JP3982026B2 - Workflow management system - Google Patents

Workflow management system Download PDF

Info

Publication number
JP3982026B2
JP3982026B2 JP27130797A JP27130797A JP3982026B2 JP 3982026 B2 JP3982026 B2 JP 3982026B2 JP 27130797 A JP27130797 A JP 27130797A JP 27130797 A JP27130797 A JP 27130797A JP 3982026 B2 JP3982026 B2 JP 3982026B2
Authority
JP
Japan
Prior art keywords
schedule
information
work
database device
rough
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP27130797A
Other languages
Japanese (ja)
Other versions
JPH11110453A (en
Inventor
慎一郎 小田
節夫 近藤
彰博 宮崎
英範 小川
雅哲 水落
理 佐々木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toppan Inc
Original Assignee
Toppan Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toppan Inc filed Critical Toppan Inc
Priority to JP27130797A priority Critical patent/JP3982026B2/en
Publication of JPH11110453A publication Critical patent/JPH11110453A/en
Application granted granted Critical
Publication of JP3982026B2 publication Critical patent/JP3982026B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Accessory Devices And Overall Control Thereof (AREA)
  • General Factory Administration (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、印刷物の受注、入稿、製版、出校等の製版工程を管理するためのワークフロー管理システムに関する。
【0002】
【従来の技術】
近年、電子化技術の進歩により、各種機器のデジタル化が進むと共に、これらデジタル機器の低価格化や性能の向上が図られている。また、この種のデジタル機器をネットワークを介して接続したインターネット、イントラネット、DTP(desk top publishing) の一般への普及が進んでいる。
【0003】
このような状況は、印刷物の製造分野において、印刷物を発注する得意先や、印刷物を制作する印刷会社にも影響を与えている。例えば、得意先や先方デザイン会社では、これらのデジタル機器が少額の投資で導入され、各デジタル機器によって製版業務の一部が行われ始めている。また、この種の得意先は、文章や写真などの通常のアナログデータの他、部品毎にデジタルデータ化した原稿をオンライン又はFD等の記憶媒体で印刷会社の印刷工場に入稿する場合が多々ある。この場合、印刷会社では、デジタルデータが得意先から入稿される関係上、入稿元の得意先との協同作業によって製版工程が行われる。なお、アナログデータが入稿されるときには印刷会社にてデジタルデータへの変換が行われる。
【0004】
ところで、製版工程では、得意先からのデジタルデータを用いるため、得意先の制作の都合が作業段取りへ影響を与えてしまう。また、デジタルデータ化された原稿が部品毎にネットワークを介して得意先から入稿される場合、製版用のフィルムの完成まで、原稿の入稿及び処理の流れが不透明で把握しにくい問題がある。
【0005】
さらに、印刷会社においては、入稿の際にデジタルデータとアナログデータとが混在するため、営業、生産管理、現場とも業務内容が従来とは異なる内容に変わる。例えば、作業の流れ(以下、作業フロー又はワークフローともいう)が品目毎に全く違うようになるので、確認作業の頻度が増え、内部の管理業務が増える問題が生じる。なお、この種の確認作業は、前述した処理等の流れの不透明さからも、頻度が増える。
【0006】
【発明が解決しようとする課題】
以上説明したように印刷物の製造分野では、デジタル化が進む状況の下、確認作業や管理業務が増えることにより、営業の受注から下版までの製版工程の生産効率を低下させてしまう問題がある。このため、製版工程の生産効率の低下を少なくとも阻止し得る何らかの手段の実現が望まれている。
【0007】
本発明は上記実情を考慮してなされたもので、営業の受注から下版までの製版工程の生産効率を最大限に向上し得るワークフロー管理システムを提供することを目的とする。
【0008】
【課題を解決するための手段】
請求項1に対応する発明は、複数種類の工程からなる印刷物を製造するためのワークフロー管理システムにおいて、少なくとも前記印刷物に関する処理量情報及び日程情報と、単位当りの時間A、準備時間B、初校と後校の比率C及び倍率xからなる前記各工程の作業パラメータと、前記各工程の日付毎に、前記印刷物の識別情報を対応させた概略日程と、前記概略日程の各工程に用いられる各装置の前記日付内の時間帯毎に、前記印刷物の作業単位の識別情報を対応させた詳細日程と、が読出/書込可能に記憶されるデータベース装置と、少なくとも前記印刷物に関する処理量情報及び日程情報を前記データベース装置に入力するための事前情報入力手段と、前記作業パラメータを前記データベース装置に設定するための設定手段と、前記データベース装置内の作業パラメータに基づいて、各工程の標準作業時間=(A・x+B)×Cを算出し、得られた各工程の標準作業時間に開始可能日時を付加したコマを工程毎に作成し、得られた各コマと前記データベース装置内の処理量情報及び日程情報に基づいて、当該処理量情報に示される処理可能な量を超えないように、前記各工程の日付毎に、前記印刷物の識別情報を対応させた概略日程を立案し、この概略日程を前記データベース装置に書き込む概略日程立案手段と、
前記印刷物に用いられる原稿の入稿の際に、前記印刷物に関する処理量情報及び日程情報を確定的に前記データベース装置に入力するための入稿手段と、前記入稿手段により入力された前記データベース装置内の処理量情報及び日程情報に基づいて、前記概略日程立案手段により立案された前記データベース装置内の概略日程を詳細化し、前記各工程に用いられる各装置の前記日付内の時間帯毎に、前記印刷物の作業単位の識別情報を対応させた詳細日程を立案し、この詳細日程を前記データベース装置に書き込む詳細日程立案手段と、前記詳細日程立案手段により立案された前記データベース装置内の詳細日程に基づいて、作業指示を出力する作業指示手段とを備えたワークフロー管理システムである。
【0009】
また、請求項2に対応する発明は、請求項1に対応するワークフロー管理システムにおいて、前記事前情報入力手段により処理量情報及び日程情報が入力されるとき、前記概略日程の立案を開始させる立案依頼指令を前記概略日程立案手段に入力するための立案依頼手段と、前記概略日程立案手段により立案された前記データベース装置内の概略日程を出力し、この概略日程に対する承認通知を受けたとき、前記概略日程を確定し、前記概略日程に対する非承認通知を受けたとき、前記データベース装置内の概略日程を消去する日程承認手段とを備えたワークフロー管理システムである。
【0012】
(作用)
従って、請求項1に対応する発明は以上のような手段を講じたことにより、事前情報入力手段が、少なくとも印刷物に関する処理量情報及び日程情報をデータベース装置に入力し、設定手段が、作業パラメータをデータベース装置に設定し、概略日程立案手段が、データベース装置内の作業パラメータに基づいて、各工程の標準作業時間=(A・x+B)×Cを算出し、得られた各工程の標準作業時間に開始可能日時を付加したコマを工程毎に作成し、得られた各コマとデータベース装置内の処理量情報及び日程情報に基づいて、当該処理量情報に示される処理可能な量を超えないように、各工程の日付毎に、印刷物の識別情報を対応させた概略日程を立案し、この概略日程をデータベース装置に書き込み、入稿手段が、印刷物に用いられる原稿の入稿の際に、印刷物に関する処理量情報及び日程情報を確定的にデータベース装置に入力し、詳細日程立案手段が、入稿手段により入力されたデータベース装置内の処理量情報及び日程情報に基づいて、概略日程立案手段により立案されたデータベース装置内の概略日程を詳細化し、各工程に用いられる各装置の日付内の時間帯毎に、印刷物の作業単位の識別情報を対応させた詳細日程を立案し、この詳細日程をデータベース装置に書き込み、作業指示手段が、詳細日程立案手段により立案されたデータベース装置内の詳細日程に基づいて、作業指示を出力するので、人手による確認作業や管理業務を削減でき、もって、営業の受注から下版までの製版工程の生産効率を最大限に向上させることができる。また、各工程の日付毎の該当する処理可能な量を越えないように概略日程を立案するので、無理な概略日程を立案することがなく、概略日程の信頼性を向上させることができる。
【0013】
また、請求項2に対応する手段は、立案依頼手段が、事前情報入力手段により処理量情報及び日程情報が入力されるとき、概略日程の立案を開始させる立案依頼指令を概略日程立案手段に入力し、日程承認手段が、概略日程立案手段により立案されたデータベース装置内の概略日程を出力し、この概略日程に対する承認通知を受けたとき、概略日程を確定し、概略日程に対する非承認通知を受けたとき、データベース装置内の概略日程を消去するので、請求項1に対応する作用に加え、立案依頼者が概略日程を承認でき、もって、立案された概略日程の妥当性を向上させることができる。
【0016】
【発明の実施の形態】
以下、本発明の一実施形態について図面を参照しながら説明する。
【0017】
図1は本発明の一実施形態に係るワークフロー管理システムを含んだ受注製造管理システムの構成を示す模式図であり、図2はワークフロー管理システムと製版作業用の端末接続構成を示す図である。図3はワークフロー管理システムの構成を示す模式図である。
【0018】
ここで、受注製造管理システムは、例えば、管理ホスト1、複数の工場ホスト2、営業用端末3、入稿用端末4、スケジューラ用端末5、外注用端末6、データダイレクションサーバ7及び現場用端末8が夫々ネットワーク9を介してワークフロー管理システム10に接続されている。
【0019】
管理ホスト1は、印刷物の受注と伝達処理を管理するためのものであり、製版の生産活動を管理するワークフロー管理システムは、図4に示す階層構造のスキーマにより定義されたデータベースを有し、例えば、印刷物の受注情報d4、受注の内訳情報d5、内訳のまとまり情報(作業単位情報)d6や、折d7、ページd8及び実用版d9の別、さらに、まとまり情報d6毎に、部品情報d10、大日程フローd11、大日程コマ作業予定日d12、大日程メンバーd13、小日程フローd14、小日程コマ予定日時d15、小日程メンバーd16、小日程の作業の実績情報d17、事前情報d18、台割り情報d19、メンテナンスユーティリティ(パターン辞書d20a、メンバー辞書d20b、フロー辞書d20c及び作業パラメータ辞書d20dを含む)d20、大日程d21、小日程d22、入稿情報d23、大日程並びに小日程の進捗情報d24、がワークフロー管理システム10により読出/書込可能に設けられている。
【0020】
なお、大日程d21は、日付単位の概略日程であり、具体的には各工程毎の処理日程である。小日程d22は、各日付内の時間帯も含む詳細日程であり、具体的には各工程の各装置毎の処理日程である。これにより、図5に示すように、大日程メンバーd13は、分解の如き各工程を示し、小日程メンバーd16は、スキャナA1の如き各装置を示している。
【0021】
各工場ホスト2は、各印刷工場における製版後の印刷・加工の予定及びFA(factory automation)を管理するためのものであり、製版の小日程d22と連動した印刷加工予定及び製版時〜製版後の各工程の日付毎に処理可能な量(毎日の各工程の処理可能な量;生産能力)が読出/書込可能に設けられている。
【0022】
営業用端末3は、操作者の操作により、事前情報d18をワークフロー管理システムに入力する機能と、図6に示す枠取り依頼(工程の予約依頼)により、事前情報d18に基づく大日程d21をワークフロー管理システム10に立案させると共に、この大日程d21の承認により大日程d21を確定させる機能とをもっている。事前情報d18は、図7に示す日程情報、図8に示す受注情報、図9に示す内訳情報、図10に示すまとまり情報、図11に示す入稿情報、図12に示す出校情報、などがある。
【0023】
日程情報は、図7に示すように、印刷物の作業単位としてのまとまり毎に、得意先とのやり取りのイベント(帰校、帰下等)日付を示すものである。受注情報は、印刷物の受注に関する書誌的な情報で図7中の“台割り流し込みテスト”i1に対応し、図8に示すように、得意先、品名、その他の属性情報からなる。内訳情報は、印刷物自体に関する情報で図7中の“かち割り氷”i2に対応し、図9に示すように、部数やサイズ、仕上げの形態などの項目がある。まとまり情報は、印刷物を製版する上でのまとまり(作業単位)を示す情報で図7中の“表紙裏”i3などに対応し、図10に示すように、ページや色数などの部品情報により詳述される。入稿情報は、印刷物に用いる原稿の入稿予定日や内容を示すもので図7中の“入稿”i4に対応して予定日が示され、また、図11に示すように、現物やデータなどの点数も記述される。出校情報は、印刷物の印刷見本の出校予定日や内容を示すもので図7中の“出校”i5に対応して予定日が示され、また、図12に示すように、印刷部数や加工,箔押し等なども記述される。
【0024】
また、営業用端末3は、操作者の操作により、台割り作成のための製本情報をワークフロー管理システム10に入力する機能をもっている。製本情報は、図13乃至図16に示すように、例えば、無線綴じ(製本形態)、右綴じ(開き)、くるみ表紙(背のつき方)、用紙のサイズや種類、などがある。
【0025】
入稿用端末4は、図17乃至図20に示すように、未入稿リストや入稿リストを表示させる機能を有し、印刷物に用いられる原稿の入稿の際に、印刷物に関する処理量情報及び日程情報を含む入稿情報d23を確定的に入力する機能と、印刷物の割付情報(図19及び図20中の“パターン”;図21に示すパターン帳pの番号など)をワークフロー管理システム10に入力する機能をもっている。なお、入稿用端末4は、入稿済の原稿に限らず、後から入稿される原稿に関しても“後送日”の如き、後送情報を入力することによりその他の処理量情報などを入力可能としている。
【0026】
スケジューラ用端末5は、ワークフロー管理システム10から得られる大日程d21及び小日程d22を出力する機能と、操作者の操作により、各日程d21,d22の充足状況を全編集し出力する機能とをもっている。
【0027】
外注用端末6は、ワークフロー管理システム10が大日程d21を立案する際に、内部生産のみでは処理できないとき、外注を手配して外注による処理量を当日処理可能な量に含めるときに使うものであり、図22に示すように、外注会社名、品目名、製版仕様、枠取り作業量の項目により外注の充足状況を管理することにより、操作者の操作に基づいて、図23に示すように、入稿された原稿のまとまり毎に、それぞれ枠取りされた外注を割り振る機能を備えている。
【0028】
図2のデジタルダイレクションサーバ(DDS)7は、ワークフロー管理システム10と現場用端末8の予定/開始/終了信号に基づいて、必要な全印刷素材データの配分を行う機能をもっている。また、デジタルダイレクションサーバ7は、ワークフロー管理システム10から受ける作業指示に連動して、関連する印刷素材データ(入稿された原稿(文章(文字列)、画像、図形、写真等)のデジタルデータ)を格納している素材データベース(DB)11より、該当する印刷素材データを読出し、この印刷素材データを作業者の端末宛てにデータサーバ7A,7Bに発信する機能をもっている。
【0029】
作業指示一覧は、図24乃至図28に示すように、例えば、時間に沿って工程毎に処理対象の品目などを指示し(工程別→検索結果リスト)、あるいは時間に沿って品目毎に工程などを指示するためのものであり(品目別→検索結果リスト)、工程別リストでは任意の品目をダブルクリックすると、その品目別リストに表示が切り替わり、品目別リストでは任意の工程をダブルクリックするとその工程別リストに表示が切り替わるようになっている。
【0030】
なお、これら作業指示一覧は、図示しないが、作業実績及び現在時刻に基づいて、作業中のまとまりの“開始予定及び終了予定”の欄内を経過時刻に比例して色領域で塗りつぶされるように色付き表示可能となっている。また、作業実績d17は、例えば作業開始時及び作業終了時に夫々バーコードリーダにて原稿袋のバーコードを読込むことにより入力可能となっている。
【0031】
進捗情報(関連工程進捗)d24は、図29に示すように、まとまり毎に小日程(予定)d21と作業実績d17とを比較して示すためのものである。なお、“まとまり”は、製版工程における出校をくくりとした入稿〜出校の作業単位の概念であり、例えば、図30に示すように、本文5/6と、別進行の柱広告とがあるとき、それぞれ“本文5/6−本文−初校”及び“本文5/6−柱広告−初校”のように作成される。このまとまりd6は、例えば図31に示すように下層に部品情報d10を含み、図32に示すように、初校〜2校までは個別に作業されるが、下版の際にはまとめられる。
【0032】
ワークフロー管理システム10は、図3に示すように、事前情報管理部11、大日程管理部12、入稿管理部13、小日程管理部14及び作業指示管理部15を備えている。なお、各管理部11〜15は、アプリケーションソフトウェアにて実現されている。
【0033】
事前情報管理部11は、営業用端末3から入力される事前情報に基づいて、台割り面付け、各種帳票出力、受注番号の取得(承認の取得)、概略的なまとまり(作業段取り)作成などを実行する機能と、図33に示すように、まとまり毎に、大日程の通りに入稿されて小日程が組まれたものを“予定通り(黒文字)”とし、大日程よりも早く入稿されて小日程が組まれたものを“出校進み予定(青文字)”とし、大日程よりも遅く入稿されて小日程が組まれたものを“出校遅れ予定(赤文字)”として進捗照会を可能とする機能とをもっている。
【0034】
大日程管理部12は、事前情報管理部11から受ける事前情報d18に基づいて、フロー選択、負荷予測計算、大日程(概略日程)d21立案などを実行する機能をもっている。
【0035】
入稿管理部13は、入稿用端末4から確定的に入力された入稿情報d23に基づいて、各種帳票出力、正確なまとまり作成を実行する機能をもっている。
【0036】
小日程管理部14は、入稿管理部13から受ける入稿情報d23に基づいて、小日程(詳細日程)d22を立案する機能をもっている。
【0037】
作業指示管理部14は、小日程管理部13により立案された小日程d22に基づいて、作業指示一覧をデジタルダイレクションサーバ7に出力する機能と、開始報告又は終了報告からなる作業実績d17をデジタルダイレクションサーバ7から受けて小日程d22の進行状況を管理し、進捗情報d24を作成してデジタルダイレクションサーバ7に出力する機能とをもっている。
【0038】
次に、このようなワークフロー管理システムを含んだ受注製造管理システムの動作を説明する。なお、この説明は、時系列に沿って図34に示すように、受注による事前情報入力(ST10)、その事前情報に基づく大日程立案(ST20)、受注内容の確定化に伴う台割り作成(ST30)、実際の原稿の入稿処理(ST40)、入稿内容に基づく小日程立案(ST50)、小日程に基づく作業指示(ST60)及び作業遅れ等による小日程の修正処理(ST70)の順に行なう。
【0039】
(事前情報入力;ST10)
いま、営業担当者が新規に印刷を受注したとする。営業用端末3では、操作者の操作により、ワークフロー管理システム10の事前情報管理部11が起動され、図35及び図7に示すように、受注品目に応じたファイルがスケジュール画面として表示される(ST11)。
【0040】
ここで、このスケジュール画面は、図8乃至図12に示すような、受注の情報画面、内訳の情報画面、まとまりの情報画面、入稿情報画面及び出校情報画面を、夫々対応するアイコン部分i1〜i5のダブルクリック操作により、ウインドウ表示可能となっている。
【0041】
例えば図7において、“台割り流し込みテスト”i1をダブルクリックすると図8の受注の情報画面が表示され、“かち割り氷”i2をダブルクリックすると、図9の内訳の情報画面が表示され、“表紙裏”i3をダブルクリックすると図10のまとまりの情報画面が表示される。また、“入稿”i4をダブルクリックすると図11の入稿情報画面が表示され、“出校”i5をダブルクリックすると図12の出校情報画面が表示される。
【0042】
よって、各情報画面の項目に従い、操作者の操作によって、事前情報d18がワークフロー管理システム10に入力される(ST12)。しかる後、営業用端末3では、操作者の操作により、図6に示すように、枠取り依頼画面が表示され、“送信”のダブルクリック操作により、事前情報d18及び枠取り依頼指令がワークフロー管理システム10に入力される(ST13)。
【0043】
なお、本実施形態では、事前情報d18を営業用端末3から入力した場合を説明したが、これに限らず、例えば“事前情報・特別納期検討依頼カード”のような帳票を作成し、この帳票を例えばスケジューラ用端末5の操作者に渡し、スケジューラ用端末5のような他の端末から事前情報d18をワークフロー管理システム10に入力してもよい。
【0044】
(大日程立案;ST20)
ワークフロー管理システム10においては、事前情報管理部11を介し、大日程管理部12が事前情報d18及び枠取り依頼指令を受けると、この事前情報を図36に示す枠取り依頼リストに登録し、しかる後、枠取り依頼リスト内の事前情報に基づいて、大日程d21を立案する。
【0045】
立案の際には、大日程管理部12は、図37に示すように、フロー候補選択モードに移行し(ST21)、図38に示すように、フロー辞書d20cを参照してフロー候補一覧FLを営業用端末3にウインドウ表示させる。営業用端末3では、操作者の操作により、フロー候補一覧FLのうち、いずれかのフロー候補が選択されると、選択結果及び事前情報に基づいて、工程の作業負荷(以下、標準作業時間ともいう)が予測的に算出される(ST22)。ここで、負荷は、例えば、図39に示すように、標準作業時間を示す次の(1)式に作業パラメータA〜C,xが設定されると、算出可能となる。
【0046】
標準作業時間=(A・x+B)C …(1)
但し、A;単位(画像1点)当りの時間、B;準備等の時間、C;初校と後校の比率、x;倍数、である。なお、比率Cは、初校のときに"0"であり、2校目以降で"任意の数値"に設定される。また、これら設定された作業パラメータは、図40に示すように表示され、作業パラメータ辞書d20dに登録される。なお、図40の列方向の各欄の項目(色分け;パターンなし、文字;生原稿、…)は、パターン辞書d20aに登録されており、図40の行方向の各欄の項目(色修正、版下カメラ、…)は、メンバー辞書d20bに登録されている。
【0047】
個々の作業の標準作業時間が算出されると、この標準作業時間に開始可能日時を付加したコマを工程毎に作成する。次に、各コマを各日付に割付けて(ST23)大日程d21を立案する。但し、立案の際に、工場ホスト2から各工程の日付毎に処理可能な量を読出すと共に、各コマを割付ける結果がその処理可能な量を越えないように、割付を調整する(ST24)。
【0048】
ここで、調整しつつ割付けた結果、全てのコマが納期までに各工程により処理可能であれば(ST25)、大日程d21が完成する(ST26)。なお、外注による処理をも処理可能な量に含める場合、ステップST24は、図41に示す手順をもつ。また、割付結果は、どのような形式で表示してもよく、例えば単なるスケジュール形式に限らず、図42及び図43に示すように、詳細情報と共に表示してもよい。
【0049】
次に、この仮に立案された大日程d21は、営業用端末3に送出されて画面表示を介して営業担当者に報告される。営業用端末3では、操作者の操作により、図44に示すように、承認用画面が表示されると共に、承認/非承認の別が大日程管理部12に入力される承認処理が実行される(ST27)。
【0050】
大日程管理部12は、承認を受けた時に大日程d12を固定的に保持し(予約し)、非承認を受けた時には大日程d12を消去して処理を終了する。なお、以上のステップST21〜ST27を各端末3,5の操作イメージで示すと、図45のようになる。
【0051】
一方、ステップST25にて、調整しても納期に間に合うような割付が不可能であれば、大日程の作成を中止して営業用端末3に“再検討”の旨のメッセージを出力し(ST28)、処理を終了する。
【0052】
また、このように大日程が固定的に保持された受注内容に関しては、例えば図46に示す入出校予定出力画面の操作により、入稿予定リスト、出校予定リスト又は帰校予定リスト等を営業用端末に出力することができる。また、これら入稿予定リスト、出校予定リスト及び帰校予定リストは、夫々、例えば予定日の前日の所定時刻に営業用端末3に表示してもよく、あるいは表示の際に、営業用端末3のスピーカから表示の際に音楽を鳴らしてもよい。
【0053】
(台割り作成;ST30)
大日程の立案後から原稿の入稿前までの任意の時点で、図47に示すように、台割りが作成される。すなわち、営業用端末3では、図13乃至図15に示す台割り編集画面が表示され(ST31)、画面内の各項目に沿って製本情報が事前情報管理部11に入力されることにより(ST32)、台割りが作成される(ST33)。また、台割りが作成されると、この台割りに基づいて、図16に示すように、面付けが行われる(ST34)。なお、この台割り作成は、営業用端末3に限らず、入稿用端末4などの他の端末を用いて作成しても良いことは言うまでもない。
【0054】
(入稿処理;ST40)
原稿が入稿されると、図48に示すように、入稿処理が行われる。この入稿処理の際に、入稿用端末4においては、操作者の操作により入稿管理部13を介して、図17又は図18に示す如き、未入稿リスト一覧が表示される(ST41)。未入稿リスト一覧の所望の品目をクリックすると、図19又は図20に示すように、その品目の入稿処理画面が表示される(ST42)。図19は電植に関する入稿処理画面であり、図20は製版に関する入稿処理画面である。夫々、画面内の各項目に沿って入稿情報d23が入力されることにより(ST43)、入稿処理が完了する。
【0055】
なお、入稿処理が大日程で示される期限までに完了しない時(すなわち、入稿されなかった時)、その品目又は部品等は入稿遅れとして取扱われる。入稿遅れは、例えば大日程のスケジュール画面にて所定の色表示などで示される。
【0056】
(小日程立案;ST50)
入稿処理が完了すると、図49に示す要検討リスト上の印刷物は小日程d22の立案が可能となり、実際に製版用の各種の装置を割付けるための小日程d22が立案される。すなわち、図50に示すように、前述同様に、営業用端末3を介し、フロー候補が選択されると(ST51)、負荷が算出され(ST52)、装置毎の標準作業時間及び開始可能日時を示すコマが作成される(ST53)。但し、前述した大日程d21とは異なり、各コマは、各工程内の各装置毎に作成される。この営業用端末3においては、操作者の操作により、図51に示すように、各コマがガントチャート上に配置されると(ST54)、小日程d21の立案が完了する(ST55)。なお、以上のような入稿処理ST40〜小日程立案処理ST55までを概念的に示すと、図52のようになる(なお、作業実績d17が図示されているが、この立案時には存在しない。)。
【0057】
また、小日程d21の立案完了後、小日程管理部14は、その品目の出校日を営業用端末3に出力する(ST56)。
【0058】
(作業指示;ST60)
立案が完了した小日程d22は、作業指示管理部15により、図24乃至図28のいずれかに示す作業指示一覧に変換され、図53に示すように、現在の日時及び作業配分とリンクしてデジタルダイレクションサーバ7に出力される(ST61)。デジタルダイレクションサーバ7では、作業指示管理部15から出力された作業指示一覧に基づいて、素材データベース21内の該当する印刷素材データを読出してデータサーバ7A,7Bに送出する。ここで、デジタルダイレクションサーバ7では、下層の製版システムA,Bから工程の開始/終了に対応してその都度、予め原稿袋等に貼付けられたバーコードがバーコードリーダ等にて読込まれることにより、開始報告又は終了報告を作業指示管理部15に入力する(ST62)。
【0059】
これらの各報告に基づいて、作業指示管理部15では、コマの長さ及び経過時刻に比例して作業実績d17が生成され、この作業実績d17と小工程d22とを比較してなる進捗情報がデジタルダイレクションサーバ7に出力される(ST63)。デジタルダイレクションサーバ7では、図29に示すように、作業実績d17と小日程d22とが進捗情報として並列表示される。これにより、現場の管理者などが小日程(予定)d22と作業実績d17とを比較することができる。
【0060】
(修正処理;ST70)
また、作業指示管理部15は、図54に示すように、作業実績d17に遅れがあるか否かを監視し(ST71)、現在の工程の作業実績に遅れがあるとき、後段の工程の開始可能日時を変更する(ST72)。但し、この場合、現在の工程の完了日時が不明確であるから修正演算をせずに変更する、すなわち、後段の工程の開始可能日時は、現工程の開始可能日時に一義的に変更される。
【0061】
また、作業指示管理部15は、この変更が大幅か(所定値を越えるか)否かを判定し(ST73)、開始可能日時が大幅に変更されるとき、小日程d22の割付けを変更する(ST74)。この変更のときにも前述同様に、各日付の該当する工程の処理可能な量を越えないように割付けを行なう。なお、この処理可能な量は、作業者の出勤体制によって異なるため、同一装置であっても日付毎に異なる値となっている。
【0062】
上述したように本実施形態によれば、事前情報管理部11が、印刷物に関する処理量情報及び日程情報を入力し、大日程管理部12が、処理量情報及び日程情報に基づいて、各工程の日付毎に、印刷物の識別情報を対応させた大日程d21を立案し、入稿管理部13が、印刷物に用いられる原稿の入稿の際に、印刷物に関する処理量情報及び日程情報を確定的に入力し、小日程管理部14が、入稿管理部14により入力された処理量情報及び日程情報に基づいて、大日程d21を詳細化し、各工程に用いられる各装置の日付内の時間帯毎に、印刷物のまとまり(作業単位)情報を対応させた小日程d22を立案し、作業指示管理部15が、小日程に基づいて、作業指示を出力するので、人手による確認作業や管理業務を削減でき、もって、営業の受注から下版までの製版工程の生産効率を最大限に向上させることができる。
【0063】
また、事前情報管理部11は、処理量情報及び日程情報が入力されるとき、枠取り依頼画面上の操作者の操作により、大日程d21の立案を開始させる枠取り依頼指令を大日程管理部12に入力し、大日程管理部12が、大日程を出力し、この大日程に対する承認通知を受けたとき、大日程を予約するため、営業担当者が大日程を承認でき、もって、立案された大日程の妥当性を向上させることができる。
【0064】
さらに、大日程管理部12が、各工程の日付毎に処理可能な量が登録された工場ホスト2から処理可能な量を参照し、この各工程の日付毎の該当する処理可能な量を越えないように大日程を立案するので、無理な大日程を立案することがなく、大日程の信頼性を向上させることができる。
【0065】
また、データダイレクションサーバ7が、作業指示管理部15から出力された作業指示一覧に基づいて、素材データベース21内の該当する印刷素材データを読出してデータサーバ7A,7Bに送出するので、印刷素材データの配分を自動的に実行でき、より一層、作業効率を向上させることができる。
【0066】
(他の実施形態)
なお、上記実施形態は、単一の管理ホスト1及びワークフロー管理システム10を用いた場合について説明したが、これに限らず、図55に示すように、複数のワークフロー管理システム10a,10bを用いて複数の印刷工場間(他の事業部間)で製版工程を管理しあう構成としても、本発明を同様に実施して同様の効果を得ることができる。
【0067】
また、上記実施形態は、各工程の日付毎に処理可能な量を読出す場合について説明したが、これに限らず、本ワークフロー管理システム10に作業者の出勤体制を登録しておき、大日程管理部12がこの出勤体制に基づいて、各工程の日付毎に処理可能な量を算出する構成としても、本発明を同様に実施して同様の効果を得ることができる。
【0068】
その他、本発明はその要旨を逸脱しない範囲で種々変形して実施できる。
【0069】
【発明の効果】
以上説明したように本発明によれば、営業の受注から下版までの製版工程の生産効率を最大限に向上できるワークフロー管理システムを提供できる。
【図面の簡単な説明】
【図1】本発明の一実施形態に係るワークフロー管理システムを含んだ受注製造管理システムの構成を示す模式図
【図2】同実施形態における受注製造管理システムの各現場端末の接続構成を示す図
【図3】同実施形態におけるワークフロー管理システムの構成を示す模式図
【図4】同実施形態におけるスキーマを示す模式図
【図5】同実施形態における大日程メンバーと小日程メンバーとの関係を示す模式図
【図6】同実施形態における枠取り依頼画面を示す模式図
【図7】同実施形態における日程情報の表示画面を示す模式図
【図8】同実施形態における受注情報の表示画面を示す模式図
【図9】同実施形態における内訳情報の表示画面を示す模式図
【図10】同実施形態におけるまとまり情報の表示画面を示す模式図
【図11】同実施形態における入稿情報の表示画面を示す模式図
【図12】同実施形態における出校情報の表示画面を示す模式図
【図13】同実施形態における台割り編集画面を示す模式図
【図14】同実施形態における面付け編集画面を示す模式図
【図15】同実施形態における台割り編集画面を示す模式図
【図16】同実施形態における面付け編集画面を示す模式図
【図17】同実施形態における未入稿リストの表示画面を示す模式図
【図18】同実施形態における未入稿リストの表示画面を示す模式図
【図19】同実施形態における入稿処理画面を示す模式図
【図20】同実施形態における入稿処理画面を示す模式図
【図21】同実施形態における割付情報を説明するための模式図
【図22】同実施形態における外注の充足状況の管理を説明するための模式図
【図23】同実施形態における外注用端末の機能を説明するための模式図
【図24】同実施形態における作業指示・報告画面を示す模式図
【図25】同実施形態における作業指示・報告画面を示す模式図
【図26】同実施形態における作業指示・報告画面を示す模式図
【図27】同実施形態における作業指示品目検索画面を示す模式図
【図28】同実施形態における作業指示・報告画面を示す模式図
【図29】同実施形態における進捗情報を示す模式図
【図30】同実施形態におけるまとまりの概念を説明するための模式図
【図31】同実施形態におけるまとまりの概念を説明するための模式図
【図32】同実施形態におけるまとまりの概念を説明するための模式図
【図33】同実施形態における進捗照会画面を示す模式図
【図34】同実施形態における動作を説明するためのフローチャート
【図35】同実施形態における動作を説明するためのフローチャート
【図36】同実施形態における枠取り依頼リストの表示画面を示す模式図
【図37】同実施形態における動作を説明するためのフローチャート
【図38】同実施形態におけるフロー候補一覧の表示画面を示す模式図
【図39】同実施形態における作業パラメータの設定画面を示す模式図
【図40】同実施形態における作業パラメータの表示画面を示す模式図
【図41】同実施形態における外注を考慮した場合の動作を示すフローチャート
【図42】同実施形態における大日程の詳細表示画面を示す模式図
【図43】同実施形態における大日程の詳細表示画面を示す模式図
【図44】同実施形態における大日程の承認画面を示す模式図
【図45】同実施形態における大日程の立案動作を各端末の操作イメージで示す模式図
【図46】同実施形態における入出校出力画面を示す模式図
【図47】同実施形態における台割り作成動作を説明するためのフローチャート
【図48】同実施形態における入稿処理動作を説明するためのフローチャート
【図49】同実施形態における小日程の要検討リストの表示画面を示す模式図
【図50】同実施形態における小日程の立案動作を示す模式図
【図51】同実施形態における小日程の表示画面を示す模式図
【図52】同実施形態における入稿処理〜小日程の立案処理の概念を示す模式図
【図53】同実施形態における作業指示動作を説明するためのフローチャート
【図54】同実施形態における修正処理動作を説明するためのフローチャート
【図55】本発明の他の実施形態の構成を示す模式図
【符号の説明】
1…管理ホスト
2…工場ホスト
3…営業用端末
4…入稿用端末
5…スケジューラ用端末
6…外注用端末
7…デジタルダイレクションサーバ
8…現場用端末
9…ネットワーク
10…ワークフロー管理システム
11…事前情報管理部
12…大日程管理部
13…入稿管理部
14…小日程管理部
15…作業指示管理部
21…素材データベース
d4…受注情報
d5…内訳情報
d6…まとまり情報
d7…折
d8…ページ
d9…実用版
d10…部品情報
d11…大日程フロー
d12…大日程コマ作業予定日
d13…大日程メンバー
d14…小日程フロー
d15…小日程コマ予定日時
d16…小日程メンバー
d17…実績情報
d18…事前情報
d19…台割り情報
d20…メンテナンスユーティリティ
d20a…パターン辞書
d20b…メンバー辞書
d20c…フロー辞書
d20d…作業パラメータ辞書
d21…大日程
d22…小日程
d23…入稿情報
d24…進捗情報
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a workflow management system for managing a plate making process such as ordering of a printed matter, submission, plate making, and leaving a school.
[0002]
[Prior art]
In recent years, with the advance of electronic technology, various devices have been digitized, and the price and performance of these digital devices have been reduced. In addition, the Internet, intranet, and DTP (desktop publishing), in which this type of digital device is connected via a network, are becoming more popular.
[0003]
Such a situation also affects customers who order printed materials and printing companies that produce printed materials in the field of printed material production. For example, in customers and design companies, these digital devices are introduced with a small investment, and a part of the plate making work is started by each digital device. Also, this type of customer often submits original analog data such as texts and photographs, as well as manuscripts converted into digital data for each part, to a printing company's printing factory on-line or on a storage medium such as an FD. is there. In this case, in the printing company, because the digital data is submitted from the customer, the plate making process is performed by the cooperative work with the customer of the submission source. When analog data is submitted, the printing company converts it into digital data.
[0004]
By the way, since digital data from the customer is used in the plate making process, the convenience of the customer's production affects the work setup. Also, when a digitalized manuscript is submitted from a customer for each part via a network, there is a problem that the manuscript submission and processing flow is opaque and difficult to grasp until the film for plate making is completed. .
[0005]
Furthermore, in a printing company, digital data and analog data are mixed at the time of submission, so that the business contents of sales, production management, and the site change to contents different from conventional ones. For example, the flow of work (hereinafter also referred to as a work flow or a workflow) is completely different for each item, so that there is a problem that the frequency of confirmation work increases and internal management work increases. Note that this type of confirmation work increases in frequency due to the opacity of the flow of processing and the like described above.
[0006]
[Problems to be solved by the invention]
As described above, in the field of printed matter production, there is a problem that the production efficiency of the plate making process from the order of sales to the lower plate is lowered due to the increase in confirmation work and management work under the progress of digitization. . For this reason, realization of some means that can at least prevent a decrease in the production efficiency of the plate making process is desired.
[0007]
The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a workflow management system capable of maximizing the production efficiency of the plate making process from the order of sales to the lower plate.
[0008]
[Means for Solving the Problems]
  The invention corresponding to claim 1 is a workflow management system for producing a printed matter comprising a plurality of types of processes.At least processing amount information and schedule information related to the printed matter, time per unit A, preparation time B, work parameter of each step consisting of the ratio C and magnification x between the first school and the back school, and the date of each step , An approximate schedule corresponding to the identification information of the printed matter, and a detailed schedule corresponding to the identification information of the work unit of the printed matter for each time zone within the date of each device used for each step of the approximate schedule, , And a database device that is readable / writable, andAt least processing amount information and schedule information about the printed matterIn the database devicePrior information input means for inputting,Based on the setting means for setting the work parameter in the database device and the work parameter in the database device, the standard work time of each step = (A · x + B) × C is calculated and each step obtained A frame with the start date and time added to the standard work time is created for each process, and each frame obtained is stored in the database device.Based on throughput information and schedule information,In order not to exceed the processable amount indicated in the processing amount information,For each date of each process, draft a rough schedule that matches the identification information of the printed matterAnd write this rough schedule to the database device.Rough scheduling means,
  When submitting a manuscript used for the printed matter, the processing amount information and the schedule information regarding the printed matter are definitely determined.In the database deviceInput means for input and input by the input meansIn the database deviceBased on the processing amount information and schedule information, it was designed by the rough schedule planning means.In the database deviceDetailed schedules are detailed, and detailed schedules are created that correspond to the identification information of the unit of work of the printed matter for each time zone within the date of each device used in each process.And write this detailed schedule to the database device.Designed by detailed schedule planning means and the detailed schedule planning meansIn the database deviceA workflow management system including work instruction means for outputting a work instruction based on a detailed schedule.
[0009]
  According to a second aspect of the present invention, in the workflow management system corresponding to the first aspect, when the processing amount information and the schedule information are input by the prior information input means, the planning of the rough schedule is started. Planning request means for inputting a request command to the rough schedule planning means, and the rough schedule planning meansIn the database deviceWhen an approximate schedule is output and an approval notification is received for this approximate schedule, the approximate schedule isConfirm and delete the rough schedule in the database device when you receive a non-approval notice for the rough scheduleA workflow management system including a schedule approval means.
[0012]
(Function)
  Therefore, the invention corresponding to claim 1 has taken the above-described means, so that the prior information input means at least provides the processing amount information and schedule information regarding the printed matter.In the database deviceInput and setting means,The work parameters are set in the database device, and the rough schedule planning means calculates the standard work time of each process = (A · x + B) × C based on the work parameters in the database device, and the obtained standard of each process. Create a scene with the start date and time added to the work time for each process, and obtain each scene in the database device.Based on throughput information and schedule information,In order not to exceed the processable amount indicated in the processing amount information,Establish a rough schedule for each date of each process, corresponding to the identification information of the printed matterAnd write this rough schedule to the database device,When the submission means submits a manuscript used for printed matter, the processing amount information and schedule information regarding the printed matter are definitely determined.In the database deviceThe detailed schedule planning means is entered by the trafficking meansIn the database deviceBased on throughput information and schedule informationIn the database deviceDetailed schedules are detailed and detailed schedules are created that correspond to the identification information of the work units of printed materials for each time zone within the date of each device used in each process.And write this detailed schedule to the database device,The work instruction means was drafted by the detailed schedule drafting meansIn the database deviceSince the work instruction is output based on the detailed schedule, manual confirmation work and management work can be reduced, so that the production efficiency of the plate making process from the order of sales to the lower plate can be maximized.In addition, since the rough schedule is planned so as not to exceed the applicable processable amount for each date of each step, it is possible to improve the reliability of the rough schedule without planning an unreasonable rough schedule.
[0013]
  Further, according to the second aspect, when the plan request means inputs the processing amount information and the schedule information by the prior information input means, the plan request instruction for starting the planning of the rough schedule is input to the rough schedule planning means. However, the schedule approval means was designed by the general schedule planning means.In the database deviceWhen a rough schedule is output and an approval notification is received for this rough schedule,Confirm and delete the rough schedule in the database device when you receive a non-approval notice for the rough scheduleTherefore, in addition to the operation corresponding to the first aspect, the plan requester can approve the rough schedule, and thus the validity of the rough schedule can be improved.
[0016]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of the present invention will be described with reference to the drawings.
[0017]
FIG. 1 is a schematic diagram showing a configuration of an order manufacturing management system including a workflow management system according to an embodiment of the present invention, and FIG. 2 is a diagram showing a terminal connection configuration for the workflow management system and plate making work. FIG. 3 is a schematic diagram showing the configuration of the workflow management system.
[0018]
Here, the order manufacturing management system includes, for example, a management host 1, a plurality of factory hosts 2, a sales terminal 3, a submission terminal 4, a scheduler terminal 5, a subcontracting terminal 6, a data direction server 7, and a field terminal. 8 are connected to the workflow management system 10 via the network 9, respectively.
[0019]
The management host 1 is for managing orders and transmission processing of printed matter, and the workflow management system for managing plate making production activities has a database defined by the hierarchical schema shown in FIG. Order information d4 of printed matter, breakdown information d5 of order received, breakdown information (work unit information) d6, fold d7, page d8 and practical version d9, and further, for each batch information d6, parts information d10, large Schedule flow d11, schedule schedule work date d12 for large schedule, schedule member d13 for large schedule, small schedule flow d14, schedule date and time d15 for small schedule, small schedule member d16, work schedule information d17 for small schedule, advance information d18, car layout information d19, maintenance utility (pattern dictionary d20a, member dictionary d20b, flow dictionary d20c and work parameters Dictionary including D 20 d) d20, large date d21, small dates d22, trafficking information d23, progress information of a large date and small dates d24, but is provided so as to be read / write by the workflow management system 10.
[0020]
The large schedule d21 is an approximate schedule in date units, and specifically a processing schedule for each process. The small schedule d22 is a detailed schedule including a time zone within each date, and specifically, is a processing schedule for each device in each process. Accordingly, as shown in FIG. 5, the large schedule member d13 indicates each process such as disassembly, and the small schedule member d16 indicates each apparatus such as the scanner A1.
[0021]
Each factory host 2 is for managing printing / processing schedules and FA (factory automation) after plate making in each printing factory. Printing process schedules and plate making times in conjunction with a small schedule d22 of plate making and after plate making An amount that can be processed for each date of each step (a daily amount that can be processed in each step; production capacity) is provided in a readable / writable manner.
[0022]
The sales terminal 3 uses the function of inputting the advance information d18 to the workflow management system by the operation of the operator and the workflow of the large schedule d21 based on the advance information d18 by the frame acquisition request (process reservation request) shown in FIG. The management system 10 has a function of making a plan and confirming the large schedule d21 by the approval of the large schedule d21. Prior information d18 includes schedule information shown in FIG. 7, order information shown in FIG. 8, breakdown information shown in FIG. 9, summary information shown in FIG. 10, submission information shown in FIG. 11, school departure information shown in FIG. There is.
[0023]
As shown in FIG. 7, the schedule information indicates an event (return to school, return, etc.) date of exchange with the customer for each group as a work unit of printed matter. The order information is bibliographic information about orders for printed materials, corresponds to the “table splitting test” i1 in FIG. 7, and includes a customer, product name, and other attribute information as shown in FIG. The breakdown information is information relating to the printed matter itself and corresponds to “Cleaving Ice” i2 in FIG. 7, and includes items such as the number of copies, size, and finishing form as shown in FIG. The group information is information indicating a group (unit of work) in making a printed material and corresponds to “back of cover” i3 in FIG. 7, and as shown in FIG. 10, by component information such as a page and the number of colors. Detailed. The submission information indicates the scheduled submission date and contents of the manuscript to be used for the printed matter, and the scheduled date is shown corresponding to “Submission” i4 in FIG. 7, and as shown in FIG. Data and other points are also described. The school entry information indicates the planned school entry date and contents of the printed sample of the printed matter, and the planned date is shown in correspondence with “going to school” i5 in FIG. 7. Also, as shown in FIG. And processing, foil stamping, etc. are also described.
[0024]
Further, the sales terminal 3 has a function of inputting bookbinding information for creating a table to the workflow management system 10 by an operation of the operator. As shown in FIGS. 13 to 16, the bookbinding information includes, for example, simple binding (bookbinding form), right binding (opening), case cover (backing), paper size and type, and the like.
[0025]
As shown in FIGS. 17 to 20, the submission terminal 4 has a function of displaying an unsubmitted list and a submission list, and processing amount information related to the printed material when the manuscript used for the printed material is submitted. The workflow management system 10 includes a function for definitely inputting the submission information d23 including the schedule information and the layout information (“pattern” in FIGS. 19 and 20; the number of the pattern book p shown in FIG. 21). It has a function to input to. It should be noted that the submission terminal 4 is not limited to the submitted manuscript, but also for the manuscript to be submitted later, other post-transmission information such as “scheduled date” can be input to input other processing amount information. Input is possible.
[0026]
The scheduler terminal 5 has a function of outputting the large schedule d21 and the small schedule d22 obtained from the workflow management system 10, and a function of completely editing and outputting the satisfaction status of the schedules d21 and d22 by the operation of the operator. .
[0027]
The subcontracting terminal 6 is used when the workflow management system 10 drafts a large schedule d21, and when the processing cannot be performed only by internal production, the subcontracting is arranged and the processing amount by subcontracting is included in the processing amount on the day. Yes, as shown in FIG. 22, by managing the subcontract satisfaction status by the items of the subcontracting company name, item name, plate making specification, and framing work amount, as shown in FIG. In addition, a function is provided for allocating outsourced outlines for each group of submitted manuscripts.
[0028]
The digital direction server (DDS) 7 in FIG. 2 has a function of allocating all necessary printing material data based on the schedule / start / end signals of the workflow management system 10 and the on-site terminal 8. In addition, the digital direction server 7 is linked to work instructions received from the workflow management system 10 and related printing material data (digital data of a submitted manuscript (text (character string), image, figure, photograph, etc.)). Is read from the material database (DB) 11 that stores the print material data, and the print material data is transmitted to the data servers 7A and 7B to the operator's terminal.
[0029]
As shown in FIGS. 24 to 28, the work instruction list indicates, for example, items to be processed for each process along time (by process → search result list), or processes for each item along time. If you double-click any item in the process-specific list, the display switches to the item-specific list, and if you double-click any process in the item-specific list The display is switched to the process-specific list.
[0030]
Although not shown in the drawing, these work instruction lists are filled with a color region in proportion to the elapsed time in the column of “scheduled start and end schedule” of the group being worked on based on the work results and the current time. Colored display is possible. The work record d17 can be input, for example, by reading the barcode of the document bag with a barcode reader at the start and end of the work.
[0031]
As shown in FIG. 29, the progress information (related process progress) d24 is for comparing and showing a small schedule (planned) d21 and work results d17 for each group. Note that “mamari” is the concept of a unit of work from submission to school that includes the entrance to school in the plate making process. For example, as shown in FIG. Are created as “text 5 / 6-text-first school” and “text 5 / 6-poster-first school”, respectively. For example, as shown in FIG. 31, the group d6 includes component information d10 in the lower layer, and as shown in FIG. 32, the first school to the second school are individually operated, but they are collected in the lower version.
[0032]
As shown in FIG. 3, the workflow management system 10 includes a prior information management unit 11, a large schedule management unit 12, a submission management unit 13, a small schedule management unit 14, and a work instruction management unit 15. Each management unit 11 to 15 is realized by application software.
[0033]
The prior information management unit 11 is based on the prior information input from the business terminal 3, layout layout, output of various forms, acquisition of order numbers (acquisition of approval), creation of a rough set (work setup), etc. As shown in Fig. 33, “Scheduled (black letters)” means that documents that have been submitted according to the large schedule and assembled with the small schedule are submitted earlier than the large schedule. “Scheduled to go to school (blue text)” as a result of a small schedule, and “Scheduled to go back to school (red text)” for a short schedule that was submitted later than a large schedule. It has a function that makes progress inquiry possible.
[0034]
The large schedule management unit 12 has a function of executing flow selection, load prediction calculation, large schedule (rough schedule) d21 planning and the like based on the prior information d18 received from the prior information management unit 11.
[0035]
The submission management unit 13 has a function of executing various forms output and accurate collection creation based on the submission information d23 that is definitely input from the submission terminal 4.
[0036]
The small schedule management unit 14 has a function of planning a small schedule (detailed schedule) d22 based on the submission information d23 received from the submission management unit 13.
[0037]
The work instruction management unit 14 digitally directs a work result d17 including a function of outputting a work instruction list to the digital direction server 7 based on the small schedule d22 planned by the small schedule management unit 13 and a start report or an end report. It has a function of receiving from the server 7 and managing the progress of the small schedule d22, creating progress information d24 and outputting it to the digital direction server 7.
[0038]
Next, the operation of the order manufacturing management system including such a workflow management system will be described. In this description, as shown in FIG. 34 along the time series, prior information input (ST10) based on an order received, large schedule planning based on the prior information (ST20), and the creation of a table with finalization of the order contents ( ST30), actual manuscript submission process (ST40), small schedule planning based on the contents of submission (ST50), work instruction based on small schedule (ST60), and small schedule correction process due to work delay (ST70). Do.
[0039]
(Advance information input; ST10)
Assume that a sales representative receives a new print order. In the sales terminal 3, the prior information management unit 11 of the workflow management system 10 is activated by an operation of the operator, and a file corresponding to the ordered item is displayed as a schedule screen as shown in FIGS. 35 and 7 ( ST11).
[0040]
Here, the schedule screen has an icon portion i1 corresponding to an order information screen, a breakdown information screen, a group information screen, a submission information screen, and a school information screen as shown in FIGS. The window can be displayed by double-clicking on i5.
[0041]
For example, in FIG. 7, when the “table splitting test” i1 is double-clicked, the order information screen shown in FIG. 8 is displayed, and when “Kakigori” i2 is double-clicked, the breakdown information screen shown in FIG. When double-clicking “back of cover” i3, a group information screen of FIG. 10 is displayed. Further, when the “input” i4 is double-clicked, the input information screen shown in FIG. 11 is displayed, and when the “exit” i5 is double-clicked, the entry information screen shown in FIG. 12 is displayed.
[0042]
Therefore, the advance information d18 is input to the workflow management system 10 by the operation of the operator according to the items on each information screen (ST12). Thereafter, as shown in FIG. 6, the sales terminal 3 displays a frame request screen as shown in FIG. 6 by the operation of the operator. By double-clicking “Send”, the advance information d18 and the frame request command are sent to the workflow management. Input to the system 10 (ST13).
[0043]
In the present embodiment, the case where the prior information d18 is input from the sales terminal 3 has been described. However, the present invention is not limited to this. For example, a form such as a “preliminary information / special delivery date review request card” is created and this form is created. May be passed to the operator of the scheduler terminal 5 and the prior information d18 may be input to the workflow management system 10 from another terminal such as the scheduler terminal 5.
[0044]
(Large schedule planning; ST20)
In the workflow management system 10, when the large schedule management unit 12 receives the prior information d18 and the frame acquisition request command via the prior information management unit 11, the prior information is registered in the frame acquisition request list shown in FIG. Then, a large schedule d21 is planned based on the prior information in the frame removal request list.
[0045]
In planning, the large schedule management unit 12 shifts to the flow candidate selection mode as shown in FIG. 37 (ST21), and refers to the flow dictionary d20c as shown in FIG. A window is displayed on the business terminal 3. In the business terminal 3, when any flow candidate is selected from the flow candidate list FL by the operation of the operator, based on the selection result and prior information, the process workload (hereinafter referred to as standard work time) is selected. Is calculated predictively (ST22). Here, for example, as shown in FIG. 39, the load can be calculated when the work parameters A to C, x are set in the following equation (1) indicating the standard work time.
[0046]
  Standard working time = (A · x + B)*C ... (1)
  However, A: time per unit (one image), B: time for preparation, etc. C: ratio of first school to second school, x: multiple. The ratio C is “0” at the first school, and is set to “arbitrary numerical value” after the second school. The set work parameters are displayed as shown in FIG. 40 and registered in the work parameter dictionary d20d. The items in each column in the column direction in FIG. 40 (color classification; no pattern, text; raw document,...) Are registered in the pattern dictionary d20a, and the items in each column in the row direction in FIG. The composition camera, ...) is registered in the member dictionary d20b.
[0047]
When the standard work time of each work is calculated, a frame obtained by adding the start date / time to the standard work time is created for each process. Next, each frame is assigned to each date (ST23), and a large schedule d21 is planned. However, at the time of planning, the processable amount is read from the factory host 2 for each date of each process, and the allocation is adjusted so that the result of allocating each frame does not exceed the processable amount (ST24). ).
[0048]
Here, as a result of the allocation while adjusting, if all the frames can be processed by each process by the delivery date (ST25), the large schedule d21 is completed (ST26). Note that when processing by outsourcing is also included in the processable amount, step ST24 has the procedure shown in FIG. Further, the allocation result may be displayed in any format, for example, not limited to a simple schedule format, but may be displayed together with detailed information as shown in FIGS. 42 and 43.
[0049]
Next, the tentatively planned large schedule d21 is sent to the sales terminal 3 and reported to the sales staff via the screen display. As shown in FIG. 44, the sales terminal 3 displays an approval screen as shown in FIG. 44, and an approval process in which approval / non-approval is input to the large schedule management unit 12 is executed. (ST27).
[0050]
The large schedule management unit 12 holds (reserves) the large schedule d12 in a fixed manner when the approval is received, and deletes the large schedule d12 when the approval is received and ends the process. In addition, when the above steps ST21 to ST27 are shown by operation images of the terminals 3 and 5, FIG. 45 is obtained.
[0051]
On the other hand, if it is impossible in step ST25 to make an allocation in time for the delivery date, the creation of a large schedule is stopped and a message “review” is output to the sales terminal 3 (ST28). ), The process is terminated.
[0052]
In addition, regarding the order contents in which the large schedule is fixedly held in this way, for example, by operating the entrance / exit schedule output screen shown in FIG. 46, the entrance schedule list, exit schedule list, return schedule list, etc. are operated. Can be output to the terminal. In addition, the submission schedule list, the school departure schedule list, and the school return schedule list may be displayed on the sales terminal 3, for example, at a predetermined time the day before the scheduled date, or at the time of display, the sales terminal Music may be played from the 3 speakers.
[0053]
(Create table layout; ST30)
As shown in FIG. 47, a table layout is created at an arbitrary time from the planning of a large schedule to the submission of a manuscript. That is, in the sales terminal 3, the table layout editing screen shown in FIGS. 13 to 15 is displayed (ST31), and bookbinding information is input to the prior information management unit 11 along each item in the screen (ST32). ), A table layout is created (ST33). Further, when the table layout is created, imposition is performed based on the table layout as shown in FIG. 16 (ST34). Needless to say, the table allocation is not limited to the sales terminal 3 but may be generated using another terminal such as the submission terminal 4.
[0054]
(Submission process; ST40)
When the manuscript is submitted, a submission process is performed as shown in FIG. During the submission process, the submission terminal 4 displays an unsubmitted list list as shown in FIG. 17 or 18 through the submission management unit 13 by the operation of the operator (ST41). ). When a desired item in the unsubmitted list is clicked, a submission process screen for the item is displayed as shown in FIG. 19 or 20 (ST42). FIG. 19 shows a submission processing screen related to power planting, and FIG. 20 shows a submission processing screen related to plate making. The submission information d23 is input along each item in the screen (ST43), and the submission process is completed.
[0055]
When the submission process is not completed by the deadline indicated in the large schedule (that is, when the submission process is not completed), the item or part is handled as a submission delay. The submission delay is indicated by, for example, a predetermined color display on the schedule screen of a large schedule.
[0056]
(Small schedule planning; ST50)
When the submission process is completed, it is possible to plan a small schedule d22 for the printed matter on the required review list shown in FIG. 49, and a small schedule d22 for actually allocating various apparatuses for plate making is planned. That is, as shown in FIG. 50, as described above, when a flow candidate is selected via the sales terminal 3 (ST51), the load is calculated (ST52), and the standard work time and startable date and time for each device are calculated. A frame to be shown is created (ST53). However, unlike the large schedule d21 described above, each frame is created for each device in each process. In this business terminal 3, when each frame is arranged on the Gantt chart as shown in FIG. 51 by the operation of the operator (ST54), the planning of the small schedule d21 is completed (ST55). It should be noted that the above-described submission process ST40 to small schedule planning process ST55 are conceptually shown in FIG. 52 (note that the work record d17 is shown, but does not exist at the time of planning). .
[0057]
In addition, after the completion of the planning of the small schedule d21, the small schedule management unit 14 outputs the school entry date of the item to the business terminal 3 (ST56).
[0058]
(Work instruction; ST60)
The small schedule d22 for which the planning has been completed is converted into a work instruction list shown in any of FIGS. 24 to 28 by the work instruction management unit 15, and is linked to the current date and work distribution as shown in FIG. The data is output to the digital direction server 7 (ST61). In the digital direction server 7, based on the work instruction list output from the work instruction management unit 15, the corresponding print material data in the material database 21 is read out and sent to the data servers 7A and 7B. Here, in the digital direction server 7, a bar code previously attached to a document bag or the like is read by a bar code reader or the like each time corresponding to the start / end of the process from the lower plate making systems A and B. Thus, the start report or the end report is input to the work instruction management unit 15 (ST62).
[0059]
Based on each of these reports, the work instruction management unit 15 generates a work record d17 in proportion to the frame length and the elapsed time, and progress information obtained by comparing the work record d17 and the small process d22. The data is output to the digital direction server 7 (ST63). In the digital direction server 7, as shown in FIG. 29, the work record d17 and the small schedule d22 are displayed in parallel as progress information. As a result, the site manager or the like can compare the small schedule (planned) d22 with the work record d17.
[0060]
(Correction process; ST70)
Further, as shown in FIG. 54, the work instruction management unit 15 monitors whether or not there is a delay in the work performance d17 (ST71), and when there is a delay in the work performance of the current process, the subsequent process starts. The possible date is changed (ST72). However, in this case, since the completion date and time of the current process is unclear, it is changed without performing a correction operation, that is, the startable date and time of the subsequent process is uniquely changed to the startable date and time of the current process. .
[0061]
Further, the work instruction management unit 15 determines whether this change is significant (exceeds a predetermined value) (ST73), and when the startable date / time is significantly changed, the assignment of the small schedule d22 is changed ( ST74). Also at the time of this change, as described above, the allocation is performed so as not to exceed the processable amount of the process corresponding to each date. Note that the amount that can be processed varies depending on the worker's attendance system, so even for the same device, the amount varies depending on the date.
[0062]
As described above, according to the present embodiment, the prior information management unit 11 inputs the processing amount information and schedule information related to the printed matter, and the large schedule management unit 12 performs the process of each process based on the processing amount information and the schedule information. For each date, a large schedule d21 corresponding to the identification information of the printed matter is drafted, and the submission management unit 13 determines the processing amount information and the schedule information related to the printed matter when submitting the manuscript used for the printed matter. The small schedule management unit 14 refines the large schedule d21 based on the processing amount information and schedule information input by the submission management unit 14, and each time zone within the date of each device used for each process In addition, a small schedule d22 corresponding to the group (work unit) information of the printed matter is formulated, and the work instruction management unit 15 outputs a work instruction based on the small schedule, thereby reducing manual confirmation work and management work. Yes, so It can be improved to maximize the production efficiency of the plate making process to lower plate from the order.
[0063]
In addition, when the processing amount information and the schedule information are input, the advance information management unit 11 issues a framing request command for starting the planning of the large schedule d21 by the operation of the operator on the framing request screen. 12 when the large schedule management unit 12 outputs a large schedule and receives an approval notification for this large schedule, the sales person can approve the large schedule to make a reservation for the large schedule. The validity of large schedules can be improved.
[0064]
Further, the large schedule management unit 12 refers to the processable amount from the factory host 2 in which the processable amount for each process date is registered, and exceeds the processable amount for each process date. Since a large schedule is planned so as not to occur, it is possible to improve the reliability of the large schedule without planning an excessively large schedule.
[0065]
Further, the data direction server 7 reads out the corresponding print material data in the material database 21 based on the work instruction list output from the work instruction management unit 15 and sends it to the data servers 7A and 7B. Can be automatically executed, and work efficiency can be further improved.
[0066]
(Other embodiments)
In the above embodiment, the case where the single management host 1 and the workflow management system 10 are used has been described. However, the present invention is not limited to this, and a plurality of workflow management systems 10a and 10b are used as shown in FIG. Even if the plate making process is managed between a plurality of printing factories (between other business departments), the present invention can be similarly implemented to obtain the same effect.
[0067]
Moreover, although the said embodiment demonstrated the case where the quantity which can be processed for every date of each process was read, not only this but a worker's attendance system is registered into this workflow management system 10, and a large schedule Even if the management unit 12 calculates the amount that can be processed for each date of each process based on this attendance system, the present invention can be implemented in the same manner to obtain the same effect.
[0068]
In addition, the present invention can be implemented with various modifications without departing from the gist thereof.
[0069]
【The invention's effect】
As described above, according to the present invention, it is possible to provide a workflow management system capable of maximizing the production efficiency of the plate making process from sales orders to lower plates.
[Brief description of the drawings]
FIG. 1 is a schematic diagram showing the configuration of an order manufacturing management system including a workflow management system according to an embodiment of the present invention.
FIG. 2 is a diagram showing a connection configuration of each on-site terminal in the order manufacturing management system according to the embodiment;
FIG. 3 is a schematic diagram showing a configuration of a workflow management system according to the embodiment.
FIG. 4 is a schematic diagram showing a schema in the embodiment;
FIG. 5 is a schematic diagram showing a relationship between a large schedule member and a small schedule member in the embodiment;
FIG. 6 is a schematic diagram showing a frame request screen in the embodiment
FIG. 7 is a schematic diagram showing a schedule information display screen according to the embodiment;
FIG. 8 is a schematic diagram showing a display screen for order information in the embodiment;
FIG. 9 is a schematic diagram showing a breakdown information display screen according to the embodiment;
FIG. 10 is a schematic diagram showing a display screen of group information according to the embodiment.
FIG. 11 is a schematic diagram showing a display screen of submitted information in the embodiment.
FIG. 12 is a schematic diagram showing a school information display screen according to the embodiment;
FIG. 13 is a schematic diagram showing a table layout editing screen according to the embodiment;
FIG. 14 is a schematic diagram showing an imposition edit screen according to the embodiment;
FIG. 15 is a schematic diagram showing a table layout editing screen according to the embodiment;
FIG. 16 is a schematic diagram showing an imposition edit screen according to the embodiment;
FIG. 17 is a schematic diagram showing a display screen of an unsubmitted list in the embodiment;
FIG. 18 is a schematic diagram showing a display screen of an unsubmitted list in the embodiment;
FIG. 19 is a schematic diagram showing a submission process screen in the embodiment.
FIG. 20 is a schematic diagram showing a submission process screen in the embodiment.
FIG. 21 is a schematic diagram for explaining allocation information in the embodiment;
FIG. 22 is a schematic diagram for explaining management of the satisfaction status of subcontracting in the embodiment;
FIG. 23 is a schematic diagram for explaining the function of the outsourcing terminal in the embodiment;
FIG. 24 is a schematic diagram showing a work instruction / report screen according to the embodiment;
FIG. 25 is a schematic diagram showing a work instruction / report screen according to the embodiment;
FIG. 26 is a schematic diagram showing a work instruction / report screen according to the embodiment;
FIG. 27 is a schematic diagram showing a work instruction item search screen in the embodiment;
FIG. 28 is a schematic diagram showing a work instruction / report screen according to the embodiment;
FIG. 29 is a schematic diagram showing progress information in the embodiment;
FIG. 30 is a schematic diagram for explaining the concept of unity in the embodiment;
FIG. 31 is a schematic diagram for explaining the concept of unity in the embodiment;
FIG. 32 is a schematic diagram for explaining the concept of unity in the embodiment;
FIG. 33 is a schematic diagram showing a progress inquiry screen in the embodiment;
FIG. 34 is a flowchart for explaining the operation in the embodiment;
FIG. 35 is a flowchart for explaining the operation in the embodiment;
FIG. 36 is a schematic diagram showing a frame removal request list display screen according to the embodiment;
FIG. 37 is a flowchart for explaining the operation in the embodiment;
FIG. 38 is a schematic diagram showing a flow candidate list display screen in the embodiment;
FIG. 39 is a schematic diagram showing a work parameter setting screen in the embodiment;
FIG. 40 is a schematic diagram showing a work parameter display screen according to the embodiment;
FIG. 41 is a flowchart showing an operation when outsourcing is considered in the embodiment;
FIG. 42 is a schematic diagram showing a detailed display screen for a large schedule according to the embodiment.
FIG. 43 is a schematic diagram showing a detailed display screen for a large schedule according to the embodiment;
44 is a schematic diagram showing a large schedule approval screen in the embodiment; FIG.
FIG. 45 is a schematic diagram showing a planning operation for a large schedule according to the embodiment as an operation image of each terminal;
FIG. 46 is a schematic diagram showing an entrance / exit output screen in the embodiment;
FIG. 47 is a flowchart for explaining a table creation operation in the embodiment;
FIG. 48 is a flowchart for explaining the submission processing operation in the embodiment;
FIG. 49 is a schematic diagram showing a display screen of a small schedule required examination list in the embodiment;
FIG. 50 is a schematic diagram showing a planning operation for a small schedule according to the embodiment;
FIG. 51 is a schematic diagram showing a small schedule display screen according to the embodiment;
FIG. 52 is a schematic diagram showing a concept of drafting processing to small schedule planning processing in the embodiment;
FIG. 53 is a flowchart for explaining a work instruction operation in the embodiment;
FIG. 54 is a flowchart for explaining the correction processing operation in the embodiment;
FIG. 55 is a schematic diagram showing the configuration of another embodiment of the present invention.
[Explanation of symbols]
1 ... Management host
2 ... Factory host
3 ... Sales terminal
4 ... Draft terminal
5 ... Scheduler terminal
6 ... Outsourcing terminal
7 ... Digital direction server
8 ... Terminal terminal
9 ... Network
10 ... Workflow management system
11 ... Advance Information Management Department
12 ... Large Schedule Management Department
13 ... Submission Management Department
14 ... Schedule Management Department
15 ... Work instruction management unit
21 ... Material database
d4 ... Order information
d5 ... Breakdown information
d6 ... Summary information
d7 ... Fold
d8 ... page
d9 ... Practical version
d10 ... Part information
d11 ... Large schedule flow
d12 ... Large schedule scheduled work date
d13 ... Large schedule member
d14 ... Small schedule flow
d15 ... Schedule top scheduled date and time
d16 ... small schedule member
d17 ... Result information
d18 ... Prior information
d19 ... table allocation information
d20: Maintenance utility
d20a ... Pattern dictionary
d20b ... Member dictionary
d20c ... Flow dictionary
d20d ... Work parameter dictionary
d21 ... Large schedule
d22 ... Small schedule
d23 ... Submission information
d24 ... Progress information

Claims (2)

複数種類の工程からなる印刷物を製造するためのワークフロー管理システムにおいて、
少なくとも前記印刷物に関する処理量情報及び日程情報と、単位当りの時間A、準備時間B、初校と後校の比率C及び倍率xからなる前記各工程の作業パラメータと、前記各工程の日付毎に、前記印刷物の識別情報を対応させた概略日程と、前記概略日程の各工程に用いられる各装置の前記日付内の時間帯毎に、前記印刷物の作業単位の識別情報を対応させた詳細日程と、が読出/書込可能に記憶されるデータベース装置と、
少なくとも前記印刷物に関する処理量情報及び日程情報を前記データベース装置に入力するための事前情報入力手段と、
前記作業パラメータを前記データベース装置に設定するための設定手段と、
前記データベース装置内の作業パラメータに基づいて、各工程の標準作業時間=(A・x+B)×Cを算出し、得られた各工程の標準作業時間に開始可能日時を付加したコマを工程毎に作成し、得られた各コマと前記データベース装置内の処理量情報及び日程情報に基づいて、当該処理量情報に示される処理可能な量を超えないように、前記各工程の日付毎に、前記印刷物の識別情報を対応させた概略日程を立案し、この概略日程を前記データベース装置に書き込む概略日程立案手段と、
前記印刷物に用いられる原稿の入稿の際に、前記印刷物に関する処理量情報及び日程情報を確定的に前記データベース装置に入力するための入稿手段と、
前記入稿手段により入力された前記データベース装置内の処理量情報及び日程情報に基づいて、前記概略日程立案手段により立案された前記データベース装置内の概略日程を詳細化し、前記各工程に用いられる各装置の前記日付内の時間帯毎に、前記印刷物の作業単位の識別情報を対応させた詳細日程を立案し、この詳細日程を前記データベース装置に書き込む詳細日程立案手段と、
前記詳細日程立案手段により立案された前記データベース装置内の詳細日程に基づいて、作業指示を出力する作業指示手段と
を備えたことを特徴とするワークフロー管理システム。
In a workflow management system for manufacturing printed materials consisting of multiple types of processes,
At least processing amount information and schedule information related to the printed matter, time per unit A, preparation time B, work parameter of each step consisting of the ratio C and magnification x between the first school and the back school, and the date of each step , An approximate schedule corresponding to the identification information of the printed matter, and a detailed schedule corresponding to the identification information of the work unit of the printed matter for each time zone within the date of each device used for each step of the approximate schedule, , And a database device that is readable / writable, and
Prior information input means for inputting at least processing amount information and schedule information related to the printed matter to the database device ;
Setting means for setting the work parameter in the database device;
Based on the work parameters in the database device, a standard work time of each process = (A · x + B) × C is calculated, and a frame obtained by adding a startable date and time to the obtained standard work time for each process Created and based on each piece obtained and the processing amount information and schedule information in the database device, for each date of each step so as not to exceed the processable amount indicated in the processing amount information, An approximate schedule planning means for planning the approximate schedule corresponding to the identification information of the printed matter and writing the approximate schedule to the database device ;
A submission means for deterministically inputting processing amount information and schedule information related to the printed matter to the database device when the manuscript used for the printed matter is submitted;
Based on the processing amount information and schedule information in the database device inputted by the submission means , the rough schedule in the database device planned by the rough schedule planning means is detailed and used for each step. Detailed schedule planning means for planning a detailed schedule corresponding to the identification information of the work unit of the printed matter for each time zone within the date of the apparatus, and writing the detailed schedule to the database device ;
A workflow management system comprising: work instruction means for outputting a work instruction based on the detailed schedule in the database device planned by the detailed schedule planning means.
請求項1に記載のワークフロー管理システムにおいて、
前記事前情報入力手段により処理量情報及び日程情報が入力されるとき、前記概略日程の立案を開始させる立案依頼指令を前記概略日程立案手段に入力するための立案依頼手段と、
前記概略日程立案手段により立案された前記データベース装置内の概略日程を出力し、この概略日程に対する承認通知を受けたとき、前記概略日程を確定し、前記概略日程に対する非承認通知を受けたとき、前記データベース装置内の概略日程を消去する日程承認手段と
を備えたことを特徴とするワークフロー管理システム。
The workflow management system according to claim 1,
A plan requesting unit for inputting a plan request command to start the planning of the rough schedule when the processing amount information and the schedule information are input by the prior information input unit;
When the rough schedule in the database device planned by the rough schedule planning means is output, and when the approval notification for the rough schedule is received, the rough schedule is confirmed, and when the non-approval notification for the rough schedule is received, A workflow management system comprising: schedule approval means for deleting a rough schedule in the database device .
JP27130797A 1997-10-03 1997-10-03 Workflow management system Expired - Fee Related JP3982026B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27130797A JP3982026B2 (en) 1997-10-03 1997-10-03 Workflow management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27130797A JP3982026B2 (en) 1997-10-03 1997-10-03 Workflow management system

Publications (2)

Publication Number Publication Date
JPH11110453A JPH11110453A (en) 1999-04-23
JP3982026B2 true JP3982026B2 (en) 2007-09-26

Family

ID=17498233

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27130797A Expired - Fee Related JP3982026B2 (en) 1997-10-03 1997-10-03 Workflow management system

Country Status (1)

Country Link
JP (1) JP3982026B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002015190A (en) * 2000-06-30 2002-01-18 Tokyo Shoseki Insatsu Kk Method and system for order reception and production of publication
JP4683443B2 (en) * 2000-10-06 2011-05-18 大日本印刷株式会社 Print production system using network
US20050033636A1 (en) * 2001-11-05 2005-02-10 Shuhei Miura Advertisement creation support system and advertisement creation support control method
JP2008044766A (en) * 2006-08-21 2008-02-28 Ishida Co Ltd Sorting information processing device and sorting system using it
JP5938430B2 (en) 2014-03-26 2016-06-22 富士フイルム株式会社 Table allocation apparatus, method and program
JP7148882B2 (en) * 2018-06-14 2022-10-06 ものレボ株式会社 Information processing equipment

Also Published As

Publication number Publication date
JPH11110453A (en) 1999-04-23

Similar Documents

Publication Publication Date Title
US7257767B1 (en) System and method for publishing documents
AU2005314721B2 (en) System and method for yearbook creation
US20100063860A1 (en) Method for managing a business process related to a document publishing project
US20030046152A1 (en) Electronic advertisement system and method
JP2002504245A (en) Operating resource management system
WO2007045632A2 (en) Method computer programme and device for generation of individualised print media copies
JP3982026B2 (en) Workflow management system
EP1298558A2 (en) Optimisation algorithm for a label printing system using plates
WO1993024892A1 (en) Methods and apparatus for quote processing
JP2004302613A (en) Electronic decision processing method, electronic decision processor, program, and recording medium
WO1997028506A1 (en) Custom product estimating and order processing system
JP2004220548A (en) Medium production information system
EP1188128A1 (en) System and method for publishing documents
JP3916199B2 (en) Workflow matter input method, workflow management system, and workflow matter automatic input device
JPH11345270A (en) Business processing system
JPH09190474A (en) Plate making process progress control system
JP2002297935A (en) Trial calculation, estimate and order receiving and placing processing system for receiving and placing order for printed matter
WO2001096118A1 (en) System and method for the grouping of print jobs through an online communications network
JP2004054311A (en) Web printing system
Braa et al. From Paperwork to Network
JP2000242724A (en) Method for linking business support system and job flow system
JP2003187113A (en) Order entry and order placement system, order entry and order placement method and order entry and order placement program
US20040186742A1 (en) Method for managing the manufacture of a printed product
Gimenez et al. Implementing a Distribution Requirement Planning System in a Distribution Company
JP2002248742A (en) Method for producing printed matter/stamp and method for intermediating printed matter/stamp order reception and placement

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040916

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070327

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070509

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070612

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070625

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100713

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110713

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110713

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120713

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120713

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130713

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees