JP3946517B2 - Seismic reinforcement method for existing steel arch bridge - Google Patents

Seismic reinforcement method for existing steel arch bridge Download PDF

Info

Publication number
JP3946517B2
JP3946517B2 JP2001400111A JP2001400111A JP3946517B2 JP 3946517 B2 JP3946517 B2 JP 3946517B2 JP 2001400111 A JP2001400111 A JP 2001400111A JP 2001400111 A JP2001400111 A JP 2001400111A JP 3946517 B2 JP3946517 B2 JP 3946517B2
Authority
JP
Japan
Prior art keywords
concrete
lightweight
arch
filling
steel arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2001400111A
Other languages
Japanese (ja)
Other versions
JP2003193420A (en
Inventor
久一 丸山
昇 坂田
修司 柳井
稔 北原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2001400111A priority Critical patent/JP3946517B2/en
Publication of JP2003193420A publication Critical patent/JP2003193420A/en
Application granted granted Critical
Publication of JP3946517B2 publication Critical patent/JP3946517B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は,鋼管アーチ橋のアーチリブなどのように構造物の荷重を受けている載荷金属管に対し,載荷状態のままで,その耐荷性能や耐震性能を向上させる既設鋼アーチ橋の耐震補強工法に関する。
【0002】
【従来の技術】
自動車荷重の増大に伴う供用時荷重の見直しや,阪神淡路大震災での被災経験などから,補強が必要な構造物は少なくないことが明らかとなってきた。鋼管アーチ橋のアーチリブなどのように,構造物の荷重を受けている金属管の場合でも同様である。このような載荷金属管(鋼管)に対して,どのようにして耐荷・耐震性能を向上させるかが課題となるが,管内にコンクリートを充填する補強法が注目される。コンクリートの充填によって管の座屈を防止し且つ剛性を高めることができるであろう。
【0003】
【発明が解決しようとする課題】
アーチリブのような鋼管内にコンクリートを充填する場合には,コンクリート充填による重量増加が下部構造に大きな影響を及ぼす。コンクリートを充填すると部材の自重は例えば単位容積質量で2.4〜3.0t/m3程度となり,そのうちコンクリートが占める単位容積質量は2.2〜2.4t/m3(普通コンクリートの場合)程度である。このため,補強部位にとどまらず,下部構造などのその他の部位にまで補強を行う必要が生ずる。しかし,この荷重増のために,基礎地盤などの下部構造をさらに補強しようとすると容易なことではない。
【0004】
単位容積質量の小さいコンクリートを充填すれば,下部構造の補強を必要としない場合もあり得ると考えられるが,軽量骨材を用いた単位容積質量の小さい通常の軽量コンクリートでは振動締固めを行わないと鋼管とコンクリートを一体化することができない。しかし,管径がそれほど大きくなく管長が長い既設アーチリブなどでは,管内でコンクリートの振動締固めを行わせることは実質的に不可能である。
【0005】
したがって本発明の課題は,このような問題を解決して,橋梁のアーチリブのような載荷金属管に対し,既設の状態で施工性よく,その耐荷性能や耐震性能を向上できる補強工法を提供することにある。
【0006】
【課題を解決するための手段】
本発明は,鋼アーチ橋のアーチリブ内にコンクリートを充填して既設橋を耐震補強する工法において,軽量骨材を配合したスランプフロー値50cm以上の軽量・高流動コンクリートを,コンクリートの打設範囲より高い位置に設けたコンクリート打設口から,アーチリブ内に存在した空気を追い出しながらアーチリブ内に流し込んで,該アーチリブの両裾底部から上方に向って順次自重充填し,最後に頂部のアーチクラウン部に,アーチリブ内に存在した空気を追い出しながら,該コンクリートを圧入充填して,アーチリブ内空間の実質上全てを単位容積質量が1.8t/m3以下の軽量コンクリートで充填することを特徴とする既設鋼アーチ橋の耐震補強工法を提供する。軽量・高流動コンクリートとしては,軽量粗骨材とモルタル(空気量を含む)との密度差が0.4g/cm3以下であるのがよく,また増粘剤を配合してペーストの粘性変化を抑制したものであるのがよい。
【0007】
【発明の実施の形態】
図1に本発明の補強工法を適用する鋼管アーチ橋の例を示した。補強対象とする鋼管製のアーチリブ1は,本発明工法の実施の便宜上,その施工部分を図の左側アーチ裾部1A,右側アーチ裾部1Bおよび中央頂部のアーチクラウン部1Cに区分する。
【0008】
図例のものでは,アーチ裾部1Aと1Bは,両者とも,さらにステップ1〜6に区分されており,これらの部分では,橋下に設置したブーム付コンクリートポンプ車2Aと2Bにより,下から上に順に(ステップ1から6に順に),両方のアーチ裾部とも打設時期をほぼ同じくしてリブ内に軽量・高流動コンクリートを充填してゆく。これによって,アーチクラウン部1Cが未打設となるが,次に橋面上に設置したブーム付コンクリートポンプ車2Cによって,裾側からステップ7〜9に区分された順に,リブ内にコンクリートを充填してゆく。
【0009】
図2は,図1のアーチリブの左半身を示したものである。図中の▲1▼〜▲9▼は図1のステップ1〜9で打設する範囲(ブロック)を示している。橋下または橋面のどのポンプ車を使用するにしろ,ステップ1〜8(▲1▼〜▲8▼のブロック)は,打設範囲より高い位置に設けたコンクリート打設口3a〜3fから軽量・高流動コンクリートを打設範囲に流し込む。そのさい,各打設ブロックにおいて,コンクリート打設口3a〜3fよりやや高い位置に空気孔4a〜4fが設けておく。このように,やや勾配が急な打設ブロック▲1▼〜▲8▼では,コンクリートの流動性を利用した高所からの「流し込みコンクリート打設方法」を採用する。図2において,この区間を「自重充填」と記してある。この自重充填を図の左半身と図示しない右半身について終えると,次にステップ9(ブロック▲9▼)では「圧入充填」(図2参照)を行う。
【0010】
すなわち,打設ブロック▲9▼ではほぼ水平に近い。ほぼ水平な管内に軽量・高流動コンクリートを流し込む場合には,気泡空隙(コンクリート中の気泡とは異なり,管内壁とコンクリートとの接合面に発生する気泡状の空隙)が発生するおそれがあることを本発明者らは実験的に確認した。管壁とコンクリートの接合面に気泡状の空隙が発生すると,この部分に応力集中をもたらすことがある。このため,コンクリートポンプ車の圧力を利用した圧入打設方法(逆巻き)を採用して管とコンクリートとの一体化を図る。
【0011】
実際には,この打設ブロック▲9▼では,管壁に設けるコンクリート投入口3gの位置を,コンクリート打設レベル(管内壁の最高位置)よりも下方に設ける。そして,このコンクリート投入口3gには,1〜2m程度の高さの打設用パイプ(図示しない)を立ち上げておき,この打設用パイプに遮断弁(図示しない)を介装しておく。これにより,投入口付近でのポンプ圧力の不慮の減少等によるコンクリートの緩みや戻りを防止する。
【0012】
このようにしてアーチリブ内に軽量・高流動コンクリートの注入を終了するが,このコンクリートがリブの内部空間に隙間や空隙なく充填されていることが肝要である。このためには,材料分離が生ぜず且つ良好な流動性を有するコンクリートを使用することはもちろんのこと,各ブロックごとにおいて充填性を確認することも必要である。この確認のために,空気孔はもとよりその他の適切な箇所にコンクリート流出口を設け,その流出口にパイプや透明ホースを取付けて空気の排出を図るとともに,これらから流出するコンクリートの性状により充填状況の観察を行う。また,打音により空隙の有無を確認することも有益である。
【0013】
アーチリブ内にコンクリートを充填すると,その重量増加による基礎構造部6A,6B等の影響が懸念されるところであるが,補強対象とする鋼管アーチ橋の地盤から見て,コンクリートを充填したあとの部材自重が単位容積質量で2.02.5t/m3程度であれば,該基礎構造物に対して殆んど補強を必要としない事例は数多くあり得る。しかし,このためには,コンクリートの自重を単位容積質量で(硬化状態)1.9t/m3以下とする必要がある。
【0014】
加えて,この軽量化のために軽量骨材を配合しても,材料分離することなくアーチリブ内を流動する良好な流動性,さらには締固めを必要としない自己充填性を具備し,硬化状態では補強工法に資することができるに十分な強度を発現する軽量・高流動コンクリートでなければならない。
【0015】
従来より,アーチリブ内に軽量・高流動コンクリートを充填した事例がなく,その充填性の評価指標も不明であるが,前記のような状況から,高い流動性,材料分離抵抗性,自己充填性,構造体として要求される圧縮強度が15〜60N/mm2で単位容積質量が1.4〜1.9t/m3の諸性質を同時に満足することが少なくとも必要である。
【0016】
軽量・高流動コンクリートは,一般に,自己充填性を有する高流動コンクリート(いわゆるハイパフォマンスコンクリート)の技術と,建築分野を中心に開発されている軽量骨材コンクリートの技術を組み合わせればよいとも考えられるが,セメントペーストより密度の小さい軽量骨材を使用する場合には,流動性を高めると材料分離が顕著となるので,本発明工法の適用には,特別の配慮が必要である。
【0017】
以下に,本発明の載荷金属管の補強工法に使用する軽量・高流動コンクリートについて説明する。
【0018】
まず,軽量骨材とペーストとの材料分離が発生のを防止しながら高い流動性と自己充填性を満足させるために,モルタル自身の軽量化を図る。すなわち,軽量粗骨材とモルタル(空気量を含む)の密度差を小さくする。実際にはその密度差を0.4g/cm3以下とする。そのために次の手法を採用する。
(1) セメントに加えてフライアッシュやシリカフュームなどの密度の小さい粉体を相当量配合してモルタルの密度を下げる。好ましくは市場で安価に入手できるフライアッシュがよい。
(2) 空気量を4〜10%混入してモルタルの密度を下げる。
(3) 細骨材の一部もしくは全部を軽量細骨材してモルタルの密度を下げる。
【0019】
この手法により,軽量粗骨材との密度差を殆んどなくすことができ,場合によってはその差を皆無とすることが可能であり,密度差による分離が生じない軽量コンクリートとすることができる。
【0020】
このほかにも,ペーストの粘性をコントロールすることにより,材料分離抵抗性を向上させ,これによって軽量粗骨材の浮き上がりを抑制することもできる。このためには,
(4) 水粉体容積比を下げてペーストの粘性を調整する。
(5) バイオポリマー系の増粘剤,好ましくはウエランガムを配合してペーストの粘性を調整する。
という手法を採用するのがよい。
【0021】
なお,(3) のように「軽量細骨材」を使用した場合には,モルタル中で材料分離が生ずる,すなわち,モルタル中のペーストと軽量細骨材の密度差によって,軽量細骨材が浮き上がる現象が起きることがあるが,この場合も,前記の (1)〜(2) および (4)〜(5) の手法を採用することによって,これを抑制することができる。
【0022】
次に,軽量骨材を使用しても,構造体としての圧縮強度15〜60N/mm2を安定して確保するために,
(6) 水結合材比を70%以下とする。
(7) コンクリート中の空気量を10%以下とする。
とくに,セメントに加えて結合材の一部としてフライアッシュやシリカフュームを使用した場合には,これらの粉体が他の結合材よりも密度が小さくかつポゾラン反応よる硬化体を形成するので,軽量で強固なコンクリートを得ることができる。
【0023】
ポンプ施工する場合には,その圧によって軽量骨材の内部空隙に吸水し,圧送中にコンクリートの流動性が失われることがある。また金属管内への注入距離が長くなったり圧力充填する場合にも同様の現象が起きる。このようなことを抑制するために,
(8) 配合する前の軽量骨材を十分にプレソーキングまたはプレウェッテイングして軽量骨材内部の空隙を予め水で満たしておく。
(9) ウエランガムを添加する。
ウエランガムを添加しておくと,骨材内部の空隙に圧入され難いような自由水(粘りのある水)がコンクリート中に形成されるので,圧を受けて軽量骨材が吸水する余地がある場合でも,その吸水を防止できる。
【0024】
また,軽量骨材では表面水率や含水率の測定が複雑になり,このため生コンクリート工場での製造時にコンクリート中の水量管理が難しく,このために自己充填性の変動が大きくなる。また,本発明では高い流動性を付与するために高性能AE減水剤の使用が前提となり,この混和剤が温度依存性があるので,外気温やコンクリート温度によってコンクリート性状が変化する。このようなコンクリート性状の変化を抑制するために,
(10)バイオポリマー系の増粘剤(ウエランガム)を添加する。
ウエランガムを添加すると,外気温やコンクリート温度に関わらずペーストの粘性を一定に保つことができ,このために高性能AE減水剤の温度依存性も緩和することができる。また,実際の練混ぜに供する軽量骨材の含水率や表面水率は刻々と変化するが,ウエランガムの添加によってそのような変化が生じていてもその変化を緩和することが可能となる。したがって,骨材の性状管理が煩雑な軽量骨材コンクリートの製造性が非常に良好となる。
【0025】
以上のような (1)〜(10)の処法を採用することによって,高い流動性(スランプフロー値で50cm以上),材料分離抵抗性,自己充填性,構造体として要求される圧縮強度16〜60N/mm2の強度,並びに単位容積質量1.4〜1.9t/m3の軽量性を有し,製造時の品質変動が少なく,長距離圧送が可能で金属管等の狭くて長い閉塞空間に圧入施工しても管壁との接合面に空隙を生ずることなく金属管とコンクリートとを一体化できる軽量・高流動性コンクリートが得られるので,本発明の載荷金属管の補強工法に有利に使用することができる。
【0026】
そのさい,使用する軽量骨材とては,比較的安価で入手が容易な軽量骨材例えばアサノライトやメサライトを使用することができ,ポンプ施工を行う場合にはこれをプレソーキング,プレウェッテイングする。ポンプ施工を行わない場合には絶乾もしくは気乾状態のものを使用できる。これらの軽量骨材の使用にあたって肝要なことは,絶乾比重で0.8〜1.3g/cm3程度,吸水率2〜8%程度の軽量骨材を使用することができるが,前記のように,軽量粗骨材として配合したときにモルタルとの密度差が0.4g/cm3以下となるように,また軽量粗骨材として配合したときにペーストとの密度差が0.4g/cm3以下となるようにすることである。
【0027】
また,少ない単位水量で高い流動性を維持するために高性能AE減水剤を使用することが不可欠であるが,使用できる高性能AE減水剤としては,市販のポリカルボン酸系,メラミンスルホン酸系またはナフタレンスルホン酸系のものが使用できる。好ましいのはポリカルボン酸系またはナフタレンスルホン酸系のものである。さらに,前記のように空気量を調整するために,空気量調整剤を配合する。セメント,フライアッシュ,高炉スラグ微粉末,シリカフューム等の粉体使用量については,材料分離抵抗性を付与するうえで400〜700kg/m3とするのがよい。
【0028】
以下に試験例を挙げる。
【0029】
試験には表1に使用材料を記した。粗骨材および細骨材とも軽量骨材である。
これらの材料を,表2に示すコンクリート配合で練り混ぜ,「高流動(1) 」「高流動(2) 」および「自己充填」の3種類のコンクリートを製造し,そのフレッシュ性状と硬化性状について,表3に示す項目の試験を行った。表4にフレッシュ性状の測定結果を,表5に硬化性状の測定結果を示した。
【0030】
【表1】

