JP3106263B2 - Construction method of building frame using filled concrete steel column - Google Patents

Construction method of building frame using filled concrete steel column

Info

Publication number
JP3106263B2
JP3106263B2 JP04140088A JP14008892A JP3106263B2 JP 3106263 B2 JP3106263 B2 JP 3106263B2 JP 04140088 A JP04140088 A JP 04140088A JP 14008892 A JP14008892 A JP 14008892A JP 3106263 B2 JP3106263 B2 JP 3106263B2
Authority
JP
Japan
Prior art keywords
steel pipe
column
concrete
short
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP04140088A
Other languages
Japanese (ja)
Other versions
JPH05311745A (en
Inventor
公佑 橋本
泰夫 東端
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP04140088A priority Critical patent/JP3106263B2/en
Publication of JPH05311745A publication Critical patent/JPH05311745A/en
Application granted granted Critical
Publication of JP3106263B2 publication Critical patent/JP3106263B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、充填コンクリート
柱を用いる建物体の構築法、特に、その充填コンク
リートの軸力負担率が増大するように鉄骨柱を溶接によ
り結合する建物体の構築法に関する。
BACKGROUND OF THE INVENTION The present invention relates to a filled concrete steel.
The present invention relates to a method of constructing a building skeleton using pipe columns, and more particularly to a method of constructing a building skeleton combining steel columns by welding so as to increase the axial load ratio of the filled concrete.

【0002】[0002]

【従来の技術】従来の充填コンクリート鋼管柱を使う建
体の建築法は、下部躯体の柱形成位置に鋼管柱を建
てて、この鋼管柱の各梁取付部に鉄骨梁を取り付け、上
記鋼管柱の上に上方の鋼管柱を建てて、上方の鋼管柱の
梁取付部に鉄骨梁を取り付け、複数階の建物体を建て
て、下方の鋼管柱と下部体とを溶接し、かつ下方の鋼
管柱と上方の鋼管柱とを溶接等により接合してから、そ
れらの鋼管柱内をコンクリートを充填し、充填コンクリ
ート鋼管柱としている。また、従来の充填コンクリート
鋼管柱とH形鋼等の鉄骨梁との接合の仕方には、大別し
て、内ダイアフラム方式と外ダイアフラム方式とがあ
る。 (1)内ダイアフラム方式の鋼管柱1には、たとえば、
図14および図15に示すように、細長い鋼板に曲げ加
工を施して半円筒状体1A、1Bを形成し、鋼板を扇形
に切断して内ダイアフラム片2A、2Bを形成し、この
内ダイアフラム片2A、2Bの扇形の外周の円弧の半径
と前記半円筒状体1A、1Bの内周の円弧の半径とを略
合致させ、一対の半円筒状体1A、1Bの内周面のH形
鋼梁4のフランジ4aの取付位置に対応する各位置に内
ダイアフラム片2A、2Bを配し、各内ダイアフラム片
2A、2Bの外周部を各半円筒状体1A、1Bの内周面
に溶接し、一対の半円筒状体1A、1Bの長さ方向の縁
部1A1、1B1を合わせ、これらの縁部1A1、1B
1を互いに溶接して鋼管柱1を形成し、かつ一対のダイ
アフラム片2A、2Bにより内ダイアフラムを形成し、
かつ、鋼管柱1の外周部の鉄骨梁4のウェブ取付位置に
ガセツトプレート3を溶接したものがある。この鋼管柱
1を、建築現場に搬入し、所定位置に建ててから、鋼管
柱1のガセツト3に鉄骨梁4のウェブ4bを固定し、そ
の後に内ダイアフラム2に対応する鋼管柱1の外側部に
鉄骨梁4のフランジ4aを溶接する。鋼管柱1への鉄骨
梁4の取付が完了してから、鋼管柱1内にコンクリート
5を充填して、充填コンクリート鋼管柱としている。 (2)外ダイアフラム方式の鋼管柱には、たとえば、図
16および図17に示すように、既製の鋼管を所定長さ
に切断して鋼管柱6を形成し、鋼板を環形に切断して外
ダイアフラム7A、7Bを形成し、鋼管柱6に複数の環
形の外ダイアフラム7A、7Bを嵌め、鋼管柱6の鉄骨
梁4のフランジ4aの取付位置に対応する各位置に外ダ
イアフラム7A、7Bを位置させ、各外ダイアフラム7
A、7Bの内周部を鋼管柱6の外周部に溶接し、鋼管柱
6の外周部の鉄骨梁4のウェブ取付位置にガセツトプレ
ート3を溶接したものが提案されている。この鋼管柱6
を、建築現場に搬入し、所定位置に建ててから、鋼管柱
6のガセツトプレート3に鉄骨梁4のウェブ4bを固定
し、その後に鋼管柱6の外ダイアフラム7A、7Bの外
側部に鉄骨梁4のフランジ部4aを溶接する。鋼管柱6
への鉄骨梁4の取付が完了してから、鋼管柱6内にコン
クリートを充填し、充填コンクリート鋼管柱としてい
る。
2. Description of the Related Art A conventional method of building a building frame using a filled concrete steel tube column is to build a steel tube column at a column forming position of a lower frame and attach a steel beam to each beam mounting portion of the steel tube column. Build the upper steel column on the column, attach the steel beam to the beam mounting part of the upper steel column, build the multi-story building frame , weld the lower steel column and the lower frame , and After joining the lower steel column and the upper steel column by welding or the like, concrete is filled in the steel column to form a filled concrete steel column. In addition, conventional methods of joining a filled concrete steel pipe column to a steel beam such as an H-section steel are roughly classified into an inner diaphragm type and an outer diaphragm type. (1) In the inner diaphragm type steel pipe column 1, for example,
As shown in FIGS. 14 and 15, a long and thin steel plate is bent to form semi-cylindrical bodies 1A and 1B, and the steel plate is cut into a fan shape to form inner diaphragm pieces 2A and 2B. The radius of the arc of the outer circumference of the sector of 2A, 2B is substantially matched with the radius of the arc of the inner circumference of the semi-cylindrical bodies 1A, 1B, and the H-section steel on the inner peripheral surface of the pair of semi-cylindrical bodies 1A, 1B The inner diaphragm pieces 2A, 2B are arranged at respective positions corresponding to the mounting positions of the flanges 4a of the beam 4, and the outer peripheral portions of the inner diaphragm pieces 2A, 2B are welded to the inner peripheral surfaces of the semi-cylindrical bodies 1A, 1B. , A pair of semi-cylindrical bodies 1A, 1B in the longitudinal direction edge 1A1, 1B1 together, these edges 1A1, 1B
1 are welded to each other to form a steel pipe column 1 and an inner diaphragm is formed by a pair of diaphragm pieces 2A and 2B;
In some cases, the gusset plate 3 is welded to the steel tube 4 at the web mounting position of the steel beam 4 on the outer peripheral portion of the steel tube column 1. The steel pipe column 1 is carried into a construction site and is built at a predetermined position. Then, the web 4b of the steel beam 4 is fixed to the gusset 3 of the steel column 1, and then the outer portion of the steel column 1 corresponding to the inner diaphragm 2. Is welded to the flange 4a of the steel beam 4. After the attachment of the steel beam 4 to the steel pipe column 1 is completed, concrete 5 is filled in the steel pipe column 1 to form a filled concrete steel pipe column. (2) As shown in FIG. 16 and FIG. 17, for example, as shown in FIG. 16 and FIG. 17, a steel pipe column 6 is formed by cutting a ready-made steel pipe to a predetermined length, and a steel plate is cut into an annular shape to form an outer pipe. Diaphragms 7A, 7B are formed, a plurality of annular outer diaphragms 7A, 7B are fitted to the steel pipe column 6, and the outer diaphragms 7A, 7B are positioned at positions corresponding to the mounting positions of the flanges 4a of the steel beam 4 of the steel pipe column 6. Let each outer diaphragm 7
A proposal has been made in which the inner peripheral portions of A and 7B are welded to the outer peripheral portion of the steel pipe column 6, and the gusset plate 3 is welded to the web mounting position of the steel beam 4 on the outer peripheral portion of the steel pipe column 6. This steel pipe column 6
Is transported to a construction site, and is built at a predetermined position. Then, the web 4b of the steel beam 4 is fixed to the gusset plate 3 of the steel pipe column 6, and thereafter, the steel frame 4 is attached to the outer portions of the outer diaphragms 7A and 7B of the steel pipe column 6. The flange 4a of the beam 4 is welded. Steel column 6
After the attachment of the steel beam 4 to the steel pipe 4 is completed, concrete is filled in the steel pipe column 6 to form a filled concrete steel pipe column.

【0003】[0003]

【発明が解決しようとする課題】従来の充填コンクリー
ト鋼管柱を使う建物体の建築法は、複数階の建物
を建てて、鋼管柱等を相互に溶接等により接合してか
ら、各鋼管柱内をコンクリートを充填しているから、鋼
管柱には最初から軸方向の力が作用しており、充填コン
クリート鋼管柱の充填コンクリートの軸力負担率が小さ
い欠点がある。また、(1)の内ダイアフラム方式のも
のは、鉄骨梁4と鋼管柱1との曲げモーメントの釣合が
よい効果があるとともに、鉄骨梁4に作用する鉛直力を
鋼管柱1内の充填コンクリートに軸力としてうまく伝達
できる効果があり、構造的に合理的なものである。しか
し、梁取付位置に対応する鋼管柱1の内部にダイアフラ
ムを固定するには、内ダイアフラム片2A、2Bの外周
部を半円筒状体1A、1Bの内周面に溶接してから、一
対の半円筒状体1A、1Bの長さ方向の縁部1A1、1
B1を合わせ、これらの縁部1A1、1B1を互いに溶
接して鋼管柱1を形成する必要があり、このことがコス
トアップの要因になっている。さらに、(2)の外ダイ
アフラム方式のものは、比較的に安価な既製の鋼管を使
う目的で提案されたものであり、鉄骨梁4と鋼管柱6と
の曲げモーメントの釣合は内ダイアフラム方式と同様に
よいが、鉄骨梁4に作用する鉛直力の充填コンクリート
鋼管柱6内の充填コンクリートへの伝達は不充分であ
る。小規模の建物では、鉄骨梁に作用する鉛直力の充填
コンクリートへの伝達は、鋼管柱の内面と充填コンクリ
ートとの付着力、鋼管柱内の梁取付位置に設けたシアー
コネクタに作用する剪断力等により行っている。しか
し、長い鋼管柱内の梁取付位置にシアーコネクタを溶接
により固着することは非常に難しい作業である。大規模
な建物に適用できる一般化された外ダイアフラム方式に
よる設計法は未だ提案されていない。充填コンクリート
鋼管柱を使う構造設計は、充填コンクリートに軸力を負
担させることにより、柱耐力を合理的に増大できる長所
をもつから、その長所を充分に発揮し得る発明に対する
要望はきわめて高い。この発明の解決しようとする課題
は、上記の従来のものが具有する欠点をもたない充填コ
ンクリート鋼管柱を用いる建物体の構築法を提供する
こと、換言すると、充填コンクリートの軸力負担率を増
大させることができ、施工等も容易な充填コンクリート
鋼管柱を使う建物体の建築法を提供することにある。
A conventional method of building a building frame using filled concrete steel pipe columns is to build a multi-story building frame and weld the steel pipe columns and the like to each other by welding or the like. Since the inside of the steel pipe column is filled with concrete, an axial force acts on the steel pipe column from the beginning, and there is a drawback that the axial load burden ratio of the filled concrete of the filled concrete steel pipe column is small. Further, the inner diaphragm type (1) has an effect that the bending moment between the steel beam 4 and the steel pipe column 1 is well balanced, and the vertical force acting on the steel beam 4 is reduced by the filling concrete in the steel pipe column 1. Has an effect of being transmitted as an axial force, and is structurally rational. However, in order to fix the diaphragm inside the steel pipe column 1 corresponding to the beam mounting position, the outer peripheral portions of the inner diaphragm pieces 2A, 2B are welded to the inner peripheral surfaces of the semi-cylindrical bodies 1A, 1B, and then a pair of the inner diaphragm pieces 1A, 1B are welded. Semi-cylindrical bodies 1A, 1B Edges 1A1, 1 in longitudinal direction
B1 needs to be combined, and these edges 1A1 and 1B1 need to be welded to each other to form the steel pipe column 1, which causes a cost increase. Further, the outer diaphragm type of (2) is proposed for the purpose of using a relatively inexpensive off-the-shelf steel pipe, and the bending moment of the steel beam 4 and the steel pipe column 6 is balanced by the inner diaphragm type. However, the transmission of the vertical force acting on the steel beam 4 to the filled concrete in the filled concrete steel tubular column 6 is insufficient. In a small building, the vertical force acting on the steel beam is transmitted to the filled concrete by the adhesive force between the inner surface of the steel column and the filled concrete, and the shear force acting on the shear connector provided at the beam mounting position in the steel column. And so on. However, it is very difficult to fix the shear connector to the beam mounting position in the long steel pipe column by welding. A generalized outer diaphragm design method applicable to large-scale buildings has not yet been proposed. Structural design using filled concrete steel pipe columns has the advantage that the column strength can be rationally increased by bearing the axial force on the filled concrete, and there is a great demand for inventions that can fully demonstrate the advantages. The problem to be solved by the present invention is to provide a method of constructing a building skeleton using a filled concrete steel tubular column which does not have the above-mentioned disadvantages of the conventional one, in other words, an axial load burden ratio of the filled concrete. Filling concrete that can increase
An object of the present invention is to provide a building method of a building frame using steel pipe columns.

【0004】[0004]

【課題を解決するための手段】この発明は、前記課題を
解決するために、次の構成を採用するものである。この
発明の建物体の構築法は、仕口構成体として、短い鋼
管柱が既成の鋼管を梁成よりも少々長く切断して形成さ
れ、短い鋼管柱の外側に一対の外ダイアフラムが溶接さ
れ、外ダイアフラム間に梁取付用ガセットが溶接され、
短い鋼管柱の内側に中央部に開口ができるように内ダイ
アフラムが溶接され、短い鋼管柱内がコンクリートで満
たされ、短い鋼管柱内のコンクリート部分が短い鋼管柱
の下端および上端から下方および上方に突出して形成さ
れ、前記コンクリート部分に上下方向に延びる貫通開口
が形成されているものを用い、長い鋼管柱として、既成
の鋼管を所定の長さに切断して形成されているものを用
い、柱形成位置の同じ軸線上に長い鋼管柱と仕口構成体
の短い鋼管柱とが交互に建てられ、仕口構成体の前記コ
ンクリート部分の短い鋼管柱の下方および上方に突出し
ている部分が長い鋼管柱の端部内に嵌められ、長い鋼管
柱と仕口構成体の短い鋼管柱とが間隔保持手段を使って
長い鋼管柱の端面と短い鋼管柱の端面との間に小さな隙
間を保って仮結合され、長い鋼管柱内および仕口構成体
の前記コンクリート部分の貫通開口内がコンクリートで
満たされて充填コンクリート鋼管柱とされ、充填コンク
リート鋼管柱に鉛直方向の荷重が作用する状態にして、
間隔保持手段を除いて鉛直方向の荷重を各鋼管柱内のコ
ンクリートで支持した状態にしてから、長い鋼管柱の端
面と仕口構成体の短い鋼管柱の端面とを互いに溶接によ
り本結合することを特徴とするものである。短い鋼管
は、たとえば、横端面が円形または角形の既成の鋼管を
梁成よりも長く切断して形成し、長い鋼管柱は、たとえ
ば、横端面が円形または角形の既成の鋼管を所定長さに
切断して形成する。
The present invention adopts the following constitution in order to solve the above-mentioned problems. The construction method of a building frame according to the present invention uses a short steel
The column is formed by cutting an existing steel pipe a little longer than the beam
A pair of outer diaphragms are welded to the outside of a short steel column.
The gusset for beam attachment is welded between the outer diaphragms,
Inner die so that there is a central opening inside the short steel tube column
The afram is welded and the inside of the short steel tube column is filled with concrete.
The concrete part inside the short steel column is short
Formed downward and upward from the lower and upper ends of the
A through opening extending vertically in the concrete portion
Is used as a long steel pipe column.
Use a tube formed by cutting a steel pipe
A long steel pipe column and connection structure on the same axis at the column formation position
A short tubular columns are erected alternately, the U-Joint structure
Projects below and above short steel column of concrete part
Is inserted into the end of the long steel column
Between the column and the short steel tube column with the connection
A small gap between the end of the long steel column and the end of the short steel column
Temporarily joined with long intervals, inside long steel tube columns and connection structure
Wherein the through opening of the concrete part is satisfied by the concrete is the filling concrete tubular columns, in the state where the load is applied in the vertical direction to fill the concrete steel Columns,
Except for the spacing means, apply the vertical load to the
After the support state in Nkurito, is characterized in that the coupling by welding together the long steel column end face and the end face of the short tubular columns of Joint constructs. A short steel pipe column is formed, for example, by cutting an existing steel pipe having a circular or square lateral end face longer than a beam, and a long steel pipe column is formed, for example, by cutting an existing steel pipe having a circular or square lateral end face to a predetermined length. And formed.

【0005】仕口構成体の鉄骨部分は、短い鋼管柱の外
側に一対の外ダイアフラムを溶接し、外ダイアフラム間
に梁取付用ガセットを溶接し、短い鋼管柱の内側面
央部に開口ができるように内ダイアフラムを溶接し
成する。内ダイアフラムは環状または扇状のイアフラ
ムで構成す。また、短い鋼管柱内をコンクリートで満
たし、短い鋼管柱内のコンクリート部分を短い鋼管柱の
下端および上端から下方または上方に突出させて形成
し、かつ上下方向に延びる貫通開口を形成して仕口構成
体を構成すると、長い鋼管柱と仕口構成体との仮結合作
業等が容易になる。コンクリート部分の上下方向に延び
る貫通開口の下方の部分を下方に開く円錐面にすると、
長い鋼管柱内へのコンクリートの充填が容易になる。短
い鋼管柱内のコンクリート部分に上下方向に延ばして複
数本の連結鉄筋を埋設し、それらの連結鉄筋の上方の部
分および下方の部分をコンクリート部分の下端または上
端から下方または上方に長く突出させると、長い鋼管柱
内に後打ちする充填コンクリートとの一体性を増大させ
ることができる。
[0005] In the steel frame portion of the connection structure, a pair of outer diaphragms are welded to the outside of the short steel pipe column, and a gusset for beam attachment is welded between the outer diaphragms, so that the inside of the short steel pipe column has a middle part. to form <br/> formed by welding the inner diaphragm so as to be opened in the central portion. Inner diaphragm that make up an annular or sectorial da Iafura <br/> beam. In addition, the inside of the short steel pipe column is filled with concrete, the concrete portion in the short steel pipe pillar is formed by projecting downward or upward from the lower end and the upper end of the short steel pipe column, and a through-opening extending vertically is formed. When the structure is formed, the work of temporarily connecting the long steel pipe column and the connection structure is facilitated. If the lower part of the vertically extending through-opening of the concrete part is a conical surface that opens downward,
The filling of concrete into long steel tube columns is facilitated. When a plurality of connecting rebars are buried in the concrete part in a short steel pipe column by extending vertically, and the upper and lower parts of these connecting rebars are protruded downward or upward from the lower or upper end of the concrete part long. In addition, it can increase the integration with the post-filled concrete in the long steel pipe column.

【0006】間隔保持手段として、たとえば、比較的低
温で溶融する材料からなる環状の間隔保持環、衝撃的な
力を与える小片になる材料からなる環状の間隔保持環等
を使うが、必要時に容易に取り除くことができるものな
らどのようなものでもよい。なお、前記間隔保持環を使
う場合は、必要に応じて、その外周部を複数片に分割可
能な保護バンドで保護するとよい。長い鋼管柱は、たと
えば、(イ)その長手方向の寸法を階高寸法から仕口構
成体の短い鉄骨柱の長手方向の寸法を減じた寸法にした
もの、(ロ)その長手方向の寸法を階高寸法の2倍から
仕口構成体の短い鉄骨柱の長手方向の寸法を減じた寸法
にしたもの、(ハ)階高寸法の3倍から仕口構成体の短
い鉄骨柱の長手方向の寸法を減じた寸法にしたもの等を
使うことができる。(ロ)および(ハ)の場合は、長い
鋼管柱の鉄骨梁の取付位置に対応する1または2の位置
に、外ダイアフラムとなる一対の環状体を嵌め、各環状
体を柱鉄骨に溶接し、かつ一対の環状体の間に鉄骨梁の
ウェブの取付部となる梁取付用ガセットを溶接する。仕
口構成体の梁取付部に取り付ける梁としては、たとえ
ば、鉄骨梁または端部に露出している鉄骨部分のある鉄
骨鉄筋コンクリート梁を使う。この発明においては、仕
口構成体、長い鋼管柱および梁はユニット化して工場生
産することができる。
As the spacing means, for example, an annular spacing ring made of a material that melts at a relatively low temperature, an annular spacing ring made of a material that becomes a small piece that gives an impact force, and the like are used. Anything that can be removed in any way. When the spacing ring is used, the outer periphery thereof may be protected by a protective band which can be divided into a plurality of pieces as necessary. A long steel pipe column is, for example, (a) its longitudinal dimension reduced to the floor height dimension minus the longitudinal dimension of the short steel column of the connection structure, and (b) its longitudinal dimension. The length obtained by subtracting the longitudinal dimension of the short steel column of the connection structure from twice the floor height dimension, and (c) the length of the short steel column of the connection member being three times the floor height dimension It is possible to use a reduced size or the like. In cases (b) and (c), a pair of annular bodies serving as outer diaphragms are fitted at positions 1 or 2 corresponding to the mounting position of the steel beam of the long steel pipe column, and each annular body is welded to the column steel frame. A gusset for beam attachment, which serves as an attachment portion for a steel beam web, is welded between the pair of annular bodies. As the beam to be attached to the beam attachment portion of the connection structure, for example, a steel frame beam or a steel reinforced concrete beam having a steel frame portion exposed at an end is used. In the present invention, the connection structure, the long steel pipe column and the beam can be unitized and factory-produced.

【0007】[0007]

【実施例】実施例1を図1ないし図12を使って説明す
る。仕口構成体10は、図4および図5に示すように、
短い鋼管柱11、外ダイアフラムを構成する環状体1
2、シアーコネクタを構成する環状体13、鉄骨梁40
のウェブの取付部となる梁取付用ガセット14、コンク
リート部分16等で構成されている。図1および図2に
示すように、短い鋼管柱11は、既製の円形断面の鋼管
を梁成以上の長さに切って形成し、その上下の端面11
aを円錐面にする。ガセット14は鋼板を鉄骨梁40の
ウェブの成の幅に切って製作する。外側の環状体12は
鋼板製の環体で構成し、環状体12の周縁に直線部分を
形成し、この部分を鉄骨梁40のフランジの取付部12
aとする。一対の環状体12を鋼管柱11の外側に嵌
め、鉄骨梁40の梁成に合わせて、鋼管柱11に溶接す
る。鉄骨梁40の取付位置に対応する一対の環状体12
の間の鋼管柱11の外側面にガセット14を溶接する。
内側の環状体13は鋼板製の環体で構成し、環状体13
を短い鋼管柱11の中央の内側にその軸線方向に対して
直角に嵌め、鋼管柱11に溶接する。そして、図1およ
び図2に示す仕口構成体10の鉄骨部分10Aとする。
なお、一対の環状体12に対応する鋼管柱11の内側の
位置にそれぞれ環状体13を嵌め、各環状体13を鋼管
11に溶接し、図3に示すような仕口構成体10の鉄
骨部分10Aとしてもよい。円形の筒状部のある下側の
型枠の上に鉄骨部分10Aの短い鋼管柱11を立て、そ
の鋼管柱11の上に筒状部のある上側の型枠をのせ、下
方にゆくにしたがって径の大きくなる円錐形の部分とこ
の部分の上方に円柱状の部分とがある中子を、短い鋼管
柱11、上側の型枠および下側の型枠内の中央に立てて
成形型を作り、この成形型の短い鋼管柱11と中子との
間に複数本の連結鉄筋15を環状に配し、これらの連結
鉄筋の上下の両端を上側および下側の型枠から上方およ
び下方に突出させる。それから、成形型内にコンクリー
トを打設して、図4および図5に示す仕口構成体10を
製作する。
Embodiment 1 Embodiment 1 will be described with reference to FIGS. As shown in FIG. 4 and FIG.
Short steel tube column 11, annular body 1 constituting outer diaphragm
2. Annular body 13 and steel beam 40 constituting the shear connector
Gussets 14 and concrete portions 16 and the like, which serve as web mounting portions. As shown in FIGS. 1 and 2, the short steel pipe column 11 is formed by cutting a ready-made steel pipe having a circular cross section to a length equal to or longer than a beam, and forming upper and lower end faces 11 thereof.
Let a be a conical surface. The gusset 14 is manufactured by cutting a steel plate to the width of the web of the steel beam 40. The outer annular body 12 is constituted by an annular body made of a steel plate, and forms a linear portion on the periphery of the annular body 12, and this portion is attached to the flange mounting portion 12 of the steel beam 40.
a. Fitting a pair of annular body 12 to the outside of the tubular columns 11, in accordance with the RyoNaru of steel beam 40, welded to the steel pipe column 11. A pair of annular bodies 12 corresponding to the mounting position of the steel beam 40
The gusset 14 is welded to the outer surface of the steel pipe column 11 between the two.
The inner annular body 13 is constituted by an annular body made of a steel plate.
Is fitted inside the center of the short steel pipe column 11 at right angles to the axial direction thereof, and welded to the steel pipe column 11. And it is set as the steel-frame part 10A of the connection structure 10 shown in FIG.1 and FIG.2.
Incidentally, each fitted with a ring member 13 to the inner position of the steel pipe column 11 corresponding to the pair of annular body 12, each annular body 13 steel pipe
It may be welded to the column 11 to form the steel frame portion 10A of the connection structure 10 as shown in FIG. A short steel column 11 having a steel frame portion 10A is erected on a lower mold having a circular cylindrical portion, and an upper mold having a cylindrical portion is placed on the steel column 11, and as it goes down, A core having a conical portion having a large diameter and a columnar portion above this portion is erected at the center in the short steel tube column 11, the upper mold frame and the lower mold frame to form a molding die. A plurality of connecting rebars 15 are annularly arranged between the short steel pipe column 11 and the core of the forming die, and upper and lower ends of these connecting rebars project upward and downward from the upper and lower molds. Let it. Then, concrete is poured into the molding die, and the joint structure 10 shown in FIGS. 4 and 5 is manufactured.

【0008】図4および図5に示す仕口構成体10は、
そのコンクリート部分16が鋼管柱11の上下端から上
方および下方に突出している。そして、突出したコンク
リート部分16aの外径は、鋼管柱11の内径より少々
小さく、コンクリート部分16aの突出長さは、コンク
リート部分16aを後記の長い鋼管柱21の上方および
下方の部分に嵌合させたとき、その嵌合が容易に外れな
い程度の長さにする。コンクリート部分16内の中央に
形成した貫通開口16bの径は、長い鋼管柱21へのコ
ンクリートの充填が可能な寸法とする。前記貫通開口1
6bの下方の部分を下方に開く円錐面16cにし、長い
鋼管柱内21へのコンクリートの充填を容易にする。仕
口構成体10の突出したコンクリート部分16aには、
図8に示すように、短い鋼管柱11の上下の端面を接触
させて、環状の間隔保持体17を嵌めて固定しておく。
間隔保持環17は、図6および図7に示され、比較的低
温で溶融する材料、衝撃的な力を与える小片になる材料
で製作し、その上下の端面17aを短長の鋼管柱11、
21の上下の端面11a、21aと一致する円錐面とす
る。必要に応じて、間隔保持環17の外周に保護バンド
18を嵌め、間隔保持環17の不慮の破壊を防ぐ。保護
バンド18は、各バンド片18aが鋼管柱11、21の
外周面と合致した内周面を備えた短い円筒を4等分した
形状の円弧状板で形成され、その両端に形成した耳片1
8aをボルト・ナット等の適宜の脱着自在の固定具で
固定することにより、環状になるように構成されてい
る。長い鋼管柱21は、既製の円形断面の鋼管を階高寸
法から短い鋼管柱の長さを減じた寸法に切って形成し、
その上下の端面11aを円錐面にする。
The connection structure 10 shown in FIG. 4 and FIG.
The concrete portion 16 projects upward and downward from the upper and lower ends of the steel pipe column 11. The outer diameter of the protruding concrete portion 16a is slightly smaller than the inner diameter of the steel pipe column 11, and the protruding length of the concrete portion 16a allows the concrete portion 16a to be fitted to the upper and lower portions of the long steel pipe column 21 described later. The length is such that the fitting does not come off easily. The diameter of the through-opening 16b formed at the center in the concrete portion 16 is set to a size that allows the long steel pipe column 21 to be filled with concrete. The through opening 1
The lower part of 6b has a conical surface 16c that opens downward, facilitating the filling of the long steel tube column 21 with concrete. In the protruding concrete portion 16a of the connection structure 10,
As shown in FIG. 8, the upper and lower end faces of the short steel tube column 11 are brought into contact with each other, and the annular spacing member 17 is fitted and fixed.
Interval holding ring 17 is shown in FIGS. 6 and 7, a relatively material that melts at low temperatures, the impact force produced by the material to be small pieces to give the end face 17a of the upper and lower short length tubular columns 11,
The upper and lower end surfaces 21a and 21a of the 21 are conical surfaces. If necessary, a protective band 18 is fitted around the outer periphery of the spacing ring 17 to prevent accidental destruction of the spacing ring 17. The protection band 18 is formed of an arc-shaped plate in which each band piece 18a is formed by dividing a short cylinder having an inner peripheral surface that matches the outer peripheral surface of the steel pipe columns 11 and 21 into four equal parts, and ear pieces formed at both ends thereof. 1
8a 1 is formed in a ring shape by fixing it with an appropriate detachable fixing tool such as a bolt and a nut. The long steel pipe column 21 is formed by cutting a ready-made steel pipe having a circular cross section into a dimension obtained by subtracting the length of the short steel pipe column from the floor height dimension,
The upper and lower end surfaces 11a are formed as conical surfaces.

【0009】次に、仕口構成体10と長い鋼管柱21と
を使って建物躯体を構築する構築法を説明する。図9に
示すように、下部躯体の短い鋼管からなる柱取付部25
の上に第1の長い鋼管柱21を建て、柱取付部25の上
端のガセット25aと第1の長い鋼管柱21の下端のガ
セット21bとを連結板24を使って仮結合する。第1
の仕口構成体10を適宜の吊り揚げ手段にて吊り揚げ、
第1の長い鋼管柱21の上端に第1の仕口構成体10の
下方に突出したコンクリート部分16aを嵌める。それ
から、第1の仕口構成体10の環状体12間に鉄骨梁4
0を配し、鉄骨梁40の端部を第1の仕口構成体10の
ガセット14に、添え板、ボルト・ナット等を使って仮
取付をする。それから、第1の仕口構成体10のコンク
リート部分16の開口16b、の上端から、第1の長い
鋼管柱21内および開口16bにコンクリートを充填
し、仕口構成体10のコンクリート部分16と鋼管柱
1および開口16b内のコンクリート部分26とを一体
に結合する。同様のやり方にて、図10に示すように、
第1の仕口構成体10の上方に突出したコンクリート部
分16aに第2の長い鋼管柱21の下端を嵌めて、第1
の仕口構成体10の上に第2の長い鋼管柱21を建て
る。同様に、第2の長い鋼管柱21の上端に第2の仕口
構成体10の下方に突出したコンクリート部分16aを
嵌める。第2の仕口構成体10の環状体12間に鉄骨梁
40を配し、鉄骨梁40の端部を仕口構成体10のガセ
ット14に、添え板、ボルト・ナット等を使って仮取付
をする。同様に、第2の仕口構成体10のコンクリート
部分16の開口16bの上端から、第2の長い鋼管柱2
1および開口16b内にコンクリートを充填し、第2の
仕口構成体10のコンクリート部分16と第2の鋼管柱
21および開口16b内のコンクリート部分とを一体に
結合する。
Next, a description will be given of a construction method for constructing a building frame using the connection member 10 and the long steel pipe columns 21. As shown in FIG. 9, a column mounting portion 25 made of a steel pipe having a short lower frame is used.
A first long steel pipe column 21 is erected on the slab, and a gusset 25 a at the upper end of the column mounting portion 25 and a gusset 21 b at the lower end of the first long steel pipe column 21 are temporarily connected using the connecting plate 24. First
Hoisting the port structure 10 by an appropriate hoisting means,
The concrete portion 16a projecting downward from the first connection member 10 is fitted to the upper end of the first long steel pipe column 21. Then, the steel beam 4 is inserted between the annular bodies 12 of the first connection structure 10.
0, and the end of the steel beam 40 is temporarily attached to the gusset 14 of the first connection member 10 by using an attachment plate, a bolt and a nut, or the like. Then, concrete is filled into the first long steel pipe column 21 and the opening 16b from the upper end of the opening 16b of the concrete portion 16 of the first joint structure 10, and the concrete portion 16 of the joint structure 10 and the steel pipe are filled. Pillar 2
1 and the concrete portion 26 in the opening 16b. In a similar manner, as shown in FIG.
The lower end of the second long steel pipe column 21 is fitted to the concrete portion 16a protruding above the first connection structure 10, and the first
A second long steel pipe column 21 is erected on the connection structure 10 of FIG. Similarly, a concrete portion 16a projecting downward from the second connection structure 10 is fitted to the upper end of the second long steel pipe column 21. A steel beam 40 is arranged between the annular bodies 12 of the second connection structure 10, and the end of the steel beam 40 is temporarily attached to the gusset 14 of the connection structure 10 by using an attachment plate, a bolt, a nut, or the like. do. Similarly, from the upper end of the opening 16b of the concrete portion 16 of the second connection structure 10, the second long steel pipe column 2
1 and the opening 16b are filled with concrete, and the concrete portion 16 of the second connection structure 10 and the concrete portion in the second steel pipe column 21 and the opening 16b are integrally joined.

【0010】同様にやり方にて、第3、第4等の長い鋼
管柱、第3、第4等の仕口構成体、鉄骨梁等を組み立
て、順次コンクリートの充填を行い、多層の建物躯体を
構築して行く。適宜の時期に、鉄骨梁40の端部のフラ
ンジを第1の仕口構成体10の環状体12の取付部12
aに溶接する。なお、コンクリート26の充填による仕
口構成体10の短い鋼管柱11と長い鋼管柱21との一
体化作業は、上述のように階毎に行ってもよいし、2な
いし4階毎に行ってもよい。また、仕口構成体10の突
出したコンクリート部分16aと長い鋼管柱21との嵌
合のみによる仮結合では強度的に不充分である場合は、
図1に示すように、長い鋼管柱21の端部に溶接した
ガセット21bと短い鋼管柱11の端部に溶接したガセ
ット11bとを連結板24を使って着脱自在に連結し、
仮結合を完全なものにする。上層の建物躯体が構築さ
れ、充填コンクリート鋼管柱20に鉛直方向の荷重が作
用した状態になってから、仕口構成体10の短い鋼管柱
11および長い鋼管柱21について、連結板24を使っ
た場合はまず連結板24を外し、保護バンド18を使っ
た場合は保護バンド18を外してから、間隔保持環17
を溶解または衝撃的な力で破壊して取り除き、図12に
示すように、充填コンクリート鋼管柱20に作用する鉛
直方向の荷重をコンクリート部分17、26のみにより
支持させた状態にする。それから、短い鋼管柱11の端
面11aと長い鋼管柱21の端面21aとにより形成さ
れる隙間gを融かした溶接用鋼材で埋めて、短い鋼管柱
11の端面と長い鋼管柱21の端面とを互いに溶接によ
り本結合する。また、長い鋼管柱21および下部躯体の
柱取付部25について、連結板24を外し、長い鋼管柱
21の端面21aと柱取付部25の管体の上端面との間
の隙間gを融かした溶接用鋼材で埋めて、長い鋼管柱2
1と柱取付部25とを互いに溶接により本結合する。な
お、必要に応じて、溶接部の近傍の鋼管柱11、21の
内周面に対応するコンクリート部分16の周囲に断熱材
層19を埋設しておき、コンクリート部分16に溶接熱
による悪影響を与えないようにする。短い鋼管柱11と
長い鋼管柱21(および長い鋼管柱21と柱取付部2
5)との溶接部分は溶接後の冷却により収縮するから、
鋼管柱11、21の溶接部の近傍の部分は収縮力が作用
する状態になり、充填コンクリー鋼管柱20の充填コン
クリートの軸力負担率が増大する。そのため、建物の完
成後に、充填コンクリート鋼管柱20に大きな鉛直方向
の荷重が作用しても、鋼管柱11、21が座屈する恐れ
がない。
In the same manner, third and fourth long steel pipe columns, third and fourth connection members, steel beams and the like are assembled, concrete is sequentially filled, and a multi-layer building frame is formed. Build and go. At an appropriate time, the flange at the end of the steel beam 40 is attached to the attachment portion 12 of the annular body 12 of the first connection member 10.
Weld to a. The work of integrating the short steel column 11 and the long steel column 21 of the connection member 10 by filling the concrete 26 may be performed for each floor as described above, or may be performed for every two to four floors. Is also good. In addition, when the temporary connection only by fitting the protruding concrete portion 16a of the connection structure 10 to the long steel pipe column 21 is insufficient in strength,
As shown in FIG. 1 0, detachably connected with the connecting plate 24 and the gusset 11b welded to the end portion of the gusset 21b and short steel column 11 which is welded to an end portion of a long tubular columns 21,
Complete the temporary connection. After the upper building frame was constructed and a vertical load was applied to the filled concrete steel column 20, the connecting plate 24 was used for the short steel column 11 and the long steel column 21 of the connection structure 10. In this case, the connecting plate 24 is first removed, and when the protective band 18 is used, the protective band 18 is removed.
Is melted or broken by an impact force to remove it, and as shown in FIG. 12, the vertical load acting on the filled concrete steel pipe column 20 is supported only by the concrete portions 17 and 26. Then, a gap g formed by the end face 11a of the short steel pipe post 11 and the end face 21a of the long steel pipe post 21 is filled with a welding steel material that has been melted, and the end face of the short steel pipe post 11 and the end face of the long steel pipe post 21 are joined. They are permanently joined to each other by welding. Further, the connection plate 24 was removed from the long steel pipe column 21 and the column mounting portion 25 of the lower frame, and the gap g between the end surface 21a of the long steel pipe column 21 and the upper end surface of the pipe of the column mounting portion 25 was melted. Long steel pipe column 2 filled with welding steel
1 and the column mounting portion 25 are permanently connected to each other by welding. In addition, if necessary, a heat insulating material layer 19 is buried around the concrete portion 16 corresponding to the inner peripheral surfaces of the steel pipe columns 11 and 21 in the vicinity of the welded portion. Not to be. The short steel column 11 and the long steel column 21 (and the long steel column 21 and the column mounting portion 2)
Since the welded part with 5) shrinks due to cooling after welding,
The portion near the welded portion of the steel pipe columns 11 and 21 is in a state where a contraction force is applied, and the axial load burden ratio of the filled concrete of the filled concrete concrete steel pipe column 20 increases. Therefore, even if a large vertical load acts on the filled concrete steel pipe column 20 after the completion of the building, there is no possibility that the steel pipe columns 11 and 21 will buckle.

【0011】実施例2は、仕口構成体10として実施例
1と同じもの使い、長い鋼管柱31として階高寸法より
も長いものを使う例である。長い鋼管柱31として、そ
の長手方向の寸法を階高寸法の2倍から仕口構成体10
の短い鋼管柱11の長手方向の寸法を減じた寸法にした
ものを使った例が図13に示されている。長い鋼管柱3
1としては、たとえば、階高寸法の3倍から仕口構成体
10の短い鋼管柱11の長手方向の寸法を減じた寸法に
したものを使うこともできる。長い鋼管柱31の鉄骨梁
の取付位置に対応する1または2の位置に、一対の板状
の環状体32を嵌め、各環状体32を鋼管柱31に溶接
し、かつ一対の環状体32の間に鉄骨梁40のウェブの
取付部となるガセット33を溶接し、図13に示すよう
にする。環状体32およびガセット33は実施例1の環
状体12およびガセット13と同じ構成のものを使う。
下部躯体の鋼管からなる柱取付部25上に第1の長い鋼
管柱31を建て、取付鋼管25の鋼管の上端のガセット
25aと第1の長い鋼管柱31の下端のガセット31b
とを連結板24を使って仮結合する。複数の第1の長い
鋼管柱31の環状体32間に梁鉄骨40を配し、梁鉄骨
40の端部のウェブをガセット33に添え板、ボルト・
ナット等を使って仮取付をする。それから、第1の仕口
構成体10を適宜の吊り揚げ手段にて吊り揚げ、第1の
長い鋼管柱31の上端に第1の仕口構成体10の下方に
突出したコンクリート部分16aを嵌める。第1の仕口
構成体10の環状体13間に鉄骨梁40を配し、鉄骨梁
40の端部のウェブを第1の仕口構成体10のガセット
13に、添え板、ボルト・ナット等を使って仮取付をす
る。適宜の時期に、鉄骨梁40の端部のフランジを環状
体12、32の取付部に溶接する。
The second embodiment is an example in which the same structure as in the first embodiment is used as the connection member 10 and the long steel pipe column 31 is longer than the floor height. As the long steel pipe column 31, the length in the longitudinal direction thereof is set to be twice as large as the height of the floor.
FIG. 13 shows an example of using a steel pipe column 11 having a reduced length in the longitudinal direction. Long steel tube column 3
As 1, it is also possible to use, for example, a size obtained by subtracting the length in the longitudinal direction of the short steel tube column 11 of the connection structure 10 from three times the height of the floor. A pair of plate-shaped annular bodies 32 are fitted at positions 1 or 2 corresponding to the attachment positions of the steel beam of the long steel pipe column 31, each annular body 32 is welded to the steel pipe column 31, and the pair of annular bodies 32 A gusset 33 serving as a web attachment portion of the steel beam 40 is welded therebetween, as shown in FIG. The annular body 32 and the gusset 33 have the same configuration as the annular body 12 and the gusset 13 of the first embodiment.
A first long steel pipe column 31 is erected on a column mounting portion 25 made of a steel pipe of a lower frame, and a gusset 25a at an upper end of the steel pipe of the mounting steel pipe 25 and a gusset 31b at a lower end of the first long steel pipe column 31.
Are temporarily connected using the connecting plate 24. The beam steel structure 40 is arranged between the annular bodies 32 of the plurality of first long steel pipe columns 31, and the web at the end of the beam steel structure 40 is attached to the gusset 33,
Temporarily mount using nuts. Then, the first connection member 10 is lifted by an appropriate lifting means, and a concrete portion 16a projecting downward from the first connection member 10 is fitted to the upper end of the first long steel pipe column 31. A steel beam 40 is arranged between the annular bodies 13 of the first connection member 10, and the web at the end of the steel beam 40 is attached to the gusset 13 of the first connection member 10, with a siding plate, a bolt, a nut, and the like. Temporarily mount using. At an appropriate time, the flange at the end of the steel beam 40 is welded to the attachment portion of the annular bodies 12 and 32.

【0012】第1の仕口構成体10のコンクリート部分
16の開口16bの上端から、第1の長い鋼管柱31内
および開口16bにコンクリートを充填し、仕口構成体
10のコンクリート部分16と鋼管柱31および開口1
6b内のコンクリート部分26とを一体に結合する。同
様にやり方にて、第2、第3等の長い鋼管柱31、第
2、第3等の仕口構成体10、鉄骨梁40等を組み立
て、順次コンクリートの充填を行い、多層の建物躯体を
構築して行く。間隔保持手段の使い方、溶接による本結
合の仕方等は実施例1と同じであるから、その説明を省
略する。実施例2によると、仕口構成体10の数が少な
くてすみ、溶接個所も少なくなるから、その分んだけ施
工性がよくなる。なお、実施例1および2においては、
建て込み時に、仕口構成体10と長い鋼管柱21、31
とを組付(仮結合)する例を説明したが、建て込み前に
仕口構成体10と長い鋼管柱21、31を仮結合してお
く場合もある。この場合は、口構成体10の短い鋼管
柱11と長い鋼管柱21、31とをガセット、連結板等
の着脱自在の連結手段を使い間隔保持環19を介して仮
結合しておいてもよい。このようにすると、建て込み作
業や結合作業が容易になる。
Concrete is filled into the first long steel pipe column 31 and the opening 16b from the upper end of the opening 16b of the concrete portion 16 of the first joint structure 10, and the concrete portion 16 of the joint structure 10 and the steel pipe are filled. Pillar 31 and opening 1
6b and the concrete part 26 in FIG. In a similar manner, the second and third long steel pipe columns 31, the second and third connection members 10, the steel beams 40 and the like are assembled, concrete is sequentially filled, and a multi-layer building frame is formed. Build and go. The method of using the spacing means, the method of the main connection by welding, and the like are the same as those in the first embodiment, and thus the description thereof will be omitted. According to the second embodiment, the number of the joint members 10 can be reduced, and the number of welded portions can be reduced. In Examples 1 and 2,
At the time of building, the connection structure 10 and the long steel pipe columns 21, 31
Although the example of assembling (temporary joining) has been described, the connecting member 10 and the long steel pipe columns 21 and 31 may be temporarily joined before being built. In this case, the gusset and specifications mouth structure 10 short tubular columns 11 and long tubular columns 21 and 31, be left temporarily coupled to via interval holding ring 19 using connecting means detachably connecting plate such as Good. In this way, the erection work and the joining work are facilitated.

【0013】[0013]

【発明の作用効果】この発明は、特許請求の範囲の欄に
記載した構成を備えることにより、次の(イ)ないし
)の作用効果を奏する。 (イ)請求項1に係る建物躯体の構築法は、次の〜
の作用効果を奏する。 仕口構成体として、短い鋼管
柱が既成の鋼管を梁成よりも少々長く切断して形成さ
れ、短い鋼管柱の外側に一対の外ダイアフラムが溶接さ
れ、外ダイアフラム間に梁取付用ガセットが溶接され、
短い鋼管柱の内側に中央部に開口ができるように内ダイ
アフラムが溶接され、短い鋼管柱内がコンクリートで満
たされ、短い鋼管柱内のコンクリート部分が短い鋼管柱
の下端および上端から下方および上方に突出して形成さ
れ、前記コンクリート部分に上下方向に延びる貫通開口
が形成されているものを用い、長い鋼管柱として、既成
の鋼管を所定の長さに切断して形成されているものを用
いるから、長い鋼管柱および仕口構成体の短い鋼管柱
既成の鋼管の切断により容易に形成でき、内ダイアフラ
ムを溶接する鋼管柱が短いため、特別の溶接器具を使わ
なくても、内ダイアフラムを短い鋼管柱の内周部に容易
に溶接することができ、簡易な切断、溶接等の作業によ
り仕口構成体及び長い鋼管柱を安価に提供できる。
柱形成位置の同じ軸線上に長い鋼管柱と仕口構成体の短
い鋼管柱とが交互に建てられ、仕口構成体の前記コンク
リート部分の短い鋼管柱の下方および上方に突出してい
る部分が長い鋼管柱の端部内に嵌められ、長い鋼管柱と
仕口構成体の短い鋼管柱とが間隔保持手段を使って長い
鋼管柱の端面と短い鋼管柱の端面との間に小さな隙間を
保って仮結合されるから、両者の間隔保持、仮結合等の
作業が容易になる。
According to the present invention, the following effects (a) to ( e ) can be obtained by providing the structure described in the claims. (A) The construction method of the building frame according to claim 1 is as follows:
The operation and effect of Short steel pipe as the connection structure
The column is formed by cutting the existing steel pipe a little longer than the beam
A pair of outer diaphragms are welded to the outside of a short steel column.
The gusset for beam attachment is welded between the outer diaphragms,
Inner die so that there is a central opening inside the short steel tube column
The afram is welded and the inside of the short steel tube column is filled with concrete.
The concrete part inside the short steel column is short
Formed downward and upward from the lower and upper ends of the
A through opening extending vertically in the concrete portion
Is used as a long steel pipe column.
Use a tube formed by cutting a steel pipe
From there, a long steel pipe columns and short steel column of the Joint structure
It can be easily formed by cutting the existing steel pipe, and the inner diaphragm
Special welding equipment is used because the steel pipe column for welding the
Easily place inner diaphragm on inner circumference of short steel tube column
Can be welded, and simple cutting, welding, etc.
The connection structure and the long steel pipe column can be provided at low cost.
Long steel pipe column and short joint structure on the same axis at the column formation position
Steel pipe columns are built alternately, and the concrete
Projecting below and above the short steel column
Part fits into the end of the long steel column,
The length of the short steel pipe column with the connection structure is long using the spacing means
Make a small gap between the end of the steel column and the end of the short column.
Since they are temporarily joined while maintaining the distance,
Work becomes easier.

【0014】 長い鋼管柱と仕口構成体の短い鋼管柱
とが間隔保持手段を使って小さな隙間を保って仮結合さ
れ、長い鋼管柱内および仕口構成体の前記コンクリート
部分の貫通開口内がコンクリートで満たされて充填コン
クリート鋼管柱とされ、充填コンクリート鋼管柱に鉛直
方向の荷重が作用する状態にして、間隔保持手段を除い
て鉛直方向の荷重を各鋼管柱内のコンクリートで支持し
た状態にしてから、長い鋼管柱の端面と仕口構成体の短
い鋼管柱の端面とを互いに溶接により本結合するため、
溶接部分が溶接後の冷却により収縮し、各鋼管柱の溶接
部分は収縮力が作用した状態になり、充填コンクリー
鋼管柱の充填コンクリートの軸力負担率を増大させるこ
とができる。したがって、建物の完成後に、充填コンク
リート鋼管柱に大きな鉛直方向の荷重が作用しても、鋼
管柱が座屈する恐れがない。 長い鋼管柱と仕口構成
体の短い鋼管柱とが間隔保持手段を使って小さな隙間を
保って仮結合され、長い鋼管柱内および仕口構成体の貫
通開口内がコンクリートで満たされて充填コンクリート
鋼管柱とされ、充填コンクリート鋼管柱に鉛直方向の荷
重が作用する状態にしてから、間隔保持手段を除き、長
い鋼管柱の端面と仕口構成体の短い鋼管柱の端面とを互
いに溶接により本結合するため、溶接に適した隙間の形
成等が容易になり、建物の完成後には、長い鋼管柱と仕
口構成体の短い鋼管柱とが溶接により接合された状態に
なっているから、充填コンクリート鋼管柱の鉄骨部分に
作用する鉛直方向の荷重を、仕口構成体の短い鋼管柱の
側に溶接した内ダイアフラムを介して、充填したコン
クリートに確実に伝達できる。
A long steel column and a short steel column with a connection structure
Is temporarily connected with a small gap using the spacing means.
The concrete in a long steel tube column and in the connection structure
The inside of the through opening of the part is filled with concrete and the filling
It is assumed to be a cleat steel pipe column,
In the direction where the load in the direction acts, and remove the spacing means.
To support the vertical load with concrete in each steel pipe column.
The end of the long steel pipe column and the short
In order to permanently join the end faces of steel pipe columns to each other by welding,
Welded parts is contracted by cooling after welding, the welding portion of each steel column is ready to shrinkage force is applied, filled concrete
The axial load burden ratio of the concrete filled with the steel pipe column can be increased. Therefore, after the building is completed,
Even if a large vertical load is applied to
There is no danger of tube columns buckling. Long steel column and connection configuration
Short gaps are made between short steel pipe columns using spacing means.
And is temporarily connected to the inside of the long steel pipe column and the connection structure.
Filling concrete filled with concrete inside the through opening
It is considered to be a steel pipe column, and the vertical load is
After the weight has been applied, remove the length
Between the end face of the steel pipe column and the end face of the short
The shape of the gap suitable for welding because the main connection is made by welding
After completion of the building, long steel pipe columns and
In a state where the short steel tube column of the mouth structure is joined by welding
Because it has become the steel part of the filled concrete steel pipe column
Acting vertical load on the short steel column of the joint
Through the diaphragm inner welded to the inner side, filled con
Can be reliably transmitted to cleats.

【0015】 (ロ)請求項2に係る発明の建物躯体の構
築法のようにすると、上記(イ)の〜の作用効果と
同じ作用効果を奏することができるだけでなく、次の
の作用効果を奏することができる。 長い鋼管柱とし
て、既成の鋼管を所定の長さに切断し、その1または2
の梁取付部に一対の外ダイアフラムが溶接され、それら
の対の外ダイアフラム間に梁取付用ガセットが溶接され
ているものを用いるから、長い鋼管柱の1または2の梁
取付部に対応する鋼管柱の部分の内側にそれぞれ内ダイ
アフラムを溶接する必要がないから、梁取付部のある長
い鋼管柱の製作が容易になり、長い鋼管柱を安価で提供
できる。 (ハ)請求項3に係る発明の仕口構成体は、短い鋼管柱
が既成の鋼管を梁成よりも少々長く切断して形成され、
短い鋼管柱の外側に一対の外ダイアフラムが溶接され、
外ダイアフラム間に梁取付用ガセットが溶接され、短い
鋼管柱の内側に中央部に開口ができるように内ダイアフ
ラムが溶接され、短い鋼管柱内がコンクリートで満たさ
れ、短い鋼管柱内のコンクリート部分が短い鋼管柱の下
端および上端から下方および上方に突出して形成され、
前記コンクリート部分に上下方向に延びる貫通開口が形
成されているから、仕口構成体の短い鋼管柱内のコンク
リート部分の貫通開口を通して、長い鋼管柱内にコンク
リートを容易に充填することができるだけでなく、上記
(イ)のおよびの作用効果と同じ作用効果を奏する
ことができる。 (ニ)請求項4に係る発明の仕口構成体のようにする
と、連結鉄筋により短い鋼管柱内のコンクリート部分と
長い鋼管柱内に後打ちするコンクリート部分とを強力に
一体化することができる。(ホ) この発明によると、充填コンクリートの軸力負担
率が大きく、鋼管柱が座屈する恐れのない充填コンクリ
ート鋼管柱を備えた建物躯体を容易に構築することがで
きる。
[0015] (b) structure of the building structures of the invention according to claim 2
In the construction method, the effects and effects of (a) above
Not only can you achieve the same effect,
The effect of the invention can be obtained. As long steel tube columns
Then, the existing steel pipe is cut to a predetermined length, and
A pair of outer diaphragms are welded to the beam mounting part of
Gussets for beam mounting are welded between the pair of outer diaphragms
One or two beams of long steel tube columns
Internal dies are installed inside the steel pipe column corresponding to the mounting part.
Since there is no need to weld the afram, the length of the beam
It is easy to manufacture steel pipe columns and offers long steel pipe columns at low cost.
it can. (C) The connection structure of the invention according to claim 3 is a short steel pipe column.
Is formed by cutting the existing steel pipe a little longer than the beam,
A pair of outer diaphragms are welded to the outside of the short steel column,
Gusset for beam mounting is welded between outer diaphragms, short
Inner diaphragm so that there is an opening at the center inside the steel tube column
The ram is welded and the inside of a short steel column is filled with concrete
The concrete section inside the short steel column is below the short steel column.
Formed protruding downward and upward from the end and upper end,
The concrete part has a through opening extending vertically.
As a result , not only can concrete be easily filled into the long steel pipe column through the through-opening of the concrete part in the short steel pipe column of the connection structure ,
(B) Has the same function and effect as and
be able to. (D) According to the joint structure of the invention according to claim 4, the concrete portion in the short steel tube column and the concrete portion to be post-cast in the long steel tube column can be strongly integrated by the connecting rebar. . (E) According to the present invention, it is possible to easily construct a building frame having a filled concrete steel pipe column in which the axial load burden ratio of the filled concrete is large and the steel pipe column is not likely to buckle.

【図面の簡単な説明】[Brief description of the drawings]

【図1】実施例1の仕口構成体の鉄骨部分の平面図FIG. 1 is a plan view of a steel frame portion of a connection structure according to a first embodiment.

【図2】図1のものそのA−A線で断面し矢印方向にみ
た正面図
FIG. 2 is a front view of FIG. 1 taken along the line AA and viewed in the direction of the arrow;

【図3】図1のものと異なる仕口構成体の鉄骨部分を図
1のA−A線と同じ線で断面し同じ矢印方向にみた正面
1. FIG. 3 is a front view of a steel frame part of a connection structure different from that of FIG. 1 taken along the same line as the line AA in FIG.

【図4】実施例1の仕口構成体の平面図FIG. 4 is a plan view of a connection structure according to the first embodiment.

【図5】図4のものをそのA−A線で断面し矢印方向に
みた正面図
FIG. 5 is a front view of FIG. 4 taken along the line AA and viewed in the direction of the arrow;

【図6】実施例1の間隔保持環および保護バンドの平面
FIG. 6 is a plan view of a spacing ring and a protection band according to the first embodiment.

【図7】図6のものをそのB−B線で断面し矢印方向に
みた正面図
FIG. 7 is a front view of FIG. 6 taken along the line BB and viewed in the direction of the arrow;

【図8】間隔保持環を嵌め仕口構成体を図4のA−A線
と同じ線で断面した正面図
FIG. 8 is a front view in which the gap holding ring is fitted and the connection structure is sectioned along the same line as the line AA in FIG. 4;

【図9】実施例1の下部体の上に建てた長い鋼管柱に
仕口構成体を結合した状態を図4のA−A線と同じ線で
縦断した正面図
FIG. 9 is a front view of a state in which a connection member is connected to a long steel pipe column built on the lower frame of the first embodiment along the line AA in FIG. 4;

【図10】長い鋼管柱と仕口構成体との仮結合部分等を
縦断した正面図
FIG. 10 is a front view in which a temporary connecting portion between a long steel pipe column and a connection member is longitudinally cut;

【図11】実施例1の長い鋼管柱と仕口構成体とをそれ
ぞれ二つ結合した状態を図4のA−A線と同じ線で断面
した正面図
FIG. 11 is a front view showing a state where two long steel pipe columns and a connection member of the first embodiment are connected to each other along the line AA in FIG. 4;

【図12】間隔保持部材を除いた状態の長い鋼管柱と仕
口構成体との結合部分を図4のA−A線と同じ線で断面
した正面図
FIG. 12 is a front view in which a connecting portion between a long steel pipe column and a connection structure without a spacing member is cut along a line AA in FIG. 4;

【図13】実施例2の長い鋼管柱と仕口構成体とを結合
したものを図4のA−A線と同じ線で断面した正面図
FIG. 13 is a front view in which the long steel pipe column of Example 2 and the joint structure are combined and cut along the line AA in FIG. 4;

【図14】従来の充填コンクリート鋼管柱の製作法を示
す正面図
FIG. 14 is a front view showing a method for manufacturing a conventional filled concrete steel pipe column.

【図15】図14のものの平面図FIG. 15 is a plan view of the one in FIG. 14;

【図16】従来の他の充填コンクリート鋼管柱の製作法
を示す正面図
FIG. 16 is a front view showing another conventional method of manufacturing a filled concrete steel pipe column.

【図17】図16のものの平面図FIG. 17 is a plan view of the one in FIG. 16;

【符号の説明】[Explanation of symbols]

10 仕口構成体 10A 仕口構成体の鉄骨部分 11 短い鋼管柱 12 環状体 13 環状体 14 ガセット 15 連結鉄筋 16 コンクリート部分 16a 突出したコンクリート部分 16b 貫通開口 16c 円錐面 17 間隔保持体 18 保護バンド 19 断熱材層 21 長い鋼管柱 24 連結板 25 柱取付部 26 コンクリート部分 31 長い鋼管柱 32 環状体 33 ガセット 40 鉄骨梁 g 隙間DESCRIPTION OF SYMBOLS 10 Connection structure 10A Steel part of connection structure 11 Short steel pipe column 12 Ring body 13 Ring body 14 Gusset 15 Connecting rebar 16 Concrete part 16a Projected concrete part 16b Through-opening 16c Conical surface 17 Spacer 18 Protective band 19 Insulation layer 21 Long steel pipe column 24 Connecting plate 25 Column mounting part 26 Concrete part 31 Long steel pipe column 32 Ring body 33 Gusset 40 Steel beam g Gap

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E04B 1/30 E04B 1/22 ──────────────────────────────────────────────────続 き Continued on the front page (58) Fields surveyed (Int.Cl. 7 , DB name) E04B 1/30 E04B 1/22

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】仕口構成体として、短い鋼管柱が既成の鋼
管を梁成よりも少々長く切断して形成され、短い鋼管柱
の外側に一対の外ダイアフラムが溶接され、外ダイアフ
ラム間に梁取付用ガセットが溶接され、短い鋼管柱の内
側に中央部に開口ができるように内ダイアフラムが溶接
され、短い鋼管柱内がコンクリートで満たされ、短い鋼
管柱内のコンクリート部分が短い鋼管柱の下端および上
端から下方および上方に突出して形成され、前記コンク
リート部分に上下方向に延びる貫通開口が形成されてい
るものを用い、長い鋼管柱として、既成の鋼管を所定の
長さに切断して形成されているものを用い、柱形成位置
の同じ軸線上に長い鋼管柱と仕口構成体の短い鋼管柱と
が交互に建てられ、仕口構成体の前記コンクリート部分
の短い鋼管柱の下方および上方に突出している部分が長
い鋼管柱の端部内に嵌められ、長い鋼管柱と仕口構成体
の短い鋼管柱とが間隔保持手段を使って長い鋼管柱の端
面と短い鋼管柱の端面との間に小さな隙間を保って仮結
され、長い鋼管柱内および仕口構成体の前記コンクリ
ート部分の貫通開口内がコンクリートで満たされて充填
コンクリート鋼管柱とされ、充填コンクリート鋼管柱に
鉛直方向の荷重が作用する状態にして、間隔保持手段を
除いて鉛直方向の荷重を各鋼管柱内のコンクリートで支
持した状態にしてから、長い鋼管柱の端面と仕口構成体
の短い鋼管柱の端面とを互いに溶接により本結合するこ
とを特徴とする建物体の構築法。
(1) A steel pipe having a short steel pipe column as a connection structure.
A short steel pipe column formed by cutting the pipe slightly longer than the beam
A pair of outer diaphragms is welded to the outside of the
Gussets for beam mounting are welded between the rams, and
The inner diaphragm is welded so that an opening is formed in the center at the side
The inside of a short steel pipe column is filled with concrete,
The lower and upper ends of steel pipe columns with short concrete sections
The contact is formed to protrude downward and upward from the end, and
A through-opening extending vertically is formed in the rear part.
The existing steel pipe is used as a long steel pipe column.
Using a steel pipe column that is cut to length , a long steel pipe column and a short steel pipe column of the joint structure on the same axis at the column formation position
Are alternately erected, and the concrete portion of the joint structure is
The lower and upper protruding parts of the short steel column
A long steel column and connection structure fitted inside the end of a steel column
The end of the short steel column is shorted by using the spacing means.
Temporary connection with a small gap between the surface and the end face of the short steel pipe column, and
Over root section of the through opening is a has been filled concrete tubular columns meet in concrete, a load in the vertical direction to fill the concrete steel pillars in a state to act, the interval holding means
Except for the vertical load, which is supported by concrete in each steel pipe column.
After the lifting state, the end face of the long tubular columns Joint structure
A method for constructing a building skeleton , characterized in that the end faces of short steel pipe columns are permanently joined to each other by welding.
【請求項2】仕口構成体として、短い鋼管柱が既成の鋼
管を梁成よりも少々長く切断して形成され、短い鋼管柱
の外側に一対の外ダイアフラムが溶接され、外ダイアフ
ラム間に梁取付用ガセットが溶接され、短い鋼管柱の内
側に中央部に開口ができるように内ダイアフラムが溶接
され、短い鋼管柱内がコンクリートで満たされ、短い鋼
管柱内のコンクリート部分が短い鋼管柱の下端および上
端から下方および上方に突出して形成され、前記コンク
リート部分に上下方向に延びる貫通開口が形成されてい
るものを用い、長い鋼管柱として、既成の鋼管を所定の
長さに切断し、その1または2の梁取付部に一対の外ダ
イアフラムが溶接され、 それらの対の外ダイアフラム間
に梁取付用ガセットが溶接されているものを用い、柱形
成位置の同じ軸線上に長い鋼管柱と仕口構成体の短い鋼
管柱とが交互に建てられ仕口構成体の短い鋼管柱内の
コンクリート部分の短い鋼管柱の下方および上方に突出
している部分が長い鋼管柱の端部内に嵌められ、長い鋼
管柱と仕口構成体の短い鋼管柱とが間隔保持手段を使っ
長い鋼管柱の端面と短い鋼管柱の端面との間に小さな
隙間を保って仮結合され長い鋼管柱内および短い鋼管
柱内のコンクリート部分の貫通開口内がコンクリートで
満たされて充填コンクリート鋼管柱とされ、充填コンク
リート鋼管柱に鉛直方向の荷重が作用する状態にして、
間隔保持手段を除いて鉛直方向の荷重を各鋼管柱内がコ
ンクリートで支持した状態にしてから、長い鋼管柱の端
面と仕口構成体の短い鋼管柱の端面とを互いに溶接によ
り本結合することを特徴とする建物体の構築
2. A steel pipe having a short steel column as a connection structure.
A short steel pipe column formed by cutting the pipe slightly longer than the beam
A pair of outer diaphragms is welded to the outside of the
Gussets for beam mounting are welded between the rams, and
The inner diaphragm is welded so that an opening is formed in the center at the side
The inside of a short steel pipe column is filled with concrete,
The lower and upper ends of steel pipe columns with short concrete sections
The contact is formed to protrude downward and upward from the end, and
A through-opening extending vertically is formed in the rear part.
The existing steel pipe is used as a long steel pipe column.
Cut to length and attach a pair of outer
The ear diaphragms are welded between their outer diaphragms
A steel tube gusset is welded to the column, and a long steel tube column and a short steel
And tubular column is built in alternating, short steel pipe in pillarless Joint structure
Projects below and above short steel tube columns in concrete sections
Part of the long steel tube column
The pipe column and the short steel pipe column of the connection structure are temporarily connected to each other with a small gap between the end face of the long steel pipe column and the end face of the short steel pipe column using spacing means, and the inside of the long steel pipe column and the short steel pipe are used.
The through openings of the concrete portion of the pillar is a compacting concrete tubular columns being met with concrete, a load in the vertical direction to fill the concrete steel pillars in a state to act,
After the vertical load is supported by concrete inside each steel pipe column except for the spacing means, the end face of the long steel pipe column and the end face of the short steel pipe column of the connection structure are permanently joined to each other by welding. Construction method of building frame characterized by the following.
【請求項3】短い鋼管柱が既成の鋼管を梁成よりも少々
長く切断して形成され、短い鋼管柱の外側に一対の外ダ
イアフラムが溶接され、外ダイアフラム間に梁取付用ガ
セットが溶接され、短い鋼管柱の内側に中央部に開口
できるように内ダイアフラムが溶接され、短い鋼管柱内
がコンクリートで満たされ、短い鋼管柱内のコンクリー
ト部分が短い鋼管柱の下端および上端から下方および
方に突出して形成され、前記コンクリート部分に上下方
向に延びる貫通開口が形成されていることを特徴とする
仕口構成体。
3. A short steel pipe column is formed by cutting an existing steel pipe a little longer than a beam, a pair of outer diaphragms are welded to the outside of the short steel pipe column, and a beam mounting gusset is welded between the outer diaphragms. , the opening in the central portion on the inner side of the short steel column
The inside diaphragm is welded so that the inside of the short steel column is filled with concrete, and the concrete portion in the short steel column is formed to protrude downward and upward from the lower end and the upper end of the short steel column. A connection structure, wherein a through opening extending in a vertical direction is formed in a concrete portion.
【請求項4】短い鋼管柱内のコンクリート部分に上下方
向に延びる複数本の連結鉄筋が埋め込まれ、それらの連
結鉄筋の下方の部分および上方の部分がコンクリート部
分の下面または上面から下方または上方に長く突出して
いることを特徴とする請求項記載の仕口構成体。
4. A concrete portion in a short steel tube column is embedded with a plurality of connecting reinforcing bars extending in a vertical direction, and a lower portion and an upper portion of the connecting reinforcing bar extend downward or upward from a lower surface or an upper surface of the concrete portion. The joint structure according to claim 3 , wherein the joint structure protrudes long.
JP04140088A 1992-05-04 1992-05-04 Construction method of building frame using filled concrete steel column Expired - Fee Related JP3106263B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP04140088A JP3106263B2 (en) 1992-05-04 1992-05-04 Construction method of building frame using filled concrete steel column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP04140088A JP3106263B2 (en) 1992-05-04 1992-05-04 Construction method of building frame using filled concrete steel column

Publications (2)

Publication Number Publication Date
JPH05311745A JPH05311745A (en) 1993-11-22
JP3106263B2 true JP3106263B2 (en) 2000-11-06

Family

ID=15260680

Family Applications (1)

Application Number Title Priority Date Filing Date
JP04140088A Expired - Fee Related JP3106263B2 (en) 1992-05-04 1992-05-04 Construction method of building frame using filled concrete steel column

Country Status (1)

Country Link
JP (1) JP3106263B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007189824A (en) * 2006-01-12 2007-07-26 Nisca Corp Magnet rotor, electromagnetic drive device therewith, and optical instrument having optical amount adjusting device
JP6706225B2 (en) * 2017-06-28 2020-06-03 東急建設株式会社 Concrete filling method for steel pipe shaft inside small section caisson pier
CN113123465B (en) * 2021-04-30 2023-09-12 郑州航空工业管理学院 Assembled building beam column node
CN114232898B (en) * 2021-12-22 2023-09-01 中铁三局集团建筑安装工程有限公司 Large-section rectangular thick plate steel tube concrete column and construction method

Also Published As

Publication number Publication date
JPH05311745A (en) 1993-11-22

Similar Documents

Publication Publication Date Title
JP3106263B2 (en) Construction method of building frame using filled concrete steel column
JP4490532B2 (en) Precast composite beam structure
JP2972043B2 (en) Method of joining different kinds of structural members and column / beam joining structural members
JPH07292773A (en) Construction method of framework with steel pipe concrete column
JP3052100B2 (en) A building drive system combining a column and a joint structure and its construction method
JPH0536587B2 (en)
JP2959325B2 (en) Construction method of steel frame reinforced concrete structure
JP3317057B2 (en) Construction method of earthquake-resistant tube frame and frame structure of high-rise office building
JP2903873B2 (en) Beam joint structure of centrifugally formed hollow PC column
JP2002332691A (en) Joint construction between column and beam
JP2645329B2 (en) Pillar construction method
JPH1150538A (en) Building and method for constructing the same
JP2896820B2 (en) Beam-column joint structure
JP3052102B2 (en) Construction method of building drive using joint structure
JPH0654049B2 (en) Filled steel tubular concrete columns and method of constructing filled tubular concrete columns
JP2592224Y2 (en) Structure of joint between RC beam and steel structure
JP2514859B2 (en) Precast Steel Reinforced Concrete Concrete Column
JP3122739B2 (en) Frame consisting of precast RC columns and precast RC beams
JPH0654042B2 (en) Shear Reinforcement Structure of Shear Head in Flat Plate Structure Building
JPH06105003B2 (en) Centrifugal molded steel rod reinforced concrete member
JP3700129B2 (en) Joint structure of composite structure and construction method thereof
JP2893406B2 (en) Precast concrete beam-column joining method
JP2857815B2 (en) Joining method for heterogeneous structural members
JPH0673785A (en) Steel framed reinforced concrete column and construction of this column and steel skeleton beam
JPS62121251A (en) Building ramen

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees