JP3233183B2 - Drilling equipment - Google Patents

Drilling equipment

Info

Publication number
JP3233183B2
JP3233183B2 JP04917694A JP4917694A JP3233183B2 JP 3233183 B2 JP3233183 B2 JP 3233183B2 JP 04917694 A JP04917694 A JP 04917694A JP 4917694 A JP4917694 A JP 4917694A JP 3233183 B2 JP3233183 B2 JP 3233183B2
Authority
JP
Japan
Prior art keywords
bit
jig
drive shoe
nut
pin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP04917694A
Other languages
Japanese (ja)
Other versions
JPH07259090A (en
Inventor
正弘 籾山
和彦 井上
雅一 藤田
正信 真居
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tobishima Corp
Original Assignee
Tobishima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tobishima Corp filed Critical Tobishima Corp
Priority to JP04917694A priority Critical patent/JP3233183B2/en
Publication of JPH07259090A publication Critical patent/JPH07259090A/en
Application granted granted Critical
Publication of JP3233183B2 publication Critical patent/JP3233183B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、アースアンカーの施工
に用いる削孔装置の改良に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an improvement in a drilling device used for installing an earth anchor.

【0002】[0002]

【従来の技術】擁壁や橋脚の転倒防止、或いはドック床
板の浮力防止や地スベリ防止等の目的で、従来、アース
アンカー工法が広く用いられている。
2. Description of the Related Art Conventionally, an earth anchor method has been widely used for the purpose of preventing falling of a retaining wall or a pier, prevention of buoyancy of a dock floor plate and prevention of ground slippage.

【0003】このアースアンカー工法は、削孔機に接続
したケーシング管内に削孔用水を注入し乍ら地盤をケー
シング管先端の削孔ビットで削孔し、削孔したアンカー
孔にアンカーケーブル(鋼線)を挿入した後、グラウト
材をアンカー孔内に加圧注入し乍らケーシング管を引き
抜いて地盤中にアンカー体を造成していくことにより地
盤と構造物との連結を図るもので、ケーシング管は削孔
深さに応じて順次接続される。
In this earth anchor method, the ground is drilled with a drill bit at the tip of the casing pipe while pouring water is injected into a casing pipe connected to a drilling machine, and an anchor cable (steel) is inserted into the drilled anchor hole. After inserting the grout material into the anchor hole, the casing tube is pulled out and an anchor body is formed in the ground to connect the ground and the structure. The pipes are connected sequentially according to the drilling depth.

【0004】而して、従来、軟弱地盤でアースアンカー
を施工する場合、使捨てビットの一つとしてクローネン
ビットが広く使用されている。図13に示すように、ク
ローネンビット1はケーシング管3の挿入側先端に螺着
されるドライブシュー5を介してケーシング管3に装着
され、ドライブシュー5に挿入される筒状部1aとドラ
イブシュー5の先端に配置される頭部1bとで構成され
ている。そして、筒状部1aをドライブシュー5に挿入
し乍ら、頭部1bの後端に設けた切欠き部7をドライブ
シュー5先端の切欠き部9に軸方向(削孔方向)に噛み
合わせてドライブシュー5に接続することで、削孔時に
ケーシング管3の回転がクローネンビット1に伝わるよ
うになっている。
[0004] Conventionally, when an earth anchor is constructed on soft ground, a kronen bit has been widely used as one of disposable bits. As shown in FIG. 13, the kronen bit 1 is mounted on the casing tube 3 via a drive shoe 5 screwed to the insertion-side end of the casing tube 3, and the tubular portion 1 a inserted into the drive shoe 5 and the drive And a head 1b arranged at the tip of the shoe 5. Then, while inserting the cylindrical portion 1a into the drive shoe 5, the notch 7 provided at the rear end of the head 1b is engaged with the notch 9 at the tip of the drive shoe 5 in the axial direction (hole drilling direction). By connecting to the drive shoe 5, the rotation of the casing tube 3 is transmitted to the kronen bit 1 during drilling.

【0005】そして、グラウト材を注入し乍らケーシン
グ管3を引き抜くと、クローネンビット1はドライブシ
ュー5と離脱してアンカー孔内に残され、グラウト材に
よって埋没されるようになっている。尚、図中、11は
削孔用水の噴出孔である。
When the casing tube 3 is pulled out while pouring the grout material, the kronen bit 1 is separated from the drive shoe 5 and is left in the anchor hole, and is buried by the grout material. In the figure, reference numeral 11 denotes a hole for drilling water.

【0006】又、その他の使捨てビットとドライブシュ
ーとの接続構造としては、図14及び図15に示すよう
に、地盤13の削孔に当たり、先端インナービット15
とドライブシュー17の周壁に夫々設けたピン挿通孔1
9,21にピン23を挿通させて、先端インナービット
15をドライブシュー17に連結する方法も知られてい
る。尚、図14中、25は先端インナービット15とド
ライブシュー17との間をシールするO−リング、27
はドライブシュー17の先端に接続されたアウタビッ
ト、そして、図15中、29は後述するインナーケーシ
ングである。
As another connection structure between the disposable bit and the drive shoe, as shown in FIG. 14 and FIG.
And pin insertion holes 1 provided in the peripheral wall of drive shoe 17 respectively
A method is also known in which the pins 23 are inserted through the pins 9 and 21 to connect the inner bit 15 to the drive shoe 17. In FIG. 14, reference numeral 25 denotes an O-ring which seals between the tip inner bit 15 and the drive shoe 17;
Is an outer bit connected to the tip of the drive shoe 17, and 29 in FIG. 15 is an inner casing described later.

【0007】[0007]

【発明が解決しようとする課題】ところで、地盤の削孔
時に削孔ビットが硬い岩盤に突き当たったような場合
や、砂礫層や締まった砂層のように削孔に伴いケーシン
グ管が締め付けられる地層に於ては、ケーシング管をフ
ラッシング動作させて削孔ビットに打撃力を与え、又、
ケーシング管のフラッシング動作でケーシング管外周の
スライムを排除し乍ら地盤を掘り進めていく必要があ
る。
By the way, when a drill bit hits hard rock during drilling of the ground, or when the casing pipe is tightened along with the drilling like a gravel layer or a tight sand layer. In this case, the casing tube is flushed to give a hitting force to the drill bit,
It is necessary to excavate the ground while eliminating the slime on the outer periphery of the casing pipe by the flushing operation of the casing pipe.

【0008】然し乍ら、図13に示すクローネンビット
1とドライブシュー5との接続構造では、ケーシング管
3をフラッシング動作させることによってクローネンビ
ット1がドライブシュー5から離脱してしまい、又、一
旦外れたクローネンビット1をドライブシュー5に接続
するのは困難で、フラッシング動作が可能なクローネン
ビットとドライブシューの接続構造が望まれていた。
However, in the connection structure of the kronen bit 1 and the drive shoe 5 shown in FIG. 13, the kronen bit 1 is detached from the drive shoe 5 by flushing the casing tube 3 and once detached. It is difficult to connect the Kronen bit 1 to the drive shoe 5 and a connection structure between the Kronen bit and the drive shoe that can perform a flushing operation has been desired.

【0009】一方、図14及び図15に示した接続構造
では、先端インナービット15がピン23を介してドラ
イブシュー17に連結されているため、ケーシング管の
フラッシング動作は可能である。
On the other hand, in the connection structure shown in FIGS. 14 and 15, since the tip inner bit 15 is connected to the drive shoe 17 via the pin 23, the casing tube can be flushed.

【0010】然し、斯かる従来例にあっては、削孔を終
えてケーシング管を引き抜く場合に、図15に示すよう
に地上から複数のインナーケーシング29を順次螺着し
乍ら全長に亘って挿入した後、これに打撃力を加えてピ
ン23を切断し先端インナービット15とドライブシュ
ー17の連結を解除するものであるため、インナーケー
シング29の挿入,回収時の螺着脱に手間がかかる欠点
が指摘されていた。
However, in such a conventional example, when the casing tube is pulled out after drilling, a plurality of inner casings 29 are sequentially screwed from the ground as shown in FIG. After the insertion, the striking force is applied to the pin 23 to cut the pin 23 to release the connection between the tip inner bit 15 and the drive shoe 17. Was pointed out.

【0011】然も、ピン23を切断するインナーケーシ
ング29の打撃の勢いでO−リング25が先端インナー
ビット15の下端側へずれてしまう虞があり、斯様にO
−リング25が下端側へずれてしまうと、地盤13が被
圧水層等の場合、ピン挿通孔19から水や砂がドライブ
シュー17やケーシング管内へ流入してアースアンカー
の施工に支障を来してしまう不具合もあった。
The O-ring 25 may be displaced toward the lower end of the inner bit 15 by the impact of the inner casing 29 that cuts the pin 23.
-If the ring 25 is displaced to the lower end side, when the ground 13 is a water layer to be pressurized, water or sand flows into the drive shoe 17 or the casing pipe from the pin insertion hole 19 and hinders the construction of the ground anchor. There was also a problem that did.

【0012】本発明は斯かる実情に鑑み案出されたもの
で、アンカー孔の削孔時にケーシング管のフラッシング
動作が可能であると共に、ケーシング管の引抜き時に削
孔ビットとドライブシューとの離脱を容易に行うことが
でき、然も、地盤が被圧水層であっても、従来の如くド
ライブシューやケーシング管内へ水や砂等が流入する虞
のないアースアンカー施工用の削孔装置を提供すること
を目的とする。
The present invention has been devised in view of the above circumstances, and enables a flushing operation of a casing pipe at the time of drilling an anchor hole, and a detachment between a drill bit and a drive shoe at the time of pulling out a casing pipe. Provided is a drilling device for earth anchor construction, which can be easily performed and, of course, does not cause water or sand to flow into a drive shoe or a casing pipe even if the ground is a pressurized water layer. The purpose is to do.

【0013】[0013]

【課題を解決するための手段】斯かる目的を達成するた
め、本発明に係る削孔装置は、削孔機に接続するケーシ
ング管の先端に螺着され、その内周にピン係合溝が形成
されたドライブシューと、当該ドライブシューと軸方向
に噛み合ってその先端に接続され、ドライブシューに挿
入される筒状部の周壁に複数のピン挿通孔が形成された
削孔ビットと、削孔ビット内に配置され、上記ピン挿通
孔を挿脱してピン係合溝に係脱自在な取付ピンを有する
ビット連結治具と、ケーシング管内に昇降自在に挿入さ
れ、当該ビット連結治具を回収するビット連結治具回収
治具とからなり、上記ビット連結治具は、中央外周に係
止溝を有するナットが一端側に螺合した軸ねじ棒と、当
該軸ねじ棒にパンタグラフ状に装着され、ナットの回動
操作による屈伸運動で上記取付ピンをドライブシューの
ピン挿通孔に挿脱させる複数対のアームを備えると共
に、ビット連結治具回収治具は、ビット連結治具のナッ
トに嵌合するナット嵌合孔と、当該ナットの係止溝に係
止する係止爪を有し、当該ビット連結治具回収治具によ
るナットの回転操作で、削孔ビットとドライブシューと
の連結状態を解除させることを特徴とする。
In order to achieve the above object, a drilling device according to the present invention is screwed to a tip of a casing tube connected to a drilling machine, and a pin engaging groove is formed on an inner periphery thereof. A formed drive shoe, a drill bit in which a plurality of pin insertion holes are formed in a peripheral wall of a cylindrical portion which is meshed with the drive shoe in the axial direction and is connected to the tip thereof, and is inserted into the drive shoe; A bit connecting jig disposed in the bit and having a mounting pin that can be inserted into and disengaged from the pin insertion hole to be disengaged from the pin engaging groove, and a bit connecting jig that is inserted into the casing pipe so as to be able to move up and down to collect the bit connecting jig. A bit connection jig recovery jig, wherein the bit connection jig is mounted in a pantograph shape on a shaft screw rod in which a nut having a locking groove on the center outer periphery is screwed to one end side, Bending and stretching by rotating the nut A plurality of pairs of arms for inserting and removing the mounting pins into and from the pin insertion holes of the drive shoe are provided, and the bit connecting jig collecting jig is provided with a nut fitting hole for fitting to a nut of the bit connecting jig, and the nut. And the connection state between the drill bit and the drive shoe is released by rotating the nut by the bit connection jig recovery jig.

【0014】[0014]

【作用】本発明に係る削孔装置によれば、ビット連結治
具の取付ピンを削孔ビットのピン挿通孔を介してドライ
ブシューのピン係合溝に係合させれば、ドライブシュー
と削孔ビットが連結される。
According to the drilling device of the present invention, if the mounting pin of the bit connecting jig is engaged with the pin engaging groove of the drive shoe via the pin insertion hole of the drill bit, the drive shoe is cut. The hole bit is connected.

【0015】従って、斯様に削孔ビットを連結したドラ
イブシューをケーシング管の先端に螺着して、削孔用水
をケーシング管内に送水し乍ら地盤を削孔していけば、
地盤にアンカー孔が削孔される。そして、削孔時にケー
シング管をフラッシング動作させても、取付ピンがピン
挿通孔を介してピン係合溝に係合しているため、削孔ビ
ットがドライブシューから外れることがない。
Therefore, if the drive shoe to which the drilling bit is connected is screwed to the tip of the casing pipe and the ground is drilled while water for drilling is supplied into the casing pipe,
An anchor hole is drilled in the ground. Even when the casing tube is flushed during drilling, the drilling bit does not come off the drive shoe because the mounting pin is engaged with the pin engaging groove via the pin insertion hole.

【0016】そして、削孔完了後、ケーシング管内にビ
ット連結治具回収治具を挿入して、ナット嵌合孔にビッ
ト連結治具のナットを嵌合させると共に、係止爪をナッ
トの係止溝に係止させてビット連結治具回収治具でナッ
トを回転操作すれば、アームが変位して取付ピンがピン
挿通孔から後退し、削孔ビットとドライブシューとの連
結状態が解除される。
After the drilling is completed, a bit connecting jig collecting jig is inserted into the casing tube, the nut of the bit connecting jig is fitted into the nut fitting hole, and the locking claw is locked by the nut. When the nut is rotated with the bit connection jig collection jig while locking it in the groove, the arm is displaced, the mounting pin retreats from the pin insertion hole, and the connection state between the drill bit and the drive shoe is released. .

【0017】そして、ビット連結治具回収治具の係止爪
がビット連結治具のナットの係止溝に係止しているの
で、削孔ビットとドライブシューとの連結状態の解除
後、ビット連結治具回収治具を引き上げれば、ビット連
結治具が同時に引き上げられて地上に回収されることと
なる。
Since the locking claw of the bit connecting jig collecting jig is locked in the locking groove of the nut of the bit connecting jig, the bit is released after the connection between the drill bit and the drive shoe is released. If the connecting jig collection jig is raised, the bit connecting jig is simultaneously raised and collected on the ground.

【0018】しかる後、アンカー孔内にアンカー引張材
を挿入してグラウト材を加圧注入し乍らケーシング管を
引き抜けば、削孔ビットはドライブシューと離脱してア
ンカー孔内に残され、グラウト材によってアンカー孔内
に埋没されることとなる。
Thereafter, if the casing tube is pulled out while inserting the anchor tension material into the anchor hole and injecting the grout material under pressure, the drill bit is separated from the drive shoe and left in the anchor hole. It will be buried in the anchor hole by the grout material.

【0019】[0019]

【実施例】以下、本発明の実施例を図面に基づき詳細に
説明する。図1は本発明に係る削孔装置の一実施例を示
し、図中、31は従来と同様、ケーシング管の先端に螺
着されるドライブシューで、その内周には一本のピン係
合溝33が形成されている。そして、その先端に削孔ビ
ット35が軸方向に噛み合って接続されている。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 shows an embodiment of a drilling device according to the present invention. In the drawing, reference numeral 31 denotes a drive shoe screwed to the tip of a casing tube, as in the conventional case, and a single pin engagement A groove 33 is formed. A drill bit 35 is axially meshed and connected to the tip.

【0020】削孔ビット35は、ドライブシュー31の
先端に配置される頭部35aと、ドライブシュー31に
挿入される筒状部35bとで構成されており、頭部35
aには削孔用水Wの噴出孔37が複数設けられ、又、筒
状部35bの周壁には、上記ピン係合溝33に対応して
正方形状のピン挿通孔39が180°の間隔を開けて設
けられている。そして、筒状部35b内に、従来と同様
な逆止弁41が頭部35aの裏面側に装着されている。
The drill bit 35 comprises a head 35a disposed at the tip of the drive shoe 31 and a cylindrical portion 35b inserted into the drive shoe 31.
a is provided with a plurality of holes 37 for drilling water W, and a square pin insertion hole 39 corresponding to the pin engagement groove 33 is formed on the peripheral wall of the cylindrical portion 35b at an interval of 180 °. It is provided open. In the tubular portion 35b, a check valve 41 similar to the conventional one is mounted on the back side of the head 35a.

【0021】即ち、図1中、43は下方に向かってテー
パ状に拡開する送水通路45が中央に設けられた弁座
で、当該弁座43は筒状部35bの内周に固着されてい
る。そして、頭部35aの裏面との間に張設したスプリ
ング47に付勢されたボール弁49が弁座43に当接し
て送水通路45を閉塞しており、ケーシング管内に削孔
用水Wが注入されると、二点鎖線で示すようにその水圧
でボール弁49がスプリング47のばね力に抗して下方
へ移動し、送水通路45が開放されるようになってい
る。尚、図中、51はドライブシュー31と削孔ビット
35との間隙をシールするO−リングである。
That is, in FIG. 1, reference numeral 43 denotes a valve seat provided at the center with a water supply passage 45 expanding downward in a tapered shape, and the valve seat 43 is fixed to the inner periphery of the cylindrical portion 35b. I have. Then, a ball valve 49 urged by a spring 47 stretched between the back surface of the head 35a and the valve seat 43 abuts the valve seat 43 to close the water supply passage 45, and the drilling water W is injected into the casing pipe. Then, as shown by the two-dot chain line, the ball pressure 49 moves downward against the spring force of the spring 47 by the water pressure, and the water supply passage 45 is opened. In the drawing, reference numeral 51 denotes an O-ring for sealing a gap between the drive shoe 31 and the drill bit 35.

【0022】そして、上記逆止弁41の上部に、削孔ビ
ット35とドライブシュー31を連結するビット連結治
具53が配置されている。ビット連結治具53は、ドラ
イブシュー31と中心軸を同じくして削孔ビット35内
に挿入,配置される1本の軸ねじ棒55を有する。そし
て、その一端側には、中央外周に係止溝57を有するナ
ット59が螺着されており、当該ナット59の回動操作
によって軸ねじ棒55が軸方向(図中、矢印A,B方
向)へ移動するようになっている。
A bit connecting jig 53 for connecting the drill bit 35 and the drive shoe 31 is disposed above the check valve 41. The bit connecting jig 53 has one shaft screw rod 55 inserted and arranged in the drill bit 35 with the same central axis as the drive shoe 31. A nut 59 having a locking groove 57 on the center outer periphery is screwed to one end thereof, and the shaft screw bar 55 is axially moved by rotating the nut 59 (in the direction of arrows A and B in the figure). ).

【0023】そして、軸ねじ棒55の先端に装着された
重り63とナット59との間には、ブラケット65,6
7を介して一対宛のアーム69,71が180°の間隔
を開けてパンタグラフ状に連結されており、ナット59
の回動操作による軸ねじ棒55の移動によって、図1及
び図2に示すようにアーム69,71が屈伸運動するよ
うになっている。
Brackets 65 and 6 are provided between the weight 63 mounted on the tip of the shaft screw rod 55 and the nut 59.
7, the pair of arms 69 and 71 are connected in a pantograph shape at an interval of 180 ° and a nut 59.
The arms 69 and 71 bend and extend as shown in FIGS. 1 and 2 due to the movement of the shaft screw rod 55 by the turning operation of.

【0024】即ち、図1に示すようにナット59を矢印
C方向へ回転操作すると、軸ねじ棒55が矢印B方向へ
移動して両ブラケット65,67間が狭まり、各アーム
69,71の連結部分73が削孔ビット35の周壁方向
(矢印D,E方向)へ突出するように変位する。そし
て、当該連結部分73には断面正方形状の取付ピン75
が取り付けられており、斯様にナット59の矢印C方向
への回転操作で各アーム69,71の連結部分73が矢
印D,E方向へ変位すると、各取付ピン75が削孔ビッ
ト35のピン挿通孔39を挿通してドライブシュー31
のピン係合溝33に係合し、削孔ビット35が当該ビッ
ト連結治具53を介してドライブシュー33に連結され
るようになっている。
That is, as shown in FIG. 1, when the nut 59 is rotated in the direction of arrow C, the shaft screw rod 55 moves in the direction of arrow B to narrow the space between the brackets 65 and 67, and connects the arms 69 and 71. The portion 73 is displaced so as to protrude in the direction of the peripheral wall of the drill bit 35 (directions of arrows D and E). The connecting portion 73 has a mounting pin 75 having a square cross section.
When the connecting portion 73 of each of the arms 69 and 71 is displaced in the directions of the arrows D and E by the rotation operation of the nut 59 in the direction of the arrow C, each of the mounting pins 75 is The drive shoe 31 is inserted through the insertion hole 39.
And the drill bit 35 is connected to the drive shoe 33 via the bit connecting jig 53.

【0025】そして、この状態でナット59を矢印F方
向へ回すと、図2に示すように軸ねじ棒55が矢印A方
向へ移動するので、両ブラケット65,67間の間隔が
広がってアーム69,71が伸長し、その結果、取付ピ
ン75がピン挿通孔39から後退して削孔ビット35と
ドライブシュー31との連結状態が解除されるようにな
っている。
When the nut 59 is turned in the direction of arrow F in this state, the shaft screw bar 55 moves in the direction of arrow A as shown in FIG. , 71 are extended, as a result, the mounting pin 75 is retracted from the pin insertion hole 39, and the connection state between the drill bit 35 and the drive shoe 31 is released.

【0026】而して、削孔ビット35とドライブシュー
31を連結するビット連結治具53は、図3に示すビッ
ト連結治具回収治具77によって削孔ビット35内から
回収される。
The bit connecting jig 53 for connecting the drill bit 35 and the drive shoe 31 is recovered from the drill bit 35 by the bit connecting jig recovery jig 77 shown in FIG.

【0027】図3はビット連結治具回収治具77の断面
図、図4は図3のIV−IV線断面図を示し、図中、79は
上記ナット59に嵌合可能な断面六角形状のナット嵌合
孔81が先端側に形成された六角柱形状の治具本体で、
当該ナット嵌合孔81の略中間部の周壁には、内方へ突
出する係止爪83が先端に設けられた係止部材85が、
180°の間隔を開けて矢印方向へ取付軸87により移
動可能に取り付けられている。そして、当該係止部材8
5の取付部位に対応させて治具本体79の外周にはゴム
リング89が取り付けられており、図3に示すようにナ
ット嵌合孔81内にナット59を嵌合させたとき、ナッ
ト59に当接した係止部材85は、二点鎖線で示すよう
にゴムリング89の弾性力に抗して取付軸87を回転中
心として外方へ移動し、そして、ナット59の係止溝5
7が通過すると、ゴムリング89の弾性力により実線で
示す位置に復帰して係止爪83がナット59の係止溝5
7に係止するようになっている。
FIG. 3 is a sectional view of the bit connecting jig collecting jig 77, and FIG. 4 is a sectional view taken along the line IV-IV of FIG. A hexagonal column-shaped jig body in which a nut fitting hole 81 is formed on the tip side,
A locking member 85 having a locking claw 83 protruding inward at a distal end thereof is provided on a peripheral wall of a substantially intermediate portion of the nut fitting hole 81.
It is movably mounted by a mounting shaft 87 in the direction of the arrow at 180 ° intervals. Then, the locking member 8
A rubber ring 89 is attached to the outer periphery of the jig body 79 so as to correspond to the attachment portion of the nut 5. When the nut 59 is fitted into the nut fitting hole 81 as shown in FIG. The abutting locking member 85 moves outward about the mounting shaft 87 as a center of rotation against the elastic force of the rubber ring 89 as shown by the two-dot chain line, and then the locking groove 5 of the nut 59.
7 passes, the elastic force of the rubber ring 89 returns to the position shown by the solid line, and the locking claw 83
7.

【0028】又、ナット嵌合孔81と仕切壁91を介し
て治具本体79の上部に設けられた取付孔93には、P
C鋼線95の一端がエポキシ接着剤97によって取り付
けられており、地上から当該PC鋼線95を矢印F方向
へ回転させて治具本体79を同方向へ回転させると、ナ
ット嵌合孔81に嵌合したナット59がこれに連動して
矢印F方向へ回転するようになっている。
A mounting hole 93 provided in the upper part of the jig main body 79 through the nut fitting hole 81 and the partition wall 91 has a P
One end of the C steel wire 95 is attached by an epoxy adhesive 97, and when the PC steel wire 95 is rotated from the ground in the direction of arrow F to rotate the jig body 79 in the same direction, the PC steel wire 95 is inserted into the nut fitting hole 81. The fitted nut 59 rotates in the direction of arrow F in conjunction with this.

【0029】従って、図1の如く取付ピン75を介して
削孔ビット35がドライブシュー31と連結していると
き、斯様にビット連結治具回収治具77でナット59を
矢印F方向へ回転させると、上述したように取付ピン7
5がピン挿通孔39から後退してピン係合溝33との係
合が解除され、そして、図5に示すようにビット連結治
具回収治具77を上昇させると、ビット連結治具回収治
具77の係止爪83がナット59の係止溝57に係止し
ているので、当該ビット連結治具回収治具77によって
ビット連結治具53が地上に回収されることとなる。
Therefore, when the drill bit 35 is connected to the drive shoe 31 via the mounting pin 75 as shown in FIG. 1, the nut 59 is rotated in the direction of arrow F by the bit connecting jig recovery jig 77 in this manner. Then, as described above, the mounting pin 7
5 is retracted from the pin insertion hole 39 to release the engagement with the pin engagement groove 33, and as shown in FIG. 5, when the bit connecting jig collecting jig 77 is raised, the bit connecting jig collecting jig is recovered. Since the locking claw 83 of the tool 77 is locked in the locking groove 57 of the nut 59, the bit connecting jig 53 is collected on the ground by the bit connecting jig collecting jig 77.

【0030】その他、図1中、99は図13に示す従来
例と同様、削孔ビット35の頭部35aの後端に形成さ
れた切欠き部、101はドライブシュー31の先端に形
成された切欠き部で、両切欠き部99,101を軸方向
(削孔方向)に噛み合わせることで、ケーシング管の回
転が削孔ビット35に伝わるようになっている。
1, reference numeral 99 denotes a notch formed at the rear end of the head 35a of the drill bit 35, as in the conventional example shown in FIG. By engaging the notches 99 and 101 in the axial direction (drilling direction) at the notch, the rotation of the casing tube is transmitted to the drill bit 35.

【0031】本実施例に係る削孔装置はこのように構成
されているから、当該削孔装置を用いてアースアンカー
を施工するには、図1に示すように、先ず、削孔ビット
35の切欠き部99とドライブシュー31の切欠き部1
01を軸方向に噛み合わせ、ビット連結治具53の取付
ピン75を削孔ビット35のピン挿通孔39を介してド
ライブシュー31のピン係合溝33に係合させる。これ
で、ドライブシュー31に削孔ビット35が連結され
る。
Since the drilling device according to the present embodiment is configured as described above, in order to construct an earth anchor using the drilling device, first, as shown in FIG. Notch 99 and Notch 1 of Drive Shoe 31
01 is engaged in the axial direction, and the mounting pin 75 of the bit connecting jig 53 is engaged with the pin engaging groove 33 of the drive shoe 31 through the pin insertion hole 39 of the drill bit 35. Thus, the drill bit 35 is connected to the drive shoe 31.

【0032】そして、図6に示すようにドライブシュー
31を削孔機に接続したケーシング管103の先端に螺
着して、削孔用水Wをケーシング管103内に送水し乍
ら、従来と同様、削孔深さに応じてケーシング管103
を順次接続して地盤105にアンカー孔107を削孔し
ていけばよく、このとき、ケーシング107管をフラッ
シング動作させても、取付ピン75がピン挿通孔39を
介してピン係合溝33と係合しているため、削孔ビット
35がドライブシュー31から外れることがない。そし
て、正方形状に形成されたピン挿通孔39に断面正方形
状の取付ピン75が挿通しているため、削孔時に削孔ビ
ット35やビット連結治具53が揺動することもない。
Then, as shown in FIG. 6, the drive shoe 31 is screwed onto the tip of the casing tube 103 connected to the drilling machine, and the drilling water W is supplied into the casing tube 103 as in the conventional case. , The casing pipe 103 according to the drilling depth
And the anchor hole 107 may be drilled in the ground 105 by sequentially connecting the mounting pins 75. At this time, even if the casing 107 tube is flushed, the mounting pin 75 is in contact with the pin engaging groove 33 through the pin insertion hole 39. Since it is engaged, the drill bit 35 does not come off the drive shoe 31. Since the mounting pin 75 having a square cross section is inserted through the pin insertion hole 39 formed in a square shape, the drill bit 35 and the bit connecting jig 53 do not swing during drilling.

【0033】又、削孔用水Wは、弁座43の送水通路4
5を経て削孔ビット35の噴出孔37から地盤105中
に噴出されるが、送水を止めると、地下水圧とスプリン
グ47のばね力によってボール弁49が弁座43の送水
通路45を閉塞し、削孔ビット35内への泥水の逆流を
防止することとなる。
The drilling water W is supplied to the water supply passage 4 of the valve seat 43.
5, the water is ejected into the ground 105 from the ejection hole 37 of the drill bit 35, but when the water supply is stopped, the ball valve 49 closes the water supply passage 45 of the valve seat 43 due to the underground water pressure and the spring force of the spring 47. This prevents the backflow of the muddy water into the drill bit 35.

【0034】そして、削孔完了後、図7の如く地上から
ビット連結治具回収治具77をケーシング管103内に
挿入し乍ら、図8に示すようにナット嵌合孔81にナッ
ト59を嵌合させて係止部材85の係止爪83をナット
59の係止溝57に係止させる。
After the drilling is completed, the nut 59 is inserted into the nut fitting hole 81 as shown in FIG. 8 while the bit connecting jig collecting jig 77 is inserted into the casing tube 103 from the ground as shown in FIG. The engaging claw 83 of the engaging member 85 is engaged with the engaging groove 57 of the nut 59 by fitting.

【0035】而して、斯かる状態で地上からPC鋼線9
5を矢印F方向へ回転させて、治具本体79でナット5
9を矢印F方向へ回転させると、図2及び図9に示すよ
うに取付ピン75がピン挿通孔39から後退してピン係
合溝33との係合が解除されるので、この後、ビット連
結治具回収治具77を徐々に上方へ引き上げれば、図5
及び図10に示すようにビット連結治具53全体が上方
へ引き上げられて地上に回収される。
In this state, the PC steel wire 9 from the ground is
5 is rotated in the direction of arrow F.
9 is rotated in the direction of arrow F, the mounting pin 75 is retracted from the pin insertion hole 39 and disengaged from the pin engaging groove 33 as shown in FIGS. If the connecting jig recovery jig 77 is gradually pulled upward, FIG.
As shown in FIG. 10, the entire bit connecting jig 53 is pulled upward and collected on the ground.

【0036】しかる後、図11に示すようにケーシング
管103内にアンカー引張材109を挿入して、グラウ
ト材Gを加圧注入し乍ら図12の如くケーシング管10
3を上方へ引き抜けば、削孔ビット35はドライブシュ
ー31と離脱してアンカー孔107内に残され、グラウ
ト材Gによってアンカー孔107内に埋没されることと
なる。
Thereafter, as shown in FIG. 11, an anchor tension member 109 is inserted into the casing tube 103, and while grout material G is injected under pressure, the casing tube 10 as shown in FIG.
When the drill bit 3 is pulled upward, the drill bit 35 separates from the drive shoe 31 and remains in the anchor hole 107, and is buried in the anchor hole 107 by the grout material G.

【0037】このように、本実施例に係る削孔装置は、
地盤105の削孔時に、ビット連結治具53の取付ピン
75をピン挿通孔39を介してピン係合溝33に係合さ
せてドライブシュー31と削孔ビット35を連結し、削
孔終了後、ビット連結治具回収治具77によるナット5
9の回転操作で取付ピン75をピン挿通孔39から後退
させてドライブシュー31と削孔ビット35の連結状態
を解除し、ビット連結治具53をビット連結治具回収治
具77で回収するようにしたので、斯かる削孔装置をア
ースアンカーの施工に用いることによって、削孔時にケ
ーシング管103のフラッシング動作が可能となると共
に、ケーシング管103の引抜き時に削孔ビット35と
ドライブシュー31との離脱を容易に行うことができ、
その結果、図13乃至図15に示す従来例に比しアース
アンカーの施工性が飛躍的に向上することとなった。
As described above, the drilling apparatus according to this embodiment is
At the time of drilling the ground 105, the mounting pin 75 of the bit connecting jig 53 is engaged with the pin engaging groove 33 through the pin insertion hole 39 to connect the drive shoe 31 and the drill bit 35, and after drilling is completed. , Nut 5 by the bit connecting jig recovery jig 77
The connecting pin 75 is retracted from the pin insertion hole 39 by the rotation operation 9 to release the connection state between the drive shoe 31 and the drill bit 35, and the bit connecting jig 53 is collected by the bit connecting jig collecting jig 77. By using such a drilling device for the construction of an earth anchor, the casing tube 103 can be flushed at the time of drilling, and the drilling bit 35 and the drive shoe 31 can be connected when the casing tube 103 is pulled out. Easy withdrawal,
As a result, the workability of the earth anchor is dramatically improved as compared with the conventional example shown in FIGS.

【0038】然も、本実施例によれば、地盤105が被
圧水層であっても、ドライブシュー31と削孔ビット3
5との連結状態を解除する際に、水や砂等がドライブシ
ュー31やケーシング管103内へ流入する虞もない。
According to this embodiment, even if the ground 105 is a water layer to be pressurized, the drive shoe 31 and the drill bit 3
When releasing the connection state with the fifth, there is no possibility that water, sand, or the like flows into the drive shoe 31 or the casing tube 103.

【0039】尚、上記実施例は、ブラケット65,67
を介して一対宛のアーム69,71を180°の間隔を
開けてパンタグラフ状に連結したが、例えば一対宛のア
ーム69,71を90°の間隔を開けてパンタグラフ状
に連結し、その連結部分73に取付ピン75を装着する
と共に、これらに対応して削孔ビット35の筒状部35
bに4個のピン挿通孔39を設けてもよく、この場合に
はピン挿通孔39は円形の小孔でよく、又、取付ピン7
5も断面円形状で足りる。
In the above embodiment, the brackets 65, 67
The arms 69 and 71 addressed to a pair are connected in a pantograph shape with a 180 ° interval therebetween. For example, the arms 69 and 71 addressed to a pair are connected in a pantograph shape with a 90 ° interval and the connection portion is formed. Attachment pins 75 are attached to the 73, and the cylindrical portion 35 of the drill bit 35 is
b may be provided with four pin insertion holes 39. In this case, the pin insertion holes 39 may be circular small holes.
5 also needs a circular cross section.

【0040】又、上記実施例では、筒状部35b内に逆
止弁41を内蔵した削孔ビット35を用いて本発明を説
明したが、本発明に係る削孔装置は、斯かる逆止弁41
を装着しない使捨てビットにも適用できることは勿論で
ある。
In the above-described embodiment, the present invention has been described using the drill bit 35 having the check valve 41 built in the cylindrical portion 35b. Valve 41
Needless to say, the present invention can be applied to a disposable bit having no.

【0041】[0041]

【発明の効果】以上述べたように、本発明に係る削孔装
置をアースアンカーの施工に用いることによって、地盤
の削孔時にケーシング管のフラッシング動作が可能とな
ると共に、ケーシング管の引抜き時に削孔ビットとドラ
イブシューとの離脱を容易に行うことができるので、従
来に比しアースアンカーの施工性が飛躍的に向上するこ
ととなった。
As described above, the use of the drilling device according to the present invention for the construction of the earth anchor enables the flushing operation of the casing pipe at the time of drilling the ground and the drilling at the time of pulling out the casing pipe. Since the hole bit and the drive shoe can be easily separated from each other, the workability of the ground anchor has been dramatically improved as compared with the related art.

【0042】然も、本発明によれば、ドライブシューと
削孔ビットの連結状態を解除する際に、地盤が被圧水層
であっても水や砂等がドライブシューやケーシング管内
へ流入する虞もない。
According to the present invention, when the connection between the drive shoe and the drill bit is released, water and sand flow into the drive shoe and the casing pipe even if the ground is a pressurized water layer. There is no fear.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施例に係る削孔装置の断面図であ
る。
FIG. 1 is a sectional view of a drilling device according to one embodiment of the present invention.

【図2】ビット連結治具回収治具の回転操作で削孔ビッ
トとドライブシューとの連結状態を解除した状態を示す
削孔装置の断面図である。
FIG. 2 is a cross-sectional view of the drilling machine showing a state in which the connection state between the drilling bit and the drive shoe has been released by rotating the bit connecting jig collecting jig.

【図3】ビット連結治具回収治具の断面図である。FIG. 3 is a sectional view of a bit connecting jig collecting jig.

【図4】図3のIV−IV線断面図である。FIG. 4 is a sectional view taken along line IV-IV of FIG. 3;

【図5】ビット連結治具回収治具でビット連結治具を引
き上げた状態を示す削孔装置の断面図である。
FIG. 5 is a cross-sectional view of the drilling device showing a state where the bit connecting jig is pulled up by the bit connecting jig collecting jig.

【図6】図1に示す削孔装置による地盤の削孔状態を示
す概略図である。
FIG. 6 is a schematic diagram showing a state of drilling of the ground by the drilling device shown in FIG. 1;

【図7】ビット連結治具回収治具をケーシング管に挿入
した状態を示す概略図である。
FIG. 7 is a schematic view showing a state where a bit connecting jig collecting jig is inserted into a casing tube.

【図8】ビット連結治具回収治具の係止爪をビット連結
治具のナットの係止溝に係止した状態を示す概略図であ
る。
FIG. 8 is a schematic view showing a state in which a locking claw of a bit connecting jig collecting jig is locked in a locking groove of a nut of the bit connecting jig.

【図9】ビット連結治具回収治具の回転操作で削孔ビッ
トとドライブシューとの連結状態を解除した状態を示す
概略図である。
FIG. 9 is a schematic view showing a state in which the connection state between the drill bit and the drive shoe has been released by rotating the bit connection jig collection jig.

【図10】ビット連結治具回収治具によってビット連結
治具を回収している状態を示す概略図である。
FIG. 10 is a schematic diagram showing a state in which the bit connecting jig is being collected by the bit connecting jig collecting jig.

【図11】アンカー引張材の挿入後、グラウト材を加圧
注入している状態を示す概略図である。
FIG. 11 is a schematic diagram showing a state in which a grout material is injected under pressure after insertion of an anchor tension material.

【図12】ケーシング管を引き抜いている状態を示す概
略図である。
FIG. 12 is a schematic view showing a state in which a casing tube has been pulled out.

【図13】従来のクローネンビットとドライブシュー及
びケーシング管の斜視図である。
FIG. 13 is a perspective view of a conventional kronen bit, a drive shoe, and a casing tube.

【図14】ピンによるドライブシューと先端インナービ
ットとの従来の連結方法を示す断面図である。
FIG. 14 is a cross-sectional view showing a conventional method of connecting a drive shoe and a tip inner bit by a pin.

【図15】ピンによるドライブシューと先端インナービ
ットとの連結状態の解除方法を示す断面図である。
FIG. 15 is a cross-sectional view showing a method of releasing a connection state between the drive shoe and the tip inner bit by a pin.

【符号の説明】[Explanation of symbols]

31 ドライブシュー 33 ピン係合溝 35 削孔ビット 35a 頭部 35b 筒状部 37 噴出孔 39 ピン挿通孔 41 逆止弁 53 ビット連結治具 55 軸ねじ棒 57 係止溝 59 ナット 65,67 ブラケット 69,71 アーム 75 取付ピン 77 ビット連結治具回収治具 79 治具本体 81 ナット嵌合孔 83 係止爪 85 係止部材 89 ゴムリング 95 PC鋼線 103 ケーシング管 105 地盤 107 アンカー孔 Reference Signs List 31 drive shoe 33 pin engaging groove 35 drill bit 35a head 35b cylindrical portion 37 ejection hole 39 pin insertion hole 41 check valve 53 bit connecting jig 55 shaft screw rod 57 locking groove 59 nut 65, 67 bracket 69 , 71 arm 75 mounting pin 77 bit connecting jig recovery jig 79 jig main body 81 nut fitting hole 83 locking claw 85 locking member 89 rubber ring 95 PC steel wire 103 casing pipe 105 ground 107 anchor hole

───────────────────────────────────────────────────── フロントページの続き (72)発明者 藤田 雅一 大阪府大阪市北区松ケ枝町6番22号 日 本基礎技術株式会社内 (72)発明者 真居 正信 大阪府大阪市北区松ケ枝町6番22号 日 本基礎技術株式会社内 (56)参考文献 特開 平7−238541(JP,A) 特開 平7−166545(JP,A) 特開 平7−3787(JP,A) 特開 平6−306859(JP,A) 特開 平4−261996(JP,A) 実開 昭58−165089(JP,U) (58)調査した分野(Int.Cl.7,DB名) E02D 5/80 E21B 7/20 E21B 7/00 E21B 10/62 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Masakazu Fujita 6-22, Matsugaeda-cho, Kita-ku, Osaka-shi, Osaka Japan Basic Technology Co., Ltd. (72) Masanobu Mai Matsugae-cho, Kita-ku, Osaka, Osaka No. 6-22 Inside Japan Basic Technology Co., Ltd. (56) References JP-A-7-238541 (JP, A) JP-A-7-166545 (JP, A) JP-A-7-3787 (JP, A) JP-A-6-306859 (JP, A) JP-A-4-261996 (JP, A) JP-A-58-165089 (JP, U) (58) Fields investigated (Int. Cl. 7 , DB name) E02D 5 / 80 E21B 7/20 E21B 7/00 E21B 10/62

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 削孔機に接続するケーシング管の先端に
螺着され、その内周にピン係合溝が形成されたドライブ
シューと、 当該ドライブシューと軸方向に噛み合ってその先端に接
続され、ドライブシューに挿入される筒状部の周壁に複
数のピン挿通孔が形成された削孔ビットと、 削孔ビット内に配置され、上記ピン挿通孔を挿脱してピ
ン係合溝に係脱自在な取付ピンを有するビット連結治具
と、 ケーシング管内に昇降自在に挿入され、当該ビット連結
治具を回収するビット連結治具回収治具とからなり、 上記ビット連結治具は、中央外周に係止溝を有するナッ
トが一端側に螺合した軸ねじ棒と、当該軸ねじ棒にパン
タグラフ状に装着され、ナットの回動操作による屈伸運
動で上記取付ピンをドライブシューのピン挿通孔に挿脱
させる複数対のアームを備えると共に、 ビット連結治具回収治具は、ビット連結治具のナットに
嵌合するナット嵌合孔と、当該ナットの係止溝に係止す
る係止爪を有し、 当該ビット連結治具回収治具によるナットの回転操作
で、削孔ビットとドライブシューとの連結状態を解除さ
せることを特徴とする削孔装置。
1. A drive shoe screwed to a tip of a casing tube connected to a drilling machine and having a pin engagement groove formed on an inner periphery thereof, meshed with the drive shoe in the axial direction and connected to the tip. A drill bit having a plurality of pin insertion holes formed in a peripheral wall of a cylindrical portion to be inserted into the drive shoe; and a drill bit disposed in the drill bit, being inserted into and removed from the pin insertion hole to engage and disengage with the pin engagement groove. A bit connecting jig having a flexible mounting pin; and a bit connecting jig recovering jig which is inserted into the casing tube so as to be able to move up and down and collects the bit connecting jig. A nut having a locking groove is screwed to one end of a shaft screw rod, and the shaft screw rod is mounted on the shaft screw rod in a pantograph shape, and the mounting pin is inserted into the pin insertion hole of the drive shoe by bending and extending movement by rotating the nut. Multiple pairs In addition to the arm, the bit connecting jig recovery jig has a nut fitting hole that fits into a nut of the bit connecting jig, and a locking claw that locks in a locking groove of the nut. A drilling device characterized in that a connection state between a drilling bit and a drive shoe is released by a rotation operation of a nut by a jig collecting jig.
JP04917694A 1994-03-18 1994-03-18 Drilling equipment Expired - Lifetime JP3233183B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP04917694A JP3233183B2 (en) 1994-03-18 1994-03-18 Drilling equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP04917694A JP3233183B2 (en) 1994-03-18 1994-03-18 Drilling equipment

Publications (2)

Publication Number Publication Date
JPH07259090A JPH07259090A (en) 1995-10-09
JP3233183B2 true JP3233183B2 (en) 2001-11-26

Family

ID=12823752

Family Applications (1)

Application Number Title Priority Date Filing Date
JP04917694A Expired - Lifetime JP3233183B2 (en) 1994-03-18 1994-03-18 Drilling equipment

Country Status (1)

Country Link
JP (1) JP3233183B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4775737B2 (en) * 2006-04-24 2011-09-21 北海電気工事株式会社 Drilling drill detachable drilling hole forming method and apparatus therefor
JP6357063B2 (en) * 2014-09-30 2018-07-11 株式会社竹中土木 Non-widening AGF construction method, ground improvement structure by the construction method, and jig used in the construction method
JP7223403B2 (en) * 2019-02-08 2023-02-16 新協地水株式会社 Drilling rig and drilling method

Also Published As

Publication number Publication date
JPH07259090A (en) 1995-10-09

Similar Documents

Publication Publication Date Title
PT1381756E (en) Method and device for drilling a hole and for securing an anchorage in a bore hole
JP3233183B2 (en) Drilling equipment
JP6663324B2 (en) Groundwater intake method and intake system
JP4484294B2 (en) Non-core drilling equipment
JP3859639B2 (en) Swivel excavator and ground improvement method
JP2006299591A (en) Casing excavation and construction equipment
JP6542179B2 (en) Core material burial method
JP4939260B2 (en) Inserting long members into the ground
JP3233181B2 (en) Drilling equipment
JP2007016394A (en) Pipe installing construction method and hole drilling device
JP4397296B2 (en) Pipe laying method by one-push propulsion method
JP3388723B2 (en) Drilling device and drilling method
JPH07166545A (en) Drilling device
JPH0663413B2 (en) Drilling bit device and drilling method
JP3058106B2 (en) Rock bolt method and drilling equipment for the method
JP2011080244A (en) Method of draining and drain pipe
JP3994726B2 (en) Double pipe drilling tools
JP4431019B2 (en) Underground construction method
JPH08326054A (en) Execution method of ground anchor and cutoff device in drilling casing
JP5007148B2 (en) Non-cutting excavation burial equipment
JP4151046B2 (en) A method of embedding a perforated pipe with a ground cutting device.
JP4195876B2 (en) Drilling rig
JP3159091B2 (en) Method of fixing bolt material in rock bolt method
WO2013105371A1 (en) Water catchment pipe laying assistance instrument and water catchment pipe laying method employing same
JP2006009313A (en) Vertical-hole excavating equipment, vertical-hole construction method using it, and lower propellant

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070921

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080921

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080921

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090921

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100921

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110921

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120921

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120921

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130921

Year of fee payment: 12

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term