Figure 0003946517
【0031】
【表2】
Figure 0003946517
【0032】
【表3】
Figure 0003946517
【0033】
【表4】
Figure 0003946517
【0034】
【表5】
Figure 0003946517
【0035】
表4および表5の結果に見られるように,各配合のコンクリートとも,本発明で目標としているスランプフロー,単位容積質量,空気量および圧縮強度を満足している。自己充填性については,軽量骨材を用いた場合の評価試験値が存在しないので,表6として挙げた普通骨材を用いた場合の評価試験値(土木学会の「高流動コンクリート施工指針」のうちの「高流動コンクリートの自己充填性のランクと各評価試験値」を参考にして,表4の結果を評価すると,「高流動(1) 」と「高流動(2) 」のものは,表6の自己充填性のランク3の条件の一部を満足しない結果となったが,「自己充填」のものは,表6の自己充填性のランク3の条件の全てを満足するものとなった。
【0036】
さらに,透明アクリル板を用いて作成した400×200×高さ1000mmの直方体の型枠を,傾斜角度30度に傾けた状態で,型枠上面に設けたコンクリート注入口(90mmφ)から前記のコンクリートを流し込み,型枠への充填状況を観察したところ,3種ともすみずみまで充填されたが,「自己充填」のものは「高流動(1) 」と「高流動(2) 」のものよりも,打設面がより水平面を保つ状況が観察され,小さい流動勾配で良好に充填されることがわかった。「高流動(1) 」と「高流動(2) 」のものも5秒間のバイブレータの使用により良好な充填性を得ることができることがわかった。脱型後の供試体外観を調べると,「自己充填」のものは気泡がなく角部が鋭角的に充填されていたのに対し,他の2体では側面に気泡が散見され,「高流動(1) 」では勾配下側角部に粗骨材が露出している状況が観察された。さらに供試体断面を切断して骨材分布を観察したところ,「自己充填」のものは他の2体のものに比べて粗骨材が一様に分布している状況が観察され,材料分離が生じていないことが確認された。
【0037】
以上の試験結果を参考にして,表6の配合のコンクリートを現場練りした。使用材料は表1に記載したものと同じであり,練り混ぜは1バッチ当り1.1m3として4バッチ合わせとした。練り混ぜ手順は,材料投入(G+S+C+FA)→空練り15秒→混練水投入(W+Ad)→300秒練り混ぜ→排出とした。生コンクリートの出荷時,アジテータ車で40分間運搬後の荷降し時,ポンプ圧送後(ポンプ車のブームを床面から8mの高さに立てて圧送し,ホースの筒先を床面から75cm離してその筒先からコンクリート吐出),および流動後(型枠のコンクリート注入口にホースの筒先を接続して注入したもの)について,それぞれ試料を採取し,フレッシュ性状と硬化性状を測定した。その結果を表7および表8に示した。
【0038】
【表6】
Figure 0003946517
【0039】
【表7】
Figure 0003946517
【0040】
【表8】
Figure 0003946517
【0041】
表7および表8の結果は,このコンクリートで図1の施工を実施する場合の管理目標値であるスランプフロー(JSCE−F503)=650±50mm,500mmフロー到達時間=3〜15秒,空気量(JISA1116)=6.0±1.5%,単位容積質量(JISA1116)=1.8t/m3以下,V75漏斗流下試験(土木学会基準案)=13±5秒,U型充填性試験(土木学会基準案)=300mm以上(障害R2 ),圧縮強度(JISA1108)=18N/mm2以上をコンクリート荷降し時において全て満足した。ポンプ圧送後では流動性は多少小さくなったが,十分なポンプ圧送性および自己充填性を有することは前例の試験結果から明らかである。
【0042】
【発明の効果】
以上説明したように,本発明によると 鋼管アーチ橋のアーチリブなどのように構造物の荷重を受けている載荷金属管に対し,載荷状態のままで,その耐荷性能や耐震性能を向上させることができる。また,本発明工法は,基礎構造などへの負荷が小さい,振動締固めを要しない,ポンプ圧送できるなどの点で,施工性および経済性に優れており,補強を必要とする載荷金属管を経済的に補強できる点で,建築・土木構造物の保全に多大の貢献ができる。
【図面の簡単な説明】
【図1】本発明の載荷金属管の補強工法を鋼管アーチ橋のアーチリブに適用する場合の施工例を示す図である。
【図2】図1のアーチリブの左半身部の詳細を示す図である。
【符号の説明】
1 アーチリブ
2 ブーム式ポンプ車
3 コンクリート打設口
4 空気孔[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a seismic reinforcement method for an existing steel arch bridge that improves the load bearing performance and seismic performance of loaded metal pipes that are subjected to structural loads such as arch ribs of steel pipe arch bridges in the loaded state. About.
[0002]
[Prior art]
It has become clear that there are many structures that need to be reinforced, based on reviews of in-service loads that accompany the increase in automobile loads and experiences from the Great Hanshin-Awaji Earthquake. The same applies to metal pipes that are subjected to structural loads, such as arch ribs on steel pipe arch bridges. The challenge is how to improve the load resistance and seismic performance of such a loaded metal pipe (steel pipe), but the reinforcement method of filling the pipe with concrete is drawing attention. Concrete filling could prevent tube buckling and increase stiffness.
[0003]
[Problems to be solved by the invention]
When filling concrete into steel pipes such as arch ribs, the increase in weight due to concrete filling has a significant effect on the substructure. When concrete is filled, the weight of the member is about 2.4 to 3.0 t / m 3 in unit volume mass, for example, and the unit volume mass occupied by concrete is 2.2 to 2.4 t / m 3 (in the case of ordinary concrete) Degree. For this reason, it is necessary to reinforce not only the reinforcement part but also other parts such as the substructure. However, it is not easy to reinforce the substructure such as the foundation ground due to this load increase.
[0004]
If concrete with a small unit volume mass is filled, it may not be necessary to reinforce the substructure, but vibration compaction is not performed with ordinary lightweight concrete with a small unit volume mass using lightweight aggregates. And steel pipe and concrete cannot be integrated. However, with existing arch ribs, etc., where the pipe diameter is not so large and the pipe length is long, it is practically impossible to cause vibration compaction of concrete in the pipe.
[0005]
Therefore, an object of the present invention is to provide a reinforcing method capable of solving such problems and improving the load carrying capacity and seismic performance of a loaded metal pipe such as an arch rib of a bridge with good workability in an existing state. There is.
[0006]
[Means for Solving the Problems]
The present invention is filled with concrete in Achiribu steel arch bridge Te method odor seismic retrofitting an existing bridge, the slump flow value 50cm or more lightweight, high fluidity concrete blended with lightweight aggregate, the concrete hitting concrete設口or we provided higher than setting range position, is poured Do expel air present in the a Chiribu is in Raa Chiribu, sequential self-weight filling me toward upward from both hem bottom of the Achiribu Finally, the concrete is pressed and filled into the top arch crown while expelling the air present in the arch rib, so that substantially the entire space inside the arch rib is light weight with a unit volume mass of 1.8 t / m 3 or less. An earthquake-proof reinforcement method for existing steel arch bridges, which is characterized by filling with concrete. For lightweight and high fluidity concrete, the density difference between lightweight coarse aggregate and mortar (including air) should be 0.4g / cm 3 or less. It is good to suppress this.
[0007]
DETAILED DESCRIPTION OF THE INVENTION
FIG. 1 shows an example of a steel pipe arch bridge to which the reinforcing method of the present invention is applied. The steel pipe arch rib 1 to be reinforced is divided into a left arch skirt portion 1A, a right arch skirt portion 1B, and an arch crown portion 1C at the center top of the drawing for the convenience of carrying out the method of the present invention.
[0008]
