JP3092398B2 - Construction method of floating pipeline - Google Patents

Construction method of floating pipeline

Info

Publication number
JP3092398B2
JP3092398B2 JP05171450A JP17145093A JP3092398B2 JP 3092398 B2 JP3092398 B2 JP 3092398B2 JP 05171450 A JP05171450 A JP 05171450A JP 17145093 A JP17145093 A JP 17145093A JP 3092398 B2 JP3092398 B2 JP 3092398B2
Authority
JP
Japan
Prior art keywords
pipeline
floating
floater
trench
sinker
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP05171450A
Other languages
Japanese (ja)
Other versions
JPH0727299A (en
Inventor
正廣 佐々木
輝俊 早田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP05171450A priority Critical patent/JP3092398B2/en
Publication of JPH0727299A publication Critical patent/JPH0727299A/en
Application granted granted Critical
Publication of JP3092398B2 publication Critical patent/JP3092398B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、湿地帯の軟弱地盤上
にパイプラインを布設する場合のパイプラインの施工法
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a pipeline when laying the pipeline on soft ground in a wetland.

【0002】[0002]

【従来の技術】従来、湿地帯のパイプラインの構造は図
3(a)に示すような埋設方式と(b)に示すような架
台方式があった。いずれも掘削、架台の構築、パイプラ
インの敷設、パイプの接続等の一連の作業は現場で行わ
れていた。
2. Description of the Related Art Conventionally, there are two types of wetland pipelines: a buried type as shown in FIG. 3A and a gantry type as shown in FIG. 3B. In each case, a series of operations such as excavation, construction of a gantry, laying of pipelines, connection of pipes, etc. were performed on site.

【0003】[0003]

【発明が解決しようとする課題】軟弱地盤の地下水位の
高い場所で埋設法或いは架台構築法によって、パイプラ
インを敷設する場合、従来の構造では、材料運搬路の確
保、架台の構築が困難であった。また特に埋設法では地
下に埋設されたパイプラインのメンテナンスは至難であ
った。かくて、敷設工期が長くなると共に敷設コスト、
メンテナンスコストが嵩むという問題点があった。本発
明はこれらの問題点を解決するよう工夫されたものであ
る。
In the case of laying a pipeline in a place with a high groundwater level on soft ground by a burial method or a gantry construction method, it is difficult to secure a material transport path and construct a gantry with a conventional structure. there were. In particular, maintenance of pipelines buried underground was extremely difficult with the burial method. Thus, the laying period becomes longer and the laying cost,
There has been a problem that the maintenance cost increases. The present invention has been devised to solve these problems.

【0004】[0004]

【課題を解決するための手段】トレンチ1を掘削し、上
載重量を支承するに十分な浮力を有するフローター3
に、所定の間隔でパイプ4を係止してフローティングパ
イプラインユニット2を形成し、前記トレンチ1に該フ
ローティングパイプラインユニット2を引き込み水面に
浮上させ、フローティングパイプラインユニット2と現
場で接合することを繰り返しながら、前記フローター3
の近傍に、シンカー7を沈め該シンカー7にフローター
3を係留してなることを特徴とする浮体式パイプライン
の施工法である。本発明では、パイプラインを敷設しよ
うとするラインに沿ってトレンチを掘削しながら地下水
位を高く確保する。別にパイプを上載する箱状のフロー
ターを製作し、長いパイプを数個の該フローターに上載
係止し、フローティングパイプユニットを構成する。該
フローターはフローティングパイプユニットを水面に浮
かすに充分な浮力のあるものとする。前記フローティン
グパイプユニットを前記トレンチの中に引き込み水上に
浮遊させ、保留チェーンでシンカーと連結し、フロータ
ーの自由移動を抑制し更にトレンチを掘削しながら複数
本の前記フローティングパイプユニットを接続し、湿地
帯のパイプラインを構成する。
The trench 1 is excavated, and
Floater 3 with sufficient buoyancy to support the weight
At a predetermined interval, the pipe 4 is locked to
An pipeline unit 2 is formed, and the trench 1 is
Pull in the loading pipeline unit 2 to the water surface
Floating, floating pipeline unit 2 and now
While repeating the joining in place, the floater 3
Sinker 7 near sinker and floater on sinker 7
Floating pipeline characterized by mooring 3
This is the construction method. In the present invention, a high groundwater level is secured while excavating a trench along a line where a pipeline is to be laid. Separately, a box-shaped floater on which a pipe is mounted is manufactured, and a long pipe is mounted and locked on several of the floaters to form a floating pipe unit. The floater has sufficient buoyancy to float the floating pipe unit on the water surface. The floating pipe unit is drawn into the trench and floated on the water, connected to a sinker by a holding chain, and connected to a plurality of the floating pipe units while suppressing free movement of the floater and further excavating the trench. Configure the pipeline.

【0005】[0005]

【実施例】図1に本発明の浮体式パイプラインの構造
一部の詳細を示す。
FIG. 1 shows the structure of a floating pipeline according to the present invention.
Here are some details.

【0006】(a)は側面図で(b)は平面図である。
(c)はフローター3の斜視図である。図2は本発明の
施工順序を示す。
(A) is a side view and (b) is a plan view.
(C) is a perspective view of the floater 3. FIG. 2 shows the construction sequence of the present invention.

【0007】(a)はトレンチ1を掘削するところを示
し、(b)は組立ヤードでパイプラインユニット2を組
み立てているところを示し、(c)はフローティングパ
イプユニット2をトレンチ1に引き込むところを示し、
(d)はフローティングパイプユニット2を送り出し、
接合しているところを示し、(e)はシンカー7をセッ
トしているところを示し、(f)はフローター3とシン
カー7を係留しパイプラインが完成したところを示して
いる。
(A) shows the excavation of the trench 1, (b) shows the assembly of the pipeline unit 2 in the assembly yard, and (c) shows the drawing of the floating pipe unit 2 into the trench 1. Show,
(D) sends out the floating pipe unit 2,
(E) shows that the sinker 7 is set, and (f) shows that the floater 3 and the sinker 7 are moored to complete the pipeline.

【0008】以下本発明を図1、図2に従って説明す
る。
Hereinafter, the present invention will be described with reference to FIGS.

【0009】図2(a)に示すように、軟弱地盤上に仮
設道路を建設し、例えば移動式簡易掘削機によりフロー
ティングパイプライン敷設用のトレンチ1を掘削する。
該トレンチ1は先ずフローティングパイプユニット2の
ほぼ1本分が布設できるものを掘削すればよい。図2
(b)に示すようにパイプラインユニット組立ヤードで
パイプラインユニット2を組み立てる。フローティング
パイプユニットの構成の詳細は図1に示す。先ずトレン
チ1に浮く例えば鉄板製の鋼殻を製作し中に鋼材腐食時
にも充分な浮力が得られるように、発泡スチロール等を
充填してフローター3とする。該フローター3はトレン
チ1の水位に浮上させた場合、乾舷はパイプ4を上載し
た稼働時に約15cmと見積もる。フローター3にはパ
イプ4を該フローター3に係止するためのU字バンド5
を遊合させボルトで締結する。パイプ4は内部の輸送物
の温度や、太陽の輻射熱によって伸縮するので、前記U
バンド5は緊結しない。更にパイプ4の保護ガセット6
をフローター3に溶接してパイプ4の移動、落下から保
護する。フローター3に係止するパイプ4は1本から数
本まで可能である。この例ではパイプ4は2本で、5m
間隔でフローター3に係止されている。次に図2(c)
に示すように(b)で組立たフローティングパイプユニ
ット2を例えばウインチ9のようなものでトレンチ1に
引き込む。フローティングパイプユニット2はフロータ
ー3の浮力によりトレンチ1内で容易に移動することが
出来る。2図(d)に示すように次のフローティングパ
イプユニット2のためのトレンチ1の掘削と並行してフ
ローティングパイプユニット2を送り出す。次いでフロ
ーティングパイプユニット2を引き込む作業を繰り返
す。接合部のパイプは現場溶接として接合する。次に図
1に示すような例えばコンクリート製のシンカー7を各
フローター3の近傍に沈める。この様子を図2(e)に
示す。最後にシンカー7を係留チェーン8をフローター
3に係止してパイプラインを完成させる。図2(f)に
この様子を示す。パイプライン完成後も浮力により上下
に移動可能であり、冠水時でもパイプラインは水面上に
保持される。
As shown in FIG. 2A, a temporary road is constructed on soft ground, and a trench 1 for laying a floating pipeline is excavated by, for example, a mobile simple excavator.
The trench 1 may first be excavated so that approximately one floating pipe unit 2 can be laid. FIG.
As shown in (b), the pipeline unit 2 is assembled in the pipeline unit assembly yard. Details of the configuration of the floating pipe unit are shown in FIG. First, for example, a steel shell made of, for example, an iron plate floating in the trench 1 is manufactured and filled with styrofoam or the like so that a sufficient buoyancy is obtained even when steel material is corroded. When the floater 3 is floated above the water level of the trench 1, the freeboard is estimated to be about 15 cm when the pipe 4 is mounted on the freeboard. A U-shaped band 5 for locking the pipe 4 to the floater 3
And fasten with bolts. The pipe 4 expands and contracts due to the temperature of the transported goods inside and the radiant heat of the sun.
Band 5 is not tied. Furthermore, protection gusset 6 for pipe 4
Is welded to the floater 3 to protect the pipe 4 from moving and falling. One to several pipes 4 can be locked to the floater 3. In this example, there are two pipes 4 and 5m
It is locked to the floater 3 at intervals. Next, FIG.
As shown in (b), the floating pipe unit 2 assembled in (b) is drawn into the trench 1 by using, for example, a winch 9 or the like. The floating pipe unit 2 can easily move in the trench 1 by the buoyancy of the floater 3. 2 As shown in FIG. 2D, the floating pipe unit 2 is sent out in parallel with the excavation of the trench 1 for the next floating pipe unit 2. Next, the operation of pulling the floating pipe unit 2 is repeated. The joint pipes are joined as field welds. Next, a sinker 7 made of, for example, concrete as shown in FIG. This state is shown in FIG. Finally, the sinker 7 is locked with the mooring chain 8 to the floater 3 to complete the pipeline. FIG. 2F shows this state. The pipeline can be moved up and down by buoyancy even after completion of the pipeline, and the pipeline is kept above the water surface even during flooding.

【0010】[0010]

【発明の効果】本発明の効果は次の通りである。The effects of the present invention are as follows.

【0011】(イ)架台式のように湿地帯の軟弱地盤に
架台を架設するという困難な作業を伴わない。
(A) There is no need for a difficult work of erection of a gantry on soft ground in a wetland as in the gantry type.

【0012】(ロ)トレンチ1の掘削はパイプ4、ガセ
ット6、U字バンド5、フローター3よりなるフローテ
ィングパイプユニット2の組立と並行作業が出来るの
で、作業効率がよく短工期である。
(B) The excavation of the trench 1 can be performed in parallel with the assembly of the floating pipe unit 2 including the pipe 4, the gusset 6, the U-shaped band 5, and the floater 3, so that the working efficiency is good and the construction period is short.

【0013】(ハ)パイプ内の輸送物の温度、太陽輻射
熱等によるパイプの伸縮にも柔軟に対応出来る。また輸
送物を保温する工事も容易である。
(C) It is possible to flexibly cope with the expansion and contraction of the pipe due to the temperature of the transported material in the pipe, solar radiation heat, and the like. It is also easy to keep the transported goods warm.

【0014】(ニ)埋設法では、パイプラインにトラプ
ルを生じた場合、メンテナンスが非常に面倒であるが、
本発明の構造では地上にパイプラインがあるのでメンテ
ナンスは極めて容易である。
(D) In the buried method, when a trap is generated in a pipeline, maintenance is very troublesome.
In the structure of the present invention, maintenance is extremely easy because there is a pipeline on the ground.

【図面の簡単な説明】[Brief description of the drawings]

【図1】フローティングパイプユニットの一部詳細図で
ある。(a)は正面図を(b)は上面図を示し(c)は
フローターの斜視図を示す。
FIG. 1 is a partial detailed view of a floating pipe unit. (A) is a front view, (b) is a top view, and (c) is a perspective view of a floater.

【図2】浮体式パイプラインの施工法を示す。 (a)トレンチ掘削。 (b)フローティングパイプユニット組立。 (c)フローティングパイプユニット引き込み。 (d)フローティングパイプユニット送り出し、接合。 (e)シンカーセット。 (f)係留、完成。 の順に示す。FIG. 2 shows a construction method of a floating pipeline. (A) Trench excavation. (B) Floating pipe unit assembly. (C) Draw the floating pipe unit. (D) Floating pipe unit delivery and joining. (E) Sinker set. (F) Mooring, completion. Are shown in order.

【図3】従来工法を示し(a)は埋設式、(b)は架台
式をしめす。
3A and 3B show a conventional method, wherein FIG. 3A shows a buried type, and FIG. 3B shows a gantry type.

【符号の説明】[Explanation of symbols]

1・・・トレンチ、2・・・フローティングパイプユニ
ット、3・・・フローター、4・・・パイプ、5・・・
Uバンド、6・・・ガセット、7・・・シンカー、8・
・・係留チェーン、9・・・ウインチ
DESCRIPTION OF SYMBOLS 1 ... Trench, 2 ... Floating pipe unit, 3 ... Floater, 4 ... Pipe, 5 ...
U band, 6 ... gusset, 7 ... sinker, 8
..Mooring chains, 9 ... winches

フロントページの続き (56)参考文献 特開 昭63−270999(JP,A) 実開 昭59−76497(JP,U) 実開 平4−131134(JP,U) 実開 昭57−184090(JP,U) 特公 昭60−17903(JP,B2) (58)調査した分野(Int.Cl.7,DB名) F16L 1/00 - 1/26 F17D 1/00 - 1/20 Continuation of the front page (56) References JP-A-63-270999 (JP, A) JP-A-59-76497 (JP, U) JP-A-4-131134 (JP, U) JP-A-57-184090 (JP) , U) JP 60-17903 (JP, B2) (58) Fields investigated (Int. Cl. 7 , DB name) F16L 1/00-1/26 F17D 1/00-1/20

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 トレンチ1を掘削し、上載重量を支承す
るに十分な浮力を有するフローター3に、所定の間隔で
パイプ4を係止してフローティングパイプラインユニッ
ト2を形成し、前記トレンチ1に該フローティングパイ
プラインユニット2を引き込み水面に浮上させ、既に引
き込まれたフローティングパイプラインユニット2と現
場で接合することを繰り返しながら、前記フローター3
の近傍に、シンカー7を沈め該シンカー7にフローター
3を係留してなることを特徴とする浮体式パイプライン
の施工法。
1. A drilled trench 1, the floater 3 having sufficient buoyancy to support the overburden weight, floating pipeline unit engages the <br/> pipe 4 at predetermined intervals
The floating pipeline unit 2 is drawn into the trench 1 and floated on the surface of the water. The floating pipeline unit 2 is repeatedly joined with the floating pipeline unit 2 that has already been drawn in place.
A sinker 7 is immersed in the vicinity of the sinker 7 and the floater 3 is moored to the sinker 7.
JP05171450A 1993-07-12 1993-07-12 Construction method of floating pipeline Expired - Fee Related JP3092398B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP05171450A JP3092398B2 (en) 1993-07-12 1993-07-12 Construction method of floating pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP05171450A JP3092398B2 (en) 1993-07-12 1993-07-12 Construction method of floating pipeline

Publications (2)

Publication Number Publication Date
JPH0727299A JPH0727299A (en) 1995-01-27
JP3092398B2 true JP3092398B2 (en) 2000-09-25

Family

ID=15923334

Family Applications (1)

Application Number Title Priority Date Filing Date
JP05171450A Expired - Fee Related JP3092398B2 (en) 1993-07-12 1993-07-12 Construction method of floating pipeline

Country Status (1)

Country Link
JP (1) JP3092398B2 (en)

Also Published As

Publication number Publication date
JPH0727299A (en) 1995-01-27

Similar Documents

Publication Publication Date Title
US10287741B2 (en) Earth retaining system such as a sheet pile wall with integral soil anchors
KR20090114863A (en) Parallelly connected iron tube and construction method for underground structure using the same
JP2007177467A (en) Debris flow blocking work and its construction method
JP3092398B2 (en) Construction method of floating pipeline
RU2624937C1 (en) Method of surface pipeline construction in swamps
JP3554933B1 (en) How to build an underwater tunnel
JP3093937B2 (en) Pipe laying method
JP4223147B2 (en) Construction method for undersea structures
JPH10204883A (en) Execution method of reinforcing bank wall
JP2023158429A (en) Buried structure of buried pipe and method for burying buried pipe
JPS6058330B2 (en) Waterproof sheet installation method
JP2576902B2 (en) Construction methods and buildings in landfills
KR200414057Y1 (en) Y Type Connecting Structure of Steel Pipe Struts
KR20020068936A (en) Coupling Structure of Vertical Steel Bar for Reinforced Earth Retaining-Wall Frame
JPH02248513A (en) Laying method for water impermeable sheet
Goby Proper Installation of Corrugated Metal Structures
JPH10183589A (en) Temporary filling structure for excavated hole
JPH1025724A (en) Method of protective construction of sea-bottom ground
Wallace et al. Trombay power station: cooling water system
JPS5844803B2 (en) Kouyaitaheki no Kochikukohou
JP2000045299A (en) Supporting method of underground buried structure
JPH0469681B2 (en)
JPS63150700A (en) Method of sinking structure
Hernandez Buoyancy Control on the 56” Cross Island Gas Pipeline Project, Trinidad and Tobago
Van Antwerp Cleveland, Ohio's 108 Inch Outfall—A Special Marine Achievement

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20000627

LAPS Cancellation because of no payment of annual fees