JP3190983U - Steel pipe pile foundation structure - Google Patents
Steel pipe pile foundation structure Download PDFInfo
- Publication number
- JP3190983U JP3190983U JP2014001400U JP2014001400U JP3190983U JP 3190983 U JP3190983 U JP 3190983U JP 2014001400 U JP2014001400 U JP 2014001400U JP 2014001400 U JP2014001400 U JP 2014001400U JP 3190983 U JP3190983 U JP 3190983U
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- pipe pile
- pile
- concrete
- foundation structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 61
- 239000010959 steel Substances 0.000 title claims abstract description 61
- 239000004567 concrete Substances 0.000 claims abstract description 18
- 230000003014 reinforcing Effects 0.000 claims abstract description 9
- 239000011800 void material Substances 0.000 abstract description 10
- 239000002689 soil Substances 0.000 description 9
- 239000004568 cement Substances 0.000 description 8
- 238000010276 construction Methods 0.000 description 3
- 238000009415 formwork Methods 0.000 description 3
- 238000009412 basement excavation Methods 0.000 description 2
- 239000002131 composite material Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 230000002238 attenuated Effects 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 230000001747 exhibiting Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
Images
Abstract
【課題】鋼管杭を使用しても安価で且つ水平抵抗力の高い鋼管杭基礎構造を提供する。
【解決手段】地盤2中に貫入された鋼管杭4Aの外側に、その上方から所定の深さにボイド管8を設置し、ボイド管内にコンクリート6Bを配したもので、鋼管杭4Aの水平抵抗力を向上させたものである。コンクリート6B内に、鉄筋を配することにより、さらに水平抵抗力を増大させることができる。
【選択図】図1To provide a steel pipe pile foundation structure that is inexpensive and has a high horizontal resistance even when a steel pipe pile is used.
SOLUTION: A steel pipe pile 4A penetrated into the ground 2 has a void pipe 8 installed at a predetermined depth from above, and a concrete pipe 6B is arranged in the void pipe. It is an improvement in power. By arranging a reinforcing bar in the concrete 6B, the horizontal resistance can be further increased.
[Selection] Figure 1
Description
本考案は、鋼管杭を使用する鋼管杭基礎構造に関する。 The present invention relates to a steel pipe pile foundation structure using a steel pipe pile.
一般的に軟弱地盤上に構築される鉄筋コンクリート造などの建物は、軟弱地盤の下方に位置する支持地盤にまで打ち込まれる鉄筋コンクリート杭や鋼管杭などの杭によって鉛直荷重が支持されるようになっている。しかしながら、このような杭は鉛直荷重を支持しながら、地震などの水平荷重にも十分に耐えることが必要である。このため、特許文献1には、軟弱地盤上に構築された建物が基礎スラブとピン接合された支持杭で支持され、この支持杭の上部外周を覆うようにして鋼管杭が打設され、この鋼管杭と支持杭の間に緩衝材が充填される基礎構造が開示されている。これによって、支持杭が基礎スラブとピン接合されたことにより、地震などの水平荷重により支持杭に発生する曲げモーメントを小さくすると共に、支持杭が軟弱地盤に拘束されず、鋼管杭内においてピン接合部を中心に回転変形することができるので、水平荷重を減衰させることができるものである。さらに、鋼管杭で支持杭の上部外周を保護できるものである。 In general, buildings such as reinforced concrete structures built on soft ground are supported by vertical piles such as reinforced concrete piles and steel pipe piles that are driven down to the support ground located below the soft ground. . However, such piles need to withstand horizontal loads such as earthquakes while supporting vertical loads. For this reason, in Patent Document 1, a building constructed on soft ground is supported by a support pile pin-bonded to the foundation slab, and a steel pipe pile is placed so as to cover the upper outer periphery of this support pile. A foundation structure in which a buffer material is filled between a steel pipe pile and a support pile is disclosed. As a result, the support pile is pin-bonded to the foundation slab, so that the bending moment generated in the support pile due to a horizontal load such as an earthquake is reduced, and the support pile is not constrained by the soft ground and is pinned in the steel pipe pile. Since it can be rotationally deformed around the part, the horizontal load can be attenuated. Furthermore, the upper outer periphery of a support pile can be protected with a steel pipe pile.
特許文献2は、ソイルセメント柱の先端が確実に支持層に到達することを確認でき、また必ずしも鋼管杭の先端を支持層に到達させなくてもソイルセメント合成杭としての鉛直支持力と地表面付近における水平抵抗力を高めるソイルセメント合成杭の造成方法及びソイルセメント合成杭を提案することを目的とするものである。このため、この特許文献2は、掘進抵抗値の変化により先端が支持層に到達していることを確認しえソイルセンメント柱を構築した後、少なくとも頭部付近、先端部付近及び昼間部に翼部を有する翼付きの鋼管杭をソイルセメント柱中に挿入してソイルセメント合成杭を造成する造成方法を開示する。これによって、ソイルセメント柱中に翼付きの鋼管杭が挿入されることで、鋼管杭とソイルセメント柱との一体性が強まり、鉛直支持能力及び地表面付近での水平抵抗も向上するものである。
特許文献3は、地中に設けられた下部構造物が、地中に所定の範囲及び間隔で複数本立設された杭と、この杭の頭部を囲むように杭の外径より大径の鋼製型枠部材(鋼板)をほぼ同軸上に配置し、これら型枠部材を鋼製地中梁を介して接続し、鋼製型枠部材の内部にコンクリートを充填してフーチングを築造したものを開示する。 In Patent Document 3, a plurality of substructures provided in the ground have a diameter larger than the outer diameter of the pile so as to surround a pile of a plurality of standing structures in the ground with a predetermined range and interval. Steel formwork members (steel plates) are arranged almost coaxially, these formwork members are connected via steel underground beams, and concrete is filled in the steel formwork members to build a footing. Is disclosed.
特許文献4は、翼が傾斜して取り付けられた短管からなる鋼管杭と、連結手段により前記鋼管杭にトルクの伝達可能且つ軸方向に着脱可能に連結されたケーシングとからなる良く付き鋼管部材を有し、この翼付き交換部材を地中にねじ込んで埋設したのち、翼付き鋼管部材内に鉄筋又はコンクリート杭を建て込んでコンクリート又は固化剤を打設又は注入し、前記ケーシングを引き抜いて造成する場所打ち杭を開示する。 Patent Document 4 discloses a well-attached steel pipe member comprising a steel pipe pile made of a short pipe attached with inclined wings, and a casing connected to the steel pipe pile by a connecting means so as to be capable of transmitting torque and being detachable in the axial direction. After the winged replacement member is screwed and buried in the ground, a reinforcing bar or concrete pile is built into the winged steel pipe member, and concrete or a solidifying agent is placed or injected, and the casing is pulled out to form Disclose the cast-in-place pile.
特許文献5は、杭頭部に羽根や大径の円筒状部材がなくても、杭頭部における水平荷重に対する抵抗力が大きく、特に支持層が傾斜する地盤に適用しても、杭頭部の切除が容易で、且つ杭頭部における水平荷重に対する大きな抵抗力を発揮し得る構造のソイルセメント合成翼付き杭を開示する。
以上の引例から明らかなように、基礎杭に対して鉛直荷重に対してはもちろん、十分な水平抵抗力を有することが求められている。また、従来工法では、鋼管材料に規格内での基準強度を元に選定されているため、必要な水平抵抗力を達成するために、鋼管肉厚が大幅に増加する傾向にあった。また、昨今の鋼管杭の高騰化に伴い、鋼管杭による安価な基礎構造が求められている。 As is clear from the above references, the foundation pile is required to have a sufficient horizontal resistance force as well as a vertical load. Moreover, in the conventional construction method, since the steel pipe material is selected based on the standard strength within the standard, the steel pipe wall thickness tends to increase significantly in order to achieve the necessary horizontal resistance. In addition, with the recent rise in steel pipe piles, an inexpensive foundation structure using steel pipe piles is required.
このため、この考案は、鋼管杭を使用しても安価で且つ水平抵抗力の高い鋼管杭基礎構造を提供することにある。 For this reason, this device is to provide a steel pipe pile foundation structure that is inexpensive and has a high horizontal resistance even when a steel pipe pile is used.
この考案は、地盤中に貫入された鋼管杭の外側に、その上方から所定の深さでコンクリートを配することにある(請求項1)。また、前記コンクリート内には、鉄筋が配されることが望ましい。(請求項2) The idea is to place concrete at a predetermined depth from above on the outside of a steel pipe pile that has penetrated into the ground (claim 1). Moreover, it is desirable that a reinforcing bar is arranged in the concrete. (Claim 2)
この鋼管杭構造は、地盤に鋼管杭を回転又は打設によって貫入し、この貫入された鋼管杭に沿って、外側掘削オーガーによって所定の径、所定の深さで鋼管杭の外側を掘削し、そこにボイド管を投入し設置する。この段階で、前記ボイド管の中に鉄筋を投入設置し、コンクリートを充填することによって鋼管杭基礎構造の形成工程を完了する。 This steel pipe pile structure penetrates the steel pipe pile into the ground by rotating or driving, and excavates the outer side of the steel pipe pile with a predetermined diameter and predetermined depth by an outer excavating auger along the penetrated steel pipe pile, A void tube is inserted and installed there. At this stage, the steel pipe pile foundation structure forming process is completed by inserting and installing reinforcing bars in the void pipe and filling it with concrete.
この考案の鋼管杭基礎構造によれば、地盤に貫入される鋼管杭の上部を、外側からコンクリートによって補強した構造であることから、安価に地表面近傍の水平抵抗力を向上させることができるものである。また、これによって、鋼管杭の厚さを、水平抵抗力を増大させるという理由だけで厚くすることを防止することができるものである。 According to the steel pipe pile foundation structure of this device, the upper part of the steel pipe pile that penetrates the ground is reinforced with concrete from the outside, so that the horizontal resistance near the ground surface can be improved at low cost. It is. Moreover, this can prevent the thickness of the steel pipe pile from being increased simply because the horizontal resistance force is increased.
以下、この考案の実施例について図面により説明する。 Embodiments of the present invention will be described below with reference to the drawings.
図1(a)に示すこの考案の実施例1に係る鋼管杭基礎構造1は、以下の方法で形成される。先ず、(1)支持層まで鋼管杭4Aを打設する。(2)その鋼管杭4Aに沿って外側掘削オーガー(図示しない)によって所定の深さまで鋼管杭4Aの外側を円筒状に掘削して穴9を形成する。(3)円筒状に掘削された穴9にボイド管8を設置する。(4)ボイド管内にコンクリートを充填してコンクリート部6Bを形成する。
The steel pipe pile foundation structure 1 which concerns on Example 1 of this invention shown to Fig.1 (a) is formed with the following method. First, (1) the
これによって、鋼管杭4Aの上部の外側にコンクリート部6Bが形成されるため、鋼管杭4Aの上部における水平抵抗力を増大させることができる。これによって、鋼管杭の厚さを、水平抵抗力を増大させるという理由だけで厚くすることを防止することができるものである。
Thereby, since the
図1(b)に示すこの考案の実施例2に係る鋼管杭基礎構造1は、以下の方法で形成される。先ず、(1)支持層まで鋼管杭4Aを打設する。(2)その鋼管杭4Aに沿って外側掘削オーガー(図示しない)によって所定の深さまで鋼管杭4Aの外側を円筒状に掘削して穴9を形成する。(3)円筒状に掘削された穴9にボイド管8を設置する。(4)このボイド管8と鋼管杭4Aの間に、縦筋金7A’と横筋金7B’によって円筒状に形成された鉄筋を配置して円筒状の鉄筋部7’を設け、(5)前記ボイド管内にコンクリートを充填して鉄筋部7’を有するコンクリート部6Bを形成する。
The steel pipe pile foundation structure 1 which concerns on Example 2 of this invention shown in FIG.1 (b) is formed with the following method. First, (1) the
これによって、鋼管杭4Aの上部の外側に、鉄筋部7’を有するコンクリート部6Bが形成されるため、鋼管杭4Aの上部における水平抵抗力を増大させることができる。これによって、鋼管杭の厚さを、水平抵抗力を増大させるという理由だけで厚くすることを防止することができるものである。
Thereby, since the
1 鋼管杭基礎構造
2 地盤
4A 鋼管杭
5 底板部
6B コンクリート部
7’ 鉄筋部
7A’ 縦筋金
7B’ 横筋金
8 ボイド管
9 穴
DESCRIPTION OF SYMBOLS 1 Steel
Claims (2)
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2008125872A Continuation JP2009275377A (en) | 2008-05-13 | 2008-05-13 | Steel pipe pile foundation structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JP3190983U true JP3190983U (en) | 2014-06-05 |
Family
ID=
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2017137698A (en) * | 2016-02-04 | 2017-08-10 | Jfeスチール株式会社 | Cast-in-place pile and construction method for the same |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2017137698A (en) * | 2016-02-04 | 2017-08-10 | Jfeスチール株式会社 | Cast-in-place pile and construction method for the same |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101014796B1 (en) | Top-down underground construction method using prefabricated concrete column member as temporary bridge column | |
JP2013136922A (en) | Earth retaining wall supporting method, earth retaining wall supporting structure, and underground skeleton constructing method | |
JP2009167660A (en) | Tower crane foundation structure and method of constructing the same | |
JP5937488B2 (en) | Temporary support method for foundation | |
KR101195235B1 (en) | Underground structure construction method using composite pile | |
JP5976373B2 (en) | Pile foundation reinforcement structure and reinforcement method | |
JP2004244955A (en) | Cast-in-place concrete-filled steel pipe pile, construction method for cast-in-place concrete-filled steel pipe pile and foundation structure of structure | |
JP2011236705A (en) | Foundation structure of structure and method of constructing the same | |
KR20120102480A (en) | Phc pile with improved end bearing capacity and piling method of phc pile using the same | |
JP5077857B1 (en) | Seismic reinforcement structure of existing structure foundation by composite ground pile foundation technology | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
JP6542036B2 (en) | Pile foundation structure | |
JP6229294B2 (en) | Method of rebuilding a structure having an underground structure and underground structure | |
JP6461690B2 (en) | Foundation structure and foundation construction method | |
JP5176788B2 (en) | Construction method of underground structure | |
JP2012087561A (en) | Construction method of outer peripheral column in inverted construction | |
JP3190983U (en) | Steel pipe pile foundation structure | |
JP2005282043A (en) | Earth retaining wall reinforcing method | |
JP6416139B2 (en) | Cast-in-place pile and its construction method | |
JP5423134B2 (en) | Foundation structure | |
JP6860895B2 (en) | Retaining wall and its construction method | |
KR20130073336A (en) | Pile structure and construction methods | |
JP2017197910A (en) | Construction method of earth retaining wall structure, and earth retaining wall structure | |
JP6832761B2 (en) | How to rebuild the building | |
JP2011157719A (en) | Earth retaining method |