In the illustrated example, the arch skirts 1A and 1B are both further divided into steps 1 to 6, and in these parts, the boom-equipped concrete pump trucks 2A and 2B are installed from the bottom up. In order (in order from step 1 to step 6), both the arch skirts are filled with lightweight, high-fluidity concrete in the ribs at almost the same timing. As a result, the arch crown portion 1C is not placed, but the concrete is filled in the ribs in the order of steps 7 to 9 from the skirt side by the boom concrete pump car 2C installed on the bridge surface. I will do it.
[0009]
FIG. 2 shows the left half of the arch rib of FIG. In the figure, (1) to (9) indicate ranges (blocks) to be placed in steps 1 to 9 in FIG. Regardless of which pump car is used under the bridge or on the bridge surface, steps 1 to 8 (blocks (1) to (8)) are light weighted from the concrete placement ports 3a to 3f provided above the placement range. Pour high fluidity concrete into the casting area. At that time, air holes 4a to 4f are provided at positions slightly higher than the concrete placement ports 3a to 3f in each placement block. In this way, in the placement blocks {circle around (1)} to {8} with a slightly steep slope, the “casting concrete placement method” from a high place using the fluidity of concrete is adopted. In FIG. 2, this section is marked as “self-weight filling”. When the self-weight filling is completed for the left half of the figure and the right half (not shown), next, in step 9 (block (9)), “press-fit filling” (see FIG. 2) is performed.
[0010]
That is, the placement block (9) is almost horizontal. When light-weight and high-fluidity concrete is poured into an almost horizontal pipe, there is a possibility that a bubble void (a bubble void generated at the joint surface between the pipe inner wall and the concrete, unlike the bubbles in the concrete) may occur. The inventors have confirmed this experimentally. If air bubbles are generated in the joint surface between the pipe wall and the concrete, stress concentration may occur in this area. For this reason, the pipe and concrete are integrated by adopting a press-fitting method (reverse winding) using the pressure of the concrete pump truck.
[0011]
Actually, in this placement block (9), the position of the concrete charging port 3g provided in the pipe wall is provided below the concrete placement level (the highest position of the pipe inner wall). Then, a casting pipe (not shown) having a height of about 1 to 2 m is set up at the concrete charging port 3g, and a shut-off valve (not shown) is interposed in the casting pipe. . This prevents loosening and returning of concrete due to an unexpected decrease in pump pressure near the inlet.
[0012]
In this way, the injection of lightweight, high-fluidity concrete into the arch rib is completed, but it is important that this concrete is filled in the internal space of the rib without gaps or voids. For this purpose, it is necessary not only to use concrete that does not cause material separation but also to have good fluidity, and also to check the filling property for each block. In order to confirm this, concrete outlets are provided not only in the air holes but also in other appropriate locations, and pipes and transparent hoses are attached to the outlets to discharge the air, and the state of filling depends on the properties of the concrete flowing out of these. Observe. It is also useful to confirm the presence or absence of voids by hitting sound.
[0013]
When concrete is filled in the arch ribs, there is a concern about the influence of the foundation structure 6A, 6B, etc. due to the increase in weight. However, the weight of the member after filling the concrete as seen from the ground of the steel pipe arch bridge to be reinforced If the unit volume mass is about 2.02.5 t / m 3 , there may be many cases where the foundation structure is hardly required to be reinforced. However, for this purpose, the concrete weight must be 1.9 t / m 3 or less in terms of unit volume mass (hardened state).
[0014]
In addition, even if lightweight aggregate is blended for this weight reduction, it has good fluidity to flow through the arch ribs without material separation, and also has a self-filling property that does not require compaction, and is cured. Then, it must be lightweight and high fluidity concrete that develops sufficient strength to contribute to the reinforcement method.
[0015]
Conventionally, there has been no case of filling lightweight and high-fluidity concrete in the arch ribs, and the evaluation index of the filling property is unknown, but from the above situation, high fluidity, material separation resistance, self-filling property, It is at least necessary to simultaneously satisfy various properties of a compressive strength required for a structure of 15 to 60 N / mm 2 and a unit volume mass of 1.4 to 1.9 t / m 3 .
[0016]
In general, lightweight / high-fluidity concrete is considered to be a combination of high-fluidity concrete with self-filling properties (so-called high performance concrete) and lightweight aggregate concrete developed mainly in the construction field. However, when lightweight aggregates with a density lower than that of cement paste are used, the material separation becomes remarkable when the fluidity is increased. Therefore, special consideration is required for the application of the method of the present invention.
[0017]
Below, the lightweight and high fluidity concrete used for the reinforcement method of the loading metal pipe of this invention is demonstrated.
[0018]
First, in order to satisfy the high fluidity and self-filling properties while preventing the occurrence of material separation between the lightweight aggregate and the paste, the weight of the mortar itself is reduced. That is, the density difference between the light coarse aggregate and the mortar (including the amount of air) is reduced. Actually, the density difference is set to 0.4 g / cm 3 or less. Therefore, the following method is adopted.
(1) In addition to cement, a considerable amount of low density powder such as fly ash and silica fume is blended to lower the density of the mortar. Preferably, fly ash which can be obtained at low cost in the market is good.
(2) Reduce the density of the mortar by mixing 4-10% of air.
(3) Reduce the density of the mortar by making a part or all of the fine aggregate lightweight lightweight aggregate.
[0019]
By this method, the density difference with the light coarse aggregate can be almost eliminated, and in some cases, the difference can be eliminated at all, and the lightweight concrete can be obtained without separation due to the density difference. .
[0020]
In addition, the material separation resistance can be improved by controlling the viscosity of the paste, thereby suppressing the lifting of the lightweight coarse aggregate. For this,
(4) Adjust the viscosity of the paste by lowering the water powder volume ratio.
(5) The viscosity of the paste is adjusted by adding a biopolymer thickener, preferably welan gum.
It is better to adopt this method.
[0021]
In addition, when “lightweight fine aggregate” is used as in (3), material separation occurs in the mortar, that is, the lightweight fine aggregate is separated by the density difference between the paste in the mortar and the lightweight fine aggregate. In some cases, this phenomenon can be suppressed by adopting the methods (1) to (2) and (4) to (5) described above.
[0022]
Next, in order to stably secure a compressive strength of 15 to 60 N / mm 2 as a structure even if a lightweight aggregate is used,
(6) The water binder ratio is 70% or less.
(7) The amount of air in the concrete shall be 10% or less.
In particular, when fly ash or silica fume is used as part of the binder in addition to cement, these powders are less dense than other binders and form a hardened body due to the pozzolanic reaction. Strong concrete can be obtained.
[0023]
When pumping, the pressure may cause water absorption in the internal space of the lightweight aggregate, and the fluidity of the concrete may be lost during pumping. The same phenomenon occurs when the injection distance into the metal tube is increased or when pressure filling is performed. To suppress this,
(8) The light-weight aggregate before blending is sufficiently pre-soaked or pre-wetted to preliminarily fill the voids inside the light-weight aggregate with water.
(9) Add welan gum.
When welan gum is added, free water (sticky water) that is difficult to be pressed into the voids inside the aggregate is formed in the concrete, so there is room for the lightweight aggregate to absorb water under pressure. However, the water absorption can be prevented.
[0024]
In addition, the measurement of surface water content and water content becomes complicated with lightweight aggregates, which makes it difficult to control the amount of water in the concrete during production in a ready-mixed concrete factory, which increases fluctuations in self-fillability. Further, in the present invention, it is premised on the use of a high-performance AE water reducing agent in order to impart high fluidity. Since this admixture is temperature-dependent, the concrete properties change depending on the outside air temperature and concrete temperature. In order to suppress such changes in concrete properties,
(10) Add a biopolymer thickener (welan gum).
When welan gum is added, the viscosity of the paste can be kept constant regardless of the outside air temperature or the concrete temperature, and therefore the temperature dependence of the high-performance AE water reducing agent can be reduced. Moreover, although the moisture content and surface water content of the lightweight aggregate used for actual mixing change every moment, even if such a change occurs due to the addition of welan gum, the change can be mitigated. Therefore, the productivity of lightweight aggregate concrete with complicated property management becomes very good.
[0025]
By adopting the above methods (1) to (10), high fluidity (slump flow value of 50 cm or more), material separation resistance, self-filling property, compressive strength required as a structure 16 It has a strength of -60 N / mm 2 and a light weight of unit volume mass 1.4-1.9 t / m 3 , has little fluctuation in quality during production, can be pumped over long distances, and is narrow and long such as a metal tube Lightweight and highly fluid concrete that can be integrated with the metal pipe and concrete without creating a gap in the joint surface with the pipe wall even if it is press-fitted into the enclosed space is obtained. It can be used advantageously.
[0026]
At the same time, lightweight aggregates that are relatively inexpensive and easily available, such as asanolite and mesalite, can be used as the lightweight aggregate to be used. When pumping, this is pre-soaked and pre-wetting. To do. When pump construction is not performed, a completely dry or air-dried one can be used. The important thing in using these lightweight aggregates is that they can use lightweight aggregates with an absolute dry specific gravity of about 0.8 to 1.3 g / cm 3 and a water absorption rate of about 2 to 8%. Thus, when blended as a lightweight coarse aggregate, the density difference from the mortar is 0.4 g / cm 3 or less, and when blended as a lightweight coarse aggregate, the density difference from the paste is 0.4 g / cm 2. It should be less than cm 3 .
[0027]
In addition, it is indispensable to use a high-performance AE water reducing agent in order to maintain high fluidity with a small amount of unit water, but as a usable high-performance AE water reducing agent, commercially available polycarboxylic acid type, melamine sulfonic acid type Or a naphthalenesulfonic acid type thing can be used. Preference is given to those based on polycarboxylic acids or naphthalenesulfonic acids. Further, an air amount adjusting agent is blended in order to adjust the air amount as described above. The amount of powder used for cement, fly ash, blast furnace slag fine powder, silica fume, etc. is preferably 400 to 700 kg / m 3 in order to impart material separation resistance.
[0028]
Test examples are given below.
[0029]
Table 1 shows the materials used in the test. Both coarse and fine aggregates are lightweight aggregates.
These materials are kneaded with the concrete composition shown in Table 2 to produce three types of concrete, “High flow (1)”, “High flow (2)” and “Self-filling”. The tests shown in Table 3 were conducted. Table 4 shows the measurement results of fresh properties, and Table 5 shows the measurement results of curable properties.
[0030]
[Table 1]
Figure 0003946517
[0031]
[Table 2]
Figure 0003946517
[0032]
[Table 3]
Figure 0003946517
[0033]
[Table 4]
Figure 0003946517
[0034]
[Table 5]
Figure 0003946517
[0035]
As can be seen from the results of Tables 4 and 5, the concretes of the respective blends satisfy the slump flow, unit volume mass, air amount and compressive strength targeted by the present invention. As for self-filling properties, there are no evaluation test values when lightweight aggregates are used, so the evaluation test values when using normal aggregates listed in Table 6 (the “High Fluid Concrete Construction Guidelines” of the Japan Society of Civil Engineers) The results of Table 4 are evaluated with reference to “Rank of self-fillability of high fluidity concrete and each evaluation test value”, and the results of “High fluidity (1)” and “High fluidity (2)” Although the result of not satisfying part of the condition of rank 3 of self-filling property in Table 6 is "Self-filling", all the conditions of rank 3 of self-filling property in Table 6 are satisfied. It was.
[0036]
Furthermore, the above-mentioned concrete is formed from a concrete injection port (90 mmφ) provided on the upper surface of a mold in a state in which a 400 × 200 × 1000 mm-high rectangular mold formed using a transparent acrylic plate is inclined at an inclination angle of 30 degrees. When filling the formwork and observing the filling of the mold, all three types were filled, but the “self-filling” ones were higher than the “high flow (1)” and “high flow (2)” types. However, it was found that the casting surface maintained a more horizontal surface, and it was filled well with a small flow gradient. It was found that “high flow (1)” and “high flow (2)” can also obtain good filling properties by using a vibrator for 5 seconds. When the appearance of the specimen after demolding was examined, the “self-filling” ones had no bubbles and the corners were filled sharply, whereas in the other two bodies, bubbles were scattered on the sides and “high flow” In (1), a situation where coarse aggregate was exposed at the lower corner of the gradient was observed. Furthermore, when the cross-section of the specimen was cut and the aggregate distribution was observed, the “self-filling” specimen showed a more uniform distribution of coarse aggregate than the other two specimens. It was confirmed that no occurred.
[0037]
With reference to the above test results, concrete having the composition shown in Table 6 was kneaded on-site. The materials used were the same as those listed in Table 1, and the mixing was performed at 4 batches with 1.1 m 3 per batch. The kneading procedure was as follows: material charging (G + S + C + FA) → empty kneading 15 seconds → kneading water charging (W + Ad) → 300 seconds kneading → discharge. At the time of shipment of ready-mixed concrete, when unloading after carrying for 40 minutes with an agitator car, after pumping (pump car with the boom of the pump car raised to 8m above the floor, pumping the hose tube tip 75cm away from the floor Samples were taken and measured for fresh properties and hardenability after concrete was discharged from the tip of the lever and after flowing (injected by connecting the tip of the hose to the concrete inlet of the formwork). The results are shown in Tables 7 and 8.
[0038]
[Table 6]
Figure 0003946517
[0039]
[Table 7]
Figure 0003946517
[0040]
[Table 8]
Figure 0003946517
[0041]
The results in Table 7 and Table 8 are slump flow (JSCE-F503) = 650 ± 50 mm, 500 mm flow arrival time = 3 to 15 seconds, air volume, which is the management target value when the construction shown in FIG. (JISA1116) = 6.0 ± 1.5%, unit volume mass (JISA1116) = 1.8 t / m 3 or less, V75 funnel flow-down test (Japan Society of Civil Engineers draft standard) = 13 ± 5 seconds, U-shaped filling test ( The civil engineering society standard proposal) = 300 mm or more (failure R2) and compressive strength (JISA1108) = 18 N / mm 2 or more were all satisfied when the concrete was unloaded. After pumping, the fluidity was somewhat reduced, but it is clear from the previous test results that it has sufficient pumping and self-filling properties.
[0042]
【The invention's effect】
As described above, according to the present invention, it is possible to improve the load carrying capacity and seismic performance of loaded metal pipes that are subjected to structural loads such as arch ribs of steel pipe arch bridges in the loaded state. it can. In addition, the construction method of the present invention is excellent in workability and economic efficiency in that the load on the foundation structure is small, vibration compaction is not required, and pumping is possible. The point that it can be economically reinforced makes a great contribution to the maintenance of construction and civil engineering structures.
[Brief description of the drawings]
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is a diagram showing a construction example when the method for reinforcing a loaded metal pipe according to the present invention is applied to an arch rib of a steel pipe arch bridge.
FIG. 2 is a view showing details of a left half part of the arch rib in FIG. 1;
[Explanation of symbols]
1 Arch Rib 2 Boom Pump Car 3 Concrete Placing Port 4 Air Hole

Claims (3)

鋼アーチ橋のアーチリブ内にコンクリートを充填して既設橋を耐震補強する工法において,軽量骨材を配合したスランプフロー値50cm以上の軽量・高流動コンクリートを,コンクリートの打設範囲より高い位置に設けたコンクリート打設口から,アーチリブ内に存在した空気を追い出しながらアーチリブ内に流し込んで,該アーチリブの両裾底部から上方に向って順次自重充填し,最後に頂部のアーチクラウン部に,アーチリブ内に存在した空気を追い出しながら,該コンクリートを圧入充填して,アーチリブ内空間の実質上全てを単位容積質量が1.8t/m3以下の軽量コンクリートで充填することを特徴とする既設鋼アーチ橋の耐震補強工法。Filled with concrete in Achiribu steel arch bridge Te method odor seismic retrofitting an existing bridge, the slump flow value 50cm or more lightweight, high fluidity concrete blended with lightweight aggregate, higher than the pouring range of concrete concrete設口or we provided in the position, is poured Do expel air present in the a Chiribu is in Raa Chiribu, and sequential self-weight filling me toward upward from both hem bottom of the Achiribu, finally While expelling the air present in the arch rib, the concrete is press-filled into the top arch crown, and substantially the entire space inside the arch rib is filled with lightweight concrete having a unit volume mass of 1.8 t / m 3 or less. A seismic reinforcement method for existing steel arch bridges. 軽量・高流動コンクリートは,軽量粗骨材とモルタル(空気量を含む)との密度差が0.4g/cm3以下である請求項1に記載の既設鋼アーチ橋の耐震補強工法。2. The method for seismic reinforcement of an existing steel arch bridge according to claim 1, wherein the light weight and high fluidity concrete has a density difference of 0.4 g / cm 3 or less between the light coarse aggregate and the mortar (including air content). 軽量・高流動コンクリートは,増粘剤を配合してペーストの粘性変化を抑制したものである請求項1または2に記載の既設鋼アーチ橋の耐震補強工法。  3. The method for seismic reinforcement of an existing steel arch bridge according to claim 1 or 2, wherein the light weight and high fluidity concrete contains a thickener to suppress the viscosity change of the paste.
JP2001400111A 2001-12-28 2001-12-28 Seismic reinforcement method for existing steel arch bridge Expired - Lifetime JP3946517B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001400111A JP3946517B2 (en) 2001-12-28 2001-12-28 Seismic reinforcement method for existing steel arch bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001400111A JP3946517B2 (en) 2001-12-28 2001-12-28 Seismic reinforcement method for existing steel arch bridge

Publications (2)

Publication Number Publication Date
JP2003193420A JP2003193420A (en) 2003-07-09
JP3946517B2 true JP3946517B2 (en) 2007-07-18

Family

ID=27604850

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001400111A Expired - Lifetime JP3946517B2 (en) 2001-12-28 2001-12-28 Seismic reinforcement method for existing steel arch bridge

Country Status (1)

Country Link
JP (1) JP3946517B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452604A (en) * 2014-12-03 2015-03-25 中铁大桥局武汉桥梁特种技术有限公司 Method for reinforcing arch rib segment in arch bridge of steel structure
CN106149574A (en) * 2016-08-08 2016-11-23 江苏聚业交通科学研究有限公司 The ruggedized construction of a kind of rigid framed arch bridge and method

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101642953B1 (en) * 2015-10-13 2016-07-26 김석희 Lightweight ecological bridge, and method for constructing lightweight ecological bridge
CN108360835B (en) * 2016-05-21 2020-02-04 叶长青 Construction method for reinforcing structure of old building
CN108104505B (en) * 2016-07-12 2019-03-05 叶长青 The reinforced construction method of concrete floor
CN108677682A (en) * 2018-08-09 2018-10-19 广西大学 Novel Deck Arch Bridges
CN110700071B (en) * 2019-11-16 2024-06-04 福州大学 Prefabricated assembled UHPC plate type arch bridge and construction method thereof

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6198864A (en) * 1984-10-19 1986-05-17 岡部株式会社 Mold frame apparatus for arch concrete
JPS6344077A (en) * 1986-08-08 1988-02-25 日本サミコン株式会社 Method of placing concrete of arch type structure
JP3191569B2 (en) * 1993-07-28 2001-07-23 住友金属工業株式会社 Composite slab, method of construction, and joint of composite slab
JP3030695B2 (en) * 1997-10-01 2000-04-10 亜州夫 米倉 Pipe arch bridge of three-dimensional restraint concrete structural member
JP2000087556A (en) * 1998-09-14 2000-03-28 Ohbayashi Corp Placing method for floatable concrete body
JP2001020219A (en) * 1999-07-12 2001-01-23 Nippon Steel Corp Arch bridge
JP3361789B2 (en) * 2000-02-25 2003-01-07 川崎重工業株式会社 Steel plate dowel and concrete filled steel pipe with corrugated stopper
JP2002201609A (en) * 2000-12-28 2002-07-19 Ps Corp Construction method for concrete arch bridge

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452604A (en) * 2014-12-03 2015-03-25 中铁大桥局武汉桥梁特种技术有限公司 Method for reinforcing arch rib segment in arch bridge of steel structure
CN106149574A (en) * 2016-08-08 2016-11-23 江苏聚业交通科学研究有限公司 The ruggedized construction of a kind of rigid framed arch bridge and method
CN106149574B (en) * 2016-08-08 2018-06-19 南京工大桥隧与轨道交通研究院有限公司 The ruggedized construction and method of a kind of rigid framed arch bridge

Also Published As

Publication number Publication date
JP2003193420A (en) 2003-07-09

Similar Documents

Publication Publication Date Title
Sonebi et al. Hardened SCC and its bond with reinforcement
Gaimster et al. Self-compacting concrete
JP3946517B2 (en) Seismic reinforcement method for existing steel arch bridge
JP5969426B2 (en) Lightweight filled mortar composition
JP5741113B2 (en) Construction method for housing foundation structure and housing foundation structure constructed using the same
JPH0660046B2 (en) Heavy grout mortar and filling method using it
JP6757947B2 (en) Seismic reinforcement method
JP4084390B2 (en) Mortar, cured mortar and bridge
KR101314799B1 (en) Management Method of Ultra High Strength Concrete for Maximizing Strength Properties
CN101462862A (en) Steel pipe core high dropping self-compaction concrete and use thereof
JP2997893B2 (en) Highly-fillable concrete material, reinforced concrete structure and steel-concrete composite structure using the concrete material
JP2652835B2 (en) Casting method of high fluidity concrete
Khayat et al. Structural response of self-consolidating concrete columns
JP3197225B2 (en) Concrete construction method
JPS5818342B2 (en) Poor mix concrete for pumping
JP3285789B2 (en) Concrete construction method
JP5664395B2 (en) Construction method for housing foundation structure and housing foundation structure constructed using the same
JP5419115B1 (en) Injection material
JP2000327395A (en) Lightweight highly-flowable concrete
JP2003192421A (en) Stain hardening type cement based composite material having self-compacting property and low shrinkability
JP2003321948A (en) Reinforcing and repairing method for existing steel tower made of hollow steel pipes
CN118005346A (en) Bridge expansion joint anchoring area concrete and preparation method thereof
JP6967438B2 (en) Lightweight cavity filling material and cavity filling method using it
JPH0217503B2 (en)
Jaafar et al. Cementitious grout for preplaced aggregate concrete: A review

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040623

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040709

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20040709

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060628

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060704

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060901

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060926

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061120

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070410

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070411

R150 Certificate of patent or registration of utility model

Ref document number: 3946517

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130420

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130420

Year of fee payment: 6

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130420

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160420

Year of fee payment: 9

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term