JP3554937B2 - Construction method of pillars - Google Patents

Construction method of pillars Download PDF

Info

Publication number
JP3554937B2
JP3554937B2 JP14837893A JP14837893A JP3554937B2 JP 3554937 B2 JP3554937 B2 JP 3554937B2 JP 14837893 A JP14837893 A JP 14837893A JP 14837893 A JP14837893 A JP 14837893A JP 3554937 B2 JP3554937 B2 JP 3554937B2
Authority
JP
Japan
Prior art keywords
block
block body
reinforcing bar
main reinforcing
pillars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP14837893A
Other languages
Japanese (ja)
Other versions
JPH06336763A (en
Inventor
真一 玉井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP14837893A priority Critical patent/JP3554937B2/en
Publication of JPH06336763A publication Critical patent/JPH06336763A/en
Application granted granted Critical
Publication of JP3554937B2 publication Critical patent/JP3554937B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Rod-Shaped Construction Members (AREA)

Description

【0001】
【産業上の利用分野】
本発明は橋脚やラーメン高架橋の柱等の柱状物の施工方法に関する。
【0002】
【従来の技術】
鉄道高架橋や橋梁等の橋脚は、型枠を用いた所謂現場打ちにより施工されているが、工期が長くかかることや多くの支保工や型枠を必要として多大の労力を必要とすることから、現場打に代わる技術の提案が望まれている。
その改善技術としては、例えば橋脚を複数に分割したブロック体を積み上げた後、全体にプレストレスを導入する方法や、建築分野で使用されているプレキャストキャスト工法を橋脚に適用し、工場等で製作した橋脚の完成品を運搬して現場に据え付ける方法が提案されている。
【0003】
【発明が解決しようとする問題点】
前記した橋脚の施工技術には次のような問題点がある。
【0004】
<イ> 地震時において橋脚に作用する荷重方向が一定ではないため、プレストレスによる圧縮応力と荷重による圧縮応力の合計に耐え得るように橋脚を高強度に設計する必要があり、鉄筋コンクリートに比べてエネルギー吸収率が低い割に経済的な負担が大きい。
【0005】
<ロ> 複数のPC鋼材を接合しながら橋脚のブロック体を積み上げると、各PC鋼材の接合処理に手数がかかる。
【0006】
<ハ> 予め製作した橋脚を据え付ける方法にあっては、橋脚の柱断面が一般に大きいことから、運搬や据え付けに大型重機類を必要とし、施工性や安全性の点で改良の余地が有る。
【0007】
【本発明の目的】
本発明は以上の問題点を解決するためになされたもので、その目的とするところは、施工性、経済性に優れた柱状物の施工方法を提供することにある。
【0008】
【問題点を解決するための手段】
本発明は、柱状物の断面形を呈するブロック体を接着層を介在させながら積み上げると共に、主鉄筋を前記ブロック体間に連続して貫挿し、ブロック体と主鉄筋の間に固結材を注入して鉄筋コンクリート製の柱状物を施工する、柱状物の施工方法である。
【0009】
【実施例1】
以下図面を参照しながら本発明の実施例について説明する。
【0010】
<イ>主鉄筋の植設工程
【0011】
図2において1はコンクリート基礎で、このコンクリート基礎1に所定の間隔を隔てて異形の主鉄筋2を植設する。
主鉄筋2はコンクリート基礎1を施工する際、或いは施工後に穿孔する等して植設するものとし、また主鉄筋2は構築予定の橋脚の高さ分の長さを有する一本ものか、或いは後述する複数のブロック体の高さ以上の長さを有する分割体を溶接や接続具等を用いて延長するものであってもよい。
【0012】
<ロ>ブロック体の積み上げ工程(図2)
【0013】
つぎに橋脚を階層的に切断した形状に予め工場等で製作したブロック体3aを主鉄筋2に貫挿させてコンクリート基礎1に載置する。
ブロック体3aは橋脚の断面形状に合わせて形成した鉄筋コンクリート製の分割体で、主鉄筋3の貫挿位置に穿設した複数の貫通孔31を有すると共に、各貫通孔31内にコルゲート状のシース32が一体に固着してある。
ブロック体3aの高さ(重量)は運搬性や取扱性を考慮して決定する。
貫通孔31の内周面が異径または凹凸状に形成してあれば、シース32を省略する場合もある。
つぎにブロック体3aの上面に接着層4を形成した後、このブロック体3aの上面に別途のブロック体3bを搭載する。
この際、ブロック体3bは下位のブロック体3aから突出する主鉄筋2を貫通孔31に嵌挿させて搭載する。
接着層4には、コンクリートの接着強度より大きな接着力を有する市販の接着剤を使用できる。
以下同様に、ブロック体3bの上面に接着層4を形成する工程と、ブロック体3nを主鉄筋2に貫挿させて搭載する工程とを繰り返しながら、所定の高さまで積み上げる。
【0014】
<ハ>ブロック体の圧着工程(図3)
【0015】
最上位のブロック体3xから突出する主鉄筋2に座板5を介してナット6を螺着して、各ブロック体3a,3b,3n……3x間を一斉に締め付け、各ブロック体3a,3b,3n……3x間をより強固に圧着させて接着する。
接着層4が硬化したらナット6を取り外して、各ブロック体3a,3b,3n……3x間に導入していた圧着力を解除する。
各ブロック体3a,3b,3n……3xの圧着手段としては、ナット6による締め付けの他に、各ブロック体3a,3b,3n……3xの自重を利用しても良い。
尚、ブロック体の圧着工程は必須ではなく省略する場合もある。
【0016】
<ニ>固結材の注入(図1)
【0017】
最下部のブロック体3aの貫通孔31を利用して、連続して配設されたシース32内にモルタルやコンクリート等の固結材7を注入して、各ブロック体3a,3b,3n……3xの一体化を図り、鉄筋コンクリート製の橋脚3を得る。
接着層4は、橋脚を構成する各ブロック体の継目を閉鎖し浸水による主鉄筋2の防錆を阻止すると共に、各ブロック体の継目に応力集中が発生するのを回避するために役立つ。
【0018】
<ホ>橋脚の性能に関する考察
【0019】
上記の工程で接合した橋脚の性能について検討する。
図4のAは2つのブロック体3a,3bを前記の工程で接合して製作した橋脚3の供試体である。
この供試体Aと同寸法の橋脚を一体打設して鉄筋コンクリート製の供試体B(図示せず)を製作し、図示する同一条件で各供試体A,Bの曲げ試験を行った。その試験結果を図5に示す。
図5によれば、プレキャスト製のブロック体3a,3bを接合した供試体Aの曲げ特性が、コンクリートを一体打設して製作した供試体Bとほぼ同一であり、性能的に大差のないことが証明された。
【0020】
【実施例2】
ブロック体の上下面に夫々凹凸する形状の凹部と凸部を形成し、これらの凹部と凸部を嵌合させて各ブロック体を積み上げても良い。
本実施例によれば、凹部と凸部の嵌合により各ブロック体の剪断抵抗が増大すると共に、各ブロック体の接着面積が増してり強固な圧着が図れる利点が得られる。
【0021】
【実施例3】
主鉄筋2は各ブロック体を積み上げた後にセットしてもよく、また固結材7の注入工程を各ブロック体の積み上げ作業と並行して行ってもよい。
【0022】
【発明の効果】
本発明は以上説明したようになるから次のような効果を得ることができる。
【0023】
<イ> 柱状物の分割体であるブロック体を使用するから、施工に大型の重機を必要としない。
特に柱状物が大断面であっても容易に施工できる。
【0024】
<ロ> 主鉄筋がブロック体を貫挿して支柱的役割を果たすため、控えワイヤ等の支保工を必要としない。
【0025】
<ハ> 各ブロック体間にコンクリートの接着強度より大きな接着力を有する接着層を介在させることで、継目間にクラックが発生するのを効果的に防止できると共に、継目からの浸水による主鉄筋の腐食も防止できる。
【0026】
<ニ>各ブロック体の貫通孔内に固結材を注入して各ブロック体を主鉄筋と一体化した柱状物が得られる。
この柱状物はコンクリートを一体打設したものと同等の性能を確保でき、しかもPC構造と比較して経済的である。
【図面の簡単な説明】
【図1】本発明に係る橋脚の縦断面図
【図2】ブロック体の積み上げ工程の説明図
【図3】ブロック体の圧着工程の説明図
【図4】供試体の曲げ試験の説明図
【図5】供試体の曲げ試験結果の説明図
[0001]
[Industrial applications]
The present invention relates to a method for constructing pillars such as piers and pillars of a rigid-frame viaduct.
[0002]
[Prior art]
Bridge piers such as railway viaducts and bridges are constructed by so-called cast-in-place using formwork, but because it takes a long construction time and requires a lot of support and formwork, and requires a lot of labor, There is a need for a proposal for a technology that can be used in place of on-site hitting.
As an improvement technique, for example, a method of introducing a prestress into the whole after stacking blocks divided into a plurality of piers, or applying a precast cast method used in the construction field to a pier and manufacturing it at a factory etc. A method has been proposed to transport the completed piers and install them on the site.
[0003]
[Problems to be solved by the invention]
The above-mentioned pier construction technology has the following problems.
[0004]
<B> Since the direction of load acting on the pier during an earthquake is not constant, it is necessary to design the pier with high strength to withstand the sum of the compressive stress due to prestress and the compressive stress due to load. Although the energy absorption rate is low, the economic burden is large.
[0005]
<B> If the blocks of the pier are stacked while joining a plurality of PC steel materials, the joining process of each PC steel material is troublesome.
[0006]
<C> In the method of installing a pier that has been manufactured in advance, since the column section of the pier is generally large, large heavy equipment is required for transportation and installation, and there is room for improvement in terms of workability and safety.
[0007]
[Object of the present invention]
The present invention has been made in order to solve the above problems, and an object of the present invention is to provide a method for constructing a columnar material having excellent workability and economy.
[0008]
[Means for solving the problem]
According to the present invention, a block having a columnar cross section is stacked with an adhesive layer interposed therebetween, and a main reinforcing bar is continuously inserted between the blocks, and a solidifying material is injected between the block and the main reinforcing bar. This is a method of constructing a columnar object, in which a columnar object made of reinforced concrete is constructed.
[0009]
Embodiment 1
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0010]
<I> Planting process of main rebar
In FIG. 2, reference numeral 1 denotes a concrete foundation on which a deformed main reinforcing bar 2 is planted at a predetermined interval.
The main reinforcing bar 2 is to be planted at the time of constructing the concrete foundation 1 or by drilling or the like after the construction, and the main reinforcing bar 2 has a length corresponding to the height of the pier to be constructed, or A divided body having a length equal to or greater than the height of a plurality of block bodies to be described later may be extended using welding, a connector, or the like.
[0012]
<B> Block stacking process (Fig. 2)
[0013]
Next, a block 3a manufactured in advance at a factory or the like is inserted into the main reinforcing bar 2 in a hierarchically cut shape of the pier, and is mounted on the concrete foundation 1.
The block body 3a is a reinforced concrete divided body formed according to the cross-sectional shape of the pier. The block body 3a has a plurality of through holes 31 pierced at the insertion position of the main reinforcing bar 3, and a corrugated sheath is provided in each through hole 31. 32 are integrally fixed.
The height (weight) of the block body 3a is determined in consideration of transportability and handleability.
If the inner peripheral surface of the through hole 31 is formed to have a different diameter or irregularities, the sheath 32 may be omitted.
Next, after the adhesive layer 4 is formed on the upper surface of the block 3a, a separate block 3b is mounted on the upper surface of the block 3a.
At this time, the main reinforcing bar 2 projecting from the lower block 3a is inserted into the through-hole 31 to mount the block 3b.
A commercially available adhesive having an adhesive strength greater than the adhesive strength of concrete can be used for the adhesive layer 4.
Hereinafter, similarly, the steps of forming the adhesive layer 4 on the upper surface of the block body 3b and the step of mounting the block body 3n by penetrating the main reinforcing bar 2 and mounting the same are repeated to a predetermined height.
[0014]
<C> Step of crimping the block (Fig. 3)
[0015]
A nut 6 is screwed onto the main reinforcing bar 2 projecting from the uppermost block body 3x via a seat plate 5, and the blocks 3a, 3b, 3n... 3x are simultaneously tightened, and the respective blocks 3a, 3b are tightened. , 3n... 3x are more firmly pressed and bonded.
When the adhesive layer 4 has hardened, the nut 6 is removed, and the crimping force introduced between the blocks 3a, 3b, 3n... 3x is released.
The crimping means for the blocks 3a, 3b, 3n... 3x may use the own weight of the blocks 3a, 3b, 3n.
The step of pressing the block body is not essential and may be omitted in some cases.
[0016]
<D> Injection of consolidated material (Fig. 1)
[0017]
Utilizing the through holes 31 of the lowermost block 3a, a solidifying material 7 such as mortar or concrete is injected into a sheath 32 arranged continuously, and the respective blocks 3a, 3b, 3n... 3x is integrated to obtain a reinforced concrete pier 3.
The adhesive layer 4 serves to close the joint of each block constituting the bridge pier, prevent rust prevention of the main reinforcing bar 2 due to water infiltration, and also to avoid the occurrence of stress concentration at the joint of each block.
[0018]
<E> Consideration on the performance of piers
The performance of the pier joined in the above process will be examined.
FIG. 4A shows a test piece of the pier 3 manufactured by joining the two block bodies 3a and 3b in the above-described process.
A pier having the same dimensions as the specimen A was integrally cast to produce a reinforced concrete specimen B (not shown), and a bending test was performed on each of the specimens A and B under the same conditions as shown. FIG. 5 shows the test results.
According to FIG. 5, the bending characteristics of the specimen A in which the precast block bodies 3a and 3b are joined are almost the same as those of the specimen B manufactured by casting concrete integrally, and there is no significant difference in performance. Was proved.
[0020]
Embodiment 2
Recesses and protrusions having irregular shapes may be formed on the upper and lower surfaces of the block, and the blocks may be stacked by fitting the recesses and protrusions.
According to this embodiment, it is possible to obtain an advantage that the shear resistance of each block body is increased by the fitting of the concave portion and the convex portion, and the bonding area of each block body is increased, so that a strong pressure bonding can be achieved.
[0021]
Embodiment 3
The main reinforcing bar 2 may be set after each block is stacked, or the step of injecting the solidifying material 7 may be performed in parallel with the operation of stacking each block.
[0022]
【The invention's effect】
Since the present invention has been described above, the following effects can be obtained.
[0023]
<B> Since a block body, which is a divided body of columnar objects, is used, a large heavy machine is not required for construction.
In particular, it can be easily constructed even if the columnar object has a large cross section.
[0024]
<B> Since the main rebar penetrates the block body and plays the role of a pillar, it does not require support such as stay wires.
[0025]
<C> By interposing an adhesive layer having an adhesive strength greater than the adhesive strength of concrete between the block bodies, it is possible to effectively prevent cracks from occurring between the joints, and to prevent the main reinforcing steel from being flooded from the joints. Corrosion can also be prevented.
[0026]
<D> A columnar material in which each block is integrated with the main reinforcing bar by injecting a consolidating material into the through hole of each block is obtained.
This columnar structure can ensure the same performance as that of concrete integrally cast, and is more economical than the PC structure.
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional view of a pier according to the present invention. FIG. 2 is an explanatory view of a step of stacking block bodies. FIG. 3 is an explanatory view of a crimping step of a block body. FIG. 4 is an explanatory view of a bending test of a specimen. FIG. 5 is an explanatory diagram of a bending test result of a specimen.

Claims (3)

柱状物の断面形を呈するブロック体を接着層を介在させながら積み上げると共に、主鉄筋を前記ブロック体間に連続して貫挿し、
前記ブロック体間を締め付けて圧着した後に、
最下部のブロック体から前記ブロック体と前記主鉄筋の間に固結材を注入して鉄筋コンクリート製の柱状物を施工する、
柱状物の施工方法。
While stacking the block body having the cross-sectional shape of the columnar object with the adhesive layer interposed, the main reinforcing bar is continuously inserted between the block bodies,
After tightening and crimping between the block bodies,
Constructing a reinforced concrete column by injecting a binder between the block body and the main reinforcing bar from the lowermost block body,
Construction method of pillars.
柱状物の断面形を呈するブロック体を接着層を介在させながら積み上げると共に、主鉄筋を前記ブロック体間に連続して貫挿し、
前記ブロック体間を締め付けて圧着した後に、導入した圧着力を解除し、
前記ブロック体と前記主鉄筋の間に固結材を注入して鉄筋コンクリート製の柱状物を施工する、
柱状物の施工方法。
While stacking the block body having the cross-sectional shape of the columnar object with the adhesive layer interposed, the main reinforcing bar is continuously inserted between the block bodies,
After tightening and crimping between the block bodies, the introduced crimping force is released,
Constructing a reinforced concrete column by injecting a solidifying material between the block body and the main rebar,
Construction method of pillars.
請求項に記載した柱状物の施工方法において、
前記固結材を最下部のブロック体から注入することを特徴とする、
柱状物の施工方法。
In the method for constructing a columnar object according to claim 2 ,
Injecting the consolidated material from the lowermost block body,
Construction method of pillars.
JP14837893A 1993-05-28 1993-05-28 Construction method of pillars Expired - Fee Related JP3554937B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14837893A JP3554937B2 (en) 1993-05-28 1993-05-28 Construction method of pillars

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14837893A JP3554937B2 (en) 1993-05-28 1993-05-28 Construction method of pillars

Publications (2)

Publication Number Publication Date
JPH06336763A JPH06336763A (en) 1994-12-06
JP3554937B2 true JP3554937B2 (en) 2004-08-18

Family

ID=15451428

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14837893A Expired - Fee Related JP3554937B2 (en) 1993-05-28 1993-05-28 Construction method of pillars

Country Status (1)

Country Link
JP (1) JP3554937B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110644676A (en) * 2019-10-17 2020-01-03 武汉市盘龙明达建筑有限公司 Synchronous pouring and construction method for preset isolation layer of concrete constructional column

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110644676A (en) * 2019-10-17 2020-01-03 武汉市盘龙明达建筑有限公司 Synchronous pouring and construction method for preset isolation layer of concrete constructional column

Also Published As

Publication number Publication date
JPH06336763A (en) 1994-12-06

Similar Documents

Publication Publication Date Title
JP4992042B2 (en) Precast horizontal beam and pier using it
CN102203346B (en) Construction method of steel composite girder bridge
CN110541354B (en) Single-section prefabricated anti-seismic pier and construction method thereof
CN211113140U (en) Equal cast-in-place assembly type hollow pier system
JPH08333714A (en) Constructing method of columnar structure used with hybrid prefabricated segments
KR100865133B1 (en) A fixing device, a pre-fabricating forms for concrete-structure and the construction method thereof
JP2927402B2 (en) Column-beam joint structure of concrete building
JP3554937B2 (en) Construction method of pillars
JPH05340031A (en) Prestressed concrete girder and its manufacture
JP2978903B1 (en) Viaduct
JP3772247B2 (en) Seismic reinforcement method for bending of existing large beams
JP5439016B2 (en) Buried formwork
JPH0520817Y2 (en)
JPH0475322B2 (en)
JP2831934B2 (en) How to build substructure
JPS5853286Y2 (en) Composite girder with PC precast concrete blocks in the tension section
Tawadrous Design of shear pocket connections in full-depth precast concrete bridge deck systems
JP3948809B2 (en) Joining structure and joining method between concrete member and steel pipe member, and concrete / steel composite truss bridge
JP4045502B2 (en) Structure
JP3072604B2 (en) Precast reinforced concrete beam and its joining method
JP3847758B2 (en) Repair structure of PC floor slab bridge
JP3314357B2 (en) Crimping method of precast concrete structure
CN114352052B (en) Method for reinforcing concrete frame node
JPH0270850A (en) Pc coupled beam and execution of construction using same
JPH0673203U (en) Beam-column joint structure

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040420

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040426

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090521

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100521

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110521

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120521

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120521

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130521

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees