JP3558229B2 - Slope stabilization method and equipment - Google Patents

Slope stabilization method and equipment Download PDF

Info

Publication number
JP3558229B2
JP3558229B2 JP20823894A JP20823894A JP3558229B2 JP 3558229 B2 JP3558229 B2 JP 3558229B2 JP 20823894 A JP20823894 A JP 20823894A JP 20823894 A JP20823894 A JP 20823894A JP 3558229 B2 JP3558229 B2 JP 3558229B2
Authority
JP
Japan
Prior art keywords
frame
mesh bag
slope
flexible
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP20823894A
Other languages
Japanese (ja)
Other versions
JPH0853845A (en
Inventor
孝之 大友
直樹 陣内
Original Assignee
株式会社日東テクノ・グループ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社日東テクノ・グループ filed Critical 株式会社日東テクノ・グループ
Priority to JP20823894A priority Critical patent/JP3558229B2/en
Publication of JPH0853845A publication Critical patent/JPH0853845A/en
Application granted granted Critical
Publication of JP3558229B2 publication Critical patent/JP3558229B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【0001】
【産業上の利用分野】
開示技術は、道路の側部等に形成される斜面の安定化を図るフレームの施工の技術分野に属する。
【0002】
【従来の技術】
周知の如く、現代社会は多くの情報に支えられており、したがって、情報処理のネットワークは全国的な規模でますますその拡充が図られてきている。
【0003】
かかる情報処理のネットワークは、単に、電気通信網や電波等の手段によるもののみばかりでなく、鉄道,道路や該鉄道,道路に沿うケーブル等によって維持されている態様も極めて多いものである。
【0004】
したがって、いずれにしても高速道路や鉄道等の建設工事は著しく重要であり、既存の周辺構築物との取り合いも無視できないもので、工事に伴う公害問題や環境との調和問題,安全保持等の点も極めて重要である。
【0005】
而して、これらの開渠,横路等の施工、及び、施工後の使用状態において、安全性の観点において樹木の倒壊,崩壊,地下水漏出等を防止するためには、それらの側部(上下側)の斜面の安定化が不可欠である。そこで、これまでは、所謂フリーフレーム等の施工技術が広く用いられている。
【0006】
而して、該斜面の安定化作業については、例えば、特開平5−140948号公報に開示の発明に見られる如く施工現場において引張り材を埋設したり、地山に配筋工事を行い、アンカーをとって搬入した重機等により型枠を介しコンクリートを打設してフレーム(梁)を形成し、該フレーム間にセメントモルタルを吹き付ける等の工事が行われていた
【0007】
しかしながら、これらの工事における鉄筋や型枠等の搬入,建込み,組み付け,治具等の解体,撤去等は、すべて人手作業による人海作戦的なものが主である。しかも、作業が斜面を成す傾斜面で行われることから作業効率が悪いという欠点がある。しかも、安全性充分に保持できない難点があるだけでなく、工事期間(その前後を含む)において周辺環境悪化を招くという不都合さもあった。
【0008】
また、樹木にフリーフレームを曲折して設置する態様もあるが、却って該樹木を痛めて環境悪化を招く不都合さがある。
【0009】
【発明が解決しようとする課題】
上述した従来技術の問題点に鑑み、この出願の発明の目的は上述従来技術に基づく開渠等構造物の設置部位の側部の斜面に対する安定化工事に伴う種々の問題点を解決すべき技術的課題とし、作業能率が良く、しかも、安全性が高く、周囲に対する作業環境悪化等の虞もなく、そのうえ、施工後の斜面の保護機能が充分に果せるようにして建設産業における土木技術利用分野に益する優れた斜面安定化工法、及び、該工法に直接使用する装置を提供せんとするものである。
【0010】
【課題を解決するための手段】
(1) 上記目的を達成するために、本発明に係る工法は、可撓性を有する第1のメッシュ袋内にフレキシブル鉄筋を挿入することによって、フレーム基体を形成しておき、さらに、可撓性を有する第2のメッシュ袋内に前記フレーム基体を挿入することによって予め形成しておいたフレームを、地山の斜面に対して設置することによって、当該斜面を安定化する工法であって、
前記地山の斜面に、所定ピッチで複数のピットを形成し、
形成された前記複数のピットのそれぞれにおいて、アンカーを固設し、
アンカーを固設した前記ピットにおいて、コンクリートを打設し、
前記斜面において、予め形成しておいた前記フレームを前記アンカーに沿って敷設し、
前記アンカーに対して、敷設した前記フレームを係合させ、
前記フレームの前記第1のメッシュ袋内に固化剤を充填し、
前記フレームの前記第2のメッシュ袋に固化剤を充填するようにする。
【0011】
(2) また、上記目的を達成するために、本発明に係る工法は、
可撓性を有する第1のメッシュ袋内にフレキシブル鉄筋を挿入することによって、フレーム基体を形成しておき、次いで、可撓性を有する複数の第2のメッシュ袋を、スリットが形成されたジョイントパイプを介して連結し、さらに、連結した前記第2のメッシュ袋内に前記フレーム基体を挿入することによって予め形成しておいたフレームを、地山の斜面に対して設置することによって、当該斜面を安定化する工法であって、
前記地山の斜面に、フックを備えた複数のアンカーを、所定ピッチで固設し、
前記斜面において、予め形成しておいた前記フレームを前記アンカーに沿って敷設し、
前記フレームの前記第1のメッシュ袋内に固化剤を充填し、
前記フレームの前記第2のメッシュ袋に固化剤を充填し、
前記アンカーのフックに対して、敷設した前記フレームのフレーム基体を引っ掛けることによって、当該フレーム基体が、前記スリットを介して前記アンカーによって引っ張り状態で固定されるようにする。
【0012】
(3) 上記(1)又は(2)記載の斜面安定化工法において、好ましくは、前記フレーム基体は、その内側に、前記フレキシブル鉄筋に加えて、屈曲して成るスペーサを有している。
【0013】
(4) 上記(1)又は(2)記載の斜面安定化工法における前記フレームを敷設する工程において、好ましくは、前記フレームを、列状,行状,およびマトリックス状の何れかの状態に敷設する。
【0014】
(5) また、上記目的を達成するために、本発明の装置は、上記(1)乃至(4)の何れかに記載の斜面安定化工法において用いられる装置であって、
フレキシブル鉄筋と、屈曲したスペーサと、当該フレキシブル鉄筋およびスペーサを内側に備える可撓性の第1のメッシュ袋と、を含むフレーム基体と;
可撓性を有する第2のメッシュ袋に前記フレーム基体を挿入して成るフレームと;を有している。
【0015】
(6) また、上記目的を達成するために、本発明の装置は、上記(1)乃至(4)の 何れかに記載の斜面安定化工法において用いられる装置であって、
端部に雄ネジが形成してあるフレキシブル鉄筋と、屈曲したスペーサと、当該フレキシブル鉄筋およびスペーサを内側に備える可撓性の第1のメッシュ袋と、を含む複数のフレーム基体と;
可撓性を有する第2のメッシュ袋に前記フレーム基体を挿入して成るフレームと;
内側に雌ネジが形成されており、前記フレーム内において前記複数のフレーム基体を連結する長ナットと;を有しており、
前記長ナットの一端は、挿入してある一のフレーム基体のフレキシブル鉄筋の端部に対して螺合させてあり、
前記長ナットの他端は、挿入された他のフレーム基体のフレキシブル鉄筋の端部に対して螺合させてある。
【0016】
(7) 上記(5)又は(6)記載の斜面安定化装置において、好ましくは、
前記フレームの前記第1のメッシュ袋内には、固化剤が充填されており、
前記フレームの前記第2のメッシュ袋には、固化剤が充填されている。
【0017】
【実施例】
次に、この出願の発明の実施例を図面を参照して説明すれば以下の通りである。
【0018】
図示する実施例は道路の側部の地山1の斜面2に対するその保護,維持のための安定化工事の態様に関する。図中、符号3はこの出願の発明の要旨の1つの中心を成す「斜面安定化装置」を示している。また、符号4は、所定メッシュの侵透性のビニールシート製等で形成された、閉断面の所定サイズの可撓性「メッシュ袋」を示している。
【0019】
図1〜図5に示す原理態様において、例えば、メッシュ袋(第1のメッシュ袋)4には、予め工場で周公知のテンション付与用のフレキシブル鉄筋5が少くとも1本挿通されるとともに、所定ピッチで該メッシュ袋4の内面に当接する「く」の字型のスペーサ6,6も適宜に挿通されるようになっている
【0020】
なお、スペーサ6はフレキシブル鉄筋5のうちの1本をその長手方向において、所定ピッチで90°ずつ縦横にジグザグ状に方向を変えて「く」の字型に曲折して成形されているものであっても良いものである。
【0021】
而して、スペーサ6は次述する如く、固化材としてのセメントペースト10をメッシュ袋4の長手方向端部から流入充填させる際に、当該メッシュ袋4の拡開姿勢を保持させるように機能するものである。
【0022】
そして、メッシュ間隙からセメントペーストを滲出させて周囲との固化一体化を図るものである。
【0023】
このようにして、セメントペースト10をメッシュ袋4内に流入充填させると、該メッシュ袋4は一種の丸太棒状になり、フレームの基体を形成することになる。
【0024】
而して、斜面安定化工事に際し、主アンカー8,8…、及び、補助アンカー8´,8´を、図7及び図8に示すように、地山1の斜面2に所定ピッチで行(または列状、或いはマトリックス状)に配列して、所定深さ打込み貫入して固定させておく。
【0025】
なお、各主アンカー8の基部には図7及び図8に示す様に、断面円形のリングヘッド9(或いは、ピンジョイントでも可)が一体的に、或いは、ネジ螺合的に設けられている。
【0026】
そして、「フレキシブル鉄筋5およびスペーサ6が挿入してあるメッシュ袋4」を内装するメッシュ袋(第2のメッシュ袋)7に、アンカー8,8´のリングヘッド9,9´に挿通係合させて行,列状のネットワークを形成する。さらに、これを基本として、図4に示すように、応用的には一種のマトリックス状フレーム11のネットワークを地山1の斜面2の表面に樹木を縫って形成敷設する。
なお、メッシュ袋4を内装する上記メッシュ袋7は、所定サイズの閉じ断面(断面円形,角形等)に形成され、メッシュ袋4の断面よりも大きな断面を有しており、ビニール製等の所定メッシュから形成されている。
【0027】
そして、各メッシュ袋4の端部よりセメントペースト(固化材)10を適宜に流入充填させる。次いで、図3に示すように、メッシュ袋7内に(該メッシュ袋7とメッシュ袋4との間にある断面リング状間隙部に)それらの端部、或いは、図示しない所定のプラグやニップルを介し図示しないコンクリートポンプによりセメントペースト,セメントモルタル10´を注入充填させる。これによりメッシュ袋7は丸太棒状のメッシュ袋4を内装して埋設した状態で(この場合、該メッシュ袋4から滲出するセメントペースト,セメントモルタルにより固化一体化する。)、断面円形にされて図9に示すような梁状のフレーム11を形成する。
【0028】
この場合、フレキシブル鉄筋5が配設されたメッシュ袋4は、メッシュ袋7を各アンカー8,8´に挿通した後において、当該メッシュ袋7に挿通するようにしても良い。
【0029】
而して、この際、フレーム11は横(または縦)の行状(または列状)の一方方向の平行配列でも良い。或いは、図4に示すように、縦横方向に会合的に交叉してマトリックス状に配列しても良い。後者の場合、図5に示すように、交叉部分において一方のメッシュ袋7が他方のメッシュ袋7の上部、或いは、下側にてオーバーラップ的に交叉するようにする。
なお、充填するセメントモルタル,セメントペースト10´等の固化材は、充填時において塑性的に変形するようになっているので、実質的には、交叉するメッシュ袋7,7が互いに干渉することはない。
また、地山1を適宜に凹状(図5の凹状部2´参照)に掘削して下側を屈曲させるようにしている。そのため、ネットワーク状のマトリックス的フレーム11の配列は、困難なく行われるようになっている。
さらに、メッシュ袋から滲出するセメントペースト,セメントモルタルにより一体化され、これらの配列姿勢は各アンカー8,8´のリングヘッド9,9´により充分に保形維持されるようになっている(但し、交叉部の固定状態は必ずしも充分に保証されるものではない)。
【0030】
そして、各フレーム11のセット施工が終了すれば、これらの各フレーム11,11間にショットクリート等の手段によりコンクリートミルクやセメントモルタルを吹き付けするようにして斜面安定化の施工を終了するようにする。
【0031】
この間、メッシュ袋7に対して、フレキシブル鉄筋5を介装したメッシュ袋4を挿入する等の作業は工場等で前作業として行うことが可能である。このように、工場等において前作業を行うことにより、施工現場における作業性は改善され、また、施工精度も充分なものとなる。また、従来のように施工現場において配筋や型枠搬入,建て付け等の作業を行う必要がないばかりか、資材の解体,撤去等の作業も省けることになる。加えて、周辺環境の悪化等を何ら招くことはない。
【0032】
上述実施例は原理的基本実施例の態様であって、図4に示すように、フレーム11がマトリックス状に配列されて、各々主アンカー8、補助アンカー8´により斜面2の地山1にセットされ、縦方向、及び、横方向の条列については図5に示す様に、クロス状態にしてセットされる態様を示してあるが、前述の施工にあっては当該図5に示すクロス部分が施工時は勿論こと、施工後にあっても相対摺動等によりその剛性が充分でない虞がある場合があるが、この出願の発明にあってはフレーム11の配列を縦、或いは、横配列のみの条列として斜面2に対し安定した構築状態を現出することを図ることもこの出願の発明の精神に含むものであり、図9に示す様に、斜面2に対し、縦、或いは、横配列の相互に平行な条列(当該図9に示す態様においては縦方向配列)にし、相互の間隔を設計施工でLの幅にとり、各フレーム11については主アンカー8、及び、補助アンカー8´を所定間隔にとって斜面2の地盤に固定するようにする。
【0033】
しかしながら、前述したように、斜面2は傾斜している。そのため、施工中(或いは施工後)において、フレーム11の各メッシュ袋7に対して、内部に充填されているセメントペースト10´やフレキシブル鉄筋5等の重力の分力により下方に対し滑り力が働くこともある。したがって、当該メッシュ袋7の斜面2に対する安定性が良くないような場合もある。
【0034】
このような場合には、図10に示すように、施工に先立って主アンカー8を設ける斜面2の部分にピット12を予め凹設形成する。次いで、当該斜面2の地盤内へ主アンカー8を貫入して、該主アンカー8の基部を緊締固結する。その後、「フレキシブル鉄筋5を挿入してあるメッシュ袋4」を内装するメッシュ袋7を主アンカー8のリングヘッド9に挿通し、さらに、セメントペースト10´を圧入充填する。
【0035】
これにより、メッシュ袋7は固形化されて主アンカー8のリングヘッド9の内周面に緊締され、さらに、ピット12の打設コンクリート12´により滲出コンクリートによって密着される。その結果、施工中、或いは、施工後において、メッシュ袋7が斜面2に沿って下降,変移することが防止されることとなる。
【0036】
而して、斜面2に対するフレーム11の施工時、或いは、施工後の斜面の安定性をより確実に保証するために、図11,図12に示す実施例のような施工態様が採用可能である。
【0037】
すなわち、まず所定サイズの短円筒状のジョイントパイプ13を用意する。当該ジョイントパイプ13の下側にはスリット21が形成されている。そして、このジョイントパイプ13に対して、両端内周面にねじ14が螺刻してある所定長さのカラー15,15を螺合させる。次いで、各カラー15に対して、メッシュ袋7の端部を挿入連結し、さらに接着剤を用いて固定する。
【0038】
また、地山1に打設したアンカー16の上端部には、アンカーマス18が、ねじ螺合19により螺合連結してある。これにより、アンカー16とアンカーマス18とが一体化するようになっている。
【0039】
一方、アンカーマス18の表面には、フックピン20が敷設固定してある。このフックピン20にメッシュ袋4を挿通させて、当該メッシュ袋4ごとフレキシブル鉄筋5を、ジョイントパイプ13のスリット21から突き出たアンカーマス18に引っ掛ける。その結果、フレキシブル鉄筋5がメッシュ袋4ごと、アンカーマス18を介して、アンカー16に対して引張り状態で固定されることとなる。
【0040】
而して、メッシュ袋4、及び、フレキシブル鉄筋5のメッシュ袋7、カラー15、ジョイントパイプ13に対する係合、及び、コンクリート12´の打設等の施工の順は適宜に行えば良い。
【0041】
このようにして、フレキシブル鉄筋5がメッシュ袋4ごとアンカー16に引張り状態で固定される。そのため、フレーム11は斜面2の地山1に対し設計通りの施工姿勢を剛に保持し、滑り降下することはない。
【0042】
また、この場合、図示していないが、「フレキシブル鉄筋5を収納したメッシュ袋4」をメッシュ袋7内の上方の定位置に配置することにより斜面2が滑った場合であってもフレキシブル鉄筋5が鉄筋コンクリート構造の法枠の引張側に確実に置かれることにより、斜面2の滑りに抵抗する力の大きな法枠を提供することができることになる。
【0043】
フレキシブル鉄筋5を挿入したメッシュ袋4をメッシュ袋7内に設ける方法については、先述したように、施工現場へのメッシュ袋7のセット時において、予め作られたフレキシブル鉄筋5内装のメッシュ袋4を、当該メッシュ袋7の端部より挿入することによって行っても良い。
【0044】
また、他の態様としては、まず、図13〜図16に示す実施例の様に、メッシュ袋7を条列状に主アンカー8及び補助アンカー8´に挿通した状態で、その長手方向に沿ってカッター等の適宜の治具を用いて所定長さのスリット23を形成する。その際、当該スリット23を幅方向に開閉自在であるようにしておく。そして、スリット23を図14に示すように部分的、或いは、全体的に開いて、フレキシブル鉄筋5を内装したメッシュ袋4を手さぐり式に挿入して長手方向にセットするようにしても良い。
【0045】
上述した他の態様の場合には、スクリュージョイントタイプのターンバックル状に形成され、内側に雌ネジ24´が螺刻してある「長ナット24」を用意する。そして、スリット23を介してのメッシュ袋4の挿入に先立って、フレキシブル鉄筋5の端部に刻設した雄ネジに対して、上記長ナット24を所定長さだけ螺合させておく(図14参照)。
【0046】
そして、フレキシブル鉄筋5内装のメッシュ袋4を、スライド挿入させることによってメッシュ袋7内にセットする。その際、フレキシブル鉄筋5の端部に螺装した長ナット24を、スリット23の端部から手さぐりにより、予め挿入されているメッシュ袋4のフレキシブル鉄筋5の尻手に対して臨ませる。続いて、図15に示すように、長ナット24の雌ネジ24´に対して、フレキシブル鉄筋5の尻手の雄ネジ5´を螺合させる(この際、双方のフレキシブル鉄筋5,5が緊張状態になるように適宜引張り力を与えて螺合するようにする)。
【0047】
なお、メッシュ袋4の先挿入分の端部はやや緩くして長ナット24に外挿するようにする。
【0048】
このようにすることによりメッシュ袋7内において、メッシュ袋4を介装したフレキシブル鉄筋5,5…を設定長の連結状態にセットすることができる。
【0049】
そして、連結を終えた後のメッシュ袋7に対しては図16に示すように、スリット23の両縁部分を合体させて、一体縁部23´が形成されるようにする。そして、そこにホッチキス等のスティプラ25,25…を介して所定ピッチ、即ち、スリット23が開かないように縫合する。
【0050】
なお、かかるメッシュ袋7内へのメッシュ袋4に内装したフレキシブル鉄筋5,5…の設定長さ連結に際してはメッシュ袋23の縫合でホッチキス等のスティプラに変えて瞬間接着剤を用い、或いは、スティプラと双方を用いること等可能である。
【0051】
なお、図15においてメッシュ袋7の開口部分はスリット23ではなく、単に透視図的に図示の都合上、切開してある部分を示すものである。
【0052】
なお、この出願の発明の実施態様は上述各実施例に限るものでないことは勿論であり、例えば、図6に示す様に、アンカー8,8´のリングヘッド9´´については方形断面を有するように形成してもよい。また、メッシュ袋7については2本以上まとめて束ねるようにしてもよい。また、各メッシュ袋7内のセメントペースト10´についても2体以上にしたり、また、内装するフレキシブル鉄筋等の鉄筋5もまた2本以上束ねるようにすることができる等は勿論のことである。
【0053】
そして、設計変更的にはフレーム11としてのメッシュ袋7のアンカー8,8´に対するセット後にラス網等をセットしてコンクリートの吹き付け打設等を行うようにすること等ができる。
【0054】
そして、適用対象は上述態様以外にも道路の側部斜面以外の鉄道の側部斜面やその開渠,横路等の斜面に対しても適用できることも勿論のことである。
【0055】
【発明の効果】
以上、この出願の発明によれば、基本的に、鉄道,道路等の側部の斜面を保護を図る安定化工事の施工に際し、何らフリーフレーム施工等のコンクリート打設に伴う現場での配筋工事や型枠セット等の手作業が要らないこととなる。したがって、施工能率が良く、安全性も高く、しかも、作業能率が良いことから、低コスト化が図ることができる。そのうえ、高精度の施工の再現性が高い設計通りの施工がなされ、斜面安定の信頼性が高められるという優れた効果が奏される。
【0056】
また、上述した発明によれば、ビニール製等の閉じ断面の可撓性のメッシュ袋に対して、フレーム本体を成すビニール製等のメッシュ袋が予めフレキシブル鉄筋等の配筋を挿入した状態で内装されるようになっている。そのため、現場搬入に際し、予め工場製作等ができ、この点からも極めて作業がし易く、安全で高能率に工事ができるという効果もある。
【0057】
しかも、メッシュ袋からのメッシュを介してのセメントペーストやセメントミルクの滲出が周囲を一体化されて固化される優れた効果が奏される。
【0058】
而して、斜面安定化装置にあっては、メッシュ袋内に配筋を挿入されたメッシュ袋を内装することにより、また、該メッシュ袋内に配筋を介してのセメントペースト等の固化材の圧入充填を行うようにしておくことにより、該メッシュ袋内へのセメントペーストやセメントモルタル等の固化材の注入充填がし易いという効果があり、充分にフレームの保形性を維持し、また、取り扱いもし易いとう効果がある。
【0059】
そして、斜面の地山に、例えば、マトリックス状に縦横方向にアンカーを貫入配列させ、それらのリングヘッドにメッシュ袋を挿入するという簡単な操作で縦横、或いは、一方方向フレーム形成のセットが確実に行われ、しかも、アンカーによりセット姿勢が確実に保護されることから、斜面安定フレームの施工状態が経時的にも充分に保証され、地山の崩壊や地下水漏出等が充分に阻止されるという効果がある。
【図面の簡単な説明】
【図1】1実施例の装置の部分切截斜視図である。
【図2】同斜面へのセット状態の取り合い部分切截側面図である。
【図3】固化材充填状態のフレームの斜面に対するセット姿勢断面図である。
【図4】斜面の地山に対するマトリックス状のフレームのセット姿勢平面図である。
【図5】フレームの交叉部分の斜視図である。
【図6】フレームのリングヘッドを介しての地山への取り付け,取り合い姿勢断面図である。
【図7】主アンカーの概略斜視図である。
【図8】補助アンカーの概略斜視図である。
【図9】別施工実施例の概略平面図である。
【図10】同、概略縦断面図である。
【図11】別の具体実施例の縦断面図である。
【図12】同、部分横断面図である。
【図13】メッシュ袋に対するスリット形成の部分拡大斜視図である。
【図14】同、メッシュに対するフレキシブル鉄筋内装のスライド挿入プロセス概略斜視図である。
【図15】メッシュ袋内フレキシブル鉄筋の長ナットを介しての連結状態斜視図である。
【図16】フレキシブル鉄筋内装のメッシュ袋のメッシュ袋内連結後のメッシュ袋のスリット縫合斜視図である。
【符号の説明】
1 地山
2 斜面
2´ 凹状部
3 斜面安定化装置
4 メッシュ袋(第1のメッシュ袋)
フレキシブル鉄筋
5´ 雄ネジ
6 スペーサ
7 メッシュ袋(第2のメッシュ袋)
8,8´ アンカー
9,9´ リングヘッド
10 セメントペースト(固化材)
10´ セメントペースト(固化材)
11 フレーム
12 ピット
13 ジョイントパイプ
14 ねじ
16 アンカー
19 ねじ螺合
20 フックピン
21 スリット
23 スリット
24 長ナット
24´ 雌ネジ
25 スティプラ
[0001]
[Industrial applications]
The disclosed technology belongs to the technical field of construction of a frame for stabilizing a slope formed on a side portion of a road or the like.
[0002]
[Prior art]
As is well known, modern society is supported by a lot of information, and therefore, information processing networks are being expanded more and more on a nationwide scale.
[0003]
Such an information processing network is not only based on a means such as a telecommunications network or a radio wave, but also in a very large number of modes maintained by a railway, a road, a cable along the railway, the road, and the like.
[0004]
Therefore, anyway, construction work on expressways and railways is extremely important, and interaction with existing surrounding structures cannot be ignored, and there are problems such as pollution problems, harmony with the environment, and safety maintenance. Is also very important.
[0005]
Therefore, in order to prevent the collapse, collapse, and leakage of groundwater from the viewpoint of safety in the construction of these open channels, horizontal roads, and the like, and in the use condition after construction, the sides (up and down) stabilization of the slope of the side) is Ru indispensable. Therefore, construction techniques such as a so-called free frame have been widely used.
[0006]
Thus, for the stabilization work of the slope, for example, as shown in the invention disclosed in Japanese Patent Application Laid-Open No. 5-140948, a tensile material is buried at a construction site, or a reinforcement work is performed on a ground. Work such as casting concrete with a heavy machine or the like carried in by taking an anchor through a form to form a frame (beam) and spraying cement mortar between the frames has been performed .
[0007]
However, carry-in, such as rebar and formwork in these works, Kenkomi, assembly, disassembly of the jig or the like, removal, etc., human wave tactics ones is Ru main der by all human hand. Moreover, from being carried out by the inclined surface work forms a slope, work efficiency is a disadvantage there Ru that bad. Moreover, not only there is a drawback that can not be maintained safety sufficiently, it was also inconvenience of causing deterioration of the surrounding environment in the construction period (including its longitudinal).
[0008]
There is also a mode in which a free frame is bent and installed on a tree. However, there is a disadvantage that the tree is damaged and the environment is deteriorated.
[0009]
[Problems to be solved by the invention]
In view of the above-mentioned problems of the prior art, an object of the invention of this application is to solve various problems associated with stabilization work on a side slope of an installation site of a structure such as an open channel based on the above-mentioned prior art. In the field of civil engineering technology in the construction industry, the work efficiency is good, the safety is high, and there is no risk of deteriorating the work environment for the surroundings. It is an object of the present invention to provide an excellent slope stabilization method which is advantageous to the above, and a device directly used in the method.
[0010]
[Means for Solving the Problems]
(1) In order to achieve the above object, in the method according to the present invention, a frame base is formed by inserting a flexible reinforcing bar into a flexible first mesh bag, and further forming a flexible base. A method of stabilizing the slope by installing the frame formed in advance by inserting the frame base into the second mesh bag having the property, by installing the slope on the ground slope,
Forming a plurality of pits at a predetermined pitch on the slope of the ground,
In each of the plurality of formed pits, an anchor is fixed,
In the pit where the anchor was fixed, concrete was poured,
On the slope, lay the previously formed frame along the anchor,
With the anchor, the laid frame is engaged,
Filling the first mesh bag of the frame with a solidifying agent,
The second mesh bag of the frame is filled with a solidifying agent.
[0011]
(2) In order to achieve the above object, the method according to the present invention
A frame base is formed by inserting a flexible reinforcing bar into a flexible first mesh bag, and then a plurality of flexible second mesh bags are connected to a slit-formed joint. By connecting a frame formed in advance by inserting the frame base into the connected second mesh bag, the frame is connected to the second mesh bag via a pipe, and the slope is formed on the slope of the ground. Is a method of stabilizing
On the slope of the ground, a plurality of anchors with hooks are fixedly provided at a predetermined pitch,
On the slope, lay the previously formed frame along the anchor,
Filling the first mesh bag of the frame with a solidifying agent,
Filling the second mesh bag of the frame with a solidifying agent,
By hooking the frame base of the laid frame on the hook of the anchor, the frame base is fixed in a tensioned state by the anchor via the slit.
[0012]
(3) In the slope stabilization method according to the above (1) or (2), preferably, the frame base has a bent spacer in addition to the flexible reinforcing bar inside the frame base.
[0013]
(4) In the step of laying the frame in the slope stabilization method according to the above (1) or (2), preferably, the frame is laid in any of a column shape, a row shape, and a matrix shape.
[0014]
(5) In order to achieve the above object, an apparatus of the present invention is an apparatus used in the slope stabilization method according to any one of (1) to (4),
A frame base including: a flexible reinforcing bar, a bent spacer, and a flexible first mesh bag including the flexible reinforcing bar and the spacer inside;
A frame formed by inserting the frame base into a flexible second mesh bag.
[0015]
(6) In order to achieve the above object, an apparatus of the present invention is an apparatus used in the slope stabilization method according to any one of (1) to (4) ,
A plurality of frame bases including: a flexible reinforcing bar having an external thread formed at an end; a bent spacer; and a flexible first mesh bag including the flexible reinforcing bar and the spacer inside;
A frame formed by inserting the frame base into a flexible second mesh bag;
A female nut is formed on the inside, and a long nut for connecting the plurality of frame bases in the frame;
One end of the long nut is screwed to an end of the flexible reinforcing bar of the inserted one frame base,
The other end of the long nut is screwed with the end of the flexible reinforcing bar of the other inserted frame base.
[0016]
(7) In the slope stabilizing device according to the above (5) or (6), preferably,
A solidifying agent is filled in the first mesh bag of the frame,
The second mesh bag of the frame is filled with a solidifying agent.
[0017]
【Example】
Next, embodiments of the invention of this application will be described with reference to the drawings.
[0018]
Illustrated embodiment, the protection against the inclined surface 2 of the natural ground 1 road side, about aspects of the stabilization works for maintenance. In the figure, reference numeral 3 indicates the "Slope stabilizer" which forms the center of one of the subject matter of the invention of this application. Reference numeral 4 denotes a flexible “mesh bag” of a predetermined size having a closed cross section , which is formed of a predetermined mesh made of a permeable vinyl sheet or the like.
[0019]
In the principle mode shown in FIGS. 1 to 5, for example, at least one flexible reinforcing bar 5 for applying tension , which is known around the circumference, is inserted into a mesh bag (first mesh bag) 4 in advance at a factory. has become so that the shape inserted into the spacer 6,6 also suitable for "V" in contact with the inner surface of the mesh bag 4 at a predetermined pitch.
[0020]
Incidentally, the spacer 6, in one its longitudinal of the flexible reinforcing bar 5, which is molded by bending changes direction to shape the "V" in a zigzag fashion in the vertical and horizontal directions by 90 ° at a predetermined pitch It may be.
[0021]
And Thus, the spacer 6 as described next, when for flowing filled with cement paste 10 as solidified material from the longitudinal ends of the mesh bag 4, functions to hold the expanded position of the mesh bag 4 Things.
[0022]
The cement paste is exuded from the mesh gap to solidify and integrate with the surroundings.
[0023]
When the cement paste 10 flows and fills into the mesh bag 4 in this way, the mesh bag 4 becomes a kind of a round bar and forms a base of the frame.
[0024]
And Thus, when the slope stabilization works, the main anchors 8,8 ..., and the auxiliary anchors 8 ', the 8', as shown in FIGS. 7 and 8, the line shape at a predetermined pitch on the slope 2 of the natural ground 1 (Or in a row or a matrix), and are fixed by being driven into a predetermined depth.
[0025]
Note that the base of each main anchor 8, as shown in FIGS. 7 and 8, a circular cross section of the ring head 9 (or even allowed by pin joint) integrally has, or, provided screw screwed manner I have.
[0026]
Then, the mesh bag (second mesh bag) 7 containing the mesh bag 4 into which the flexible reinforcing bars 5 and the spacers 6 are inserted” is inserted into and engaged with the ring heads 9 and 9 ′ of the anchors 8 and 8 ′. To form a network of rows and columns . Furthermore, based on this, as shown in FIG. 4, a network of a kind of matrix-like frame 11 is formed and laid by sewing trees on the surface of the slope 2 of the ground 1 as an application.
The mesh bag 7 inside the mesh bag 4 is formed in a closed cross section of a predetermined size (circular cross section, square, etc.), has a cross section larger than the cross section of the mesh bag 4, and has a predetermined cross section made of vinyl or the like. It is formed from a mesh.
[0027]
Then, the end portion of the mesh bag 4, Ru is appropriately flowed filled with cement paste (consolidated material) 10. Then, as shown in FIG. 3, these ends or predetermined plugs or nipples (not shown) are placed in the mesh bag 7 ( at a ring-shaped cross section between the mesh bag 7 and the mesh bag 4). the concrete pump (not shown) through, cement paste, Ru is injected filled with cement mortar 10 '. Thus, the mesh bag 7 is in a state of being embedded in interior mesh pouch 4 logs rod-shaped (in this case, the cement paste, and solidified integrally by cement mortar exuded from the mesh bag 4.), Into a circular cross section Thus, a beam-shaped frame 11 as shown in FIG. 9 is formed.
[0028]
In this case, the mesh bag 4 in which the flexible reinforcing bars 5 are disposed may be inserted into the mesh bag 7 after the mesh bag 7 is inserted into each of the anchors 8 and 8 '.
[0029]
And Thus, this time, the frame 11 is not good in one direction of parallel alignment of rows (or columns) of the lateral (or vertical). Alternatively, as shown in FIG. 4, but it may also be arranged in a matrix in association to cross in the vertical and horizontal directions. In the latter case, as shown in FIG. 5, one mesh bag 7 is overlapped with the other mesh bag 7 at the intersection at an upper portion or a lower portion at the intersection.
Incidentally, cement mortar filling, solidification agent of cement paste 10 ', etc., so adapted to Oite plastically deformed during filling, in effect, that the mesh bags 7,7 which cross interfere with each other There is no.
In addition, the ground 1 is appropriately dug into a concave shape (see a concave portion 2 ′ in FIG. 5) so that the lower side is bent . Therefore, the arrangement of the network-like matrix-like frames 11 is performed without difficulty .
Further, the cement paste exudes from the mesh bag, are integrated by cement mortar, these sequences posture is sufficiently adapted to be shape-retaining maintained by the ring head 9, 9 'of each anchor 8, 8' (where However, the fixed state of the crossover portion is not always sufficiently guaranteed).
[0030]
Then, when the set construction of each frame 11 is completed, concrete milk or cement mortar is sprayed between these frames 11 and 11 by means such as shotcrete or the like, so that the slope stabilization construction is completed. .
[0031]
During this time, the pair mesh bag 7, operations such as inserting a mesh bag 4 is interposed a flexible reinforcing bar 5 may be carried out as a pre-work in a factory or the like. As described above, by performing the preparatory work in a factory or the like, the workability at the construction site is improved, and the construction accuracy is also sufficient . In addition, the conventional reinforcement and formwork carried in a construction site in this way, not only is not necessary to perform the work of built with, etc., dismantling of materials, ing to be Habukeru also work of removal and the like. In addition, it does not cause any deterioration of the surrounding environment.
[0032]
The above embodiment is an aspect of the basic basic embodiment. As shown in FIG. 4, the frames 11 are arranged in a matrix and set on the ground 1 on the slope 2 by the main anchor 8 and the auxiliary anchor 8 ', respectively. The vertical and horizontal rows are shown as being set in a cross state as shown in FIG. 5, but in the above-described construction, the cross portion shown in FIG. At the time of construction, of course, even after the construction, there is a case where the rigidity may not be sufficient due to relative sliding or the like. However, in the invention of this application, the arrangement of the frame 11 is vertical or horizontal only. It is also included in the spirit of the invention of the present application to realize a stable construction state on the slope 2 as a row. As shown in FIG. 9, the slope 2 is vertically or horizontally arranged. Parallel to each other (an embodiment shown in FIG. 9) In the vertical direction), the distance between them is set to L by design and construction, and the main anchor 8 and the auxiliary anchor 8 'are fixed to the ground of the slope 2 with a predetermined interval for each frame 11. .
[0033]
However, as described above, the slope 2 is inclined. Therefore, during the construction (or after construction), each relative to the mesh bag 7, sliding force to lower the cement paste 10 'and the flexible reinforcing bar 5 and the like gravity force component of which is filled therein work of the frame 11 Sometimes. Therefore, there are cases where the stability of the mesh bag 7 with respect to the slope 2 is not good .
[0034]
In such a case, as shown in FIG. 10, prior to the construction, the part of the slope 2 providing the main anchor 8, advance recessed form pits 12. Next, the main anchor 8 penetrates into the ground of the slope 2, and the base of the main anchor 8 is tightened. Thereafter, a mesh bag 7 to interior a "mesh bag 4 has been inserted a flexible reinforcing bar 5 'is inserted through the ring head 9 of the main anchor 8, further pressed filled with cement paste 10'.
[0035]
Thus, the mesh bag 7 is fastened to the inner peripheral surface of the ring head 9 of the main anchor 8 is solidified, and is further adhered by exudation concrete by pouring concrete 12 'pit 12. As a result, the mesh bag 7 is prevented from falling and displacing along the slope 2 during or after construction.
[0036]
Thus, in order to more reliably assure the stability of the slope 11 at the time of applying the frame 11 to the slope 2 or after the execution, an embodiment such as the embodiment shown in FIGS. 11 and 12 can be adopted. .
[0037]
That is, first, a short cylindrical joint pipe 13 of a predetermined size is prepared. A slit 21 is formed below the joint pipe 13. Then, collars 15, 15 of a predetermined length having screws 14 threaded on the inner peripheral surfaces of both ends are screwed into the joint pipe 13. Next, the end of the mesh bag 7 is inserted and connected to each collar 15 and further fixed using an adhesive.
[0038]
An anchor mass 18 is screwed and connected to an upper end portion of the anchor 16 cast on the ground 1 by a screw screw 19. Thereby, the anchor 16 and the anchor mass 18 are integrated.
[0039]
On the other hand, a hook pin 20 is laid and fixed on the surface of the anchor mass 18. The mesh bag 4 is inserted through the hook pins 20, and the flexible rebar 5 together with the mesh bag 4 is hooked on the anchor mass 18 protruding from the slit 21 of the joint pipe 13. As a result, the flexible rebar 5 together with the mesh bag 4 is fixed to the anchor 16 via the anchor mass 18 in a tensile state.
[0040]
Thus, the order of the mesh bag 4, the engagement of the flexible rebar 5 with the mesh bag 7, the collar 15, the joint pipe 13, and the construction of the concrete 12 'may be performed as appropriate.
[0041]
In this manner, the flexible rebar 5 together with the mesh bag 4 is fixed to the anchor 16 under tension. Therefore, the frame 11 firmly maintains the construction posture as designed with respect to the ground 1 on the slope 2 and does not slide down.
[0042]
In this case, although not shown, by placing a "flexible rebar 5 mesh bags 4 that houses the" in place of the above in a mesh bag 7, even when the slope 2 is slipped, flexible By ensuring that the rebar 5 is placed on the tension side of the reinforced concrete structure frame, it is possible to provide a law frame with a large resistance to sliding of the slope 2.
[0043]
As described above, when the mesh bag 4 into which the flexible reinforcing bar 5 is inserted is provided in the mesh bag 7, the mesh bag 4 having the flexible reinforcing bar 5 interior prepared in advance is set when the mesh bag 7 is set at the construction site. Alternatively, it may be performed by inserting from the end of the mesh bag 7.
[0044]
As another embodiment, first, as in the embodiment shown in FIGS. 13 to 16, the mesh bags 7 are inserted in the main anchor 8 and the auxiliary anchor 8 ′ in the form of a row and along the longitudinal direction thereof. Then, a slit 23 having a predetermined length is formed using an appropriate jig such as a cutter . At that time, your Ku as a freely opening and closing the slit 23 in the width direction. Then, partly to show the slit 23 in FIG. 14, or open as a whole, the mesh bag 4 that decorated flexible reinforcing bar 5 may be set in the longitudinal direction by inserting a trial and error type .
[0045]
In the case of the other embodiment described above, a "long nut 24" which is formed in a screw joint type turnbuckle shape and has a female screw 24 'threaded inside is prepared. Prior to insertion of the mesh bag 4 through the slit 23, the long nut 24 is screwed by a predetermined length to a male screw engraved on the end of the flexible reinforcing bar 5 (FIG. 14). reference).
[0046]
Then, the mesh bag 4 inside the flexible reinforcing bar 5 is set in the mesh bag 7 by slidingly inserting the same. At this time, the long nut 24 screwed to the end of the flexible reinforcing bar 5 is made to face the hand of the flexible reinforcing bar 5 of the mesh bag 4 which has been inserted in advance by hand-raising from the end of the slit 23. Subsequently, as shown in FIG. 15, the male screw 5 ′ of the tail of the flexible rebar 5 is screwed into the female screw 24 ′ of the long nut 24 (in this case, both flexible rebars 5, 5 are in a tensioned state). ) And apply a tensile force as needed to screw together.
[0047]
The end portion of the mesh bag 4 for the first insertion is slightly loosened so as to be inserted outside the long nut 24.
[0048]
In this way, in the mesh bag 7, the flexible reinforcing bar 5,5 ... with interposed mesh bag 4 can be set to a connection state of setting length.
[0049]
Then, with respect to the mesh bag 7 after the connection is completed , as shown in FIG. 16, both edge portions of the slit 23 are united so that an integral edge portion 23 ' is formed. Then, a stitch is stitched through a stapler 25 such as a stapler or the like so as to prevent the slit 23 from opening.
[0050]
When the set lengths of the flexible rebars 5, 5,... Provided inside the mesh bag 4 are connected to the mesh bag 7, a stapler such as a stapler is used by sewing the mesh bag 23, or an instant adhesive is used. It is possible to use both.
[0051]
In FIG. 15, the opening portion of the mesh bag 7 is not a slit 23, but merely shows a cut-away portion for convenience of illustration in a perspective view.
[0052]
It is needless to say that the embodiments of the invention of this application are not limited to the above-described embodiments. For example, as shown in FIG. 6, the ring head 9 ″ of the anchors 8, 8 ′ has a rectangular cross section . It may be formed as follows. Further, the mesh bag 7 may be bundled two or more together. Further, it is needless to say that the cement paste 10 'in each mesh bag 7 can be made of two or more bodies, and that two or more reinforcing bars 5 such as flexible reinforcing bars to be installed can be bundled.
[0053]
As a design change, a lath net or the like can be set after setting the mesh bag 7 as the frame 11 to the anchors 8 and 8 ', and the concrete can be sprayed and cast.
[0054]
In addition to the above-described embodiments, the present invention can be applied to a side slope of a railway other than the side slope of a road, and a slope such as an open channel or a cross road.
[0055]
【The invention's effect】
As described above, according to the invention of this application, basically, at the time of stabilization work for protecting side slopes such as railroads and roads, there is no reinforcement at the site accompanying concrete casting such as free frame construction. No manual work such as construction or form setting is required . Therefore, since the construction efficiency is good, the safety is high, and the work efficiency is good, the cost can be reduced . In addition, construction is performed as designed with high reproducibility of high-precision construction, and an excellent effect that reliability of slope stability is enhanced is exhibited.
[0056]
Further, according to the invention described above, with respect to the flexibility of the mesh bag closed cross section of the vinyl or the like, furnished in a state in which the mesh bag vinyl such as forming a frame body has previously inserted a reinforcement such as a flexible reinforcing bar It has become so that is. For this reason, it is possible to manufacture a factory in advance at the time of loading into the site, and from this point, the work is extremely easy, and there is an effect that the construction can be performed safely and efficiently.
[0057]
In addition, an excellent effect is obtained in which the exudation of the cement paste or the cement milk from the mesh bag through the mesh is integrated around the periphery and solidified.
[0058]
Thus, in the slope stabilizing device, the mesh bag in which the reinforcing bar is inserted is internally provided in the mesh bag, and a solidifying material such as cement paste is provided in the mesh bag via the reinforcing bar. By performing the press-fitting, there is an effect that it is easy to inject and fill a solidifying material such as cement paste or cement mortar into the mesh bag, sufficiently maintaining the shape retention of the frame, and It is easy to handle.
[0059]
Then, for example, the anchors are vertically and horizontally arranged in a matrix in the vertical and horizontal directions in the ground on the slope, and a simple operation of inserting the mesh bag into their ring heads, or the set of one-way frame formation is surely performed. The effect is that the set posture is reliably protected by the anchor, so that the construction state of the slope stabilization frame is sufficiently ensured over time, and the collapse of the ground and leakage of groundwater are sufficiently prevented. There is.
[Brief description of the drawings]
FIG. 1 is a partial cutaway perspective view of an apparatus according to one embodiment.
FIG. 2 is a partially cut-away side view of a setting state of the inclined surface.
FIG. 3 is a cross-sectional view of a setting posture with respect to a slope of a frame in a state where a solidified material is filled.
FIG. 4 is a plan view of a set posture of a matrix-shaped frame with respect to a ground on a slope.
FIG. 5 is a perspective view of a crossing portion of the frame.
FIG. 6 is a cross-sectional view illustrating a mounting posture of a frame to a ground through a ring head.
FIG. 7 is a schematic perspective view of a main anchor.
FIG. 8 is a schematic perspective view of an auxiliary anchor.
FIG. 9 is a schematic plan view of another construction example.
FIG. 10 is a schematic longitudinal sectional view of the same.
FIG. 11 is a longitudinal sectional view of another specific embodiment.
FIG. 12 is a partial cross-sectional view of the same.
FIG. 13 is a partially enlarged perspective view of forming a slit in the mesh bag.
FIG. 14 is a schematic perspective view of a slide insertion process of the flexible rebar interior into the mesh.
FIG. 15 is a perspective view showing a connection state of a flexible reinforcing bar in a mesh bag via a long nut.
FIG. 16 is a perspective view of a slit stitch of the mesh bag after the mesh bag inside the flexible reinforcing bar is connected to the mesh bag.
[Explanation of symbols]
1 Ground 2 Slope
2 'concave portion 3 slope stabilizing device 4 mesh bag (first mesh bag)
5 Flexible rebar
5 'male screw 6 spacer 7 mesh bag (second mesh bag)
8, 8 'anchor 9, 9' ring head 10 cement paste (solidifying material)
10 ' cement paste (solidifying material)
11 frames
12 pits
13 Joint pipe
14 Screw
16 Anchor
19 Screw thread
20 hook pins
21 slit
23 slit
24 long nut
24 'female screw
25 Stipula

Claims (7)

可撓性を有する第1のメッシュ袋内にフレキシブル鉄筋を挿入することによって、フレーム基体を形成しておき、さらに、可撓性を有する第2のメッシュ袋内に前記フレーム基体を挿入することによって予め形成しておいたフレームを、地山の斜面に対して設置することによって、当該斜面を安定化する工法であって、By inserting a flexible reinforcing bar into a flexible first mesh bag to form a frame base, and further inserting the frame base into a flexible second mesh bag. A method of stabilizing the slope by installing a previously formed frame on the slope of the ground,
前記地山の斜面に、所定ピッチで複数のピットを形成し、Forming a plurality of pits at a predetermined pitch on the slope of the ground,
形成された前記複数のピットのそれぞれにおいて、アンカーを固設し、In each of the plurality of formed pits, an anchor is fixed,
アンカーを固設した前記ピットにおいて、コンクリートを打設し、In the pit where the anchor was fixed, concrete was poured,
前記斜面において、予め形成しておいた前記フレームを前記アンカーに沿って敷設し、On the slope, lay the previously formed frame along the anchor,
前記アンカーに対して、敷設した前記フレームを係合させ、With the anchor, the laid frame is engaged,
前記フレームの前記第1のメッシュ袋内に固化剤を充填し、Filling the first mesh bag of the frame with a solidifying agent,
前記フレームの前記第2のメッシュ袋に固化剤を充填することを特徴とする斜面安定化工法。A slope stabilization method, wherein a solidifying agent is filled in the second mesh bag of the frame.
可撓性を有する第1のメッシュ袋内にフレキシブル鉄筋を挿入することによって、フレーム基体を形成しておき、次いで、可撓性を有する複数の第2のメッシュ袋を、スリットが形成されたジョイントパイプを介して連結しておき、さらに、連結した前記第2のメッシュ袋内に前記フレーム基体を挿入することによって予め形成しておいたフレームを、地山の斜面に対して設置することによって、当該斜面を安定化する工法であって、A frame base is formed by inserting a flexible reinforcing bar into a flexible first mesh bag, and then a plurality of flexible second mesh bags are connected to a slit-formed joint. By connecting via a pipe, further, by inserting the frame base into the connected second mesh bag, a frame previously formed, by installing on the slope of the ground, A method of stabilizing the slope,
前記地山の斜面に、フックを備えた複数のアンカーを、所定ピッチで固設し、On the slope of the ground, a plurality of anchors with hooks are fixedly provided at a predetermined pitch,
前記斜面において、予め形成しておいた前記フレームを前記アンカーに沿って敷設し、On the slope, lay the previously formed frame along the anchor,
前記フレームの前記第1のメッシュ袋内に固化剤を充填し、Filling the first mesh bag of the frame with a solidifying agent,
前記フレームの前記第2のメッシュ袋に固化剤を充填し、Filling the second mesh bag of the frame with a solidifying agent,
前記アンカーのフックに対して、敷設した前記フレームのフレーム基体を引っ掛けることによって、当該フレーム基体が、前記スリットを介して前記アンカーによって引っ張り状態で固定されるようにすることを特徴とする斜面安定化工法。A slope stabilizing method, wherein a frame base of the laid frame is hooked on a hook of the anchor so that the frame base is fixed in a tensioned state by the anchor through the slit. Law.
前記フレーム基体は、その内側に、前記フレキシブル鉄筋に加えて、屈曲して成るスペーサを有していることを特徴とする請求項1又は2記載の斜面安定化工法。The slope stabilization method according to claim 1, wherein the frame base has a bent spacer in addition to the flexible reinforcing bar inside the frame base. 前記フレームを敷設する工程において、前記フレームを、列状,行状,およびマトリックス状の何れかの状態に敷設することを特徴とする請求項1又は2記載の斜面安定化工法。The slope stabilization method according to claim 1, wherein, in the step of laying the frame, the frame is laid in any one of a column shape, a row shape, and a matrix shape. 上記請求項1乃至4の何れかに記載の斜面安定化工法において用いられる装置であって、An apparatus used in the slope stabilization method according to any one of claims 1 to 4,
フレキシブル鉄筋と、屈曲したスペーサと、当該フレキシブル鉄筋およびスペーサを内側に備える可撓性の第1のメッシュ袋と、を含むフレーム基体と;A frame base including a flexible reinforcing bar, a bent spacer, and a flexible first mesh bag including the flexible reinforcing bar and the spacer inside;
可撓性を有する第2のメッシュ袋に前記フレーム基体を挿入して成るフレームと;を有していることを特徴とする斜面安定化装置。A frame formed by inserting the frame base into a flexible second mesh bag.
上記請求項1乃至4の何れかに記載の斜面安定化工法において用いられる装置であって、An apparatus used in the slope stabilization method according to any one of claims 1 to 4,
端部に雄ネジが形成してあるフレキシブル鉄筋と、屈曲したスペーサと、当該フレキシブル鉄筋およびスペーサを内側に備える可撓性の第1のメッシュ袋と、を含む複数のフレーム基体と;A plurality of frame bases including: a flexible reinforcing bar having an external thread formed at an end; a bent spacer; and a flexible first mesh bag including the flexible reinforcing bar and the spacer inside;
可撓性を有する第2のメッシュ袋に前記フレーム基体を挿入して成るフレームと;A frame formed by inserting the frame base into a flexible second mesh bag;
内側に雌ネジが形成されており、前記フレーム内において前記複数のフレーム基体を連結する長ナットと;を有しており、A female nut is formed on the inside, and a long nut for connecting the plurality of frame bases in the frame;
前記長ナットの一端は、挿入してある一のフレーム基体のフレキシブル鉄筋の端部に対して螺合させてあり、One end of the long nut is screwed to an end of the flexible reinforcing bar of the inserted one frame base,
前記長ナットの他端は、挿入された他のフレーム基体のフレキシブル鉄筋の端部に対して螺合させてあることを特徴とする斜面安定化装置。The other end of the long nut is screwed into an end of a flexible reinforcing bar of another inserted frame base, and the other end of the long nut is screwed.
前記フレームの前記第1のメッシュ袋内には、固化剤が充填されており、A solidifying agent is filled in the first mesh bag of the frame,
前記フレームの前記第2のメッシュ袋には、固化剤が充填されていることを特徴とする請求項5又は6記載の斜面安定化装置。The slope stabilizing device according to claim 5, wherein the second mesh bag of the frame is filled with a solidifying agent.
JP20823894A 1994-08-10 1994-08-10 Slope stabilization method and equipment Expired - Fee Related JP3558229B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20823894A JP3558229B2 (en) 1994-08-10 1994-08-10 Slope stabilization method and equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20823894A JP3558229B2 (en) 1994-08-10 1994-08-10 Slope stabilization method and equipment

Publications (2)

Publication Number Publication Date
JPH0853845A JPH0853845A (en) 1996-02-27
JP3558229B2 true JP3558229B2 (en) 2004-08-25

Family

ID=16552950

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20823894A Expired - Fee Related JP3558229B2 (en) 1994-08-10 1994-08-10 Slope stabilization method and equipment

Country Status (1)

Country Link
JP (1) JP3558229B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7285482B2 (en) * 2019-08-05 2023-06-02 日本植生株式会社 Law frame forming tool and law frame forming method

Also Published As

Publication number Publication date
JPH0853845A (en) 1996-02-27

Similar Documents

Publication Publication Date Title
US3934422A (en) Pile splicing apparatus and method
EP2242885A2 (en) Wind turbine and associated construction method
JP2829825B2 (en) Close-contact protection net construction method for falling rocks and its rope / net anchor structure
EP0777019B1 (en) Method of jointing structure members
JP3558229B2 (en) Slope stabilization method and equipment
JP2535722B2 (en) Reinforcement concrete column and steel beam connection structure and building construction method
US4126001A (en) Method for constructing a soil structure
KR100661301B1 (en) Support structure for concreting in a head of steel pile and construction method using it
JPH03156094A (en) Under-roadbed traverse round section structure and its construction
JP6175791B2 (en) Ground reinforcement method and structure
JPH10317381A (en) Structure for protecting face of slope by retaining wall and method for constructing the same
CH621174A5 (en) Method of constructing a retaining wall and set of structural parts for carrying out this method
JPH09287318A (en) Repairing method of corroded and decayed utility-line pole
JPH0226014B2 (en)
JP2006283548A (en) Grating crib structure and method for constructing grating crib structure
KR101285987B1 (en) Improved Compound Roof Tunnel Method
JPH0681352A (en) Connecting method for precast concrete member
JPS6397721A (en) Slope frame construction work
JP2739562B2 (en) Anchor fixing body, method of manufacturing the same, and method of assembling anchor
JPH0967823A (en) Slope stabilizing method and anchor fixing pedestal used therefor
JP3629684B2 (en) Sound insulation wall foundation block
JPH0376929A (en) Steel-framed foundation
JPH09279610A (en) Method for constructing retaining wall and equipment therefor
JPH0211477Y2 (en)
JPH07102574A (en) Method for stabilizing slope

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040129

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040210

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040326

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040427

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040514

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090528

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090528

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100528

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100528

Year of fee payment: 6

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100528

Year of fee payment: 6

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110528

Year of fee payment: 7

LAPS Cancellation because of no payment of annual fees