JP3695824B2 - Construction method by reverse driving method in underground construction - Google Patents
Construction method by reverse driving method in underground construction Download PDFInfo
- Publication number
- JP3695824B2 JP3695824B2 JP04887796A JP4887796A JP3695824B2 JP 3695824 B2 JP3695824 B2 JP 3695824B2 JP 04887796 A JP04887796 A JP 04887796A JP 4887796 A JP4887796 A JP 4887796A JP 3695824 B2 JP3695824 B2 JP 3695824B2
- Authority
- JP
- Japan
- Prior art keywords
- column
- construction
- slab
- reinforcement
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Description
【0001】
【発明の属する技術分野】
本発明は地下工事における逆打工法による構築方法、更に詳細に説明すると柱筋の配筋方法に係るものである。
【0002】
【従来の技術】
従来、地下工事における柱筋の施工においては、図4(イ)に示すように柱配筋が可能になる梁下の位置まで掘削を行った後、図4(ロ)に示すように掘削底部上に配設した足場aにより柱筋bを圧接、配筋し、図4(ハ)に示す如く柱の下部となる梁、スラブの型枠cを組み立て、図4(ニ)に示す如く梁、スラブdのコンクリートを打設する。
【0003】
更に図4(ホ)に示す如く同梁、スラブdの下部を掘削し、前記工程を反覆して作業床d’の施工が完了した段階で、柱fのコンクリートを打設している。(図4(ヘ)参照)
【0004】
【発明が解決しようとする課題】
しかしながら前記従来の方法によれば柱筋の配筋の施工においては、(イ)柱筋の配筋を下部の梁下まで行うので、下部より1m程度下がった位置まで掘削を行うこととなり、掘削土工量が大で、多くの手間を要する。また(ロ)柱筋の配筋において溶接ジョイントが梁下となり、掘削が梁下まで施工された時に行われるため、足場組を行い足場上での高所作業となり、また足場の組立、解体作業工程を行う。
【0005】
本発明は前記従来技術の有する問題点に鑑みて提案されたもので、その目的とするところは仮設工事が節減され、施工性が大幅に向上された地下工事における逆打工法による構築法を提供する点にある。
【0006】
【課題を解決するための手段】
前記の目的を達成するため、本発明に係る地下工事における逆打工法による構築法によれば、被構築物の柱を構築する位置に仮支柱を立設し、構築しようとする下階部の梁下位置まで掘削し、当該下階部の梁スラブの型枠を建込み、前記型枠内の配筋しようとする柱筋に対応した位置に、帯筋を設けたパイプを配設して柱筋の貫通口を確保し、前記型枠内に梁スラブのコンクリートを打設することで前記仮支柱に固定された梁スラブを構築し、前記パイプ内に柱筋を挿通し、その挿通した柱筋5の上端を、上の階から垂下している柱筋の下端に圧接し、前記パイプ内にグラウトを注入して柱筋を前記梁スラブと一体化するものである。
【0007】
【発明の実施の形態】
以下、本発明を図面に示す本発明の最も好ましい形態について説明する。
図1(イ)に示すように、被構築物の柱を構築する位置に仮支柱2を立設したのちに、 構築しようとする下階部の梁下部の止め枠1が組立てられる位置まで掘削し、この時点ではまだ当該下階部の柱の柱筋の施工を行わない。次いで当該下階部の梁スラブ4の型枠を建込み、その型枠内の仮支柱2を囲繞する位置(配筋しようとする柱筋に対応した位置)に、帯筋8を設けたにワインディングパイプ3を配設して柱筋の貫通口を確保し、その型枠内に梁スラブ4のコンクリートを打設することで仮支柱2に固定された梁スラブ4を構築する。(図1(ロ)参照)
次いで図1(ハ)に示す如く更に下の下階部の掘削工程を完了したのち、既に梁スラブのコンクリートの打設を完了している上述した下階部(スラブ既設階)の前記ワインディングパイプ3によって画成された柱筋貫通口に柱筋5を挿通し、その挿通した柱筋5の上端を、前記スラブ既設階の上の階から垂下している柱筋5の下端に圧接する。これによって前記スラブ既設階の柱筋5は、前記ワインディシングパイプ3内に通されて配筋された状態になる(図1(ニ)及び(ホ)参照)。次いで、同柱筋貫通口にグラウト6を注入して前記ワインディングパイプ3内の柱筋5と同パイプ3との間隙を充填し(図1(ヘ)、及び図2、図3参照)、これによって柱筋5を梁スラブ4と一体化する。
なお図中8は帯筋、wは柱筋5の圧接部である。
【0008】
【発明の効果】
本発明によれば前記したように、被構築物の柱を構築する位置に仮支柱を立設し、構築しようとする下階部の梁下位置まで掘削し、当該下階部の梁スラブの型枠を建込み、前記型枠内の配筋しようとする柱筋に対応した位置に、帯筋を設けたパイプを配設して柱筋の貫通口を確保し、前記型枠内に梁スラブのコンクリートを打設することで前記仮支柱に固定された梁スラブを構築し、前記パイプ内に柱筋を挿通し、その挿通した柱筋の上端を、上の階から垂下している柱筋の下端に圧接し、前記パイプ内にグラウトを注入して柱筋を前記梁スラブと一体化することにより、柱筋の施工は施工が完了した本設のスラブ上での作業となり、柱筋の圧接も一般工法における柱筋圧接位置と同じスラブ上1メートル程度での作業とすることができるため、従来工法における如き足場が不要となり、施工性が著しく向上する。
【0009】
また掘削作業については、梁下の止め枠が施工できる位置までの掘削となり、梁下止め枠を掘削面で直接受けることができ、梁支保工が不要となり、更に掘削土工量が節減され、施工性が向上する。
【0010】
【図面の簡単な説明】
【図1】 (イ)(ロ)(ハ)(ニ)(ホ)(ヘ)は本発明に係る地下工事における逆打工法による構築法の作業工程を示す縦断面図である。
【図2】 柱配筋の詳細を示す拡大平面図である。
【図3】 図2の縦断面図である。
【図4】 (イ)(ロ)(ハ)(ニ)(ホ)(ヘ)は従来工法の作業工程を示す縦断面図である。
【符号の説明】
1 止め枠
2 仮支柱
3 ワインディングパイプ
4 梁スラブ
5 柱筋
6 グラウト
7 型枠組
8 帯筋
w 柱筋の圧接部[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method using a reverse driving method in underground construction, and more specifically to a column reinforcement arrangement method.
[0002]
[Prior art]
Conventionally, in the construction of column reinforcement in underground construction, after excavating to a position below the beam where column reinforcement is possible as shown in FIG. 4 (a), the bottom of the excavation is shown in FIG. 4 (b). The column reinforcement b is pressed and arranged by the scaffold a disposed above, and a beam and a slab form c as shown in FIG. 4 (c) are assembled, and the beam as shown in FIG. 4 (d) is assembled. The concrete of slab d is laid.
[0003]
Further, as shown in FIG. 4 (e), the lower part of the beam and the slab d is excavated, and the concrete of the column f is placed when the work floor d 'is completed by repeating the above process. (See Fig. 4 (f))
[0004]
[Problems to be solved by the invention]
However, according to the above-mentioned conventional method, in the reinforcement of column reinforcement, (b) the reinforcement of the column reinforcement is carried out to the lower beam, so that the excavation is carried out to a position about 1 m below the lower part. The amount of earthwork is large and requires a lot of work. (B) Since the welding joint is under the beam and the excavation is performed to the bottom of the beam in the reinforcement of the column reinforcement, the scaffolding is performed and the work is performed at a high place on the scaffolding, and the scaffold is assembled and disassembled. Perform the process.
[0005]
The present invention has been proposed in view of the above-described problems of the prior art, and the object of the present invention is to provide a construction method by a reverse driving method in underground construction in which temporary work is reduced and workability is greatly improved. There is in point to do.
[0006]
[Means for Solving the Problems]
In order to achieve the above object, according to the construction method by the reverse driving method in the underground work according to the present invention , a temporary support column is erected at the position for constructing the pillar of the construction object, and the beam of the lower floor part to be constructed is constructed. It was drilled to a lower position, the formwork beam slab of the lower floor portion Kenkomi, at a position corresponding to the pillar muscle to be reinforcement in the mold, by arranging a pipe provided with a hoop pillar Build a beam slab fixed to the temporary support by placing a beam slab concrete in the formwork to secure a through- hole of the line, insert a column bar into the pipe, and the inserted column The upper end of the
[0007]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the present invention will be described with reference to the most preferred embodiments of the present invention shown in the drawings.
As shown in FIG. 1 (a), after the
Then after further completing the excavation process of the lower floor portion of the lower, as shown in FIG. 1 (c), the winding pipe of the lower floor portion already mentioned above have completed pouring of the concrete beam slab (slab existing floor) 3 through interpolation the
In the figure, 8 is a band, and w is a pressure contact portion of the
[0008]
【The invention's effect】
According to the present invention, as described above, a temporary support column is erected at a position for constructing a pillar of the construction object, and is excavated to a position below the beam on the lower floor portion to be constructed, and a beam slab pattern on the lower floor portion is constructed. A frame is installed, and a pipe with a bar is provided at a position corresponding to the column reinforcement to be arranged in the formwork to secure a through- hole for the column reinforcement, and a beam slab in the formwork. A beam slab fixed to the temporary support column is constructed by placing the concrete of the column, a column reinforcement is inserted into the pipe, and the upper end of the inserted column reinforcement is suspended from the upper floor. of pressure contact with the lower end, by Rukoto the pillar muscle by injecting grout into the pipe turn into integral with the beam slab, construction of pillars muscle becomes a work on the slab of this set which construction has been completed, the pillars muscle of pressure also may be working on the same slab on the order of one meter pillars muscle pressing position in the general method , Such as scaffolding is not needed in the conventional method, workability is significantly improved.
[0009]
For excavation work, drilling is performed up to the position where the stop frame under the beam can be constructed, the beam stop frame can be directly received by the excavation surface, beam support work is not required, and the excavation earth work amount is further reduced. Improves.
[0010]
[Brief description of the drawings]
FIGS. 1A, 1B, 1C, and 1E are longitudinal sectional views showing work steps of a construction method using a reverse driving method in underground construction according to the present invention.
FIG. 2 is an enlarged plan view showing details of column reinforcement.
3 is a longitudinal sectional view of FIG.
4 (a), (b), (c), (d), (e), and (f) are vertical cross-sectional views showing work steps of a conventional method.
[Explanation of symbols]
DESCRIPTION OF
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP04887796A JP3695824B2 (en) | 1996-03-06 | 1996-03-06 | Construction method by reverse driving method in underground construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP04887796A JP3695824B2 (en) | 1996-03-06 | 1996-03-06 | Construction method by reverse driving method in underground construction |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH09242092A JPH09242092A (en) | 1997-09-16 |
JP3695824B2 true JP3695824B2 (en) | 2005-09-14 |
Family
ID=12815523
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP04887796A Expired - Fee Related JP3695824B2 (en) | 1996-03-06 | 1996-03-06 | Construction method by reverse driving method in underground construction |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3695824B2 (en) |
-
1996
- 1996-03-06 JP JP04887796A patent/JP3695824B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH09242092A (en) | 1997-09-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3728654B2 (en) | Building dismantling and construction methods | |
JP4881555B2 (en) | Construction method of underground structure | |
KR102286225B1 (en) | Method for constructing underground structure busing PC integrating method without support | |
CN109898669B (en) | Construction method for underground first-layer beam column joint by reverse construction method | |
JP3625892B2 (en) | Construction method of underground structure using precast concrete column | |
KR100673475B1 (en) | A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof | |
JP3695824B2 (en) | Construction method by reverse driving method in underground construction | |
KR0179708B1 (en) | Working method for underground structure of a building | |
KR100562686B1 (en) | The underground structure and it's construction method is using sheet pile and cast in a place concrete | |
JP6514739B2 (en) | Construction method for forming underground structure and underground structure completed thereby | |
KR20110034831A (en) | Method for non excavated excavating construction using steel pipe and steel pipe with hole | |
KR100722198B1 (en) | Strut system of temporary retaining wall and subgrade external wall construction method utilizing the same | |
JPH0754364A (en) | Construction method of basement floor | |
JPH10317374A (en) | Method for constructing underground column made of reinforced concrete | |
JPH04185816A (en) | Construction of beam in underground wall | |
JP2794330B2 (en) | Method of erection of girder beam for underground structure | |
KR101028695B1 (en) | A method of PC-girder jointing for top down-construction | |
JPH11166242A (en) | Underground space constructing method and supporting structure in underground space construction | |
KR200372405Y1 (en) | Underground tunnel structure using steel tubes | |
JP2757107B2 (en) | Reinforcement arrangement structure in reverse hitting method | |
JPH0430026A (en) | Constructing method of underground structure | |
JP2506978Y2 (en) | Synthetic retaining wall | |
JPH10299003A (en) | Foundation work using precast concrete member | |
JPS6217233A (en) | Foundation base column | |
KR200405652Y1 (en) | A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050406 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050408 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050513 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050628 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050628 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080708 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090708 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100708 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100708 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110708 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120708 Year of fee payment: 7 |
|
LAPS | Cancellation because of no payment of annual fees |