JP3245753B2 - Slope stabilization method - Google Patents
Slope stabilization methodInfo
- Publication number
- JP3245753B2 JP3245753B2 JP02161093A JP2161093A JP3245753B2 JP 3245753 B2 JP3245753 B2 JP 3245753B2 JP 02161093 A JP02161093 A JP 02161093A JP 2161093 A JP2161093 A JP 2161093A JP 3245753 B2 JP3245753 B2 JP 3245753B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- anchor
- slope
- formwork
- mold
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、斜面上に鉄筋コンクリ
−ト梁を設置して斜面の安定化を図る工法に関するもの
である。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for stabilizing a slope by installing a reinforced concrete beam on the slope.
【0002】[0002]
【従来の技術】従来の斜面の安定化工法は、次のような
種々の方法により行われている。 <イ>斜面上に、人力により鉄筋および型枠を組み立て
た後、コンクリ−トを打設してアンカ−で定着する方
法。2. Description of the Related Art A conventional slope stabilization method is performed by the following various methods. <A> A method of assembling a reinforcing bar and a formwork on a slope by manpower, then pouring concrete and fixing with an anchor.
【0003】<ロ>斜面上に鉄筋および金網型枠を組み
立てた後、コンクリ−トを吹き付けて施工する方法。<B> A method of assembling a reinforcing bar and a wire mesh form on a slope, and then spraying concrete to perform the construction.
【0004】<ハ>斜面上に工場作製したコンクリ−ト
ブロック体を設置して、アンカ−で定着する方法。<C> A method of setting a concrete block body manufactured on a slope on a slope and fixing the concrete block with an anchor.
【0005】[0005]
【発明が解決しようとする課題】上記の従来技術には、
次のような問題点が存在する。 (1)上記<イ>の工法は、斜面上で人力により鉄筋お
よび型枠を組み立てるため、作業が煩雑であり、多大の
費用がかかる。特に、岩盤の切取斜面では地山の凹凸が
顕著であり、その凹凸に合わせて型枠を作製する必要が
あるため、型枠加工が複雑であると共に、型枠を他の施
工場所に転用することができず、省資源の観点からも問
題である。SUMMARY OF THE INVENTION The above prior arts include:
The following problems exist. (1) In the method <A>, since the reinforcing bar and the formwork are assembled manually on a slope, the work is complicated and a large cost is required. Especially, in the cut slope of the bedrock, the unevenness of the ground is remarkable, and it is necessary to manufacture the formwork according to the unevenness, so that the formwork processing is complicated and the formwork is diverted to another construction site. This is a problem from the viewpoint of resource saving.
【0006】(2)上記<ロ>のコンクリ−ト吹き付け
工法は高価であり、しかも打設作業に時間がかかる。(2) The concrete spraying method described in <b> is expensive and requires a long time for the casting operation.
【0007】(3)上記<ハ>のコンクリ−トブロック
体を用いた方法の場合は、ブロック体底面と斜面との間
の隙間を完全に無くすことは事実上困難であるため、そ
の隙間から雨水等が侵入し、アンカ−を腐食させる原因
となる。また、ブロック体は地山との密着性が低いの
で、仮にアンカ−が切断した場合、ブロック体が斜面上
から滑落する危険性がある。さらに、凹凸のある地山で
はアンカ−の緊張による支圧力が地山の凸部に集中荷重
として働いてしまい、ブロック体が破壊する危険性があ
る。(3) In the case of the method using the concrete block of <c>, since it is practically difficult to completely eliminate the gap between the bottom of the block and the slope, rainwater flows from the gap. Etc. may enter and cause corrosion of the anchor. Further, since the block body has low adhesion to the ground, if the anchor is cut, there is a risk that the block body will slide down from the slope. Further, in the case of an uneven ground, the bearing force due to the tension of the anchor works as a concentrated load on the convex portion of the ground, and there is a risk that the block body is broken.
【0008】[0008]
【本発明の目的】本発明は、上記のような問題点を解決
するためになされたもので、施工の省力化、アンカ−の
腐食防止、地山との一体性の確保、施工の安全性を図る
ことができる斜面安定化工法を提供することを目的とす
る。SUMMARY OF THE INVENTION The object of the present invention is to solve the above-mentioned problems and to save labor for construction, prevent corrosion of anchors, ensure integrity with the ground, and secure construction. It is an object of the present invention to provide a slope stabilization method capable of achieving the following.
【0009】[0009]
【課題を解決するための手段】本発明は、天板と側板と
底部シ−トによりコンクリ−トの打設空間を形成し、こ
の打設空間内部に鉄筋を組み込み、かつアンカ−の貫通
孔を設けた型枠を、地山に定着したアンカ−の頭部を前
記貫通孔に貫通させて斜面に配置し、型枠内にコンクリ
−トを打設し、硬化後に脱型して鉄筋コンクリ−ト梁を
作製した後、アンカ−を緊張して緊張力を鉄筋コンクリ
−ト梁を介して地山に伝達して行う、斜面安定化工法で
ある。According to the present invention, a space for placing concrete is formed by a top plate, a side plate and a bottom sheet, a reinforcing bar is incorporated in the space for placing concrete, and a through hole for an anchor is provided. The formwork provided with the anchor is fixed to the ground, the head of the anchor is penetrated through the through-hole, and placed on the slope, and a concrete is poured into the formwork, and after hardening, it is released from the mold to reinforce the concrete. This is a slope stabilization method in which, after the beam is made, the anchor is tensioned to transmit the tension to the ground through the reinforced concrete beam.
【0010】[0010]
【実施例】以下、図面を参照しながら、本発明の一実施
例について説明する。 <イ>型枠の構造(図1) 型枠1は、天板11と側板12と底部シ−ト13により
コンクリ−トの打設空間を形成し、この打設空間内部に
鉄筋17を組み込み、かつアンカ−の貫通孔13を設け
た構造であり、工場でこれらを一体に作製したものであ
る。An embodiment of the present invention will be described below with reference to the drawings. <A> Structure of Formwork (FIG. 1) The formwork 1 forms a concrete casting space by the top plate 11, the side plate 12, and the bottom sheet 13, and the reinforcing bar 17 is incorporated inside the casting space. And a structure in which anchor through-holes 13 are provided, and these are integrally formed in a factory.
【0011】(1)天板、側板 天板11と、面対向する二枚の側板12により逆U字状
の上型枠を形成する。天板11及び側板12は、鉄板、
合板、プラスチック板等の剛性を有する板材を使用す
る。図1は逆U字状に上型枠を形成した場合を示してい
るが、逆U字状だけでなく、コンクリ−ト梁の断面形状
に合わせた形状に適宜作製する。また、図1は直線状の
型枠の場合であるが、十字状や多方向形状の型枠を作製
する場合もある。(1) Top plate, side plate A top plate 11 and two side plates 12 facing each other form an upper U-shaped upper frame. The top plate 11 and the side plate 12 are iron plates,
Use a rigid plate material such as plywood or plastic plate. FIG. 1 shows a case in which the upper mold frame is formed in an inverted U-shape, but the upper mold is not only formed in an inverted U-shape but is appropriately formed in a shape corresponding to the cross-sectional shape of the concrete beam. Although FIG. 1 shows a case of a linear mold, a cross or a multidirectional mold may be produced.
【0012】(2)貫通孔 貫通孔13は、天板11の中央部に鉛直方向に貫通させ
たアンカ−の挿入孔である。例えば、管体を型枠1内に
取り付け、その端部を天板11の中央に開口させる構造
が考えられる。この貫通孔13の径は、少なくともアン
カ−の径よりも大きいものとする。(2) Through-hole The through-hole 13 is an insertion hole for an anchor penetrating vertically through the center of the top plate 11. For example, a structure is conceivable in which a tubular body is mounted in the mold 1 and an end of the tubular body is opened in the center of the top plate 11. The diameter of the through hole 13 is at least larger than the diameter of the anchor.
【0013】(3)底部シ−ト 底部シ−ト14は、両側板12の下端部間にゆとりを持
たせて取り付けた可撓性のシ−トである。この底部シ−
ト14は、両側部15をコンクリ−トの透過しない素材
で形成し、中央部16をコンクリ−トの透過する素材で
形成してある。例えば、側部15の素材には織布や不織
布等を使用し、中央部16の素材には網体等を使用す
る。そのほか中央部16は、側部15間に紐体を横断さ
せる構造や、側部15と同一の素材に開口を設けた構造
でも良い。(3) Bottom Sheet The bottom sheet 14 is a flexible sheet attached with a space between the lower end portions of both side plates 12. This bottom sheet
In the case 14, both sides 15 are formed of a material which does not transmit concrete, and a central portion 16 is formed of a material which transmits concrete. For example, a woven or non-woven fabric is used for the material of the side portion 15, and a net or the like is used for the material of the central portion 16. In addition, the central portion 16 may have a structure in which the cord body is crossed between the side portions 15 or a structure in which an opening is provided in the same material as the side portion 15.
【0014】(4)鉄筋 鉄筋17は、鉄筋コンクリ−ト梁に必要な量を、天板1
1と側板12と底部シ−ト13により形成したコンクリ
−トの打設空間内に、予め工場において組み込んでお
く。鉄筋17の組み込み方法は、例えば、側板12間に
ロッドを架設し、このロッドに接合する方法などが考え
られる。(4) Reinforcing bar The reinforcing bar 17 is provided in the top plate 1 in an amount necessary for a reinforcing bar concrete beam.
The concrete is installed in a factory in advance in a concrete casting space formed by the side plate 1, the side plate 12 and the bottom sheet 13. As a method of assembling the reinforcing bar 17, for example, a method in which a rod is provided between the side plates 12 and joined to the rod may be considered.
【0015】<ロ>アンカ−の定着、型枠の配置(図
2) 図2に示すように、施工対象の地山にアンカ−2を定着
する。次に、斜面から露出するアンカ−2の頭部を貫通
孔13内に貫通させて、上記のように構成した型枠1を
斜面上に配置する。型枠1の配置は、このように斜面上
に置くだけで完了する。<B> Fixing of anchor and arrangement of formwork (FIG. 2) As shown in FIG. 2, anchor 2 is fixed to the ground to be constructed. Next, the head of the anchor-2 exposed from the slope is penetrated into the through hole 13, and the mold 1 configured as described above is arranged on the slope. The arrangement of the mold 1 is completed simply by placing it on the slope in this way.
【0016】<ハ>コンクリ−トの打設(図3) 斜面上に配置された型枠1内にコンクリ−ト3を打設す
る。その結果、底部シ−ト14の可撓性により、コンク
リ−ト3は地山の凹凸に馴染んで充填され、コンクリ−
ト梁と地山との密着性を高めることができる。また、底
部シ−ト14の両側部15はコンクリ−ト3が透過しな
いため、外部にコンクリ−ト3が流出するのを規制で
き、中央部16ではコンクリ−ト3が透過して直接斜面
に接触するため、密着性が高められる。このとき、型枠
1はアンカ−2により係止されるため、滑落するおそれ
はない。 そして、コンクリ−ト3の養生、硬化後、天
板11と側板12のみを脱型し、鉄筋コンクリ−ト梁を
構築する。<C> Casting concrete (FIG. 3) Concrete 3 is cast in the formwork 1 arranged on the slope. As a result, the flexibility of the bottom sheet 14 allows the concrete 3 to be filled with the unevenness of the ground and filled.
The adhesion between the beam and the ground can be improved. Also, since the concrete 3 does not pass through the both sides 15 of the bottom sheet 14, the concrete 3 can be prevented from flowing out to the outside. Due to the contact, the adhesion is enhanced. At this time, since the mold 1 is locked by the anchor 2, there is no possibility of slipping. Then, after curing and hardening of the concrete 3, only the top plate 11 and the side plate 12 are removed from the mold to construct a reinforced concrete beam.
【0017】<ニ>アンカ−の緊張 型枠1の貫通孔13から露出するアンカ−2の頭部をジ
ャッキ等により把持し、引っ張ってアンカ−2を緊張す
る。そして、アンカ−2の頭部を鉄筋コンクリ−ト梁上
面に定着具により定着する。 これによって、緊張力を
鉄筋コンクリ−ト梁に伝達でき、斜面の安定化を図るこ
とができる。<D> Tension of the anchor The head of the anchor-2 exposed from the through hole 13 of the mold frame 1 is gripped by a jack or the like, and pulled to tension the anchor-2. Then, the head of the anchor-2 is fixed to the upper surface of the reinforced concrete beam by a fixing tool. Thus, the tension can be transmitted to the reinforced concrete beam, and the slope can be stabilized.
【0018】[0018]
【本発明の効果】本発明は以上説明したようになるた
め、次のような効果を得ることができる。 <イ>型枠内には鉄筋も組み込まれており、斜面上に置
くだけで配置を完了することができる。そのため、斜面
上での鉄筋及び型枠の組み立て作業を省略でき、著しい
施工の省力化を達成することができる。また、複雑な作
業がないため、熟練工が不要であり、機械化施工が可能
となる。Since the present invention has been described above, the following effects can be obtained. <B> Reinforcing bars are also incorporated in the formwork, and the placement can be completed simply by placing them on the slope. Therefore, the work of assembling the reinforcing bar and the formwork on the slope can be omitted, and remarkable labor saving in construction can be achieved. In addition, since there is no complicated work, a skilled worker is not required, and mechanized construction can be performed.
【0019】<ロ>型枠底部にシ−トを用いたため、地
山の凹凸に馴染んでコンクリ−トが打設される。従っ
て、コンクリ−ト梁と地山との密着性を高めることがで
き、滑落や破損などの無い安全な施工が可能となる。<B> Since a sheet is used at the bottom of the formwork, the concrete is cast in conformity with the unevenness of the ground. Therefore, the adhesion between the concrete beam and the ground can be enhanced, and safe construction without slipping or breakage can be achieved.
【0020】<ハ>コンクリ−ト梁と地山との密着性が
高いため、雨水等の侵入を遮断することができ、アンカ
−の腐食を防止することができる。<C> Since the adhesion between the concrete beam and the ground is high, it is possible to block the intrusion of rainwater or the like and to prevent corrosion of the anchor.
【0021】<ニ>型枠底部はシ−トで形成するため、
コストが安くなる。また、型枠上部の天板と側板は、他
の施工場所に転用することができるため、省資源の観点
から有効である。<D> Since the bottom of the formwork is formed by a sheet,
Lower costs. In addition, the top plate and side plate on the upper part of the formwork can be diverted to another construction site, which is effective from the viewpoint of resource saving.
【図1】 型枠構造の説明図FIG. 1 is an explanatory view of a formwork structure.
【図2】 型枠を斜面上に配置した状態の説明図FIG. 2 is an explanatory view of a state where a formwork is arranged on a slope.
【図3】 型枠内にコンクリ−トを打設した状態の説明
図FIG. 3 is an explanatory view of a state where concrete is cast in a formwork.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 長岡 信玄 東京都台東区元浅草1−6−12 フリ− 工業株式会社内 (72)発明者 永田 幸嗣 東京都台東区元浅草1−6−12 フリ− 工業株式会社内 (56)参考文献 特開 昭61−72124(JP,A) 特開 平2−8417(JP,A) 特開 平3−161615(JP,A) (58)調査した分野(Int.Cl.7,DB名) E02D 17/20 104 ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Shingen Nagaoka 1-6-12 Moto Asakusa, Taito-ku, Tokyo Free Industry Co., Ltd. (72) Inventor Koji Nagata 1-6-12 Moto-Asakusa, Taito-ku, Tokyo -Within Industrial Co., Ltd. (56) References JP-A-61-72124 (JP, A) JP-A-2-8417 (JP, A) JP-A-3-161615 (JP, A) (58) Fields investigated ( Int.Cl. 7 , DB name) E02D 17/20 104
Claims (2)
トの打設空間を形成し、この打設空間内部に鉄筋を組み
込み、かつ管体からなるアンカ−の貫通孔を設けた型枠
を、 地山に定着したアンカ−の頭部を前記貫通孔に貫通させ
て斜面に配置し、 型枠内にコンクリ−トを打設し、硬化後に脱型して鉄筋
コンクリ−ト梁を作製した後、アンカ−を緊張して緊張
力を鉄筋コンクリ−ト梁を介して地山に伝達して行う、
斜面安定化工法。(1) Concrete by a top plate, a side plate and a bottom sheet.
Forming a intercluster of hitting設空, embedded rebar therein between the droplet設空and anchor consisting tube - the through-hole of the head - a mold having a through hole, the anchor was fixed on natural ground of The concrete is cast into a formwork, and after hardening, it is released from the mold to produce a reinforced concrete beam, and then the anchor is tensioned to reduce the tension in the reinforced concrete. It is transmitted to the ground via beams,
Slope stabilization method.
しない素材で形成し、中央部はコンクリ−トの透過する
素材で形成した型枠を用いた請求項1記載の斜面安定化
工法。2. The slope stabilizing method according to claim 1, wherein both sides of the bottom sheet are formed of a material through which concrete does not penetrate, and a center portion is formed by a mold formed of a material through which concrete passes. Law.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP02161093A JP3245753B2 (en) | 1993-01-18 | 1993-01-18 | Slope stabilization method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP02161093A JP3245753B2 (en) | 1993-01-18 | 1993-01-18 | Slope stabilization method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06212639A JPH06212639A (en) | 1994-08-02 |
JP3245753B2 true JP3245753B2 (en) | 2002-01-15 |
Family
ID=12059814
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP02161093A Expired - Fee Related JP3245753B2 (en) | 1993-01-18 | 1993-01-18 | Slope stabilization method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3245753B2 (en) |
-
1993
- 1993-01-18 JP JP02161093A patent/JP3245753B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH06212639A (en) | 1994-08-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6679649B1 (en) | Barrier wall apparatus and method of construction | |
JP3245753B2 (en) | Slope stabilization method | |
JP3707006B2 (en) | New method for opening openings in existing masonry walls | |
JP3029411U (en) | Formwork attachment device for forming concrete bands and lintels | |
JP3665805B2 (en) | Slope stabilization method | |
JPH0657952A (en) | Anchoring structure of main reinforcing bar | |
JPH03281855A (en) | Floor framing construction for building | |
JPH10317381A (en) | Structure for protecting face of slope by retaining wall and method for constructing the same | |
JPH04128424A (en) | Method for constructing anchor supporting beam | |
JP2754523B2 (en) | Slope stabilization method | |
JP2709346B2 (en) | Block for legal framework | |
JP3459184B2 (en) | Formwork support | |
JP4059413B2 (en) | Formwork mounting apparatus for building a frame and method for building a frame using the same | |
JP4116794B2 (en) | Slope reinforcement structure | |
JPH09165861A (en) | Precast concrete plate and its joining method | |
KR100200474B1 (en) | Stiffening method of the concrete beam | |
JPH01226943A (en) | Slip prevention of beam main-reinforcement at joint section of column and beam in reinforced concrete structure | |
JP2719991B2 (en) | Construction method of slope protection structure | |
JPH0674590B2 (en) | Block for building legal framework and method for building legal framework | |
JP3091180B2 (en) | Legal frame, frame used for legal frame, and legal frame construction method | |
JP3843239B2 (en) | Member connection method | |
JP3678484B2 (en) | Reinforcement structure and reinforcement method for underfloor ventilation hole | |
JP2922789B2 (en) | Formwork, its manufacturing method and slope stabilization method | |
JPH05295742A (en) | Method for constructing concrete blocks and concrete slope frame | |
JPH03132544A (en) | Setting of precast beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081102 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091102 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101102 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101102 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111102 Year of fee payment: 10 |
|
LAPS | Cancellation because of no payment of annual fees |