JP3771816B2 - Method for forming openings in sabo dams - Google Patents

Method for forming openings in sabo dams Download PDF

Info

Publication number
JP3771816B2
JP3771816B2 JP2001170764A JP2001170764A JP3771816B2 JP 3771816 B2 JP3771816 B2 JP 3771816B2 JP 2001170764 A JP2001170764 A JP 2001170764A JP 2001170764 A JP2001170764 A JP 2001170764A JP 3771816 B2 JP3771816 B2 JP 3771816B2
Authority
JP
Japan
Prior art keywords
opening
dam
block
forming
sabo
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2001170764A
Other languages
Japanese (ja)
Other versions
JP2002363951A (en
Inventor
公 西尾
Original Assignee
コンクリートコーリング株式会社
國井建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by コンクリートコーリング株式会社, 國井建設株式会社 filed Critical コンクリートコーリング株式会社
Priority to JP2001170764A priority Critical patent/JP3771816B2/en
Publication of JP2002363951A publication Critical patent/JP2002363951A/en
Application granted granted Critical
Publication of JP3771816B2 publication Critical patent/JP3771816B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、砂防ダムにおける開口部の形成方法に関し、特に、既存の砂防ダムで内部に土砂が堆積している場合に、周辺に悪影響を及ぼすことなく開口部を形成する方法に関するものである。
【0002】
【従来の技術】
砂防ダムの本来の目的は、鉄砲水などの急激な出水に伴う土砂流出を防止し、土石流災害などから河川の流域沿線を保護するためのものである。
【0003】
ところが、最近では護岸などの発達により、砂防ダムの重要性が低下していて、ダム上流に堆積した土砂などによって、砂防ダムとしての機能が自由分に発揮されないものや、ヘドロ状の腐葉土の堆積による下流側の水質汚染や汚濁など、却ってその存在が環境に悪影響を及す場合などもある。
【0004】
一方、最近では河川を淡水魚育成のための資源として見直す傾向にあるが、前述のごとき既存の砂防ダムを放置したままであると、今度は回遊性淡水魚の遡上障害となる。
【0005】
そこで、河川流域漁業の振興およびこれに伴う漁獲量増産や、上流に作られる養魚場施設のためなどに、既存の砂防ダムに魚道用開口部を開けて、淡水魚類の遡上を可能にする方策が採られるようになってきた。
【0006】
しかしながら、既存の砂防ダムに土砂が堆積している状態で魚道用開口部を形成する際には、以下に説明する課題があった。
【0007】
【発明が解決しようとする課題】
すなわち、既存の砂防ダムにおいて、上流側に堆積された土砂をそのままの状態として開口部を形成してしまうと、一度に多量の堆積土砂が下流側に流れ、濁水の原因となるだけでなく、下流域における鱒、鮎などの漁業資源に大きな影響を与え、漁獲量の激減による漁業補償の問題などが起こる。
この発明は、このような問題を解決するためになされたもので、その目的とするところは、砂防ダムに溜った堆積土砂の下流側へ流出を避けつつ必要な開口部を形成することができる砂防ダムにおける開口部の形成方法を提供することにある。
【0008】
【課題を解決するための手段】
前記目的を達成するため、本発明は、既存の砂防ダムの上流側に堆積した土砂を浚渫する第1工程と、ワイヤソーなどの切断手段により前記砂防ダムのダム堤体を前記浚渫後の堆積土砂表面より上の位置に至る深さまで切込んで矩形状切断ブロックを形成する第2工程と、前記矩形状切断ブロックをジャッキアップして、当該矩形状切断ブロックの下部に、前記ダム堤体を貫通する水抜き開口部を設け、この水抜き開口部より水を放流し、前記砂防ダム内の水位を低下させる第3工程と、前記矩形状切断ブロックを除去して、前記ダム堤体に部分開口部を形成する第4工程とを含み、前記第1から第4工程を順次繰り返すことにより、前記ダム堤体に所定の長さの開口部を形成するようにした。
【0009】
このように構成した本発明にかかる開口部の形成方法によれば、土砂の浚渫を行った後に、その上部側の水抜き開口部から水を放流し、さらに、浚渫と放流とを繰り返えして、部分開口部を下方に延長して、ダム堤体に所定の長さの開口部を形成するので、砂防ダムに堆積している土砂の下流側への流出を避けつつ、必要な開口部を形成することができる。
【0010】
本発明の場合、前記矩形状切断ブロックは、斜め分割線により、先細テーパ状のブロックと、逆テーパ状のブロックとの2ブロックに分断され、これらのブロックを交互にジャッキアップすることができる。
【0011】
この構成によれば、矩形状切断ブロックの競り合いを回避しつつ、円滑にジャッキアップすることができる。
【0012】
また、本発明の場合、前記ダム堤体と前記矩形状ブロックとの間に相互に跨る一対のガイド孔を、前記ダム堤体のほぼ垂直方向に穿設し、前記ブロックをジャッキアップする際のガイド用のガイドロッドを、各ガイド孔内に挿入することができる。
【0013】
この構成によれば、水流の圧力に抗して、ブロックを円滑にジャッキアップすることができる。
【0014】
さらに、本発明の場合、前記開口部は、前記ダム堤体に所定の間隔を隔てて、3箇所以上設けられ、一方側の2箇所に前記部分開口部を形成した後、残る1個所以上の開口部の予定位置周縁を仮締切りし、前記部分開口部の下方に形成した前記水抜き開口部から水を放流しつつ、残る1個所以上の開口部の形成予定位置をドライ状態にして、この開口部の形成予定個所に、前記部分開口部を設けることなく、所定の長さの開口部を形成することができる。
【0015】
【発明の実施の形態】
以下、本発明の好ましい実施の形態について添付図面を参照して詳細に説明する。図1〜図8は本発明にかかる砂防ダムにおける開口部の形成方法の一実施例を示している。
【0016】
これらの図に示した開口部の形成方法は、既存砂防ダムに魚道用の開口部を形成する際に本発明を適用した場合であり、各図には、いずれも正面図とそのA−A線、B−B線における断面を示している。
【0017】
本実施例の開口部の形成方法は、
▲1▼.既存の砂防ダム1の上流側に堆積した土砂5を浚渫する第1工程と、
▲2▼.ワイヤソーなどの切断手段により砂防ダム1のダム堤体を浚渫後の堆積土砂5の表面より上の位置に至る深さまで切込んで矩形状切断ブロックBを形成する第2工程と、
▲3▼.矩形状切断ブロックBをジャッキアップして、当該矩形状切断ブロックB]の下部に、ダム堤体1を貫通する水抜き開口部Oを設け、この水抜き開口部Oより水を放流し、砂防ダム1内の水位を低下させる第3工程と、
▲4▼.矩形状切断ブロックBを除去して、ダム堤体1に部分開口部S1を形成する第4工程とを含み、
▲5▼.これらの第1から第4工程を順次繰り返すことにより、部分開口部S1を順次下方に延長して、ダム堤体1に所定の長さの開口部Sを形成することを基本構成としている。
【0018】
本実施例で開口部Sを形成しようとしている既存の砂防ダムは、図1に示すように、砂防ダム1の堤体が、中央に凹部が設けられたコンクリート製ダムであって、その中央下部にはやや大形の水抜き孔2および、その左右上下に小型の水抜き孔3、4が貫通形成され、角落し式のゲートなどにより、各水抜き孔2〜4を閉塞した構造になっている。
【0019】
なお、図中符号(R)は右岸を、(L)は左岸を示す。また、破線で示す部分は、魚道用開口部Sの形成予定箇所を示し、これらの開口部Sは、各水抜き孔2、3、4の形成位置を通過して、その下方に到達するように、合計3カ所に形成する。
【0020】
この既存砂防ダム1の施工前の状態を説明すると、当該ダム1の上流側には、概略ダム1の高さ分の土砂5が堆積し、水面WLはダム1の中央部より若干高くなっていて、堤体1を溢流して下流側に放流されている。
【0021】
この状態で、先ず各水抜き孔2,3,4を閉塞した状態で、上流側に堆積した土砂5をクラムシェルなどにより、所定の深さ位置まで土砂5を浚渫排除する(第1工程)。
【0022】
このとき、左岸側では、ダム1の近傍まで浚渫し、その後、左岸上流側の堆積土砂5上に盛土6を施して足場を確保した上で、資材揚重と浚渫作業などを兼用するクローラクレーン7を盛土6の上部側に設置する。
【0023】
次に、図2に示すように、予め地組みされた作業架台8を、中央および左岸(L)側のスリット形成予定位置上部にクレーン7で吊上げて設置する。
【0024】
また、このとき左岸(L)側の上部水抜き孔3は鉄板などで閉塞する。さらに、左岸側にはブラケット足場9を複数段仮設する。次いで、作業架台8上にワイヤソー駆動装置10を設置する。
【0025】
そして、図3に示すように、スリット形成予定位置に、ダム1をほぼ水平に貫通するようなワイヤー通し孔を開口した後、ワイヤソーWをこれら通し孔およびワイヤソー駆動装置10間に掛け回し、ガイドによる左右両側および中央の鉛直切断と底部の水平切断を行い、矩形状切断ブロックBを形成する(第2工程)。このときの切断深さは、浚渫された堆積土砂5の地表面ELの若干上での水中切断が可能となる位置に設定する。
【0026】
また、この作業と平行して切断ブロックBのジャッキアップ用のアンカー鋼棒11を、1ブロックに対して8本用意し、これらのアンカー鋼棒11を各矩形状切断ブロックBにそれぞれに挿通固定する。
【0027】
次に、図4に示すように、作業架台8上にアンカー鋼棒11に連結するジャッキ12を配置し、切断ブロックBをジャッキアップすることにより、矩形状切断ブロックBの下部に、水位低下用の水抜き開口部Oをあけ、この水抜き開口部Oよりダム1内の水を放流し、ダム1内の背面水位を徐々に低下させる(第3工程)。
【0028】
なお、この場合、水抜き開口部Oの断面積面積を大きくして、一度に開けると放流時に土砂を巻込んで濁水が発生するため、清流状態を保つべく、その開口度合をジャッキアップのリフト量により調整しながら放流する。
【0029】
また、矩形状切断ブロックBの切断形状と、そのジャッキアップの詳細手順については後述する。矩形状切断ブロックBを引上げた状態で、そのまま保持し、ダム1の水位が低下したなら、図5に示すように、上流部の堆積土砂5をさらに浚渫し、この作業が完了したのなら、水抜き孔2、および4のゲートをあけ、さらに水位WLを低下させる。
【0030】
なお、本実施例の場合には、水抜き孔2が存在しているので、このような処置ができるが、水抜き孔2がない場合には、この工程は、必要としない。このようにして、ダム1内の水位が低下すると、その後、浚渫された土砂5の斜面に土嚢15を積んでその流出を阻止する。
【0031】
その後は、矩形状切断ブロックBをジャッキダウンし、さらに切り分けて細分化し、クレーン6で順次吊上げ撤去することで、図6に示すように、中央および左岸(L)側の部分開口部S1が形成される。この場合、矩形状切断ブロックBは、ジャッキダウンすることなく、そのまま上方にジッャキアップして除去することもできる(第4工程)。
また、この作業と平行して右岸(R)を浚渫し、浚渫完了後はドライ作業により、前記と同様なワイヤソーWを用いた切断作業により順次切断しながら、この部分には、部分開口部S1を形成することなく、一度に所定長さの矩形状切断ブロックを形成し、これを除去することにより所定長さの開口部Sを完成させる。
【0032】
次に図7に示すように、右岸(R)の仮締切りを撤去し、左岸(L)に土嚢15を積んで仮締切りし、ドライ作業により、左岸側の部分開口部S1の下方に、連続して残りの部分を、前記と同様な作業手順により順次切断撤去して完全な長さの開口部Sを完成させる。
【0033】
最後は、図8に示すように、中央を土嚢15で仮締切りして左右の開口部Sから水を流し、ドライ作業により、中央部分の部分開口部S1の下方に、連続して残りの部分を、前記と同様な作業手順により順次切断撤去して完全な長さの開口部Sを完成させる。
【0034】
図9は以上の砂防ダム1の完成状態を示すもので、ダム1の上流側と下流側水位WLの落差は、開口部Sの底面高さに応じて極めて低いものとなり、魚類の遡上の妨げとならない程度の高さとなる。なお、図においては、開口部Sの底面は、下流側に向く傾斜勾配としているが、前記各開口部Sの底面を仕上げる段階で階段状の段差を設けても良い。
【0035】
次に、前述した矩形状切断ブロックBの切断形状、および、矩形状切断ブロックBの詳細なジャッキアップ手順を図10に基づいて説明する。
【0036】
図10(a)は、ワイヤソーWにより切断が完了した状態の矩形状切断ブロックBの上面図と側面図とを示している。本実施例の場合、矩形状切断ブロックBは、左右の切断ブロックB1,B2に分断されている。
【0037】
各ブロックB1,B2の垂直切断線L1と水平切断線L2との交点および中央の分割線L3と水平切断線L2の交点には、それぞれ予めワイヤソーWの通し孔SHが、堤体1を貫通するように穿設されている。
【0038】
分割線L3は、垂直でなく、斜めに形成され、これによって左側ブロックB1を先細りのテーパ形状とし、右側ブロックB2を逆テーパとし、切断後のジャッキアップ作業の容易性を確保している。
【0039】
また、両側の垂直切断線L1のほほ中央位置には、ダム1の堤体厚みの中央部分に位置するようにして、一対の円形のガイド孔GHがほぼ垂直に穿設されている。
【0040】
このガイド孔GHは、ダム1の堤体と、切断線L,L2で堤体から離間された矩形状切断ブロックBの左,右側ブロックB1,B2間に跨るように形成され、各ガイド孔GHには、ジャッキアップする際のガイド用のガイドロッド14が挿入されている。
【0041】
ジャッキアップ用のアンカー鋼棒11は、各ブロックB1,B2の四隅に4本ずつ埋設設置されている。このような矩形状切断ブロックBをジャッキアップする際には、以下の手順で行われる。
【0042】
すなわち、先ず、先細りのテーパ形状となっている左側ブロックB1を、アンカー鋼棒11を介して、図示省略のジャッキにより、図10(b)に示すごとく、上方に引上げる。そして、この左側ブロックB1をある程度引上げたら、この位置に保持する。
【0043】
この状態では、図10(c)に示すごとく、右側ブロックB2の引上げが可能となり、今度は、右側ブロックB2を、アンカー鋼棒11を介して、図示省略のジャッキにより、上方に引上げる。
【0044】
この時、右側ブロックB1は、左側ブロックB1と同じ位置まで引き上げ、その位置に保持する。このような交互ジャッキアップ操作を繰返し行うことにより、両ブロックB1,B2の引上げ作業が可能となり、その下部に所定の放流用の水抜き開口部Oを形成することができる。
【0045】
本実施例で、矩形状切断ブロックBを、先細りのテーパ形状と逆テーパ形状とに斜めの分割線L3で分断するのは、以下の理由による。すなわち、ワイヤソーにより切断線L,L2を形成して、矩形状のままでこれを上方に引上げようとすると、ワイヤソーWにより形成される切断線L,L2は、その幅が十数mm程度で、比較的小さく、しかも、切削の進行に伴って、その幅が狭くなり、さらに、切削抵抗などの関係で、正確に垂直に形成することが難しいので、引上げる際に、切断面が競り合って、その引き上げが非常に困難になり、殆ど不可能になる。
【0046】
ところが、矩形状切断ブロックBを先細りのテーパ形状と逆テーパ形状とに斜めの分割線L3で分断すると、先細りテーパ形状のブロックB1を先に引き上げ、その後、交互にジャッキアップ操作を繰返してブロックB1,B2の引上げ作業を行うと、このような競り合いがなく円滑に引上げることができる。
【0047】
この場合、左,右側ブロックB1,B2間に跨るように形成された各ガイド孔GHには、ガイドロッド14が挿入されているので、各ブロックB1,B2のジッャキアップが円滑に行える。
【0048】
また、矩形状切断ブロックBを上方に引上げる際には、ダム1内の水が下流側に流れようとして、これに伴う水圧が作用するが、この場合に、左,右側ブロックB1,B2間に跨るように形成された各ガイド孔GHには、ガイドロッド14が挿入されているので、この水圧に対抗して、各ブロックB1,B2を所定の位置および状態に保持することができ、その結果、容易に引上げ作業を行うことができる。
【0049】
なお、上記実施例では、矩形状切断ブロックBを形成する切断手段として、ワイヤソーWを例示したが、本発明の実施は、これに限定されることはなく、例えば、円板状の刃物を用いる切断手段でもよく、また、これらを併用する切断手段であってもよい。
【0050】
また、上記実施例では、2回の工程の繰り返しで、所定長さの開口部Sを形成する場合を例示したが、本発明の実施は、これに限定されることはなく、これ以上の回数を繰り返してもよい。
【0051】
【発明の効果】
以上説明したように、本発明方法では、堆積土砂の下流側への流出を防止しつつ魚道用開口部を形成することができるため、土砂流出による下流側への影響を未然に防止できる。
【図面の簡単な説明】
【図1】本発明方法の最初の工程を示す説明図である。
【図2】図1に引続く次の工程を示す説明図である。
【図3】同次の工程を示す説明図である。
【図4】同次の工程を示す説明図である。
【図5】同次の工程を示す説明図である。
【図6】同次の工程を示す説明図である。
【図7】同次の工程を示す説明図である。
【図8】同最終工程を示す説明図である。
【図9】施工完成状態を示す斜視図である。
【図10】(a)〜(c)は切断ブロックの切断形状および引上げ手順を示す説明図である。
【符号の説明】
1 砂防ダム
5 堆積土砂
7 クローラクレーン
WL 水面
8 作業架台
10 ワイヤソー駆動装置
12 ジャッキ
W ワイヤソー
S1 部分開口部
S 開口部
B 矩形状切断ブロック
B1,B2 切断ブロック
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for forming an opening in a sabo dam, and more particularly, to a method for forming an opening without adversely affecting the periphery when soil is accumulated inside an existing sabo dam.
[0002]
[Prior art]
The original purpose of the sabo dam is to prevent sediment runoff due to sudden flooding such as flash floods, and to protect the river basin along the debris flow disaster.
[0003]
Recently, however, the importance of sabo dams has declined due to the development of revetments, etc., and sediments accumulated in the upstream of the dam cannot function freely as sabo dams, or deposits of sludge humus In some cases, such as downstream water pollution or pollution caused by sewage, its presence may adversely affect the environment.
[0004]
On the other hand, rivers tend to be reviewed as a resource for breeding freshwater fish recently. However, if the existing sabo dam is left untouched as described above, it will become an obstacle to the migration of migratory freshwater fish.
[0005]
Therefore, for the promotion of river basin fisheries and the accompanying increase in catch production and for fish farm facilities constructed upstream, opening of fishway openings in existing sabo dams will enable freshwater fish to run up. Measures have come to be taken.
[0006]
However, when forming an opening for a fishway with earth and sand accumulating on an existing sabo dam, there are problems described below.
[0007]
[Problems to be solved by the invention]
That is, in the existing sabo dam, if the opening is formed with the sediment deposited on the upstream side as it is, not only does a large amount of sediment sediment flow to the downstream side, causing turbid water, The fishery resources such as salmon and carp in the downstream area will be greatly affected, and fishery compensation problems will occur due to the drastic decrease in catch.
The present invention has been made to solve such a problem, and the object of the present invention is to form a necessary opening while avoiding the outflow of the sediment accumulated in the sabo dam to the downstream side. It is providing the formation method of the opening part in a sabo dam.
[0008]
[Means for Solving the Problems]
In order to achieve the above object, the present invention provides a first step of dredging sediment deposited on the upstream side of an existing sabo dam, and a dam dam body of the sabo dam by a cutting means such as a wire saw to deposit sediment after the dredging. A second step in which a rectangular cutting block is formed by cutting to a depth reaching a position above the surface; and the rectangular cutting block is jacked up, and the dam dam body is penetrated under the rectangular cutting block. A third step of providing a drain opening to discharge water from the drain opening to lower the water level in the sabo dam, removing the rectangular cutting block, and partially opening the dam dam body A fourth step of forming a section, and by sequentially repeating the first to fourth steps, an opening having a predetermined length is formed in the dam dam body.
[0009]
According to the method of forming an opening according to the present invention configured as described above, after dredging earth and sand, water is discharged from the drain opening on the upper side, and further, dredging and discharging are repeated. Since the opening of a predetermined length is formed in the dam body by extending the partial opening downward, the necessary opening while avoiding the outflow of earth and sand accumulated in the sabo dam to the downstream side The part can be formed.
[0010]
In the case of the present invention, the rectangular cutting block is divided into two blocks of a tapered taper block and an inverse taper block by an oblique dividing line, and these blocks can be jacked up alternately.
[0011]
According to this configuration, it is possible to smoothly jack up while avoiding the competition of the rectangular cutting blocks.
[0012]
Further, in the case of the present invention, a pair of guide holes straddling each other between the dam dam body and the rectangular block are formed in a substantially vertical direction of the dam dam body, and the block is jacked up. A guide rod for guide can be inserted into each guide hole.
[0013]
According to this configuration, the block can be jacked up smoothly against the pressure of the water flow.
[0014]
Furthermore, in the case of the present invention, the opening is provided at three or more locations at a predetermined interval in the dam dam body, and after the partial opening is formed at two locations on one side, the remaining one or more locations are provided. Temporarily cut off the peripheral edge of the predetermined position of the opening, and while discharging water from the drain opening formed below the partial opening, the formation planned position of the remaining one or more openings is made dry. An opening having a predetermined length can be formed without providing the partial opening at a position where the opening is to be formed.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. 1-8 has shown one Example of the formation method of the opening part in the sabo dam concerning this invention.
[0016]
The formation method of the opening part shown in these figures is a case where this invention is applied when forming the opening part for fishway in the existing sabo dam, and each figure is a front view and its AA in each figure. The cross section in a line and a BB line is shown.
[0017]
The method of forming the opening of this example is as follows:
(1). A first step of dredging sediment 5 deposited on the upstream side of the existing sabo dam 1;
(2). A second step of forming a rectangular cutting block B by cutting the dam body of the sabo dam 1 to a depth reaching a position above the surface of the sediment earth 5 after dredging by cutting means such as a wire saw;
(3). The rectangular cutting block B is jacked up, and a drain opening O penetrating the dam dam body 1 is provided at the lower part of the rectangular cutting block B], and water is discharged from the drain opening O to prevent sabo. A third step of lowering the water level in the dam 1,
(4) including a fourth step of removing the rectangular cutting block B and forming the partial opening S1 in the dam body 1;
(5). By repeating these first to fourth steps sequentially, the basic configuration is to form the opening S having a predetermined length in the dam dam body 1 by sequentially extending the partial opening S1 downward.
[0018]
As shown in FIG. 1, the existing sabo dam which is intended to form the opening S in this embodiment is a concrete dam in which a dam body of the sabo dam 1 is provided with a recess in the center, and a lower center portion thereof. Slightly large drainage holes 2 and small drainage holes 3 and 4 are formed in the left and right and top and bottom of the drainage holes 2, and each drainage hole 2 to 4 is closed by a corner-dropping gate or the like. ing.
[0019]
In the figure, symbol (R) indicates the right bank and (L) indicates the left bank. Moreover, the part shown with a broken line shows the formation planned location of the opening part S for fishways, and these opening parts S pass through the formation position of each drain hole 2, 3, and 4 so that it may reach below it. And a total of three locations.
[0020]
The state before construction of the existing sabo dam 1 will be described. On the upstream side of the dam 1, the earth and sand 5 approximately the height of the dam 1 is deposited, and the water surface WL is slightly higher than the central portion of the dam 1. The levee body 1 overflows and is discharged downstream.
[0021]
In this state, first, the drainage holes 2, 3 and 4 are closed, and the sediment 5 accumulated on the upstream side is removed to a predetermined depth position by a clamshell or the like (first step). .
[0022]
At this time, on the left bank side, crawling up to the vicinity of the dam 1 and then applying the embankment 6 on the sedimentary sand 5 upstream of the left bank to secure a scaffold, and then crawler crane that combines material lifting and dredging work etc. 7 is installed on the upper side of the embankment 6.
[0023]
Next, as shown in FIG. 2, a prefabricated work platform 8 is installed by being lifted by a crane 7 above the planned slit formation position on the center and left bank (L) side.
[0024]
At this time, the upper drain hole 3 on the left bank (L) side is closed with an iron plate or the like. Further, a plurality of bracket scaffolds 9 are temporarily installed on the left bank side. Next, the wire saw driving device 10 is installed on the work platform 8.
[0025]
Then, as shown in FIG. 3, after opening a wire through hole penetrating the dam 1 almost horizontally at the slit formation scheduled position, the wire saw W is hung between the through hole and the wire saw driving device 10 and guided. The left and right sides and the center are cut vertically and the bottom is cut horizontally to form a rectangular cutting block B (second step). The cutting depth at this time is set at a position where underwater cutting is possible slightly above the ground surface EL of the laid sedimentary sand 5.
[0026]
In parallel with this operation, eight anchor steel bars 11 for jacking up the cutting block B are prepared for each block, and these anchoring steel bars 11 are inserted and fixed to the rectangular cutting blocks B, respectively. To do.
[0027]
Next, as shown in FIG. 4, the jack 12 connected to the anchor steel bar 11 is arranged on the work platform 8, and the cutting block B is jacked up, so that the water level lowering portion is formed below the rectangular cutting block B. The water drain opening O is opened, the water in the dam 1 is discharged from the water drain opening O, and the back water level in the dam 1 is gradually lowered (third step).
[0028]
In this case, if the cross-sectional area of the drainage opening O is increased, and if it is opened at once, dirt and sand will be entrained at the time of discharge and turbid water will be generated. Discharge while adjusting the amount.
[0029]
The cutting shape of the rectangular cutting block B and the detailed procedure for jacking up will be described later. If the rectangular cutting block B is pulled up and held as it is, and the water level of the dam 1 is lowered, as shown in FIG. The gates of the drain holes 2 and 4 are opened, and the water level WL is further lowered.
[0030]
In the case of the present embodiment, since the drain hole 2 exists, such a treatment can be performed. However, when there is no drain hole 2, this step is not necessary. Thus, when the water level in the dam 1 falls, the sandbag 15 is piled on the slope of the dredged earth and sand 5 and the outflow is blocked | prevented.
[0031]
Thereafter, the rectangular cutting block B is jacked down, further cut and subdivided, and then lifted and removed sequentially by the crane 6 to form a partial opening S1 on the center and left bank (L) side as shown in FIG. Is done. In this case, the rectangular cutting block B can be removed by jacking up as it is without jacking down (fourth step).
Further, in parallel with this work, the right bank (R) is beaten, and after the dredging is completed, a dry work is performed, and a cutting work using the wire saw W similar to the above is sequentially performed. Without forming the rectangular cut block, a rectangular cutting block having a predetermined length is formed at a time, and the opening S having a predetermined length is completed by removing the rectangular cutting block.
[0032]
Next, as shown in FIG. 7, the right bank (R) temporary cut-off is removed, the sand bank 15 is loaded on the left bank (L), and the temporary cut-off is performed. Then, the remaining portion is sequentially cut and removed by the same operation procedure as described above to complete the full-length opening S.
[0033]
Finally, as shown in FIG. 8, the center is temporarily cut off with a sandbag 15 and water is allowed to flow from the left and right openings S, and the remaining part is continuously provided below the partial opening S1 of the central part by a dry operation. Are sequentially cut and removed by the same operation procedure as described above to complete the full length opening S.
[0034]
FIG. 9 shows the completed state of the sabo dam 1 described above. The drop between the upstream and downstream water levels WL of the dam 1 is extremely low depending on the bottom surface height of the opening S, and the fish runs up and down. The height will not hinder. In the figure, the bottom surface of the opening S has an inclined slope toward the downstream side. However, a stepped step may be provided at the stage of finishing the bottom surface of each opening S.
[0035]
Next, the cutting shape of the rectangular cutting block B and the detailed jack-up procedure of the rectangular cutting block B will be described with reference to FIG.
[0036]
FIG. 10A shows a top view and a side view of the rectangular cutting block B in a state where the cutting with the wire saw W has been completed. In this embodiment, the rectangular cutting block B is divided into left and right cutting blocks B1 and B2.
[0037]
A through hole SH of the wire saw W penetrates the dam body 1 in advance at the intersection of the vertical cutting line L1 and the horizontal cutting line L2 and the intersection of the central dividing line L3 and the horizontal cutting line L2 of each block B1, B2. So that it is drilled.
[0038]
The dividing line L3 is not vertical but is formed obliquely, whereby the left block B1 has a tapered shape and the right block B2 has a reverse taper to ensure the ease of jack-up work after cutting.
[0039]
In addition, a pair of circular guide holes GH are formed substantially vertically so as to be positioned at the central part of the dam body thickness of the dam 1 at approximately the center position of the vertical cutting lines L1 on both sides.
[0040]
This guide hole GH is formed so as to straddle between the dam body of the dam 1 and the left and right blocks B1 and B2 of the rectangular cutting block B separated from the dam body by cutting lines L and L2. A guide rod 14 for guiding when jacking up is inserted.
[0041]
Four anchoring steel bars 11 for jacking up are embedded in four corners of each of the blocks B1 and B2. When jacking up such a rectangular cutting block B, the following procedure is performed.
[0042]
That is, first, as shown in FIG. 10B, the left block B <b> 1 having a tapered shape is pulled upward by an unillustrated jack through the anchor steel rod 11. And if this left side block B1 is pulled up to some extent, it will hold | maintain in this position.
[0043]
In this state, as shown in FIG. 10C, the right block B <b> 2 can be pulled up, and this time, the right block B <b> 2 is pulled upward by the jack (not shown) via the anchor steel bar 11.
[0044]
At this time, the right block B1 is pulled up to the same position as the left block B1 and held at that position. By repeatedly performing such alternate jack-up operation, both the blocks B1 and B2 can be pulled up, and a predetermined drainage opening O for discharge can be formed in the lower part thereof.
[0045]
In this embodiment, the rectangular cutting block B is divided into a tapered taper shape and a reverse taper shape by an oblique dividing line L3 for the following reason. That is, if the cutting lines L and L2 are formed by a wire saw and are to be pulled upward while remaining rectangular, the cutting lines L and L2 formed by the wire saw W have a width of about a dozen mm, It is relatively small, and as the cutting progresses, its width becomes narrower, and furthermore, it is difficult to form accurately perpendicularly due to cutting resistance etc., so when pulling up, the cutting surface competes, The raising becomes very difficult and almost impossible.
[0046]
However, when the rectangular cutting block B is divided into a taper taper shape and an inverse taper shape by an oblique dividing line L3, the taper taper block B1 is pulled up first, and then the jack-up operation is repeated alternately to block B1. , B2 can be lifted smoothly without such competition.
[0047]
In this case, since the guide rod 14 is inserted into each guide hole GH formed so as to straddle between the left and right blocks B1 and B2, the blocks B1 and B2 can be smoothly jacked up.
[0048]
Further, when the rectangular cutting block B is pulled upward, water in the dam 1 tends to flow downstream, and the water pressure associated therewith acts. In this case, between the left and right blocks B1 and B2 Since the guide rod 14 is inserted into each guide hole GH formed so as to straddle the block, each block B1, B2 can be held in a predetermined position and state against this water pressure. As a result, the pulling operation can be easily performed.
[0049]
In the above embodiment, the wire saw W is exemplified as the cutting means for forming the rectangular cutting block B. However, the embodiment of the present invention is not limited to this, and for example, a disk-shaped blade is used. Cutting means may be used, or cutting means using these in combination.
[0050]
Further, in the above embodiment, the case where the opening S having a predetermined length is formed by repeating the process twice, but the implementation of the present invention is not limited to this and the number of times more than this. May be repeated.
[0051]
【The invention's effect】
As described above, according to the method of the present invention, the fishway opening can be formed while preventing the sediment sediment from flowing out to the downstream side, so that the downstream impact due to the sediment outflow can be prevented.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram showing a first step of a method of the present invention.
FIG. 2 is an explanatory diagram showing a next step subsequent to FIG.
FIG. 3 is an explanatory view showing the same process.
FIG. 4 is an explanatory view showing the same process.
FIG. 5 is an explanatory view showing the same process.
FIG. 6 is an explanatory view showing the same process.
FIG. 7 is an explanatory view showing the same process.
FIG. 8 is an explanatory diagram showing the final step.
FIG. 9 is a perspective view showing a construction completion state.
FIGS. 10A to 10C are explanatory views showing a cutting shape of a cutting block and a pulling-up procedure.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Sabo dam 5 Accumulated sediment 7 Crawler crane WL Water surface 8 Work stand 10 Wire saw drive device 12 Jack W Wire saw S1 Partial opening S Opening B Rectangular cutting block B1, B2 Cutting block

Claims (4)

既存の砂防ダムの上流側に堆積した土砂を浚渫する第1工程と、
ワイヤソーなどの切断手段により前記砂防ダムのダム堤体を前記浚渫後の堆積土砂表面より上の位置に至る深さまで切込んで矩形状切断ブロックを形成する第2工程と、
前記矩形状切断ブロックをジャッキアップして、当該矩形状切断ブロックの下部に、前記ダム堤体を貫通する水抜き開口部を設け、この水抜き開口部より水を放流し、前記砂防ダム内の水位を低下させる第3工程と、
前記矩形状切断ブロックを除去して、前記ダム堤体に部分開口部を形成する第4工程とを含み、
前記第1から第4工程を順次繰り返すことにより、前記ダム堤体に所定の長さの開口部を形成することを特徴とする砂防ダムにおける開口部の形成方法。
A first step of dredging sediment deposited on the upstream side of an existing sabo dam;
A second step of forming a rectangular cutting block by cutting the dam body of the sabo dam to a depth reaching a position above the surface of the sediment after the dredging by cutting means such as a wire saw;
Jack up the rectangular cutting block, and provide a drain opening through the dam dam body at the lower part of the rectangular cutting block, to discharge water from the drain opening, and in the sabo dam A third step of lowering the water level;
A fourth step of removing the rectangular cutting block and forming a partial opening in the dam dam body,
A method of forming an opening in a sabo dam, wherein an opening having a predetermined length is formed in the dam dam body by sequentially repeating the first to fourth steps.
前記矩形状切断ブロックは、斜め分割線により、先細テーパ状のブロックと、逆テーパ状のブロックとの2ブロックに分断され、これらのブロックを交互にジャッキアップすることを特徴とする請求項1記載の開口部の形成方法。2. The rectangular cutting block is divided into two blocks of a tapered taper block and a reverse taper block by oblique dividing lines, and these blocks are alternately jacked up. Of forming the opening of the substrate. 前記ダム堤体と前記矩形状ブロックとの間に相互に跨る一対のガイド孔を、前記ダム堤体のほぼ垂直方向に穿設し、前記ブロックをジャッキアップする際のガイド用のガイドロッドを、各ガイド孔内に挿入することを特徴とする請求項2記載の開口部の形成方法。A pair of guide holes straddling each other between the dam levee body and the rectangular block are drilled in a substantially vertical direction of the dam dam body, and a guide rod for guiding when jacking up the block, The method for forming an opening according to claim 2, wherein the opening is inserted into each guide hole. 前記開口部は、前記ダム堤体に所定の間隔を隔てて、3箇所以上設けられ、
一方側の2箇所に前記部分開口部を形成した後、残る1個所以上の開口部の予定位置周縁を仮締切りし、
前記部分開口部の下方に形成した前記水抜き開口部から水を放流しつつ、残る1個所以上の開口部の形成予定位置をドライ状態にして、
この開口部の形成予定個所に、前記部分開口部を設けることなく、所定の長さの開口部を形成することを特徴とする請求項1記載の砂防ダムにおける開口部の形成方法。
The opening is provided at three or more locations at a predetermined interval in the dam dam body,
After forming the partial opening at two locations on one side, temporarily cut off the periphery of the planned position of the remaining one or more openings,
While discharging water from the drain opening formed below the partial opening, the formation position of the remaining one or more openings is in a dry state,
2. The method for forming an opening in a sabo dam according to claim 1, wherein the opening having a predetermined length is formed at a place where the opening is to be formed without providing the partial opening.
JP2001170764A 2001-06-06 2001-06-06 Method for forming openings in sabo dams Expired - Lifetime JP3771816B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001170764A JP3771816B2 (en) 2001-06-06 2001-06-06 Method for forming openings in sabo dams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001170764A JP3771816B2 (en) 2001-06-06 2001-06-06 Method for forming openings in sabo dams

Publications (2)

Publication Number Publication Date
JP2002363951A JP2002363951A (en) 2002-12-18
JP3771816B2 true JP3771816B2 (en) 2006-04-26

Family

ID=19012631

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001170764A Expired - Lifetime JP3771816B2 (en) 2001-06-06 2001-06-06 Method for forming openings in sabo dams

Country Status (1)

Country Link
JP (1) JP3771816B2 (en)

Also Published As

Publication number Publication date
JP2002363951A (en) 2002-12-18

Similar Documents

Publication Publication Date Title
JP4107425B2 (en) Sabo dam for catching mud flow type debris flow
CN111270698A (en) Protective structure for exposed diseases of bridge pile foundation in sand-mining river channel in mountainous area and construction method of protective structure
CN213952150U (en) A water area fish culture blocks fish system for cleaning water source
JP3483847B2 (en) Intake structure of river surface water with sloped intake screen installed at floor stop
JP3211107B2 (en) Submersion dam construction method
JP3771816B2 (en) Method for forming openings in sabo dams
CN212223936U (en) A protective structure that is used for mountain area to adopt sand river course inner bridge pile foundation to expose disease
JP4504864B2 (en) Dam body reinforcement structure with wave-dissipating function
JP3663541B2 (en) Impermeable mountain retaining wall with groundwater flow conservation function and its groundwater flow conservation method
JPH1060871A (en) Method of dam renewal
JP2008231705A (en) Method for improving roughness of revetment structure
KR100743550B1 (en) Scour prevention block
JP3748391B2 (en) Floor firming cascade fishway
KR100776621B1 (en) Pile structure for preventing a disaster by debris flow
CN1296565C (en) Frame mount type combined dam
Matsuura Stream-bank protection in narrow channel bends using'barbs': A laboratory study
JP2980311B2 (en) Construction method of coping submerged revetment and vibro hammer used in the construction method.
JP3446186B2 (en) Pollution control caisson for dredging and dredging method
CN220318450U (en) Check dam structure for erosion ditch treatment
CN211773743U (en) A drainage reinforced structure for landslide is administered
Zech et al. Evaluation of ALDOT Ditch Check Practices using Large-Scale Testing Techniques
KR200429763Y1 (en) Scour prevention block
TW201016930A (en) Regulation method for river with the function of protecting bridge pier and dike, and with the function of forming sand and stone collecting specific area
JP2999170B2 (en) Dam sediment treatment method
Haas et al. Bank stabilization by revetments and dikes

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060124

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060210

R150 Certificate of patent or registration of utility model

Ref document number: 3771816

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090217

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100217

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100217

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110217

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110217

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120217

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130217

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130217

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140217

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term