dam
sediment
sedimentation
downstream
sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2507598A
Other languages
Japanese (ja)
Other versions
JPH11209952A (en
Inventor
徳行 鈴木
Original Assignee
徳行 鈴木
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 徳行 鈴木 filed Critical 徳行 鈴木
Priority to JP2507598A priority Critical patent/JP2999170B2/en
Publication of JPH11209952A publication Critical patent/JPH11209952A/en
Application granted granted Critical
Publication of JP2999170B2 publication Critical patent/JP2999170B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Barrages (AREA)
  • Revetment (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明はダムの堆砂の処理方
法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for treating sediment of a dam.

【0002】[0002]

【発明が解決しようとする課題】ダムは建設後、年数の
経過と共に土砂が堆積する。したがってダムの機能を維
持するためには該堆砂を掘削して除去しなければならな
い。しかし掘削により発生する土砂の捨場所がなく、処
理費も高くつくので、該土砂の処理にも苦しんでいるの
が現状である。
After the dam has been constructed, sediment accumulates over the years. Therefore, the sediment must be excavated and removed to maintain the function of the dam. However, there is no place to dispose of the earth and sand generated by the excavation, and the processing cost is high.

【0003】[0003]

【課題を解決するための手段】本発明は上記従来の課題
を解決するための手段として、ダム(2) 下流の河川(1)
広巾部(1A)に堰(3) を設けて土砂堆積場(4) を区画し、
該土砂堆積場(4) にダム(2) 堆砂を掘削して堆積せしめ
る構成であって、該堰(3) の高さを河川(1) の通常時水
位L1 よりも高くかつ洪水時水位L2 よりも低く設定
し、洪水時に該土砂堆積場(4,)に堆積してある土砂Sを
下流に流下させるダム堆砂処理方法およびダム(2) 下流
の河川(1) 広巾部(1A)に段差(3A)を設け て土砂堆積場(4
A)を区画し、該土砂堆積場(4A)にダム(2) 堆砂を掘削し
て堆 積せしめる構成であって、高段部を土砂堆積場(4A)
として該土砂堆積場(4A) の高さを河川の通常時水位L 1
よりも高くかつ洪水時水位L 2 よりも低く設 定し、洪水
時に該土砂堆積場(4A)に堆積してある土砂を下流に流下
させるダ ム堆砂処理方法を提供するものである。
According to the present invention, as a means for solving the above-mentioned conventional problems, a river (1) downstream of a dam (2) is provided.
Weirs (3 ) are set up in the wide section (1A) to divide the sediment dump (4),
該土sand dumps (4) to have a configuration allowed to deposit drilled a dam (2) sedimentation, high and flood than normal water level L 1 of the river (1) the height of the weir (3) set to be lower than the water level L 2
And, flood upon該土sand dumps (4) to the dam sediment treatment method and dams to flow down to the sand S are downstream deposition (2) downstream
River (1) A step (3A) is set up in the wide area (1A)
A) and dig a dam (2) sediment in the sedimentation area (4A).
A Te sedimentary allowed to configure, sedimentation field high-stage portion (4A)
The height of the sedimentation area (4A) as the normal water level L 1 of the river.
Set lower than high and flooding when the water level L 2 than floods
Sometimes the sediment deposited in the sedimentation site (4A) flows down
There is provided a dam sediment treatment method of.

【0004】[0004]

【発明の実施の形態】図1および図2に本発明の一実施
例を示す。図1において(2) は河川(1) に設けられてい
るダムであり、該ダム(2) の下流においてダム(2) 近く
の河川(1) の広巾部(1A)を選び、該広巾部(1A)にコンク
リート、蛇かご、布団かご、玉石等からなる堰(3) を設
けて土砂堆積場(4) を区画する。
FIG. 1 and FIG. 2 show an embodiment of the present invention. In FIG. 1, (2) is a dam provided in the river (1), and a wide section (1A) of the river (1) near the dam (2) is selected downstream of the dam (2). In (1A), a weir (3) consisting of concrete, snake basket, futon basket, cobblestone, etc. will be provided to divide the sediment dump (4).

【0005】該土砂堆積場(4) は河川(1) の広巾部(1A)
の曲りの外側に設けられることが望ましく、また図2に
示すように堰(3) の高さは河川(1) の通常時の水位L1
よりも高く、また洪水時(小洪水時)の水位L2 よりも
低く設定する。
[0005] The sediment dump (4) is located in the wide area (1A) of the river (1).
And the height of the weir (3) is set at the normal water level L 1 of the river (1) as shown in FIG.
Higher than, also set lower than the water level L 2 of the flood (at small flood).

【0006】上記構成において、ダム(2) に堆積した土
砂を掘削して除去し、掘削によって発生した土砂Sは土
砂堆積場(4) に堆積する。
[0006] In the above configuration, the earth and sand deposited on the dam (2) is excavated and removed, and the earth and sand S generated by the excavation is accumulated on the earth and sand accumulation site (4).

【0007】通常時(水位L1 )には河川(1) の水は図
1太矢印に示すように堰(3) にはばまれてその外側を流
れる。そして小洪水時(水位L2 )以上で該河川(1) の
水は図1細矢印に示すように堰(3) を乗り越え、該土砂
堆積場(4) に堆積している土砂Sを同伴して下流に流下
する。
In normal times (water level L 1 ), the water of the river (1) is jumped by the weir (3) as shown by the thick arrow in FIG. At the time of a small flood (water level L 2 ) or more, the water in the river (1) crosses the weir (3) as shown by the thin arrow in FIG. 1 and entrains the sediment S deposited on the sedimentation site (4). And flow downstream.

【0008】このようにして該土砂堆積場(4) に堆積し
ている土砂Sは洪水時に河川(1) に自然に排出され流下
するが、洪水時には河川(1) の水量は多く、土砂Sの河
川に対する影響は少なくなる。
[0008] In this way, the sediment S deposited on the sedimentation site (4) is naturally discharged into the river (1) during the flood and flows down. Impact on rivers is reduced.

【0009】図3には本発明の他の実施例が示される。
本実施例においては前実施例の堰(3) の代りに段差(3A)
が形成され、高段部を土砂堆積場(4A)とする。該段差(3
A)は人工のものであっても自然に形成されたものであっ
てもよい。本実施例にあっても通常時(水位L1 )には
河川(1) の水は段差(3A)にはばまれてその外側を流れ、
小洪水時(水位L2 )以上では段差(3A)を乗り越え、該
土砂堆積場(4A)に堆積している土砂Sを同伴して下流に
流下する。
FIG. 3 shows another embodiment of the present invention.
In this embodiment, a step (3A) is used instead of the weir (3) of the previous embodiment.
Is formed, and the high step is used as a sedimentation area (4A). The step (3
A) may be artificial or naturally formed. Even in this embodiment, at normal times (water level L 1 ), the water of the river (1) is interrupted by the step (3A) and flows outside thereof.
At the time of a small flood (water level L 2 ) or more, the vehicle climbs over the step (3A) and flows down along with the sediment S deposited at the sedimentation site (4A).

【0010】[0010]

【発明の効果】本発明では上記したようにダム堆砂の掘
削により生じた土砂を、洪水時にのみ自然に除去するよ
うにするから、人手が全くかゝらずそして土砂の河川に
対する影響は少ない。
According to the present invention, as described above, the sediment generated by the excavation of the dam sediment is naturally removed only at the time of the flood, so that no human labor is required and the influence of the sediment on the river is small. .

【図面の簡単な説明】[Brief description of the drawings]

図1および図2は本発明の一実施例を示すものである。 1 and 2 show an embodiment of the present invention.

【図1】一部省略平面図FIG. 1 is a partially omitted plan view.

【図2】図1におけるA−A断面図FIG. 2 is a sectional view taken along line AA in FIG.

【図3】本発明の他の実施例の図1におけるA−A相当
断面図
FIG. 3 is a sectional view corresponding to AA in FIG. 1 of another embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 河川 1A 広巾部 2 ダム 3 堰 3A 段差 4,4A 土砂堆積場 S 土砂 1 River 1A Wide section 2 Dam 3 Weir 3A Step 4,4A Sedimentation site S Sediment

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】ダム下流の河川広巾部に堰を設けて土砂堆
積場を区画し、該土砂堆積場にダム堆砂を掘削して堆積
せしめる構成であって、該堰の高さを河川の通常時水位
よりも高くかつ洪水時水位よりも低く設定し、洪水時に
該土砂堆積場に堆積してある土砂を下流に流下させるこ
とを特徴とするダム堆砂処理方法
1. A provided weir defines a sedimentation field rivers Hirohaba portion of the dam downstream, a configuration that allowed to deposit drilled dams sediment in該土sand dumps, the height of the weir of river set lower than high and flooding when water levels than normal water level, dam sedimentation processing method for causing to flow down sediment downstream that is deposited該土sand dumps during floods
【請求項2】ダム下流の河川広巾部に段差を設けて土砂(2) A step is provided in a wide portion of a river downstream of a dam to make the soil
堆積場を区画し、Compile the deposition area, 該土砂堆積場にダム堆砂を掘削して堆Excavation of dam sediment at the sedimentation site
積せしめる構成であって、高段部を土It is a configuration that can be stacked, 砂堆積場として該Sand deposit
土砂堆積場の高さを河川の通常時水位よりも高くかつ洪The height of the sedimentation pit is higher than the normal
water 時水位よりも低く設定し、洪水時に該土砂堆積場に堆Lower than the water level during the flood, and
積してある土砂を下流Downstream of piled earth and sand に流下させることを特徴とするダCharacterized by flowing down
ム堆砂処理方法Mud treatment method
JP2507598A 1998-01-21 1998-01-21 Dam sediment treatment method Expired - Lifetime JP2999170B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2507598A JP2999170B2 (en) 1998-01-21 1998-01-21 Dam sediment treatment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2507598A JP2999170B2 (en) 1998-01-21 1998-01-21 Dam sediment treatment method

Publications (2)

Publication Number Publication Date
JPH11209952A JPH11209952A (en) 1999-08-03
JP2999170B2 true JP2999170B2 (en) 2000-01-17

Family

ID=12155818

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2507598A Expired - Lifetime JP2999170B2 (en) 1998-01-21 1998-01-21 Dam sediment treatment method

Country Status (1)

Country Link
JP (1) JP2999170B2 (en)

Also Published As

Publication number Publication date
JPH11209952A (en) 1999-08-03

Similar Documents

Publication Publication Date Title
RU2665072C1 (en) Method of reservoir water area localization of pollutants entering reservoir from tributaries and drains
JP4107425B2 (en) Sabo dam for catching mud flow type debris flow
JP2999170B2 (en) Dam sediment treatment method
JP3483847B2 (en) Intake structure of river surface water with sloped intake screen installed at floor stop
JP2005030070A (en) Flowing-down promoting dam structure and flowing-down promoting method of deposit sediment in dam water reservoir
JP3882997B2 (en) Reservoir sand removal method and sand removal equipment
JP3347104B2 (en) Sand removal method of reservoir and sand removal equipment of reservoir
JPH05331827A (en) Dredging device for deposited silt in reservoir
JP2008308894A (en) Triple lake dam structure
JP4118770B2 (en) Sabo dam storage and drainage structure
RU2393293C1 (en) Arrangement method of drying system with narrow enclosure ploughing of drained soils
JP3461897B2 (en) Estuarine water pollution control facilities
KR100680156B1 (en) Sediment remove facility for river bottom
KR100730993B1 (en) Intake Facility for First runoff in Stream
JP2008231705A (en) Method for improving roughness of revetment structure
JPS62262788A (en) Cleaning method for river
JP3771816B2 (en) Method for forming openings in sabo dams
JP7116506B1 (en) Water intake structures and water intake facilities
RU2088723C1 (en) Method for controlling unstable river channels
KR101934106B1 (en) River ecological restoration facilities considering river water level and geological characteristics of sediments, installation and utilization
SU1723233A1 (en) Method of maintaining river waterway in operating condition
SU1604172A1 (en) Device for protecting gullies against outwashing with surface flow
JP2003268754A (en) River activating regenerating method and river activating regenerating device
RU1808900C (en) Spillway
JP3683108B2 (en) Purification channel

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19991005