JP3883686B2 - Diagonal pile drilling method using pressurized water and pressurized water supply equipment - Google Patents
Diagonal pile drilling method using pressurized water and pressurized water supply equipment Download PDFInfo
- Publication number
- JP3883686B2 JP3883686B2 JP03274498A JP3274498A JP3883686B2 JP 3883686 B2 JP3883686 B2 JP 3883686B2 JP 03274498 A JP03274498 A JP 03274498A JP 3274498 A JP3274498 A JP 3274498A JP 3883686 B2 JP3883686 B2 JP 3883686B2
- Authority
- JP
- Japan
- Prior art keywords
- water
- pressure
- pressurized water
- foundation
- bit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Foundations (AREA)
- Earth Drilling (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、山岳地等に建設される送電線路の鉄塔基礎や道路橋等基礎構造物に係り、特に深礎基礎や円形底板逆T型基礎における拡底基礎の斜杭削孔工法および加圧水供給装置に関する。
【0002】
【従来の技術】
従来、主として山岳地に建設される送電線路の鉄塔は、上部構造物の特性、地盤の性状、地形の状況、および施工性等を総合的に考慮して基礎形式を選定されるが、大型の場合は深礎基礎を、中型では円形底板逆T型基礎を選定してその上に構造物を設置する場合が多い。
【0003】
そして円形底板には鉄塔から受ける圧縮力・引揚力の基礎荷重に対し、底板部を拡底し、建設費のコストダウンを図った拡底基礎が多く採用されている。
【0004】
この場合、拡底部の掘削はずい道掘削となるため支保工が必要となるが、一般には斜杭鋼棒の埋設支保工での施工が殆どである。
【0005】
すなわち上記の拡底基礎の掘削は、通常拡底部の上面高さから地山に至るように傾斜させた土留めの支保工となる多数の斜杭鋼棒を放射状に埋設するものである。
【0006】
【発明が解決しようとする課題】
しかしながら上述した斜杭鋼棒埋設支保工を削岩機+ブレーカーの組み合わせにより施工する場合、地質がシルト岩で湧き水があると、削孔時に削岩機のピット空気孔に岩石粉や粘土等のクリ粉が水を含んで目詰まりを生じるためその都度削孔作業が停止してしまう不具合を生じていた。
【0007】
このような場合、目詰まりを除去するのに約30〜60分もの時間がかかり、この間は削孔作業を中断しなければならず、しかもこのような状況が1脚当たり数回〜10数回繰りかえされ、作業時間の大きなロスとなっていた。
【0008】
また削孔作業の際には粉塵が多量に発生するため視界が悪くなるとともに衛生上問題があり、かつ作業効率低下の原因ともなっていた。
【0009】
【課題を解決するための手段】
本発明は、上記のような削孔工事における不具合を解消し、空気孔の目詰まりがなく、高効率に斜杭削孔作業が行えるようにした斜杭削孔工法および加圧水供給装置を提供することを課題としたもので、その解決手段としては加圧水を利用して削孔作業中ビット空気孔の目詰まりとなるクリ粉の付着を防止するようにしたことにある。
【0010】
すなわち本発明は、送電線の鉄塔等を設置する基礎体の深礎基礎または円形底板逆T型基礎の拡底部支保工として、該拡底部の傾斜面に沿って放射状に斜杭鋼棒を埋設させるための斜杭孔施工を、エア圧によりビットを進退駆動して地盤を削孔する削岩において、削岩機のビット先端から圧力水を噴射しつつ削孔することを特徴とする。
【0011】
また、掘削時にビット先端から噴射させる圧力水の供給系は、水を収容する水溜めとこの水溜めの水を加圧する水加圧器を有し、この水溜めの上方部にビット駆動用コンプレッサから圧縮エアを導入する圧力エアホースを圧力調整バルブを介して接続し、該コンプレッサからの圧縮エアにより圧力調整された水を圧力水噴出口へ導くようにしたことを特徴とする。
【0012】
【発明の実施の形態】
以下、本発明を図面に示す実施の形態を参照して説明する。
図1は本発明にかかる斜杭削孔工法の一例を示すもので、一般に山岳地等に建設される送電線路の鉄塔等の基礎は、深礎基礎や円形底板逆T型基礎1(図5参照)上に取付けられるようになっているが、この基礎1のうち地表から適宜深さに埋設された上部が台形状をなす基礎体の拡底部1aは、その上面の周りを地表から基礎体の拡底部1aの上面に至る高さを有して中で作業する作業員を保護するための環状のライナー2により囲まれた状態に置かれており、斜杭孔4は前記基礎体の拡底部1aの周囲に形成された傾斜面1bに沿って頂部から地中に向かうように施工される。
【0013】
