Nursery facilities

Info

Publication number
JP3491490B2
JP3491490B2 JP08461197A JP8461197A JP3491490B2 JP 3491490 B2 JP3491490 B2 JP 3491490B2 JP 08461197 A JP08461197 A JP 08461197A JP 8461197 A JP8461197 A JP 8461197A JP 3491490 B2 JP3491490 B2 JP 3491490B2
Authority
JP
Japan
Prior art keywords
seedling box
pallet
seedling
stacked
stacking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP08461197A
Other languages
Japanese (ja)
Other versions
JPH10248390A (en
Inventor
博一 牟田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Iseki and Co Ltd
Original Assignee
Iseki and Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Iseki and Co Ltd filed Critical Iseki and Co Ltd
Priority to JP08461197A priority Critical patent/JP3491490B2/en
Publication of JPH10248390A publication Critical patent/JPH10248390A/en
Application granted granted Critical
Publication of JP3491490B2 publication Critical patent/JP3491490B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/10Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
    • Y02A40/25Greenhouse technology, e.g. cooling systems therefor

Landscapes

  • Greenhouses (AREA)
  • Cultivation Receptacles Or Flower-Pots, Or Pots For Seedlings (AREA)

Description

【発明の詳細な説明】 【0001】 【発明の属する技術分野】本発明は、苗移植機に使用す
る苗を育成する育苗施設に関する。 【0002】 【従来の技術】水稲栽培等において苗移植機に使用する
苗を育成するための育苗施設では、種籾を播種した苗箱
を苗箱段積装置によって一定数づつ段積み状に積み重
ね、その段積み状の苗箱を温度・湿度・明度等を管理し
た発芽室内で適当日数保管して種籾を発芽させ、種籾が
発芽した後、段積み状の苗箱を発芽室から出し、各苗箱
を苗箱積替装置によって棚状の緑化台車に積み替え、一
定大きさの苗になるまで育成するようにしている。 【0003】一般的に上記育苗施設では、播種された苗
箱を苗箱段積装置によってパレットの上に段積み状に積
み重ね、そのパレットに載った段積み状の苗箱をフォー
クリフト等を用いて発芽室に搬入及び発芽室から搬出す
ると共に、苗箱積替装置によって段積み状の苗箱が緑化
台車に積み替えられた後の空のパレットもフォークリフ
ト等を用いて苗箱段積装置へ戻していた。 【0004】 【発明が解決しようとする課題】現在、育苗施設の作業
能率向上を図るために、苗箱の発芽室への搬入及び発芽
室からの搬出を自動化する技術の開発が進められている
が、苗箱積替装置によって段積み状の苗箱が緑化台車に
積み替えられた後の空のパレットをいかにして能率よく
苗箱段積装置へ戻すかという点が課題となっている。 【0005】 【課題を解決するための手段】上記課題を解決するため
に本発明は次のように構成した。すなわち、本発明にか
かる育苗施設は、播種された苗箱を苗箱段積装置によっ
てパレットの上に段積み状に積み重ね、当該段積み状の
苗箱を発芽室内へ搬入して苗箱の種子を発芽させ、種子
が発芽した後、パレットに載せた段積み状の苗箱を発芽
室から搬出し、それを苗箱積替装置によって緑化台車に
積み替えるようにした育苗施設であって、前記苗箱積替
装置によって段積み状の苗箱が緑化台車に積み替えられ
た後の空のパレットを複数枚づつ段積み状に積み重ねる
パレット段積装置と、該パレット段積装置によって段積
み状に積み重ねられた複数枚のパレットを前記苗箱段積
装置の近傍へ搬送するパレット搬送装置と、該パレット
搬送装置によって前記苗箱段積装置の近傍に搬送された
段積み状の複数枚のパレットを前記苗箱段積装置に1枚
づつ供給するパレット供給装置とを具備することを特徴
としている。 【0006】 【発明の実施の形態】以下、図面に表された育苗施設に
基づいて、本発明を具体的に説明する。図1は育苗施設
の1階の平面図、図2はその中2階の平面図、図3は作
業の流れを示す側面図、図4乃至図6は要部の構造を示
す図である。 【0007】この育苗施設は2本の播種ラインを備え、
苗箱置場となっている中2階に保管されている苗箱C,
…が、苗箱コンベヤ1,1によって苗箱供給装置2,2
まで運ばれ、該苗箱供給装置によって、1階に設置した
2基の播種機3,3に苗箱が1個づつ順次供給される。 【0008】播種機3は、播種コンベヤ5で苗箱Cを一
定方向に搬送しつつ、その搬送中の苗箱に床土供給装置
6にて床土を入れて鎮圧・均平し、その床土の上に播種
装置7にて種籾を播種し、その上から覆土供給装置8に
て覆土を入れ、そして最後に灌水を施す構成となってい
る。なお、床土タンク6a及び覆土タンク8aの土補給
口は中2階に設置されており、1階に設置した土ホッパ
9に投入される土が、土エレベータ9aによって中2階
へ上げられ、そこから正逆回転可能な土コンベヤ9bに
よって床土タンク6a及び覆土タンク8aに補給される
ようになっている。また、播種装置7で播種される種籾
は、水を張った浸種槽11に浸した後、催芽室12で催
芽処理したものが使用される。13は浸種及び催芽処理
のために種籾を容れるコンテナ、13aはコンテナ13
を浸種槽11に没入させながら移動させる浸種リフト装
置、13bはコンテナ13を運搬するコンテナ台車、1
4は浸種及び催芽処理後の種籾を播種装置7の播種タン
ク7aに投入する種籾供給リフトである。 【0009】播種された苗箱Cは、段積装置16によっ
て所定個数(30個程度)づつパレットPの上に段積み
状に積み重ねられる。なお、パレットPには、上記段積
み状の苗箱群(以下、「苗箱段積体」とする)が前後に
2列、左右に3列づつ載置される。パレットPに載せら
れた苗箱段積体は、後記苗箱搬入・搬出装置23によっ
て発芽室17,…に搬入、及び発芽室17,…から搬出
される。 【0010】発芽室17は、搬入口17aと搬出口17
bを結ぶ通路17bの両側に、パレットごと苗箱を収容
する苗箱収容部18a,…が上下に複数段、前後に複数
列(図示例では上下4段、前後9列)づつ形成された架
台18,18が設けられている。苗箱収容部18aは、
苗箱段積体を載せたパレットPの前後両端部を前後一対
の支持部材18b,18bによって支持するようになっ
ている。 【0011】架台18の最下段の苗箱収容部18aと発
芽室17の床面との間のスペースには温風ダクト19が
配設されており、発芽室17の外部に設けた暖房機20
から供給される温風がこの温風ダクト19から吹き出さ
れる。また、発芽室17の天井部には吸気ダクト21が
配設されており、発芽室内の空気がこの吸気ダクト21
を通って暖房機20に戻される。このように、発芽室内
の空気を循環させ、温風が発芽室内を下から上へ通り抜
けるようにすることにより、発芽室内を均一に暖房する
ことができる。パレットPに載置されている各苗箱段積
体は相互間に隙間が設けられているので、温風が各苗箱
の周囲によく行きわたり、各苗箱が効果的に暖められ
る。 【0012】なお、温風ダクト19の代わりに温湯パイ
プ、蒸気管等の他の加温設備を設けてもよく、また吸気
ダクト21を配設せず、攪拌機等で発芽室内の空気を攪
拌するようにしてもよい。 【0013】図の育苗施設は、このような発芽室が左右
並列に3室設けられている。水稲の場合、発芽に要する
日数は通常3日であるので、毎日同じ作業ペースで播種
処理を行うためには、1日当たり発芽室1室分づつ苗箱
に播種処理を行えばよい。 【0014】苗箱搬入・搬出装置23は、パレットPに
載った苗箱段積体を苗箱段積装置16,16から所定位
置まで搬送する段積コンベヤ24,24と、該段積コン
ベヤによって搬送されてきた同苗箱段積体を引き継ぎ、
それを発芽室17の搬入口近傍まで搬送する搬入ステー
ションコンベヤ25と、該搬入ステーションコンベヤに
よって搬送されてきた同苗箱段積体を受け取り、それを
架台18の各苗箱収容部18aへ移載すると共に、各苗
箱収容部18aの同苗箱段積体を発芽室17の搬出口近
