Correction tool for installation of soil injection press-in propulsion device

Info

Publication number
JP3340694B2
JP3340694B2 JP07320399A JP7320399A JP3340694B2 JP 3340694 B2 JP3340694 B2 JP 3340694B2 JP 07320399 A JP07320399 A JP 07320399A JP 7320399 A JP7320399 A JP 7320399A JP 3340694 B2 JP3340694 B2 JP 3340694B2
Authority
JP
Japan
Prior art keywords
propulsion device
propulsion
base
installation
press
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP07320399A
Other languages
Japanese (ja)
Other versions
JP2000265783A (en
Inventor
正尋 池田
隆 樋田
Original Assignee
和興エンジニアリング株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 和興エンジニアリング株式会社 filed Critical 和興エンジニアリング株式会社
Priority to JP07320399A priority Critical patent/JP3340694B2/en
Publication of JP2000265783A publication Critical patent/JP2000265783A/en
Application granted granted Critical
Publication of JP3340694B2 publication Critical patent/JP3340694B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、地下水平掘削路を
掘り進む土入圧入推進装置の設置作業において、設置す
る同推進装置の水平、垂直方向の推進方向を容易に変更
できる土入圧入推進装置の設置補正具に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a soil injection press-in propulsion device capable of easily changing the horizontal and vertical propulsion directions of the installed propulsion device in an installation work of the soil injection press-in propulsion device for digging an underground horizontal excavation path. Related to the installation correction tool.

【0002】[0002]

【従来の技術】従来より、電話線をはじめ、送電用の電
気ケーブル、水道管等は道路下に埋設されており、工事
期間、道路の閉鎖や開削により生ずる残土(産業廃棄
物)等の処理問題を解決するために、埋設箇所を開削し
ないで、両端に立坑を設け、一方の立坑から他方の立坑
間まで水平方向に推進管を土入圧入し、この推進管の中
に配線等を行う工法がある。このような推進管の土入圧
入は、推進管の正確な推進位置を測定するために、推進
管の先頭にその位置を検知するセンサを備えた先端装置
が設けられ、目的とする他の立坑まで先端装置と複数の
推進管を、一方の立坑内底部に設置された推進装置によ
り押し進めて、推進路を開削していた。
2. Description of the Related Art Conventionally, telephone lines, electric cables for power transmission, water pipes, and the like are buried under roads, and during construction, disposal of residual soil (industrial waste) caused by closing or excavation of roads. In order to solve the problem, without excavating the buried place, provide shafts at both ends, press-fit the propulsion pipe in the horizontal direction from one shaft to the other, and perform wiring etc. in this propulsion tube There is a construction method. In order to measure the exact propulsion position of the propulsion pipe, a tip device equipped with a sensor for detecting the position of the propulsion pipe is provided at the head of the propulsion pipe. Until now, the propulsion device installed at the bottom of one of the shafts pushed the tip device and a plurality of propulsion tubes to cut the propulsion path.

【0003】図5は、前記土入圧入推進装置を立坑内に
搬入する様子を示す説明図であり、図中、20は、前記
立坑、21は、該立坑20の開口部、22は、該立坑2
0の内底部、23は、前記立坑20の内底部22に設置
され、推進管を地中内に押し進める推進装置、24は、
前記推進装置を前記内底部22に設置する際に、吊り下
げるワイヤーロープ、また、25は、前記推進装置23
により地中内に埋設され、その管内に配線等が行われる
推進管である。立坑20は、例えば、電話等の通信線を
埋設するためには、通常深さ約5m、内底部面の縦5m
〜6m、同横1m〜2mの大きさの立坑が開削される。
[0005] FIG. 5 is an explanatory view showing a state in which the above-mentioned digging press-in propulsion device is carried into a shaft, in which 20 is the shaft, 21 is an opening of the shaft 20, and 22 is an opening of the shaft. Shaft 2
0, an inner bottom portion 23 is installed on the inner bottom portion 22 of the shaft 20, and a propulsion device for pushing a propulsion pipe into the ground, 24
When the propulsion device is installed on the inner bottom portion 22, a wire rope suspended from the propulsion device 25 is connected to the propulsion device 23.
It is a propulsion pipe that is buried in the ground and is used for wiring and the like. In order to bury communication lines such as telephones, the shaft 20 usually has a depth of about 5 m and a vertical length of 5 m on the inner bottom surface.
A shaft with a size of up to 6 m and a width of 1 m to 2 m is opened.

【0004】前記立坑20の開口部21は、道路際に開
削されることが多く、この道路を使用する車両や通行人
に、通行止め等の不便を与えないようになるべく狭い面
積の開削であることが要求される。
[0004] The opening 21 of the shaft 20 is often cut along a road, and the opening 21 has a small area so as not to inconvenience vehicles and pedestrians who use this road, such as blocking traffic. Is required.

【0005】また、前記推進装置23は、前記推進管2
5を前記一方の立坑から土入圧入するためのものであ
り、長さ4400mm〜5460mm、幅800mm〜
1270mm、高さ1440mm〜1500mm程度の
大きさであり、また、地中に大きな圧力で推進管を押し
込むため、その重量も3t〜4t程度の重量を有するも
のである。
[0005] The propulsion device 23 is provided with the propulsion pipe 2.
5 for injecting into the soil from one of the shafts, and has a length of 4400 mm to 5460 mm and a width of 800 mm to
It has a size of about 1270 mm and a height of about 1440 mm to 1500 mm, and has a weight of about 3 t to 4 t because the propulsion pipe is pushed into the ground with a large pressure.

【0006】このような推進装置23は、前記立坑20
内に搬入され、前記立坑20の内底部22の所定位置に
載置されるには、トラック等の荷台に積載されて運ばれ
た推進装置23にワイヤーロープ24を巻き付け、クレ
ーン車等を用いて、吊り下げ、設置する作業にて行われ
る。
[0006] Such a propulsion device 23 is provided with the shaft 20.
The wire rope 24 is wound around a propulsion device 23 which is loaded and carried on a carrier such as a truck, and is loaded using a crane truck or the like. , Hanging and installation work.

【0007】[0007]

【発明が解決しようとする課題】この開口部21と内底
部22の間には、既に埋設されている水道や電気、ガス
等の都市生活に欠かせない様々な埋設管が存在すること
も多く、この設置作業に際しては、これらの既設の埋設
管に損傷を与えないように注意深く、これらの既設管の
間を縫って設置しなければならないことが多い。そこ
で、この設置作業は、前述するように、比較的狭く開削
された前記立坑20の開口部21において、同推進装置
23を縦につり下げたり、斜めにつり下げたりしなが
ら、前記既設管の間を縫っての設置作業であり、かなり
の困難を伴うものであった。すなわち、前述したよう
に、道路に立坑を掘削した場合は、開口部を広くできな
いため、ワイヤーロープで吊り下げた推進装置を斜めに
して立坑内に搬入しなければならず、また、例えば、電
話線を配線するために立坑を掘削すると、道路と立坑の
内底部の間には、既に他の水道管、電気ケーブル等の配
管が露出してしまうことがあり、この場合には推進装置
の設置位置が、他の配管の下になるため、これらの配管
を損傷しないように、配管の隙間を通ってワイヤーロー
プで吊り下げられた推進装置を搬入して、目的とする位
置に設置しなければならず、これらの作業は非常に困難
であった。このため、ひとつの方法として、該推進装置
を分割して、立坑内底部に搬入し、立坑内底部で組み立
てる方法もあるが、分割・組立作業に時間を要すると共
に、作業員に組立技術が必要となり、推進装置の設置に
要する時間を増加させることとなっていた。さらに、上
述したように、推進装置は、重量が3t〜4tと非常に
重いため、一旦、前記立坑内底部22に設置した後で
は、僅かな設置位置のずれがあっても、設置後に、その
設置位置を変更することは非常に困難であった。また、
立坑から目的とする他の立坑向かって土入圧入される推
進管の推進方向が、目的とする推進方向へ向けて土入圧
入されない場合は、推進管の先頭に設けられた先端装置
による大幅な方向補正が必要となり、そのために埋設さ
れる推進管が地中内を蛇行してしまうといった問題があ
った。
Between the opening 21 and the inner bottom 22, there are often various buried pipes which are already buried, such as water supply, electricity and gas, which are indispensable for city life. In this installation work, it is often necessary to sew the existing buried pipes carefully so as not to damage them. Therefore, as described above, this installation work is performed by suspending the propulsion device 23 vertically or obliquely in the opening 21 of the shaft 20 which is relatively narrow and excavated, while removing the existing pipe. It was an installation work with a gap between them, which involved considerable difficulty. That is, as described above, when a shaft is excavated on a road, the opening cannot be widened, so that the propulsion device suspended by a wire rope must be carried into the shaft at an angle, and for example, a telephone When a shaft is excavated for wiring, other pipes such as water pipes and electric cables may already be exposed between the road and the inner bottom of the shaft. Since the position is below other pipes, the propulsion device suspended by a wire rope must be carried in through the gap between the pipes and installed at the target position so as not to damage these pipes. In addition, these tasks were very difficult. For this reason, as one method, there is a method of dividing the propulsion device, carrying it into the bottom of the shaft, and assembling it at the bottom of the shaft. Therefore, the time required for installing the propulsion device is to be increased. Furthermore, as described above, since the propulsion device has a very heavy weight of 3t to 4t, once it is installed on the bottom 22 of the shaft, even if there is a slight shift in the installation position, it will be It was very difficult to change the installation position. Also,
If the propulsion direction of the propulsion pipe from the shaft to other target shafts is not injected into the target propulsion direction, a drastic increase in the tip equipment provided at the head of the propulsion pipe Direction correction is required, which causes a problem that the buried propulsion pipe meanders in the ground.

【0008】本発明は、上記従来の事情に鑑みてなされ
たもので、重量機材である推進装置が、目的とする位置
に、正確に設置されてなくても、仮の設置後に推進装置
の水平位置、垂直位置を容易に修正することのできる土
入圧入推進装置の設置補正具を提供することを目的とす
る。
[0008] The present invention has been made in view of the above-mentioned conventional circumstances, and even if the propulsion device, which is a heavy equipment, is not accurately installed at a target position, the propulsion device may not move horizontally after provisional installation. It is an object of the present invention to provide an installation correction tool for a soil-intrusion press-in propulsion device that can easily correct the position and vertical position.

【0009】[0009]

【課題を解決するための手段】本願請求項1に係る発明
は、土入圧入推進装置の設置補正具に係り、地中内水平
方向に推進管を土入圧入する土入圧入推進装置の設置補
正具において、上方が開口し、一側部付近に側面と平行
に支板が設けられた基台と、前記基台の開口部分に設け
られ、所定の方向に向けて設置される前記土入圧入推進
装置が載置される摺動台と、前記摺動台内部に設けられ
前記基台の長さ範囲内で、車輪により水平方向に移動す
る台車と、前記台車の一側部を貫通してネジ穴を有する
ナットスリーブとの外周部が固着され、ネジ状のボルト
アームの一端が前記基台に設けられた支板を貫通して回
動可能に取り付けられ、該ボルトアームのネジが前記ナ
ットスリーブとのネジ穴に螺結された摺動部と、前記摺
動部のボルトアームの一端に連結して設けられ、上下動
により間歇一方向回転運動を伝達する回転方向切替スイ
ッチが設けられたラチェットを有する操作レバーとから
なることを特徴とする土入圧入推進装置の設置補正具。
また、本願請求項2に係る発明は、前記請求項1に記載
の土入圧入推進装置の設置補正具に係り、前記基台の長
尺両側端底部にジャッキ挿入口を設け、ジャッキの起重
ペダルをはめ込んで起重し、垂直方向の高さ位置を補正
するようにしたことを特徴とする。
The invention according to claim 1 of the present application relates to an installation correction tool for a soil injection press-in propulsion device, and more particularly, to the installation of a soil injection press-in propulsion device for soil-injecting a propulsion pipe horizontally in the ground. In the compensator, a base having an opening at an upper side and having a support plate provided near one side in parallel with a side surface, and the dirt provided at an opening of the base and installed in a predetermined direction. A slide base on which the press-in propulsion device is mounted, a bogie provided inside the slide base, within a length range of the base, a bogie horizontally moved by wheels, and penetrating one side of the bogie. The outer periphery of the nut sleeve having a screw hole is fixed, and one end of a screw-shaped bolt arm is rotatably mounted through a support plate provided on the base. A sliding portion screwed into a screw hole of the nut sleeve, and a bolt arm of the sliding portion; And an operation lever having a ratchet provided with a rotation direction changeover switch for transmitting intermittent one-way rotation by up-and-down movement. .
The invention according to claim 2 of the present application relates to the installation correction tool for the soil-in press-fitting propulsion device according to claim 1, wherein a jack insertion port is provided at the bottom of each of the long sides of the base to raise the jack. It is characterized in that the pedal is fitted and raised to correct the vertical height position.

【0010】[0010]

【発明の実施の形態】以下、本発明の一実施の形態に係
る土入圧入推進装置の設置補正具を、図面を参照して詳
細に説明する。なお、立坑内に設置される土入圧入推進
装置は、図5に示した従来とものと同様のものであるた
め、同一部分は、同一の符号を付して説明する。図1
は、本発明の一実施の形態に係る土入圧入推進装置の設
置補正具1の概略斜視図であり、図2(a)は、図1に
おけるY−Y’、Z−Z’の断面図であり、同(b)
は、図1におけるX−X’の断面図である。図1、図2
において、符号2は、同補正具1の全体を包含する基
台、3は、その上に前記推進装置が載置されたまま位置
を修正する摺動台、4は、前記摺動台3を押さえる押
具、5は、回動することにより、前記摺動台3を所定位
置まで摺動し、所定位置で止める摺動操作レバー、6
は、前記基台2の長手方向を仕切る形状で一端付近に設
けられ、前記摺動操作レバー5を設ける支板、7、8
は、前記摺動台3を載置する台車であり、内部にレール
溝上に載置された複数の車輪を有する。9は、前記台車
8に設けられ、前記摺動操作レバー5を回動させること
により、回動するボルトアーム9bおよびこのボルトア
ーム9bの回動により、螺合するナットスリーブ9aが
水平方向に摺動するように構成された摺動部であり、ま
た、10は、前記基台2の両下端に差し込まれ、両端部
の高さを上下修正するジャッキである。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is an exploded perspective view of an embedding press-fitting propulsion device according to an embodiment of the present invention. In addition, since the soil injection press-in propulsion device installed in the shaft is the same as the conventional one shown in FIG. 5, the same parts will be described with the same reference numerals. FIG.
FIG. 2 is a schematic perspective view of an installation corrector 1 of the soil injection press-in propulsion device according to one embodiment of the present invention, and FIG. 2A is a cross-sectional view taken along YY ′ and ZZ ′ in FIG. (B)
FIG. 2 is a sectional view taken along line XX ′ in FIG. 1. 1 and 2
In the figure, reference numeral 2 denotes a base that covers the entire correction tool 1, reference numeral 3 denotes a slide table for correcting the position while the propulsion device is mounted thereon, and reference numeral 4 denotes The pressing tool 5 for pressing slides the slide table 3 to a predetermined position by rotating, and a sliding operation lever 6 for stopping at a predetermined position.
Are provided near one end in a shape that partitions the longitudinal direction of the base 2, and support plates on which the sliding operation lever 5 is provided;
Is a trolley on which the slide table 3 is mounted, and has a plurality of wheels mounted on rail grooves therein. Reference numeral 9 denotes a bolt arm 9b that is provided on the carriage 8 and rotates the sliding operation lever 5 so that the nut arm 9a to be screwed in the horizontal direction slides by the rotation of the bolt arm 9b and the bolt arm 9b. Numeral 10 is a jack which is inserted into both lower ends of the base 2 to adjust the height of both ends up and down.

【0011】基台2は、本実施の形態では、長さ142
0mm、奥行き約220mm、高さ80mmの上方が開
口した箱体で形成され、通常は、二本を一組として、前
記土入圧入推進装置23の前後に配置して使用される。
また、前記基台2の長手方向の一端部付近には、摺動操
作レバー5および前記摺動部9が取り付けられる支板6
が設けられている。さらに、前記基台2の両端底部に
は、後述するジャッキ10の起重ペダル10aを挿入す
るために、側部方向から幅10cm程度、高さ15mm
で約60mm切り欠かれたジャッキ挿入口2a、2b
が、それぞれ設けられている。また、この基台2の内底
部には、後述する台車7、8の車輪が載置されるレール
溝2c、2dが設けられている。前記摺動台3は、本実
施の形態では、断面U字状に形成され、中央の扁平な部
分を上方に、前記基台2の内側にはめ込まれ、前記基台
2の長手方向に摺動可能に構成される。
The base 2 has a length 142 in this embodiment.
It is formed of a box having an opening of 0 mm, a depth of about 220 mm, and a height of 80 mm, and is normally used by arranging two pieces as a set in front of and behind the soil press-in propulsion device 23.
In the vicinity of one end of the base 2 in the longitudinal direction, a supporting plate 6 to which the sliding operation lever 5 and the sliding portion 9 are attached is attached.
Is provided. Furthermore, in order to insert a lifting pedal 10a of the jack 10 to be described later, a width of about 10 cm and a height of 15 mm from a side direction are provided at the bottom of both ends of the base 2.
Jack insertion opening 2a, 2b cut out by about 60mm
Are provided respectively. In addition, rail grooves 2c and 2d on which wheels of trucks 7 and 8 described later are mounted are provided on an inner bottom portion of the base 2. In the present embodiment, the slide base 3 is formed in a U-shaped cross section, and is fitted into the base 2 with a flat central portion upward and slides in the longitudinal direction of the base 2. It is configured to be possible.

【0012】前記摺動操作レバー5は、一方向の回動す
ることにより、その中心(図示外)に設けられるボルト
アーム9bを回動させる。なお、この摺動操作レバー5
には、噛み合わされる爪の向きを右回転用又は左回転用
に変えることにより、同レバー5を単に前後に(図1に
示すA方向)にのみ回動させるだけで、前記ボルトアー
ム9bが右回転又は左回転のみを行うラチェット手段を
備える。なお、前記押具4は、L字型の金属片からな
り、一面が前記基台2の長手方向側面に予め設けられた
ネジ穴4bにボルト4aで取り付けられ、前記基台2に
はめ込まれた前記摺動台3を摺動可能、かつ、外れない
ように上方から押さえている。
The sliding operation lever 5 rotates in one direction, thereby rotating a bolt arm 9b provided at the center (not shown). This sliding operation lever 5
By changing the direction of the claw to be engaged to the right rotation or the left rotation, the bolt arm 9b can be rotated simply by moving the lever 5 back and forth (direction A shown in FIG. 1) only. Ratchet means for performing only right or left rotation is provided. The pusher 4 is formed of an L-shaped metal piece, one surface of which is attached to a screw hole 4b provided in advance in a longitudinal side surface of the base 2 with a bolt 4a, and is fitted into the base 2. The slide table 3 is slidably pressed from above so as not to come off.

【0013】つぎに、図1、図2を参照して、前記土入
圧入推進装置の設置補正具1の内部に設けられた前記台
車7、8および摺動部9の各構成について説明する。前
記土入圧入推進装置の設置補正具1の内部には、図1お
よび図2から知り得るように、前記摺動台3を載置した
2つの台車7、8を備える。これらのうち、台車7は、
前記摺動台3の一端(図2中、左側)に設けられ、台車
8は、前記摺動操作レバー5側(図2中、右側)に設け
られている。
Next, with reference to FIG. 1 and FIG. 2, each configuration of the bogies 7, 8 and the sliding portion 9 provided inside the installation corrector 1 of the soil-in press-in propulsion device will be described. As can be seen from FIGS. 1 and 2, two carriages 7, 8 on which the slide table 3 is mounted are provided inside the installation correction tool 1 of the soil-in press-in propulsion device. Among these, the cart 7 is
The carriage 8 is provided on one end (the left side in FIG. 2) of the slide table 3, and the carriage 8 is provided on the slide operation lever 5 side (the right side in FIG. 2).

【0014】台車7は、内側に所定の間隔で平行に設け
られる二つの車輪取付部7b、7cを有する下方が開口
した車体7aからなる、そして、該二つの車輪取付部7
b、7cには、それぞれ3つの車輪7d、7d、7
が、前記基台2の底部に設けられたレール溝2c、
2d上に載置される構造を有する。また、該車輪7
、7d、7dは、それぞれ、ボルト7eおよび
ナット7fで構成される車軸により回動可能に前記車輪
取付部7b、7cに取り付けられる。そして、これら車
輪7d、7d、・・、7dの中心部は、図示外の
ベアリングが設けられ、前記基台2の内底部に設けられ
たレール溝2c、2dを滑らかに転がる構成となってい
る。
The carts 7 are provided in parallel at predetermined intervals inside.
The lower side having two wheel mounting portions 7b and 7c to be opened
And the two wheel mounting portions 7
b and 7c each have three wheels 7d1, 7d2, 7
d3A rail groove 2c provided at the bottom of the base 2;
It has a structure mounted on 2d. The wheels 7
d 1, 7d2, 7d3Are bolts 7e and
The wheel is rotatable by an axle composed of a nut 7f.
It is attached to the attachment portions 7b and 7c. And these cars
Wheel 7d1, 7d2, ..., 7d6The center of the
A bearing is provided on the inner bottom of the base 2.
Rail grooves 2c and 2d that roll smoothly
You.

【0015】台車8は、前記台車7と同様の構成である
ので、その詳細は省略する。ただ、この台車8の一側部
(図2において右側)には、上述した摺動操作レバー5
の操作により、前記摺動台3を所定位置に摺動させる摺
動部9が設けられ、対向する側部(図2において左側)
には、貫通穴8eが設けられている。
The trolley 8 has the same configuration as the trolley 7, and the details thereof are omitted. However, one side (right side in FIG. 2) of the cart 8 has the sliding operation lever 5 described above.
Is provided with a sliding portion 9 for sliding the slide table 3 to a predetermined position, and the opposite side portion (the left side in FIG. 2)
Is provided with a through hole 8e.

【0016】該摺動部9は、前記台車8の一端(図2に
おいては右側)に設けられたナットスリーブ9aと、前
記基台2に設けられた支板6に回動可能に取り付けら
れ、ナットスリーブ9aとを螺動するボルトアーム9b
からなる。ナットスリーブ9aとは、中央にネジ穴9c
を有し、前記台車8の一つの側面の略中央部(図2にお
いて右側部)に貫通固定して取り付けられている。
The sliding portion 9 is rotatably mounted on a nut sleeve 9a provided on one end (right side in FIG. 2) of the carriage 8 and a support plate 6 provided on the base 2. Bolt arm 9b for screwing nut sleeve 9a
Consists of The nut sleeve 9a is a screw hole 9c in the center.
And is fixedly penetrated and attached to a substantially central portion (a right side portion in FIG. 2) of one side surface of the carriage 8.

【0017】そして、このナットスリーブ9aおよびボ
ルトアーム9bとは、同じねじ切りが行われ、該ナット
スリーブ9aは、前記ボルトアーム9bとネジ螺合され
ている。したがって、前記基台2に設けられた支板6
に、該ボルトアーム9bのボルトヘッドが、貫通して回
動可能に取り付けられているので、該ボルトアーム9b
が回動すると、その回動に伴って、前記ナットスリーブ
9aが水平方向に移動する。すなわち、前記摺動操作レ
バー5を前面A方向に上下動すると、下に倒したとき、
同方向にボルトアーム9bのネジが前記ナットスリーブ
9aとのネジ穴9cを左螺動し、螺動した長さ分、台車
8(台車8が取り付けられた摺動台3)が左側に摺動
し、上に起こしたとき空回りする。この摺動操作レバー
5をA方向に所定回数上下動することで、台車8(台車
8が取り付けられた摺動台3)が、前記ボルトアーム9
bの長さ範囲内で所望とする位置まで左方向へ摺動す
る。また、前記摺動操作レバー5に設けられた回転切替
スイッチを右回転に切り替えると、摺動操作レバー5を
前面A方向に下に倒すことで、逆方向にボルトアーム9
bのネジが前記ナットスリーブ9aとのネジ穴9cを右
螺動し、螺動した長さ分、台車8(台車8が取り付けら
れた摺動台3)が右側に摺動し、上に起こすとき空回り
をして、これを所定回数上下動することで、台車8(台
車8が取り付けられた摺動台3)が、前記ボルトアーム
9bの長さ範囲内で所望とする位置まで右方向へ摺動す
る。
The same threading is performed on the nut sleeve 9a and the bolt arm 9b, and the nut sleeve 9a is screwed with the bolt arm 9b. Therefore, the support plate 6 provided on the base 2
Since the bolt head of the bolt arm 9b is rotatably mounted therethrough,
When the nut rotates, the nut sleeve 9a moves in the horizontal direction with the rotation. That is, when the sliding operation lever 5 is moved up and down in the direction of the front surface A,
In the same direction, the screw of the bolt arm 9b left-screws the screw hole 9c with the nut sleeve 9a, and the bogie 8 (the slide 3 on which the bogie 8 is attached) slides to the left by the length of the screwing. Then spins up when raised. By moving the sliding operation lever 5 up and down a predetermined number of times in the direction A, the bogie 8 (the sliding base 3 to which the bogie 8 is attached) is moved by the bolt arm 9.
Slide leftward to the desired position within the length range of b. When the rotation changeover switch provided on the sliding operation lever 5 is switched to the right rotation, the sliding operation lever 5 is tilted downward in the direction of the front surface A, so that the bolt arm 9 is moved in the opposite direction.
The screw “b” screw-threads the screw hole 9c with the nut sleeve 9a to the right, and the bogie 8 (the slide 3 on which the bogie 8 is attached) slides to the right by the length of the screwing and raises upward. When the vehicle rotates idly and moves up and down a predetermined number of times, the carriage 8 (the slide base 3 to which the carriage 8 is attached) moves rightward to a desired position within the length range of the bolt arm 9b. Slide.

【0018】前記ジャッキ10は、本実施の形態では、
油圧式の小型軽量のものを使用し、前記基台2のジャッ
キ挿入口2aおよび、またはジャッキ挿入口2bに、ジ
ャッキ10に設けられた起重ペダル10aを挿入し、操
作ハンドル10bを上下動すると、油圧がかかり起重ペ
ダル10aが、約10cmの範囲内で、前記基台2を上
に持ち上げる。また、圧抜きレバー10cを上方向に持
ち上げると油圧が下がり、起重ペダル10aが下がる。
すなわち、前記基台2のジャッキ挿入口2aからジャッ
キ10の起重ペダル10aを挿入して所定高さ位置まで
持ち上げ、同様に前記基台2のジャッキ挿入口2bにジ
ャッキ10の起重ペダル10aを挿入して所定高さ位置
まで持ち上げると、本発明の土入圧入推進装置の設置補
正具1に載置された推進装置23が持ち上げられる構成
となっている。
In the present embodiment, the jack 10 is
When a small and light hydraulic type is used, the lifting pedal 10a provided on the jack 10 is inserted into the jack insertion opening 2a and / or the jack insertion opening 2b of the base 2, and the operation handle 10b is moved up and down. When the hydraulic pressure is applied, the lifting pedal 10a raises the base 2 within a range of about 10 cm. When the pressure release lever 10c is lifted upward, the hydraulic pressure decreases, and the lifting pedal 10a lowers.
That is, the lifting pedal 10a of the jack 10 is inserted from the jack insertion opening 2a of the base 2 and lifted to a predetermined height position. Similarly, the lifting pedal 10a of the jack 10 is inserted into the jack insertion opening 2b of the base 2. When inserted and lifted to a predetermined height position, the propulsion device 23 mounted on the installation correction tool 1 of the soil-filling press-in propulsion device of the present invention is lifted.

【0019】このような土入圧入推進装置の設置補正具
1は、本実施の形態では、1つの重量が約65kgであ
り、1人または2人の作業員で立坑内に容易に運びこむ
ことができる。
In the present embodiment, the installation correction tool 1 for such a soil immersion press-in propulsion device has a weight of about 65 kg and can be easily carried into the shaft by one or two workers. Can be.

【0020】つぎに、上記構成の土入圧入推進装置の設
置補正具1を用いて立坑内底部に推進装置23を設置し
て使用する様子について説明する。図3および図4は、
本発明の一実施の形態に係る土入圧入推進装置の設置補
正具1を二本用いて、前記立坑内底部に搬入された推進
装置23が、この二本の土入圧入推進装置の設置補正具
1の上に載置された様子を示すものであり、このうち、
図3は、その上面図、図4は、同側面図である。、な
お、図3および図4において、推進装置23の先頭側に
設置されるものを設置補正具1、推進装置23の後方
に設置されるものを設置補正具1として説明する。従
来と同様に、道路下に推進管の土入圧入を行うために、
推進部両端に立坑を設ける。そして、上記二本の本実施
の形態に係る土入圧入推進装置の設置補正具1、1
を立坑内底部に搬入する。搬入された設置補正具1
は、土入圧入される推進管の推進方向に対し、該設
置補正具1、1の長手方向が垂直となるように、所
定の間隔をおいて2カ所に設置する。
Next, a description will be given of how the propulsion device 23 is installed and used at the bottom of the shaft using the installation corrector 1 of the above-described construction. FIG. 3 and FIG.
The propulsion device 23 carried into the bottom of the vertical shaft using two installation correction tools 1 of the soil injection press-in propulsion device according to one embodiment of the present invention is used to correct the installation of the two soil injection press-in propulsion devices. It shows a state of being placed on the tool 1, of which
FIG. 3 is a top view thereof, and FIG. 4 is a side view thereof. , In FIGS. 3 and 4, the installation correction device 1 1 are disposed to the head side of the propulsion apparatus 23 will be described are disposed to the rear of the propulsion device 23 as the installation correction instrument 1 2. As before, in order to inject the propulsion pipe into the ground under the road,
Shafts will be provided at both ends of the propulsion section. Then, the installation correctors 11 , 12 of the two digging and press-in propulsion devices according to the present embodiment.
To the bottom of the shaft. Carried-in installed correction device 1 1,
1 2, compared propulsion direction of the propulsion tube to be press-fitted Donyu, as the installed correction device 1 1, 1 2 in the longitudinal direction is perpendicular, installed in two locations at predetermined intervals.

【0021】立坑内底部に本発明の土入圧入推進装置の
設置補正具1、1を設置した後、その上に前記土入
圧入推進装置23をクレーン等で吊り下げて、立坑内に
搬入、設置する。この場合に、立坑の開口部が広けれ
ば、推進装置23を水平に吊り下げてそのまま立坑内に
降ろしながら、設置予定の場所に載置することができる
が、立坑の開口部が広くできない場所では、推進装置2
3を斜めに傾けたりして(図5参照)、立坑内に降ろ
し、先に設置された本実施の形態に係る土入圧入推進装
置の設置補正具1、1上に載置する。
[0021] After placing the installation correction device 1 1, 1 2 of Donyu pressed propulsion apparatus of the present invention in vertical shafts in the bottom, the Donyu press-propulsion devices 23 hung by a crane or the like thereon, in the pit Carry in and install. In this case, if the opening of the shaft is wide, the propulsion device 23 can be suspended horizontally and lowered into the shaft as it is, and can be placed at the place where the shaft is to be installed. , Propulsion device 2
3 and tilting obliquely (see FIG. 5), down into the pit, and placed on the installation correction device 1 1, 1 2 of Donyu press-propulsion device according to the present embodiment installed earlier.

【0022】そして、推進方向に向けて、土入圧入推進
装置23を設置するのであるが、この際に、正しい位置
に設置される場合には問題がないが、前述するように、
設置位置が正しく推進方向に合致していない場合には、
例えば、立坑内に搬入、載置された推進装置23が、推
進管を土入圧入して推進させる方向より、立坑壁面に対
して右寄りに向いていた場合には、先端側の設置補正具
の摺動操作レバー5(図3、図4では図示しない)
を操作して、摺動台3を立坑壁面に対して左(C方
向)に摺動すると、推進装置23の先端側の位置を所定
方向に移動して、推進管の正しい推進方向に修正・補正
することができる。また、推進装置23の設置位置によ
っては、後方側の設置補正具1の摺動台3を立坑壁
面に対して右(D方向)に摺動すると、推進装置23の
先端側は、逆に左(C方向)に向き、推進装置23の向
きを推進管の推進方向に合わせて・修正補正することが
できる。このように、推進装置23が載置された設置補
正具1、1のいずれか、または両方を摺動操作する
ことにより、本実施の形態では、左右各9cmの範囲で
推進装置23の向きを補正することができる。
Then, the digging press-in propulsion device 23 is installed in the propulsion direction. At this time, there is no problem if the device is installed in a correct position.
If the installation position does not match the propulsion direction correctly,
For example, when the propulsion device 23 carried and placed in the shaft is directed rightward with respect to the wall of the shaft from the direction in which the propulsion pipe is immersed and press-fitted, the installation correction tool 1 on the tip side is used. 1 sliding operation lever 5 (not shown in FIGS. 3 and 4)
By operating the, when the slide board 3 1 slides to the left (C direction) with respect to the vertical shaft wall, by moving the position of the tip end of the propulsion device 23 in a predetermined direction, corrected to the correct propulsion direction of the propulsion tube・ Can be corrected. Further, depending on the installation position of the propulsion device 23, when the sliding base 3 2 Installation correcting device 1 2 of the rear side slides right (D direction) with respect to the vertical shaft wall, the tip end of the propulsion device 23, reverse The direction of the propulsion device 23 can be corrected and corrected in accordance with the direction of the propulsion of the propulsion pipe. Thus, by sliding operation of either or both, of the propulsion unit 23 placed correcting device 1 1 placed is 1 2, in the present embodiment, the propulsion device 23 at a range of right and left 9cm The orientation can be corrected.

【0023】また、例えば、推進管は通常、地面に対し
て水平方向より若干上向きに土入圧入されることから、
水平にする場合には、後方の設置補正具1の両側部に
設けられたジャッキ挿入口2aにジャッキ10の起重ペ
ダル10aを挿入して、持ち上げ、推進管を土入圧入し
て推進させる。また、推進装置23が載置される立坑内
底がいづれかに傾いている場合には、下がっている側部
のジャッキ挿入口2a、2bに起重ペダル10aを挿入
して、所望とする位置(10cm以内)まで垂直方向に
持ち上げると、推進装置23が正しい高さ方向に修正・
補正される。
Also, for example, since the propulsion pipe is usually immersed and pressed into the ground slightly upward from the horizontal direction,
When the horizontal, insert the electromotive heavy pedal 10a of the jack 10 to the jack insertion slot 2a provided on both sides of the installation correction device 1 2 of the rear, lifting, propelling the propulsion tube Donyu pressed to . When the bottom of the shaft where the propulsion device 23 is placed is inclined at any angle, the lifting pedal 10a is inserted into the jack insertion openings 2a and 2b on the lower side, and the desired position ( When lifted vertically to within 10 cm), the propulsion device 23 corrects to the correct height.
Will be corrected.

【0024】なお、上記実施の形態では、土入圧入推進
装置の設置補正具1に立坑から推進管を土入圧入する推
進装置の向きを変えものとして説明したが、設置方向を
容易に移動することのできない重量工作物に容易に応用
でき、載置される工作物は特に限定されない。また、載
置される重量機材の大きさ、重量に伴い、本発明の土入
圧入推進装置の設置補正具1は、さらに大きく、摺動範
囲を広くしてもよく、その大きさは特に限定しない。な
お、上記実施の形態では、摺動台に車輪を有する台車を
取り付けて、水平方向に摺動するようにしたが、車輪に
変えて摺動台にレール溝を、基台にレール溝受けを設け
て摺動するようにしてもよい。
Although the above embodiment has been described assuming that the direction of the propulsion device for inserting the propulsion pipe from the shaft into the soil corrector 1 is changed, the installation direction can be easily moved. It can be easily applied to heavy workpieces that cannot be mounted, and the workpieces to be placed are not particularly limited. Also, depending on the size and weight of the heavy equipment to be placed, the installation correction tool 1 of the soil immersion press-in propulsion device of the present invention may be even larger and the sliding range may be widened, and the size is particularly limited. do not do. In the above-described embodiment, the carriage having wheels is mounted on the slide table so as to slide horizontally.However, instead of wheels, rail grooves are provided on the slide table, and rail groove receivers are provided on the base. It may be provided to slide.

【0025】[0025]

【発明の効果】本発明の土入圧入推進装置の設置補正具
によると、ワイヤーロープで吊り下げた推進装置を斜め
にして搬入した場合や、他の水道管、電気ケーブル等が
設けられていた場合に、立坑内底部に設置した後、水
平、垂直の方向を容易に修正・補正することができる。
これにより、立坑の開口部が広くできなかったり、他の
配管と接触しないように狭い開口部から推進装置を搬入
する場合にも、推進装置を分割して立坑内底部で組み立
てるといった作業や作業時間が軽減される。また、本発
明の土入圧入推進装置の設置補正具によると、載置した
土入圧入推進装置を水平、垂直に方向補正ができるた
め、重量が3t〜4tと非常に重い推進装置の設置位置
や方向を、その場で容易に変更することができる。さら
に、本発明の土入圧入推進装置の設置補正具により、推
進装置の設置方向を所望とする方向へ容易に修正・補正
できるため、一の立坑から他の立坑向かって推進管を推
進させる場合にも、所望とする方向へ推進管を正確に土
入圧入できる。
According to the installation correction tool for the soil-in press-in propulsion device of the present invention, when the propulsion device suspended by the wire rope is carried in obliquely, other water pipes, electric cables, etc. are provided. In this case, the horizontal and vertical directions can be easily corrected and corrected after being installed at the bottom of the shaft.
As a result, even when the opening of the shaft cannot be widened, or when the propulsion device is carried in from a narrow opening so as not to contact with other piping, the operation and work time for dividing the propulsion device and assembling it at the bottom of the shaft are Is reduced. Further, according to the installation correction tool of the soil injection press-in propulsion device of the present invention, since the mounted soil injection press-in propulsion device can be corrected in the horizontal and vertical directions, the installation position of the very heavy propulsion device having a weight of 3 to 4 t. And direction can be easily changed on the spot. Furthermore, since the installation correction tool of the soil injection press-in propulsion device of the present invention can easily correct and correct the installation direction of the propulsion device in a desired direction, the propulsion pipe is propelled from one shaft to another shaft. In addition, the propulsion pipe can be accurately pressed into the ground in a desired direction.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施の形態に係る土入圧入推進装置
の設置補正具の外観図である。
FIG. 1 is an external view of an installation correction tool of a soil-intrusion press-in propulsion device according to an embodiment of the present invention.

【図2】本発明の一実施の形態に係る土入圧入推進装置
の設置補正具の側面図、断面図である。
FIG. 2 is a side view and a cross-sectional view of an installation correction tool of the soil injection press-in propulsion device according to the embodiment of the present invention.

【図3】本発明の一実施の形態に係る土入圧入推進装置
の設置補正具により、土入圧入推進装置の水平方向を変
える様子の説明図である。
FIG. 3 is an explanatory diagram showing a state where the horizontal direction of the soil injection press-in propulsion device is changed by the installation correction tool of the soil injection press-in propulsion device according to one embodiment of the present invention.

【図4】本発明の一実施の形態に係る土入圧入推進装置
の設置補正具により、土入圧入推進装置の垂直方向を変
える様子の説明図である。
FIG. 4 is an explanatory view showing a state in which the vertical direction of the soil injection press-in propulsion device is changed by the installation correction tool of the soil injection press-in propulsion device according to one embodiment of the present invention.

【図5】従来の土入圧入推進装置を立坑内に搬入・設置
する様子の説明図である。
FIG. 5 is an explanatory view showing a state in which a conventional soil injection press-in propulsion device is carried in and installed in a shaft.

【符号の説明】[Explanation of symbols]

1・・土入圧入推進装置の設置補正具 2・・基台 3・・摺動台 4・・押具 5・・摺動操作レバー 6・・支板 7、8・・台車 9・・摺動部 10・・ジャッキ 23・・推進装置 1 ·························································································································································· Sliding 9 Moving part 10. Jack 23. Propulsion device

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 昭55−98596(JP,A) 特開 昭63−236894(JP,A) 実開 昭52−49504(JP,U) 実開 昭61−159492(JP,U) 実公 昭48−15934(JP,Y1) (58)調査した分野(Int.Cl.7,DB名) E21D 9/06 311 ──────────────────────────────────────────────────続 き Continuation of the front page (56) References JP-A-55-98596 (JP, A) JP-A-63-236894 (JP, A) Fully open 52-49504 (JP, U) Really open 159492 (JP, U) Jiko 48-15934 (JP, Y1) (58) Field surveyed (Int. Cl. 7 , DB name) E21D 9/06 311

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 地中内に水平方向に推進管を土入圧入す
る土入圧入推進装置の設置する際に使用する同装置の位
置補正具において、 上方が開口する基台内で、前記土入圧入推進装置を載置
したまま所定方向に摺動する摺動台と、 該摺動台下部に所定の間隔で平行に設けられる二つの車
輪取付部にそれぞれ車軸およびベアリング軸受けを介し
て複数の車輪が取り付けられた一または二以上の車体
と、 前記複数の車輪が載置される前記基台の内底部上に設け
られるレール溝と、 前記車体のうちの少なくとも一方に取り付けられるネジ
切り構造を有するナットスリーブおよび該ナットスリー
ブと同じネジ切り構造を有し、互いにネジ螺合されるボ
ルトアームとからなり、該ボルトアームの回動により、
前記ナットスリーブが水平方向に移動する摺動部と、 前記ボルトアームを前記基台に回動可能に固定する支板
と、 前記ボルトアームに対向して支板に設けられ、回転切替
手段の切り替えにより、前記ボルトアームを一方向にの
み回動させるラチェット手段を備えた摺動操作レバー
と、 からなることを特徴とする土入圧入推進装置の設置補正
具。
1. A position correction tool for use in installing a soil immersion press-in propulsion device for immersing a propulsion pipe in a horizontal direction in the ground, comprising: A plurality of sliding bases which slide in a predetermined direction with the press-fitting propulsion device mounted thereon, and a plurality of wheel mounting parts provided in parallel at a predetermined interval below the sliding bases via an axle and a bearing. One or more vehicle bodies with wheels mounted thereon, a rail groove provided on an inner bottom of the base on which the plurality of wheels are mounted, and a threaded structure mounted on at least one of the vehicle bodies. A nut sleeve having the same thread cutting structure as the nut sleeve, and comprising a bolt arm screwed to each other, and by rotation of the bolt arm,
A sliding portion in which the nut sleeve moves in the horizontal direction; a support plate for rotatably fixing the bolt arm to the base; and a support plate provided on the support plate facing the bolt arm, and switching of rotation switching means. And a sliding operation lever provided with a ratchet means for rotating the bolt arm in only one direction.
【請求項2】 前記基台の長尺両側端底部に設けられた
ジャッキ挿入口と、 このジャッキ挿入口に、その起重ペダルが挿入され、前
記基台位置を垂直方向に移動するジャッキと、 からなることを特徴とする前記請求項1に記載の土入圧
入推進装置の設置補正具。
2. A jack insertion port provided at the bottom of each of the long sides of the base, and a jack, into which the lifting pedal is inserted, and which vertically moves the position of the base. The installation correction tool for a soil-injection and propulsion device according to claim 1, wherein the installation correction tool comprises:
JP07320399A 1999-03-18 1999-03-18 Correction tool for installation of soil injection press-in propulsion device Expired - Fee Related JP3340694B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP07320399A JP3340694B2 (en) 1999-03-18 1999-03-18 Correction tool for installation of soil injection press-in propulsion device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP07320399A JP3340694B2 (en) 1999-03-18 1999-03-18 Correction tool for installation of soil injection press-in propulsion device

Publications (2)

Publication Number Publication Date
JP2000265783A JP2000265783A (en) 2000-09-26
JP3340694B2 true JP3340694B2 (en) 2002-11-05

Family

ID=13511367

Family Applications (1)

Application Number Title Priority Date Filing Date
JP07320399A Expired - Fee Related JP3340694B2 (en) 1999-03-18 1999-03-18 Correction tool for installation of soil injection press-in propulsion device

Country Status (1)

Country Link
JP (1) JP3340694B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010187892A (en) * 2009-02-18 2010-09-02 Sansei R&D:Kk Game machine

Also Published As

Publication number Publication date
JP2000265783A (en) 2000-09-26

Similar Documents

Publication Publication Date Title
KR101447509B1 (en) Cable installing device used for apparatus and method for installing underground cable
JPS637121A (en) Method and apparatus for installing cable in conduit
AU2011200659A1 (en) Handling device and method
JP3340694B2 (en) Correction tool for installation of soil injection press-in propulsion device
JP2008088643A (en) Underground multistory parking lot for bicycle
CN110053936B (en) Pipeline conveying device and pipeline conveying method
JP2003239366A (en) Concrete block transporter
CN115057368A (en) Pipeline installation equipment and method for underground pipeline
JP4236761B2 (en) Pipe-type carriage for transporting pipes
JP5399111B2 (en) Method and apparatus for laying heavy objects
JP3139935B2 (en) Pipe handling equipment
CN218940585U (en) Communication pipeline on-site protection device
JPS63255424A (en) Construction of piping in tunnel and vehicle therefor
CN111006068A (en) Large steel pipe transportation welding alignment tool car and use method thereof
CN220353539U (en) Telegraph pole burying device for electric power construction
CN220953428U (en) Tool for preventing foundation pit collapse in municipal engineering
JPS5833956B2 (en) Large pipe laying method in tunnels and large pipe laying trolley used in the method
JPH08338567A (en) Burying process for gas pipe line
JP6719110B1 (en) Underground structure transportation device and underground structure transportation method in excavation method
CN219601304U (en) Electrician material conveying device
CN221150917U (en) Cable cross-road rolling-preventing protection device
JPH06288189A (en) Laying method for portal culvert
JPH0110098Y2 (en)
KR100426802B1 (en) Steel pipe moving apparatus in water tunnel
JP2001262571A (en) Penetration method for rotary pile

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20020730

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070816

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080816

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080816

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090816

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100816

Year of fee payment: 8

LAPS Cancellation because of no payment of annual fees