JP3379391B2 - Temporary deadline method and temporary deadline structure - Google Patents

Temporary deadline method and temporary deadline structure

Info

Publication number
JP3379391B2
JP3379391B2 JP17860397A JP17860397A JP3379391B2 JP 3379391 B2 JP3379391 B2 JP 3379391B2 JP 17860397 A JP17860397 A JP 17860397A JP 17860397 A JP17860397 A JP 17860397A JP 3379391 B2 JP3379391 B2 JP 3379391B2
Authority
JP
Japan
Prior art keywords
temporary
precast
precast panel
vertical
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP17860397A
Other languages
Japanese (ja)
Other versions
JPH1121908A (en
Inventor
正三 加藤
憲章 田中
信 森山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP17860397A priority Critical patent/JP3379391B2/en
Publication of JPH1121908A publication Critical patent/JPH1121908A/en
Application granted granted Critical
Publication of JP3379391B2 publication Critical patent/JP3379391B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、仮締切工法および
仮締切構造体に関し、特に、水中構造物の修理,補強な
どの改修を行う際に好適な仮締切工法および仮締切構造
体に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a temporary shutoff method and a temporary shutoff structure, and more particularly to a temporary shutoff method and a temporary shutoff structure suitable for repairing or repairing an underwater structure. is there.

【0002】[0002]

【従来の技術】地震などによる構造物の損傷および崩壊
などの被害は、陸上部の構造物に留まらず、河川や海上
部に構築されている水中構造物、例えば、橋梁基礎や護
岸などにも及んでいる。
2. Description of the Related Art Damage such as damage and collapse of structures due to earthquakes is not limited to structures on land, but also to underwater structures constructed on rivers and sea tops, such as bridge foundations and revetments. It has reached.

【0003】このような水中構造物が被害を受けた場合
にも陸上構造物と同様に、耐震補強対策を施す必要があ
る。河川や海上にある水中構造物に耐震補強を実施する
際には、構造物の周囲から水を排除して、ドライな環境
で作業を行う必要があることから、従来、二重締切工を
用いる工法が一般的に採用されている。
Even when such an underwater structure is damaged, it is necessary to take measures against seismic reinforcement as in the case of a land structure. When performing seismic retrofitting on underwater structures on rivers or the sea, it is necessary to remove water from the surroundings of the structures and work in a dry environment. The construction method is generally adopted.

【0004】この二重締切工法の代表的な施工状態を図
9に示している。同図に示した二重締切工法は、橋脚1
の補強改修工事を行う場合の適用例であり、フーチング
2の外周を取り囲むようにして締切工3が構築される。
FIG. 9 shows a typical construction state of this double cutoff construction method. The double deadline method shown in the figure is used for pier 1
This is an application example in the case of carrying out the reinforcement and repair work of No. 3, and the deadline 3 is constructed so as to surround the outer periphery of the footing 2.

【0005】締切工3は、フーチング2の外周側の水底
地盤中に矢板を打設して形成した内,外壁3a,3b
と、この内,外壁3a,3b間を連結する複数のタイロ
ッド3cとから構成されている。
The cut-off work 3 is formed by placing a sheet pile in the water bottom ground on the outer peripheral side of the footing 2 to form inner and outer walls 3a, 3b.
And a plurality of tie rods 3c connecting the inner and outer walls 3a and 3b.

【0006】この締切工3では、内,外壁3a,3b間
に中詰め土砂4を充填することにより、止水性と安定性
とを確保して、内壁3a内の水を排除することでドライ
状態にし、橋脚1の外周に補強工5を施す改修工事が行
われる。
[0006] In this shut-off work 3, a water filling and a stability are ensured by filling the inside stuffed sand 4 between the inner and outer walls 3a and 3b, and water in the inner wall 3a is removed so as to be in a dry state. Then, the renovation work is performed to apply the reinforcement work 5 to the outer periphery of the pier 1.

【0007】しかしながら、このような従来の二重締切
工法には、以下に説明する技術的な課題があった。
However, such a conventional double deadline construction method has the following technical problems.

【0008】[0008]

【発明が解決しようとする課題】すなわち、前述した二
重締切工法では、矢板の打設,撤去を伴うため、組立,
解体に時間と手間が掛かり、仮設構造物の築造,撤去費
用が全体の工費中に大きな割合を占めるという問題があ
った。
That is, in the above-mentioned double deadline construction method, since the sheet pile is driven in and out, the assembly,
There was a problem that dismantling took time and effort, and construction and removal costs of temporary structures accounted for a large proportion of the total construction cost.

【0009】また、図9に示したように、橋梁上部の桁
下に矢板を打設する際には、クリアランスの関係から長
尺物の施工が困難になるため、短尺物の継ぎ足しとな
り、使用機械の制限も受けるので、より一層施工に時間
がかかるという問題もあった。
Further, as shown in FIG. 9, when a sheet pile is placed under the girder at the upper part of the bridge, it is difficult to construct a long product due to clearance, so that a short product is added to the pile. There is also a problem that construction will take more time because the machine is limited.

【0010】さらに、二重締切工法では、広い面積を長
期間占有することになるので、流水の阻害および水上交
通の妨げになり、通年施工が困難になるという問題もあ
った。
Further, in the double cut-off method, since a large area is occupied for a long period of time, there is a problem that running water is obstructed and water traffic is obstructed, which makes construction difficult all year round.

【0011】さらに、中詰め土砂4を充填すると、砂の
投入,撤去時に水質汚濁問題が発生する恐れがあった。
Further, when the filling sand 4 is filled, there is a possibility that a water pollution problem may occur when the sand is put in and taken out.

【0012】本発明は、このような従来の問題点に鑑み
てなされたものであって、その目的とするところは、組
立,解体が簡単かつ迅速に行えるとともに、水質汚濁の
発生しない仮締切工法および仮締切構造体を提供するこ
とにある。
The present invention has been made in view of such conventional problems, and an object of the present invention is to assemble and disassemble easily and quickly and to prevent temporary pollution by a water supply method. And to provide a temporary deadline structure.

【0013】[0013]

【課題を解決するための手段】上記目的を達成するため
に、本発明は、橋梁基礎などの水中構造物の外周を仮締
切工で囲撓し、前記仮締切工の内部を排水して、前記水
中構造物の修理,補強などの改修を行う仮締切工法にお
いて、前記仮締切工は、前記水中構造物の鉛直および周
方向に沿って分断され、相互に連結可能な複数のプレキ
ャストパネルを備え、前記水中構造物の基礎部分に一端
が定着された複数の定着アンカーを立設し、前記プレキ
ャストパネルを前記水中構造物の改修現場まで運搬した
後に、前記プレキャストパネル間の分断部分および上下
方向の接合部分,前記プレキャストパネルと前記基礎部
分との間にそれぞれシール材を介在させながら、前記定
着アンカーを挿通させて前記基礎部分上に積層連結し、
この状態で、前記定着アンカーにプレストレス力を導入
して、前記基礎部分と積層連結されたプレキャストパネ
ルとを一体化させる工法であって、前記定着アンカーに
プレストレス力を導入する前に、積層連結された前記プ
レキャストパネルと前記水中構造物との間に、伸縮自在
なジャッキからなる支保材を、前記仮締切工の周方向に
沿って複数設置するとともに、最下段の前記プレキャス
トパネルに突設されたストッパーにより、前記プレキャ
ストパネルと前記基礎部分との間に介在させた前記シー
ル材の位置規制をするようにした。このように構成され
た仮締切工法によれば、仮締切工の主要部分となるプレ
キャストパネルは、予め工場生産することができるの
で、高品質なものが得られるとともに、これを水中構造
物の改修現場まで運搬した後に、分断部分および上下方
向の接合部分,プレキャストパネルと基礎部分との間に
それぞれにシール材を介在させながら、基礎部分に立設
された定着アンカーを挿通させて、基礎部分上に積層連
結し、この状態で、定着アンカーにプレストレス力を導
入して、基礎部分と積層連結されたプレキャストパネル
とを一体化させることで構築され、矢板の打設などのよ
うな現場工事が非常に少なくなるので、簡単かつ迅速に
構築することができるとともに、解体もこの手順を逆に
行うので、同様に簡単且つ迅速に行える。また、本発明
の仮締切工法では、前記定着アンカーにプレストレス力
を導入する前に、積層連結された前記プレキャストパネ
ルと前記水中構造物との間に、支保材を設置するので、
プレストレス力を導入した際の、仮締切工の安定性を確
保することができる。この場合、前記支保材は、伸縮自
在なジャッキから構成するので、プレキャストパネルと
水中構造物との間の間隔のバラツキに容易に対応するこ
とができる。さらに、本発明は、橋梁基礎などの水中構
造物の外周を仮締切工で囲撓し、前記仮締切工の内部を
排水して、前記水中構造物の修理,補強などの改修を行
う仮締切構造体において、前記仮締切工は、前記水中構
造物の鉛直および周方向に沿って分断され、前記水中構
造物の基礎部分に立設された定着アンカーに挿通された
状態で、相互に連結可能な複数のプレキャストパネルを
備え、前記プレキャストパネルは、周方向に連結された
状態で外周面を隔成するスキンプレートと、前記スキン
プレートに垂設固定された複数の縦梁と、前記プレキャ
ストパネルの上下方向の内面に固設され、連結状態で環
状に形成される横梁と、前記プレキャストパネルの積層
連結状態で分断部分および上下方向の接合部分に介在さ
れるシール材と、最下段に配置する前記プレキャストパ
ネルに突設され、前記プレキャストパネルと前記基礎部
分との間に介在させるシール材の位置規制をするストッ
パーとで構成した。このように構成された仮締切構造体
によれば、工法と同様に、仮締切工の主要部分となるプ
レキャストパネルは、予め工場生産することができるの
で、高品質なものが得られるとともに、矢板の打設など
のような現場工事が非常に少なくなるので、簡単かつ迅
速に構築することができるとともに、解体もこの手順を
逆に行うので、簡単且つ迅速に行える。前記縦梁には、
前記プレキャストパネルを周方向に連結した際に、連結
したプレキャストパネルの水平移動を許容するピン支承
部を設けることができる。この構成によれば、仮締切工
に偏荷重が加わった際に、仮締切工に曲げ応力が作用し
ないようにすることができる。前記スキンプレートの内
面側には、鉛直方向に延びる複数の補強用縦リブを設け
ることができる。
In order to achieve the above object, the present invention encloses an outer periphery of an underwater structure such as a bridge foundation with a temporary cut-off work, and drains the inside of the temporary cut-off work. In the temporary cut-off method for performing repairs such as repair and reinforcement of the underwater structure, the temporary cut-off is divided along the vertical and circumferential directions of the underwater structure, and includes a plurality of precast panels that can be connected to each other. , Erected a plurality of anchoring anchors, one end of which is fixed to the foundation part of the underwater structure, and after transporting the precast panel to the renovation site of the underwater structure, the divided part between the precast panels and the vertical direction While interposing a sealing material between the joint portion, the precast panel and the base portion, the fixing anchor is inserted and laminated and connected on the base portion,
In this state, the Prestressing force to the fixing anchor, a method for integrating the said base part and laminated linked precast panels, prior to introducing the prestressing force to the fixing anchor, lamination Between the connected precast panel and the underwater structure, a plurality of supporting members composed of expandable and contractible jacks are installed along the circumferential direction of the temporary cut-off work, and the precast at the bottom stage.
The pre-cap can be
The seat interposed between the strike panel and the foundation portion.
The position of the lumber is regulated . According to the temporary cut-off method constructed in this way, the precast panel, which is the main part of the temporary cut-off work, can be factory-produced in advance. After transporting to the site, insert a fixing anchor that is erected on the foundation part while inserting a sealing material between the divided part and the joint part in the vertical direction, the precast panel and the foundation part, It is constructed by integrating and connecting the foundation part and the precast panel that is laminated and connected in this state by introducing prestressing force to the anchoring anchor in this state, and on-site construction such as piling of sheet piles. It is so few that it can be easily and quickly constructed, and disassembly is also the reverse of this procedure, so it can be done just as easily and quickly. Further, in the temporary cutoff method of the present invention, before introducing the prestressing force to the fixing anchor, between the precast panel and the underwater structure that are laminated and connected, a supporting material is installed ,
When introducing the pre-stress force, it is possible to ensure the stability of the provisional deadline Engineering. In this case, since the supporting member is composed of a stretchable jack, it is possible to easily deal with the variation in the distance between the precast panel and the underwater structure. Furthermore, the present invention provides a temporary deadline for performing repairs such as repair and reinforcement of the underwater structure by surrounding the outer circumference of an underwater structure such as a bridge foundation with a temporary deadline and draining the inside of the temporary deadline. In the structure, the temporary cofferdam is divided along the vertical and circumferential directions of the underwater structure, and can be connected to each other while being inserted into a fixing anchor erected on the foundation of the underwater structure. A plurality of precast panels, the precast panel is a skin plate that separates the outer peripheral surface in a state of being connected in the circumferential direction, a plurality of vertical beams vertically fixed to the skin plate, and of the precast panel. is fixed in the vertical direction of the inner surface, a seal member is interposed and a horizontal beam which is formed in an annular shape, the joint portion of the dividing portion and the vertical direction in a stacked connection state of the precast panel coupled state, arranged in the bottom The precast path that
The precast panel and the foundation part projecting on the flannel.
The stopper that regulates the position of the sealing material
Composed with par . According to the temporary cut-off structure constructed in this way, the precast panel, which is the main part of the temporary cut-off work, can be factory-produced in advance in the same manner as the construction method, so that a high quality product can be obtained and the sheet pile Since the number of on-site works such as casting, etc. is extremely reduced, it is possible to construct easily and quickly, and disassembling is also carried out in the reverse order of this procedure, so that it can be done easily and quickly. The vertical beams include
When the precast panels are connected in the circumferential direction, a pin support portion that allows horizontal movement of the connected precast panels can be provided. According to this configuration, it is possible to prevent the bending stress from acting on the temporary shutoff when an unbalanced load is applied to the temporary shutoff. A plurality of vertical reinforcing ribs extending in the vertical direction may be provided on the inner surface side of the skin plate.

【0014】[0014]

【発明の実施の形態】以下、本発明の好適な実施の形態
について、添付図面を参照にして詳細に説明する。図1
から図7は、本発明にかかる仮締切工法および仮締切構
造体の一実施例を示している。同図に示す仮締切工法
は、水中構造物である橋梁10の修理,補強などの改修
工事を行う際に適用した場合を例示している。
Preferred embodiments of the present invention will now be described in detail with reference to the accompanying drawings. Figure 1
7 to 7 show one embodiment of the temporary cutoff method and the temporary cutoff structure according to the present invention. The temporary cut-off method shown in the figure illustrates a case where it is applied when performing repair work such as repair and reinforcement of the bridge 10 which is an underwater structure.

【0015】橋梁10は、橋脚12と、その下端に一体
的に形成された基礎部分であるフーチング14とを備え
ている。橋脚12は、その水平断面が略円形のものであ
り、フーチング14は、平面形状が円形に形成されてい
て、その下端の一部が水底地盤16中に埋没している。
The bridge 10 includes a bridge pier 12 and a footing 14 which is a base portion integrally formed at the lower end of the bridge pier 12. The horizontal cross section of the pier 12 is substantially circular, and the footing 14 is formed in a circular shape in plan view, and a part of the lower end thereof is buried in the submarine ground 16.

【0016】本実施例の仮締切工18は、橋脚12の外
周を囲撓するように設置され、その内部側の水を排水し
て、橋脚12の外周にドライな環境条件を創出するため
に使用される。
The temporary cofferdam 18 of this embodiment is installed so as to encircle the outer circumference of the pier 12, and drains water on the inner side thereof to create a dry environmental condition on the outer circumference of the pier 12. used.

【0017】仮締切工18は、橋脚12と同形状の同心
円状の構造体であって、橋脚12の鉛直方向および周方
向に沿って分断された実質的に同一構成の複数のプレキ
ャストパネル20を主要構成部材としている。各プレキ
ャストパネル20は、本実施例の場合には、円を等角度
間隔で4分割された形状になっていて、スキンプレート
20aと、複数の縦梁20bと、一対の横梁20cと、
複数の縦リブ20dとを有している。
The temporary cofferdam 18 is a concentric circular structure having the same shape as the pier 12, and a plurality of precast panels 20 of substantially the same structure divided along the vertical direction and the circumferential direction of the pier 12. It is a main component. In the case of this embodiment, each precast panel 20 has a shape in which a circle is divided into four at equal angular intervals, and a skin plate 20a, a plurality of vertical beams 20b, and a pair of horizontal beams 20c,
It has a plurality of vertical ribs 20d.

【0018】スキンプレート20aは、円弧状に屈曲し
ていて、プレキャスパネル20を周および鉛直方向に連
結した際に、円筒状になって、締切工18の外周面を隔
成する。
The skin plate 20a is bent in an arc shape, and when the pre-cass panel 20 is connected in the circumferential and vertical directions, the skin plate 20a becomes cylindrical and separates the outer peripheral surface of the cut-off work 18.

【0019】縦梁20bは、スキンプレート20aの周
方向の両端と、その中央部分に配置されていて、スキン
プレート20aの内面の鉛直方向に固設されている。ス
キンプレート20aの両端に固設された一対縦梁20b
の外周面には、後述するピン支承部を構成する厚肉鋼管
の挿入用凹部20fが、鉛直方向に沿って設けられてい
る。
The vertical beams 20b are arranged at both ends of the skin plate 20a in the circumferential direction and at the central portion thereof, and are fixed to the inner surface of the skin plate 20a in the vertical direction. A pair of vertical beams 20b fixed to both ends of the skin plate 20a
The outer peripheral surface of the is provided with a recess 20f for inserting a thick-walled steel pipe that constitutes a pin support portion described later along the vertical direction.

【0020】一対の横梁20cは、円弧状の平板から構
成され、スキンプレート20aおよび縦梁20bの上下
方向の端面に固設されている。この横梁20cは、プレ
キャストパネル20を周鉛直方向に連結した際に、環状
となり、締切工18の強度を補強する。なお、この横梁
20cは、一対に限ることはなく、スキンプレート20
aの中間に設けてもよい。
The pair of horizontal beams 20c are formed of arc-shaped flat plates and fixed to the end faces of the skin plate 20a and the vertical beams 20b in the vertical direction. When the precast panel 20 is connected in the circumferential vertical direction, the cross beam 20c becomes annular and reinforces the strength of the deadline 18. The horizontal beams 20c are not limited to one pair, and the skin plate 20
It may be provided in the middle of a.

【0021】また、各横梁20cには、後述する定着ア
ンカー22の挿通孔20eが貫通形成されている。縦リ
ブ20dは、スキンプレート20aの内周面側にあっ
て、その鉛直方向に延設固定され、スキンプレート20
aの強度を補強している。
Further, each horizontal beam 20c is formed with a through hole 20e for a fixing anchor 22 which will be described later. The vertical ribs 20d are on the inner peripheral surface side of the skin plate 20a and are extended and fixed in the vertical direction of the skin plate 20a.
The strength of a is reinforced.

【0022】なお、この縦リブ20dは、例えば、スキ
ンプレート20aの厚みを大きくした場合などには、必
ずしも必要としない。
The vertical rib 20d is not always necessary, for example, when the thickness of the skin plate 20a is increased.

【0023】次に、上記構成のプレキャストパネル20
を用いて、仮締切工18を組立てる手順について説明す
る。仮締切工18を組立てる際には、プレキャストパネ
ル20は、橋梁10の改修現場近傍の製作ヤードで製造
され、橋梁10の近傍まで運搬される。
Next, the precast panel 20 having the above structure.
A procedure for assembling the temporary cut-off work 18 will be described using. When assembling the temporary cofferdam 18, the precast panel 20 is manufactured in a manufacturing yard near the repair site of the bridge 10 and transported to the vicinity of the bridge 10.

【0024】一方、フーチング14には、下端が貫入固
設され、橋脚12に沿って鉛直方向に延びる下部定着ア
ンカー21が立設される。この下部定着アンカー21
は、プレキャストパネル20の高さよりも短くなってい
て、運搬されたプレキャストパネル20一段分が、下部
定着アンカー21に、横梁20cに設けられている挿通
孔20eを挿通させて沈設され、パネル20の組み立て
が終了すると、下部定着アンカー21には、カプラ25
を介して上部定着アンカー22が連結される。
On the other hand, the footing 14 is provided with a lower fixing anchor 21 having a lower end penetratingly fixed and extending vertically along the pier 12. This lower anchor 21
Is shorter than the height of the precast panel 20, and one stage of the transported precast panel 20 is sunk by inserting the insertion hole 20e provided in the cross beam 20c into the lower anchoring anchor 21, and thus the panel 20 When the assembly is completed, the coupler 25 is attached to the lower anchor 21.
The upper fixing anchor 22 is connected via the.

【0025】このとき、最下段のプレキャストパネル2
0の横梁20cと、フーチング14との間には、図4に
示すように、断面がL字型のシール材24が介装され
る。
At this time, the lowermost precast panel 2
As shown in FIG. 4, a seal material 24 having an L-shaped cross section is interposed between the horizontal beam 20 c of 0 and the footing 14.

【0026】なお、図4において、符号20gで示した
部材は、最下段に設置される横梁20cの下面に突設さ
れたシール材24の位置規制用のストッパーであり、こ
のストッパー20gは、フーチング14の外周を取り囲
むように設けられている。
In FIG. 4, a member 20g is a stopper for restricting the position of the sealing material 24 protruding from the lower surface of the horizontal beam 20c installed at the bottom, and this stopper 20g is a footing. It is provided so as to surround the outer circumference of 14.

【0027】定着アンカー22に挿通された4個のプレ
キャストパネル20は、その周方向の分断位置で、図5
に示すような状態で連結される。同図に示した連結状態
は、周方向に隣接する縦梁20b間に、止水シール材2
6、具体的には、止水用ゴム板を介装し、予め縦梁20
bに穿設されている貫通孔内にボルト27を挿通して、
ナット28を螺着することで行われる。
The four precast panels 20 inserted through the fixing anchors 22 are shown in FIG.
Are connected in the state shown in. In the connected state shown in the figure, the waterproof sealing material 2 is provided between the vertical beams 20b adjacent in the circumferential direction.
6. Specifically, a vertical beam 20 is provided in advance with a water blocking rubber plate interposed.
Insert the bolt 27 into the through hole formed in b,
It is performed by screwing the nut 28.

【0028】止水シール材26は、縦梁20bに設けら
れている凹部20fを覆うように配置され、凹部20f
には、厚肉鋼管30が挿入される。この凹部20fと厚
肉鋼管30とでピン支承部を構成している。止水シール
材26は、円筒状に組立てられるプレキャストパネル2
0の上端から下端に到達する長さを有している。
The water sealing material 26 is arranged so as to cover the recess 20f provided in the vertical beam 20b, and the recess 20f is provided.
A thick steel pipe 30 is inserted in the. The recess 20f and the thick-walled steel pipe 30 form a pin support portion. The water sealing material 26 is a precast panel 2 assembled in a cylindrical shape.
It has a length of 0 from the upper end to the lower end.

【0029】厚肉鋼管28は、止水シール材26とほぼ
同じ長さを有していて、その下端は、図6に示すよう
に、横梁20bの上面から上方に離間した位置になって
いる。ボルト27が挿入される貫通孔は、水平方向に長
く形成されていて、ボルト27とナット28とで連結さ
れたプレキャストパネル20が、水平方向に移動できる
ようになっている。
The thick-walled steel pipe 28 has substantially the same length as the waterproof seal material 26, and the lower end thereof is located at a position spaced upward from the upper surface of the horizontal beam 20b as shown in FIG. . The through hole into which the bolt 27 is inserted is formed to be long in the horizontal direction, and the precast panel 20 connected by the bolt 27 and the nut 28 can be moved in the horizontal direction.

【0030】なお、ピン支承部を構成する構造は、凹部
20fと厚肉鋼管30とのこうぞに限ることはなく、例
えば、図8に示すように、縦梁20bに相互に嵌合する
凹凸部20hを設け、この凹凸部20h間に止水シール
材26を挟み込む構造であってもよい。
The structure for forming the pin support is not limited to the groove between the recess 20f and the thick-walled steel pipe 30, but for example, as shown in FIG. The structure may be such that the portion 20h is provided and the water blocking sealing material 26 is sandwiched between the uneven portions 20h.

【0031】ボルト27,ナット28の結合により、4
個のプレキャストパネル20が周方向に連結されて、一
段分の環状部分が形成されると、その上段側に同様な方
法により、プレキャストパネル20を順次積層し、分断
位置をボルトナット27,28により連結する。
By connecting the bolt 27 and the nut 28,
When the individual precast panels 20 are connected in the circumferential direction to form an annular portion for one step, the precast panels 20 are sequentially laminated on the upper step side in the same manner, and the dividing position is set by the bolt nuts 27, 28. Link.

【0032】このとき、上下方向に隣接するプレキャス
トパネル20の横梁20c間には、図7に示すように、
シール材32が介装される。なお、各シール材32に
は、定着アンカー22の挿通用の孔が設けられている。
At this time, as shown in FIG. 7, between the horizontal beams 20c of the precast panel 20 which are vertically adjacent to each other, as shown in FIG.
The sealing material 32 is interposed. It should be noted that each sealing material 32 is provided with a hole for inserting the fixing anchor 22.

【0033】そして、所定の段数のプレキャストパネル
20の積層連結が終了すると、プレキャストパネル20
と橋脚12との間に支保用のジッャキ34が設置され
る。
When the lamination and connection of the predetermined number of precast panels 20 is completed, the precast panels 20 are
A jerk 34 for support is installed between the pier and the pier 12.

【0034】ジャッキ34の設置位置は、本実施例の場
合には、プレキャストパネル20の周方向の分断位置に
設定され、各ジッャキ34の伸縮プランジャが、プレキ
ャストパネル20の縦梁20bに当接するように設置さ
れる。
In the case of the present embodiment, the installation position of the jack 34 is set to a dividing position in the circumferential direction of the precast panel 20, and the telescopic plunger of each jack 34 is brought into contact with the vertical beam 20b of the precast panel 20. Is installed in.

【0035】また、ジャッキ34は、構築する仮締切工
18の大きさや高さなどに対応して、周方向に沿って等
角度間隔で複数設けられ、かつ、必要に応じて鉛直方向
に多段状に設置される。
Further, a plurality of jacks 34 are provided at equal angular intervals along the circumferential direction in accordance with the size and height of the temporary cofferdam 18 to be constructed, and, if necessary, in a multistage shape in the vertical direction. Is installed in.

【0036】なお、プレキャストパネル20と橋脚12
との間に設ける支保材は、後述するように、定着アンカ
ー22にプレストレス力を導入した際に、積層された仮
締切工18の安定性を確保するために設置するものであ
るが、ジャッキ34に限ることはない。
The precast panel 20 and the pier 12
As will be described later, the supporting member provided between the fixing member 22 and the supporting member is provided to ensure the stability of the laminated temporary cofferdams 18 when the prestressing force is applied to the fixing anchor 22. It is not limited to 34.

【0037】この場合、ジャッキ34を用いると、プレ
キャストパネル20と橋脚12との間の間隔のバラツキ
に容易に対応することができ、支保材の設置が容易に行
えるという利点がある。
In this case, if the jack 34 is used, it is possible to easily cope with the variation in the distance between the precast panel 20 and the pier 12, and it is possible to easily install the supporting material.

【0038】ジャッキ34による仮締切工18の内方か
らの支保が終了すると、最上段のプレキャストパネル2
0から上方に突出している定着アンカー22に、ホール
インジャッキなどの引張工具を装着し、定着アンカー2
2にプレストレスを導入して、定着アンカー22をプレ
キャストパネル20に固定する。
When the support of the temporary cut-off work 18 from the inside by the jack 34 is completed, the uppermost precast panel 2
Attach a tension tool such as a hole-in jack to the fixing anchor 22 protruding upward from 0 to fix the fixing anchor 2
The fixing anchor 22 is fixed to the precast panel 20 by introducing a prestress to the precast panel 20.

【0039】定着アンカー22にプレストレス力を導入
すると、上下方向に積層されているプレキャストパネル
20の横梁20cが、シール材32を挟圧するようにし
て、相互に密着し、フーチング14と積層連結されたプ
レキャストパネル20とが一体化された止水構造の仮締
切工18が完成する。
When a prestressing force is applied to the fixing anchor 22, the transverse beams 20c of the precast panel 20 which are vertically laminated are in close contact with each other so as to sandwich the sealing material 32, and are laminated and connected to the footing 14. The temporary cut-off work 18 having a water blocking structure, which is integrated with the precast panel 20, is completed.

【0040】仮締切工18が完成すると、内部の水を排
水して、橋脚12の周囲にドライな作業空間を創り出
し、橋脚12やフーチング14の補強などの改修作業が
行われ、改修作業が終了すると、仮締切工18内に水を
導入して、組立時と逆の作業を行うことにより、仮締切
工18の解体,撤去が行われる。
When the temporary deadline 18 is completed, the internal water is drained to create a dry working space around the pier 12, and the repair work such as the reinforcement of the pier 12 and the footing 14 is performed, and the repair work is completed. Then, water is introduced into the temporary deadline 18 and the work opposite to that at the time of assembling is performed, whereby the temporary deadline 18 is disassembled and removed.

【0041】さて、以上のように構成された仮締切工法
および仮締切構造体によれば、仮締切工18の主要部分
となるプレキャストパネル20は、予め工場生産するの
で、高品質なものが得られるとともに、これを水中構造
物の改修現場まで運搬した後に、分断部分および上下方
向の接合部分と水中構造物(フーチング14)との間に
シール材24,26,32を介在させて、橋脚12の外
周を囲撓するように設置すし、定着アンカー22にプレ
ストレス力を導入すると構築することができ、矢板の打
設などのような現場工事が非常に少なく、このため仮締
切工18を簡単かつ迅速に構築することができる。
According to the temporary cut-off method and the temporary cut-off structure constructed as described above, the precast panel 20, which is the main part of the temporary cut-off work 18, is manufactured in advance in a factory, and therefore a high quality product is obtained. At the same time, after transporting this to the site of repairing the underwater structure, the seal members 24, 26, 32 are interposed between the underwater structure (footing 14) and the dividing part and the joint in the vertical direction, and the pier 12 It can be constructed by surrounding the outer circumference of the anchor and introducing prestressing force to the anchoring anchor 22, and there is very little on-site work such as placing a sheet pile. Therefore, the temporary deadline 18 is easy. And it can be built quickly.

【0042】また、改修工事後の撤去も簡単に行え、急
速施工に適したものとなる。さらに、本実施例の場合に
は、仮締切工18をフーチング14の上面側に構築し、
従来の仮締切工のように二重構造と異なり、一重構造な
ので、仮締切工18は、フーチング14の大きさよりも
小さくなり、広い面積を占有しないので、水上交通の障
害にならない。
Further, the removal after the repair work can be easily performed, which is suitable for the rapid construction. Further, in the case of the present embodiment, the temporary cut-off work 18 is constructed on the upper surface side of the footing 14,
Unlike the conventional temporary cutout, which has a single structure unlike the double structure, the temporary cutoff 18 is smaller than the size of the footing 14 and does not occupy a large area, which does not hinder water traffic.

【0043】また、本発明の仮締切工18は、中詰め土
砂が不要になるので、水質を汚濁することもない。さら
に、本実施例の場合には、プレキャストパネル20を周
方向に連結した際に、連結したプレキャストパネル20
の水平移動を許容するピン支承部となる鋼管収容用凹部
20fを設けているので、仮締切工18に偏荷重が加わ
った際に、仮締切工18に曲げ応力が作用しないように
することができる。
Further, since the temporary shut-off work 18 of the present invention does not require the filling of earth and sand, it does not pollute the water quality. Further, in the case of the present embodiment, when the precast panels 20 are connected in the circumferential direction, the connected precast panels 20 are connected.
Since the steel pipe accommodating recess 20f serving as a pin supporting portion that allows the horizontal movement of the temporary fastening member 18 is provided, it is possible to prevent bending stress from acting on the temporary fastening member 18 when an unbalanced load is applied to the temporary fastening member 18. it can.

【0044】なお、上記実施例では、円形断面の仮締切
工18を例示したが、本発明の実施は、この形状に限定
されることはなく、例えば、多角形状や楕円形状,長円
形状にも適用することができる。
In the above embodiment, the temporary cut-off work 18 having a circular cross section is illustrated, but the embodiment of the present invention is not limited to this shape. For example, a polygonal shape, an elliptical shape, or an oval shape can be used. Can also be applied.

【0045】また、プレキャストパネル20の周方向の
分割数も4に限ることはなく、構築しようとする仮締切
工の大きさに応じて適宜選択することができる。
The number of divisions of the precast panel 20 in the circumferential direction is not limited to four, and can be appropriately selected according to the size of the temporary cofferdam to be constructed.

【0046】[0046]

【発明の効果】以上、実施例で詳細に説明したように、
本発明にかかる仮締切工法および仮締め切り構造体によ
れば、以下の作用効果が得られる。 .プレキャストパネルは、工場生産が可能であり、こ
のため高品質なものが得られるとともに、その転用も可
能なので、経済的な面でも有利になる。 .一重構造で、コンパクトな構造なため、急速施工に
適し、かつ、広い占有面積を必要としないので、経済的
であり、水上交通の妨げにならない。
As described above in detail in the embodiments,
According to the temporary cutoff method and the temporary cutoff structure according to the present invention, the following operational effects are obtained. . The precast panel can be manufactured in a factory, and therefore, a high quality one can be obtained, and the precast panel can be diverted, which is economically advantageous. . The single structure and compact structure are suitable for rapid construction and do not require a large occupied area, so they are economical and do not hinder water transportation.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明にかかる仮締切構造体の組立状態の半
断面図である。
FIG. 1 is a half cross-sectional view of an assembled state of a temporary shutoff structure according to the present invention.

【図2】図1の上面図である。FIG. 2 is a top view of FIG.

【図3】図1に示した仮締切構造体で用いるプレキャス
トパネルの斜視図である。
3 is a perspective view of a precast panel used in the temporary shut-off structure shown in FIG. 1. FIG.

【図4】図1のA部拡大図である。FIG. 4 is an enlarged view of part A in FIG.

【図5】図2のB部拡大図である。5 is an enlarged view of part B in FIG.

【図6】図1のA部の他の部分を示す拡大図である。FIG. 6 is an enlarged view showing another portion of section A of FIG.

【図7】図1のC部拡大図である。FIG. 7 is an enlarged view of a C portion of FIG.

【図8】本発明の仮締切構造体で用いるピン支承部の他
の例を示す要部断面図である。
FIG. 8 is a sectional view of an essential part showing another example of the pin support part used in the temporary shut-off structure of the present invention.

【図9】従来の二重締切工法の一例を示す平面および断
面説明図である。
FIG. 9 is a plan view and a cross-sectional explanatory view showing an example of a conventional double deadening method.

【符号の説明】[Explanation of symbols]

10 橋梁 12 橋脚 14 フーチング 18 仮締切工 20 プレキャストパネル 20a スキンプレート 20b 縦梁 20c 横梁 20d 縦リブ 22 定着アンカー 24 シール材 26 止水シール材 32 シール材 34 ジャッキ 10 bridges 12 piers 14 footing 18 Temporary deadline 20 precast panel 20a skin plate 20b vertical beam 20c horizontal beam 20d vertical rib 22 Fixing anchor 24 Seal material 26 Water sealing material 32 Seal material 34 Jack

フロントページの続き (56)参考文献 特開 平4−336123(JP,A) 実公 昭48−3442(JP,Y2) (58)調査した分野(Int.Cl.7,DB名) E02D 19/04 Continuation of the front page (56) References JP-A-4-336123 (JP, A) Jitsuko 48-3442 (JP, Y2) (58) Fields investigated (Int.Cl. 7 , DB name) E02D 19 / 04

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 橋梁基礎などの水中構造物の外周を仮締
切工で囲撓し、前記仮締切工の内部を排水して、前記水
中構造物の修理,補強などの改修を行う仮締切工法にお
いて、 前記仮締切工は、前記水中構造物の鉛直および周方向に
沿って分断され、相互に連結可能な複数のプレキャスト
パネルを備え、 前記水中構造物の基礎部分に一端が定着された複数の定
着アンカーを立設し、 前記プレキャストパネルを前記水中構造物の改修現場ま
で運搬した後に、前記プレキャストパネル間の分断部分
および上下方向の接合部分,前記プレキャストパネルと
前記基礎部分との間にそれぞれシール材を介在させなが
ら、前記定着アンカーを挿通させて前記基礎部分上に積
層連結し、 この状態で、前記定着アンカーにプレストレス力を導入
して、前記基礎部分と積層連結されたプレキャストパネ
ルとを一体化させる工法であって、 前記定着アンカーにプレストレス力を導入する前に、積
層連結された前記プレキャストパネルと前記水中構造物
との間に、伸縮自在なジャッキからなる支保材を、前記
仮締切工の周方向に沿って複数設置するとともに、最下段の前記プレキャストパネルに突設されたストッパ
ーにより、前記プレキャストパネルと前記基礎部分との
間に介在させた前記シール材の位置規制をする ことを特
徴とする仮締切工法。
1. A temporary cut-off method in which the outer periphery of an underwater structure such as a bridge foundation is bent by a temporary cut-off work, and the inside of the temporary cut-off work is drained to perform repairs such as repair and reinforcement of the underwater structure. In, the temporary cut-off work is divided along the vertical and circumferential directions of the underwater structure, comprises a plurality of precast panels that can be connected to each other, a plurality of one end is fixed to the foundation portion of the underwater structure. A fixing anchor is erected, and after transporting the precast panel to the site of renovation of the underwater structure, a dividing portion between the precast panels and a vertical joint portion, and a seal between the precast panel and the foundation portion, respectively. While interposing a material, the fixing anchor is inserted and laminated and connected on the base portion, and in this state, a prestressing force is introduced to the fixing anchor to A method of integrating the divided and stacked linked precast panels, the before introducing the prestressing force to the fixing anchor, during lamination linked the precast panel and said underwater structure, telescopic A plurality of supporting materials consisting of various jacks are installed along the circumferential direction of the temporary cut-off work, and a stopper provided on the lowermost precast panel
Between the precast panel and the foundation by
A temporary cut-off construction method characterized in that the position of the sealing material interposed therebetween is regulated .
【請求項2】 橋梁基礎などの水中構造物の外周を仮締
切工で囲撓し、前記仮締切工の内部を排水して、前記水
中構造物の修理,補強などの改修を行う仮締切構造体に
おいて、 前記仮締切工は、前記水中構造物の鉛直および周方向に
沿って分断され、前記水中構造物の基礎部分に立設され
た定着アンカーに挿通された状態で、相互に連結可能な
複数のプレキャストパネルを備え、 前記プレキャストパネルは、周方向に連結された状態で
外周面を隔成するスキンプレートと、 前記スキンプレートに垂設固定された複数の縦梁と、 前記プレキャストパネルの上下方向の内面に固設され、
連結状態で環状に形成 される横梁と、 前記プレキャストパネルの積層連結状態で分断部分およ
び上下方向の接合部分に介在されるシール材と、 最下段に配置する前記プレキャストパネルに突設され、
前記プレキャストパネルと前記基礎部分との間に介在さ
せるシール材の位置規制をするストッパーとを有するこ
とを特徴とする仮締切構造体。
[2] Temporarily tightening the outer circumference of an underwater structure such as a bridge foundation
Encircle with the cut work, drain the inside of the temporary cut-off work, and
For temporary shut-off structures that perform repairs such as repairs and reinforcements for medium structures
In the above, the temporary cut-off work is performed in the vertical and circumferential directions of the underwater structure.
It is divided along and is erected on the foundation of the underwater structure.
Can be connected to each other while being inserted into the fixed anchor
A plurality of precast panels are provided, the precast panels being connected in the circumferential direction.
A skin plate defining an outer peripheral surface, a plurality of vertical beams vertically mounted on the skin plate, and fixedly provided on an inner surface of the precast panel in the vertical direction,
In the connected state, the cross beam is formed into an annular shape, and in the laminated connected state of the precast panel, there are divided parts and
And a sealing material that is interposed between the vertical joining portion and the precast panel that is arranged at the bottom,
There is an interposition between the precast panel and the foundation part.
A stopper to regulate the position of the sealing material
And a temporary deadline structure.
【請求項3】 前記縦梁には、前記プレキャストパネル3. The precast panel on the vertical beam.
を周方向に連結した際に、連結したプレキャストパネルThe precast panels that were joined when they were joined in the circumferential direction
の水平移動を許容するピン支承部を設けたことを特徴とCharacterized by the provision of a pin support part that allows horizontal movement of the
する請求項2記載の仮締切構造体。The temporary deadline structure according to claim 2.
【請求項4】 前記スキンプレートの内面側に鉛直方向4. The vertical direction on the inner surface side of the skin plate
に延びる複数の補強用縦リブを設けたことを特徴とするA plurality of vertical reinforcing ribs extending in the
請求項2または3記載の仮締切構造体。The temporary deadline structure according to claim 2 or 3.
JP17860397A 1997-07-03 1997-07-03 Temporary deadline method and temporary deadline structure Expired - Lifetime JP3379391B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17860397A JP3379391B2 (en) 1997-07-03 1997-07-03 Temporary deadline method and temporary deadline structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17860397A JP3379391B2 (en) 1997-07-03 1997-07-03 Temporary deadline method and temporary deadline structure

Publications (2)

Publication Number Publication Date
JPH1121908A JPH1121908A (en) 1999-01-26
JP3379391B2 true JP3379391B2 (en) 2003-02-24

Family

ID=16051349

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17860397A Expired - Lifetime JP3379391B2 (en) 1997-07-03 1997-07-03 Temporary deadline method and temporary deadline structure

Country Status (1)

Country Link
JP (1) JP3379391B2 (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4589789B2 (en) * 2004-10-06 2010-12-01 新日本製鐵株式会社 Structure and its corner structure and column structure
JP4604771B2 (en) * 2005-03-10 2011-01-05 株式会社大林組 Water shutoff structure and water stop method for temporary closing
JP2007239244A (en) * 2006-03-07 2007-09-20 Kenji Takemoto Temporary structure
KR100936161B1 (en) 2009-07-31 2010-01-12 현대엔지니어링 주식회사 Nature friendly polygon cell type coffering method for harbor, river and dam construction
CN102926387B (en) * 2012-10-22 2014-11-05 中交第二航务工程局有限公司 Mounting and guiding device and positioning method for underwater circuit purlins of steel sheet pile cofferdam
CN104005339B (en) * 2014-06-12 2016-01-20 中铁五局(集团)有限公司 A kind of device for speedway pier cap beam bed die
CN105089066B (en) * 2015-09-02 2017-01-18 中国石油天然气股份有限公司 Assembled cofferdam for emergency treatment of leakage of oil pipeline of wetland
JP6868417B2 (en) * 2017-02-24 2021-05-12 Jfe建材株式会社 How to build hollow segments, annular structures, water stop wall structures and water stop wall structures
CN109457715A (en) * 2018-11-29 2019-03-12 中设设计集团股份有限公司 A kind of revetment cofferdam
KR102011321B1 (en) * 2018-12-27 2019-10-21 (주)더브릿지 Construction method of foundation using rectangular pipe and its foundation
CN116290005B (en) * 2023-05-15 2023-07-14 山东省路桥集团有限公司 Highway bridge construction cofferdam device

Also Published As

Publication number Publication date
JPH1121908A (en) 1999-01-26

Similar Documents

Publication Publication Date Title
US11072934B2 (en) Foundation with pedestal and ribs for towers
US9937635B2 (en) Method of constructing a wind tower foundation
US9096985B1 (en) Foundation with slab, pedestal and ribs for columns and towers
US8661752B2 (en) Foundation with slab, pedestal and ribs for columns and towers
US10138648B2 (en) Tower and method for assembling tower
US20110061321A1 (en) Fatigue reistant foundation system
US6449791B1 (en) Prefabricated pier system
JP3379391B2 (en) Temporary deadline method and temporary deadline structure
JP3928225B2 (en) Temporary deadline structure
JP3928226B2 (en) Temporary deadline structure
JP3788245B2 (en) Temporary deadline construction method
JPH08193330A (en) Construction method of strut/beam material in underground structure
JPH1136232A (en) Composite column base structure and its construction method
JPH11117521A (en) Suspended scaffold
JPH10147941A (en) Cofferdam construction method
KR20040034555A (en) Abutment and pier using composite pile and sheet pile of a bridge, and it's construction method
JPH08100464A (en) Joint structure and work execution method for structure using it
JP4024449B2 (en) Seismic isolation method for existing buildings
US20080008538A1 (en) Foundation system
JP3387436B2 (en) Temporary deadline method and temporary deadline structure
JP3849234B2 (en) Reinforced concrete underground outer wall construction method
JP4604771B2 (en) Water shutoff structure and water stop method for temporary closing
JP2802612B2 (en) Underwater formwork method
JP2615344B2 (en) Foundation using expanded polystyrene and its construction method
JP2024521265A (en) Building Foundations

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071213

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081213

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091213

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091213

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101213

Year of fee payment: 8

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101213

Year of fee payment: 8

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111213

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121213

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121213

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131213

Year of fee payment: 11

EXPY Cancellation because of completion of term