傍へ移載する移載機26と、該移載機によって発芽室1
7の搬出口近傍へ移載された同苗箱段積体を受け取り、
それを所定位置まで搬送する搬出ステーションコンベヤ
27と、該搬出ステーションコンベヤによって所定位置
まで搬送された同苗箱段積体を引き継ぎ、それを後記積
替装置40,40へ搬送する積替コンベヤ28,28と
で構成されている。 【0015】移載機26は、前記支持部材18b,18
bの間を通過可能な前後長を有するパレット台30を備
え、そのパレット台30が昇降ベ一ス31に左右にスラ
イド可能に取り付けられ、さらに昇降ベ一ス31が昇降
ガイド枠32に昇降可能に取り付けられている。昇降ガ
イド枠32は、発芽室17の通路17cとその搬入口側
延長線上及び搬出口側延長線上にある上下の前後移動レ
ール33,34に沿って前後移動可能となっている。ま
た、前後移動レール33,34の搬入口側延長部33
a,34aと搬入ステーションコンベヤ25は、上下の
搬入口側左右移動レール35,36,36に沿って左
移動可能で、各発芽室17,…の搬入ステーションに停
止させられるようになっている。同様に、前後移動レー
ル33,34の搬出口側延長部33b,34bと搬出ス
テーションコンベヤ27は、上下の搬出口側左右移動レ
ール37,38,38に沿って左右移動可能で、各発芽
室17,…の搬出ステーションに停止させられるように
なっている。 【0016】搬入ステーションコンベヤ25の終端部及
び搬出ステーションコンベヤ27の始端部には、少なく
ともパレット台30の厚み分以上搬送面よりも下降する
ように昇降可能な昇降ローラコンベヤ25a,27aが
設けられている。この昇降ローラコンベヤ25a,27
aの前後長は、パレットPの前後長よりも短く、かつパ
レット台30の前後長よりも長くしてある。 【0017】苗箱搬入作業を行う場合は、苗箱を搬入し
ようとする発芽室17の搬入ステーションへ前後移動レ
ールの搬入口側延長部33a,34aと搬入ステーショ
ンコンベヤ25を移動させる。苗箱搬入作業開始時、パ
レット台30が昇降ベース31の左右中心にあり、昇降
ベース31が昇降ガイド枠32の最下位にあり、昇降ガ
イド枠32が前後移動レールの搬入口側延長部33a,
34aに位置する状態で移載機24が待機している。 【0018】その状態で、搬入ステーションコンベヤ2
5の終端部にパレットPに載った苗箱段積体が搬送され
てくると、昇降ローラコンベヤ25aが下降し、次い
で、パレット台30が搬入ステーションコンベヤ25側
へスライドして下降位置にある昇降ローラコンベヤ25
aの上側にくる。そして、パレット台30が搬入ステー
ションコンベヤ25の搬送面よりも上昇することによ
り、該搬入ステーションコンベヤ上の同苗箱段積体をパ
レット台30が保持する。同苗箱段積体を保持したパレ
ット台30は、昇降ベース31の左右中心まで戻る。 【0019】次いで、昇降ガイド枠32が前後移動レー
ル33,34に沿って移動すると共に、昇降ベース31
が上昇し、パレット台30が所望の苗箱収容部18aの
横へ到達する。この時、パレット台30の上面は支持部
材18b,18bの上面よりも若干上位となっている。
そして、パレット台30が当該苗箱収容部18aの側へ
スライドし、さらにパレット台30の上面が支持部材1
8b,18bの上面よりも下位となる位置まで昇降ベー
ス31が下降することにより、パレット台30が保持し
ていた同苗箱段積体を苗箱収容部18aに移載する。 【0020】苗箱段積体を移載した移載機26は元の待
機状態に戻る。そして、次に搬入ステーションコンベヤ
25の終端部に搬送されてくる同苗箱段積体を前回と異
なる苗箱収容部18aに移載する。これを繰り返すこと
により、各苗箱収容部18a,…に同苗箱段積体を移載
する。 【0021】苗箱搬出作業を行う場合は、苗箱を搬出し
ようとする発芽室17の搬出ステーションへ、前後移動
レールの搬出口側延長部33b,34bと搬出ステーシ
ョンコンベヤ27を移動させる。作業を開始すると、パ
レット台30が所望の苗箱収容部18aの横へ移動す
る。この時、パレット台30の上面は支持部材18b,
18bの上面よりも若干下位となっている。そして、パ
レット台30が当該苗箱収容部18aの下側へスライド
し、さらにパレット台30の上面が支持部材18b,1
8bの上面よりも上位となる位置まで昇降ベース31が
上昇することにより、苗箱収容枠18aに収容されてい
るパレットPの載った苗箱段積体をパレット台30が保
持する。同苗箱段積体を保持したパレット台30は、昇
降ベース31の左右中心まで戻る。 【0022】次いで、昇降ベース31が最下位近傍へ下
降すると共に、昇降ガイド枠32が前後移動レールの搬
出口側延長部33b,34bまで移動する。すると、搬
出ステーションコンベヤ27の昇降ローラコンベヤ27
aが下降し、その下降した昇降ローラコンベヤ27aの
上側へパレット台30がスライドする。さらに、パレッ
ト台30が搬出ステーションコンベヤ27の搬送面より
も下降することにより、パレット台30が保持していた
同苗箱段積体を搬出ステーションコンベヤ27の上に載
置する。パレット台30が昇降ベース31の左右中心ま
で戻り、次の同苗箱段積体の搬出作業に移る。 【0023】搬出ステーションコンベヤ27の上に同苗
箱段積体が載置されると、昇降ローラコンベヤ25aが
元の高さまで上昇する。そして、搬出ステーションコン
ベヤ27と積替コンベヤ28が作動して同苗箱段積体を
苗箱積替装置40へ搬送する。 【0024】苗箱積替装置40へ搬出された苗箱段積体
の各苗箱は、苗箱積替装置40によって棚状の緑化台車
41に積み替えられる。そして、苗箱を収容した緑化台
車41が磁気誘導式の案内レール41aに沿って自動走
行する緑化台車搬送車42によって緑化室43に搬入さ
れ、さらに緑化室43内で苗が所定の大きさまで成育し
たなら、緑化台車搬送車42によって緑化台車41を緑
化室43から搬出し、苗箱Cを出荷する。 【0025】一方、苗箱積替装置40,40によって苗
箱段積体が緑化台車41に積み替えられ空になったパレ
ットPは、パレット段積装置50,50によって段積み
状に積み重ねられ、そして、その段積み状に積み重ねら
れた複数枚のパレットP,…が、リフト式のパレット搬
送装置51によって育苗施設1階の上部空間を搬送して
苗箱段積装置16,16の近傍に戻され、パレット供給
装置52,52によって苗箱段積装置16,16に1枚
づつパレットが供給される。 【0026】このように、パレットPを複数枚づつまと
めて苗箱積替装置40から苗箱段積装置16へ搬送する
ことにより、1ラインのパレット搬送装置51で、複数
台の苗箱積替装置40(図示例では2台)から複数台の
苗箱段積装置16(図示例では2台)へパレットを戻す
ことが可能で、パレット搬送のためのスペースを小さく
することができる。また、パレット搬送装置51は、パ
レットが育苗施設1階の上部空間を搬送されるようにな
っているので、育苗施設内を通行する作業者等の邪魔に
ならない。 【0027】 【発明の効果】以上説明した如く、本発明にかかる育苗
施設は、苗箱積替装置から苗箱段積装置へ空のパレット
を戻す作業を自動的に行うので作業効率がよく、しかも
苗箱積替装置から苗箱段積装置へ空のパレットを複数枚
づつまとめて搬送するので、1ラインのパレット搬送装
置で複数台の苗箱積替装置から複数台の苗箱段積装置へ
パレットを戻すことが可能で、パレット搬送のためのス
ペースを小さくすることができるようになった。
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a seedling raising facility for growing seedlings for use in a seedling transplanter. 2. Description of the Related Art In a seedling raising facility for growing seedlings used for a seedling transplanter in paddy rice cultivation or the like, a certain number of seedling boxes in which seeds are sown are stacked in a stack by a seedling box stacking device. The stacked seedling boxes are stored for a suitable number of days in a germination room where the temperature, humidity, lightness, etc. are controlled, and the seeds are germinated.After the seeds germinate, the stacked seedling boxes are taken out of the germination room, and each seedling is removed. The boxes are transferred to a shelf-like greening cart by a seedling box transfer device, and the seedlings are grown until they reach a certain size. In general, in the above-mentioned seedling raising facilities, seeded seedling boxes are stacked in a stack on a pallet by a seedling box stacking device, and the stacked seedling boxes placed on the pallet are moved using a forklift or the like. The empty pallets after the stacking seedling boxes are transferred to the greening cart by the seedling box transfer device are also returned to the seedling box stacking device using a forklift or the like, while being carried into and out of the germination room. Was. [0004] At present, in order to improve the working efficiency of the seedling raising facility, a technique for automatically carrying a seedling box into and out of the germination chamber is being developed. However, there is a problem how to efficiently return an empty pallet after the stacked seedling boxes are transferred to the greening cart by the seedling box transfer device to the seedling box stacking device. [0005] In order to solve the above problems, the present invention is configured as follows. That is, the seedling raising facility according to the present invention stacks seeded seedling boxes in a stack on a pallet by a seedling box stacking device, loads the stacked seedling boxes into a germination chamber, and seeds the seedling boxes. Germinating, after the seeds germinate, take out the stepped seedling boxes placed on the pallet from the germination room, it is a nursery facility that is re-transferred to a greening cart by a seedling box transfer device, A pallet stacking device for stacking a plurality of empty pallets after the stacked seedling boxes are transferred to the greening cart by the seedling box transfer device, and stacking in a stack by the pallet stacking device. A plurality of pallets transferred to the vicinity of the seedling box stacking device, and a plurality of stacked pallets transferred to the vicinity of the seedling box stacking device by the pallet transfer device. For seedling box stacking equipment It is characterized by comprising a single one by supplying pallet feeder. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the present invention will be specifically described based on a seedling raising facility shown in the drawings. FIG. 1 is a plan view of the first floor of a nursery facility, FIG. 2 is a plan view of a mezzanine floor, FIG. 3 is a side view showing a work flow, and FIGS. [0007] This nursery facility has two sowing lines,
Seedling box C stored on the mezzanine floor, which is the seedling box storage area,
, But the seedling box conveyors 1, 1 use the seedling box supply devices 2, 2.
The seedling boxes are supplied one by one to the two seeding machines 3 and 3 installed on the first floor by the seedling box supply device. The seeding machine 3 conveys the seedling boxes C in a certain direction by the seeding conveyor 5, puts the bed soil into the seedling boxes being conveyed by the bed soil supply device 6, flattens and flattens the bed. Seed paddy is sown on the soil by a seeding device 7, soil is put on the soil by a soil covering supply device 8, and finally, irrigation is performed. The soil supply ports of the floor soil tank 6a and the cover soil tank 8a are installed on the mezzanine floor, and the soil put into the earth hopper 9 installed on the first floor is raised to the mezzanine floor by the earth elevator 9a. From there, the floor soil tank 6a and the cover soil tank 8a are replenished by a soil conveyor 9b which can be rotated forward and backward. The seed rice sowed by the sowing apparatus 7 is immersed in a soaking tank 11 filled with water and then germinated in a germination chamber 12. 13 is a container for storing seed rice for soaking and germination, and 13a is a container 13
Immersion lift device for moving the container 13 while immersing it in the immersion tank 11, 13b is a container truck for transporting the container 13, 1
Reference numeral 4 denotes a seed pad supply lift for putting the seed paddies after the seeding and germination treatments into the seeding tank 7a of the seeding apparatus 7. The seedling boxes C sowed are stacked in a predetermined number (about 30 pieces) on the pallet P by the stacking device 16 in a stacked manner. The tiered seedling box group (hereinafter, referred to as a “seedling box stacked body”) is placed on the pallet P in two rows in front and back and three rows in left and right. The seedling box stacks placed on the pallet P are carried into and out of the germination chambers 17, by the seedling box carrying-in / out device 23 described later. The germination chamber 17 has a carry-in port 17a and a carry-out port 17a.
, on both sides of the passage 17b connecting the b., a plurality of seedling box storage portions 18a,. 18, 18 are provided. The seedling box storage section 18a
Both front and rear ends of the pallet P on which the seedling box stack is placed are supported by a pair of front and rear support members 18b, 18b. A warm air duct 19 is provided in a space between the seedling box housing portion 18a at the bottom of the gantry 18 and the floor of the germination chamber 17, and a heater 20 provided outside the germination chamber 17 is provided.
Is supplied from the hot air duct 19. An air intake duct 21 is provided at the ceiling of the germination chamber 17, and air in the germination chamber is
Through the heater 20. In this way, by circulating the air in the germination chamber and allowing the warm air to pass through the germination chamber from below to above, the germination chamber can be uniformly heated. Since there is a gap between each of the seedling box stacked bodies placed on the pallet P, warm air can well flow around each seedling box, and each seedling box can be effectively warmed. It is to be noted that other heating equipment such as a hot water pipe and a steam pipe may be provided in place of the hot air duct 19, and the air in the germination chamber is stirred by a stirrer or the like without disposing the intake duct 21. You may do so. In the nursery facility shown in the figure, three such germination rooms are provided in parallel on the left and right sides. In the case of paddy rice, the number of days required for germination is usually three days. Therefore, in order to perform the sowing process at the same work pace every day, the seeding process may be performed in one seedling box per germination room per day. The seedling box loading / unloading device 23 includes a stacking conveyor 24, 24 for transferring the seedling box stacks placed on the pallet P from the seedling box stacking devices 16, 16 to a predetermined position, and the stacking conveyor. Take over the same seedling box stacked body that has been transported,
The loading station conveyor 25 for transporting the seedling box to the vicinity of the loading port of the germination chamber 17 and the same seedling box stack transported by the loading station conveyor are received and transferred to the respective seedling box storage portions 18 a of the gantry 18. At the same time, a transfer machine 26 for transferring the same seedling box stack of each seedling box storage section 18a to the vicinity of the carry-out exit of the germination chamber 17, and the germination chamber 1
Receiving the same seedling box stack transferred near the exit of 7,
An unloading station conveyor 27 that transports the same to a predetermined position, and a transfer conveyor 28 that transfers the same seedling box stacked products that have been transported to the predetermined position by the unloading station conveyor, and transfers the stacked products to the reloading devices 40 and 40 described below. 28. The transfer machine 26 is provided with the support members 18b, 18
b, a pallet table 30 having a front-rear length capable of passing between spaces b. The pallet table 30 is slidably mounted on a lifting base 31 left and right, and the lifting base 31 can be raised and lowered on a lifting guide frame 32. Attached to. The elevating guide frame 32 can be moved back and forth along the up-and-down moving rails 33 and 34 on the passage 17c of the germination chamber 17 and on the extension line on the carry-in side and on the carry-out side. In addition, the carry-in side extension portion 33 of the front and rear moving rails 33 and 34.
a, 34a and input station conveyor 25, left right movable and along the top and bottom of the entrance-side horizontal movement rails 35,36,36, each germinating chambers 17, ... are adapted to be stopped in the input station of . Similarly, outlet port side extension portion 33b of the front and rear movable rails 33 and 34, 34b and output station conveyor 27, it left right movable and along the top and bottom of the outlet port side horizontal movement rails 37,38,38, each germinating chambers 17, ... are stopped. At the end of the carry-in station conveyor 25 and at the start of the carry-out station conveyor 27, elevating roller conveyors 25a and 27a are provided, which can move up and down at least by the thickness of the pallet table 30 from the conveying surface. I have. The lifting roller conveyors 25a, 27
The front-rear length of a is shorter than the front-rear length of the pallet P and is longer than the front-rear length of the pallet table 30. When carrying out the seedling box carrying-in operation, the carrying-in station conveyor 25 is moved to the carrying-in station of the germination room 17 into which the seedling box is to be carried-in. At the start of the seedling box carrying-in operation, the pallet table 30 is located at the left and right centers of the elevating base 31, the elevating base 31 is at the lowest position of the elevating guide frame 32, and the elevating guide frame 32 is located at the carry-in side extension 33 a of the front and rear moving rail.
The transfer machine 24 is on standby in a state where it is located at 34a. In this state, the loading station conveyor 2
When the seedling box stack on the pallet P is conveyed to the end of the pallet 5, the lifting roller conveyor 25a is lowered, and then the pallet table 30 is slid toward the loading station conveyor 25 and moved up and down to the lower position. Roller conveyor 25
Comes above a. Then, as the pallet table 30 is raised above the transport surface of the loading station conveyor 25, the pallet table 30 holds the same seedling box stack on the loading station conveyor. The pallet table 30 holding the seedling box stacked body returns to the left and right centers of the elevating base 31. Next, the elevating guide frame 32 moves along the front and rear moving rails 33 and 34 and the elevating base 31 is moved.
Rises, and the pallet table 30 reaches the side of the desired seedling box housing portion 18a. At this time, the upper surface of the pallet table 30 is slightly higher than the upper surfaces of the support members 18b, 18b.
Then, the pallet table 30 slides toward the seedling box housing portion 18a, and the upper surface of the pallet table 30 is
The raising / lowering base 31 is lowered to a position lower than the upper surfaces of 8b and 18b, so that the same seedling box stacked body held by the pallet table 30 is transferred to the seedling box housing portion 18a. The transfer machine 26 to which the seedling box stack has been transferred returns to the original standby state. Then, the seedling box stacked body conveyed to the terminal end of the loading station conveyor 25 is transferred to a seedling box storage part 18a different from the previous one. By repeating this, the same seedling box stack is transferred to each seedling box storage section 18a,. When carrying out the seedling box carrying-out operation, the carrying-out side conveyors 27 and the carrying-out side extension portions 33b and 34b of the front and rear moving rails are moved to the carrying-out station of the germination room 17 where the seedling box is to be carried out. When the operation is started, the pallet table 30 moves to the side of the desired seedling box storage section 18a. At this time, the upper surface of the pallet table 30 is
18b is slightly lower than the upper surface. Then, the pallet table 30 slides to the lower side of the seedling box housing portion 18a, and the upper surface of the pallet table 30 further supports the support members 18b, 1
The pallet table 30 holds the seedling box stacked body on which the pallets P are stored in the seedling box storage frame 18a by raising the lifting base 31 to a position higher than the upper surface of 8b. The pallet table 30 holding the seedling box stacked body returns to the left and right centers of the elevating base 31. Next, the lifting base 31 moves down to the lowermost position, and the lifting guide frame 32 moves to the carry-out side extension portions 33b and 34b of the front and rear moving rails. Then, the lifting roller conveyor 27 of the unloading station conveyor 27
a is lowered, and the pallet table 30 slides over the lowered roller conveyor 27a. Further, the pallet table 30 is lowered below the transport surface of the unloading station conveyor 27, so that the seedling box stacked body held by the pallet table 30 is placed on the unloading station conveyor 27. The pallet table 30 returns to the left and right centers of the elevating base 31 and moves on to the next operation of carrying out the same seedling box stack. When the seedling box stack is placed on the carry-out station conveyor 27, the lifting roller conveyor 25a is raised to its original height. Then, the unloading station conveyor 27 and the transfer conveyor 28 operate to transfer the seedling box stack to the seedling box transfer device 40. Each seedling box of the seedling box stacked body carried out to the seedling box transshipment device 40 is transshipped by the seedling box transshipment device 40 to a shelf-shaped greening truck 41. Then, the greening cart 41 containing the seedling boxes is carried into the greening room 43 by the greening cart carrier 42 which automatically travels along the guide rail 41a of the magnetic induction type, and the seedlings grow to a predetermined size in the greening room 43. Then, the greening cart 41 is carried out of the greening room 43 by the greening cart carrier 42, and the seedling box C is shipped. On the other hand, the pallets P which have been emptied after the seedling box stacks have been transferred to the greening truck 41 by the seedling box transfer devices 40, 40 are stacked in a stack by the pallet stacking devices 50, 50. Are transported in the upper space of the first floor of the seedling raising facility by the lift-type pallet transport device 51, and returned to the vicinity of the seedling box stacking devices 16, 16. The pallets are supplied one by one to the seedling box stacking devices 16, 16 by the pallet supply devices 52, 52. As described above, a plurality of seedling boxes are transferred by the one-line pallet transfer device 51 by transferring a plurality of pallets P one by one from the seedling box transfer device 40 to the seedling box stacking device 16. The pallets can be returned from the apparatus 40 (two in the illustrated example) to the plurality of seedling box stacking apparatuses 16 (two in the illustrated example), and the space for pallet transport can be reduced. Further, since the pallet is transported in the upper space on the first floor of the seedling raising facility, the pallet transporting device 51 does not obstruct an operator or the like passing through the seedling raising facility. As described above, the nursery facility according to the present invention automatically returns the empty pallets from the seedling box transshipment device to the seedling box stacking device. Moreover, since a plurality of empty pallets are conveyed collectively from the seedling box reloading device to the seedling box stacking device, a plurality of seedling box reloading devices can be transferred from a plurality of seedling box reloading devices to a plurality of seedling box stacking devices using a one-line pallet transfer device. The pallet can be returned to the pallet, and the space for transporting the pallet can be reduced.

【図面の簡単な説明】 【図1】第一例の育苗施設の1階の平面図である。 【図2】その中2階の平面図である。 【図3】作業の流れを示す側面図である。 【図4】発芽室等の平面図である。 【図5】図4におけるS1−S1断面図である。 【図6】図4におけるS2−S2断面図である。 【符号の説明】 C 苗箱 P パレット 3 播種機 16 段積装置 17 発芽室 23 苗箱搬入・搬出装置 40 積替装置 41 緑化台車 50 パレット段積装置 51 パレット搬送装置 52 パレット供給装置[Brief description of the drawings] FIG. 1 is a plan view of the first floor of a nursery facility of a first example. FIG. 2 is a plan view of the mezzanine floor. FIG. 3 is a side view showing a work flow. FIG. 4 is a plan view of a germination chamber and the like. FIG. 5 is a sectional view taken along line S1-S1 in FIG. FIG. 6 is a sectional view taken along line S2-S2 in FIG. [Explanation of symbols] C Seedling box P pallet 3 Seeding machine 16 Stacking device 17 Germination room 23 Seedling box loading / unloading device 40 Transshipment equipment 41 Greening cart 50 Pallet stacking device 51 Pallet transfer device 52 Pallet supply device

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) A01G 9/00 A01G 9/02 610 A01G 9/14 ──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 7 , DB name) A01G 9/00 A01G 9/02 610 A01G 9/14

Claims (1)

(57)【特許請求の範囲】 【請求項1】 播種された苗箱を苗箱段積装置によって
パレットの上に段積み状に積み重ね、当該段積み状の苗
箱を発芽室内へ搬入して苗箱の種子を発芽させ、種子が
発芽した後、パレットに載せた段積み状の苗箱を発芽室
から搬出し、それを苗箱積替装置によって緑化台車に積
み替えるようにした育苗施設であって、前記苗箱積替装
置によって段積み状の苗箱が緑化台車に積み替えられた
後の空のパレットを複数枚づつ段積み状に積み重ねるパ
レット段積装置と、該パレット段積装置によって段積み
状に積み重ねられた複数枚のパレットを前記苗箱段積装
置の近傍へ搬送するパレット搬送装置と、該パレット搬
送装置によって前記苗箱段積装置の近傍に搬送された段
積み状の複数枚のパレットを前記苗箱段積装置に1枚づ
つ供給するパレット供給装置とを具備することを特徴と
する育苗施設。
(57) [Claims] [Claim 1] The seeded seedling boxes are stacked on a pallet by a seedling box stacking device, and the stacked seedling boxes are carried into a germination chamber. After the seeds in the seedling box are germinated and the seeds germinate, the stacked seedling boxes placed on the pallet are taken out of the germination room and transferred to a greening cart by the seedling box transfer device at a nursery facility. A pallet stacking device for stacking a plurality of empty pallets after the seedling boxes are stacked on the greening cart by the seedling box transfer device; and a pallet stacking device. A pallet transport device that transports a plurality of pallets stacked in a stack to the vicinity of the seedling box stacking device; and a plurality of stacked pallets that are transported to the vicinity of the seedling box stacking device by the pallet transport device. Pallets into the seedling box stacking device Nursery, characterized by comprising a one by supplying pallet feeder.
JP08461197A 1997-03-17 1997-03-17 Nursery facilities Expired - Fee Related JP3491490B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP08461197A JP3491490B2 (en) 1997-03-17 1997-03-17 Nursery facilities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP08461197A JP3491490B2 (en) 1997-03-17 1997-03-17 Nursery facilities

Publications (2)

Publication Number Publication Date
JPH10248390A JPH10248390A (en) 1998-09-22
JP3491490B2 true JP3491490B2 (en) 2004-01-26

Family

ID=13835502

Family Applications (1)

Application Number Title Priority Date Filing Date
JP08461197A Expired - Fee Related JP3491490B2 (en) 1997-03-17 1997-03-17 Nursery facilities

Country Status (1)

Country Link
JP (1) JP3491490B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012120454A (en) * 2010-12-06 2012-06-28 Tsubakimoto Chain Co Plant cultivation device
JP5477427B2 (en) * 2012-07-23 2014-04-23 井関農機株式会社 Nursery facility

Also Published As

Publication number Publication date
JPH10248390A (en) 1998-09-22

Similar Documents

Publication Publication Date Title
JPS61173722A (en) Seedling growing facilities
JP3491490B2 (en) Nursery facilities
JP3564931B2 (en) Nursery facilities
JP3835088B2 (en) Seedling box stacking equipment
JP3521655B2 (en) Nursery facilities
JP3597288B2 (en) Nursery facilities
JPH09308377A (en) Apparatus for growing plant
JP3849327B2 (en) Nursery box transshipment device
JP4212343B2 (en) Mushroom cultivation method and mushroom cultivation equipment
JP4169582B2 (en) Mushroom fruit growing method and mushroom fruit growing facility
JP3511842B2 (en) Nursery facilities
JP4033760B2 (en) Mushroom cultivation method and mushroom cultivation equipment
JP3348337B2 (en) Nursery box
JP3521657B2 (en) Nursery facilities
JP3173165B2 (en) Seeding facility
JP2000044058A (en) Seeding and tiering-up device for raising seedling box
JPS61162119A (en) Seedling growing facilities
JPH03243530A (en) Transportation device for seedling raising box
JP3817956B2 (en) Nursery facility
WO2024138939A1 (en) Automated plant factory assembly line and automated planting method thereof
JP4770068B2 (en) Nursery facility
JPH1154A (en) Vessels-arranging machine
JP2831913B2 (en) Nursery box transfer facility
JP3247667B2 (en) Box arrangement device
JPH0764421B2 (en) Nursery box assembly carrier at nursery facility

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091114

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121114

Year of fee payment: 9