この削孔4は作業員が前記ライナー2内で基礎体1の上面に立った状態で削岩機3を用いて行うもので、地上にはコンプレッサ5、水加圧器6、およびドラム缶等の水溜め7等が設置され、コンプレッサ5により圧縮されたエアーは、一方は水加圧器6に、他方は前記削岩機3にそれぞれエアーホース8,9を通じて送られ、また水溜め7の水は水加圧器6にホース10を通じて送られ、ここで加圧されて高圧ホース11を通じて削岩機3に送られるようになっている。なお水溜め7への水は図示しない水源からホース12を通じて供給される。
【0014】
図2は図1の水加圧器6の一部を破断して示すもので、コンプレッサ5により圧縮された加圧エアー(圧力は例えば5〜7kg/cm2 )は調整バルブ15により調圧され、その加圧エア(圧力は例えば2〜3kg/cm2 )は水加圧器6内の水を加圧し、この水加圧器6から押し出された加圧水は前述のように高圧ホース11を通じて削岩機3に達し、削岩機3のピット17に至るようになっている。そして削岩機3ビット17の先端部には圧力水噴出口13が設けられている。
【0015】
図2中、符号14は水残量計、15aは圧力ゲージ、16は水量を加減する調整バルブである。
【0016】
したがって削岩機3による削孔時にビット17の先端の圧力水噴出口13からの圧力水を噴射することにより空気孔の目詰まりの原因となっていたクリ粉等が液状化されるので、ビット17およびロッド18の空気孔の目詰まりが解消される。
【0017】
この場合、水量の調節は水加圧器6の上部に設けられた圧力調整バルブ15により、また水量の調整は削岩機3のハンドル3b近くに設けられている調整バルブ16を調整することにより適正な噴射が行える。
【0018】
図3は図1の斜杭部分の拡大図で、斜杭孔4の施工が完了して鋼棒19が図示しないブレーカーにより打ち込まれた状態を示すものである。
【0019】
ライナー2の詳細は内周壁を裏込めモルタル2aにより上下を凹凸の隣合わせ状態に形成されており、最下部の周囲にはH型鋼等の補強リング20が設置され、この補強リング20には下方に垂下する支持部21aを有し、この支持部21aに鋼棒19の上端側が支持されている。
【0020】
なお基礎体1aの寸法は例えば図3に示すような大きさとなっている。また鋼棒19の大きさは例えば直径32mm,長さが1500mm程度のものである。
【0021】
図4は斜杭が打込まれた状態の平面図を示すもので、前記鋼棒19は基礎体の拡底部1aの中心に対して放射状に多数(図示の例では、1脚当り40本)が埋設されており、これにより基礎体の拡底部1aを安定させている。
【0022】
図5は鉄塔22が上部基礎体1cの上部に設置された状態の一例を示すもので、鉄塔22の脚を支持する基礎体の拡底部1aの下部が円形底板逆T型基礎で形成される。この場合前記ライナー2は取り外されるか、あるいはそのまま地中に埋め込まれることになる。
【0023】
【発明の効果】
本発明は以上説明したように構成したことにより次に示すような効果が得られる。
1)実験結果によれば、削岩機の施工性については従来のエアーブロー方式と比較した場合、本発明による加圧水ブロー方式では作業日数が(脚当たり)従来の1.7日に対して本発明ではビットおよびロッドの空気孔の目詰まりの除去等による中断がないために1.0日と大幅に短縮された。
2)作業性については、空気と共に水を送ることにより空気圧に水圧効果も加わって空気圧のみの状態に比べ、最も相性の悪かった泥岩地盤における粘土層においても従来工法で頻繁に生じていたビットおよびロッドの空気孔の目詰まりが解消されるので除去作業が不要となり、これにより円滑な連続作業が可能となる。
3)安全性については、水を送ることにより多量に発生していた粉塵が全く発生しないので安全、衛生面が向上し、その結果作業性の向上にもつながる。
4)作業・経済性については、岩とビットとの間に生ずる摩擦熱が水の冷却効果により抑えられ、ビットを冷やしながらの削孔作業ができるから、ビットへの負担が軽減され、耐久性・作業効率の大幅な向上と劣化速度を遅らせることができて経済的にも向上する。
【図面の簡単な説明】
【図1】本発明にかかる斜杭削孔工法の一例を示す説明図。
【図2】図1の水加圧器の一部を破断して示す構造図。
【図3】図1の斜杭部分の拡大図。
【図4】図3の平面図。
【図5】図3の円形底板逆T型基礎に送電線路の鉄塔脚が取付けられた状態を示す外観図。
【符号の説明】
1 鉄塔等の拡底基礎
1a 基礎体の拡底部
1b 傾斜面
3 削岩機
3b ハンドル
4 斜杭孔
5 コンプレッサ
6 水加圧器
8,9 エアーホース
11 高圧ホース
13 圧力水噴出口
15 空気の圧力調整バルブ
15a 圧力ゲージ
16 水量調整バルブ
17 ビット
18 ロッド
19 鋼棒
22 鉄塔[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a foundation structure such as a steel tower foundation or a road bridge of a transmission line constructed in a mountainous area or the like, and in particular, a slant pile foundation slant pile drilling method and a pressurized water supply device for a deep foundation or a circular bottom plate inverted T-type foundation. About.
[0002]
[Prior art]
Conventionally, transmission towers constructed mainly in mountainous areas have been selected based on comprehensive consideration of the characteristics of the superstructure, ground properties, topographic conditions, workability, etc. In many cases, a deep foundation is selected, and in the middle size, a circular bottom plate inverted T-type foundation is selected and a structure is installed thereon.
[0003]
And for the round bottom plate, many bottom-up foundations are used to reduce the construction cost by expanding the bottom plate part against the basic load of compressive force / lifting force received from the steel tower.
[0004]
In this case, a support work is necessary because the excavation of the bottom of the excavation is a drainage excavation, but in general, the work is mainly carried out with a support work for buried oblique pile steel bars.
[0005]
That is, in the excavation of the above-mentioned expanded foundation, a large number of slant pile steel rods that serve as supporters for earth retaining which are inclined so as to reach the natural ground from the height of the upper surface of the expanded bottom portion are embedded in a radial pattern.
[0006]
[Problems to be solved by the invention]
However, when constructing the above-mentioned support for buried pile steel rods using a combination of rock drill and breaker, if the geology is siltstone and there is spring water, rock powder, clay, etc. will be placed in the pit air hole of the rock drill during drilling. Since the chestnut powder contained water and clogged, there was a problem that the drilling operation was stopped each time.
[0007]
In such a case, it takes about 30 to 60 minutes to remove the clogging, and during this time, the drilling operation must be interrupted, and such a situation occurs several times to several times per leg. Repeatedly, it was a big loss of work time.
[0008]
Further, during the drilling operation, a large amount of dust is generated, resulting in poor visibility and sanitary problems, and causes a reduction in work efficiency.
[0009]
[Means for Solving the Problems]
The present invention provides a slant pile drilling method and a pressurized water supply device that eliminates the above-described problems in the hole drilling work, eliminates clogging of air holes, and enables slant pile drilling work to be performed with high efficiency. The solution to this problem is to prevent the adhesion of chestnut powder that clogs the bit air holes during the drilling operation using pressurized water.
[0010]
That is, the present invention embeds oblique pile steel rods radially along the inclined surface of the bottom as a deep foundation of a foundation for installing a steel tower of a transmission line or a bottom expansion support of a circular bottom plate inverted T type foundation. In the rock drilling for drilling the ground by drilling the bit forward and backward by air pressure, drilling the pressure pile from the tip of the rock drilling machine.
[0011]
The pressure water supply system to be injected from the tip of the bit during excavation has a water reservoir for storing water and a water pressurizer for pressurizing the water in the water reservoir. A compressor for driving the bit is provided above the water reservoir. A pressure air hose for introducing compressed air is connected via a pressure adjusting valve, and water whose pressure is adjusted by compressed air from the compressor is guided to a pressure water jet port.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
The present invention will be described below with reference to embodiments shown in the drawings.
FIG. 1 shows an example of a slant pile drilling method according to the present invention. Generally, a foundation such as a steel tower of a transmission line constructed in a mountainous area is a deep foundation or a circular bottom plate inverted T-type foundation 1 (FIG. 5). Reference) Although the
[0013]
This drilling hole 4 is made by using a
[0014]
FIG. 2 is a partially broken view of the
[0015]
In FIG. 2,
[0016]
Therefore, when drilling with the
[0017]
In this case, the water amount is adjusted by adjusting the
[0018]
FIG. 3 is an enlarged view of the oblique pile portion of FIG. 1, and shows a state where the construction of the oblique pile hole 4 is completed and the
[0019]
The details of the
[0020]
The dimensions of the
[0021]
FIG. 4 is a plan view showing a state in which slant piles are driven, and a large number of the steel bars 19 are radially formed with respect to the center of the bottom expanded
[0022]
FIG. 5 shows an example of a state in which the steel tower 22 is installed on the upper part of the
[0023]
【The invention's effect】
Since the present invention is configured as described above, the following effects can be obtained.
1) According to the experimental results, when compared to the conventional air blow method, the workability of the rock drilling machine is less than the conventional 1.7 days (per leg) in the pressurized water blow method according to the present invention. In the invention, since there was no interruption due to removal of clogging of the air holes of the bit and rod, the time was significantly reduced to 1.0 days.
2) Regarding workability, the bit that was frequently generated in the conventional method even in the clay layer in the mudstone ground, which was the least compatible, compared to the state of only air pressure by adding water pressure effect by sending water together with air, Since the clogging of the air holes of the rod is eliminated, the removal work is not necessary, thereby enabling a smooth continuous work.
3) As for safety, since dust generated in large quantities by sending water is not generated at all, safety and hygiene are improved. As a result, workability is improved.
4) With regard to work and economy, the frictional heat generated between the rock and the bit is suppressed by the cooling effect of the water, and drilling work can be performed while cooling the bit, reducing the burden on the bit and durability. -Significantly improve work efficiency and slow down the deterioration rate, so it improves economically.
[Brief description of the drawings]
FIG. 1 is an explanatory view showing an example of a diagonal pile drilling method according to the present invention.
FIG. 2 is a structural diagram showing a part of the water pressurizer of FIG.
FIG. 3 is an enlarged view of the diagonal pile portion of FIG. 1;
4 is a plan view of FIG. 3. FIG.
5 is an external view showing a state where a transmission tower tower is attached to the circular bottom plate inverted T-type foundation of FIG. 3; FIG.
[Explanation of symbols]
DESCRIPTION OF
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP03274498A JP3883686B2 (en) | 1998-02-16 | 1998-02-16 | Diagonal pile drilling method using pressurized water and pressurized water supply equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP03274498A JP3883686B2 (en) | 1998-02-16 | 1998-02-16 | Diagonal pile drilling method using pressurized water and pressurized water supply equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11229739A JPH11229739A (en) | 1999-08-24 |
JP3883686B2 true JP3883686B2 (en) | 2007-02-21 |
Family
ID=12367360
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP03274498A Expired - Lifetime JP3883686B2 (en) | 1998-02-16 | 1998-02-16 | Diagonal pile drilling method using pressurized water and pressurized water supply equipment |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3883686B2 (en) |
-
1998
- 1998-02-16 JP JP03274498A patent/JP3883686B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH11229739A (en) | 1999-08-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101669249B1 (en) | Slime disposal device and method of construction for large caliber Basic file construction | |
JP4282022B2 (en) | Drain pipe burial method and structures, etc. to prevent tilting, sinking or floating | |
US20060275087A1 (en) | Soil extraction/grouting device | |
US20090269146A1 (en) | Method for Construction of Piles and Caissons and Soil Improvement by Using Rubber Hoses | |
JP3886261B2 (en) | Slope stabilization method and slope independent pressure receiving device | |
JP3233613B2 (en) | Continuous lap drilling method using leaderless auger machine and apparatus used for the method | |
JP3883686B2 (en) | Diagonal pile drilling method using pressurized water and pressurized water supply equipment | |
JP2863487B2 (en) | Pile pull-out method and device | |
CN113266019B (en) | Construction method of foundation pit steel pipe support system | |
KR20060079446A (en) | Apparatus for reducing pull-out resistance of pile and pull-out method thereof | |
JP5472878B2 (en) | Labor-saving track lift-up device and lift-up method | |
JP2005213879A (en) | Drain pipe construction method and ground drilling unit | |
JP5308895B2 (en) | Pile hole wall protection method | |
CN110985017B (en) | Construction method for shield tunneling of rainwater box culvert under expansive soil stratum | |
JP3169911B2 (en) | Heavy weight type steel pipe digging and driving method using the same | |
JP4504752B2 (en) | Construction method and apparatus for tubular precast concrete member | |
JPH0676689B2 (en) | Method and device for removing existing piles | |
JP3973401B2 (en) | Ground compaction method | |
JPH01207525A (en) | Digging of pile hole to remove existing pile and dig pile hole for new pile and device thereof | |
CN218861534U (en) | Reinforcing cage transfer centering device for construction of ultra-long cast-in-situ bored pile | |
JPH11229740A (en) | Subsoil excavation method and device | |
JP2958426B2 (en) | Differential settlement correction method | |
JPH073791A (en) | Method and device for extracting existing pile | |
RU41312U1 (en) | MOBILE TECHNICAL COMPLEX FOR THE FORMATION OF SUPPORTS IN SOILS | |
JPH07507362A (en) | Method for constructing concrete structures from ground level on coarse material and equipment for carrying out said method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040917 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060609 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060613 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060721 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20061020 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20061115 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091124 Year of fee payment: 3 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091124 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091124 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101124 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111124 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111124 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121124 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121124 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131124 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |