JP3656452B2 - Seismic isolation method for existing buildings - Google Patents

Seismic isolation method for existing buildings Download PDF

Info

Publication number
JP3656452B2
JP3656452B2 JP09432299A JP9432299A JP3656452B2 JP 3656452 B2 JP3656452 B2 JP 3656452B2 JP 09432299 A JP09432299 A JP 09432299A JP 9432299 A JP9432299 A JP 9432299A JP 3656452 B2 JP3656452 B2 JP 3656452B2
Authority
JP
Japan
Prior art keywords
existing building
seismic isolation
slab
pile
pile head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP09432299A
Other languages
Japanese (ja)
Other versions
JP2000282695A (en
Inventor
晴久 井上
正芳 松原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP09432299A priority Critical patent/JP3656452B2/en
Publication of JP2000282695A publication Critical patent/JP2000282695A/en
Application granted granted Critical
Publication of JP3656452B2 publication Critical patent/JP3656452B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、既存建物を免震化するための工法に関するものである。
【0002】
【従来の技術】
周知のように、従来、既存建物を免震化する際には、既存建物の下方の地盤を掘削しつつ、仮受け治具を用いて既存建物を支持し、次いで、既存建物の下方に基礎コンクリートを構築し、さらに、基礎コンクリートと既存建物との間に免震装置を介装し、しかる後に、仮受け治具を撤去することとしていた。
【0003】
【発明が解決しようとする課題】
しかしながら、このように免震化を行った場合、仮受け治具の設置を行いながら、既存建物下方の地盤を部分毎に掘削しなければならないため、工期が長期化するという問題点があった。
【0004】
また、免震化対象の既存建物の自重が大きなものであると、これに合わせて仮受け治具を大がかりなものとしなければならず、これにより、仮受け治具の設置スペースを確保するために掘削土量を増やさなければならなくなり、施工上問題があった。さらに、この場合、仮受け治具自体に要する費用も嵩むものとなっていた。
【0005】
さらに、免震化対象の既存建物の地下階数が多い場合には、仮受け治具の設置位置が深くなることから、仮受け治具の設置作業が手間のかかるものとなっていた。
【0006】
本発明は、このような事情に鑑みなされたものであり、従来に比較して工期を短縮化することができるとともに、免震化対象の既存建物の自重が大きい場合、あるいは、地下階数が多い場合においても、良好に適用しうる免震化工法を提供することを課題とする。
【0007】
【課題を解決するための手段】
上記課題を解決するために本発明においては以下の手段を採用した。
すなわち、請求項1記載の既存建物の免震化工法は、既存建物を免震化するための工法であって、
前記既存建物の下方の地盤に、杭を、その杭頭が、前記既存建物の底版より所定寸法下方に位置するように構築するとともに、該構築時に、前記杭頭に対して、柱材を、該杭頭上面から前記既存建物の底版に至る位置にまで突出させた状態で埋設しておき、
前記既存建物の底版と前記柱材の上端とを一体的に接合し、
前記既存建物の側方および下方の地盤を掘削し、
前記既存建物の底版の下方に、基礎スラブを、前記杭頭と一体化させた状態で、なおかつ、前記底版と離間させた状態で構築し、
前記基礎スラブと前記底版との間に免震装置を介装し、
しかる後に、前記柱材のうち、前記既存建物の底版と前記基礎スラブとの間に位置する部分を撤去することを特徴としている。
【0008】
このような構成により、既存建物の下方に免震装置を介装するにあたって、既存建物を杭から柱材を介して支持することができる。
【0009】
【発明の実施の形態】
以下、本発明の実施の形態の一例を、図面に基づいて説明する。
図1は、免震化工事が行われた既存建物1と、その下部構造2とを示す図である。
【0010】
この既存建物1は、免震化工事が行われる以前は 図2に示すように、下部構造2(図1参照)に対応する部分を有さず、その底版3が地盤G上に直接的に支持された構成とされていたものであり、免震化工事を施すことにより、図1に示すように下部構造2が新たに構築され、免震化されたものとなっている。
【0011】
下部構造2は、地盤G中に構築された杭4と、杭4の杭頭5に対して一体化されて構築された基礎スラブ6と、基礎スラブ6上に配列されて既存建物1の底版3を支持する積層ゴムからなる免震装置7,…とを備えた構成となっている。
【0012】
既存建物1を免震化して図1に示した状態とするには、まず、図3に示すように、杭4を、既存建物1の下方の地盤Gに構築する。この場合、既存建物1の底版3に貫通孔8を設け、この貫通孔8の下方に杭4を構築するようにする。または、杭4を構築する際には、杭頭5を、既存建物1の底版3よりも一定寸法下方に位置させるとともに、杭頭5上面に鉄骨からなる構真柱(柱材)9を埋設しておく。このとき、構真柱9の上端9aは、底版3と略同一のレベルまで至るように配置される。
【0013】
次に、図4に示すように、既存建物1の底版3上に補強梁10を設置する。このとき、補強梁10内に構真柱9の上端9aを埋設するようにし、これにより底版3と構真柱9の上端9aとを補強梁10を介して一体化させる。
【0014】
続いて、図5に示すように、既存建物1の側方および下方に位置する地盤Gを掘削し、地盤Gと既存建物1の底版3との間に間隙を形成する。これにより、既存建物1は、構真柱9により仮受けされることとなる。また、既存建物1の側方の地盤Gに対しては、山留め壁11および切梁12を設けることによりこれを支持する。
【0015】
この後、図6に示すように既存建物1の下方の掘削した地盤G上に、基礎スラブ6を設け、また山留め壁11の内側に側壁13を設ける。この場合、基礎スラブ6を、杭4の杭頭5と一体的に形成するようにする。
【0016】
そして、図7に示すように、既存建物1の底版3と基礎スラブ6との間に免震装置7,…を取付け、さらに、構真柱9のうち、底版3と基礎スラブ6との間に位置する部分を撤去することにより、図1に示したように、既存建物1の免震化が完了される。
【0017】
以上述べた既存建物1の免震化工法は、免震装置7を取り付ける際に既存建物1を仮受けするにあたって、既存建物1の下方に杭4を先行構築するとともに、既存建物1と杭4とを構真柱9を介して一体化するようにしたため、地盤Gを掘削する以前に杭4から構真柱9を介して既存建物1を支持することができる。したがって、従来の免震化工法と異なり、地盤を部分毎に掘削しながら仮受け治具を設置していく必要が無く、工期の短縮化を図ることができる。
また、仮受け治具を用いないために、仮受け治具設置に係るコストを軽減することが可能であり、特に、既存建物1の自重が大きい場合に、従来と異なり、仮受け治具の設置スペースを確保するために掘削土量を増やすような必要が無いため、施工コストの削減および労力の軽減を図ることができる。また、仮受け治具を用いないために、既存建物1の地下階数が多い場合においても、施工手間が煩雑なものとならない。
【0018】
【発明の効果】
以上説明したように、本発明の既存建物の免震化工法においては、免震装置を取り付ける際に既存建物を仮受けするにあたって、既存建物の下方に杭を先行構築するとともに、既存建物と杭とを柱材を介して一体化するようにしたため、地盤を掘削する以前に杭から柱材を介して既存建物を支持することができる。したがって、従来の免震化工法と異なり、地盤を部分毎に掘削しながら仮受け治具を設置していく必要が無く、工期の短縮化を図ることができる。
また、仮受け治具を用いないために、仮受け治具設置に係るコストを軽減することが可能であり、特に、既存建物の自重が大きい場合に、従来と異なり、仮受け治具の設置スペースを確保するために掘削土量を増やすような必要が無いため、施工コストの削減および労力の軽減を図ることができる。また、仮受け治具を用いないために、既存建物の地下階数が多い場合においても、施工手間が煩雑なものとならない。
【図面の簡単な説明】
【図1】 本発明の一実施の形態を模式的に示す図であって、免震化工法が施された既存建物の立断面図である。
【図2】 同、免震化工法が施される以前の既存建物の立断面図である。
【図3】 本発明の既存建物の免震化工法の一工程を示す図である。
【図4】 本発明の既存建物の免震化工法における図3の次工程を示す図である。
【図5】 同、図4の次工程を示す図である。
【図6】 同、図5の次工程を示す図である。
【図7】 同、図6の次工程を示す図である。
【符号の説明】
1 既存建物
3 底版
4 杭
5 杭頭
6 基礎スラブ
7 免震装置
9 構真柱(柱材)
9a 上端
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method for isolating an existing building.
[0002]
[Prior art]
As is well known, conventionally, when an existing building is to be seismic isolated, the existing building is supported using a temporary receiving jig while excavating the ground below the existing building, and then the foundation is placed below the existing building. Concrete was constructed, and a seismic isolation device was installed between the foundation concrete and the existing building, and then the temporary support jig was removed.
[0003]
[Problems to be solved by the invention]
However, when performing seismic isolation in this way, there was a problem that the construction period was prolonged because the ground below the existing building had to be excavated for each part while installing the temporary receiving jig. .
[0004]
In addition, if the existing building to be seismically isolated has a large weight, the provisional jig must be made large in accordance with this, so as to secure the installation space for the provisional jig. However, the amount of excavated soil had to be increased, and there was a problem in construction. Further, in this case, the cost required for the temporary receiving jig itself is increased.
[0005]
Furthermore, when the number of basement floors of the existing building to be seismically isolated is large, the installation position of the temporary receiving jig becomes deep, so that the installation work of the temporary receiving jig is troublesome.
[0006]
The present invention has been made in view of such circumstances, and the construction period can be shortened compared to the conventional case, and the existing building to be seismically isolated has a large weight or has a large number of underground floors. Even in the case, it is an object to provide a seismic isolation method that can be applied well.
[0007]
[Means for Solving the Problems]
In order to solve the above problems, the present invention employs the following means.
That is, the seismic isolation method for an existing building according to claim 1 is a method for isolating an existing building,
On the ground below the existing building, a pile is constructed such that the pile head is positioned below a predetermined dimension from the bottom slab of the existing building, and at the time of the construction, a column material is provided to the pile head, Embed it in a state of protruding from the top of the pile head to the position reaching the bottom plate of the existing building,
The bottom plate of the existing building and the upper end of the pillar material are integrally joined,
Excavating the side and lower ground of the existing building,
Under the bottom slab of the existing building, the foundation slab is built in a state integrated with the pile head, and is separated from the bottom slab,
A seismic isolation device is interposed between the foundation slab and the bottom plate,
Thereafter, a portion of the pillar material located between the bottom slab of the existing building and the foundation slab is removed.
[0008]
With such a configuration, when the seismic isolation device is interposed below the existing building, the existing building can be supported from the pile via the pillar material.
[0009]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an example of an embodiment of the present invention will be described with reference to the drawings.
FIG. 1 is a diagram showing an existing building 1 that has undergone seismic isolation work and its lower structure 2.
[0010]
As shown in FIG. 2, this existing building 1 does not have a portion corresponding to the lower structure 2 (see FIG. 1), and its bottom slab 3 is directly on the ground G, as shown in FIG. As shown in Fig. 1, the lower structure 2 is newly constructed and seismically isolated by performing seismic isolation work.
[0011]
The substructure 2 includes a pile 4 constructed in the ground G, a foundation slab 6 constructed integrally with a pile head 5 of the pile 4, and a bottom slab of the existing building 1 arranged on the foundation slab 6 3 is provided with a seismic isolation device 7 made of laminated rubber that supports 3.
[0012]
In order to make the existing building 1 seismic isolation into the state shown in FIG. 1, first, as shown in FIG. 3, the pile 4 is constructed on the ground G below the existing building 1. In this case, the through hole 8 is provided in the bottom slab 3 of the existing building 1, and the pile 4 is constructed below the through hole 8. Alternatively, when building the pile 4, the pile head 5 is positioned below the bottom plate 3 of the existing building 1 by a certain dimension, and a built-up column (column material) 9 made of steel is embedded on the top surface of the pile head 5. Keep it. At this time, the upper end 9a of the stem column 9 is arranged so as to reach substantially the same level as the bottom plate 3.
[0013]
Next, as shown in FIG. 4, the reinforcing beam 10 is installed on the bottom slab 3 of the existing building 1. At this time, the upper end 9 a of the frame column 9 is embedded in the reinforcing beam 10, and thereby the bottom plate 3 and the upper end 9 a of the frame column 9 are integrated via the reinforcing beam 10.
[0014]
Subsequently, as shown in FIG. 5, the ground G located on the side and below the existing building 1 is excavated to form a gap between the ground G and the bottom slab 3 of the existing building 1. As a result, the existing building 1 is provisionally received by the construction pillar 9. Further, the ground G on the side of the existing building 1 is supported by providing a retaining wall 11 and a beam 12.
[0015]
Thereafter, as shown in FIG. 6, the foundation slab 6 is provided on the excavated ground G below the existing building 1, and the side wall 13 is provided inside the retaining wall 11. In this case, the foundation slab 6 is formed integrally with the pile head 5 of the pile 4.
[0016]
Then, as shown in FIG. 7, seismic isolation devices 7 are attached between the bottom slab 3 and the foundation slab 6 of the existing building 1, and among the construction pillars 9, between the bottom slab 3 and the foundation slab 6. By removing the portion located at, the seismic isolation of the existing building 1 is completed as shown in FIG.
[0017]
In the seismic isolation method for the existing building 1 described above, when the existing building 1 is provisionally received when the seismic isolation device 7 is attached, the pile 4 is constructed in advance under the existing building 1 and the existing building 1 and the pile 4 Are integrated with each other through the structural pillar 9, so that the existing building 1 can be supported from the pile 4 through the structural pillar 9 before excavating the ground G. Therefore, unlike the conventional seismic isolation method, it is not necessary to install a temporary receiving jig while excavating the ground for each part, and the construction period can be shortened.
Moreover, since the temporary receiving jig is not used, the cost for installing the temporary receiving jig can be reduced. In particular, when the weight of the existing building 1 is large, the temporary receiving jig is different from the conventional one. Since it is not necessary to increase the amount of excavated soil in order to secure the installation space, it is possible to reduce the construction cost and labor. Moreover, since the temporary receiving jig is not used, even when the existing building 1 has a large number of underground floors, the construction labor is not complicated.
[0018]
【The invention's effect】
As described above, in the seismic isolation method for an existing building according to the present invention, when temporarily installing the existing building when installing the seismic isolation device, a pile is constructed in advance under the existing building, and the existing building and the pile are also constructed. Are integrated through the pillar material, so that the existing building can be supported from the pile through the pillar material before excavating the ground. Therefore, unlike the conventional seismic isolation method, it is not necessary to install a temporary receiving jig while excavating the ground for each part, and the construction period can be shortened.
In addition, since the temporary receiving jig is not used, it is possible to reduce the cost for installing the temporary receiving jig. Since it is not necessary to increase the amount of excavated soil in order to secure a space, it is possible to reduce the construction cost and labor. Moreover, since a temporary receiving jig is not used, even if the existing building has a large number of underground floors, the construction labor is not complicated.
[Brief description of the drawings]
FIG. 1 is a diagram schematically showing an embodiment of the present invention, and is a vertical sectional view of an existing building subjected to a seismic isolation method.
FIG. 2 is a vertical sectional view of an existing building before the seismic isolation method is applied.
FIG. 3 is a diagram showing a step of the seismic isolation method for an existing building according to the present invention.
4 is a diagram showing the next step of FIG. 3 in the seismic isolation method for an existing building of the present invention.
FIG. 5 is a diagram showing a step subsequent to FIG. 4;
6 is a diagram showing a step subsequent to FIG. 5. FIG.
FIG. 7 is a view showing the next step of FIG. 6;
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Existing building 3 Bottom plate 4 Pile 5 Pile head 6 Foundation slab 7 Seismic isolation device 9 True column (column material)
9a top

Claims (1)

既存建物を免震化するための工法であって、
前記既存建物の下方の地盤に、杭を、その杭頭が、前記既存建物の底版より所定寸法下方に位置するように構築するとともに、該構築時に、前記杭頭に対して、柱材を、該杭頭上面から前記既存建物の底版に至る位置にまで突出させた状態で埋設しておき、
前記既存建物の底版と前記柱材の上端とを一体的に接合し、
前記既存建物の側方および下方の地盤を掘削し、
前記既存建物の底版の下方に、基礎スラブを、前記杭頭と一体化させた状態で、なおかつ、前記底版と離間させた状態で構築し、
前記基礎スラブと前記底版との間に免震装置を介装し、
しかる後に、前記柱材のうち、前記既存建物の底版と前記基礎スラブとの間に位置する部分を撤去することを特徴とする既存建物の免震化工法。
A construction method for seismic isolation of existing buildings,
On the ground below the existing building, a pile is constructed such that the pile head is positioned below a predetermined dimension from the bottom slab of the existing building, and at the time of the construction, a column material is provided to the pile head, Embed it in a state of protruding from the top of the pile head to the position reaching the bottom plate of the existing building,
The bottom plate of the existing building and the upper end of the pillar material are integrally joined,
Excavating the side and lower ground of the existing building,
Under the bottom slab of the existing building, the foundation slab is built in a state integrated with the pile head, and is separated from the bottom slab,
A seismic isolation device is interposed between the foundation slab and the bottom plate,
After that, the seismic isolation method for the existing building is characterized in that a part of the pillar material located between the bottom slab of the existing building and the foundation slab is removed.
JP09432299A 1999-03-31 1999-03-31 Seismic isolation method for existing buildings Expired - Fee Related JP3656452B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP09432299A JP3656452B2 (en) 1999-03-31 1999-03-31 Seismic isolation method for existing buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP09432299A JP3656452B2 (en) 1999-03-31 1999-03-31 Seismic isolation method for existing buildings

Publications (2)

Publication Number Publication Date
JP2000282695A JP2000282695A (en) 2000-10-10
JP3656452B2 true JP3656452B2 (en) 2005-06-08

Family

ID=14107058

Family Applications (1)

Application Number Title Priority Date Filing Date
JP09432299A Expired - Fee Related JP3656452B2 (en) 1999-03-31 1999-03-31 Seismic isolation method for existing buildings

Country Status (1)

Country Link
JP (1) JP3656452B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4546357B2 (en) * 2005-09-01 2010-09-15 株式会社竹中工務店 A method to renovate the underfloor part of the projecting frame of an existing structure
JP2009155794A (en) * 2007-12-25 2009-07-16 Shimizu Corp Base isolation construction method
JP5535778B2 (en) * 2010-06-10 2014-07-02 株式会社竹中工務店 Structure support structure and method for constructing structure support structure
JP6425584B2 (en) * 2015-02-27 2018-11-21 大成建設株式会社 Horizontal movement restraint method

Also Published As

Publication number Publication date
JP2000282695A (en) 2000-10-10

Similar Documents

Publication Publication Date Title
JP3728654B2 (en) Building dismantling and construction methods
KR101212240B1 (en) Structure for underground downward extension of structural remodeling and methode thereof
KR20190022132A (en) Top-down method using precast-concrete colum
JP3799036B2 (en) Building basic structure and construction method
JP3656452B2 (en) Seismic isolation method for existing buildings
KR100976621B1 (en) Construction method for basement extention
JP2001311314A (en) Method for realizing base isolation structure of existing building
US6220789B1 (en) Integrated excavation shoring building foundation method
JP4624867B2 (en) Seismic isolation repair method for existing buildings
JP3706997B2 (en) Base seismic isolation method for existing buildings
JPH09184144A (en) Construction method for base isolation pit for existing building
JP2000179161A (en) Vibration-isolation construction method for existing building
JP4228308B2 (en) Reinforcement method for existing floors and seismic isolation method for existing buildings
JP3648651B2 (en) Construction method of base-isolated building by the reverse driving method
JP3290887B2 (en) Seismic isolation method for existing building with pile foundation
JPH09256644A (en) Existing building base isolation construction
JPH11152928A (en) Base isolation building and method of base isolating construction of existing building
JP2016079651A (en) Support structure
JP3381066B2 (en) Existing building seismic isolation method and seismic isolation building
JPH1113290A (en) Base isolation implementating method for existing building
JP6534026B2 (en) Seismic isolation building and its construction method
JP4890098B2 (en) Construction method of seismic isolation building
JP2001173269A (en) Constructing method for base isolation building
JP2003328587A (en) Base isolation construction method for existing building
JPH11350503A (en) Construction method of vibration isolation building

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050107

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050215

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050228

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080318

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090318

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100318

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110318

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120318

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120318

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130318

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130318

Year of fee payment: 8

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140318

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees