスク毎に管理される。
【0059】
文書管理情報テーブルは、文書コード、文書名、URL/file名、V/L、部署名、作成者コード、テンプレートコード、最終改版日等とで構成される。文書コード、文書名及びURL/file名は、それぞれオブジェクトテーブルT36のオブジェクトコード、オブジェクト名称、実体格納先に対応する。
【0060】
図10は、作業実績管理処理を説明するフローチャート図である。また、図11は、作業実績管理処理の概略を示す図である。
【0061】
図10より、図9の予定情報入力画面110を表示する(ステップS41)。
表示された予定情報入力画面110に予定開始日や予定終了日、担当者を入力すると、図11の工程管理情報エントリ処理151は、入力された項目のチェックを行う(ステップS43)。項目のチェック後、工程管理情報エントリ処理151は、工程管理情報データベース152へ情報を格納する(ステップS44)。
図11より、工程管理情報データベース152は、上記工程管理情報テーブル及び上記文書管理情報テーブルを管理する。
【0062】
予定情報に応じた実績情報を入力する実績情報入力画面は、図9に示す予定情報入力画面110と同様の構成であって、作業完了時に、または、1日の作業を終えた時に、実績に関する情報を入力するために起動される(ステップS45)。
【0063】
表示された実績情報入力画面(予定情報入力画面110)から、実績開始日、実績終了日、進捗率、乖離理由コード及び乖離理由等の工程管理情報と、成果物に関する文書名(オブジェクト名称)及びURL/file名(オブジェクトの格納先)等の文書管理情報とを入力する(ステップS46)。さらに、オブジェクト(成果物)に関するV/L、部署名、作成者、テンプレート、最終改版日等の詳細情報を入力する(ステップS47)。この場合、図9に示す文書管理情報域130には、タスク名「注文明細累計(PGM0010)」の作業で作成された成果物として「チェック更新定義」、「業務関数定義書」、「レコード定義書」とが入力される。
【0064】
実績情報入力画面の『更新』ボタン(図示せず)を押すことによって、工程管理情報エントリ処理151が起動し(ステップS48)、工程管理情報データベース152へ情報を格納する(ステップS49)と共に、成果物データベース153で管理されるオブジェクトテーブルT36との関連付けをチェックした後、作業実績管理処理を終了する(ステップS50)。
【0065】
上記作業実績管理処理によって、タスク毎に、乖離理由コード140と乖離理由141で示される乖離情報が管理され、また、タスク毎に関連する成果物(文書またはプログラム)が管理される。従って、タスクの予定が実績と乖離した理由を容易に取得でき、かつ、乖離した成果物の情報を文書リストとして同一画面上で参照することができる。
【0066】
さらに、図11より、作業実績管理装置100において、図9の予定情報入力画面110の文書管理情報域130から、所望の文書名を選択する(例えば、クリックする)ことによって、成果物データベース153から選択された文書名に応じたURL/file名(格納先)を参照し該当文書データを取得し、その文書データ用のAPI(Application Program Interface)154によって図1の表示ユニット15に該文書データ155を表示する。
【0067】
上記より、乖離した理由を詳細に検証する場合等において、対象となる成果物の参照を容易に行なうことができる。
【0068】
次に、本発明の実施の一形態に係る作業計画支援装置200について説明する。作業計画支援装置200は、作業実績管理装置100のハードウェア構成と同様の構成を有する。
【0069】
作業計画支援装置200のCPU11によって実行される作業計画支援処理について、図12、図13及び図14で説明する。
【0070】
図12は、新プロジェクト情報編集画面の例を示す図である。
【0071】
図12において、作業計画支援処理によって図1に示す表示ユニット15に表示される新プロジェクト情報編集画面210は、新プロジェクトコード211と、新プロジェクト作業開始日212と、参照プロジェクトコード213と参照プロジェクト作業開始日214と、プロジェクト情報域220とで構成される。
【0072】
新プロジェクトコード211は、新規プロジェクトのプロジェクトコードを設定するための入力域である。
【0073】
新プロジェクト作業開始日212は、新規プロジェクトの開始予定日を設定するための入力域である。
【0074】
参照プロジェクトコード213は、新規プロジェクトで参照される既存のプロジェクトのプロジェクトコードを入力するための入力域である。
【0075】
参照プロジェクト作業開始日214には、上記参照プロジェクトコード213に入力されたプロジェクトの作業開始日が表示される。
【0076】
プロジェクト情報域220は、参照プロジェクトコード213で入力されたプロジェクトコードに応じたプロジェクトに関するタスクの情報が表示される。
【0077】
さらに、プロジェクト情報域220は、タスク毎に、予定開始日、予定終了日、実績開始日、実績終了日、予定工数、予定金額、実績工数、実績金額、乖離理由コード、乖離理由等とを表示する参照プロジェクト情報221と、それに対応させて予定開始日、予定終了日、予定工数、予定金額、担当者コード、保有資格等とを入力する作成プロジェクト情報222とを有する。
【0078】
この場合、参照プロジェクトコード213の入力値「PJ0010」に関連するタスクコード「A1SA2」、「A1SA3」等のタスク情報と、各タスクに関する予定情報と実績情報示す参照プロジェクト情報221が表示される。
【0079】
作成プロジェクト情報222には、参照プロジェクト情報221の乖離理由コード及び乖離理由を含む乖離情報に基づいて、参照プロジェクトの各タスクの実績を評価しつつ、予定情報が設定される。
【0080】
上記新プロジェクト情報編集画面210を用いて、参照プロジェクトを評価しつつ新規プロジェクトを設定する作業計画支援処理について、図13、図14及び図15で説明する。
【0081】
図13は、作業計画支援処理を説明するフローチャート図である。
【0082】
図13より、新規プロジェクトを設定する作業計画支援処理を起動すると、新プロジェクト情報編集画面210が表示される(ステップS61)。表示された新プロジェクト情報編集画面210で、新プロジェクトコード211、新プロジェクト開始日212及び参照プロジェクトコード213を入力すると(ステップS62)、図15に示すプロジェクト情報抽出処理230が起動する(ステップ6)。
【0083】
プロジェクト情報抽出処理230は、図1の補助記憶装置16に記録された既存(または旧)プロジェクトの情報を、図15に示す工程管理情報データベース及び成果物データベースから参照プロジェクト情報として読み込み(ステップS64)、新プロジェクト情報編集画面210のプロジェクト情報域220に表示する。
【0084】
さらに、プロジェクト情報抽出処理230は、各タスク情報を工程管理情報データベース152から取得し、日付修正処理P650を起動することによって、入力された新プロジェクト作業開始日212に基づいて、作成プロジェクト情報の予定開始日及び予定終了日を判断し、その判断結果に応じた予定工数及び予定金額を予測し、新プロジェクト情報編集画面210の作成プロジェクト情報222に表示する(S66)。
【0085】
例えば、日付修正処理P650によって、参考プロジェクトの予定開始日及び予定終了日が、新プロジェクトの予定開始日及び予定終了日として決定された場合、参考プロジェクトの予定工数及び予定金額が新プロジェクトの予定工数及び予定金額として表示される。一方、参考プロジェクトの実績開始日及び実績終了日が、新プロジェクトの予定開始日及び予定終了日として決定された場合、参考プロジェクトの実績工数及び実績金額が新プロジェクトの予定工数及び予定金額として表示される。
【0086】
利用者の予定情報の調整入力及び確認後、例えば、「確認」または「OK」ボタンのクリックによって(ステップS68)、図15に示す新規プロジェクト情報創成処理240が起動される(ステップS69)。
【0087】
起動された新規プロジェクト情報創成処理240は、新プロジェクト情報編集画面210のプロジェクト情報域220に表示されたタスク情報と各タスクに対応して予定情報が入力された作成プロジェクト情報222とに基づいて、新プロジェクトコード211に応じた工程管理情報及び文書管理情報を生成し、工程管理情報データベースに格納する(ステップS69)。また、各タスクの作成プロジェクト情報222に基づく文書管理情報が成果物データベースへ格納される。
【0088】
データベースへの格納が完了すると、作業計画支援処理を終了する。
【0089】
参照プロジェクトの各タスクを、乖離理由コード及び乖離理由に基づいて、予定と実績を評価する日付修正処理P650について説明する。
【0090】
図14は、日付修正処理を説明するフローチャート図である。
【0091】
図14より、起動された日付修正処理P650は、図15の工程管理情報データベース152から、新プロジェクト情報編集画面210の参照プロジェクトコード213に基づいて、工程管理情報データベース152からタスク毎に乖離理由コード及び乖離理由等の乖離情報を取得する(ステップS71)。
【0092】
取得した乖離理由コードに基づいて、図7に示す乖離理由テーブルT37から乖離理由分類区分を取り出し、該乖離理由分類区分に基づいて予定開始日及び予定終了日を示す予定情報及び実績開始日及び実績終了日を示す実績情報のいずれを採用すべきかを判断する(ステップS73)。
【0093】
乖離理由分類区分が‘0’の場合、ステップS74が実行され、タスク情報の予定開始日及び予定終了日が採用される。
【0094】
乖離理由分類区分が‘1’の場合、ステップS75が実行され、タスク情報の実績開始日及び実績終了日が採用される。
【0095】
乖離理由分類区分が‘2’の場合、ステップS74が実行され、タスク情報の実績開始日及び実績終了日が採用される。
【0096】
乖離理由分類区分が‘9’の場合、ステップS77が実行され、タスク情報の予定開始日及び予定終了日が採用される。
【0097】
取得したタスク毎の予定情報又は実績情報から所要日数を算出する(ステップS78)。
【0098】
算出された所要日数に基づいて、新プロジェクト作業開始日212を起点日とし、新規プロジェクトのタスクの作業開始日及び終了予定日を決定する(ステップS79)。
【0099】
図12の新プロジェクト情報編集画面210のプロジェクト情報域220において、例えば、項番1のタスクコード「A1SA2」の場合、参照プロジェクト情報221の乖離理由コード「70890」の乖離理由分類区分は、図7の乖離理由テーブルT37より‘2’となる。よって、ステップS37の判断によって、ステップS76が起動され、参照プロジェクト情報221の実績開始日「1999.08.01」及び実績終了日「1999.09.10」が採用される。
【0100】
そして、ステップS78によって、実績開始日「1999.08.01」及び実績終了日「1999.09.10」から所要日数が計算され、所要日数「40日」を得る。
【0101】
さらに、ステップS79によって、新プロジェクト作業開始日212の値「2001.04.01」に基づいて、タスクコード「A1SA2」の作成プロジェクト情報222の予定開始日に「2001.04.01」及び予定終了日に「2001.05.10」が新プロジェクト「PJ3000」の予定情報として決定する。
【0102】
また、項番2のタスクコード「A1SA3」の場合、参照プロジェクトの情報221の予定開始日「1999.09.11」及び予定終了日「1999.09.30」に基づいて、新プロジェクト「PJ3000」の予定情報が決定される。
【0103】
日付修正処理P650終了後、決定された新プロジェクトの予定情報が図12の新プロジェクト情報編集画面210の作成プロジェクト情報222に表示される。
【0104】
上記作業計画支援装置200は、新規のプロジェクトを生成する際に、参照プロジェクトの乖離情報に基づいて、該参照プロジェクトの予定情報と実績情報が評価され、その評価結果が新規プロジェクトの予定情報として採用される。
【0105】
また、該評価結果に基づいて、新プロジェクト作業開始日212を起点日として、予定開始日及び予定終了日が設定される。
【0106】
従って、タスク毎の作業経験が無いプロジェクト管理者でも、プロジェクト計画を容易に作成することが可能となる。
【0107】
上記作業計画支援処理の終了によって作成された新規プロジェクトを参照、或いは、実績情報等の入力による編集を行なう場合には、作業実績管理装置100による作業実績管理処理を起動し、表示された実績情報入力画面(図9の予定情報入画面110と同等)からタスク毎の実績情報を入力する。
【0108】
また、作業実績管理装置100によってタスク毎の予定情報を入力時、或いは、作業計画支援装置200によって新規プロジェクトの生成時等に、作業実績管理装置100によって表示された予定情報入力画面110又は作業計画支援装置200によって表示された新プロジェクト情報編集画面210に示されるタスク情報に加えて、他プロジェクトでのタスク情報または乖離情報を参照する場合、作業実績管理装置100及び作業計画支援装置200は後述する図16または図17に示す処理フローに従って、他プロジェクトでのタスク情報または乖離情報を提供することができる。
【0109】
図16は、成果物の検索処理を説明するフローチャート図である。
【0110】
図16より、所定のアイコンのクリック、或いは、予定情報入力画面110または新プロジェクト情報編集画面210のメニューバーからの選択によって成果物の検索処理を起動すると、実績紹介画面が図1の表示ユニット15に表示される(ステップS81)。
【0111】
表示された実績紹介画面から、検索キー項目情報を入力する(ステップS82)。該検索キー項目情報は、例えば、プロジェクトコード、工程コード、プロセスコード、又は、タスクコード等である。
【0112】
入力された検索キー項目情報に基づいて、工程管理情報データベース152を検索し関連するタスク情報を表示ユニット15に表示する(ステップS83)。
【0113】
利用者によって選択されたタスク情報に応じて、成果物のURL/file名(格納先情報)と、該URL/file名から取得したファイル種別情報とによって、成果物に応じたAPIを起動する(ステップS84)。
【0114】
APIの起動によって、選択されたタスク情報に応じた成果物が表示ユニット15に表示され(ステップS85)、成果物の検索処理を終了する。
【0115】
図17は、乖離理由の検索処理を説明するフローチャート図である。
【0116】
図17より、所定のアイコンのクリック、或いは、予定情報入力画面110または新プロジェクト情報編集画面210のメニューバーからの選択によって乖離理由の検索処理を起動すると、実績紹介画面が図1の表示ユニット15に表示される(ステップS91)。
【0117】
表示された実績紹介画面から、検索キー項目情報を入力する(ステップS92)。該検索キー項目情報は、例えば、タスクコード等である。
【0118】
入力された検索キー項目情報に基づいて、工程管理情報データベース152を検索し乖離理由コード及び乖離理由を含む乖離理由情報を表示ユニット15に表示し(ステップS93)、乖離理由の検索処理を終了する。
【0119】
上記実施例において、タスク毎に乖離情報を含む実績情報を管理し、新規プロジェクト210の作成時には、参照プロジェクトを指定することによって、関連するタスク情報を取得し、乖離情報を含むタスク情報に基づいて、タスク毎に新規プロジェクトの予定情報を容易に決定することができる。
【0120】
また、各タスク情報に対象となる成果物(設計書等の文書、プログラム等のオブジェクト又はロードモジュール)の名称及び格納先情報を関連付けしておくことで、新規プロジェクトを作成する際に、参照プロジェクトとして参照されたタスクを評価しながら、或いは、必要に応じて、タスクを参照しながら、新規プロジェクトの予定を計画することができる。
【0121】
なお、上記例において、図10に示すステップS44での処理が第一の格納手段に対応し、図10に示すステップS49及びS50での処理が第二の格納手段に対応する。
【0122】
また、図10に示すステップS41及び45での処理が表示制御手段に対応する。
【0123】
さらに、図13に示すステップS61での処理が表示制御手段に対応し、図13に示す処理P650での処理が判断手段に対応する。
【0124】
【発明の効果】
以上、説明してきたように、本発明によれば、作業工程の予定情報と実績情報とを、予定情報と実績情報の差異を示す乖離情報と関連付けされて格納される。また、作業工程に関連する成果物ファイル情報も関連付けされて格納される。従って、予定情報と実績情報の差異を容易に知ることができると共に、関連する成果物ファイルを参照することが容易となる。
【0125】
また、既存プロジェクトの各作業工程の乖離情報に基づいて、新規プロジェクトが生成されるため、各作業工程に関連する成果物の作成状況等を調査することなく、新規プロジェクトの予定情報を作成することができる。
【0126】
さらに、上記のような作業実績管理装置及び作業計画支援装置での処理をコンピュータに行なわせるためのプログラムを格納した記憶媒体を提供することができる。
【図面の簡単な説明】
【図1】図1は、ハードウェア構成を示す図である。
【図2】図2は、データの関連構成を示す図である。
【図3】図3は、テーブルの例を示す図である。
【図4】図4は、テーブルの例を示す図である。
【図5】図5は、テーブルの例を示す図である。
【図6】図6は、テーブルの例を示す図である。
【図7】図7は、テーブルの例を示す図である。
【図8】図8は、テーブルの例を示す図である。
【図9】図9は、予定情報入力画面の例を示す図である。
【図10】図10は、作業実績管理処理を説明するフローチャート図である。
【図11】図11は、作業実績管理処理の概略を示す図である。
【図12】図12は、新プロジェクト情報編集画面の例を示す図である。
【図13】図13は、作業計画支援処理を説明するフローチャート図である。
【図14】図14は、日付修正処理を説明するフローチャート図である。
【図15】図15は、作業計画支援処理の概略を示す図である。
【図16】図16は、成果物の検索処理を説明するフローチャート図である。
【図17】図17は、乖離理由の検索処理を説明するフローチャート図である。
【符号の説明】
11 CPU
12 メモリユニット
13 出力ユニット
14 入力ユニット
15 表示ユニット
16 補助記憶装置
17 CD−ROMドライバ
20 CD−ROM
B バス
100 作業実績管理装置
110 予定情報入力画面
140 乖離理由コード
141 乖離理由
152 工程管理情報データベース
153 成果物データベース
200 作業計画支援装置
210 新プロジェクト情報編集画面
220 プロジェクト情報域
250 日付修正処理
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a work performance management apparatus that manages a project and a work plan support apparatus that supports planning of a new project while referring to an existing project. More specifically, the present invention relates to information on work processes constituting a project, and information on each work process. A new project based on the work information management device that associates and manages divergence information that indicates the difference between the schedule and the actual result, and the divergence information corresponding to each work process that constitutes the existing project while referring to the existing project It is intended to provide a work plan support device that supports the creation of a schedule plan.
[0002]
The present invention also relates to a storage medium storing a program for causing a computer to perform processing in these devices.
[0003]
[Prior art]
In an information processing system development project, documents and programs are the main development target products of the project. Therefore, in general, project plans (schedules, required resources, etc.) are drafted or changed at the start of the project or at the time of reviewing the schedule in each process, and documents and programs are created based on the drafted or changed work plan. Is done.
[0004]
The schedule management tool (for example, commercially available MS-Project 98) used at this time is composed of task name, necessary resources (people, things, days), start and end dates, etc., and can manage the relationship between tasks. did it.
[0005]
In addition, the name of the deliverable, the person in charge, the amount of the deliverable, and the like are managed using a list created by spreadsheet software or a word processor.
[0006]
[Problems to be solved by the invention]
In general, when a project is promoted, it is rare that the work schedule proceeds as originally planned, and therefore there is a case where the plan and the actual result are different (the actual value tends to be delayed).
[0007]
However, the above-mentioned conventional management method manages information on the schedule / actuals of the amount of deliverables such as the schedule / actual result, the name of the person in charge, the number of pages, the number of steps, etc. Since there is no way to record the discrepancy between the plan and the actual result (mainly the reason for delay) each time, when evaluating the project later, it depends on the memory of the worker, There was the inconvenience of relying on work records. Therefore, there was a problem that the evaluation of the project became ambiguous.
[0008]
In addition, the conventional management method defines the relationship between the information on the schedule and results for each work task and the “object” (= deliverable) passed between the preceding task and the succeeding task. In order to refer to this case as it is when creating a schedule for a subsequent project, it was necessary to examine the deliverables of that project and determine whether it would be helpful.
[0009]
In addition, specific deliverables (design documents, programs, or load modules) are managed separately from the work schedule, and it is difficult to identify which deliverables were created in a work task. there were. Even if the product name was known, there was no easy way to identify it from a huge amount of libraries.
[0010]
In such a management method, it is difficult to predict the specific deliverables created by a certain task on the schedule only from the names of the deliverables, even if the schedule schedule and results are shown as past cases. In addition, since the reason for work divergence (reason for delay) is not clear, it has been difficult to estimate how much man-hours are appropriate.
[0011]
Therefore, it is almost impossible for project management beginners to create their own project schedules based on the schedules presented as past cases. However, it was necessary to create a schedule, and it took time to transfer the know-how of creating a schedule.
[0012]
Therefore, it is desirable to be able to easily refer to the reason for the divergence between the schedule and results of each task related to the project, and to easily acquire actual deliverables related to each task.
[0013]
Therefore, the problem of the present invention is to manage information relating to work processes constituting a project and divergence information indicating the difference between the schedule and the actual result of each work process. Supporting the planning of a new project based on deviation information corresponding to each work process that constitutes the existing project while referring to the existing project It is to provide a work performance management apparatus.
[0015]
[Means for Solving the Problems]
In order to solve the above problems, the present invention refers to existing project information composed of a plurality of work process information, and generates new project information based on schedule information and performance information in the plurality of work process information. In the work performance management device that provides support, Already Existing project of Working process every The work process information for managing the schedule information and the result information input according to the schedule information is associated with the deviation information indicating the reason for the difference between the schedule information and the result information. As existing project information First management means for managing by storing in the first database, a new project code for specifying the new project information, and the new project so Display control means for displaying on the display means a screen having an input area for inputting the reference project code for specifying the existing project information to be referred to, and the reference project code input from the screen using the reference project code. Based on the existing project search means for searching the existing project information referred to from one database, and the deviation information included in the searched existing project information, Concerned Judgment means for judging whether either the schedule information or the performance information included in the work process information of the existing project information is the schedule information of the work process information of the new project information, and the judgment made by the judgment means Based on either the schedule information or the performance information included in each work process information of the existing project information, the schedule of each work process information of the new project information is based on the start date of the input new project. And a schedule information determining means for determining information.
[0017]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0018]
A hardware configuration of a computer system in which a work performance management apparatus and a work plan support apparatus according to an embodiment of the present invention are configured is, for example, as shown in FIG.
[0019]
In FIG. 1, the work performance management apparatus 100 and the work plan support apparatus 200 include a CPU (Central Processing Unit) 11, a memory unit 12, an output unit 13, an input unit 14, a display unit 15, an auxiliary storage device 16, and a CD-. A ROM drive unit 17 is provided. These units 11, 12, 13, 14, 15, 16 and the CD-ROM drive unit 17 are connected to the bus B.
[0020]
The CPU 11 controls the work performance management apparatus according to the program stored in the memory unit 12 and performs processing in the work performance management apparatus as described later. The memory unit 12 includes a RAM and a ROM, and stores programs executed by the CPU 11, data necessary for processing by the CPU 11, data obtained by processing by the CPU 11, and the like. A part of the memory unit 12 is allocated as a work area used for processing by the CPU 11.
[0021]
The input unit 14 includes a mouse, a keyboard, and the like, and is used for inputting various necessary information such as data input for a user to perform work performance management processing as will be described later and changes in input data. The display unit 16 displays various information necessary for the user under the control of the CPU 11.
[0022]
The auxiliary storage device 16 is composed of, for example, a hard disk unit, and stores various files, tables, and programs.
[0023]
A program related to work performance management processing is provided to the system by, for example, the CD-ROM 20. That is, when the CD-ROM 20 storing the program related to the work performance management process is set in the CD-ROM drive unit 17, the CD-ROM drive unit 17 reads the program from the CD-ROM 20, and the read program is It is installed in the auxiliary storage device 16 via the bus B. When the work performance management process is activated, the CPU 11 starts the process according to the program installed in the auxiliary storage device 16. The medium for storing the program is not limited to the CD-ROM 20 and may be any computer-readable medium.
[0024]
FIG. 2 is a diagram illustrating a related configuration of data.
[0025]
As shown in FIG. 2, the related configuration of the core part of the data managed by the work performance management apparatus 100 and the work plan support apparatus 200 is composed of eight entities: a project 30, an organization 31, a person 32, and a process 33. And a process 34, a task 35, an object 36, and a divergence reason 37.
[0026]
One project 30 is assigned to a plurality of organizations.
[0027]
One organization 31 constitutes a plurality of organizations, and a plurality of people 32 belong to one organization 32.
[0028]
The one project 30 is divided into a plurality of processes 33, and one process 33 is divided into a plurality of processes 34. In Divided. Furthermore, one process 34 is divided into a plurality of tasks. The plurality of tasks 35 are related to the plurality of tasks 35.
[0029]
The divergence reasons 37 classify the tasks 35, and one divergence reason 37 corresponds to a plurality of tasks 35.
[0030]
One task 35 inputs a plurality of objects 36 or outputs a plurality of objects 36. The plurality of tasks 35 are handled by a plurality of people 32 and managed by the plurality of people 32.
[0031]
One person 32 creates a plurality of objects 36.
[0032]
Next, a table corresponding to each entity will be described with reference to FIGS. The tables shown in FIGS. 3 to 8 are stored in the auxiliary storage device 16 of FIG.
[0033]
In the tables shown in FIGS. 3 to 8, items with solid lines indicate keys in the table, and items with dotted lines indicate external keys (keys for referencing other tables) in the table.
[0034]
The project table T30 shown in FIG. 3A corresponds to the project 30 in FIG. And a project code uniquely given to each project, a project name indicating a project name, an order number indicating a project order number, and the like.
[0035]
From FIG. 3A, for example, SEQ. The project code of “0001” is “PJ0010”, the project name is “A system development”, and the order number is “AA92050”.
[0036]
The organization table T31 shown in FIG. 3B corresponds to the organization 31 in FIG. , An organization code uniquely given to each organization, a project code uniquely given to each project and managed by the project table T30, an organization name, a parent organization code indicating the organization code of the parent organization, and the like.
[0037]
From FIG. 3B, for example, SEQ. The organization code of “0001” is “2929”, the project code is “PJ0010”, the organization name is “first division”, and the parent organization code is “(blank)” (blank if you are the parent organization).
[0038]
The person table T32 shown in FIG. 4A corresponds to the person 32 in FIG. The person-in-charge code uniquely assigned to the person in charge, the person-in-charge name, the SE experience years of the person in charge, the possession qualifications held by the person in charge, etc.
[0039]
From FIG. 4A, for example, SEQ. The person-in-charge code of “0001” is “19900256”, the person-in-charge name is “Oyama □ male”, the SE experience years is “10 years”, and the possession qualification is “one type of information processing”.
[0040]
The process table T33 shown in FIG. 4B corresponds to the process 32 of FIG. The process code uniquely assigned to each process, the project code uniquely assigned to each project, and managed by the project table T30, the process name, and the like.
[0041]
From FIG. 4B, for example, SEQ. The process code of “0001” is “SP”, the project code is “PJ0010”, and the process name is “system planning process”.
[0042]
The process table T34 shown in FIG. 5 corresponds to the process 34 of FIG. The process code uniquely assigned to each process, the process code managed by the process table T33 uniquely assigned to each process, the process name, and the like.
[0043]
From FIG. 5, for example, SEQ. The process code “0001” is “A1SA”, the process code is “SA”, and the process name is “business method design”.
[0044]
The task table T35 shown in FIG. 6 corresponds to the task 35 of FIG. , A task code uniquely assigned to each task, a process code uniquely assigned to each process and managed by the process table T34, a parent task code indicating a parent task, a preceding task code indicating a preceding task, and a subsequent task Subsequent task code, task name, scheduled start date, scheduled end date, actual start date, actual end date, review completion date, planned man-hour, actual man-hour, planned amount, actual amount, person-in-charge code, divergence reason table T37 ( The divergence reason code managed in (described later), the divergence reason entered by the person in charge, the progress rate (denominator), the progress rate (numerator), and the like.
[0045]
The reason for the divergence indicates the reason why the divergence between the scheduled man-hour man-hour, the scheduled program man-hour, or the actual amount with respect to the scheduled amount has occurred.
[0046]
From FIG. 6, for example, SEQ. The task code of “0001” is “A1SA2”, the process code is “SA”, the parent task code and the preceding task code are “(blank)” (blank if there is no parent task and preceding task), and the succeeding task code is “A1SA3”, task name “investigation of current work”, scheduled start date “1999.08.01”, scheduled end date “1999.08.31”, actual start date “1999.08.01”, actual end date “1999.09” .10 ", review completion date is" 1999.09.24 ", planned man-hour is" 300h ", actual man-hour is" 350h ", planned amount is" 3 million yen ", actual amount is" 3.2 million yen ", “19900256”, the deviation reason code is “70890”, the reason for deviation is “estimation error”, the progress rate (denominator) is “100”, and the progress rate (numerator) is “100”.
[0047]
The object table T36 shown in FIG. 7 corresponds to the object 36 in FIG. The object code, input task code, output task code, object name, entity file name, entity storage destination, object size, version number, etc., uniquely assigned to each object.
[0048]
The entity storage location indicates the storage location of the object by, for example, a URL address or directory information.
[0049]
From FIG. 7, for example, SEQ. The object code of “1000” is “CUD00100”, the input task code is “(blank)” (blank if there is no corresponding task code), the output task code “C1PS”, the object name is “check update definition”, and the entity file The name is “PGM00100.CUD”, the entity storage destination is “http: //dicserv.˜.˜.co.jp”, the object size is “267800 bytes”, and the version number is “3”.
[0050]
The divergence reason table T37 shown in FIG. 8 corresponds to the divergence reason 37 in FIG. , A divergence reason code uniquely given according to the divergence reason classification, a divergence reason classification name, a divergence reason classification category, and the like.
[0051]
From FIG. 8, for example, SEQ. The deviation reason code of “0010” is “00100”, the deviation reason classification name is “error range (allowable range)”, and the deviation reason classification classification is “0”.
[0052]
Next, work performance management processing executed by the CPU 11 of the work performance management apparatus 100 will be described with reference to FIGS. 9, 10, and 11.
[0053]
FIG. 9 is a diagram illustrating an example of a schedule information input screen.
[0054]
In FIG. 9, the schedule information input screen 110 displayed on the display unit 15 shown in FIG. 1 by the work result management process is a screen for inputting task information in order to manage the task schedule information and the result information. The process management information area 120 and the document management information area 130 are configured.
[0055]
Further, the process management information area 120 is an area for inputting or displaying information based on a record corresponding to the task name 121 from the process management information table configured in association with the task table T35.
[0056]
Process management information table includes task code, task name, person in charge code, progress rate (denominator), progress rate (numerator), scheduled start date, scheduled end date, actual start date, actual end date, deviation reason code, deviation reason Etc. By associating with the person table T32, the person-in-charge name is associated with the person-in-charge code.
[0057]
The document management information area 130 is an area for inputting or displaying information based on a record corresponding to the task name 121 in the process management information area 120 from the document management information table configured in association with the object table T36. .
[0058]
From the above, the deviation reason code 140 and the deviation reason 141 are managed for each task.
[0059]
The document management information table includes a document code, document name, URL / file name, V / L, department name, creator code, template code, last revision date, and the like. The document code, document name, and URL / file name correspond to the object code, object name, and entity storage location of the object table T36, respectively.
[0060]
FIG. 10 is a flowchart for explaining work performance management processing. Moreover, FIG. 11 is a figure which shows the outline of work performance management processing.
[0061]
From FIG. 10, the schedule information input screen 110 of FIG. 9 is displayed (step S41).
When a schedule start date, a schedule end date, and a person in charge are input on the displayed schedule information input screen 110, the process management information entry process 151 in FIG. 11 checks the input items (step S43). After checking the items, the process management information entry process 151 stores information in the process management information database 152 (step S44).
As shown in FIG. 11, the process management information database 152 manages the process management information table and the document management information table.
[0062]
The record information input screen for inputting record information corresponding to the schedule information has the same configuration as the schedule information input screen 110 shown in FIG. 9 and relates to the record when the work is completed or when the work for one day is finished. It is activated to input information (step S45).
[0063]
From the displayed record information input screen (schedule information input screen 110), process management information such as record start date, record end date, progress rate, divergence reason code and divergence reason, and document name (object name) related to the deliverable Document management information such as URL / file name (object storage destination) is input (step S46). Further, detailed information such as V / L, department name, creator, template, date of last revision, etc. regarding the object (product) is input (step S47). In this case, the document management information area 130 shown in FIG. 9 includes “check update definition”, “business function definition document”, “record definition” as deliverables created in the task name “cumulative order details (PGM0010)”. Is entered.
[0064]
By pressing an “update” button (not shown) on the result information input screen, the process management information entry process 151 is activated (step S48), and information is stored in the process management information database 152 (step S49). After checking the association with the object table T36 managed in the property database 153, the work performance management process is terminated (step S50).
[0065]
By the work performance management process, the divergence information indicated by the divergence reason code 140 and the divergence reason 141 is managed for each task, and the related product (document or program) is managed for each task. Therefore, the reason why the task schedule deviates from the actual result can be easily acquired, and information on the deviated deliverables can be referred to as a document list on the same screen.
[0066]
Further, referring to FIG. 11, the work result management apparatus 100 selects (for example, clicks) a desired document name from the document management information area 130 of the schedule information input screen 110 of FIG. The corresponding document data is obtained by referring to the URL / file name (storage location) corresponding to the selected document name, and the document data 155 is displayed on the display unit 15 of FIG. 1 by the API (Application Program Interface) 154 for the document data. Is displayed.
[0067]
From the above, when the reason for the deviation is verified in detail, the target product can be easily referred to.
[0068]
Next, a work plan support apparatus 200 according to an embodiment of the present invention will be described. The work plan support apparatus 200 has the same configuration as the hardware configuration of the work performance management apparatus 100.
[0069]
The work plan support process executed by the CPU 11 of the work plan support apparatus 200 will be described with reference to FIGS.
[0070]
FIG. 12 is a diagram illustrating an example of a new project information editing screen.
[0071]
12, the new project information editing screen 210 displayed on the display unit 15 shown in FIG. 1 by the work plan support process includes a new project code 211, a new project work start date 212, a reference project code 213, and a reference project work. It consists of a start date 214 and a project information area 220.
[0072]
The new project code 211 is an input area for setting a project code for a new project.
[0073]
The new project work start date 212 is an input area for setting a scheduled start date for a new project.
[0074]
The reference project code 213 is an input area for inputting a project code of an existing project referred to by a new project.
[0075]
In the reference project work start date 214, the work start date of the project input in the reference project code 213 is displayed.
[0076]
In the project information area 220, task information related to the project corresponding to the project code input as the reference project code 213 is displayed.
[0077]
Further, the project information area 220 displays, for each task, a scheduled start date, a scheduled end date, an actual start date, an actual end date, a planned man-hour, a planned amount, an actual man-hour, an actual amount, a deviation reason code, a reason for deviation, and the like. Reference project information 221 to be generated, and creation project information 222 for inputting a scheduled start date, a planned end date, a planned man-hour, a planned amount, a person-in-charge code, a possession qualification, and the like corresponding thereto.
[0078]
In this case, task information such as task codes “A1SA2” and “A1SA3” related to the input value “PJ0010” of the reference project code 213, schedule information and results information about each task The The reference project information 221 shown is displayed.
[0079]
In the created project information 222, schedule information is set while evaluating the performance of each task of the reference project based on the deviation information including the deviation reason code and the deviation reason of the reference project information 221.
[0080]
A work plan support process for setting a new project while evaluating a reference project using the new project information editing screen 210 will be described with reference to FIGS. 13, 14, and 15. FIG.
[0081]
FIG. 13 is a flowchart for explaining the work plan support process.
[0082]
From FIG. 13, when the work plan support process for setting a new project is started, a new project information editing screen 210 is displayed (step S61). When the new project code 211, the new project start date 212, and the reference project code 213 are input on the displayed new project information editing screen 210 (step S62), the project information extraction process 230 shown in FIG. 15 is started (step 6). 3 ).
[0083]
The project information extraction process 230 reads the existing (or old) project information recorded in the auxiliary storage device 16 of FIG. 1 as reference project information from the process management information database and product database shown in FIG. 15 (step S64). And displayed in the project information area 220 of the new project information editing screen 210.
[0084]
Further, the project information extraction process 230 acquires each task information from the process management information database 152, and starts the date correction process P650, so that the schedule of the created project information is based on the input new project work start date 212. The start date and the scheduled end date are determined, and the estimated man-hour and the estimated amount according to the determination result are predicted and displayed on the created project information 222 of the new project information editing screen 210 (S66).
[0085]
For example, when the scheduled start date and the scheduled end date of the reference project are determined as the scheduled start date and the scheduled end date of the new project by the date correction process P650, the planned man-hour and the planned amount of the reference project are determined as And displayed as the planned amount. On the other hand, when the actual project start date and actual project end date are determined as the planned start date and planned end date of the new project, the actual project man-hours and actual project amount for the reference project are displayed as the planned man-hours and planned project cost for the new project. The
[0086]
After adjustment input and confirmation of the user's schedule information, for example, by clicking the “confirm” or “OK” button (step S68), a new project information creation process 240 shown in FIG. 15 is started (step S69).
[0087]
The started new project information creation process 240 is based on the task information displayed in the project information area 220 of the new project information editing screen 210 and the created project information 222 in which schedule information is input corresponding to each task. Process management information and document management information corresponding to the new project code 211 are generated and stored in the process management information database (step S69). Also, document management information based on the creation project information 222 for each task is stored in the deliverable database.
[0088]
When the storage in the database is completed, the work plan support process is terminated.
[0089]
The date correction process P650 for evaluating the schedule and the performance of each task of the reference project based on the deviation reason code and the reason for deviation will be described.
[0090]
FIG. 14 is a flowchart for explaining the date correction process.
[0091]
As shown in FIG. 14, the started date correction process P650 is performed based on the reference project code 213 on the new project information editing screen 210 from the process management information database 152 in FIG. And divergence information, such as a divergence reason, is acquired (step S71).
[0092]
Based on the acquired divergence reason code, the divergence reason classification category is extracted from the divergence reason table T37 shown in FIG. 7, and based on the divergence reason category category, the schedule information indicating the planned start date and the planned end date, the actual start date, and the actual result are shown. It is determined which of the performance information indicating the end date should be adopted (step S73).
[0093]
If the divergence reason classification category is “0”, step S74 is executed, and the scheduled start date and scheduled end date of the task information are adopted.
[0094]
When the divergence reason classification category is “1”, step S75 is executed, and the actual start date and actual end date of the task information are adopted.
[0095]
When the divergence reason classification category is “2”, step S74 is executed, and the actual start date and actual end date of the task information are adopted.
[0096]
When the divergence reason classification category is “9”, step S77 is executed, and the scheduled start date and scheduled end date of the task information are adopted.
[0097]
The required number of days is calculated from the acquired schedule information or performance information for each task (step S78).
[0098]
Based on the calculated required number of days, the new project work start date 212 is used as the starting date, and the work start date and scheduled end date of the task of the new project are determined (step S79).
[0099]
In the project information area 220 of the new project information editing screen 210 of FIG. 12, for example, in the case of the task code “A1SA2” of item number 1, the divergence reason classification category of the divergence reason code “70890” of the reference project information 221 is shown in FIG. The difference reason table T37 is “2”. Accordingly, step S76 is activated by the determination in step S37, and the actual start date “1999.08.01” and actual end date “1999.09.10” of the reference project information 221 are adopted.
[0100]
In step S78, the required number of days is calculated from the actual start date “1999.08.01” and the actual end date “1999.09.10” to obtain the required number of days “40 days”.
[0101]
Further, in step S79, based on the value “2001.04.01” of the new project work start date 212, “2001.04.01” and the scheduled end date “2001.05” are created in the scheduled project start date 222 of the task code “A1SA2”. .10 "is determined as schedule information for the new project" PJ3000 ".
[0102]
In the case of the task code “A1SA3” of item number 2, the schedule information of the new project “PJ3000” is based on the scheduled start date “1999.09.11” and the scheduled end date “1999.09.30” of the reference project information 221. It is determined.
[0103]
After completion of the date correction process P650, the determined new project schedule information is displayed in the created project information 222 of the new project information editing screen 210 in FIG.
[0104]
When generating a new project, the work plan support apparatus 200 evaluates the schedule information and the actual information of the reference project based on the deviation information of the reference project, and adopts the evaluation result as the schedule information of the new project. Is done.
[0105]
Also, based on the evaluation result, the scheduled start date and the scheduled end date are set with the new project work start date 212 as the starting date.
[0106]
Therefore, even a project manager who has no work experience for each task can easily create a project plan.
[0107]
When referring to a new project created by the end of the work plan support process or editing by inputting actual information, the actual work information management apparatus 100 starts the actual work result management process and displays the displayed actual information. Input screen (schedule information input in Fig. 9 Power The result information for each task is input from the screen 110).
[0108]
The schedule information input screen 110 or the work plan displayed by the work result management apparatus 100 when the work result management apparatus 100 inputs schedule information for each task or when the work plan support apparatus 200 generates a new project. When referring to task information or deviation information in another project in addition to the task information displayed on the new project information editing screen 210 displayed by the support device 200, the work performance management device 100 and the work plan support device 200 will be described later. Task information or deviation information in another project can be provided according to the processing flow shown in FIG.
[0109]
FIG. 16 is a flowchart for explaining a search process for deliverables.
[0110]
From FIG. 16, when the search process of the deliverable is started by clicking a predetermined icon or selecting from the menu bar of the schedule information input screen 110 or the new project information editing screen 210, the result introduction screen is displayed on the display unit 15 of FIG. Is displayed (step S81).
[0111]
Search key item information is input from the displayed result introduction screen (step S82). The search key item information is, for example, a project code, a process code, a process code, or a task code.
[0112]
Based on the input search key item information, the process management information database 152 is searched and related task information is displayed on the display unit 15 (step S83).
[0113]
In accordance with the task information selected by the user, the API corresponding to the deliverable is activated by the URL / file name (storage location information) of the deliverable and the file type information acquired from the URL / file name ( Step S84).
[0114]
With the activation of the API, a deliverable corresponding to the selected task information is displayed on the display unit 15 (step S85), and the deliverable search process is terminated.
[0115]
FIG. 17 is a flowchart for explaining the search process for the reason for deviation.
[0116]
From FIG. 17, when the search process of the reason for divergence is activated by clicking a predetermined icon or selecting from the menu bar of the schedule information input screen 110 or the new project information editing screen 210, the result introduction screen displays the display unit 15 of FIG. (Step S91).
[0117]
Search key item information is input from the displayed result introduction screen (step S92). The search key item information is, for example, a task code.
[0118]
Based on the input search key item information, the process management information database 152 is searched to display deviation reason information including the deviation reason code and the deviation reason on the display unit 15 (step S93), and the deviation reason search processing is terminated. .
[0119]
In the above embodiment, track record information including deviation information is managed for each task, and when creating a new project 210, by specifying a reference project, related task information is obtained, and based on task information including deviation information The schedule information of a new project can be easily determined for each task.
[0120]
In addition, by associating each task information with the name of the target deliverable (document such as design document, object such as program or load module) and storage location information, when creating a new project, the reference project The schedule of a new project can be planned while evaluating the task referred to as, or referring to the task as necessary.
[0121]
In the above example, the process in step S44 shown in FIG. 10 corresponds to the first storage unit, and the processes in steps S49 and S50 shown in FIG. 10 correspond to the second storage unit.
[0122]
Further, the processing in steps S41 and S45 shown in FIG. 10 corresponds to the display control means.
[0123]
Furthermore, the process in step S61 shown in FIG. 13 corresponds to the display control means, and the process in process P650 shown in FIG. 13 corresponds to the determination means.
[0124]
【The invention's effect】
As described above, according to the present invention, the schedule information and performance information of the work process are stored in association with the divergence information indicating the difference between the schedule information and the performance information. Further, product file information related to the work process is also stored in association with each other. Therefore, it is possible to easily know the difference between the schedule information and the performance information and to easily refer to the related product file.
[0125]
In addition, since a new project is generated based on the deviation information of each work process of the existing project, it is necessary to create schedule information for the new project without investigating the creation status of deliverables related to each work process. Can do.
[0126]
Furthermore, it is possible to provide a storage medium that stores a program for causing a computer to perform the processes in the work performance management apparatus and the work plan support apparatus as described above.
[Brief description of the drawings]
FIG. 1 is a diagram illustrating a hardware configuration.
FIG. 2 is a diagram illustrating a related configuration of data.
FIG. 3 is a diagram illustrating an example of a table.
FIG. 4 is a diagram illustrating an example of a table.
FIG. 5 is a diagram illustrating an example of a table.
FIG. 6 is a diagram illustrating an example of a table.
FIG. 7 is a diagram illustrating an example of a table.
FIG. 8 is a diagram illustrating an example of a table.
FIG. 9 is a diagram illustrating an example of a schedule information input screen.
FIG. 10 is a flowchart illustrating work performance management processing.
FIG. 11 is a diagram showing an outline of work performance management processing;
FIG. 12 is a diagram illustrating an example of a new project information editing screen.
FIG. 13 is a flowchart for explaining work plan support processing;
FIG. 14 is a flowchart for explaining date correction processing;
FIG. 15 is a diagram showing an outline of work plan support processing;
FIG. 16 is a flowchart for explaining deliverable search processing;
FIG. 17 is a flowchart for explaining search processing for a reason for divergence;
[Explanation of symbols]
11 CPU
12 Memory unit
13 Output unit
14 Input unit
15 Display unit
16 Auxiliary storage
17 CD-ROM driver
20 CD-ROM
B bus
100 work performance management device
110 Schedule information input screen
140 Reason code for deviation
141 Reason for deviation
152 Process management information database
153 Product database
200 Work plan support device
210 New project information edit screen
220 Project information area
250 Date correction processing

Claims (5)

複数の作業工程情報で構成される既存プロジェクト情報を参照し、該複数の作業工程情報内の予定情報と実績情報とに基づいて、新規プロジェクト情報の生成支援を行う作業実績管理装置において、
存プロジェクト作業工程に予定情報と予定情報に応じて入力された実績情報とを管理する作業工程情報と、該予定情報と該実績情報とに差を生じさせた理由を示す乖離情報とを関連付けて既存プロジェクト情報として第一データベースに記憶することによって管理する第一の管理手段と、
上記新規プロジェクト情報を特定する新規プロジェクトコードと、該新規プロジェクト参照される上記既存プロジェクト情報を特定する参照プロジェクトコードとを入力するための入力域を備えた画面を表示手段に表示させる表示制御手段と、
上記画面より入力された参照プロジェクトコードを用いて上記第一データベースから上記参照される既存プロジェクト情報を検索する既存プロジェクト検索手段と、
上記検索された既存プロジェクト情報に含まれる上記乖離情報に基づいて、当該既存プロジェクト情報の上記作業工程情報に含まれる上記予定情報または上記実績情報のいずれかを新規プロジェクト情報の作業工程情報の予定情報とするかを判断する判断手段と、
上記判断手段によって判断された上記既存プロジェクト情報の上記各作業工程情報に含まれる上記予定情報または上記実績情報のいずれかに基づいて、入力された新規プロジェクトの開始日を起点日として、上記新規プロジェクト情報の各作業工程情報の予定情報を決定する予定情報決定手段とを有する作業実績管理装置。
With reference to existing project information composed of a plurality of work process information, based on the schedule information and the result information in the plurality of work process information, in the work result management apparatus for supporting the generation of new project information,
And the work process information to manage and record information that has been entered in accordance with the schedule information and schedule information for each work process of the existing project, and the deviation information indicating the reason that caused the difference between the the schedule information and the actual information A first management means for managing by associating and storing in the first database as existing project information ;
The new and new project code that identifies the project information, the existing project information display control means for displaying on the display means a screen with an input area for inputting a reference project code that identifies the referenced by the new project When,
Existing project search means for searching for the existing project information referred to from the first database using the reference project code input from the screen;
Based on the deviation information included in the retrieved existing project information, schedule information of the work process information of the new project information one of the schedule information or the performance information contained in the working process information of the existing project information A determination means for determining whether or not
Based on either the schedule information or the performance information included in each work process information of the existing project information determined by the determination means, the start date of the input new project is used as the starting date, and the new project A work performance management apparatus comprising schedule information determination means for determining schedule information of each work process information of information.
請求項1記載の作業実績管理装置において、
上記既存プロジェクト検索手段によって検索された既存プロジェクト構成する各作業工程情報に関する予定情報と実績情報と乖離情報とを含む作業工程情報を上記画面に表示させるようにした作業実績管理装置。
In the work performance management apparatus according to claim 1,
The existing project search schedule for each work process information constituting an existing project that was retrieved by means information and actual information and work record management apparatus the work process information so as to be displayed on the screen and a deviation information.
請求項1又は2記載の作業実績管理装置において、
上記既存プロジェクト情報の作業工程情報毎の実績情報の入力によって上記第一データベースを更新する実績情報更新手段を有する作業実績管理装置。
In the work performance management apparatus according to claim 1 or 2,
A work performance management apparatus having performance information update means for updating the first database by inputting performance information for each work process information of the existing project information.
請求項3又は4記載の作業実績管理装置において、
既存プロジェクトの作業工程で生成される成果物ファイルが格納されている格納先情報を有する成果物ファイル情報を上記既存プロジェクト情報の上記作業工程情報と関連付けて第二データベースに記憶することによって管理する第二の管理手段を有し、
上記画面に上記成果物ファイルの上記格納先情報を上記作業工程情報と対応させて表示するようにした作業実績管理装置。
In the work performance management apparatus according to claim 3 or 4,
The product file information having the storage location information in which the product file generated in the work process of the existing project is stored is stored in the second database in association with the work process information of the existing project information. Has two management means,
A work performance management apparatus configured to display the storage location information of the deliverable file on the screen in association with the work process information.
複数の作業工程情報で構成される既存プロジェクト情報を参照し、該複数の作業工程情報内の予定情報と実績情報とに基づいて、新規プロジェクト情報の生成支援を行う作業実績管理装置としてコンピュータを機能せるためのプログラムを格納した記憶媒体において、
上記新規プロジェクト情報を特定する新規プロジェクトコードと、該新規プロジェクト参照される上記既存プロジェクト情報を特定する参照プロジェクトコードとを入力するための入力域を備えた画面を表示手段に表示させる表示制御手順と、
上記画面より入力された参照プロジェクトコードを用いて、存プロジェクト作業工程に予定情報と予定情報に応じて入力された実績情報とを管理する作業工程情報と、該予定情報と該実績情報とに差を生じさせた理由を示す乖離情報とを関連付けて既存プロジェクト情報として記憶している第一データベースから上記参照される既存プロジェクト情報を検索する既存プロジェクト検索手順と、
上記検索された既存プロジェクト情報に含まれる上記乖離情報に基づいて、当該既存プロジェクト情報の上記作業工程情報に含まれる上記予定情報または上記実績情報のいずれかを新規プロジェクト情報の作業工程情報の予定情報とするかを判断する判断手順と、
上記判断手順によって判断された上記既存プロジェクトの上記各作業工程の上記予定情報または上記実績情報のいずれかに基づいて、入力された新規プロジェクトの開始日を起点日として、上記新規プロジェクト情報の各作業工程情報の予定情報を決定する予定情報決定手順とをコンピュータに実行させるためのプログラムを格納した記憶媒体。
The computer functions as a work performance management apparatus that refers to existing project information composed of a plurality of work process information and supports generation of new project information based on schedule information and performance information in the plurality of work process information. In a storage medium storing a program for
A new project code specifying the new project information, the display control procedure to be displayed on the display means a screen with an input area for inputting a reference project code that identifies the existing project information referenced in the new project When,
Using the reference project code inputted from the screen, and the work process information for managing the record information which has been input in response to the schedule information and schedule information for each work process of existing projects, the schedule information and the record information An existing project search procedure for searching the existing project information referenced above from the first database stored as the existing project information in association with the divergence information indicating the reason that caused the difference between
Based on the deviation information included in the retrieved existing project information, schedule information of the work process information of the new project information one of the schedule information or the performance information contained in the working process information of the existing project information A judgment procedure for judging whether or not
Based on either the schedule information or the performance information of each work process of the existing project determined by the determination procedure, each work of the new project information is based on the start date of the input new project. A storage medium storing a program for causing a computer to execute a schedule information determination procedure for determining schedule information of process information.
JP2000215088A 2000-07-14 2000-07-14 Work result management apparatus, work plan support apparatus, and storage medium storing a program for causing a computer to perform processing in these apparatuses Expired - Fee Related JP4011269B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000215088A JP4011269B2 (en) 2000-07-14 2000-07-14 Work result management apparatus, work plan support apparatus, and storage medium storing a program for causing a computer to perform processing in these apparatuses

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000215088A JP4011269B2 (en) 2000-07-14 2000-07-14 Work result management apparatus, work plan support apparatus, and storage medium storing a program for causing a computer to perform processing in these apparatuses

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2006307048A Division JP4696050B2 (en) 2006-11-13 2006-11-13 Work result management apparatus, work plan support apparatus, and storage medium storing a program for causing a computer to perform processing in these apparatuses

Publications (2)

Publication Number Publication Date
JP2002032225A JP2002032225A (en) 2002-01-31
JP4011269B2 true JP4011269B2 (en) 2007-11-21

Family

ID=18710567

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000215088A Expired - Fee Related JP4011269B2 (en) 2000-07-14 2000-07-14 Work result management apparatus, work plan support apparatus, and storage medium storing a program for causing a computer to perform processing in these apparatuses

Country Status (1)

Country Link
JP (1) JP4011269B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005148933A (en) * 2003-11-12 2005-06-09 Nec Corp Project management system and method
JP2005148963A (en) * 2003-11-13 2005-06-09 Hitachi Ltd Schedule and result management device
JP2011108145A (en) * 2009-11-20 2011-06-02 Prime Japan Co Ltd Settlement data analysis system
JP2011123700A (en) * 2009-12-11 2011-06-23 Prime Japan Co Ltd Settlement service evaluation system
JP6009327B2 (en) * 2012-11-14 2016-10-19 株式会社イトーキ Schedule management system

Also Published As

Publication number Publication date
JP2002032225A (en) 2002-01-31

Similar Documents

Publication Publication Date Title
US6901407B2 (en) System and method for updating project management scheduling charts
JP2001256333A (en) Operation allocation system and method, decentralized client-server system, and computer program storage medium
JP3323105B2 (en) Action execution management device and computer-readable recording medium storing a program for causing a computer to function as the device
JP3181994B2 (en) How to automatically create job flow specifications
JP2008217651A (en) Design support device, design support method and program
US11138534B1 (en) Apparatus and method for integrating construction project specifications and related submittal documentation
US20090222277A1 (en) Defining and implementing custom task processes
JP4011269B2 (en) Work result management apparatus, work plan support apparatus, and storage medium storing a program for causing a computer to perform processing in these apparatuses
JP3227066B2 (en) Program generation method using program parts
JP4069701B2 (en) Work support device
US6141665A (en) Model-based job supporting system and method thereof
JP4696050B2 (en) Work result management apparatus, work plan support apparatus, and storage medium storing a program for causing a computer to perform processing in these apparatuses
JP2010152699A (en) Method, system, device and program for reusing data
JP4312789B2 (en) Business continuity analysis program and business continuity analyzer
JP4088760B2 (en) Design work support device
JP2000242490A (en) Software development managing device, information presenting device, and program recording medium
JP2001076045A (en) Operation flowchart generation assisting device and recording medium thereof
JPH1083420A (en) Model-based operation support system and method therefor
JP2000215038A (en) Information management device and recording medium
JP6019818B2 (en) Management device, management program, management method
JP4032306B2 (en) Design work support device
JP2004310317A (en) Business support device
US20070260983A1 (en) Method for providing a summary of user activities
JP3424558B2 (en) Object management method
JP3695410B2 (en) Production technology management method and apparatus therefor

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060829

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060912

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061113

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070130

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070402

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070515

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070712

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070828

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070905

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100914

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100914

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110914

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120914

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120914

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130914

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees