JP3779978B2 - Elevated traffic route - Google Patents

Elevated traffic route Download PDF

Info

Publication number
JP3779978B2
JP3779978B2 JP2004250240A JP2004250240A JP3779978B2 JP 3779978 B2 JP3779978 B2 JP 3779978B2 JP 2004250240 A JP2004250240 A JP 2004250240A JP 2004250240 A JP2004250240 A JP 2004250240A JP 3779978 B2 JP3779978 B2 JP 3779978B2
Authority
JP
Japan
Prior art keywords
footing
road
bridge
elevated
traffic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2004250240A
Other languages
Japanese (ja)
Other versions
JP2005009309A (en
Inventor
信明 小林
直 小原
弘太郎 小林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2004250240A priority Critical patent/JP3779978B2/en
Publication of JP2005009309A publication Critical patent/JP2005009309A/en
Application granted granted Critical
Publication of JP3779978B2 publication Critical patent/JP3779978B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

本発明は、交通路における高架式交通路に関する。   The present invention relates to an elevated traffic route in a traffic route.

従来、交通路の交差点における渋滞を解消するために、交差点を立体化させる施工では、既存の交通路の直上に高架式交通路を構築する際に、作業区間となる既存の交通路の通行が大規模に規制され、恒常的な渋滞が発生していた。   Conventionally, in order to eliminate traffic congestion at traffic road intersections, when constructing an elevated traffic road directly above an existing traffic road, the construction of an elevated traffic road directly above the existing traffic road requires the passage of the existing traffic road. Regulated on a large scale and constant traffic jams occurred.

このように、通行規制された交通路では、以下の方法によって車両の通行を確保していた。
(1)作業区間となる既存の交通路の周辺に構築した同一平面上の迂回路を経由して車両を通行させる、迂回路による通行方法。
(2)作業区間となる既存の交通路を分割して規制し、部分的に車線の通行を停止して施工を行い、同時に他の車線のみを用いて交互に既存の車両を通行させる、分割規制による通行方法。
In this way, on traffic routes that are restricted in traffic, vehicle traffic is ensured by the following method.
(1) A method of passing by a detour that allows a vehicle to pass through a detour on the same plane constructed around an existing traffic route as a work section.
(2) Divide and regulate the existing traffic route that will be the work section, partially stop the lane traffic and perform construction, and at the same time use the other lane only to pass the existing vehicle alternately How to pass by regulation.

しかしながら、従来の作業区間における交通路の通行方法では、以下の問題が存在していた。
(1)前記迂回路による通行方法では、同一平面上の迂回路の構築用地を確保しなければならず、また、同一平面上の迂回路の構築に係る施工期間を長く必要とするため、施工費が高くなっていた。
However, the following problems existed in the conventional method of passing traffic in the work section.
(1) In the method of passing by the detour, it is necessary to secure a site for constructing a detour on the same plane, and the construction period for constructing the detour on the same plane is long. The cost was high.

(2)前記分割規制による通行方法では、作業区間となる既存の交通路の通行量が制限されるため、交通渋滞が発生し、周辺地域社会の環境及び経済活動に対する影響が大きくなり、また、一括して施工が行えないため、施工期間が長く必要となり、施工費が高くなっていた。 (2) In the traffic method based on the above-mentioned division regulation, the traffic volume of the existing traffic road that is the work section is limited, so traffic congestion occurs, and the impact on the environment and economic activities of the surrounding community becomes large, Since construction cannot be performed in a lump, the construction period was long and construction costs were high.

したがって、作業区間となる既存の交通路の直上に高架式交通路を構築して車両の通行を確保することが望まれるが、高架式交通路の構築は既存の交通を大幅に規制し、車両の通行を長期間停止する必要があり、周辺地域社会の環境及び経済活動に対する影響が大きくなるため、効果的な高架式交通路の開発が望まれていた。   Therefore, it is desirable to establish an elevated traffic route directly above the existing traffic route that will be the work section to ensure vehicle traffic. However, the construction of the elevated traffic route greatly restricts existing traffic, Therefore, the development of an effective elevated transportation route has been desired because it will have a significant impact on the environment and economic activities of the surrounding community.

そこで、本発明は、既存の交通路上に作業領域を確保する場合において、既存の交通路の周辺に迂回路を構築することなく、既存の交通に対する影響を低減した状態で、既存の交通路上に高架式交通路を容易に構築する高架式交通路を提供することを課題とする。   Therefore, in the case where the work area is secured on the existing traffic road, the present invention does not construct a detour around the existing traffic road and reduces the influence on the existing traffic on the existing traffic road. It is an object of the present invention to provide an elevated traffic route for easily constructing an elevated traffic route.

本発明は、前記課題を解決すべく構成されるものであり、高架式交通路であって、既存の交通路に沿って所定の間隔をあけて埋設された複数のプレキャスト部材であるフーチングと、各フーチングに立設されている複数の支柱と、支柱間に架設されている複数の分割された橋梁からなり、既存の交通路と接続するようにして斜路が形成されている橋梁と、から構成され、フーチングには、基礎杭を嵌合可能な貫通孔を有するプレキャスト部材である基礎杭用フーチングが接合されており、基礎杭用フーチングの貫通孔には、基礎杭が接合され、フーチング同士の間には、プレキャスト部材である繋ぎ梁が設けられていることを特徴とする。また、繋ぎ梁に貫通させたPC鋼材の両端部をフーチングに定着させて緊張力を付加することにより、フーチングと繋ぎ梁を一体化してもよい。 The present invention is configured to solve the above-mentioned problem, is an elevated traffic route, and a footing that is a plurality of precast members embedded at a predetermined interval along an existing traffic route, Consists of a plurality of struts erected on each footing and a bridge that is composed of a plurality of divided bridges erected between the struts and is formed with a ramp so as to connect to existing traffic paths The footing for the foundation pile, which is a precast member having a through hole into which the foundation pile can be fitted, is joined to the footing, and the foundation pile is joined to the through hole of the footing for the foundation pile , A connecting beam, which is a precast member, is provided between them. Moreover, you may integrate a footing and a connection beam by fixing the both ends of the PC steel material penetrated to the connection beam to the footing, and adding tension.

ここで、交通路とは、道路、鉄道線路等の各種交通機関及び歩道等の通行路をいう。   Here, the traffic road refers to various transportation such as roads, railway tracks, and traffic paths such as sidewalks.

本発明の高架式交通路では、フーチングを基礎として支柱を支持することで、広範囲の施工用地を必要とすることなく、短期間に高架式交通路を構築し、作業区間における車両等の通行を早期に確保することができるため、既存の交通に与える影響を低減することができる。   In the elevated traffic route of the present invention, by supporting the support on the basis of the footing, an elevated traffic route can be constructed in a short period of time without the need for a wide range of construction sites, and vehicles etc. in the work section can be passed. Since it can be secured early, the impact on existing traffic can be reduced.

また、フーチングによる基礎を設けた高架式交通路によって車両等の通行を確保した後に、高架式道路の路面の直下で基礎杭を設けることができるため、車両等の通行に影響を与えることなく、高架式交通路の安定性をより高めることができる。   In addition, it is possible to install foundation piles directly under the road surface of the elevated road after securing the passage of the vehicle etc. by the elevated traffic road with the foundation by footing, so that the traffic of the vehicle etc. is not affected. The stability of the elevated traffic route can be further increased.

さらに、フーチングを予め工場等で形成されたプレキャスト部材にすることで、フーチングの設置作業が簡易化されるとともに、施工範囲がより縮小されるため、基礎を構築する際の交通規制をより軽減することができる。   In addition, the footing is precasted in advance at a factory, etc., which simplifies the footing installation work and further reduces the construction range, further reducing traffic restrictions when building the foundation. be able to.

また、繋ぎ梁によってフーチング同士を連結することで、フーチングに係る荷重が複数のフーチングに分散されることから、フーチングの平面寸法が縮小されるため、施工範囲が縮小され、フーチングを施工する際の交通規制を軽減することができる。 In addition , by connecting the footings with connecting beams, the load related to the footing is distributed to a plurality of footings, so that the plane dimensions of the footings are reduced, so that the construction range is reduced and the footing is constructed. Traffic regulations can be reduced.

また、繋ぎ梁を予め工場等で形成されたプレキャスト部材にすることで、繋ぎ梁の設置作業が簡易化されるとともに、施工範囲がより縮小されるため、基礎を構築する際の交通規制をより軽減することができる。   In addition, by making the connecting beam a precast member formed in advance in a factory, etc., the installation work of the connecting beam is simplified and the construction range is further reduced, so traffic restrictions when building the foundation are further reduced. Can be reduced.

したがって、本発明の高架式交通路では、広範囲の施工用地を必要とすることなく、既存の交通路の上方に既存の交通に対する影響を低減した状態で、高い安定性を有する高架式交通路を容易かつ短期間に構築することができるため、既存の交通路の周囲に迂回路を設けることなく、周辺地域社会の環境及び経済活動に対する影響を低減するとともに、施工期間を短縮し、施工費を削減することができる。
さらに、軟弱地盤に高架式交通路を構築する場合であるとしても、高架式交通路によって車両等の通行を確保した状態で、高架式交通路に基礎杭を容易かつ短期間に構築することができる。
Therefore, in the elevated traffic road of the present invention, an elevated traffic road having high stability can be provided in a state where the influence on the existing traffic is reduced above the existing traffic road without requiring a wide construction site. Since it can be constructed easily and in a short period of time, it will reduce the impact on the environment and economic activities of the surrounding community without creating a detour around the existing traffic route, shorten the construction period, and reduce the construction cost. Can be reduced.
Furthermore, even if an elevated traffic route is constructed on soft ground, foundation piles can be constructed easily and in a short period of time on the elevated traffic route while securing the passage of vehicles, etc. by the elevated traffic route. it can.

次に、本発明の実施形態について、適宜図面を参照しながら詳細に説明する。   Next, embodiments of the present invention will be described in detail with reference to the drawings as appropriate.

本発明の実施形態に係る高架式交通路は、自動車の道路、列車の線路、若しくは歩道等の交通路に適用可能であるが、この実施形態では、自動車の道路における交差点に高架式道路を設けることで、交差点を立体化する場合を例として説明する。   The elevated traffic road according to the embodiment of the present invention can be applied to a traffic road such as an automobile road, a train track, or a sidewalk. In this embodiment, an elevated road is provided at an intersection in an automobile road. Thus, a case where the intersection is three-dimensional will be described as an example.

図1は支柱立設工程を示した図で、(a)は支柱を立設した際を示す側面図、(b)は支柱を立設した際を示す平面図である。図2は橋梁架設工程を示した図で、(a)は橋梁を架設した際を示す側面図、(b)はA−A断面図である。図3は橋梁降下工程を示した図で、(a)は橋梁の側面図、(b)は橋梁を降下した際を示す側面図である。図4は橋梁降下工程を示した図で、(a)は図3(b)のB−B断面図、(b)は橋梁降下工程の他の例を示した正面断面図である。図5は橋梁降下工程を示した図で、図3(b)のC−C断面図である。図6は繋ぎ梁の他の構成を示した図で、(a)は道路の幅員方向のみに繋ぎ梁を設けた構成の平面図、(b)は道路の長手方向及び幅員方向に繋ぎ梁を設けた構成の平面図である。   FIGS. 1A and 1B are diagrams illustrating a column erecting process, in which FIG. 1A is a side view illustrating when the column is erected, and FIG. 1B is a plan view illustrating when the column is erected. 2A and 2B are views showing a bridge erection process, in which FIG. 2A is a side view showing a state where a bridge is erected, and FIG. 2B is an AA cross-sectional view. FIGS. 3A and 3B are views showing a bridge lowering process, in which FIG. 3A is a side view of the bridge, and FIG. 3B is a side view showing when the bridge is lowered. 4A and 4B are diagrams showing a bridge lowering process, in which FIG. 4A is a cross-sectional view taken along line BB in FIG. 3B, and FIG. 4B is a front cross-sectional view illustrating another example of the bridge lowering process. FIG. 5 is a cross-sectional view taken along the line CC in FIG. FIG. 6 is a diagram showing another configuration of the connecting beam. (A) is a plan view of the configuration in which the connecting beam is provided only in the width direction of the road, and (b) is a plan view of the connecting beam in the longitudinal direction and the width direction of the road. It is a top view of the structure provided.

まず、本発明の実施形態に係る高架式道路における各装置を説明する。
支柱4及び仮設柱5は、橋梁2を支持する役割を果たすものであり、図1,図2に示すように、支柱4は道路3の両側3’,3’に左右対称に立設した棒状の柱であり、道路3の両側3’,3’において一組の支柱4,4毎に所定の高さで、地中に埋設された各フーチング40に立設している。
また、高さの異なる各支柱4の上部に、所定の高さの仮設柱5を設けることで、道路3に立設した支柱4又は仮設柱5の上端が同一の高さになっている。
なお、支柱4及び仮設柱5は、後記する橋梁2を支持したときの荷重に耐えられるものであり、橋梁2を支持したときの安定性を十分に備えた構造であれば、その材料は限定されるものではない。
First, each device in the elevated road according to the embodiment of the present invention will be described.
The column 4 and the temporary column 5 play a role of supporting the bridge 2, and as shown in FIG. 1 and FIG. 2, the column 4 is a rod-like shape erected symmetrically on both sides 3 ′ and 3 ′ of the road 3. These pillars are erected on each footing 40 embedded in the ground at a predetermined height for each pair of support columns 4 and 4 on both sides 3 ′ and 3 ′ of the road 3.
In addition, by providing the temporary pillars 5 having a predetermined height above the pillars 4 having different heights, the upper ends of the pillars 4 or the temporary pillars 5 erected on the road 3 have the same height.
The column 4 and the temporary column 5 can withstand the load when the bridge 2 described later is supported, and the material is limited as long as the structure has sufficient stability when the bridge 2 is supported. Is not to be done.

さらに、フーチング40は予め工場等で形成されたプレキャスト部材であり、図1に示すように、道路3の長手方向において対となるフーチング40の間に繋ぎ梁41を設けることで、フーチング40同士を連結している。ここで、フーチング40と繋ぎ梁41は、内部にPC鋼線やPC鋼棒等のPC鋼材42を貫通させ、このPC鋼線やPC鋼棒等のPC鋼材42の両端を各フーチング40,40に定着させて緊張力を付加する、所謂ポストテンション方式によって一体化している。
したがって、フーチング40に係る荷重が、繋ぎ梁41を通じて複数のフーチング40に分散されるため、圧力を受けるフーチング40の平面寸法を縮小し、フーチング40を小型のプレキャスト部材とすることができる。
なお、フーチング40と繋ぎ梁41を一体化する方法は、PC鋼線やPC鋼棒等のPC鋼材42によって緊張力を付加するポストテンション方式に限られるものではなく、容易かつ確実に一体化することができるのであれば、一体化の方法は限定されるものではない。
Further, the footing 40 is a precast member formed in advance at a factory or the like. As shown in FIG. 1, by providing a connecting beam 41 between the pair of footings 40 in the longitudinal direction of the road 3, the footings 40 are connected to each other. It is connected. Here, the footing 40 and the connecting beam 41 penetrate a PC steel material 42 such as a PC steel wire or a PC steel rod inside, and both ends of the PC steel material 42 such as a PC steel wire or a PC steel rod are connected to the footings 40, 40. They are integrated by a so-called post-tensioning method in which they are fixed to each other and tension is applied.
Therefore, since the load related to the footing 40 is distributed to the plurality of footings 40 through the connecting beam 41, the planar dimension of the footing 40 that receives pressure can be reduced, and the footing 40 can be made a small precast member.
The method of integrating the footing 40 and the connecting beam 41 is not limited to the post tension method in which tension is applied by the PC steel material 42 such as a PC steel wire or a PC steel rod, and it is easily and reliably integrated. The integration method is not limited as long as it can be used.

そして、橋梁2は高架式道路1を構成する役割を果たすものであり、図3(a)に示すように、複数の分割された橋梁2’から構成された橋である。この分割された橋梁2’は、車両が安全に通行することができるものであれば、その材質及び構造は限定されるものではない。   And the bridge 2 plays the role which comprises the elevated road 1, and as shown to Fig.3 (a), it is a bridge comprised from the some divided | segmented bridge 2 '. The material and structure of the divided bridge 2 ′ are not limited as long as the vehicle can pass safely.

次に、本発明の実施形態に係る高架式道路の構築方法について説明する。
まず、(1)支柱立設工程では、図1に示すように、フーチング40を、道路3の長手方向に所定の間隔をあけて、道路3の両側3’,3’の地中に埋設し、道路3の長手方向に隣接する各フーチング40同士の間に繋ぎ梁41を設け、PC鋼線やPC鋼棒等のPC鋼材42を用いてポストテンション方式で連結する。
なお、フーチング40及び各分割された繋ぎ梁41’は小型のプレキャスト部材であることから、掘削量が少なく、施工範囲が縮小されることから、容易かつ短期間に埋設することができるため、基礎の施工による交通規制を軽減することができる。
Next, the construction method of the elevated road according to the embodiment of the present invention will be described.
First, in (1) the column erecting step, as shown in FIG. 1, the footing 40 is embedded in the ground on both sides 3 ′ and 3 ′ of the road 3 at a predetermined interval in the longitudinal direction of the road 3. A connecting beam 41 is provided between the footings 40 adjacent to each other in the longitudinal direction of the road 3 and is connected by a post tension method using a PC steel material 42 such as a PC steel wire or a PC steel bar.
In addition, since the footing 40 and each divided connecting beam 41 ′ are small precast members, the excavation amount is small and the construction range is reduced, so that the foundation can be embedded easily and in a short period of time. Traffic restrictions due to construction can be reduced.

ここで、フーチング40の繋ぎ梁41は、前記道路3の長手方向において対となるフーチング40の間に設ける構成に限られるものではなく、図6(a)に示すように、道路3の幅員方向のみに設ける構成や、図6(b)に示すように、道路3の幅員方向と長手方向の両方に設ける構成など、高架式道路1の荷重、地盤条件等によって適宜選定することが好ましい。
さらに、フーチング40及び繋ぎ梁41は、プレストレスを導入したプレキャスト部材に限られるものではなく、プレストレスを導入しないプレキャスト部材で構成してもよい。
Here, the connecting beam 41 of the footing 40 is not limited to the configuration provided between the pair of footings 40 in the longitudinal direction of the road 3, and as shown in FIG. configuration and provided only, as shown in FIG. 6 (b), etc. configuration provided on both width direction and longitudinal direction of the road 3, it is preferable to appropriately select the load of elevated road 1, by ground conditions, etc. .
Furthermore, the footing 40 and the connecting beam 41 are not limited to the precast member introduced with prestress, and may be configured with a precast member that does not introduce prestress.

次に、各フーチング40に支柱4を立設し、図2(a)に示すように、所定の高さの仮設柱5を各支柱4の上部に設ける。なお、仮設柱5は、分割された橋梁2’を一時的に支持した後に撤去されるため、仮設柱5と支柱4はボルトジョイント等の容易に分離可能な接合方法で接合する。   Next, the pillar 4 is erected on each footing 40, and a temporary pillar 5 having a predetermined height is provided on the upper part of each pillar 4 as shown in FIG. Since the temporary pillar 5 is removed after temporarily supporting the divided bridge 2 ′, the temporary pillar 5 and the column 4 are joined by an easily separable joining method such as a bolt joint.

次に、(2)橋梁架設工程では、図2(b)に示すように、分割された橋梁2’をトラック等の輸送手段によって搬入し、この分割された橋梁2’をクレーンKによって吊上げて道路3の長手方向に立設された2組の支柱4,4の間に架設する。このとき、分割された橋梁2’に一時的な固定処置を施すことで仮受け状態としている。   Next, (2) in the bridge erection step, as shown in FIG. 2 (b), the divided bridge 2 ′ is carried in by a transportation means such as a truck, and the divided bridge 2 ′ is lifted by a crane K. It is installed between two sets of support columns 4, 4 erected in the longitudinal direction of the road 3. At this time, a temporary fixing state is obtained by applying a temporary fixing treatment to the divided bridge 2 '.

次に、図3(a)に示すように、橋梁架設工程を繰り返すことにより、道路3の直上に分割された橋梁2’によって構成された橋梁2を構築する。   Next, as shown in FIG. 3A, the bridge erection process is repeated to construct the bridge 2 constituted by the bridge 2 'divided immediately above the road 3.

ここで、前記橋梁架設工程において、クレーンKを用いることなく分割された橋梁2’を架設することも可能であり、例えば、道路3の両側3’,3’に立設した複数の橋脚によって支持された板状のステージを作業場として分割された橋梁2’を道路3の直上で作成し、ステージから道路3に配置した門型の台車を用いて分割された橋梁2’を送り出すことで、支柱4,4の間に分割された橋梁2’を架設してもよく、また、各支柱4の上端部に、道路3の長手方向に沿ってレールを架設し、分割された橋梁2’をレール上で移動させて各支柱4に受け替えてもよく、道路3の上方空間を利用して分割された橋梁2’の架設を行うものであれば、その構成は限定されるものではない。   Here, in the bridge erection step, it is also possible to erection the divided bridge 2 ′ without using the crane K, for example, supported by a plurality of piers standing on both sides 3 ′ and 3 ′ of the road 3. By creating a bridge 2 'divided directly on the road 3 using the plate-like stage as a work place, and sending out the divided bridge 2' using a portal-type carriage placed on the road 3 from the stage, A bridge 2 'divided between 4 and 4 may be installed, and a rail is installed on the upper end of each column 4 along the longitudinal direction of the road 3, and the divided bridge 2' is railed. It may be moved up and replaced with each support column 4, and the configuration is not limited as long as the bridge 2 ′ divided using the upper space of the road 3 is constructed.

そして、(3)橋梁降下工程では、図3(b)に示すように、分割された橋梁2’を降下させ、支柱4毎に高さが定められた各支柱4の上端に固定することで橋梁2に斜路部を設け、橋梁2の両端部に摺付け部6を設置して道路3と接続する。
ここで、分割された橋梁2’の降下方法について説明する。分割された橋梁2’の降下は、図4(a)に示すように、油圧式昇降装置4eを備えた車両4dによって降下させる。まず、夜間等の交通の停止時間帯に既存の車両の通行を一時的に規制した状態で、道路3に車両4dを配置し、油圧式昇降装置4eによって分割された橋梁2’を支持する。次に、各支柱4から仮設柱5を撤去することで、分割された橋梁2’を油圧式昇降装置4eのみによって支持した後に、油圧式昇降装置4eを降下させることで、分割された橋梁2’を支柱4の上端部に受け替えて固定する。
Then, (3) in the bridge lowering step, as shown in FIG. 3 (b), the divided bridge 2 'is lowered and fixed to the upper end of each column 4 whose height is determined for each column 4. A ramp is provided on the bridge 2, and sliding portions 6 are installed on both ends of the bridge 2 to connect to the road 3.
Here, a method for lowering the divided bridge 2 'will be described. As shown in FIG. 4A, the divided bridge 2 ′ is lowered by a vehicle 4d provided with a hydraulic lifting device 4e. First, the vehicle 4d is arranged on the road 3 in a state where traffic of an existing vehicle is temporarily restricted during a traffic stoppage time such as at night, and the bridge 2 'divided by the hydraulic lifting device 4e is supported. Next, the temporary pillar 5 is removed from each support column 4 so that the divided bridge 2 ′ is supported only by the hydraulic lifting device 4 e, and then the hydraulic lifting device 4 e is lowered to separate the divided bridge 2. Replace 'with the upper end of the column 4 and fix it.

また、分割された橋梁2’の降下方法は、短時間に安定した状態で降下作業を行えるものであれば限定されるものではなく、例えば、図4(b)に示すように、支柱立設工程において、道路3の幅員方向において対となる支柱4,4の上端部に、クレーン等によって固定梁4aを設け、この固定梁4aの所定部に配置した油圧ジャッキ4bに支持された鋼棒4cによって、支柱4,4の内寸法よりも幅の狭い分割された橋梁2’を吊り下げることで、道路3の直上に橋梁2を仮保持する。次に、橋梁降下工程において、油圧ジャッキ4bによって鋼棒4cを降下させることで分割された橋梁2’を降下させ、所定位置で支柱4にブラケット等で固定し、橋梁2に斜路部を設ける方法もある。なお、固定梁4aは分割された橋梁2’の降下後に支柱4,4から撤去する。   Further, the method for lowering the divided bridge 2 'is not limited as long as it can perform the lowering work in a stable state in a short time. For example, as shown in FIG. In the process, a steel beam 4c supported by a hydraulic jack 4b provided at a predetermined portion of the fixed beam 4a is provided with a fixed beam 4a by a crane or the like at the upper end of the columns 4 and 4 which are paired in the width direction of the road 3. The bridge 2 is temporarily held immediately above the road 3 by suspending the divided bridge 2 ′ narrower than the internal dimensions of the columns 4 and 4. Next, in the bridge lowering process, the steel bridge 4c is lowered by the hydraulic jack 4b, and the divided bridge 2 'is lowered, fixed to the column 4 at a predetermined position with a bracket or the like, and the bridge 2 is provided with the ramp portion. There is also. The fixed beam 4a is removed from the columns 4 and 4 after the divided bridge 2 'is lowered.

さらに、橋梁架設工程において、クレーンKによって分割された橋梁2’を吊り下げた状態にしておくことで、仮設柱5を用いることなく、橋梁2を道路3の上方に仮保持した後に、クレーンKによって分割された橋梁2’を降下させて支柱4に固定する方法もある(図2(b)参照)。   Further, in the bridge erection process, the bridge 2 ′ divided by the crane K is kept in a suspended state so that the bridge 2 is temporarily held above the road 3 without using the temporary pillar 5, and then the crane K There is also a method in which the bridge 2 'divided by the above is lowered and fixed to the support column 4 (see FIG. 2B).

最後に、道路3の直上にある高架式道路1の路面7を使用して既存の車両の通行を確保する。   Finally, the road surface 7 of the elevated road 1 directly above the road 3 is used to ensure the passage of existing vehicles.

したがって、本発明の実施形態に係る高架式道路1では、既存の交通に対する影響を低減した状態で、道路3の上方に、高い安定性を有する高架式道路1を容易かつ短期間に構築することができる。   Therefore, in the elevated road 1 according to the embodiment of the present invention, the elevated road 1 having high stability can be easily and quickly built above the road 3 in a state where the influence on the existing traffic is reduced. Can do.

また、高架式道路1を構築する道路3の地盤が軟弱地盤である場合は、フーチングのみを支柱4の基礎とする構造では、高架式道路1が確実に安定しないため、地盤改良を行うとともに、フーチングに基礎杭を設ける必要がある。   In addition, when the ground of the road 3 that constructs the elevated road 1 is soft ground, in the structure in which only the footing is the foundation of the support column 4, the elevated road 1 is not reliably stabilized, so the ground is improved, It is necessary to install foundation piles in the footing.

以下、添付図面を参照して、基礎杭を設けた高架式道路の構築方法について説明する。
図7は基礎杭を設けた高架式道路の側面図である。図8は基礎杭を設けたフーチングを示した図で、(a)は図7のD−D断面図、(b)はフーチングの他の構成を示した平面図である。図9は基礎杭を設けた高架式道路を示した図で、図7のE−E断面図である。
Hereinafter, a method for constructing an elevated road provided with foundation piles will be described with reference to the accompanying drawings.
FIG. 7 is a side view of an elevated road provided with foundation piles. FIG. 8 is a view showing a footing provided with a foundation pile, where (a) is a sectional view taken along the line DD in FIG. 7, and (b) is a plan view showing another configuration of the footing. FIG. 9 is a view showing an elevated road provided with foundation piles, and is a cross-sectional view taken along line EE of FIG.

まず、支柱4を立設する道路の両側3’,3’を地盤改良する(図9参照)。この地盤改良の方法は、地盤の支持力を高めるものであれば、その方法は限定されるものではなく、軟弱地盤の土砂を良質材料に置き換える置換、地盤を締め固める高密度化及びセメント等を注入して混合する固結等があり、対象とする地盤に適した方法を用いることが好ましい。   First, the ground is improved on both sides 3 'and 3' of the road on which the column 4 is erected (see FIG. 9). This ground improvement method is not limited as long as it enhances the support capacity of the ground. Replacement of the soft ground with high quality materials, replacement of the ground with high density, cement, etc. It is preferable to use a method suitable for the target ground because there is consolidation such as injection and mixing.

次に、図7,図9に示すように、地盤改良した道路3の両側3’,3’の地中に基礎杭用フーチング40’及び繋ぎ梁41を埋設し、前記実施形態と同様の方法によって高架式道路1を構築する。
ここで、基礎杭用フーチング40’は、図8(a)に示すように、基礎杭43と接合する部分に鉄筋44が配筋されていない構造となっており、この部分に基礎杭43が嵌合可能な垂直孔45が貫通している。
Next, as shown in FIGS. 7 and 9, foundation pile footing 40 'and connecting beam 41 are embedded in the ground on both sides 3' and 3 'of the improved road 3, and the same method as in the above embodiment is used. The elevated road 1 is constructed by
Here, as shown in FIG. 8A, the foundation pile footing 40 ′ has a structure in which the reinforcing bar 44 is not arranged at a portion to be joined to the foundation pile 43, and the foundation pile 43 is disposed at this portion. The vertical hole 45 which can be fitted is penetrated.

次に、高架式道路1を基礎杭用フーチング40’のみによって支持した状態で使用し、既存の車両30の通行を確保する。
最後に、図9に示すように、各支柱4が立設している基礎杭用フーチング40’の垂直孔45を貫通して地中に基礎杭43を打設し、基礎杭43の上端部と基礎杭用フーチング40’を接合する。このとき、基礎杭用フーチング40’には基礎杭43が嵌合する垂直孔45が設けられているため、基礎杭43を基礎杭用フーチング40’の上方から地中に容易に打設することができる。
Next, the elevated road 1 is used in a state of being supported only by the footing 40 ′ for the foundation pile, and the passage of the existing vehicle 30 is ensured.
Finally, as shown in FIG. 9, a foundation pile 43 is driven through the vertical hole 45 of the foundation pile footing 40 ′ in which each support column 4 is erected, and an upper end portion of the foundation pile 43. And foundation pile footing 40 '. At this time, since the foundation pile footing 40 'is provided with the vertical hole 45 into which the foundation pile 43 is fitted, the foundation pile 43 can be easily driven into the ground from above the foundation pile footing 40'. Can do.

ここで、フーチングの構成は、図8(b)に示すように、フーチング40だけを予め設け、このフーチング40に支柱4を立設して高架式道路1を構築し、車両の通行を確保した後に、基礎杭用フーチング46を接合して基礎杭43を設ける構成もあり、この構成では、フーチング40がより小型化されるため、支柱立設工程においてフーチング40を埋設する際の施工範囲をより縮小することができる。   Here, as shown in FIG. 8 (b), the footing is configured by providing only the footing 40 in advance, and the post 4 is erected on the footing 40 to construct the elevated road 1, thereby ensuring the passage of the vehicle. There is also a configuration in which the foundation pile 43 is provided by joining the foundation pile footing 46 later. In this configuration, since the footing 40 is further downsized, the construction range when embedding the footing 40 in the column erecting process is further increased. Can be reduced.

したがって、高架式道路1の路面の直下で、高架式道路1に車両を通行させながら基礎杭43を設けるため、既存の交通に影響を与えることなく、高架式道路1に容易かつ短期間に基礎杭43を設けることができる。
なお、基礎杭43は容易かつ短期間に設けることができるため、橋梁降下工程の前に、既存の車両30の通行を一時的に規制して施工してもよい。
Therefore, since the foundation pile 43 is provided directly under the road surface of the elevated road 1 while passing the vehicle through the elevated road 1, the foundation can be easily and quickly installed on the elevated road 1 without affecting the existing traffic. A pile 43 can be provided.
In addition, since the foundation pile 43 can be provided easily and in a short period of time, the passage of the existing vehicle 30 may be temporarily restricted before the bridge descent process.

以上、本発明について、好適な実施形態についての一例を説明したが、本発明は当該実施形態に限られず、本発明の趣旨を逸脱しない範囲で適宜設計変更が可能である。   As mentioned above, although an example about a suitable embodiment was explained about the present invention, the present invention is not restricted to the embodiment concerned, and a design change is possible suitably in the range which does not deviate from the meaning of the present invention.

本発明の実施形態に係る支柱立設工程を示した図で、(a)は支柱を立設した際を示す側面図、(b)は支柱を立設した際を示す平面図である。It is the figure which showed the support | pillar standing-up process which concerns on embodiment of this invention, (a) is a side view which shows the time of standing upright, and (b) is a top view which shows the time of standing upright. 本発明の実施形態に係る橋梁架設工程を示した図で、(a)は橋梁を架設した際を示す側断面図、(b)はA−A断面図である。It is the figure which showed the bridge construction process which concerns on embodiment of this invention, (a) is a sectional side view which shows the time of constructing a bridge, (b) is AA sectional drawing. 本発明の実施形態に係る橋梁降下工程を示した図で、(a)は橋梁の側面図、(b)は橋梁を降下した際を示す側面図である。It is the figure which showed the bridge lowering process which concerns on embodiment of this invention, (a) is a side view of a bridge, (b) is a side view which shows the time of dropping a bridge. 本発明の実施形態に係る橋梁降下工程を示した図で、(a)は図3(b)のB−B断面図、(b)は橋梁降下工程の他の例を示した正面断面図である。It is the figure which showed the bridge lowering process which concerns on embodiment of this invention, (a) is BB sectional drawing of FIG.3 (b), (b) is front sectional drawing which showed the other example of the bridge lowering process. is there. 本発明の実施形態に係る橋梁降下工程を示した図で、図3(b)のC−C断面図である。It is the figure which showed the bridge lowering process which concerns on embodiment of this invention, and is CC sectional drawing of FIG.3 (b). 繋ぎ梁の他の構成を示した図で、(a)は道路の幅員方向のみに繋ぎ梁を設けた構成の平面図、(b)は道路の長手方向及び幅員方向に繋ぎ梁を設けた構成の平面図である。It is the figure which showed the other structure of a connecting beam, (a) is a top view of the structure which provided the connecting beam only in the width direction of the road, (b) is the structure which provided the connecting beam in the longitudinal direction and the width direction of the road FIG. 基礎杭を設けた高架式道路の側面図である。It is a side view of an elevated road provided with foundation piles. 基礎杭を設けたフーチングを示した図で、(a)は図7のD−D断面図、(b)はフーチングの他の構成を示した平面図である。It is the figure which showed the footing which provided the foundation pile, (a) is DD sectional drawing of FIG. 7, (b) is the top view which showed the other structure of the footing. 基礎杭を設けた高架式道路を示した図で、図7のE−E断面図である。It is the figure which showed the elevated road which provided the foundation pile, and is EE sectional drawing of FIG.

符号の説明Explanation of symbols

1 高架式道路
2 橋梁
2’ 分割された橋梁
3 道路
4 支柱
30 車両
40 基礎杭用フーチング
41 繋ぎ梁
42 PC鋼材
43 基礎杭
DESCRIPTION OF SYMBOLS 1 Elevated road 2 Bridge 2 'Divided bridge 3 Road 4 Post 30 Vehicle 40 Foundation pile footing 41 Connecting beam 42 PC steel 43 Foundation pile

Claims (2)

既存の交通路に沿って所定の間隔をあけて埋設された複数のプレキャスト部材であるフーチングと、
前記各フーチングに立設されている複数の支柱と、
前記支柱間に架設されている複数の分割された橋梁からなり、前記既存の交通路と接続するようにして斜路が形成されている橋梁と、から構成され、
前記フーチングには、基礎杭を嵌合可能な貫通孔を有するプレキャスト部材である基礎杭用フーチングが接合されており、前記基礎杭用フーチングの前記貫通孔には、前記基礎杭が接合され
前記フーチング同士の間には、プレキャスト部材である繋ぎ梁が設けられていることを特徴とする高架式交通路。
A footing that is a plurality of precast members embedded at predetermined intervals along an existing traffic route,
A plurality of struts erected on each footing;
It is composed of a plurality of divided bridges erected between the columns, and a bridge in which a ramp is formed so as to connect to the existing traffic road,
The footing for a foundation pile which is a precast member having a through hole into which the foundation pile can be fitted is joined to the footing, and the foundation pile is joined to the through hole of the footing for the foundation pile ,
An elevated traffic road characterized in that a connecting beam, which is a precast member, is provided between the footings .
前記繋ぎ梁に貫通させたPC鋼材の両端部を前記フーチングに定着させて緊張力を付加することにより、前記フーチングと前記繋ぎ梁が一体化されていることを特徴とする請求項に記載の高架式交通路。 By adding the tension by the opposite ends is fixed to the footing of the PC steel material is passed through the connecting crossbeams, according to claim 1, characterized in that the tie beam and the footing are integrated Elevated traffic route.
JP2004250240A 2004-08-30 2004-08-30 Elevated traffic route Expired - Fee Related JP3779978B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004250240A JP3779978B2 (en) 2004-08-30 2004-08-30 Elevated traffic route

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004250240A JP3779978B2 (en) 2004-08-30 2004-08-30 Elevated traffic route

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2001219521A Division JP3616587B2 (en) 2001-07-19 2001-07-19 Construction method of elevated traffic route

Publications (2)

Publication Number Publication Date
JP2005009309A JP2005009309A (en) 2005-01-13
JP3779978B2 true JP3779978B2 (en) 2006-05-31

Family

ID=34101469

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004250240A Expired - Fee Related JP3779978B2 (en) 2004-08-30 2004-08-30 Elevated traffic route

Country Status (1)

Country Link
JP (1) JP3779978B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2936215C (en) * 2016-02-12 2017-01-03 Grade Separation Systems Inc. Construction methods and systems for grade separation structures
JP7128094B2 (en) * 2018-11-22 2022-08-30 株式会社竹中工務店 Construction method of foundation structure

Also Published As

Publication number Publication date
JP2005009309A (en) 2005-01-13

Similar Documents

Publication Publication Date Title
US8006339B1 (en) Prefabricated articulating pier cap
JP5045214B2 (en) Column head construction method
JP2004278148A (en) Construction method of bridge
JP3443739B2 (en) Foundation construction method, footing foundation and foundation structure of elevated traffic route
JP4343606B2 (en) Bridge construction method
JP3851539B2 (en) Block-type traffic roads, split-bridge-type traffic roads, and bridge traffic roads
KR101187282B1 (en) Railway bridge constructing method using 2 post type abutment structure
JP4685341B2 (en) Viaduct construction method
JP3779978B2 (en) Elevated traffic route
JP3616587B2 (en) Construction method of elevated traffic route
JP4477467B2 (en) Bridge structure and its replacement method
JP4196267B2 (en) Construction method of multilevel intersection road
JP4422978B2 (en) Steel shell for footing foundation, bridge structure, bridge construction method, and three-dimensional intersection bridge construction method
JP3682247B2 (en) Construction method of elevated traffic route
JP4047660B2 (en) Elevated traffic road foundation structure and elevated traffic road
JP3854545B2 (en) Box-type transportation
JP3895339B2 (en) Approach structure of multilevel crossover bridge and its construction method
JP4263935B2 (en) Construction method and elevated detour
JP2004300914A (en) Structure of bridge pier
JP4094416B2 (en) Construction method of multilevel intersection
JP2003003420A (en) Supporting member for prefabricated bridge
JP2536376B2 (en) Foundation structure of shed for road protection
JP2004278230A (en) Method of constructing grade separation of roads, and pier connection structure
JP3619515B2 (en) Split-bridge type traffic road and method for constructing split-bridge type traffic road
JP2007291801A (en) Elevated road structure and its construction method

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20051207

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060116

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060222

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060303

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090310

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100310

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110310

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110310

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120310

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130310

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140310

Year of fee payment: 8

LAPS Cancellation because of no payment of annual fees