JP3139367B2 - Continuous underground wall construction method - Google Patents

Continuous underground wall construction method

Info

Publication number
JP3139367B2
JP3139367B2 JP08076707A JP7670796A JP3139367B2 JP 3139367 B2 JP3139367 B2 JP 3139367B2 JP 08076707 A JP08076707 A JP 08076707A JP 7670796 A JP7670796 A JP 7670796A JP 3139367 B2 JP3139367 B2 JP 3139367B2
Authority
JP
Japan
Prior art keywords
concrete
groove
construction method
continuous underground
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP08076707A
Other languages
Japanese (ja)
Other versions
JPH09264017A (en
Inventor
哲司 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP08076707A priority Critical patent/JP3139367B2/en
Publication of JPH09264017A publication Critical patent/JPH09264017A/en
Application granted granted Critical
Publication of JP3139367B2 publication Critical patent/JP3139367B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、連続地中壁工法
に関し、特に、縦溝掘進機により掘削形成された縦溝内
にコンクリートを打設し、これを硬化させる工程を、構
築すべき壁体の延長方向に順次繰り返して、これらの縦
溝内のコンクリートが連続一体化した連続壁を構築する
ための連続地中壁工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a continuous underground wall construction method, and more particularly, to a method in which concrete is poured into a vertical groove excavated by a vertical excavator and the concrete is hardened. The present invention relates to a continuous underground wall construction method for constructing a continuous wall in which concrete in these flutes is continuously integrated by successively repeating in a body extending direction.

【0002】[0002]

【従来の技術】連続地中壁工法は、例えば矩形状の掘削
断面形状を有する各種の縦溝掘削機を用いて、掘削中の
縦溝内に泥水を充填することにより壁面の崩壊を防止し
ながら、所定の深度まで掘削作業を行い、しかる後に、
充填した泥水をコンクリートと置き換えてこれを固化す
ることにより単位壁体とし、この単位壁体を、構築すべ
き壁体の延長方向に連続形成して、かかる複数の単位壁
体が一体となった連続地中壁を構築するものであり、こ
のようにして構築された連続地中壁は、これによって囲
まれる地盤の掘削作業を可能にする土留壁や基礎杭、あ
るいは地中構造物の一部として用いれらるものである。
2. Description of the Related Art A continuous underground wall construction method uses, for example, various flute excavators having a rectangular excavation cross-sectional shape to prevent collapse of a wall surface by filling muddy water into a flute during excavation. While excavating to a predetermined depth,
The filled muddy water is replaced with concrete and solidified to form a unit wall, and this unit wall is continuously formed in the extending direction of the wall to be constructed, and the plurality of unit walls are integrated. A continuous underground wall is to be constructed, and the continuous underground wall constructed in this manner is a retaining wall, a foundation pile, or a part of an underground structure that enables excavation work of the ground surrounded by the underground wall. It is used as

【0003】このような連続地中壁工法においては、縦
溝内の泥水をコンクリートと置き換える作業は、例えば
トレミー管等の配管を介して、縦溝の下方部分から、コ
ンクリートを縦溝内に順次落下打設してゆくことにより
行われるが、このような配管を介したコンクリートの打
設作業を容易にすべく、また、コンクリートを縦溝内に
比較的早い速度で打ち上げて行くことを目的として、流
動性の良いコンクリートが使用される場合が多い。
In such a continuous underground wall construction method, the work of replacing the muddy water in the flutes with concrete involves, for example, passing concrete from the lower part of the flute into the flute through a pipe such as a tremy pipe. It is performed by dropping and casting, but in order to facilitate the work of placing concrete through such pipes, and to launch concrete at a relatively high speed in vertical grooves. In many cases, concrete with good fluidity is used.

【0004】そして、このような連続地中壁工法に用い
られるコンクリートは、その流動性を確保するために、
コンクリートの水和反応に必要な水以外の余剰水を多量
に含んでいるため、コンクリートを打設した後、硬化す
るまでの間に、多量のブリージングが発生することにな
る。
[0004] The concrete used for such a continuous underground wall construction method is required to ensure its fluidity.
Since a large amount of surplus water other than the water necessary for the hydration reaction of the concrete is contained, a large amount of breathing occurs after the concrete is cast and before it is hardened.

【0005】すなわち、このブリージングは、コンクリ
ート中の比重の小さい成分である水や、これにセメント
ペースト分やモルタル分が混入した、いわゆるブリージ
ング水が、コンクリート中の骨材の間隙を縫うようにし
て水みちを作りながら上方に上昇してゆく現象であり、
特に連続地中壁工法においては、柔らかい状態のコンク
リートが大きな圧力を受けることになって多量かつ勢い
の強いブリージングを生じることになる。
[0005] That is, the breathing is carried out in such a manner that water, which is a component having a small specific gravity in the concrete, or so-called breathing water in which a cement paste component and a mortar component are mixed, sew the gap between the aggregates in the concrete. It is a phenomenon that rises upward while making water paths,
In particular, in the continuous underground wall construction method, the concrete in a soft state receives a large pressure, so that a large amount of strong breathing occurs.

【0006】また、この連続地中壁工法におけるブリー
ジングは、縦溝の内壁面の近傍、すなわち打設したコン
クリートの外周部分に沿って生じる場合が多く、かかる
部分には多くの水みちができて、この部分のコンクリー
トのセメント分が洗い流されることになり、その結果、
この部分には品質の劣るコンクリートしか形成されない
ことになる。
[0006] In addition, breathing in the continuous underground wall construction method often occurs near the inner wall surface of the vertical groove, that is, along the outer peripheral portion of the poured concrete, and many water channels are formed in such a portion. , The cement in this part of the concrete will be washed away,
Only poor quality concrete will be formed in this area.

【0007】そして、従来の連続地中壁工法において
は、このような外周部分のコンクリートを断面欠損部分
と考えて、例えばコンクリートのかぶりを大きく取り、
品質の劣るコンクリートを除いた断面で強度を発揮でき
るような設計を行なう方法が採用されていた。
[0007] In the conventional continuous underground wall construction method, the concrete on the outer peripheral portion is considered to be a portion having a cross-sectional defect, and for example, the cover of the concrete is largely removed.
A method has been adopted in which a design is made so that the strength can be exerted in a section excluding concrete of inferior quality.

【0008】[0008]

【発明が解決しようとする課題】しかしながら、従来の
ように、縦溝に打設されたコンクリートの外周部分を断
面欠損部分と考えて大きな断面で設計する方法によれ
ば、連続地中壁がこの部分を加えた大きさの断面を有す
ることとなるように、余堀部分を加えた掘削断面で掘削
作業を行う必要を生じるとともに、かかる余堀部分のコ
ンクリートを余分に加えてコンクリートを打設する必要
があるため、施工費や材料費が嵩むことになる。
However, according to the conventional method of designing a concrete having a large cross-section by considering the outer peripheral portion of the concrete cast in the vertical groove as a cross-section defect portion, the continuous underground wall has a problem. It is necessary to perform the excavation work on the excavated cross section including the surplus part so as to have the cross section of the size including the part, and concrete is added by adding the extra concrete of the surplus part. Because of the necessity, construction costs and material costs increase.

【0009】一方、多量のブリージングが生じないよう
に、連続地中壁工法のためのコンクリートとして、水中
不分離性を有するコンクリートを使用することも考えら
れるが、かかるコンクリートは、一般に高価であって経
済的な施工を行うことができない。
On the other hand, it is conceivable to use underwater inseparable concrete as concrete for the continuous underground wall construction method so as not to cause a large amount of breathing. However, such concrete is generally expensive. Economical construction cannot be performed.

【0010】そこで、この発明は、かかる従来の課題に
着目してなされたもので、ブリージングの発生による断
面欠損部分の範囲を小さく留めて、効率的かつ経済的な
連続地中壁の設計、施工を行うことを可能にする連続地
中壁工法を提供することを目的とするものである。
In view of the foregoing, the present invention has been made in view of such a conventional problem, and the design and construction of an efficient and economical continuous underground wall by keeping the area of a cross-sectional defect due to the occurrence of breathing small. It is an object of the present invention to provide a continuous underground wall construction method capable of performing the following.

【0011】[0011]

【課題を解決するための手段】そして、この発明は、上
記目的を達成するためになされたもので、その要旨は、
縦溝掘進機により掘削形成された縦溝内にコンクリート
を打設し、これを硬化させる工程を、構築すべき壁体の
延長方向に順次繰り返して、これらの縦溝内のコンクリ
ートが連続一体化した連続壁を構築するための連続地中
壁工法において、前記各縦溝内にコンクリートを打設す
る際に、縦溝の内壁面に沿って延長し、断面コの字形の
溝形形状であって、その開口面を覆うようにして粗骨材
を通過させない程度の目の大きさの金網が取り付けられ
てなるブリージング水の排出溝を人工的に設けることを
特徴とする連続地中壁工法にある。
SUMMARY OF THE INVENTION The present invention has been made to achieve the above object, and the gist of the invention is as follows.
The process of placing concrete in the flutes excavated and formed by the flute machine and curing it is sequentially repeated in the direction of extension of the wall to be constructed, and the concrete in these flutes is continuously integrated. In the continuous underground wall construction method for constructing a continuous wall, when concrete is poured into each of the vertical grooves, the concrete wall extends along the inner wall surface of the vertical groove, and has a U-shaped cross section. A continuous underground wall construction method characterized by artificially providing a draining groove for breathing water to which a wire mesh having a mesh size enough to prevent the coarse aggregate from passing so as to cover the opening surface. is there.

【0012】ここで、上記記載において、人工的に設け
る排出溝とは、ブリージングの発生により、コンクリー
ト中に自然に生じる排出溝としての水みち以外の、例え
ば断面コの字形の溝形形状であって、その開口面を覆う
ようにして粗骨材を通過させない程度の目の大きさの金
網が取り付けられてなる溝状の部材を縦溝の内壁面に沿
って延長配設することにより、コンクリート中のブリー
ジング水を当該溝状の部材内に流入させ、これに沿って
移動させるような、排出用の溝部材を別途取り付けるこ
とによって形成される排出溝を意味するものである。
Here, in the above description, the artificially provided discharge groove is, for example, a groove shape having a U-shaped cross section other than a water channel as a discharge groove naturally generated in concrete due to the occurrence of breathing. Te, by extending disposed along the groove-like parts material wire mesh size of the eye so as not to pass through the way coarse aggregate covering the opening surface is mounted to the inner wall surface of the longitudinal groove, This means a discharge groove formed by separately attaching a discharge groove member that allows breathing water in concrete to flow into and move along the groove-shaped member.

【0013】そして、この発明の連続地中壁工法によれ
ば、上記縦溝の内壁面に沿って延長配設される人工的な
ブリージング水の排出溝は、例えば溝部材を、掘削形成
された縦溝内にコンクリートの打設作業に先立って設置
される補強用の鉄筋篭に対して、これが縦溝内に設置さ
れた場合に縦溝の内壁面に沿って配設されるような位置
に、予め取り付けておけば、この鉄筋篭を縦溝内に建て
込むことにより、所望の位置に当該溝部材が容易に設置
されて人工的な排出溝が形成されることになる。
According to the continuous underground wall construction method of the present invention, the artificial breathing water discharge groove extending along the inner wall surface of the vertical groove is formed by excavating a groove member, for example. Reinforcement cages for reinforcement installed prior to concrete placement in the flutes should be placed along the inner wall of the flutes when they are installed in the flutes. If it is attached in advance, by embedding this rebar cage in the vertical groove, the groove member is easily installed at a desired position, and an artificial discharge groove is formed.

【0014】また、縦溝の内壁面に沿って溝部材を延長
配設した後、縦溝内にコンクリートを打設すると、コン
クリート中の余剰水は、若干のペースト分やモルタル分
を伴いながら、ブリージング水として溝部材により形成
された排出溝の中に容易に浸出流入し、これに沿ってス
ムースに移動し排出されることになるので、コンクリー
ト中にブリージング水による多くの水みちが発生するこ
とがなく、また、ブリージング水によりコンクリートを
洗掘する力を容易に弱めることができる。
[0014] When concrete is poured into the vertical groove after the groove member is extended along the inner wall surface of the vertical groove, the excess water in the concrete is removed with a slight amount of paste or mortar. Breathing water easily leaches into and flows into the discharge grooves formed by the groove members, and moves smoothly along the discharge grooves to be discharged.Therefore, many water paths due to breathing water are generated in concrete. And the ability to scour concrete with breathing water can be easily reduced.

【0015】すなわち、この発明の連続地中壁工法によ
れば、ブリージング水を排出溝に集積しこれに沿ってス
ムースに移動排出することにより、コンクリート中に多
くの水みちが発生するのを効果的に抑制し、これによっ
て品質の劣るコンクリートの発生を容易に防止すること
ができるとともに、排出溝によって集中的にブリージン
グ水を排出し、また、排出溝は設計された所定の位置に
容易に延長配設することができるので、断面欠損の生じ
る位置を限定して多くの断面欠損を生じさせることな
く、効率の良い断面での連続地中壁の設計施工を、高価
な特別のコンクリートを用いることなく経済的に行うこ
とができることになる。
That is, according to the continuous underground wall construction method of the present invention, the breathing water is accumulated in the discharge ditch and smoothly moved and discharged along the discharge ditch, so that many water paths are generated in the concrete. To prevent the generation of inferior concrete, and to discharge bleeding water intensively by the discharge groove, and the discharge groove is easily extended to the designed position. It is possible to design and construct a continuous underground wall with an efficient cross-section by using expensive special concrete without limiting the location where the cross-section defect occurs and causing many cross-section defects. It can be done economically without.

【0016】[0016]

【発明の実施の形態】以下、この発明の好ましい実施の
形態すなわち実施例について、添付図面を参照しつつ詳
細に説明する。この実施例によれば、一般の連続地中壁
工法に使用する、従来より公知の各種の縦溝掘削機を用
いて、縦溝10を掘削形成し、図1に部分的な平面図と
して示すように、この縦溝10内に鉄筋篭11を建て込
んだ後、内部に充填されている泥水と置き換えるように
してコンクリートを打設するとともに、これを硬化させ
ることによって単位壁体12を形成し、このようにして
単位壁体12を形成する作業を、構築すべき連続地中壁
の延長方向に沿って順次連続して行ってゆくことによ
り、これらの単位壁体12が一体となった連続地中壁を
形成してゆくものである。そして、掘削形成された縦溝
10にコンクリートを打設する際に、この実施例の連続
地中壁工法が採用されることになる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments, ie, embodiments of the present invention will be described below in detail with reference to the accompanying drawings. According to this embodiment, a flute 10 is formed by excavation using various well-known flute excavators conventionally used for a general underground wall construction method, and is shown in a partial plan view in FIG. As described above, after the reinforcing bar 11 is erected in the vertical groove 10, concrete is poured in such a manner as to replace the muddy water filled therein, and the unit wall 12 is formed by hardening the concrete. By continuously performing the operation of forming the unit wall bodies 12 in this way along the extension direction of the continuous underground wall to be constructed, the unit wall bodies 12 are integrated into a continuous It forms an underground wall. Then, when the concrete is poured into the excavated vertical groove 10, the continuous underground wall construction method of this embodiment is adopted.

【0017】すなわち、この実施例によれば、各縦溝1
0の内壁面13に沿って、上下方向に延長する溝部材1
4が複数配設された状態で、縦溝10の内部にコンクリ
ートが打設されることになる。
That is, according to this embodiment, each longitudinal groove 1
Groove member 1 extending vertically along inner wall surface 13
Concrete is cast inside the vertical groove 10 in a state in which a plurality of 4 are arranged.

【0018】ここで、溝部材14は、図2に拡大して示
すように、断面コの字形の溝形形状の例えば鋼材からな
る部材であって、その両側辺部分15には、これの縁部
に沿って縦長に切り欠き形成された流入窓16が、上下
方向に間隔をおいて多数形成されている。
The groove member 14 is a member made of, for example, steel having a U-shaped cross section as shown in FIG. A large number of inflow windows 16 which are notched vertically along the portion are formed at intervals in the vertical direction.

【0019】また、この溝部材14には、コの字形断面
の開口面及び流入窓16を覆うようにして、粗骨材を通
過させない程度の目の大きさの金網19が取り付けられ
ており、コンクリートを打設する際に、当該コンクリー
トが溝部材14の内部に流入するのを制御している。
Further, a wire mesh 19 having a mesh size enough to prevent coarse aggregate from passing therethrough is attached to the groove member 14 so as to cover the opening surface of the U-shaped cross section and the inflow window 16. When the concrete is poured, the concrete is controlled to flow into the inside of the groove member 14.

【0020】そして、この溝部材14は、地上において
鉄筋篭11を製作する際に、この鉄筋篭11の側面に、
例えばスプリング部材17や弾性力のあるゴム状の取り
付け紐、あるいは番線や鋼棒等を介して取り付けられ、
鉄筋篭11とともに、縦溝10の内部に建て込み設置さ
れることになる。
The groove member 14 is provided on a side surface of the reinforcing bar 11 when the reinforcing bar 11 is manufactured on the ground.
For example, it is attached via a spring member 17 or a rubber-like attachment string having elasticity, or a wire or a steel rod,
Together with the reinforcing bar 11, it will be installed inside the vertical groove 10.

【0021】なお、この実施例では、鉄筋篭11の一対
の長辺部分には各々3ケ所、一対の短辺部分には各々1
ケ所の合計8カ所に溝部材14が取り付けられている
が、かかる溝部材14の設置数や設置間隔、あるいは溝
部材14の幅や高さ、形状等は使用するコンクリートの
品質や、縦溝10の長さ、幅等を鑑みて適宜設計される
ものである。
In this embodiment, three pairs of long sides of the reinforcing bar 11 and one pair of short sides of the pair of short sides are provided.
The groove members 14 are attached to a total of eight places, and the number and interval of the groove members 14 or the width, height, shape, and the like of the groove members 14 are determined by the quality of the concrete used, the length of the longitudinal grooves 10 and the like. It is appropriately designed in consideration of the length, width, and the like.

【0022】また、鉄筋篭11に取り付けられた溝部材
14は、縦溝10の内部に鉄筋篭11を建て込んだ後
に、例えば収縮固定状態にあったスプリング部材17を
解放してこれの付勢力により溝部材14を縦溝10の内
壁面13に押しつけることにより、あるいは取り付け紐
により取り付けられている場合には、縦溝10に打設し
たコンクリートの流動圧を背面から受けて内壁面13に
押しつけられることにより、縦溝10の内壁面13に沿
って上下方向に容易に延長配設されることになる。
Further, the groove member 14 attached to the reinforcing bar 11 releases the spring member 17 in the contracted and fixed state, for example, after the reinforcing bar 11 is built inside the longitudinal groove 10 and the urging force of the spring member 17 is released. By pressing the groove member 14 against the inner wall surface 13 of the vertical groove 10 or, when the groove member 14 is attached by a mounting cord, receiving the flow pressure of the concrete poured into the vertical groove 10 from the back and pressing the groove member 14 against the inner wall surface 13. By doing so, it can be easily extended in the vertical direction along the inner wall surface 13 of the vertical groove 10.

【0023】さらに、この実施例によれば、鉄筋篭11
の一対の短辺部分の一方に取り付けられた溝部材14
は、縦溝10内において、先行形成された単位壁体12
の端面18に当接設置されることにより、隣接する単位
壁体12の接続部分におけるブリージング水の排出を促
して、これらの連続する単位壁体12の強固な接続一体
化を容易に図ることができるようになっている。
Further, according to this embodiment, the reinforced cage 11
Groove member 14 attached to one of a pair of short side portions of
Is a unit wall 12 formed in advance in the vertical groove 10.
Abutting on the end face 18 of the unit wall, discharge of breathing water at a connection portion of the adjacent unit wall bodies 12 is promoted, and strong connection integration of these continuous unit wall bodies 12 can be easily achieved. I can do it.

【0024】そして、この実施例の連続地中壁工法によ
れば、次に、縦溝10内の泥水と置き換えるようにし
て、コンクリートを打設する作業を行う。
Then, according to the continuous underground wall construction method of this embodiment, a concrete placing operation is performed next so as to replace the muddy water in the vertical groove 10.

【0025】すなわち、かかるコンクリートの打設作業
は、例えば縦溝10内に吊り込んだトレミー管を介し
て、これの下端部分が打設されたコンクリート中に埋入
されている状態を保持しつつ、縦溝10の底部から上方
にコンクリートを順次打ち上げて行くことにより行われ
る。
That is, the concrete placing operation is performed, for example, through a tremy tube suspended in the vertical groove 10 while maintaining the state in which the lower end portion is buried in the cast concrete. The concrete is sequentially lifted upward from the bottom of the vertical groove 10.

【0026】ここで、この実施例によれば、かかるトレ
ミー管を介したコンクリートの打設作業を容易にすべ
く、余剰水の多い柔らかいコンクリートを使用すること
になるが、かかる多量の余剰水によって生じるブリージ
ング水を迅速かつスムースに排出することにより、コン
クリート中に多くの水みちが生じることを防止して品質
の良い連続地中壁が構築されることになる。
According to this embodiment, soft concrete with a large amount of surplus water is used in order to facilitate the work of placing concrete through the tremy tube. By discharging the generated breathing water quickly and smoothly, it is possible to prevent the formation of many water paths in the concrete and to build a high quality continuous underground wall.

【0027】すなわち、コンクリート中の余剰水は、ブ
リージング水となって流入窓16を介して溝部材14の
内部にスムースに浸出流入し(図2参照)、溝部材14
に沿って上方にスムースに移動し排出されることになる
ので、コンクリート中にブリージング水による多くの水
みちを生じることがなく、また、ブリージング水のコン
クリートを洗掘する力を容易に弱めることになる。
That is, the surplus water in the concrete becomes breathing water and smoothly leaches into the inside of the groove member 14 through the inflow window 16 (see FIG. 2).
It will move smoothly upward along the sea and will be discharged, so it will not cause many water paths due to breathing water in the concrete, and easily reduce the power to scour the concrete of the breathing water Become.

【0028】したがって、コンクリート中に多くの水み
ちが発生することによる品質の劣化を効果的に防止する
ことができるとともに、単位壁体12の断面欠損を溝部
材14による排出溝の部分のみに計画的に留めて、多く
の断面欠損を生じることなく、かつかぶり部分を大きく
とることなく効率の良い断面での連続地中壁の設計施工
を行うことができることになる。
Therefore, it is possible to effectively prevent the deterioration of the quality due to the generation of many water channels in the concrete, and to plan the sectional defect of the unit wall 12 only in the discharge groove portion by the groove member 14. In short, it is possible to design and construct a continuous underground wall with an efficient cross section without causing many cross-sectional defects and without taking a large cover portion.

【0029】なお、この発明は上記実施例の実施の態様
のものに限定されるものではなく、請求項に記載された
構成の範囲内において種々変更して採用することができ
る。例えば、縦溝の内壁面に沿って形成される排出溝
は、上下方向のみに設ける場合に限定されることなく、
これに加えてあるいはこれに代えて、横方向や斜め方向
にも設けることができる。また、溝部材14には、開口
面等を覆う金網19を必ずしも設ける必要はない。
The present invention is not limited to the embodiment of the above embodiment, but can be variously modified and adopted within the scope of the constitution described in the claims. For example, the discharge groove formed along the inner wall surface of the vertical groove is not limited to being provided only in the vertical direction,
Additionally or alternatively, they can be provided in the horizontal or oblique direction. Further, the wire member 19 does not necessarily need to be provided in the groove member 14 to cover the opening surface and the like.

【0030】[0030]

【発明の効果】以上詳細に説明したように、この発明の
連続地中壁工法によれば、掘削形成された各縦溝内にコ
ンクリートを打設する際に、縦溝の内壁面に沿って延長
するブリージング水の排出溝を人工的に設けることによ
り構成されるので、ブリージング水を排出溝に集積しこ
れに沿ってスムースに移動排出することにより、ブリー
ジングの発生による断面欠損部分の範囲を小さく留め
て、効率的かつ経済的な連続地中壁の設計、施工を容易
に行うことができる。
As described above in detail, according to the continuous underground wall construction method of the present invention, when concrete is poured into each excavated vertical groove, the concrete is placed along the inner wall surface of the vertical groove. Since it is configured by artificially providing a breathing water discharge groove that extends, breathing water is accumulated in the discharge groove and smoothly moved and discharged along this to reduce the area of the cross-sectional defect due to the occurrence of breathing. In this way, efficient and economical continuous underground wall design and construction can be easily performed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明の一実施例にかかる連続地中壁工法の
実施状況を説明する部分平面図である。
FIG. 1 is a partial plan view illustrating an implementation state of a continuous underground wall construction method according to an embodiment of the present invention.

【図2】縦溝の内壁面に沿って排出溝を人工的に設ける
際に使用する、溝部材の一例を示す拡大斜視図である。
FIG. 2 is an enlarged perspective view showing an example of a groove member used for artificially providing a discharge groove along an inner wall surface of a vertical groove.

【符号の説明】[Explanation of symbols]

10 縦溝 11 鉄筋篭 12 単位壁体 13 内壁面 14 溝部材(排出溝) DESCRIPTION OF SYMBOLS 10 Vertical groove 11 Reinforced basket 12 Unit wall 13 Inner wall surface 14 Groove member (discharge groove)

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 縦溝掘進機により掘削形成された縦溝内
にコンクリートを打設し、これを硬化させる工程を、構
築すべき壁体の延長方向に順次繰り返して、これらの縦
溝内のコンクリートが連続一体化した連続壁を構築する
ための連続地中壁工法において、前記各縦溝内にコンク
リートを打設する際に、縦溝の内壁面に沿って延長し、
断面コの字形の溝形形状であって、その開口面を覆うよ
うにして粗骨材を通過させない程度の目の大きさの金網
が取り付けられてなるブリージング水の排出溝を人工的
に設けることを特徴とする連続地中壁工法。
1. A step of placing concrete in a flute formed by a flute machine and curing the concrete in order in the direction of extension of a wall to be built, is sequentially repeated. In the continuous underground wall construction method for constructing a continuous wall in which the concrete is continuously integrated, when placing concrete in each of the vertical grooves, extending along the inner wall surface of the vertical grooves,
Artificially provide a breathing water discharge groove that has a U-shaped cross section and is fitted with a wire mesh that covers the opening surface and has a mesh size enough to prevent coarse aggregate from passing through. A continuous underground wall construction method.
JP08076707A 1996-03-29 1996-03-29 Continuous underground wall construction method Expired - Fee Related JP3139367B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP08076707A JP3139367B2 (en) 1996-03-29 1996-03-29 Continuous underground wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP08076707A JP3139367B2 (en) 1996-03-29 1996-03-29 Continuous underground wall construction method

Publications (2)

Publication Number Publication Date
JPH09264017A JPH09264017A (en) 1997-10-07
JP3139367B2 true JP3139367B2 (en) 2001-02-26

Family

ID=13613007

Family Applications (1)

Application Number Title Priority Date Filing Date
JP08076707A Expired - Fee Related JP3139367B2 (en) 1996-03-29 1996-03-29 Continuous underground wall construction method

Country Status (1)

Country Link
JP (1) JP3139367B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9248066B2 (en) 2013-09-17 2016-02-02 Panasonic Intellectual Property Management Co., Ltd. Wheelchair and combined bed

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9248066B2 (en) 2013-09-17 2016-02-02 Panasonic Intellectual Property Management Co., Ltd. Wheelchair and combined bed

Also Published As

Publication number Publication date
JPH09264017A (en) 1997-10-07

Similar Documents

Publication Publication Date Title
JP2007126846A (en) Reinforcing cage, construction method for cast-in-place concrete pile, and cast-in-place concrete pile
JP2837128B2 (en) Construction method of cast-in-place concrete pile
CN108867690A (en) The reverse construction of peg board barricade of big foundation pit
KR100383409B1 (en) Construction Method of Direct Foundation for using Caisson
JP3139367B2 (en) Continuous underground wall construction method
KR100699359B1 (en) Underground diaphragm wall with post-tensioning equipment and construction method the same
KR100995831B1 (en) A self-reliance wall
JP7085464B2 (en) How to build a retaining wall structure in the reverse striking method
KR101181619B1 (en) Building method of high wall block for large scale underground structure using earth anchor represtressing
JP2006037700A (en) Block for retaining wall and retaining wall structure
JP5681988B2 (en) Breakwater reinforcement method and reinforced breakwater
CN212104113U (en) Anchor pile and soil nail wall combined retaining structure
JP6453165B2 (en) Bottom plate construction method and bottom plate structure
CN112411590A (en) Underground diaphragm wall structure and construction method
JP6740064B2 (en) Construction method of concrete frame
JPS5945073B2 (en) Liner plate for shaft and its usage
JP3008804B2 (en) Joint structure in underground diaphragm wall
JPS58195692A (en) Sheathing wall for shaft pit
JP4100619B2 (en) Rock fall prevention method
CN215801568U (en) Bored concrete pile structure for reducing filling coefficient in ultra-deep silt geology
CN114808955A (en) Pile foundation and pile foundation reinforcing method
JP2558414B2 (en) Construction method of the main retaining wall and the retaining wall
KR200434400Y1 (en) Casing for earthquake
JP4576768B2 (en) Composite type underground continuous wall and construction method of the same wall
KR20090051727A (en) Serial waterproof wall grouting method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees