JP3671343B2 - Foundation construction method - Google Patents

Foundation construction method Download PDF

Info

Publication number
JP3671343B2
JP3671343B2 JP2000102218A JP2000102218A JP3671343B2 JP 3671343 B2 JP3671343 B2 JP 3671343B2 JP 2000102218 A JP2000102218 A JP 2000102218A JP 2000102218 A JP2000102218 A JP 2000102218A JP 3671343 B2 JP3671343 B2 JP 3671343B2
Authority
JP
Japan
Prior art keywords
steel pipe
concrete
pile head
pile
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2000102218A
Other languages
Japanese (ja)
Other versions
JP2001288755A (en
Inventor
泰秀 持田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2000102218A priority Critical patent/JP3671343B2/en
Publication of JP2001288755A publication Critical patent/JP2001288755A/en
Application granted granted Critical
Publication of JP3671343B2 publication Critical patent/JP3671343B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)
  • Joining Of Building Structures In Genera (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は建物の基礎に係わり、特に杭頭部と柱脚部とを鋼管を介して軸方向に接合する構造の基礎を施工するための方法に関する。
【0002】
【従来の技術】
建物の基礎としては杭頭部と柱脚部と基礎梁とをフーチングを介して接合するものが最も一般的であるが、より簡略で合理的な基礎の構造として、図13に示すように杭1と柱2とを直接的に接合して基礎梁およびフーチングを省略することが近年試みられている。そのような構造では杭1と柱2とを確実強固に接合するべく、たとえば図14に示すように、柱脚を杭頭に対してアンカー3により直接的に接合することに加え、杭頭部と柱脚部に跨るように鋼管4を外挿してその内部にコンクリート5を打設充填することで接合強度を確保することが提案されている(特開平11−100854号公報)。
【0003】
【発明が解決しようとする課題】
上記のような構造の基礎は従来一般の基礎より十分な簡略化を実現できることから広く普及する気運にあるが、現時点では試行的に施工されるに留まっていてそのための施工方法は未だ確立されておらず、そのような構造の基礎を合理的に施工するための有効適切な施工方法の開発が急務とされている。
【0004】
【課題を解決するための手段】
上記事情に鑑み、請求項1の発明は、杭頭部と柱脚部とを鋼管を介して軸方向に接合してなる基礎を施工するに際し、杭を施工した後、杭頭部に鋼管の下半部を装着して該鋼管内にコンクリートを打設することにより該鋼管の下半部を杭頭部に対して固定し、しかる後に該鋼管内に柱脚部を挿入して柱を立設し、該鋼管内にコンクリートをさらに打設して柱脚部を鋼管に対して固定するようにしたものである。
【0005】
請求項2の発明は、請求項1の発明の施工方法において、前記鋼管を杭頭部に装着するに際し、該鋼管の内面に突設せしめたスペーサを杭頭部周面に当接せしめることで該鋼管の径方向の位置決めを行うようにしたものである。
【0006】
請求項3の発明は、請求項1または2の発明の施工方法において、前記鋼管を杭頭部に装着するに際し、杭頭部の周囲に捨てコンクリートを打設し、該捨てコンクリートにより前記鋼管の下端を支持せしめて該鋼管の上下方向の位置決めを行いかつ鉛直建て込み精度を確保するようにしたものである。
【0009】
請求項4の発明は、請求項1,2または3の発明の施工方法において、前記柱の柱脚部にスタッドを設けておくことで該柱脚部のコンクリートに対する定着強度を高めるようにしたものである。
【0010】
【発明の実施の形態】
図1〜図12を参照して本発明の実施形態を説明する。まず、本発明の施工方法が対象としている基礎の構造について図1〜図3を参照して概略説明する。その基礎は図13および図14に示したものと基本的に同様の構造のもので、本例では図1に示すように柱2および梁6からなる単層(平屋建て)の鉄骨造建物に適用され、杭1と柱2とが鋼管4を介して軸方向に接合されることにより通常の基礎における基礎梁とフーチングとが省略されたものである。
【0011】
上記の基礎の構造を図2および図3によりさらに説明すると、本例では杭1としてPHC杭が採用されてそれが地盤に打ち込まれ、その杭頭部には杭径よりやや大径の鋼管4の下半部が装着され、鋼管4の上半部には角形鋼管からなる柱2の柱脚部が挿入され、その鋼管4内全体にコンクリート5が打設充填されることでそのコンクリート5および鋼管4を介して杭頭部と柱脚部とが確実強固に接合されている。符号7は捨てコンクリート、8は柱脚部に設けたスタッド、9は地盤改良体、10はこの建物の1階床面となる土間コンクリートであるが、これらについては後述する。
【0012】
上記構造の基礎の施工方法を図4〜図12を参照して詳細に説明する。
【0013】
図4に示すように杭1を地盤に打ち込んだ後、図5に示すように杭頭部の周囲を根切りして杭頭部を露出せしめ、その根切り底に捨てコンクリート7を打設し、鋼管4を杭頭部に装着して捨てコンクリート7を支持面として建て込む。その際、捨てコンクリート7により鋼管4の上下方向の位置決めを行うとともに建て込み精度を確保し、径方向の位置決めは図11に示すように鋼管4内に予め突設せしめておいたスペーサ11により行う。
【0014】
スペーサ11は鋼管4の内周面に沿って等間隔で少なくととも3カ所に取り付けておき、鋼管4を杭頭部に装着するとそれらスペーサ11によって杭頭部との間に自ずと適正かつ均等な間隔が確保されるようにしておく。なお、図示しているように、スペーサ11を上下2段にわたって設けておくことにより鋼管4の鉛直建て込み精度を自ずと確保できるし、スペーサ11を逆三角形状としておくと、鋼管4を装着する際にスペーサ11の斜面により鋼管4が径方向に自ずと案内されるので装着作業を容易に行い得る。さらに、このスペーサ11は鋼管4内に打設充填されるコンクリート5に対する定着強度を高めるためのスタッドとしても機能する。
【0015】
次に、図6に示すように鋼管4内の下半部にコンクリート5を打設して杭頭部を埋設し、杭頭部に対して鋼管4を固定する。本実施形態では杭1がPHC杭等の中空杭であるので、コンクリート5の打設に先立って杭1内にコンクリート止めとなる閉塞板12を取り付ける。閉塞板12の取付位置は鋼管4の下端レベルとする。
【0016】
上記のコンクリート5の打設工程と相前後して、図7に示すように杭頭部の周囲を埋め戻し、転圧を行った後、地盤表層部に対して地盤改良を行って層状の地盤改良体9を形成する。この地盤改良体9は建物の1階床面となる土間コンクリート10の支持面となるとともに、建物の完成後には鋼管4およびその内部に打設充填されたコンクリート5を介して杭頭部の水平変位を拘束する機能を有するものである。地盤改良体9の厚さは適宜設定すれば良いが、たとえば350mm程度で良い。
【0017】
上記の地盤改良工程と相前後して、図8に示すように柱2を建て込む。本実施形態では柱2として角形鋼管を採用し、その柱脚部には多数のスタッド8を取り付けておき、その柱脚部を鋼管4内に挿入することで建て込む。
【0018】
その際、柱2の建て込みは図12に示す治具15および治具16を用いて次の手順で行う。治具15は柱2の芯出しを行うためのもので、レーザー測量にて鋼管4にマーキングしたポイントを基準として(a)に示すように柱芯Oを設定するものである。治具16は治具15を基準として鋼管4の上部にクランプ17により固定されることで(b)に示すように柱2の表面の位置を設定するものである。その治具16により案内することで柱2を適正位置に建て込んだら(c)に示すようにさらに同様の治具16を鋼管4に固定してそれら2台の治具16により柱2を両側から挟み込んで仮支持する。それら治具15,16はアングル材を柱2の寸法に応じて組み立てて溶接することにより簡便かつ安価に製作できるものであるし、繰り返し転用できるものである。
【0019】
そして、図9に示すように鋼管4内にコンクリート5をさらに打設し、相前後して柱2内にも所定高さまでコンクリート18を打設して少なくとも柱脚部にはコンクリート18を充填する。コンクリート5が硬化すればそのコンクリート5および鋼管4を介して杭1と柱2とが確実強固に接合される。
【0020】
その後、図10に示すように土間コンクリート10を打設して1階床面を形成する。なお、土間コンクリート10の打設に先立ち、治具16を取り外しても良い。土間コンクリート10には地盤改良体9とともに杭頭部の水平変位を拘束する機能を持たせるために土間コンクリート10を地盤改良体9と一体に形成することが好ましい。引き続いて梁6の架設等、地上部の躯体の施工を行い、建物を完成させる。
【0021】
以上の施工方法によれば、杭1と柱2とが鋼管4を介して確実強固に接合されることはもとより、杭1の施工後には、杭頭部への鋼管4の装着、コンクリート5の打設、柱2の建て込み、コンクリート5のさらなる打設、という簡便な作業を順次行うことのみで効率的な施工が可能であり、極めて施工性に優れる。
【0022】
特に、鋼管4内にスペーサ11を設けておくことで杭頭部に対する鋼管4の径方向の位置決めを容易にかつ精度良く行い得るし、鋼管4の上下方向の位置決めおよび建て込み精度の確保は捨てコンクリート7により精度良くかつ支障なく行うことができる。また、建物の完成後には、地盤の表層部に形成した層状の地盤改良体9およびその上部に形成した土間コンクリート10にて杭頭部の水平変位を拘束することができるので構造的にも安定した基礎の施工が可能である。さらに、柱脚部にはスタッド8を設けているので、コンクリート5に対する定着強度が高められ、コンクリート5および鋼管4を介しての杭1と柱2との接合強度を十分に高めることができる。
【0023】
なお、上記実施形態では杭1としてPHC杭を採用したが、それに限らず鋼管杭や場所打ちコンクリート杭等も採用可能である。また、柱2としては角形鋼管に限ることなく円形鋼管はもとよりH形鋼の鋼材も当然に採用可能である。さらに、図14に示した従来のものと同様に、柱2の柱脚にベースプレートを取り付けておいて鋼管4内のコンクリート5に対してアンカーにより定着するようにしても良い。
【0024】
また、上記実施形態では地盤改良体9と土間コンクリート10の双方に杭頭部の水平変位を拘束する機能をもたせるようにしたが、そのような機能は不要であれば省略して良いし、あるいは地盤改良体9か土間コンクリート10のいずれか一方にのみその機能を持たせることでも良い。その他、本発明は上記実施形態に限定されることなく適宜の設計的変更が可能であることは言うまでもない。
【0025】
【発明の効果】
請求項1の発明は、杭頭部と柱脚部とを鋼管を介して軸方向に接合してなる基礎を施工するに際し、杭を施工した後、杭頭部に鋼管の下半部を装着して鋼管内にコンクリートを打設することにより鋼管の下半部を杭頭部に対して固定し、しかる後に鋼管内に柱脚部を挿入して柱を立設し、鋼管内にコンクリートをさらに打設して柱脚部を鋼管に対して固定するようにしたから、簡便な作業で杭と柱とを確実強固に接合することができることはもとより極めて合理的で施工性に優れ、上記構造の基礎の施工方法として最適である。
【0026】
請求項2の発明は、鋼管の内面に突設せしめたスペーサを杭頭部周面に当接せしめることでその鋼管の径方向の位置決めを行うようにしたので、特に杭頭部に対する鋼管の径方向の位置決めを容易にかつ精度良く行い得る。
【0027】
請求項3の発明は、杭頭部の周囲に捨てコンクリートを打設し、その捨てコンクリートにより鋼管の下端を支持せしめて鋼管の上下方向の位置決めを行いかつ鉛直建て込み精度を確保するようにしたので、特に鋼管の上下方向の位置決めを捨てコンクリートにより精度良くかつ支障なく行うことができる。
【0030】
請求項4の発明は、柱の柱脚部にスタッドを設けておくので、柱脚部のコンクリートに対する定着強度を十分に高めることができる。
【図面の簡単な説明】
【図1】 本発明が施工対象としている基礎の構造を示す概要図である。
【図2】 同基礎の構造の詳細を示す立面図である。
【図3】 同、断面図である。
【図4】 本発明の実施形態である施工方法を工程順に示すもので、杭を施工した状態を示す図である。
【図5】 同、杭頭部に鋼管を装着した状態を示す図である。
【図6】 同、鋼管内にコンクリートを打設して鋼管を固定した状態を示す図である。
【図7】 同、埋め戻しと地盤改良を行った状態を示す図である。
【図8】 同、柱を建て込んだ状態を示す図である。
【図9】 同、鋼管内にさらにコンクリートを打設して柱脚部を固定した状態を示す図である。
【図10】 土間コンクリートを打設した状態を示す図である。
【図11】 同、鋼管の装着工程を示す図である。
【図12】 同、治具による柱の建方工程を示す図である。
【図13】 杭と柱とを直接的に接合する構造の基礎の従来例を示す図である。
【図14】 同基礎の構造の詳細を示す図である。
【符号の説明】
1 杭
2 柱
4 鋼管
5 コンクリート
7 捨てコンクリート
8 スタッド
9 地盤改良体
10 土間コンクリート
11 スペーサ
15,16 治具
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a building foundation, and more particularly to a method for constructing a foundation having a structure in which a pile head and a column base are joined in an axial direction via a steel pipe.
[0002]
[Prior art]
As the foundation of a building, a structure in which a pile head, a column base, and a foundation beam are joined via a footing is the most common. However, as shown in FIG. In recent years, it has been attempted to directly join 1 and the column 2 and omit the foundation beam and the footing. In such a structure, in order to securely and firmly join the pile 1 and the column 2, for example, as shown in FIG. 14, in addition to directly joining the column base to the pile head by the anchor 3, the pile head It has been proposed to secure the joint strength by extrapolating the steel pipe 4 so as to straddle the column base and placing and filling the concrete 5 therein (Japanese Patent Laid-Open No. 11-1000085).
[0003]
[Problems to be solved by the invention]
The foundation of the structure as described above seems to be widely spread because it can realize simplification more sufficiently than the conventional general foundation, but at present, the construction method for that purpose has not yet been established. However, there is an urgent need to develop an effective and appropriate construction method for rationally constructing the foundation of such a structure.
[0004]
[Means for Solving the Problems]
In view of the above circumstances, the invention of claim 1, when constructing a foundation formed by joining a pile head and a column base in the axial direction via a steel pipe, after constructing the pile, The lower half of the steel pipe is fixed to the pile head by placing concrete in the steel pipe with the lower half attached, and then the column base is inserted into the steel pipe to stand the column. And concrete is placed in the steel pipe to fix the column base to the steel pipe.
[0005]
The invention according to claim 2 is the construction method according to claim 1, wherein when the steel pipe is mounted on the pile head, the spacer projected from the inner surface of the steel pipe is brought into contact with the circumferential surface of the pile head. The steel pipe is positioned in the radial direction.
[0006]
According to a third aspect of the present invention, in the construction method of the first or second aspect of the invention, when the steel pipe is mounted on the pile head, a discarded concrete is placed around the pile head, and the steel pipe is The lower end is supported to position the steel pipe in the vertical direction and to ensure vertical erection accuracy.
[0009]
According to a fourth aspect of the present invention, in the construction method according to the first, second or third aspect of the present invention, the fixing strength of the column base to the concrete is increased by providing a stud on the column base of the column. It is.
[0010]
DETAILED DESCRIPTION OF THE INVENTION
An embodiment of the present invention will be described with reference to FIGS. First, the basic structure targeted by the construction method of the present invention will be schematically described with reference to FIGS. The foundation is basically the same as that shown in FIGS. 13 and 14, and in this example, as shown in FIG. 1, a single-layer (one-storied) steel-frame building consisting of columns 2 and beams 6 is used. The foundation beam and footing in a normal foundation are omitted by applying the pile 1 and the column 2 in the axial direction via the steel pipe 4.
[0011]
2 and 3 further explain the structure of the foundation described above. In this example, a PHC pile is employed as the pile 1 and is driven into the ground, and a steel pipe 4 having a diameter slightly larger than the pile diameter is placed on the pile head. The lower half of the steel pipe 4 is mounted, and the column base of the pillar 2 made of a square steel pipe is inserted into the upper half of the steel pipe 4, and the concrete 5 and the concrete 5 The pile head and the column base are securely and firmly joined to each other via the steel pipe 4. Reference numeral 7 is abandoned concrete, 8 is a stud provided on the column base, 9 is a ground improvement body, and 10 is a soil concrete which becomes the first floor of the building, which will be described later.
[0012]
The construction method of the foundation of the said structure is demonstrated in detail with reference to FIGS.
[0013]
After driving the pile 1 into the ground as shown in FIG. 4, as shown in FIG. 5, the periphery of the pile head is rooted to expose the pile head, and the discarded concrete 7 is placed on the root bottom. The steel pipe 4 is attached to the pile head and the discarded concrete 7 is built as a support surface. At that time, the steel pipe 4 is positioned in the vertical direction by using the discarded concrete 7 and the erection accuracy is secured, and the radial positioning is performed by the spacer 11 previously projected in the steel pipe 4 as shown in FIG. .
[0014]
The spacers 11 are attached to the pile head at at least three locations at equal intervals along the inner peripheral surface of the steel pipe 4, and when the steel pipe 4 is mounted on the pile head, the spacer 11 naturally and properly and equally between the pile head. Make sure the interval is secured. In addition, as shown in the figure, the vertical erection accuracy of the steel pipe 4 can be secured by providing the spacer 11 in two upper and lower stages, and when the spacer 11 is in an inverted triangle shape, the steel pipe 4 is mounted. In addition, since the steel pipe 4 is naturally guided in the radial direction by the slope of the spacer 11, the mounting operation can be easily performed. Further, the spacer 11 also functions as a stud for increasing the fixing strength of the concrete 5 cast and filled in the steel pipe 4.
[0015]
Next, as shown in FIG. 6, concrete 5 is placed in the lower half of the steel pipe 4 to bury the pile head, and the steel pipe 4 is fixed to the pile head. In the present embodiment, since the pile 1 is a hollow pile such as a PHC pile, a closing plate 12 serving as a concrete stopper is attached to the pile 1 prior to placing the concrete 5. The attachment position of the blocking plate 12 is the lower end level of the steel pipe 4.
[0016]
Before and after the concrete 5 placing step, the periphery of the pile head is backfilled and rolled as shown in FIG. 7, and then the ground surface is improved to form a layered ground. An improved body 9 is formed. The ground improvement body 9 serves as a support surface for the soil concrete 10 which becomes the first floor of the building, and after the completion of the building, the pile head is leveled through the steel pipe 4 and the concrete 5 cast and filled therein. It has a function of restraining displacement. The thickness of the ground improvement body 9 may be set as appropriate, but may be about 350 mm, for example.
[0017]
In parallel with the above ground improvement process, the pillar 2 is built as shown in FIG. In this embodiment, a square steel pipe is adopted as the column 2, and a large number of studs 8 are attached to the column base, and the column base is built by inserting the column base into the steel pipe 4.
[0018]
At that time, the pillar 2 is built in the following procedure using the jig 15 and the jig 16 shown in FIG. The jig 15 is for centering the column 2 and sets the column core O as shown in (a) with reference to the point marked on the steel pipe 4 by laser surveying. The jig 16 is fixed to the upper part of the steel pipe 4 with a clamp 17 on the basis of the jig 15 to set the position of the surface of the column 2 as shown in FIG. When the pillar 2 is installed at an appropriate position by being guided by the jig 16, a similar jig 16 is further fixed to the steel pipe 4 as shown in FIG. Temporarily support by sandwiching. The jigs 15 and 16 can be manufactured easily and inexpensively by assembling and welding the angle members according to the dimensions of the pillars 2 and can be repeatedly used.
[0019]
Then, as shown in FIG. 9, the concrete 5 is further cast into the steel pipe 4, and the concrete 18 is cast into the pillar 2 to a predetermined height before and after, and at least the column base is filled with the concrete 18. . When the concrete 5 is hardened, the pile 1 and the column 2 are securely and firmly joined via the concrete 5 and the steel pipe 4.
[0020]
Thereafter, as shown in FIG. 10, soil concrete 10 is placed to form the first floor surface. Prior to placing the soil concrete 10, the jig 16 may be removed. It is preferable to form the soil concrete 10 integrally with the ground improvement body 9 in order to give the soil concrete 10 a function of restraining the horizontal displacement of the pile head together with the ground improvement body 9 . Subsequently, the building of the ground part such as the construction of the beam 6 is carried out to complete the building.
[0021]
According to the above construction method, the pile 1 and the column 2 are securely and firmly joined to each other via the steel pipe 4, and after the pile 1 is constructed, the steel pipe 4 is attached to the pile head, and the concrete 5 Efficient construction is possible only by sequentially performing simple operations such as placing, erection of pillars 2 and further placing of concrete 5, and the construction is extremely excellent.
[0022]
In particular, by providing the spacer 11 in the steel pipe 4, the radial positioning of the steel pipe 4 with respect to the pile head can be easily and accurately performed, and the positioning of the steel pipe 4 in the vertical direction and the securing of the erection accuracy are discarded. The concrete 7 can be performed with high accuracy and without any trouble. Moreover, after the building is completed, the horizontal displacement of the pile head can be constrained by the layered ground improvement body 9 formed on the surface layer of the ground and the soil concrete 10 formed on the upper part thereof, so that the structure is stable. The foundation can be constructed. Furthermore, since the stud 8 is provided in the column base, the fixing strength with respect to the concrete 5 is increased, and the bonding strength between the pile 1 and the column 2 through the concrete 5 and the steel pipe 4 can be sufficiently increased.
[0023]
In addition, although the PHC pile was employ | adopted as the pile 1 in the said embodiment, not only that but a steel pipe pile, a cast-in-place concrete pile, etc. are employable. Further, the pillar 2 is not limited to a square steel pipe, and naturally a steel material of H-shape steel as well as a round steel pipe can be adopted. Further, similarly to the conventional one shown in FIG. 14, a base plate may be attached to the column base of the column 2 and fixed to the concrete 5 in the steel pipe 4 by an anchor.
[0024]
In the above embodiment, both the ground improvement body 9 and the soil concrete 10 have the function of restraining the horizontal displacement of the pile head, but such a function may be omitted if unnecessary. Only one of the ground improvement body 9 and the soil concrete 10 may have the function. In addition, it goes without saying that the present invention is not limited to the above-described embodiment, and appropriate design changes are possible.
[0025]
【The invention's effect】
In the invention of claim 1, when constructing a foundation formed by joining a pile head and a column base in the axial direction via a steel pipe, after constructing the pile, the lower half of the steel pipe is attached to the pile head Then, by placing concrete in the steel pipe, the lower half of the steel pipe is fixed to the pile head, and then the column base is inserted into the steel pipe to erect the column, and the concrete is placed in the steel pipe. Furthermore, because the column base is fixed to the steel pipe by placing it, the pile and the column can be securely and firmly joined by simple work, and it is extremely rational and excellent in workability. It is optimal as a foundation construction method.
[0026]
In the invention of claim 2, since the steel pipe is positioned in the radial direction by bringing the spacer projecting on the inner surface of the steel pipe into contact with the peripheral surface of the pile head, the diameter of the steel pipe particularly with respect to the pile head Directional positioning can be easily and accurately performed.
[0027]
According to the invention of claim 3, discarded concrete is cast around the pile head, the lower end of the steel pipe is supported by the discarded concrete, the vertical positioning of the steel pipe is performed, and vertical erection accuracy is ensured. Therefore, in particular, the vertical positioning of the steel pipe can be discarded and the concrete can be performed with high accuracy and without any trouble.
[0030]
In the invention of claim 4 , since the stud is provided in the column base portion of the column, the fixing strength of the column base portion to the concrete can be sufficiently increased.
[Brief description of the drawings]
FIG. 1 is a schematic diagram showing the structure of a foundation that is a construction object of the present invention.
FIG. 2 is an elevation view showing details of the structure of the foundation.
FIG. 3 is a sectional view of the same.
FIG. 4 shows a construction method according to an embodiment of the present invention in the order of steps, and is a diagram showing a state in which a pile is constructed.
FIG. 5 is a view showing a state in which a steel pipe is mounted on the pile head.
FIG. 6 is a view showing a state in which concrete is placed in the steel pipe and the steel pipe is fixed.
FIG. 7 is a view showing a state where backfilling and ground improvement are performed.
FIG. 8 is a diagram showing a state in which pillars are built.
FIG. 9 is a view showing a state where concrete is further placed in the steel pipe and the column base portion is fixed.
FIG. 10 is a view showing a state in which soil concrete is placed.
FIG. 11 is a view showing a steel pipe mounting step.
FIG. 12 is a view showing a column building process using a jig.
FIG. 13 is a view showing a conventional example of a foundation of a structure in which a pile and a column are directly joined.
FIG. 14 is a diagram showing details of the basic structure.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Pile 2 Pillar 4 Steel pipe 5 Concrete 7 Discarded concrete 8 Stud 9 Ground improvement body 10 Dough concrete 11 Spacers 15, 16 Jig

Claims (4)

杭頭部と柱脚部とを鋼管を介して軸方向に接合してなる基礎を施工するに際し、杭を施工した後、杭頭部に鋼管の下半部を装着して該鋼管内にコンクリートを打設することにより該鋼管の下半部を杭頭部に対して固定し、しかる後に該鋼管内に柱脚部を挿入して柱を立設し、該鋼管内にコンクリートをさらに打設して柱脚部を鋼管に対して固定することを特徴とする基礎の施工方法。  When constructing a foundation made by joining the pile head and the column base in the axial direction via a steel pipe, after constructing the pile, attach the lower half of the steel pipe to the pile head and place concrete in the steel pipe. To fix the lower half of the steel pipe to the pile head, and then insert a column base into the steel pipe to erect a column, and further cast concrete into the steel pipe. And the construction method of the foundation characterized by fixing a column base part with respect to a steel pipe. 請求項1記載の基礎の施工方法において、前記鋼管を杭頭部に装着するに際し、該鋼管の内面に突設せしめたスペーサを杭頭部周面に当接せしめることで該鋼管の径方向の位置決めを行うことを特徴とする基礎の施工方法。  2. The foundation construction method according to claim 1, wherein when the steel pipe is mounted on the pile head, a spacer projecting from the inner surface of the steel pipe is brought into contact with the circumferential surface of the pile head so that the radial direction of the steel pipe is increased. A foundation construction method characterized by positioning. 請求項1または2記載の基礎の施工方法において、前記鋼管を杭頭部に装着するに際し、杭頭部の周囲に捨てコンクリートを打設し、該捨てコンクリートにより前記鋼管の下端を支持せしめて該鋼管の上下方向の位置決めを行いかつ鉛直建て込み精度を確保することを特徴とする基礎の施工方法。  3. The foundation construction method according to claim 1, wherein when the steel pipe is mounted on the pile head, the discarded concrete is placed around the pile head, and the lower end of the steel pipe is supported by the discarded concrete. A foundation construction method characterized by positioning the steel pipe in the vertical direction and ensuring vertical installation accuracy. 請求項1,2または3記載の基礎の施工方法において、前記柱の柱脚部にスタッドを設けておくことで該柱脚部のコンクリートに対する定着強度を高めることを特徴とする基礎の施工方法。4. The foundation construction method according to claim 1 , wherein studs are provided on the column bases of the columns to increase the fixing strength of the column bases to the concrete.
JP2000102218A 2000-04-04 2000-04-04 Foundation construction method Expired - Lifetime JP3671343B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000102218A JP3671343B2 (en) 2000-04-04 2000-04-04 Foundation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000102218A JP3671343B2 (en) 2000-04-04 2000-04-04 Foundation construction method

Publications (2)

Publication Number Publication Date
JP2001288755A JP2001288755A (en) 2001-10-19
JP3671343B2 true JP3671343B2 (en) 2005-07-13

Family

ID=18616142

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000102218A Expired - Lifetime JP3671343B2 (en) 2000-04-04 2000-04-04 Foundation construction method

Country Status (1)

Country Link
JP (1) JP3671343B2 (en)

Families Citing this family (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4756750B2 (en) * 2001-02-26 2011-08-24 旭化成建材株式会社 Anchor frame fixing method
JP3900344B2 (en) * 2002-09-19 2007-04-04 株式会社奥村組 Column-to-pile connection structure of steel structure building and its construction method
EP1579077A4 (en) * 2002-12-30 2008-10-22 Koo Min Se Prestressed composite girder, continuous prestressed composite girder structure and methods of fabricating and connecting the same
JP3764729B2 (en) * 2003-03-24 2006-04-12 東京電力株式会社 Construction method of steel tower foundation using concrete restraint joint member
JP4558522B2 (en) * 2005-01-25 2010-10-06 株式会社奥村組 Building basic structure
JP4962831B2 (en) * 2005-02-23 2012-06-27 武藤 日出夫 Foundation structure of column base and its construction method
JP4523869B2 (en) * 2005-04-11 2010-08-11 新日鉄エンジニアリング株式会社 Column fixing member installation method and column fixing member installation device for steel pipe foundation pile
JP4835918B2 (en) * 2005-11-04 2011-12-14 清水建設株式会社 Pile-column connection structure and method
JP5043351B2 (en) * 2006-03-22 2012-10-10 前田建設工業株式会社 Joint structure of steel column and ready-made pile
JP4793643B2 (en) * 2006-05-31 2011-10-12 清水建設株式会社 Stress reduction structure and stress reduction method for foundation pile
JP5041758B2 (en) * 2006-08-04 2012-10-03 Jfeスチール株式会社 Seismic isolation structure with artificial ground
JP5041759B2 (en) * 2006-08-04 2012-10-03 Jfeスチール株式会社 Seismic isolation structure
JP2009162034A (en) * 2008-01-10 2009-07-23 Tokyo Electric Power Co Inc:The Method of constructing foundation of structure
KR101137475B1 (en) * 2009-12-30 2012-04-20 재단법인 포항산업과학연구원 Double steel pipe foundation and construction method thereof
JP5850528B2 (en) * 2011-11-25 2016-02-03 株式会社竹中工務店 Structure with ramen frame
JP6702687B2 (en) * 2015-02-09 2020-06-03 株式会社西部工建 Prestressed concrete pile head cap
JP2017197984A (en) * 2016-04-28 2017-11-02 清水建設株式会社 Joining structure of phc pile and steel column
JP6916643B2 (en) * 2017-03-22 2021-08-11 大和ハウス工業株式会社 Pile foundation structure and its construction method
CN107938663B (en) * 2017-09-22 2024-02-06 上海市政工程设计研究总院(集团)有限公司 PHC pipe pile penetrating through main structure part as supporting system lattice column connector
JP2019090266A (en) * 2017-11-16 2019-06-13 東京電力ホールディングス株式会社 Installation method of main leg material and installation jig of main leg material
JP7101109B2 (en) * 2018-12-12 2022-07-14 Jfeシビル株式会社 Pile connection strut structure and its construction method
JP7240926B2 (en) * 2019-03-28 2023-03-16 株式会社熊谷組 Structure of pile cap
JP7008663B2 (en) * 2019-06-06 2022-01-25 博信 宮坂 Column pile rotation suppression structure

Also Published As

Publication number Publication date
JP2001288755A (en) 2001-10-19

Similar Documents

Publication Publication Date Title
JP3671343B2 (en) Foundation construction method
JP4835918B2 (en) Pile-column connection structure and method
JP2006207265A (en) Joining method of pile and column and its structure
JP2001303584A (en) Structure for connecting head of foundation pile with footing
JPH11181790A (en) Execution method of building foundation
JP4050816B2 (en) Construction method of underground part of steel reinforced concrete building
JP3671344B2 (en) Joint structure between foundation pile and column base and its construction method
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
JP2000291031A (en) Construction method for base isolation structure
JP2001132275A (en) Sign pole foundation and method for constructing the same
JP4971053B2 (en) Pile and column connection structure of steel building and its construction method
JP2002021096A (en) Building and constructing method therefor
JPH09302703A (en) Base isolation method for existing structure having pile foundation
JP5043351B2 (en) Joint structure of steel column and ready-made pile
JP3850400B2 (en) Pile head joint structure between pile and column and construction method of the pile head joint structure
JPH0533351A (en) Steel column base of steel frame structure and execution thereof
JP4473400B2 (en) Foundation of construction and construction method
JP3700119B2 (en) Pillar construction method
JP7053750B1 (en) Reinforcing bar unit and rebar assembly method
JP7232660B2 (en) pile foundation structure
JP2004143878A (en) Construction method for joining foundation pile and column together and metal joint for joining
JP2000273880A (en) Pile head connecting method
JPH09256366A (en) Permanent sub-structural column used for pliers and underground building construction making use thereof
JP2873307B2 (en) Joint method between concrete foundation and steel column
JP3700113B2 (en) Direct foundation and construction method

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041221

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050216

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050315

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050406

R150 Certificate of patent or registration of utility model

Ref document number: 3671343

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080428

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090428

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100428

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110428

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120428

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120428

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130428

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130428

Year of fee payment: 8

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140428

Year of fee payment: 9

EXPY Cancellation because of completion of term