JP3713652B2 - Construction method for interior equipment - Google Patents

Construction method for interior equipment Download PDF

Info

Publication number
JP3713652B2
JP3713652B2 JP03937698A JP3937698A JP3713652B2 JP 3713652 B2 JP3713652 B2 JP 3713652B2 JP 03937698 A JP03937698 A JP 03937698A JP 3937698 A JP3937698 A JP 3937698A JP 3713652 B2 JP3713652 B2 JP 3713652B2
Authority
JP
Japan
Prior art keywords
wall panel
wall
ceiling
unit
wiring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP03937698A
Other languages
Japanese (ja)
Other versions
JPH11236746A (en
Inventor
真幸 竹内
高之 坂本
幸子 立野
直人 三根
幸昭 内川
義光 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP03937698A priority Critical patent/JP3713652B2/en
Publication of JPH11236746A publication Critical patent/JPH11236746A/en
Application granted granted Critical
Publication of JP3713652B2 publication Critical patent/JP3713652B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、例えばマンションの各住戸内の廊下等を施工するときに用いて好適な、内装設備の施工工法に関するものである。
【0002】
【従来の技術】
一般に、マンション等の建物は、建物の躯体を構成する柱、梁、スラブ等を形成し、これら柱、梁、スラブによって複数の住戸を区切って形成する。そして、各住戸においては、天井材、壁材等の内装工事を施すとともに、電気配線、給水給湯,排水,ガス,換気用の配管等の設備工事を行っている。
【0003】
電気配線、空調配管や換気ダクトなどの配線・配管は、それが設置される天井や、壁部分の位置のコンクリートスラブの下部に、内装工事に先行してまとめて取り付けられている。そして、内装工事の進捗に応じて、配線・配管の引き出し、正規の位置へのセット等が行われる。
【0004】
【発明が解決しようとする課題】
しかしながら、上述したような従来の技術には以下のような問題が存在する。
すなわち、上記したような内装・設備工事は、通常下地材や壁ボード,天井ボードの取付施工は内装業者が行い、配管や配線作業については、ガス、水道、電気等それぞれ専門の業者が個別に行うようになっている。
このため、実際の現場においては、複数の業者が同時に工事を行うと作業が錯綜してしまうため、通常はそれぞれの業者の工事が重複しないようスケジュールを立てているが、これでは言うまでもなくロスが多く、効率が悪い。また前の業者の作業工程が完了しない限り次の業者が作業を行えないために、作業の「待ち」が発生することもある。このように、従来の工事の進め方ではロスが多く、工期および施工コストの面で改善の余地があった。
【0005】
また、天井や壁等を形成するに際しては、多数の下地材を組み、さらにこの下地材に壁ボードや天井ボード等の仕上げ材を取り付けなければならず、非常に手間がかかるものとなっている。
【0006】
本発明は、以上のような点を考慮してなされたもので、施工の効率化を図り、工期を短縮するとともに施工コストを削減することのできる内装設備の施工工法を提供することを課題とする。
【0007】
【課題を解決するための手段】
請求項1に係る発明は、廊下等、一方向に連続する空間への内装設備の施工工法であって、前記空間の壁を形成する壁パネルを所定の位置に設置する第一の工程と、前記一方向への長さ寸法が後付け天井ユニットよりも短い先付け天井ユニットを、前記空間の連続する方向において所定間隔ごとに前記壁パネルに設置する第二の工程と、洗面やトイレの入り口部分に仮置き天井ユニットを設置し、次いで配管配線を束ねて巻いたリールを前記仮置き天井ユニット上に載置して、前記仮置き天井ユニット上のリールから配管等を巻き出して前記先付け天井ユニットの上面側に配管等を通す第三の工程と、互いに前後する前記先付け天井ユニット間に後付け天井ユニットを取り付ける第四の工程と、からなることを特徴としている。
【0008】
請求項2に係る発明は、請求項1記載の内装設備の施工工法において、前記壁パネルが、該壁パネルの骨格をなす下地材を、壁の一面側を形成するボードに予め一体に取り付けた構成からなり、前記第一の工程で前記壁パネルを設置した後には、壁内に配線等を行い、しかる後に前記壁の他面側を形成するボードを前記壁パネルに取り付けることを特徴としている。
【0009】
請求項3に係る発明は、請求項1または2記載の内装設備の施工工法において、前記第一の工程で前記壁パネルを設置するに際しては、前記壁パネルや、出入口や開口部等を形成する枠体を、前記空間の一端側から他端側に向けて順次組み付けていく構成としたことを特徴としている。
【0012】
【発明の実施の形態】
以下、本発明に係る内装設備の施工工法の実施の形態の一例、ならびにそれに用いる内装ユニットおよび天井ユニットの一例を、図1ないし図11を参照して説明する。ここでは、本発明を、例えばマンションの住戸内の廊下に適用する場合の例を用いて説明する。
【0013】
図1に示すものは、マンションの住戸の平面レイアウト図であり、この図において、符号Jは住戸、Tは共用廊下、Rは住戸J内に複数配置された部屋、Cは共用廊下T側の出入口と住戸J内の各部屋Rとの間の住戸内廊下(空間)、をそれぞれ示している。
【0014】
住戸Jを構築するには、まずマンションの躯体を構成する柱1,梁(図示なし),スラブ2,外壁3,戸境壁4等を、鉄筋コンクリート造、鉄骨鉄筋コンクリート造、鉄骨造等により構築する。
【0015】
続いて、このようにして形成されたスラブ2,外壁3,戸境壁4等によって区分されて形成された住戸Jにおいて、以下のように内装設備工事を行う。
【0016】
[壁パネルの設置]
まず、図2に示すように、住戸内廊下Cの両側の壁を形成すべき位置に沿って、上階のスラブ(図示なし)の下面と、当該階のスラブ2の上面とに、木製の上部ランナー6,6、下部ランナー7,7を設置する。さらに、これら上下の上部ランナー6および下部ランナー7の間には、扉枠取付部や壁コーナー部等に例えば木製の支柱8を取り付ける。
【0017】
次いで、これら上部ランナー6,下部ランナー7,支柱8に、住戸内廊下Cの壁面を形成する壁パネル10や、各部屋Rへの出入口を形成する扉枠11等を固定して設置する。
【0018】
図2および図3に示すように、この壁パネル10は、住戸内廊下C側の壁面を構成する各種ボード材からなる壁面ボード(ボード)10aと、木製の角材等からなる下地材10bとが一体化されたもので、工場等において予め製作されている。下地材10bは、壁面ボード10aの反対面側に壁面ボード12を取り付けるための機能と、両面へのボード施工後は壁の強度そのものを担う支柱としての機能等を有し、従来は先付けしていたものである。
【0019】
また、図2に示したように、この壁パネル10には、配線を係止するための配線用取付具13が、天井面よりも上方となる位置に予め取り付けてある。この配線用取付具13の形式については具体的に何ら限定するものではないが、配線作業を容易に行うため、ワンタッチで配線を係止できるような構造のものが望ましい。
【0020】
図4に示すように、扉枠11も、工場等において予め所定形状に組み立てられたものであり、ここでは、その上端の高さが、住戸内廊下Cの天井レベルLと略等しくなるよう設定されている。
【0021】
これら壁パネル10や扉枠11の設置に際しては、まず、住戸内廊下Cの一端側から、壁パネル10や扉枠11を順次建て込んでいくようにする。すなわち、図3および図5に示すように、住戸内廊下Cの一端部に位置する壁パネル10Aを、所定の位置にセットして上部ランナー6,下部ランナー7,支柱8(図3参照)等に固定した後には、この壁パネル10Aに隣接する扉枠11Bを、図5中に示した矢印の如く、先に取り付けた壁パネル10A側に向けて押し、扉枠11Bの切欠き14(図3参照)に壁パネル10Aの端部をはめ込むようにする。次いで設置する壁パネル10C,扉枠11Dについても、同様に一方向に押し込むようにしてこれを所定の位置に建て込んでいくようにする。
【0022】
また、図1に示したように、住戸内廊下Cの壁だけでなく、周囲の各部屋Rを仕切る壁15についても、同様にして予め所定形状にユニット化された壁パネルの設置を行っていく。
【0023】
次いで、図6に示すように、壁面に取り付けるコンセントや照明スイッチ用等の住戸内の強電および弱電の配線16を配設する。この配線16は、壁パネル10の配線用取付具13に係止させるようにする。
【0024】
[天井ユニットの設置・配線配管]
図7に示すように、住戸内廊下Cの両側の壁を構成する壁パネル10の設置後、天井を構成する天井ユニット17の設置を行う。
天井ユニット17は、先行して取り付けを行う先付けユニット(先付け天井ユニット)17Aと、後行して取り付けを行う後付けユニット(先付け天井ユニット)17Bとからなり、先付けユニット17Aは、その長さ(住戸内廊下Cが連続する方向における寸法)が後付けユニット17Bの長さよりも十分に短くなるよう設定されている。
【0025】
図6に示したように、まず、複数枚の先付けユニット17Aを、住戸内廊下Cが連続する方向において所定間隔(後付けユニット17Bの長さ寸法)をあけて所定の高さに取り付けていく。その取付は、先付けユニット17Aの両端部を、壁パネル10に釘等の各種接合手段を用いて固定することにより行う。
【0026】
次いで、図1に示したように、共用廊下Tから各住戸J内に引き込まれるメインの配線配管作業を行うが、これに先立ち、特にガス・給水等の配管が集中し、分岐箇所が多い洗面R1やトイレR2の入り口部分に、この部分の天井を構成する天井ユニットを仮置き天井ユニット19として先に設置する。
【0027】
そして、図8に示すように、この仮置き天井ユニット19の上面に、とぐろ状に束ねて巻かれているリール20を置く。
仮置き天井ユニット19から各部屋R側においては、仮置き天井ユニット19上のリール20から配線や配管(配線,配管)21を巻き出していき、照明やコンセント用等の配線を行う。
一方、仮置き天井ユニット19から住戸内廊下C側においては、洗面R1,トイレR2の入り口の扉枠11の上部の開口部22から、図6に示したように、先付けユニット17A,17A,…の上部空間に配線や配管21を通す。
このとき、仮置き天井ユニット19と、先付けユニット17A,17A,…とは略同レベルであるので、天井ユニット17上に置かれたリール20から巻き出した配線や配管21には、余分な引張力等がかからないようになっている。
【0028】
この後、図7に示したように、住戸内廊下Cの後付けユニット17Bの取り付けを行う。図9に示すように、後付けユニット17Bは、住戸内廊下Cの天井面を形成する天井フレーム25に、配線や配管21を固定するための配管用サドル(サドル)26が取り付けられたものである。
後付けユニット17Bを先付けユニット17A,17A間に取付固定した後、図10に示すように、既に仮配管した各配線や配管21を配管用サドル26にはめ込む。この後、天井フレーム25に所定のボード等の仕上げ材を貼り付ける。
【0029】
図11に示すように、さらに、壁パネル10の裏面側に、住戸内廊下Cに隣接する各部屋Rの壁面を構成する壁面ボード12を、ビス等の接合手段を用いて壁パネル10の下地材10bに固定する。
【0030】
これにより、住戸内廊下Cの天井ユニット17の取付、および配線配管作業が全て完了し、住戸内廊下Cが完成することとなる。
【0031】
なお、住戸内廊下C以外の部分、例えばユニットバス、トイレ、キッチンユニット等の什器類の設置、各部屋Rの内装施工等については、住戸内廊下Cの施工の進捗に対応させて支障のないよう、所要のタイミングで施工を行っていく。
【0032】
上述したように、一方向に連続してその天井裏に各住戸Jにおけるメインの配線配管が集中する住戸内廊下Cを施工するには、壁パネル10を設置した後、天井を形成する先付けユニット17Aを所定間隔ごとに設置し、これら先付けユニット17A上に配線や配管21を通し、しかる後に先付けユニット17A,17A間に後付けユニット17Bを設置する構成とした。このようにして住戸内廊下Cの内装を壁パネル10や天井ユニット17でユニット化を図ることにより、住戸内廊下Cの内装および設備の施工をシステマティックに行うことができ、施工効率を高めることができる。しかも、住戸内廊下Cの天井裏を通るメインの配線や配管21については、壁パネル10や天井ユニット17の建て込み作業を行う多能工が一括して行うことができ、各部屋Rにおける給湯設備やガス設備等へのつなぎ込みのみそれぞれ専門の業者が行えばよいので、この点においても施工効率を高めることができ、工期短縮および工費削減を図ることができる。
【0033】
壁パネル10が、下地材10bを壁面ボード10aに予め一体に取り付けてなる構成からなり、壁パネル10を設置した後には、壁内に配線等を行い、しかる後に壁の他面側を形成する壁面ボード12を壁パネル10に取り付ける構成となっている。これにより、壁パネル10を固定するための最低限の支柱8を設けるのみでよく、現場における下地材の設置作業を削減することができ、壁や天井の施工の効率化を図ることができる。
【0034】
さらに、壁パネル10を設置するに際しては、壁パネル10や扉枠11を、住戸内廊下Cの一端側から他端側に向けて順次片押しで組み付けていく構成とした。これにより、ユニット化した壁パネル10や扉枠11を効率よく組み立てることができる。
【0035】
加えて、天井ユニット17の後付けユニット17Bは、天井面を形成する天井フレーム25と、その上面側に配管や配管21を固定する配管用サドル26とを一体に備えた構成となっている。これにより、配線や配管21を天井裏のスペースに仮配管し、これを天井ユニット17の配管用サドル26にはめ込むことにより、配管作業を容易かつ確実に行うことが可能となる。
【0036】
さらには、配線や配管21を配設するときには、配線や配管21が集中して分岐が多い洗面R1やトイレR2の入り口部分に仮置き天井ユニット19を設置し、この仮置き天井ユニット19の上面にリール20等を載置し、配線や配管21等をここから巻き出していく構成とした。従来は配線や配管の巻き出し作業は床上で行っており、これにより、配線や配管21等に引張力が作用したり、またその引張力により組み立てた下地材等が破損したりすることがある。これに対し、前記構成によれば、天井レベルに仮置き天井ユニット19を設置することにより、仮置き天井ユニット19と先付けユニット17A,17A,…とが略同レベルとなり、天井ユニット17上に置かれたリール20から巻き出した配線や配管21には、余分な引張力等がかからず、施工を円滑かつ確実に行うことができる。しかも住戸内廊下C側においては、メインの各配線や配管21をそのまま共用廊下T側に引き込めばよいので、作業も容易に行うことができる。また、この仮置き天井ユニット19は、この部分の天井を構成する天井ユニットにより形成されているので、配線配管作業の完了後にはそのまま本設材となり、施工の手間を省くことができる。
【0037】
なお、上記実施の形態において、本発明にかかる内装設備の施工工法を、例えばマンションの各住戸J内の住戸内廊下Cに適用する構成としたが、もちろんその間取りについては前記したものに何ら限定するものではないのは言うまでもなく、また、一方向に連続する空間であって、かつ天井裏に配線や配管等が集中する空間であれば、住戸内廊下に沿って複数の部屋が位置するマンションの外廊下や、ホテル内の廊下等、他の空間にも全く同様に適用することが可能である。
【0038】
また、住戸内廊下Cを構成する各部材の具体的な構成、例えば壁パネル10や扉枠11、天井ユニット17の構造や形状,材質等については何ら問うものではない。
【0039】
また、上記実施の形態において、扉枠11を住戸内廊下Cの天井レベルの高さを有するものとしたが、もちろんそれよりも低くても何ら問題はなく、その場合は扉枠11の上部に天井ユニット17との隙間を塞ぐパネル等を設置すればよい。
【0040】
さらに、天井ユニット17の上方の空間に配設される配線や配管21は、前記したような電気、ガス、水道等のみに限らず、例えば換気用のダクト等にも全く同様に適用することができる。
【0041】
これ以外にも、本発明の主旨を逸脱しない範囲内であれば、いかなる構成を採用しても良く、また上記したような構成を適宜選択的に組み合わせたものとしても良いのは言うまでもない。
【0042】
【発明の効果】
以上説明したように、請求項1に係る内装設備の施工工法によれば、廊下等、一方向に連続する空間の壁を形成する壁パネルを所定の位置に設置する第一の工程と、一方向への長さ寸法が後付け天井ユニットよりも短い先付け天井ユニットを所定間隔ごとに壁パネルに設置する第二の工程と、洗面やトイレの入り口部分に仮置き天井ユニットを設置し、次いで配管配線を束ねて巻いたリールを仮置き天井ユニット上に載置して、仮置き天井ユニット上のリールから配管等を巻き出して先付け天井ユニットの上面側に配管等を通す第三の工程と、互いに前後する先付け天井ユニット間に後付け天井ユニットを取り付ける第四の工程とからなる構成となっている。このようにして、廊下等の一方向に連続する空間の施工をシステマティックに行うことができ、施工効率を高めることができる。しかも、廊下の天井裏を通るメインの配線や配管については、壁パネルや天井ユニットの建て込み作業を行う多能工が一括して行うことができ、各室における給湯設備やガス設備等へのつなぎ込みのみそれぞれ専門の業者が行えばよいので、この点においても施工効率を高めることができ、工期短縮および工費削減を図ることができる。また、配管等を配設するときには、洗面やトイレの入り口部分に仮置き天井ユニットを設置し、この仮置き天井ユニット上にリールを載置し、このリールから配管等を巻き出していく構成となっている。これにより、作業を容易に行うことができる。
【0043】
請求項2に係る内装設備の施工工法によれば、壁パネルが、下地材を壁の一面側を形成するボードに予め一体に取り付けた構成からなり、第一の工程で壁パネルを設置した後には、壁内に配線等を行い、しかる後に壁の他面側を形成するボードを壁パネルに取り付ける構成となっている。これにより、壁パネルを固定するための最低限の支柱を設けるのみでよく、下地材の設置作業を削減することができ、壁や天井の施工の効率化を図ることができる。
【0044】
請求項3に係る内装設備の施工工法によれば、第一の工程で壁パネルを設置するに際しては、壁パネルや、出入口や開口部等を形成する枠体を、空間の一端側から他端側に向けて順次組み付けていく構成となっている。これにより、ユニット化した壁パネルや枠体を効率よく組み立てることができる。
【図面の簡単な説明】
【図1】 本発明に係る内装設備の施工工法を適用する空間の一例であって、マンション等の住戸の廊下を示す平面レイアウト図である。
【図2】 前記廊下の内装設備の施工工程を示す図であって、壁パネルを取り付ける状態を示す斜視図である。
【図3】 前記廊下の壁を示す平断面図である。
【図4】 同壁の立面図である。
【図5】 前記壁パネルや扉枠の取付方法を示す図である。
【図6】 前記廊下の内装設備の施工工程を示す図であって、先付け天井ユニットを取り付け、配線や配管を通した状態を示す斜視図である。
【図7】 同、後付け天井ユニットを取り付ける状態を示す斜視図である。
【図8】 同、配線や配管の配設方法を示す斜視図である。
【図9】 前記後付け天井ユニットを示す斜視図である。
【図10】 前記廊下の内装設備の施工工程を示す図であって、天井ユニットの取り付けた完了した状態を示す斜視図である。
【図11】 同、壁パネルの他面側に壁面を構成するボードを取り付ける状態を示す斜視図である。
【符号の説明】
10 壁パネル
10a 壁面ボード(ボード)
10b 下地材
11 扉枠
17 天井ユニット
17A 先付けユニット(先付け天井ユニット)
17B 後付けユニット(後付け天井ユニット)
21 配線や配管(配線,配管)
25 天井フレーム
26 配管用サドル(サドル)
C 住戸内廊下(空間)
[0001]
BACKGROUND OF THE INVENTION
The present invention is, for example, suitable for use when applying a corridor or the like in the dwelling unit of apartments, in which about the construction construction method of the interior equipment.
[0002]
[Prior art]
In general, a building such as a condominium is formed by forming columns, beams, slabs, and the like constituting a building frame, and dividing the plurality of dwelling units by these columns, beams, and slabs. In each dwelling unit, interior work such as ceiling materials and wall materials is performed, and equipment work such as electrical wiring, hot water and hot water supply, drainage, gas, and ventilation pipes is performed.
[0003]
Wiring and piping such as electrical wiring, air conditioning piping, and ventilation ducts are collectively installed prior to interior work on the ceiling where the wiring is installed and the concrete slab at the wall. Then, according to the progress of the interior work, the wiring / pipe is pulled out and set to a proper position.
[0004]
[Problems to be solved by the invention]
However, the conventional techniques as described above have the following problems.
In other words, the interior / facility construction as described above is usually performed by interior contractors to install the base material, wall board, and ceiling board, and the pipes and wiring work are individually performed by specialized contractors such as gas, water, and electricity. To do.
For this reason, at the actual site, if multiple contractors work at the same time, the work is complicated, so usually the schedule is set so that the work of each contractor does not overlap, but it goes without saying that this is a loss. Many are inefficient. Moreover, since the next trader cannot work unless the work process of the previous trader is completed, a “waiting” work may occur. As described above, the conventional construction method has a lot of loss, and there is room for improvement in terms of construction period and construction cost.
[0005]
Moreover, when forming a ceiling, a wall, etc., it is necessary to assemble a large number of base materials and attach a finishing material such as a wall board or a ceiling board to the base material, which is very laborious. .
[0006]
The present invention has been made in view of the above, aims to improve efficiency of the construction, providing construction construction method of the interior equipment capable of reducing the construction costs as well as shortening the construction period And
[0007]
[Means for Solving the Problems]
The invention according to claim 1 is a construction method of interior equipment to a space that continues in one direction, such as a corridor, and a first step of installing a wall panel that forms a wall of the space at a predetermined position; In the second step of installing the front ceiling unit having a length dimension in one direction shorter than the retrofitted ceiling unit on the wall panel at a predetermined interval in the continuous direction of the space, and in the entrance part of the toilet or toilet A temporary ceiling unit is installed, and then a reel in which piping wiring is bundled and wound is placed on the temporary ceiling unit, and piping is unwound from the reel on the temporary ceiling unit to It is characterized by comprising a third step of passing a pipe or the like on the upper surface side, and a fourth step of attaching a retrofit ceiling unit between the front and rear ceiling units that move back and forth.
[0008]
According to a second aspect of the present invention, in the construction method for interior equipment according to the first aspect, the wall panel integrally attaches the base material forming the skeleton of the wall panel to a board that forms one side of the wall in advance. After the wall panel is installed in the first step, wiring is performed in the wall, and then a board that forms the other side of the wall is attached to the wall panel. .
[0009]
The invention according to claim 3 is the construction method for interior equipment according to claim 1 or 2, wherein when the wall panel is installed in the first step, the wall panel, an entrance / exit, an opening, or the like is formed. The frame body is structured to be assembled sequentially from one end side to the other end side of the space.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an example of an embodiment of a construction method for interior equipment according to the present invention , and an example of an interior unit and a ceiling unit used therefor will be described with reference to FIGS. 1 to 11. Here, the present invention will be described using an example in a case where the present invention is applied to, for example, a corridor in a condominium dwelling unit.
[0013]
1 is a plan layout diagram of a dwelling unit of an apartment. In this figure, symbol J is a dwelling unit, T is a common corridor, R is a plurality of rooms arranged in the dwelling unit J, and C is a common corridor T side. The dwelling unit interior corridor (space) between the entrance and each room R in the dwelling unit J is shown.
[0014]
In order to build the dwelling unit J, first, the pillar 1, beam (not shown), slab 2, outer wall 3, door boundary wall 4 etc. that make up the housing of the apartment are built by reinforced concrete, steel reinforced concrete, steel frame, etc. .
[0015]
Subsequently, in the dwelling unit J formed by being divided by the slab 2, the outer wall 3, the door boundary wall 4 and the like thus formed, the interior equipment work is performed as follows.
[0016]
[Installation of wall panels]
First, as shown in FIG. 2, along the positions where the walls on both sides of the dwelling unit interior corridor C are to be formed, the lower surface of the slab (not shown) on the upper floor and the upper surface of the slab 2 on the floor are made of wood. Install upper runners 6 and 6 and lower runners 7 and 7. Further, between these upper and lower upper runners 6 and lower runners 7, for example, wooden columns 8 are attached to door frame attachment portions, wall corner portions, and the like.
[0017]
Next, the wall panel 10 that forms the wall surface of the interior corridor C, the door frame 11 that forms the entrance to each room R, and the like are fixedly installed on the upper runner 6, the lower runner 7, and the column 8.
[0018]
As shown in FIGS. 2 and 3, the wall panel 10 includes a wall surface board (board) 10a made of various board materials constituting the wall surface on the side of the dwelling unit corridor C, and a base material 10b made of a wooden square or the like. These are integrated and manufactured in advance in factories and the like. The base material 10b has a function for attaching the wall surface board 12 to the opposite surface side of the wall surface board 10a, a function as a column that bears the strength of the wall itself after the board construction on both sides, and the like has been previously applied. It is a thing.
[0019]
As shown in FIG. 2, the wall panel 10 is preinstalled with a wiring fixture 13 for locking the wiring at a position above the ceiling surface. The type of the wiring fixture 13 is not specifically limited at all. However, in order to easily perform the wiring work, a structure that can lock the wiring with one touch is desirable.
[0020]
As shown in FIG. 4, the door frame 11 is also assembled in a predetermined shape in a factory or the like, and here, the height of the upper end is set to be substantially equal to the ceiling level L of the dwelling unit interior corridor C. Has been.
[0021]
When installing the wall panel 10 and the door frame 11, first, the wall panel 10 and the door frame 11 are sequentially built from one end side of the dwelling unit interior corridor C. That is, as shown in FIGS. 3 and 5, the wall panel 10A located at one end of the dwelling unit interior corridor C is set at a predetermined position, and the upper runner 6, the lower runner 7, the column 8 (see FIG. 3), etc. After fixing to the wall panel 10A, the door frame 11B adjacent to the wall panel 10A is pushed toward the wall panel 10A attached earlier as shown by the arrow in FIG. 3), the end of the wall panel 10A is fitted. Next, the wall panel 10C and the door frame 11D to be installed are similarly pushed in one direction and built in predetermined positions.
[0022]
In addition, as shown in FIG. 1, not only the walls of the corridor C in the dwelling unit but also the walls 15 that partition the surrounding rooms R are similarly installed with wall panels unitized in advance in a predetermined shape. Go.
[0023]
Next, as shown in FIG. 6, the high- and low-power wirings 16 in the dwelling unit such as an outlet or a lighting switch attached to the wall surface are arranged. The wiring 16 is locked to the wiring fixture 13 of the wall panel 10.
[0024]
[Installation of ceiling unit and wiring piping]
As shown in FIG. 7, after the installation of the wall panels 10 constituting the walls on both sides of the dwelling unit interior corridor C, the ceiling unit 17 constituting the ceiling is installed.
The ceiling unit 17 is composed of a leading unit (prior ceiling unit) 17A that is attached in advance, and a retrofit unit (prior ceiling unit) 17B that is followed and attached, and the leading unit 17A has a length (dwelling unit). (Dimension in the direction in which the inner corridor C continues) is set to be sufficiently shorter than the length of the retrofit unit 17B.
[0025]
As shown in FIG. 6, first, the plurality of leading units 17 </ b> A are attached at a predetermined height with a predetermined interval (the length dimension of the retrofit unit 17 </ b> B) in the direction in which the dwelling unit interior corridor C continues. The attachment is performed by fixing both ends of the leading unit 17A to the wall panel 10 using various joining means such as nails.
[0026]
Next, as shown in FIG. 1, the main wiring piping work that is drawn from the common corridor T into each dwelling unit J is performed. Prior to this, piping for gas and water supply is concentrated, and the wash surface has many branch points. At the entrance of R1 and toilet R2, the ceiling unit constituting the ceiling of this part is first installed as a temporary storage ceiling unit 19.
[0027]
Then, as shown in FIG. 8, a reel 20 that is wound in a round shape is placed on the upper surface of the temporary storage ceiling unit 19.
On the side of each room R from the temporary ceiling unit 19, wiring and piping (wiring, piping) 21 are unwound from the reel 20 on the temporary ceiling unit 19, and wiring for lighting and outlets is performed.
On the other hand, on the side of the corridor C from the temporary ceiling unit 19, as shown in FIG. 6, the leading units 17 A, 17 A,... Pass wiring and piping 21 through the upper space.
At this time, the temporary ceiling unit 19 and the tipping units 17A, 17A,... Are substantially at the same level, and therefore, there is an extra tension on the wiring or piping 21 unwound from the reel 20 placed on the ceiling unit 17. Power is not applied.
[0028]
Thereafter, as shown in FIG. 7, the retrofit unit 17B of the dwelling unit interior corridor C is attached. As shown in FIG. 9, the retrofit unit 17 </ b> B is a unit in which a pipe saddle (saddle) 26 for fixing wiring and pipes 21 is attached to a ceiling frame 25 that forms the ceiling surface of the dwelling unit interior corridor C. .
After attaching and fixing the retrofit unit 17B between the front units 17A and 17A, as shown in FIG. Thereafter, a finishing material such as a predetermined board is attached to the ceiling frame 25.
[0029]
As shown in FIG. 11, a wall surface board 12 constituting the wall surface of each room R adjacent to the dwelling unit corridor C is further attached to the back side of the wall panel 10 by using a joining means such as a screw. It fixes to the material 10b.
[0030]
Thereby, the installation of the ceiling unit 17 and the wiring piping work of the dwelling unit interior corridor C are completed, and the dwelling unit interior corridor C is completed.
[0031]
It should be noted that the installation of furniture other than the corridor C in the dwelling unit, such as unit baths, toilets, kitchen units, etc., and the interior construction of each room R, will not interfere with the progress of the construction of the corridor C in the dwelling unit. The construction will be carried out at the required timing.
[0032]
As described above, in order to construct the dwelling unit interior corridor C where the main wiring pipes in each dwelling unit J are concentrated on the back of the ceiling continuously in one direction, after the wall panel 10 is installed, the tip unit that forms the ceiling 17A is installed at predetermined intervals, and wiring and piping 21 are passed over these advance units 17A, and then the retrofit unit 17B is installed between the advance units 17A and 17A. By thus unitizing the interior of the dwelling unit interior corridor C with the wall panel 10 and the ceiling unit 17, the interior of the dwelling unit interior corridor C and the construction of the facilities can be systematically performed, and the construction efficiency can be improved. it can. Moreover, the main wiring and piping 21 passing through the ceiling of the interior corridor C can be performed collectively by a multi-skilled worker who builds the wall panel 10 and the ceiling unit 17. Since it is only necessary for a specialized contractor to connect only to the facilities and gas facilities, the construction efficiency can be increased in this respect as well, and the construction period can be shortened and the construction cost can be reduced.
[0033]
The wall panel 10 has a configuration in which the base material 10b is integrally attached to the wall board 10a in advance. After the wall panel 10 is installed, wiring or the like is performed in the wall, and then the other side of the wall is formed. The wall board 12 is attached to the wall panel 10. Thereby, it is only necessary to provide the minimum support column 8 for fixing the wall panel 10, the installation work of the base material at the site can be reduced, and the efficiency of the construction of the wall and the ceiling can be improved.
[0034]
Further, when the wall panel 10 is installed, the wall panel 10 and the door frame 11 are assembled by one-pressing sequentially from one end side to the other end side of the dwelling interior corridor C. Thereby, the unitized wall panel 10 and door frame 11 can be assembled efficiently.
[0035]
In addition, the retrofit unit 17B of the ceiling unit 17 has a configuration in which a ceiling frame 25 that forms a ceiling surface and a piping saddle 26 that fixes the piping and the piping 21 on the upper surface side thereof are integrally provided. As a result, the wiring and piping 21 are temporarily installed in the space behind the ceiling, and are fitted into the piping saddle 26 of the ceiling unit 17 so that the piping work can be performed easily and reliably.
[0036]
Further, when the wiring and piping 21 are arranged, the temporary ceiling unit 19 is installed at the entrance of the wash surface R1 and the toilet R2 where the wiring and piping 21 are concentrated and branching frequently, and the upper surface of the temporary ceiling unit 19 is installed. The reel 20 or the like is placed on the wiring, and the wiring, the piping 21 or the like is unwound from here. Conventionally, unwinding work of wiring and piping is performed on the floor, and this may cause tensile force to act on the wiring and piping 21 or the like, and the assembled base material may be damaged by the tensile force. . On the other hand, according to the above configuration, by installing the temporary ceiling unit 19 at the ceiling level, the temporary ceiling unit 19 and the prior units 17A, 17A,... The wiring and piping 21 unwound from the reel 20 are not subjected to excessive tensile force and the like, and the construction can be performed smoothly and reliably. Moreover, on the side of the dwelling unit corridor C, it is only necessary to draw each main wiring and pipe 21 as they are into the common corridor T side, so that the work can be easily performed. In addition, since the temporary ceiling unit 19 is formed by a ceiling unit that constitutes the ceiling of this portion, the temporary installation unit 19 is used as it is after the completion of the wiring and piping work, and the labor of construction can be saved.
[0037]
In the above embodiment, a construction construction method of such interior equipment in the present invention, for example, it is configured to apply to the dwelling in the corridor C in each dwelling unit J of apartments, of course no to those for the floor plan is that the Needless to say, it is not limited, and if the space is continuous in one direction and the wiring, piping, etc. are concentrated on the back of the ceiling, multiple rooms are located along the corridor in the dwelling unit. The present invention can be applied in exactly the same manner to other spaces such as an outer corridor of a condominium and a corridor in a hotel.
[0038]
Further, there is no question about the specific configuration of each member constituting the dwelling unit interior corridor C, for example, the structure, shape, material, and the like of the wall panel 10, the door frame 11, and the ceiling unit 17.
[0039]
Moreover, in the said embodiment, although the door frame 11 shall have the height of the ceiling level of the dwelling unit interior corridor C, of course, there is no problem even if it is lower than that, and in that case, in the upper part of the door frame 11 A panel or the like that closes the gap with the ceiling unit 17 may be installed.
[0040]
Furthermore, the wiring and the piping 21 arranged in the space above the ceiling unit 17 are not limited to electricity, gas, water, etc. as described above, and can be applied to the duct for ventilation, for example, in the same manner. it can.
[0041]
Other than this, as long as it does not deviate from the gist of the present invention, any configuration may be adopted, and it is needless to say that the above-described configurations may be appropriately combined.
[0042]
【The invention's effect】
As described above, according to the construction method of the interior equipment according to claim 1, a first step of placing corridor or the like, the wall panels forming the walls of the space continuously in one direction to a predetermined position, one The second step of installing the front ceiling unit, whose length in the direction is shorter than the retrofitted ceiling unit , on the wall panel at predetermined intervals , the temporary ceiling unit is installed at the entrance of the bathroom and toilet, and then the piping wiring And a third step of placing the reel wound on the temporary ceiling unit, unwinding the pipe from the reel on the temporary ceiling unit, and passing the pipe to the upper surface of the front ceiling unit. And a fourth step of attaching the retrofit ceiling unit between the front and rear advancement ceiling units. In this way, construction of a space continuous in one direction such as a corridor can be systematically performed, and construction efficiency can be improved. Moreover, the main wiring and piping passing through the ceiling behind the corridor can be performed collectively by multi-functional workers who build wall panels and ceiling units, and are connected to hot water and gas facilities in each room. Since it is only necessary for each of the specialists to perform the connection, the construction efficiency can be improved in this respect, and the construction period can be shortened and the construction cost can be reduced. Also, when installing pipes, etc., a temporary ceiling unit is installed at the entrance of the bathroom or toilet, a reel is placed on the temporary ceiling unit, and the pipe is unwound from the reel. It has become. Thereby, work can be performed easily.
[0043]
According to the construction method of the interior equipment according to claim 2, the wall panel has a configuration in which the base material is integrally attached to a board that forms one side of the wall in advance, and after the wall panel is installed in the first step. Has a configuration in which wiring or the like is performed in the wall, and then a board that forms the other side of the wall is attached to the wall panel. Thereby, it is only necessary to provide a minimum support column for fixing the wall panel, the installation work of the base material can be reduced, and the efficiency of the construction of the wall and the ceiling can be improved.
[0044]
According to the interior equipment construction method according to claim 3, when installing the wall panel in the first step, the wall panel, the frame forming the entrance / exit, the opening, and the like are moved from one end of the space to the other end. It is structured to be assembled sequentially toward the side. Thereby, the unitized wall panel and frame can be assembled efficiently.
[Brief description of the drawings]
[1] an example of spatial applying the construction construction method of the interior equipment according to the present invention, is a plan layout diagram showing a corridor dwelling units of condominiums.
FIG. 2 is a perspective view showing a construction process of interior equipment in the hallway, and shows a state in which a wall panel is attached.
FIG. 3 is a plan sectional view showing a wall of the hallway.
FIG. 4 is an elevational view of the same wall.
FIG. 5 is a view showing a method for attaching the wall panel and the door frame.
FIG. 6 is a diagram showing a construction process of the interior equipment in the hallway, and is a perspective view showing a state where a front ceiling unit is attached and wiring and piping are passed.
FIG. 7 is a perspective view showing a state where a retrofit ceiling unit is attached.
FIG. 8 is a perspective view showing a wiring and piping arrangement method.
FIG. 9 is a perspective view showing the retrofit ceiling unit.
FIG. 10 is a diagram showing a construction process of the interior equipment in the hallway, and is a perspective view showing a completed state in which the ceiling unit is attached.
FIG. 11 is a perspective view showing a state in which the board constituting the wall surface is attached to the other surface side of the wall panel.
[Explanation of symbols]
10 Wall Panel 10a Wall Board (Board)
10b Base material 11 Door frame 17 Ceiling unit 17A Pre-attached unit (Pre-attached ceiling unit)
17B Retrofit unit (retrofitted ceiling unit)
21 Wiring and piping (wiring, piping)
25 Ceiling frame 26 Saddle for piping (saddle)
C Dwelling hallway (space)

Claims (3)

廊下等、一方向に連続する空間への内装設備の施工工法であって、
前記空間の壁を形成する壁パネルを所定の位置に設置する第一の工程と、
前記一方向への長さ寸法が後付け天井ユニットよりも短い先付け天井ユニットを、前記空間の連続する方向において所定間隔ごとに前記壁パネルに設置する第二の工程と、
洗面やトイレの入り口部分に仮置き天井ユニットを設置し、次いで配管配線を束ねて巻いたリールを前記仮置き天井ユニット上に載置して、前記仮置き天井ユニット上のリールから配管等を巻き出して前記先付け天井ユニットの上面側に配管等を通す第三の工程と、
互いに前後する前記先付け天井ユニット間に後付け天井ユニットを取り付ける第四の工程と、
からなることを特徴とする内装設備の施工工法
A construction method for interior equipment in a space that continues in one direction, such as a corridor,
A first step of installing a wall panel forming a wall of the space at a predetermined position;
A second step of installing a front ceiling unit whose length dimension in one direction is shorter than a retrofitted ceiling unit on the wall panel at predetermined intervals in the continuous direction of the space;
Install a temporary ceiling unit at the entrance to the bathroom or toilet, and then place a reel of bundled pipe wiring on the temporary ceiling unit and wind pipes, etc. from the reel on the temporary ceiling unit. A third step of taking out the piping etc. through the upper surface side of the advanced ceiling unit;
A fourth step of attaching a retrofit ceiling unit between the precedent ceiling units that move back and forth with each other;
Construction method of interior equipment characterized by comprising
請求項1記載の内装設備の施工工法において、前記壁パネルが、該壁パネルの骨格をなす下地材を、壁の一面側を形成するボードに予め一体に取り付けた構成からなり、
前記第一の工程で前記壁パネルを設置した後には、壁内に配線等を行い、しかる後に前記壁の他面側を形成するボードを前記壁パネルに取り付けることを特徴とする内装設備の施工工法
In the construction method of the interior equipment according to claim 1, the wall panel has a configuration in which a base material that forms a skeleton of the wall panel is integrally attached to a board that forms one side of the wall in advance.
After installing the wall panel in the first step, wiring is performed in the wall, and then a board forming the other side of the wall is attached to the wall panel. Construction method .
請求項1または2記載の内装設備の施工工法において、前記第一の工程で前記壁パネルを設置するに際しては、前記壁パネルや、出入口や開口部等を形成する枠体を、前記空間の一端側から他端側に向けて順次組み付けていく構成としたことを特徴とする内装設備の施工工法3. The construction method for interior equipment according to claim 1 or 2, wherein when installing the wall panel in the first step, the wall panel, a frame forming an entrance / exit, an opening, or the like is used as one end of the space. A construction method for interior equipment, characterized in that it is assembled sequentially from the side toward the other end.
JP03937698A 1998-02-20 1998-02-20 Construction method for interior equipment Expired - Fee Related JP3713652B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP03937698A JP3713652B2 (en) 1998-02-20 1998-02-20 Construction method for interior equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP03937698A JP3713652B2 (en) 1998-02-20 1998-02-20 Construction method for interior equipment

Publications (2)

Publication Number Publication Date
JPH11236746A JPH11236746A (en) 1999-08-31
JP3713652B2 true JP3713652B2 (en) 2005-11-09

Family

ID=12551322

Family Applications (1)

Application Number Title Priority Date Filing Date
JP03937698A Expired - Fee Related JP3713652B2 (en) 1998-02-20 1998-02-20 Construction method for interior equipment

Country Status (1)

Country Link
JP (1) JP3713652B2 (en)

Also Published As

Publication number Publication date
JPH11236746A (en) 1999-08-31

Similar Documents

Publication Publication Date Title
US2168725A (en) Building construction
US7765745B2 (en) Reusable worker housing and methods relating thereto
US20140000192A1 (en) Wall assembly for a building structure
JP3713652B2 (en) Construction method for interior equipment
EP2973910A1 (en) Single and multi-part prefabricated interior finish layer assemblies, building wall assemblies, and methods of manufacturing these assemblies
US3605354A (en) Construction unit
JP3140229B2 (en) Dwelling unit variable housing system
WO2006125844A1 (en) Procedure for the construction of partitions with siding boards and partitions thus obtained
JP2002097730A (en) Fixing structure for partition wall
AU2011201797A1 (en) Prefabricated Room Assembly
JP4849997B2 (en) Mounting structure for short piping under the wall
KR100438259B1 (en) Light-weight wall system
CA2776267C (en) Brackets and covers for electrical wire routing at interior corners of a building
JP2771759B2 (en) Building and building renovation methods
KR200228583Y1 (en) The fixation device for light-weight wall
JPH11124985A (en) Floor device for outdoor use
JP3281095B2 (en) Aluminum frame structure
JP2001324052A (en) Piping box unit for building and its construction method
JPH05295815A (en) Wall panel for facility piping and wiring and facility piping and wiring work
JP3190201B2 (en) Underfloor piping structure of building unit
JP2001123681A (en) Unit type kitchen and sanitary space facility
JPH073938A (en) Panel for building unit
JP2002054265A (en) Ceiling structure of concrete structure building
JP2008050871A5 (en)
JPH11182077A (en) Toilet unit

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040628

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040713

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040907

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050419

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050613

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050712

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050811

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees