JP3796576B2 - Shaft rebar fixing method in underwater confined construction method - Google Patents
Shaft rebar fixing method in underwater confined construction method Download PDFInfo
- Publication number
- JP3796576B2 JP3796576B2 JP2001248580A JP2001248580A JP3796576B2 JP 3796576 B2 JP3796576 B2 JP 3796576B2 JP 2001248580 A JP2001248580 A JP 2001248580A JP 2001248580 A JP2001248580 A JP 2001248580A JP 3796576 B2 JP3796576 B2 JP 3796576B2
- Authority
- JP
- Japan
- Prior art keywords
- reinforcing bar
- underwater
- fixing
- shaft
- drilling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Description
【0001】
【発明の属する技術分野】
本発明は、水中の既設構造物の補強工法の1つである水中コンファインド工法に関連し、特に当該工法の一工程として位置付けられる軸方向補強鉄筋の定着方法に関する。
【0002】
【従来の技術】
コンファインド工法は、主として既設橋脚の耐震性強化を目的とした補強工法の1つである。本発明は特に、橋脚が水底から立設しフーチング部分が水中に在る場合における耐震補強工法、すなわち水中コンファインド工法に関連するため、先ず従来の当該工法の代表例を簡単に説明する。
【0003】
図4は、従来の代表的な水中コンファインド工法による施工後の橋脚20の概略的な側面図である。水中コンファインド工法では、フーチング22上に橋脚20の周囲を取り囲むようにプレキャストコンクリートパネル46を組み立て水中50に沈設した後、橋脚20とプレキャストコンクリートパネル46の間隙にコンクリートを充填することにより両者を一体化する。この工法においては、プレキャストコンクリートパネル46内に水平方向に挿通した複数の帯鉄筋(PC鋼材)を緊張させることによりコンファインド(拘束)効果を強化する。
【0004】
図5は、上記工法の施工途中における橋脚20の概略的断面図である。橋脚20とプレキャストコンクリートパネル46の間隙44には、橋脚の曲げ耐力を増すために複数の軸方向補強鉄筋すなわち軸鉄筋42が設置されている。施工手順としてこれらの軸鉄筋42は、プレキャストコンクリートパネル46の組み立てに先立って、既設フーチングに対してアンカー定着させる必要がある。
【0005】
図6は、軸鉄筋42のフーチング22への固定部における軸方向の概略的断面図である。施工においては、先ずフーチング22に対して軸鉄筋42の定着孔10の削孔を行う。従来、この削孔は専らダイヤモンドコアドリルを用いたコアボーリング技術により行われていた。削孔後軸鉄筋42を挿入して定着材(一種の接着剤)で固定する。水中から立設する橋脚20の場合、これは水中での作業となる。その後、橋脚20を取り囲んでプレキャストコンクリートパネル46を組み立て沈設し、間隙44の土砂や水を排出してコンクリートを充填する。
【0006】
【発明が解決しようとする課題】
上記の通り、軸鉄筋42の定着孔10の削孔は水中での作業となることから、種々の問題がある。第1に、通常、フーチング22の内部には既設鉄筋が存在するが、定着孔10の削孔に先立って、既設鉄筋の場所を探査する必要がある。これらの既設鉄筋を避けて軸鉄筋42を配置しなければならないからである。しかしながら、水中における鉄筋探査の施工実績は少なく、探査機械の選定、センサの防水処理方法、探査精度等、未だ十分な技術が確立されていない。
【0007】
第2に、不十分な探査に基づいてダイヤモンドコアドリルによるコアボーリングを行うと、仮にその場所に既設鉄筋があった場合、既設鉄筋は簡単に切断されてしまうという問題がある。従って、既設鉄筋の非破壊鉄筋探査機の使用が不可能な場合は、コアボーリングによる削孔はできないこととなる。
【0008】
第3に、コアボーリングによる削孔では、孔壁が滑らかで凹凸が少ないため、軸鉄筋を挿入して定着材で固定した場合、引抜耐力が不足するという問題がある。
【0009】
以上の問題点に鑑み本発明は、水中コンファインド工法において既設鉄筋を確実に避けて補強用の軸鉄筋を強固に定着させる方法、特に既設鉄筋を避けるための削孔方法を提供することを目的とする。
【0010】
【課題を解決するための手段】
(1)本発明による、水中の既設建造物を補強する水中コンファインド工法における軸鉄筋定着方法は、少なくとも次の工程を有する。
(a)水と研磨材とを含む研磨材スラリーのジェット噴射を用い、コンクリートを削孔可能としかつ鉄筋を切断不能とする条件にて前記既設建造物の対象箇所に対して軸鉄筋用の定着孔を削孔する工程
(b)前記定着孔に軸鉄筋を挿入し定着材により固定する工程
そして、上記 (a) の削孔する工程において前記ジェット噴射により前記定着孔の孔壁面に凹凸が形成される。
【0011】
(2)上記(1)の軸鉄筋定着方法において好適には、(a)の既設建造物の対象箇所に対して軸鉄筋用の定着孔を削孔する工程に先立ち、(c)前記条件を決定するための削孔試験データを予め取得する工程をさらに有する。
【0012】
(3)上記(1)又は(2)の軸鉄筋定着方法において、前記条件として前記ジェット噴射のジェット圧力及びジェットノズル回転数を少なくとも含むことが好適である。
【0013】
(4)上記(1)〜(3)のいずれかの軸鉄筋定着方法においてさらに好適には、前記軸鉄筋がエポキシ樹脂塗装鉄筋でありかつ前記定着材がエポキシ樹脂接着剤である。
【0014】
【発明の実施の形態】
以下、図1〜図3を参照して本発明の実施の形態を説明する。
図1は、本発明による水中コンファインド工法における軸鉄筋定着方法を用いた施工時の概略的配置構成図である。本発明では、高圧ポンプによる高圧流体噴射いわゆるウォータージェット技術を用いて削孔を行うことを特徴とする。特に、研磨材と水を混合したスラリーを高圧ポンプにより加圧噴射させる直接加圧式アブレシブジェット技術を用いる。図1に示すように、水タンク32からの水と、研磨材タンク33からの研磨材をミキサー34で混合して研磨材スラリーを形成し、この研磨材スラリーを高圧スラリーポンプ35へ送出する。高圧スラリーポンプ35は、孔管ロッド31を通してその先端に設けたジェットノズル30へ高圧の研磨材スラリーを送出する。そしてジェットノズル30から研磨材スラリーが直接噴射される。
【0015】
孔管ロッド31は、削孔マシン(図示せず)により支持されかつ前進後退及び回転するべく駆動される。これによりジェットノズル30が前進後退及び回転することができる。また、本発明では水中削孔を行うので、削孔効率を高めるためにエアーコンプレッサ36により高圧エアーをジェットノズル30まで送出し、研磨材スラリーと共に噴射する。従ってこの場合、孔管ロッド31は、研磨材スラリー用通路と高圧エアー用通路とを具備する2孔管ロッドである。本発明による方法は、これらの各装置を含む研磨材スラリージェットシステムにより実施することができる。
【0016】
研磨材スラリーの高圧噴射は、比較的低圧でも大きな加工能力をもつ噴流を形成することが可能である。また圧力を制御することにより広範な適用範囲を有する。例えば、剥離・洗浄等の構造物の表面処理から、切断・削孔等の構造部物の改造解体処理まで可能であり、コンクリート削孔にも好適である。
【0017】
図2は、本発明による水中コンファインド工法における軸鉄筋定着方法の実施フローを概略的に示す流れ図である。
【0018】
・ステップ101:先ず、施工対象とする既設橋脚の水中における既設鉄筋の探査が可能か否かを判断する。実際に、水中における橋脚内部鉄筋の水中探査試験を行うことにより判断する。
【0019】
・ステップ102:前述の通り、水中における信頼性のある鉄筋探査はほとんどの場合不可能である。従って、この場合、コアボーリングによる削孔はできない。そこで本発明では、施工対象の橋脚への実際の施工に先立って、研磨材スラリージェット削孔試験を行う。図3は、本発明における研磨材スラリージェット削孔試験方法を示す概略構成図である。先ず、供試体60を用意する。供試体60は、コンクリート製であり施工対象である橋脚フーチング等の既設構造物と同条件のコンクリートであることが好適である。供試体60の内部には、試験用鉄筋63が配置されている。試験用鉄筋63もまた、施工対象である既設構造物内部の既設鉄筋と同条件であることが好適である。さらに、供試体60の上面は、貯水壁61内に試験用水62が張られている。この試験用水62に覆われた上面に対して、実際の施工に用いる研磨材スラリージェットシステムを用いて削孔試験を行う。すなわち孔管ロッド31の先端のジェットノズル30から研磨材スラリーをジェット噴射して、供試体60を削孔することにより、種々のデータを収集する。
【0020】
削孔試験において取得すべき主要なデータは、次の通りである。
(1)コンクリートのみを削孔するときのジェット圧力及びジェットノズル回転数と、削孔径、削孔時間との関係。
(2)鉄筋を切断するときのジェット圧力及びジェットノズル回転数と、切断時間の関係。
(3)削孔時の水の汚濁状況(目視確認)。
(4)コンクリートの削孔壁面の状態。
(5)削孔後、定着材により定着させた鉄筋の引抜耐力。
上記のうち少なくとも(1)及び(2)は、研磨材スラリーのジェット噴射により鉄筋を切断することなくコンクリートのみを削孔する条件を決定する上で必須のデータである。これらの削孔試験データにより研磨材スラリージェット噴射の適用性を確認することができる。
【0021】
尚、実際の施工に先立って行う削孔試験は、必ずしも全ての既設構造物の施工について毎回行う必要はなく、既に得られた削孔試験データをそのまま適用できる場合は既存の削孔試験データを転用してもよい。例えば、複数の既設構造物の各々がほぼ同条件で建造されている場合である。
【0022】
・ステップ103:ステップ102の削孔試験でデータを得た後、実際に水中コンファインド工法による施工を実施する。すなわち、研磨材スラリージェットにより橋脚フーチング等の既設構造物の対象箇所に対し軸鉄筋用定着孔の削孔を行う。このとき、予め取得した削孔試験データに基づき、コンクリートのみを削孔可能としかつ鉄筋を切断不能とする条件を決定する。このような条件(通常、一定の許容範囲がある)としては、例えば、ジェット圧力とジェットノズル回転数、あるいは少なくともこれらのいずれか一方である。このような条件に設定して削孔を行うと、たとえ削孔途中に既設鉄筋に当たったとしてもその鉄筋を切断することはなく、削孔不能(ジェットノズルが進行不能)となることでその位置に鉄筋があることを感知することができる。既設鉄筋に当たった場合は、その位置を避けて別の場所に削孔する。削孔後、軸鉄筋を定着孔に挿入し、定着材で固定する。好適例では、定着材として水中硬化型エポキシ樹脂接着剤を用い、軸方向鉄筋としてエポキシ樹脂塗装鉄筋を用いた場合に、定着材と鉄筋の付着性が良好であった。また、コアボーリングによる削孔と比較すると、本発明の研磨材スラリージェット噴射により削孔された定着孔の孔壁面は滑らかではなく、適度の凹凸があるため、軸鉄筋定着後の引抜耐力が大きい。
【0023】
・ステップ104:尚、上記ステップ101において、施工対象とする既設橋脚の水中における既設鉄筋の探査が可能であると判断された場合は、従来通りのコアボーリングを行うことが可能である。しかしながら、既設鉄筋探査が可能な場合であっても、本発明の方法によれば強固な軸鉄筋の定着力が得られるので、本発明による方法を行ってもよい。
【0024】
【発明の効果】
本発明による水中コンファインド工法における軸鉄筋定着方法は、研磨材スラリージェット噴射についてコンクリートのみを削孔可能としかつ鉄筋を切断不能とする条件(ジェット圧力やジェットノズル回転数)を含む削孔試験データを取得し、前記削孔試験データに基づきコンクリートのみを削孔しかつ鉄筋を切断しないような条件により橋脚フーチング等の既設建造物の対象箇所に定着孔を削孔する。これにより、既設鉄筋に当たっても当該鉄筋を切断することなく、既設鉄筋に当たることにより削孔不能となることで、既設鉄筋の存在を感知できる。従って、既設鉄筋に損傷を与えることなく、既設鉄筋の無い場所に補強用の軸鉄筋を配置定着させることができる。
【0025】
さらに、研磨材スラリージェット噴射による削孔では孔壁に適度の凹凸が形成されることから定着材と孔壁との間の強固な付着力が得られ、この結果、軸鉄筋の引抜耐力が向上する。さらに、エポキシ樹脂塗装鉄筋とエポキシ樹脂系定着材を用いた場合には、最も強固な引抜耐力が実現される。
【0026】
本発明は、水中コンファインド工法の一工程である軸鉄筋定着工程における種々の問題点を解決したものであるが、上記の通り強固に定着した軸鉄筋が実現されることから、水中コンファインド工法全体としての効果すなわち水中建造物の耐震性強化に対しても多大に寄与する方法である。
【図面の簡単な説明】
【図1】本発明による水中コンファインド工法における軸鉄筋定着方法を用いた施工時の概略的配置構成図である。
【図2】本発明による水中コンファインド工法における軸鉄筋定着方法の実施フローを概略的に示す流れ図である。
【図3】本発明における研磨材スラリージェット削孔試験方法を示す概略構成図である。
【図4】従来の代表的な水中コンファインド工法による施工後の橋脚の概略的な側面図である。
【図5】図4に示した橋脚の施工途中における概略的断面図である。
【図6】図5に示した軸鉄筋のフーチングへの固定部における軸方向の概略的断面図である。
【符号の説明】
10 軸鉄筋定着孔
20 橋脚
22 フーチング
30 ジェットノズル
31 2孔管ロッド
32 水タンク
33 研磨材タンク
34 ミキサー
35 高圧スラリーポンプ
36 エアーコンプレッサ
40 既設鉄筋
42 軸方向補強鉄筋
44 コンクリート充填空間
46 プレキャストパネル
50 水
60 供試体
61 貯水壁
62 試験用水
63 試験用鉄筋[0001]
BACKGROUND OF THE INVENTION
The present invention relates to an underwater confined construction method, which is one of the reinforcement methods for existing structures in water, and more particularly to a fixing method for axially reinforced reinforcing bars positioned as one step of the construction method.
[0002]
[Prior art]
The confined construction method is one of reinforcement methods mainly for the purpose of strengthening the earthquake resistance of existing piers. Since the present invention relates to the seismic reinforcement method when the pier stands from the bottom of the water and the footing part is underwater, that is, the underwater confined method, first, a typical example of the conventional method will be briefly described.
[0003]
FIG. 4 is a schematic side view of the
[0004]
FIG. 5 is a schematic cross-sectional view of the
[0005]
FIG. 6 is a schematic cross-sectional view in the axial direction of the fixing portion of the
[0006]
[Problems to be solved by the invention]
As described above, since the drilling of the
[0007]
Secondly, when core boring with a diamond core drill is performed based on insufficient exploration, if there is an existing reinforcing bar at that location, the existing reinforcing bar is easily cut. Therefore, when it is impossible to use a non-destructive reinforcing bar survey machine for existing reinforcing bars, drilling by core boring cannot be performed.
[0008]
Thirdly, in the drilling by core boring, since the hole wall is smooth and there are few irregularities, there is a problem that the pulling strength is insufficient when the shaft reinforcing bar is inserted and fixed with the fixing material.
[0009]
In view of the above problems, an object of the present invention is to provide a method for firmly fixing an axial reinforcing bar for reinforcement by reliably avoiding an existing reinforcing bar in an underwater confining method, and in particular, a drilling method for avoiding an existing reinforcing bar. And
[0010]
[Means for Solving the Problems]
(1) The shaft reinforcing bar fixing method in the underwater confined construction method for reinforcing an existing underwater structure according to the present invention includes at least the following steps.
(a) Fixation for shaft reinforcing bars to the target location of the existing building under the condition that the concrete can be drilled and the reinforcing bars cannot be cut using jetting of abrasive slurry containing water and abrasive The process of drilling holes
(b) A step of inserting a shaft rebar into the fixing hole and fixing with a fixing material
In the step (a) of drilling, irregularities are formed on the hole wall surface of the fixing hole by the jet injection.
[0011]
(2) In the shaft reinforcing bar fixing method of (1) above, preferably, (a) prior to the step of drilling the shaft reinforcing bar fixing hole in the target location of the existing building, (c) The method further includes a step of acquiring in advance drilling test data for determination.
[0012]
(3) In the shaft reinforcing bar fixing method according to (1) or (2), it is preferable that the conditions include at least the jet pressure of the jet injection and the number of rotations of the jet nozzle.
[0013]
(4) In the shaft reinforcing bar fixing method according to any one of (1) to (3), more preferably, the shaft reinforcing bar is an epoxy resin-coated reinforcing bar, and the fixing material is an epoxy resin adhesive.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of the present invention will be described with reference to FIGS.
FIG. 1 is a schematic arrangement configuration diagram at the time of construction using the shaft reinforcing bar fixing method in the underwater confining method according to the present invention. The present invention is characterized in that drilling is performed using a high-pressure fluid injection by a high-pressure pump, so-called water jet technology. In particular, a direct pressurizing abrasive jet technique in which a slurry in which an abrasive and water are mixed is pressurized and injected by a high-pressure pump is used. As shown in FIG. 1, water from the
[0015]
The
[0016]
High-pressure injection of the abrasive slurry can form a jet having a large processing capability even at a relatively low pressure. It has a wide range of application by controlling the pressure. For example, it is possible from surface treatment of structures such as peeling and cleaning to remodeling and dismantling processing of structural parts such as cutting and drilling, and is also suitable for concrete drilling.
[0017]
FIG. 2 is a flowchart schematically showing an execution flow of the shaft reinforcing bar fixing method in the underwater confining method according to the present invention.
[0018]
Step 101: First, it is determined whether or not it is possible to search for existing reinforcing bars in the water of existing piers to be constructed. Judgment is made by conducting an underwater exploration test of the internal reinforcement of the pier underwater.
[0019]
Step 102: As mentioned above, reliable rebar exploration in water is almost impossible. Therefore, in this case, drilling by core boring is not possible. Therefore, in the present invention, an abrasive slurry jet drilling test is performed prior to actual construction on the construction target pier. FIG. 3 is a schematic configuration diagram showing an abrasive slurry jet drilling test method according to the present invention. First, the specimen 60 is prepared. The specimen 60 is preferably made of concrete and concrete under the same conditions as an existing structure such as a pier footing to be constructed. A
[0020]
The main data to be acquired in the drilling test is as follows.
(1) Relationship between jet pressure and jet nozzle rotation speed when drilling only concrete, hole diameter and time.
(2) Relationship between the cutting time and the jet pressure and jet nozzle rotation speed when cutting reinforcing bars.
(3) Water contamination status during drilling (visual confirmation).
(4) The state of the wall surface of the drilled concrete.
(5) Pull-out strength of rebar fixed by fixing material after drilling.
Among the above, at least (1) and (2) are essential data for determining conditions for drilling only concrete without cutting the rebar by jetting the abrasive slurry. The applicability of abrasive slurry jet injection can be confirmed from these drilling test data.
[0021]
The drilling test performed prior to the actual construction does not necessarily need to be performed every time for the construction of all existing structures. If the already obtained drilling test data can be applied as is, the existing drilling test data should be used. You may divert. For example, this is a case where each of a plurality of existing structures is constructed under substantially the same conditions.
[0022]
Step 103: After obtaining data in the drilling test in
[0023]
Step 104: If it is determined in
[0024]
【The invention's effect】
The shaft reinforcing bar fixing method in the underwater confined construction method according to the present invention is a drilling test data including conditions (jet pressure and jet nozzle rotation speed) that allow only the concrete to be drilled and cannot cut the reinforcing bar in the abrasive slurry jet injection. Then, based on the drilling test data, a fixing hole is drilled at a target location of an existing building such as a bridge pier footing under the condition that only the concrete is drilled and the reinforcing bar is not cut. Thereby, even if it hits an existing reinforcing bar, the presence of the existing reinforcing bar can be sensed by making it impossible to drill a hole by hitting the existing reinforcing bar without cutting the reinforcing bar. Therefore, the reinforcing shaft reinforcing bars can be arranged and fixed in a place where there is no existing reinforcing bars without damaging the existing reinforcing bars.
[0025]
In addition, drilling with abrasive slurry jets creates moderate irregularities on the hole wall, resulting in a strong adhesion between the fixing material and the hole wall, which improves the pull-out strength of the shaft reinforcement. To do. Furthermore, when the epoxy resin coated reinforcing bar and the epoxy resin-based fixing material are used, the strongest pulling strength is realized.
[0026]
The present invention solves various problems in the shaft rebar fixing process, which is one step of the underwater confined construction method. However, since the shaft rebar is firmly fixed as described above, the underwater confined construction method is realized. It is a method that greatly contributes to the overall effect, that is, to strengthening the earthquake resistance of underwater buildings.
[Brief description of the drawings]
FIG. 1 is a schematic arrangement configuration diagram at the time of construction using a shaft reinforcing bar fixing method in an underwater confinement method according to the present invention.
FIG. 2 is a flowchart schematically showing an execution flow of a shaft reinforcing bar fixing method in an underwater confinement method according to the present invention.
FIG. 3 is a schematic configuration diagram showing an abrasive slurry jet drilling test method in the present invention.
FIG. 4 is a schematic side view of a pier after construction by a conventional typical underwater confining method.
FIG. 5 is a schematic cross-sectional view during construction of the pier shown in FIG.
6 is a schematic cross-sectional view in the axial direction of a fixing part to the shaft reinforcing bar footing shown in FIG.
[Explanation of symbols]
10 shaft
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001248580A JP3796576B2 (en) | 2001-08-20 | 2001-08-20 | Shaft rebar fixing method in underwater confined construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001248580A JP3796576B2 (en) | 2001-08-20 | 2001-08-20 | Shaft rebar fixing method in underwater confined construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003055917A JP2003055917A (en) | 2003-02-26 |
JP3796576B2 true JP3796576B2 (en) | 2006-07-12 |
Family
ID=19077718
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001248580A Expired - Fee Related JP3796576B2 (en) | 2001-08-20 | 2001-08-20 | Shaft rebar fixing method in underwater confined construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3796576B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5015049B2 (en) * | 2008-03-24 | 2012-08-29 | 前田建設工業株式会社 | Pier extension method |
-
2001
- 2001-08-20 JP JP2001248580A patent/JP3796576B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2003055917A (en) | 2003-02-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2007126846A (en) | Reinforcing cage, construction method for cast-in-place concrete pile, and cast-in-place concrete pile | |
CN114396022A (en) | Method for repairing dam crack defects by using magnetic mortar | |
CA2254428C (en) | Masonry reinforcement system | |
JP7134750B2 (en) | Investigation and reinforcement method of existing piles | |
JP2007032169A (en) | Pipe anchor burying method | |
JP3796576B2 (en) | Shaft rebar fixing method in underwater confined construction method | |
CN214883611U (en) | Bearing pile or uplift pile with multiple main ribs | |
JP4906335B2 (en) | Pipe anchor burial equipment | |
JPH1054031A (en) | Pre-stress concrete pile and its positioning method of pile | |
JP3763604B2 (en) | Repair method for cracks in structure | |
KR100498536B1 (en) | Method for costructing anchors under the ground using high pressure grouting | |
JP2005023567A6 (en) | Pre-stressed concrete grout reinjection method | |
JP5875849B2 (en) | Injection stirring ground improvement method | |
JP2005023567A (en) | Prestressed concrete grout reinjection method | |
Shong et al. | Design & construction of micropiles | |
US6505450B1 (en) | Masonry reinforcement system | |
KR20180062669A (en) | Micropile and micropile molding method for earthquake-proof and strengthening ground | |
JP3172694B2 (en) | Embedding method of straight pillar in reverse hitting method | |
CN109440801A (en) | A kind of reinforcement for pile foundation | |
KR100609335B1 (en) | Construction method of stiffener into the earth | |
JP3476166B2 (en) | Construction management method and device in embedded pile method | |
JP3755472B2 (en) | Ground improvement method | |
JP3813781B2 (en) | Anchor device installation method | |
CN110485422B (en) | Pile pulling construction method of pile pulling device | |
CN108221965B (en) | The more plate-resistant pouring pile construction methods of concrete back-pressure rotation type |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050803 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050823 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20051017 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060314 |
|
A711 | Notification of change in applicant |
Free format text: JAPANESE INTERMEDIATE CODE: A711 Effective date: 20060324 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060329 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20060324 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090428 Year of fee payment: 3 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100428 Year of fee payment: 4 |
|
R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100428 Year of fee payment: 4 |
|
R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
R371 | Transfer withdrawn |
Free format text: JAPANESE INTERMEDIATE CODE: R371 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100428 Year of fee payment: 4 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100428 Year of fee payment: 4 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110428 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120428 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120428 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130428 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130428 Year of fee payment: 7 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130428 Year of fee payment: 7 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140428 Year of fee payment: 8 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |