JP3872739B2 - Concrete placement method - Google Patents

Concrete placement method Download PDF

Info

Publication number
JP3872739B2
JP3872739B2 JP2002263156A JP2002263156A JP3872739B2 JP 3872739 B2 JP3872739 B2 JP 3872739B2 JP 2002263156 A JP2002263156 A JP 2002263156A JP 2002263156 A JP2002263156 A JP 2002263156A JP 3872739 B2 JP3872739 B2 JP 3872739B2
Authority
JP
Japan
Prior art keywords
pipe
concrete
placement
branch
path
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002263156A
Other languages
Japanese (ja)
Other versions
JP2004100262A (en
Inventor
久人 田中
郁郎 甚内
篤彦 延田
正広 真鍋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Toray Engineering Co Ltd
Original Assignee
Kajima Corp
Toyo Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Toyo Construction Co Ltd filed Critical Kajima Corp
Priority to JP2002263156A priority Critical patent/JP3872739B2/en
Publication of JP2004100262A publication Critical patent/JP2004100262A/en
Application granted granted Critical
Publication of JP3872739B2 publication Critical patent/JP3872739B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、鉛直方向に延在する打設予定領域にコンクリートを打設するコンクリート打設方法に関する。
【0002】
【従来の技術】
発電所等の施工現場において、立坑の内壁面等、鉛直方向に延在する打設予定領域にコンクリートを打設する方法としては、コンクリートバケット・シュート打設、スネークシュート打設、コンクリート落下装置による打設、コンクリートポンプ車高圧打設(吹上げ)等が従来一般的である。これらの方法のうちいずれを実施するかは、立坑の深さやコンクリートの打設量に応じて適宜決定される。
【0003】
なお、施工現場の任意の地点にコンクリートを運搬・打設する技術として、特許文献1に記載のコンクリート打設システムが提案されている。
【0004】
【特許文献1】
特開平11−269852号公報
【0005】
【発明が解決しようとする課題】
しかしながら、コンクリートの打設量が多い場合には、コンクリートバケット・シュート打設によれば、コンクリートバケットの昇降に長時間を要するため施工効率が悪化する。スネークシュート打設よれば、スネークシュートの耐久性に不安がある。
【0006】
また、コンクリート落下装置による打設にあっては、クレーンによりコンクリート落下装置を吊り下げた状態で打設を行うため、作業員の安全性を確保しながらの作業となり施工効率が悪化するおそれがある。さらに、コンクリートポンプ車高圧打設にあっては、下方からの打設となるため、施工現場の立地上実施できない場合が多い。
【0007】
そこで、本発明は、このような事情に鑑みてなされたものであり、高低差が100mを超えるような大規模な打設予定領域に対して大量のコンクリートを打設する場合に好適なコンクリート打設方法を提供することを目的とする。
【0008】
【課題を解決するための手段】
上記目的を達成するために、本発明に係るコンクリート打設方法は、鉛直方向に延在する打設予定領域にコンクリートを打設するコンクリート打設方法であって、打設予定領域に沿って当該打設予定領域内にコンクリートの輸送路を複数系列形成する輸送路形成工程と、輸送路における第1の位置に第1の分岐路を形成する第1の分岐路形成工程と、輸送路を上方から輸送されてきたコンクリートを第1の分岐路を通じて打設予定領域に打設する第1の打設工程と、第1の打設工程の後、輸送路における第1の位置より上方の第2の位置に第2の分岐路を形成する第2の分岐路形成工程と、輸送路を上方から輸送されてきたコンクリートを第2の分岐路を通じて打設予定領域に打設する第2の打設工程とを備えることを特徴とする。
【0009】
このコンクリート打設方法によれば、鉛直方向に延在する打設予定領域に対して、第1の分岐路を通じてコンクリートを打設した後、第1の分岐路より上方の第2の分岐路を通じてコンクリートを打設するため、打設予定領域における下方の領域から順次コンクリートを打設していくことができる。したがって、打設予定領域が例えば100mを超えるような高低差を有する大規模なものであり、大量のコンクリートを打設する必要がある場合にも、打設予定領域の全範囲にわたってコンクリートを確実且つ効率的に打設することができ、施工効率の向上を図れる。また、各分岐路を通じて大量のコンクリートを連続打設することが可能であるため、打設したコンクリートに分離が生じるのを防止することができる。
【0010】
本発明に係るコンクリート打設方法においては、輸送路は、複数の管体を接続することにより形成され、第1の分岐路形成工程は、管体のうち第1の位置に配置された管体を、分岐管が形成された第1の分岐管付管体に交換する工程であり、第2の分岐路形成工程は、管体のうち第2の位置に配置された管体を、分岐管が形成された第2の分岐管付管体に交換する工程であることが好ましい。このように、複数の管体を接続することにより輸送路を形成すれば、様々な打設予定領域に幅広く対応することが可能になる。また、第1及び第2の位置に配置された管体を分岐管付管体に交換することによって、上述した第1及び第2の分岐路を容易に形成することができる。
【0011】
本発明に係るコンクリート打設方法においては、輸送路は、管体のうち第1の位置に配置された管体の上端に接続された管体と下端に接続された管体との間の距離を保持する第1の保持手段と、管体のうち第2の位置に配置された管体の上端に接続された管体と下端に接続された管体との間の距離を保持する第2の保持手段とを有することが好ましい。第1の位置に配置された管体に対して、その上側に接続された管体の重量等による荷重がかかっても、第1の位置に配置された管体の上端に接続された管体と下端に接続された管体との間の距離は、第1の保持手段により確実に保持される(第2の位置に配置された管体についても同様)。したがって、第1及び第2の位置において、各管体及び各分岐管付管体の輸送路に対する着脱を安全且つ容易に行うことできる。
【0012】
【発明の実施の形態】
以下、本発明に係るコンクリート打設方法の好適な実施形態について、図面を参照して詳細に説明する。なお、図面の説明において同一又は相当部分には同一符号を付し、重複する説明を省略する。
【0013】
図1は、水力発電所の施工現場を示す側面図である。同図において、立坑1内に、複数の水圧鉄管2を接続してなる水圧鉄管ユニットを構築するためには、立坑1の内壁面と各水圧鉄管2との間隙(打設予定領域)Sにコンクリートを詰込む必要がある。そのために、以下のようにして間隙Sへのコンクリートの打設を行う。
【0014】
最初に、コンクリートの輸送路4を立坑1の内壁面に沿って形成する。この輸送路4の上端は、所定の配管を介して受ホッパ5に接続され、この受ホッパ5には、上方のコンクリートポンプ車6から輸送路7を介してコンクリートが圧送される。これにより、輸送路4においては、上方から下方に向かってコンクリートが圧送される。なお、輸送路7は、下端部近傍において上方に向けて屈曲された屈曲部7aを有し、この屈曲部7aと受ホッパ5との間には油圧式のシャッタバルブ7bが設置されている。このような屈曲部7aを設けることによって、コンクリート打設時の衝撃が低減され、さらには、打設中断時においても常にコンクリートが配管内に残ることになるため、打設再開時には分離しない状態でコンクリートが圧送される。また、シャッタバルブ7bは、コンクリートポンプ車6の圧送開始・停止と連動して開閉するため、圧送停止時にコンクリートが配管内を急激に送られて真空状態になるようなことが防止される。
【0015】
輸送路4は、多数の圧送管ユニット8と打設用圧送管ユニット9(輸送路4における第1の位置及びそれより上方の第2の位置に配置)とを接続し、各ユニット8,9を立坑1の内壁面に固定することによって形成される。このように、輸送路4を立坑1の内壁面に固定することによって、安全且つ確実なコンクリートの打設が可能になる。第1及び第2の位置は、コンクリートの打設を行う位置として予め設定されるが、立坑1の規模等によっては、さらに、第3,第4,…の位置を設定し、各位置に打設用圧送管ユニット9を介在させてもよい。
【0016】
図2に示すように、圧送管ユニット8は、鋼管からなる2本の圧送管(管体)10を並設することにより構成され(図2は側面図であるため、圧送管10が1本しか現れていない)、ケミカルアンカー11により立坑1の内壁面に固定される。各圧送管10の両端部には、他の圧送管に接続するための高圧用のカラー12が取り付けられており、圧送管10の一側方には、各種作業を行うためのタラップ13が設けられている。
【0017】
また、図3に示すように、打設用圧送管ユニット9は、鋼材により形成された矩形状の保持フレーム14を有し、ケミカルアンカー11により立坑1の内壁面に固定される。保持フレーム14において、上フレーム部14aには、鋼管からなる2本の圧送管(管体)15aが平行に固定され、下フレーム部14bには、鋼管からなる2本の圧送管(管体)15bが平行に固定されている。各圧送管15a,15bの両端部にはカラー12が取り付けられており、保持フレーム14の一側方にはタラップ13が設けられている。
【0018】
さらに、圧送管15aと圧送管15bとの間には、鋼管からなる交換用圧送管16が配置され、その両端部のカラー12を介して各圧送管15a,15bに接続されている。また、圧送管15aと圧送管15bとの間には、交換用圧送管16に替えて、鋼管からなる分岐管付圧送管18を接続することができる。この分岐管付圧送管18は、図4に示すように、カラー12を介して各圧送管15a,15bに接続される本管18aと、この本管18aから斜め下方に分岐する分岐管18bとを有して構成されている。
【0019】
上述のように圧送管ユニット8と打設用圧送管ユニット9とにより立坑1内に輸送路4を形成した後、図5に示すように、第1の位置に配置された打設用圧送管ユニット9の下端近傍まで水圧鉄管2を所定段数建て込む。続いて、図6に示すように、最上段の水圧鉄管2の上端開口部を天蓋21で覆い、この天蓋21上に作業用足場22を設置する。そして、打設用圧送管ユニット9の一方の交換用圧送管(第1の位置に配置された管体)16を取り外し、クレーンにより吊り込んだ分岐管付圧送管(第1の分岐管付管体)18を接続する。
【0020】
この打設用圧送管ユニット9においては、その上側に接続された圧送管ユニット8の重量等による荷重がかかっても、圧送管15a,15b間の距離が保持フレーム(第1の保持手段)14により確実に保持される。したがって、交換用圧送管16と分岐管付圧送管18との交換に際しては、各圧送管16,18の着脱を安全且つ容易に行うことできる。
【0021】
続いて、図7に示すように、分岐管付圧送管18の分岐管(第1の分岐路)18b先端にコンクリートシュート23を接続する。そして、コンクリートポンプ車6から所定の輸送路を介して受けホッパ5にコンクリートを投入し、輸送路4に対して上方から下方にコンクリートを圧送する。なお、受けホッパ5を用いずに、コンクリートポンプ車6から輸送路4にコンクリートを直接圧送するような構成としてもよい。
【0022】
輸送路4へのコンクリートの圧送が開始されると、分岐管18b及びコンクリートシュート23を通じて、立坑1の内壁面と水圧鉄管2との間隙Sにコンクリートが供給される。そして、分岐管18b及びコンクリートシュート23を回転させながら水圧鉄管2の周囲にコンクリートを打設する。最上段の水圧鉄管2の上端近傍までコンクリートを打設した後、上部から少量の水を流して第1の位置上方の輸送路4の洗浄を行う。そして、分岐管付圧送管18を取り外してこれを洗浄し、さらに、先に取り外した交換用圧送管16を接続する。
【0023】
次に、第2の位置に配置された打設用圧送管ユニット9の下端近傍まで、水圧鉄管2を所定段数建て込み、この打設用圧送管ユニット9の一方の交換用圧送管(第2の位置に配置された管体)16を取り外して分岐管付圧送管(第2の分岐管付管体)18を接続する。この打設用圧送管ユニット9においても、圧送管15a,15b間の距離が保持フレーム(第2の保持手段)14により確実に保持されるため、各圧送管16,18の着脱を安全且つ容易に行うことできる。
【0024】
続いて、分岐管付圧送管18の分岐管18b先端にコンクリートシュート23を接続し、その後、輸送路4に対して上方から下方にコンクリートを圧送する。以下、上述の第1の位置と同様にして、分岐管(第2の分岐路)18b及びコンクリートシュート23を通じて、立坑1の内壁面と水圧鉄管2との間隙Sにコンクリートを打設する。
【0025】
さらに、第3,第4,…の位置に打設用圧送管ユニット9を介在させた場合は、第3,第4,…の位置においても同様に、水圧鉄管2を所定段数建て込んだ後、交換用圧送管16を分岐管付圧送管18に交換し、分岐管付圧送管18の分岐管18bを通じてコンクリートの打設を行う。
【0026】
以上説明したコンクリート打設方法によれば、立坑1の内壁面と水圧鉄管2との間隙Sに対して、第1の位置においてコンクリートの打設を行った後、第1の位置より上方の第2の位置においてコンクリートの打設を行うため、間隙Sにおける下方の領域から順次コンクリートを打設していくことができる。したがって、立坑1が100mを超えるような深さを有する大規模なものであり、間隙Sに大量のコンクリートを打設する必要がある場合にも、間隙Sの全範囲にわたってコンクリートを確実且つ効率的に打設することができ、施工効率の向上を図れる。また、各位置において大量のコンクリートを連続打設することが可能であるため、打設したコンクリートに分離が生じるのを防止することができる。
【0027】
また、圧送管ユニット8と打設用圧送管ユニット9とによって輸送路4を形成するため、様々な規模の立坑1に幅広く対応することが可能になる。そして、ユニット化によって輸送路4の剛性が非常に高くなり、コンクリートの圧送に伴う荷重(衝撃)に対しても高い安全性が確保される。また、第1及び第2の位置に配置された打設用圧送管ユニット9において交換用圧送管16を分岐管付圧送管18に交換することによって、輸送路4から分岐する分岐路を各位置に容易に形成することができる。
【0028】
さらに、輸送路4は、圧送管10,15a,15b及び交換用圧送管16からなる配管を2系列有しているため、上述のように一系列の配管のみをコンクリートの圧送に使用して、他系列の配管を排水用配管として使用することができる。そして、2系列の配管を順次切り替えながらコンクリートの圧送に使用することによって、コンクリートの大量打設に伴う各系列の配管の摩耗を抑制することができ、輸送路4の長寿命化を図れる。
【0029】
なお、本発明は上記実施形態に限定されない。例えば、本発明に係る輸送路は、2系列の配管を有するものに限らず、1系列の配管を有するものであってもよいし、3系列以上の配管を有するものであってもよい。また、上記実施形態では、打設予定領域である間隙S内に輸送路4を直接形成したが、本発明に係る輸送路は、打設予定領域に沿って形成すれば、打設予定領域の外部に形成してもよい。
【0030】
また、上記実施形態では、交換用圧送管16を分岐管付圧送管18に交換することによって分岐路を形成したが、例えば、輸送路を形成する圧送管に分岐管を直接接続することによって分岐路を形成することもできる。さらに、本発明は、水圧鉄管等、立坑内の構造物の構築に限らず、鉛直方向に高低差のある構造物の構築に適用可能である。
【0031】
【発明の効果】
本発明に係るコンクリート打設方法は、高低差が100mを超えるような大規模な打設予定領域に対して大量のコンクリートを打設する場合に好適に実施することができる。
【図面の簡単な説明】
【図1】本発明に係るコンクリート打設方法の一実施形態が実施される水力発電所の施工現場を示す側面図である。
【図2】図1に示す輸送路を形成する圧送管ユニットの側面図である。
【図3】図1に示す輸送路を形成する打設用圧送管ユニットの正面図である。
【図4】図3に示す打設用圧送管ユニットに取り付けられる分岐管付圧送管を示す正面図である。
【図5】図1に示す立坑における水圧鉄管の建て込みの様子を示す概念図である。
【図6】図1に示す立坑における交換用圧送管と分岐管付圧送管との交換の様子を示す概念図である。
【図7】図1に示す立坑におけるコンクリートの打設の様子を示す概念図である。
【符号の説明】
1…立坑、2…水圧鉄管、4…輸送路、10,15a,15b…圧送管(管体)、14…保持フレーム(第1の保持手段、第2の保持手段)、16…交換用圧送管(第1の位置に配置された管体、第2の位置に配置された管体)、18…分岐管付圧送管(第1の分岐管付管体、第2の分岐管付管体)、18b…分岐管、S…間隙。
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a concrete placement method for placing concrete in a placement plan area extending in a vertical direction.
[0002]
[Prior art]
At the construction site such as a power plant, concrete can be placed in a vertical placement area such as the inner wall of a vertical shaft, using concrete bucket / chute placement, snake chute placement, or a concrete dropping device. Conventionally, driving, concrete pump car high-pressure driving (blowing), and the like are common. Which of these methods is to be performed is appropriately determined according to the depth of the shaft and the amount of concrete to be placed.
[0003]
In addition, the concrete placement system of patent document 1 is proposed as a technique of conveying and placing concrete in the arbitrary points of a construction site.
[0004]
[Patent Document 1]
Japanese Patent Laid-Open No. 11-269852
[Problems to be solved by the invention]
However, when a large amount of concrete is placed, according to the concrete bucket / chute placement, it takes a long time to raise and lower the concrete bucket, so the construction efficiency deteriorates. According to the snake shot placement, there is concern about the durability of the snake shot.
[0006]
In addition, in the placement by the concrete dropping device, since the placement is performed with the concrete dropping device suspended by a crane, the work is performed while ensuring the safety of the worker, and the construction efficiency may be deteriorated. . Furthermore, in the high-pressure placement of a concrete pump car, since it is placed from below, there are many cases where it cannot be carried out due to the location of the construction site.
[0007]
Accordingly, the present invention has been made in view of such circumstances, and is suitable for placing a large amount of concrete in a large-scale placement area where the height difference exceeds 100 m. The purpose is to provide an installation method.
[0008]
[Means for Solving the Problems]
To achieve the above object, concrete設方method according to the present invention is a concrete設方method for pouring the concrete pouring scheduled region extending in the vertical direction, along the pouring region where the A transportation route forming step for forming a plurality of concrete transportation routes in the planned placement area, a first branching route forming step for forming a first branching route at a first position in the transportation route, and a transportation route upward A first placement step of placing the concrete transported from the first planned route into the planned placement region, and a second position above the first position in the transportation route after the first placement step. A second branch path forming step of forming a second branch path at the position of the second, and a second placement of placing the concrete transported from the upper side of the transport path into the placement planned area through the second branch path And a process.
[0009]
According to this concrete placement method, after placing concrete through the first branch path in the planned placement area extending in the vertical direction, through the second branch path above the first branch path. In order to place concrete, it is possible to place concrete sequentially from the lower region in the planned placement region. Therefore, even when the placement area is large, for example, having a height difference exceeding 100 m, and it is necessary to place a large amount of concrete, the concrete can be reliably and completely covered over the entire area of the placement area. It can be placed efficiently and construction efficiency can be improved. Further, since it is possible to continuously cast a large amount of concrete through each branch path, it is possible to prevent separation of the placed concrete.
[0010]
In the concrete placing method according to the present invention, the transportation path is formed by connecting a plurality of pipe bodies, and the first branch path forming step is a pipe body arranged at the first position among the pipe bodies. Is replaced with the first branch pipe-attached tube body in which the branch pipe is formed, and the second branch path forming step replaces the pipe body arranged at the second position in the pipe body with the branch pipe. It is preferable that it is the process of replacing | exchanging with the 2nd pipe | tube body with a branch pipe formed. In this way, if a transportation path is formed by connecting a plurality of pipes, it is possible to deal widely with various placement areas. Moreover, the 1st and 2nd branch path mentioned above can be easily formed by replacing | exchanging the pipe body arrange | positioned in the 1st and 2nd position to a pipe body with a branch pipe.
[0011]
In the concrete placing method according to the present invention, the transport path is a distance between the pipe connected to the upper end of the pipe arranged at the first position and the pipe connected to the lower end of the pipe. A first holding means for holding the second and a second pipe for holding a distance between the pipe connected to the upper end of the pipe arranged at the second position and the pipe connected to the lower end of the pipe. It is preferable to have the holding means. A tube connected to the upper end of the tube disposed at the first position even when a load due to the weight or the like of the tube connected to the upper side is applied to the tube disposed at the first position And the tube connected to the lower end are reliably held by the first holding means (the same applies to the tube arranged at the second position). Therefore, in the 1st and 2nd position, attachment / detachment with respect to the transport path of each pipe body and each pipe body with a branch pipe can be performed safely and easily.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, a preferred embodiment of a concrete placing method according to the present invention will be described in detail with reference to the drawings. In the description of the drawings, the same or corresponding parts are denoted by the same reference numerals, and redundant description is omitted.
[0013]
FIG. 1 is a side view showing a construction site of a hydroelectric power plant. In the figure, in order to construct a hydraulic iron pipe unit in which a plurality of hydraulic iron pipes 2 are connected in the shaft 1, a gap (planned placement area) S between the inner wall surface of the shaft 1 and each hydraulic iron pipe 2 is formed. It is necessary to pack concrete. For this purpose, concrete is placed in the gap S as follows.
[0014]
First, the concrete transport path 4 is formed along the inner wall surface of the shaft 1. The upper end of the transport path 4 is connected to a receiving hopper 5 via a predetermined pipe, and concrete is pumped to the receiving hopper 5 from an upper concrete pump truck 6 via a transport path 7. Thereby, in the transport path 4, concrete is pumped from the upper part to the lower part. The transport path 7 has a bent portion 7 a bent upward in the vicinity of the lower end portion, and a hydraulic shutter valve 7 b is installed between the bent portion 7 a and the receiving hopper 5. By providing such a bent portion 7a, the impact at the time of placing the concrete is reduced, and furthermore, the concrete always remains in the pipe even when the placing is interrupted. Concrete is pumped. Further, since the shutter valve 7b opens and closes in conjunction with the start and stop of the pumping of the concrete pump vehicle 6, it is possible to prevent the concrete from being suddenly sent through the pipe and being in a vacuum state when the pumping is stopped.
[0015]
The transporting path 4 connects a number of pumping pipe units 8 and a driving pumping pipe unit 9 (arranged at a first position in the transporting path 4 and a second position above the transporting path 4). Is fixed to the inner wall surface of the shaft 1. Thus, by fixing the transport path 4 to the inner wall surface of the shaft 1, safe and reliable placement of concrete can be performed. The first and second positions are set in advance as positions for placing concrete. However, depending on the scale of the shaft 1, the positions of the third, fourth,... The installation pressure feeding pipe unit 9 may be interposed.
[0016]
As shown in FIG. 2, the pressure feeding pipe unit 8 is configured by arranging two pressure feeding pipes (tube bodies) 10 made of steel pipes in parallel (since FIG. 2 is a side view, one pressure feeding pipe 10 is provided. It is fixed to the inner wall surface of the shaft 1 by the chemical anchor 11. A high pressure collar 12 for connecting to other pressure feeding pipes is attached to both ends of each pressure feeding pipe 10, and a trap 13 for performing various operations is provided on one side of the pressure feeding pipe 10. It has been.
[0017]
Further, as shown in FIG. 3, the driving pressure feeding pipe unit 9 has a rectangular holding frame 14 formed of a steel material, and is fixed to the inner wall surface of the shaft 1 by a chemical anchor 11. In the holding frame 14, two pressure feed pipes (tube bodies) 15a made of steel pipes are fixed in parallel to the upper frame portion 14a, and two pressure feed pipes (tube bodies) made of steel pipes are fixed to the lower frame portion 14b. 15b is fixed in parallel. A collar 12 is attached to both ends of each of the pressure feeding pipes 15 a and 15 b, and a trap 13 is provided on one side of the holding frame 14.
[0018]
Further, a replacement pressure feeding pipe 16 made of a steel pipe is disposed between the pressure feeding pipe 15a and the pressure feeding pipe 15b, and is connected to the pressure feeding pipes 15a and 15b via the collars 12 at both ends thereof. In addition, a pressure-feed pipe 18 with a branch pipe made of a steel pipe can be connected between the pressure-feed pipe 15 a and the pressure-feed pipe 15 b instead of the replacement pressure-feed pipe 16. As shown in FIG. 4, the branch pipe-attached pressure feed pipe 18 includes a main pipe 18 a connected to the respective pressure feed pipes 15 a and 15 b via the collar 12, and a branch pipe 18 b that branches obliquely downward from the main pipe 18 a. It is comprised.
[0019]
After the transport path 4 is formed in the shaft 1 by the pressure feed pipe unit 8 and the placement pressure feed pipe unit 9 as described above, as shown in FIG. 5, the pressure feed pipe for placement disposed at the first position. A predetermined number of hydraulic iron pipes 2 are built up near the lower end of the unit 9. Subsequently, as shown in FIG. 6, the upper end opening of the uppermost hydraulic iron pipe 2 is covered with a canopy 21, and a working scaffold 22 is installed on the canopy 21. Then, one replacement pressure feed pipe (tube body arranged at the first position) 16 of the placement pressure feed pipe unit 9 is removed, and the pressure feed pipe with the branch pipe suspended by the crane (the pipe with the first branch pipe). Body) 18 is connected.
[0020]
In the pressure-feeding pipe unit 9 for placement, even if a load due to the weight of the pressure-feeding pipe unit 8 connected to the upper side is applied, the distance between the pressure-feeding pipes 15a and 15b is the holding frame (first holding means) 14. Is held securely. Therefore, when exchanging the replacement pressure feeding pipe 16 and the branch pipe-attached pressure feeding pipe 18, the pressure feeding pipes 16 and 18 can be safely and easily attached and detached.
[0021]
Subsequently, as shown in FIG. 7, a concrete chute 23 is connected to the tip of the branch pipe (first branch path) 18b of the branch pipe-attached pressure feed pipe 18. Then, concrete is put into the receiving hopper 5 from the concrete pump vehicle 6 through a predetermined transportation path, and the concrete is pumped from the upper side to the lower side with respect to the transportation path 4. In addition, it is good also as a structure which pumps concrete directly from the concrete pump vehicle 6 to the transport path 4 without using the receiving hopper 5.
[0022]
When the concrete pumping to the transport path 4 is started, the concrete is supplied to the gap S between the inner wall surface of the shaft 1 and the hydraulic iron pipe 2 through the branch pipe 18 b and the concrete chute 23. Then, concrete is placed around the hydraulic iron pipe 2 while rotating the branch pipe 18b and the concrete chute 23. After pouring concrete up to the vicinity of the upper end of the uppermost hydraulic iron pipe 2, a small amount of water is poured from the upper part to clean the transportation path 4 above the first position. Then, the branch pipe-attached pressure feed pipe 18 is removed and cleaned, and the replacement pressure feed pipe 16 previously removed is connected.
[0023]
Next, a predetermined number of stages of the hydraulic iron pipes 2 are built up to the vicinity of the lower end of the placement pressure feeding pipe unit 9 arranged at the second position, and one replacement pressure feeding pipe of the placement pressure feeding pipe unit 9 (second 16) is removed, and a pressure-feed pipe with a branch pipe (second pipe with a branch pipe) 18 is connected. Also in this pressure feeding pipe unit 9 for placement, since the distance between the pressure feeding pipes 15a and 15b is securely held by the holding frame (second holding means) 14, the pressure feeding pipes 16 and 18 can be attached and detached safely and easily. Can be done.
[0024]
Subsequently, the concrete chute 23 is connected to the tip of the branch pipe 18 b of the pressure feed pipe 18 with the branch pipe, and then the concrete is pumped from the upper side to the lower side with respect to the transport path 4. Thereafter, concrete is placed in the gap S between the inner wall surface of the shaft 1 and the hydraulic iron pipe 2 through the branch pipe (second branch path) 18b and the concrete chute 23 in the same manner as the first position described above.
[0025]
Further, when the casting pressure feeding pipe unit 9 is interposed at the third, fourth,... Positions, similarly, the predetermined number of stages of the hydraulic iron pipes 2 are installed at the third, fourth,. Then, the replacement pressure feeding pipe 16 is replaced with a pressure feeding pipe 18 with a branch pipe, and concrete is placed through the branch pipe 18b of the pressure feeding pipe 18 with the branch pipe.
[0026]
According to the concrete placement method described above, concrete is placed in the first position with respect to the gap S between the inner wall surface of the shaft 1 and the hydraulic iron pipe 2, and then the first position above the first position. Since the concrete is placed at the position 2, the concrete can be placed sequentially from the lower region in the gap S. Therefore, even when the shaft 1 is a large scale having a depth exceeding 100 m and a large amount of concrete needs to be placed in the gap S, the concrete is surely and efficiently applied over the entire range of the gap S. It is possible to improve the construction efficiency. Further, since it is possible to continuously cast a large amount of concrete at each position, it is possible to prevent separation of the placed concrete.
[0027]
In addition, since the transport path 4 is formed by the pressure feeding pipe unit 8 and the placement pressure feeding pipe unit 9, it is possible to deal with a wide range of shafts 1 of various scales. And the rigidity of the transport path 4 becomes very high by unitization, and high safety is ensured against the load (impact) accompanying the pumping of concrete. Further, by replacing the replacement pressure feed pipe 16 with the branch pipe pressure feed pipe 18 in the placement pressure feed pipe unit 9 arranged at the first and second positions, the branch path branched from the transport path 4 is changed to each position. Can be easily formed.
[0028]
Furthermore, since the transportation path 4 has two lines of piping composed of the pressure feeding pipes 10, 15a, 15b and the replacement pressure feeding pipe 16, only one line of piping is used for concrete pressure feeding as described above. Other series of piping can be used as drainage piping. Then, by using the two series of pipes for the concrete pumping while sequentially switching, the wear of the pipes of each series accompanying the large-scale placement of concrete can be suppressed, and the life of the transportation path 4 can be extended.
[0029]
In addition, this invention is not limited to the said embodiment. For example, the transportation route according to the present invention is not limited to having two lines of piping, but may have one line of piping, or may have three or more lines of piping. Moreover, in the said embodiment, although the transportation path 4 was directly formed in the gap | interval S which is a placement plan area | region, if the transportation path which concerns on this invention is formed along a placement plan area | region, it will be a plan placement area | region. It may be formed outside.
[0030]
In the above embodiment, the branch path is formed by replacing the replacement pressure feed pipe 16 with the pressure feed pipe 18 with the branch pipe. For example, the branch pipe is directly connected to the pressure feed pipe forming the transport path. A path can also be formed. Furthermore, the present invention is not limited to the construction of a structure in a shaft such as a hydraulic iron pipe, but can be applied to construction of a structure having a height difference in the vertical direction.
[0031]
【The invention's effect】
The concrete placement method according to the present invention can be suitably implemented when a large amount of concrete is placed in a large placement area where the height difference exceeds 100 m.
[Brief description of the drawings]
FIG. 1 is a side view showing a construction site of a hydroelectric power plant in which an embodiment of a concrete placing method according to the present invention is implemented.
FIG. 2 is a side view of a pressure feeding pipe unit that forms the transportation path shown in FIG. 1;
FIG. 3 is a front view of a pressure feeding pipe unit for placing that forms the transportation path shown in FIG. 1;
4 is a front view showing a pressure-feed pipe with a branch pipe attached to the pressure-feed pipe unit for placement shown in FIG. 3. FIG.
FIG. 5 is a conceptual diagram showing how a hydraulic iron pipe is built in the shaft shown in FIG. 1;
6 is a conceptual diagram showing a state of replacement between a replacement pressure feed pipe and a branch pipe-attached pressure feed pipe in the shaft shown in FIG. 1. FIG.
7 is a conceptual diagram showing a state of placing concrete in the shaft shown in FIG. 1. FIG.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Vertical shaft, 2 ... Hydraulic iron pipe, 4 ... Transport route, 10, 15a, 15b ... Pressure feed pipe (pipe body), 14 ... Holding frame (1st holding means, 2nd holding means), 16 ... Pumping for replacement | exchange Pipes (tubes arranged at the first position, pipes arranged at the second position), 18 ... pressure feed pipe with branch pipe (first pipe with pipe, second pipe with pipe) ), 18b ... branch pipe, S ... gap.

Claims (3)

鉛直方向に延在する打設予定領域にコンクリートを打設するコンクリート打設方法であって、
前記打設予定領域に沿って当該打設予定領域内にコンクリートの輸送路を複数系列形成する輸送路形成工程と、
前記輸送路における第1の位置に第1の分岐路を形成する第1の分岐路形成工程と、
前記輸送路を上方から輸送されてきたコンクリートを前記第1の分岐路を通じて前記打設予定領域に打設する第1の打設工程と、
前記第1の打設工程の後、前記輸送路における前記第1の位置より上方の第2の位置に第2の分岐路を形成する第2の分岐路形成工程と、
前記輸送路を上方から輸送されてきたコンクリートを前記第2の分岐路を通じて前記打設予定領域に打設する第2の打設工程とを備えることを特徴とするコンクリート打設方法。
A concrete placement method for placing concrete in a planned placement area extending in a vertical direction,
A transportation route forming step for forming a plurality of concrete transportation routes in the placement planned region along the planned placement region ;
A first branch path forming step of forming a first branch path at a first position in the transport path;
A first placing step of placing the concrete that has been transported from above the transportation path into the placement planned area through the first branch path;
After the first placing step, a second branch path forming step for forming a second branch path at a second position above the first position in the transport path;
A concrete placing method, comprising: a second placing step of placing the concrete transported from above on the transportation path into the placement planned area through the second branch path.
前記輸送路は、複数の管体を接続することにより形成され、
前記第1の分岐路形成工程は、前記管体のうち前記第1の位置に配置された管体を、分岐管が形成された第1の分岐管付管体に交換する工程であり、
前記第2の分岐路形成工程は、前記管体のうち前記第2の位置に配置された管体を、分岐管が形成された第2の分岐管付管体に交換する工程であることを特徴とする請求項1に記載のコンクリート打設方法。
The transport path is formed by connecting a plurality of pipes,
The first branch path forming step is a step of replacing the pipe body arranged at the first position in the pipe body with a first branch pipe-attached pipe body in which a branch pipe is formed,
The second branch path forming step is a step of replacing the pipe body arranged at the second position in the pipe body with a second pipe with a branch pipe in which a branch pipe is formed. The concrete placement method according to claim 1, wherein the concrete is placed.
前記輸送路は、
前記管体のうち前記第1の位置に配置された管体の上端に接続された管体と下端に接続された管体との間の距離を保持する第1の保持手段と、
前記管体のうち前記第2の位置に配置された管体の上端に接続された管体と下端に接続された管体との間の距離を保持する第2の保持手段とを有することを特徴とする請求項2に記載のコンクリート打設方法。
The transport route is
A first holding means for holding a distance between a pipe connected to the upper end of the pipe arranged at the first position and a pipe connected to the lower end of the pipe;
A second holding means for holding a distance between the pipe connected to the upper end of the pipe arranged at the second position and the pipe connected to the lower end of the pipe. The concrete placing method according to claim 2, wherein the concrete is placed.
JP2002263156A 2002-09-09 2002-09-09 Concrete placement method Expired - Fee Related JP3872739B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002263156A JP3872739B2 (en) 2002-09-09 2002-09-09 Concrete placement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002263156A JP3872739B2 (en) 2002-09-09 2002-09-09 Concrete placement method

Publications (2)

Publication Number Publication Date
JP2004100262A JP2004100262A (en) 2004-04-02
JP3872739B2 true JP3872739B2 (en) 2007-01-24

Family

ID=32262998

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002263156A Expired - Fee Related JP3872739B2 (en) 2002-09-09 2002-09-09 Concrete placement method

Country Status (1)

Country Link
JP (1) JP3872739B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105604323A (en) * 2015-12-24 2016-05-25 魏乾坤 Slurry lifting and transferring device

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020153074A (en) * 2019-03-18 2020-09-24 清水建設株式会社 High head concrete placement device, and placement method
CN114059542B (en) * 2021-11-16 2023-05-26 中国建筑第七工程局有限公司 Unit assembled chute system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105604323A (en) * 2015-12-24 2016-05-25 魏乾坤 Slurry lifting and transferring device

Also Published As

Publication number Publication date
JP2004100262A (en) 2004-04-02

Similar Documents

Publication Publication Date Title
KR101066648B1 (en) Catchment Apparatus for Tunnel
CN111074902A (en) Construction method for dismantling deep foundation pit concrete support beam in soft soil area
JP3872739B2 (en) Concrete placement method
CN110966017A (en) Construction method for water-rich stratum shield interval outer wrapping type tunnel portal ring beam
JP4524756B2 (en) Side wall construction method for underground tank
CN101603315B (en) Method for constructing seepage prevention system of secondary cofferdam for immersed tube tunnel
JP2010261165A (en) Structure and construction method for temporarily installing incidental equipment in coastal work
JP2005256433A (en) Treated sewage and rainwater sending and draining system
EP2993275B1 (en) Pump station, wastewater system and method of transporting wastewater
JP7359471B2 (en) sand pond
JP2014084568A (en) Concrete placing system and concrete placing method
NO323968B1 (en) Storage tank assembly
CN112726434B (en) Three-span deck reinforced concrete arch bridge dismantling method
CN107237348B (en) The temporary punching and restorative procedure of industrial underground pipe gallery
JP5700678B2 (en) Air supply method and air supply device to work room in pneumatic caisson
CN216131502U (en) A sewage pipes for clearing up moist pipe mortar of high-rise building
CN118065447B (en) Pile foundation section increasing method
KR100792577B1 (en) A steel chamber for being used as a manhole of steam pipeline
CN112797235B (en) Method for installing water conveying pipeline in tunnel
JP7389724B2 (en) Advance mortar recovery method and advance mortar recovery device
CN215154682U (en) Concrete placement auxiliary device
KR102580456B1 (en) Sewage bypass device in manhole pump station
JP2614805B2 (en) Underground water drainage system
CN217492036U (en) Cleaning system for coal container of collection truck
CN214147022U (en) Integrated exhaust emptying well for buried pressure water delivery pipeline

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050330

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060328

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060404

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060605

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20061010

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20061020

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121027

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121027

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151027

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees