JP3079381U - Revetment concrete block - Google Patents

Revetment concrete block

Info

Publication number
JP3079381U
JP3079381U JP2000005771U JP2000005771U JP3079381U JP 3079381 U JP3079381 U JP 3079381U JP 2000005771 U JP2000005771 U JP 2000005771U JP 2000005771 U JP2000005771 U JP 2000005771U JP 3079381 U JP3079381 U JP 3079381U
Authority
JP
Japan
Prior art keywords
block
main body
embankment
block main
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000005771U
Other languages
Japanese (ja)
Inventor
好治 加藤
Original Assignee
新田特殊建材工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 新田特殊建材工業株式会社 filed Critical 新田特殊建材工業株式会社
Priority to JP2000005771U priority Critical patent/JP3079381U/en
Application granted granted Critical
Publication of JP3079381U publication Critical patent/JP3079381U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)

Abstract

(57)【要約】 【課題】 通常、流水に洗われることのない河川敷の外
側や、湖沼等の緑化護岸堤防に用いる強固でかつ施行性
に優れた護岸用コンクリートブロックを提供する。 【解決手段】 底面が平坦で所定の強度を有する厚みを
有し、正面からみて方形状に成形されたコンクリートブ
ロックで、表面にたすき掛け状の突リブが突出してお
り、その交差部に水抜き孔を有すると共に厚さ方向に貫
通する植生用孔を備えていること及びブロック本体を並
べたとき相互に連通して棒鋼が挿通される連結用孔を備
えていることを特徴とする。
(57) [Summary] [PROBLEMS] To provide a concrete block for revetment which is strong and excellent in workability, which is usually used on the outside of a riverbed which is not washed by running water or on a greening revetment embankment such as a lake. SOLUTION: A concrete block having a flat bottom surface and a thickness having a predetermined strength, and formed in a square shape when viewed from the front side, has cross-shaped projecting ribs protruding from the surface, and drains water at intersections thereof. It has a hole for vegetation which has a hole and penetrates in the thickness direction, and has a hole for connection in which a bar is inserted in communication with each other when the block bodies are arranged.

Description

【考案の詳細な説明】[Detailed description of the invention]

【0001】[0001]

【考案の属する技術分野】[Technical field to which the invention belongs]

本考案は、例えば河川における遊水池のように、通常は冠水しない箇所の大型 堤防や、湖沼等の堤防に用いる護岸用コンクリートブロックに関する。 TECHNICAL FIELD The present invention relates to a concrete embankment used for a large embankment at a place where water is not normally flooded, for example, a flood pond in a river, or a dike for a lake or marsh.

【0002】[0002]

【従来の技術】[Prior art]

通常、流水に洗われることのない河川敷の外側に構築された堤防では盛土の表 面に草類の植生を施したものが一般的であった。 Usually, embankments constructed outside riverbeds that are not washed by running water generally have grass vegetation on the surface of the embankment.

【0003】 しかし、このような堤防であっても、過度の大雨による増水があると、崩壊の 危険性が高い。このため護岸用コンクリートブロックを法面に沿って積み上げて 補強することがなされている。[0003] However, even with such embankments, there is a high risk of collapse if there is an increase in water due to excessive heavy rain. For this reason, concrete blocks for revetment are piled up along the slope and reinforced.

【0004】 かかるコンクリートブロックによる護岸の場合には、コンクリート面が露出す るため、周囲の景観を著しく変化させるという問題がある。このため、従来では 特開平6−248627公報に記載された構造の護岸用コンクリートブロックが 用いられている。[0004] In the case of revetment using such concrete blocks, there is a problem that the surrounding scenery is significantly changed because the concrete surface is exposed. For this reason, a concrete block for revetment having a structure described in JP-A-6-248627 is conventionally used.

【0005】 図11は、上述した公報に記載された護岸用コンクリートブロックを示し、方 形状に形成された厚板のブロック本体50の底面に、堤防盛土内に埋め込む一対 の縦向きの板状をなしたアンカー部51,51が一体的に突設されている。 ブロック本体50の表面側には一対の突リブ52,52が一体に突設されてお り、この一対の突リブ52,52の間には広幅の蟻溝状の凹溝53となっている 。[0005] Fig. 11 shows a concrete block for revetment described in the above-mentioned publication, and a pair of vertically-oriented plate shapes to be embedded in embankment embankments are formed on the bottom surface of a thick block body 50 formed in a square shape. The anchor portions 51, 51 are integrally provided so as to protrude. A pair of protruding ribs 52, 52 are integrally formed on the surface side of the block body 50, and a wide dovetail-shaped concave groove 53 is formed between the pair of protruding ribs 52, 52. .

【0006】 又、ブロック本体にはコンクリート充填孔54が面方向に沿って貫通してる。 このコンクリート充填孔54は護岸用コンクリートブロックを施工するため、ブ ロック本体50を並べたとき、隣接するブロック本体50のコンクリート充填孔 54との間に鋼線及びコンクリートを充填して隣接するブロック体を連結するも のである。A concrete filling hole 54 penetrates through the block body along the surface direction. Since the concrete filling hole 54 is used for embankment concrete blocks, when the block main bodies 50 are arranged, a steel wire and concrete are filled between the concrete filling holes 54 of the adjacent block main bodies 50 and the adjacent block bodies 50 are filled. Is a concatenation of

【0007】 このような従来の護岸用コンクリートブロックの施工は以下のようにして行う 。まず、場所打コンクリートからなる基礎の上に、アンカー部51を築堤盛土の 法面側に向けた状態でブロック本体50を所定角度で積み上げる。この積み上げ は、ブロック本体50間でコンクリート充填孔54が連通するように行う。又、 ブロック本体50の積み上げ時には、ブロック本体50の底面に裏込め用の土砂 を詰めて築堤盛土と一体化する。 かかる積み上げの際には、連通状態のコンクリート充填孔54に鋼線及びコン クリートを充填して隣接するブロック本体を連結する。その後、表面側の凹溝5 3の間に表層盛土を充填しながら表層盛土を突き固める。この際、表層盛土に草 類の種子や肥料を混入させておくことにより、芝生類を成育させ、これにより緑 化護岸とすることができる。The construction of such a conventional seawall concrete block is performed as follows. First, the block main body 50 is stacked at a predetermined angle on a foundation made of cast-in-place concrete with the anchor portion 51 facing the slope side of the embankment. The stacking is performed such that the concrete filling holes 54 communicate between the block main bodies 50. In addition, when stacking the block main body 50, the bottom surface of the block main body 50 is filled with backfill soil and integrated with the embankment embankment. At the time of such stacking, the concrete filling hole 54 in the communicating state is filled with the steel wire and the concrete, and the adjacent block main bodies are connected. Thereafter, the surface embankment is compacted while filling the surface embankment between the concave grooves 53 on the front surface side. At this time, by mixing grass seeds and fertilizer into the surface embankment, the lawn can be grown, and thereby the greening seawall can be used.

【0008】[0008]

【考案が解決しようとする課題】[Problems to be solved by the invention]

しかしながら、従来の護岸用コンクリートブロックでは、ブロック本体50の 底面から突設しているアンカー部51を築堤盛土に対して並べる必要があるため 、施工が面倒となっている。又、アンカー部51の突設長さ分、ブロック本体5 0が大きくなると共に、重量が増すため、取扱いが難しくなり、施工効率が低下 する。 However, in the conventional concrete block for revetment, since the anchor portion 51 projecting from the bottom surface of the block body 50 needs to be arranged on the embankment embankment, the construction is troublesome. In addition, since the block body 50 becomes large and the weight increases by the length of the projecting portion of the anchor portion 51, the handling becomes difficult and the construction efficiency decreases.

【0009】 さらに、コンクリートブロックを積み上げたあとに、コンクリートブロックの 底面のアンカー部51,51の間隙に裏込め用の土砂を詰めて築堤盛土と一体化 させる手順となるため、施工効率面で問題があった。[0009] Furthermore, after the concrete blocks are stacked, the gap between the anchor portions 51, 51 on the bottom of the concrete block is filled with earth and sand for backfilling and integrated with the embankment embankment. was there.

【0010】 加えて、コンクリートブロックを積み上げた場合、ブロック本体表面の突リブ の間に突き固められた表層盛土が法面に沿って下方に滑り出して崩壊を起こし易 い。このため覆土の締め固めを均一、且つ十分にする必要があり、結果として施 工効率が悪くなる問題があった。 本考案はこのような従来の問題点を考慮してなされたものであり、取扱い性が 良好で、施工も簡単で施工効率を向上させることができ、さらには、施工後の崩 壊も起こすことのない護岸用コンクリートブロックを提供することを目的とする 。[0010] In addition, when the concrete blocks are stacked, the surface embankment compacted between the projecting ribs on the surface of the block main body slides down along the slope and easily collapses. For this reason, it is necessary to make the compaction of the cover soil uniform and sufficient, and as a result, there is a problem that the construction efficiency is deteriorated. The present invention has been made in consideration of such conventional problems, and has good handling properties, is easy to construct, can improve construction efficiency, and can cause collapse after construction. The purpose of the present invention is to provide a concrete block for revetment without rust.

【0011】[0011]

【課題を解決するための手段】[Means for Solving the Problems]

上記目的を達成するため、請求項1の考案にかかる護岸用コンクリートブロッ クの特徴は、底面が平坦面に形成され、表面にたすき掛け状の突リブが突出した ブロック本体と、 前記ブロック本体における突リブの交差部分を貫通する水抜き孔と、 前記ブロック本体における突リブ形成部位以外の部分に設けられ、ブロック本 体の厚さ方向に貫通する植生用孔と、 前記ブロック本体の面方向に沿って貫通し、ブロック本体が隣接して並べられ たとき、相互に連通して内部に棒鋼が挿通される連結用孔とを備え、 前記突リブがブロック本体から異なった角度で立ち上がる2つの斜面を有して おり、大きな角度で立ち上がる斜面が小さな角度で立ち上がる斜面の上方側に位 置するように前記ブロック本体が並べられることを特徴とする。 To achieve the above object, the concrete block for revetment according to the invention of claim 1 is characterized in that a bottom surface is formed in a flat surface, and a cross-shaped projecting rib projects from the surface; A drain hole that penetrates the intersection of the protruding ribs; a vegetation hole that is provided in a portion of the block main body other than the protruding rib forming portion and penetrates in the thickness direction of the block main body; And a connecting hole through which the steel bar is inserted when the block bodies are arranged adjacent to each other. The projecting ribs rise from the block body at different angles. The block main bodies are arranged such that a slope rising at a large angle is positioned above a slope rising at a small angle.

【0012】 請求項2の考案は、前記植生用孔がブロック本体の表面側が大径で、且つ、底 面側が小径となるようにブロック本体を貫通すると共に、表面側と底面側で偏心 していることを特徴とする請求項1記載の護岸用コンクリートブロックである。The invention according to claim 2 is that the vegetation hole penetrates the block main body so that the surface side of the block main body has a large diameter and the bottom surface side has a small diameter, and is eccentric on the surface side and the bottom side. The concrete block for revetment according to claim 1, characterized in that:

【0013】 このような護岸用コンクリートブロックは、堤体盛土に上下左右に隣接して並 べてコンクリート護岸壁を構築し、該コンクリート護岸壁の表面の突リブを埋め 込む一定厚さの表層盛土を敷設し、該盛土に植生を施すことで緑化護岸堤防を構 築することができる。Such a revetment concrete block is a surface embankment having a constant thickness in which a concrete revetment wall is constructed by lining up the embankment embankment vertically and horizontally and embedding projecting ribs on the surface of the concrete revetment wall. A greening revetment embankment can be constructed by laying vegetation and applying vegetation to the embankment.

【0014】 また、たすき掛け状の突リブは、ブロック本体が横に隣接して並べられたとき 左右に隣接するブロック本体の突リブと組み合うことにより、突リブ間に菱形の 凹部を形成するため、表層盛土のすべり出しを防止する。一方、上下に隣接して 並べられたとき上下左右のブロック本体の突リブが折れ線状の凹部を構成するた め、堤体傾斜面の下方への表層盛土のすべり出しを防止する。In addition, the cross rib-shaped projecting ribs form a diamond-shaped recess between the projecting ribs by combining with the projecting ribs of the block body adjacent to the left and right when the block bodies are arranged side by side. Prevents surface embankment from sliding. On the other hand, the protruding ribs of the upper, lower, left and right block bodies constitute bent-line concave parts when they are arranged vertically adjacent to each other, so that the surface embankment is prevented from sliding below the slope of the embankment.

【0015】 さらに、前記突リブがブロック本体から異なった角度で立ち上がる2つの斜面 を有しており、大きな角度で立ち上がる斜面が小さな角度で立ち上がる斜面の上 方側に位置するように前記ブロック本体が並べられることにより、前記の菱形の 凹部と折れ線状の凹部に表層盛土を充填し易く、さらに締め固めを均一にできる 。これにより表層盛土のすべり出しを抑制する。Further, the projecting rib has two slopes rising at different angles from the block body, and the block body is positioned such that the slope rising at a large angle is located above the slope rising at a small angle. By arranging, it is easy to fill the surface embankment into the rhombic concave portion and the polygonal concave portion, and the compaction can be made more uniform. Thereby, the sliding of the surface embankment is suppressed.

【0016】 又さらに、植生用孔は、ブロック本体の表面側が大径で、且つ底面側が小径と なるようにブロック本体を貫通していることから苗木等の植物の植え込みを容易 に行える。しかも貫通している孔が表面側と底面側で偏心していることにより堤 防の傾斜に対して、植生苗木が根本部で曲ることなく垂直に成長できるばかりで なく、苗木の根部が堤体本体内に張り出すため、コンクリート護岸と堤体盛土と を強固に定着させることができる。[0016] Furthermore, since the vegetation hole penetrates the block body so that the surface side of the block body has a large diameter and the bottom side has a small diameter, plants such as seedlings can be easily planted. In addition, the penetrating holes are eccentric on the front side and bottom side, so that not only can the vegetation seedlings grow vertically without bending at the root, but also the roots of the seedlings can be Since it protrudes into the main body, concrete revetment and embankment embankment can be firmly established.

【0017】 なお、表層盛土上にしみ込んだ雨水は、堤体の傾斜の下方のブロック本体の突 リブ交差部分に集まるが、交差部分を貫通する水抜き孔を通水して堤体最下部ま で確実に排水できる。[0017] Rainwater that has infiltrated the surface embankment collects at the protruding rib intersections of the block body below the slope of the embankment, but flows through the drainage hole penetrating the intersection to reach the bottom of the embankment. The drain can be surely done.

【0018】[0018]

【実施の形態】Embodiment

図1〜図7は本考案の一実施の形態の護岸用コンクリートブロック1を示す。 1 to 7 show a concrete block 1 for seawall according to an embodiment of the present invention.

【0019】 この護岸用コンクリートブロック1は、底面14及び表面15を有した方形状 に形成されたブロック本体10と、ブロック本体10に設けられた水抜き孔20 、植生用孔30及び連結用孔40とを備え、全体が鉄筋コンクリートによって成 形されている。 ブロック本体10は所定の強度を有する厚みを有し、正面から見て方形状に成 形されている。ブロック本体10の底面14は図2〜図4に示すように、平坦面 となっており、底面14からの突起物は存在しない。又、表面15には突リブ1 1が突出している。The revetment concrete block 1 has a rectangular block body 10 having a bottom surface 14 and a surface 15, a drain hole 20, a vegetation hole 30, and a connection hole provided in the block body 10. 40, and the whole is made of reinforced concrete. The block body 10 has a thickness having a predetermined strength, and is formed in a square shape when viewed from the front. The bottom surface 14 of the block main body 10 is a flat surface as shown in FIGS. 2 to 4, and there is no protrusion from the bottom surface 14. The protruding rib 11 protrudes from the surface 15.

【0020】 図1に示すように、ブロック本体10の方形状の4隅部に端部が一致し、且つ 、方形状の略中央部分で交差するたすき掛け状となって表面15から突出してい る。突リブ11は断面台形形状に成形されており、このため、ブロック本体10 の表面15から傾斜状に立ち上がる2つの斜面11a,11bと、斜面11a, 11bの頂部を連設する平面状の頂面11eとを備えている。又、2つの斜面に おける一方の斜面11aは他方の斜面11bよりも大きな角度で立ち上がるもの であり、施工時には大きな角度で立ち上がる斜面11aが上方側に位置し、小さ な角度で立ち上がる斜面11bが下方側に位置するようにブロック本体10が並 べられる。As shown in FIG. 1, the ends of the block main body 10 coincide with the four corners of the square, and the block main body 10 protrudes from the surface 15 in a cross-like shape that intersects at substantially the center of the square. . The protruding rib 11 is formed to have a trapezoidal cross section. Therefore, two flat surfaces 11a and 11b rising from the surface 15 of the block main body 10 in an inclined manner, and a flat top surface in which the top portions of the slopes 11a and 11b are continuously provided. 11e. In addition, one slope 11a of the two slopes rises at a larger angle than the other slope 11b. During construction, the slope 11a rising at a large angle is located on the upper side, and the slope 11b rising at a small angle is located on the lower side. The block bodies 10 are lined up so as to be located on the side.

【0021】 水抜き孔20はかかるたすき掛け状の突リブ11の交差部分に設けられる。水 抜き孔20は突リブの交差部分を貫通するように設けられ、施工時には、この水 抜き孔20が上下方向を向くようにブロック本体10が並べられる。The drain hole 20 is provided at the intersection of the cross rib-shaped projecting ribs 11. The drain holes 20 are provided so as to penetrate the intersections of the protruding ribs, and at the time of construction, the block bodies 10 are arranged so that the drain holes 20 face up and down.

【0022】 植生用孔30はブロック本体10における突リブ11形成部位以外の部分に形 成されている。この実施の形態では、突リブ11によって区画された内の一の区 画部に植生用孔30が形成されているが、二以上の区画部に形成されていても良 い。かかる植生用孔30は堤体で成長した苗木等が抜き出るものであり、ブロッ ク本体10を厚さ方向に貫通している。The vegetation hole 30 is formed in a portion of the block main body 10 other than the portion where the projecting rib 11 is formed. In this embodiment, the vegetation hole 30 is formed in one of the sections defined by the protruding ribs 11, but may be formed in two or more sections. The vegetation holes 30 are for extracting seedlings and the like grown on the embankment, and penetrate the block body 10 in the thickness direction.

【0023】 図6に示すように、植生用孔30はブロック本体10の表面15側が大径で、 且つ底面14側が小径となるようにブロック本体10を貫通している。又、この 実施の形態の植生用孔30は表面15側の開口中心と、底面14側の開口中心と が偏心するように貫通しており、これにより、水抜き孔20から離れた内面が緩 やかに傾斜した構造となっている。このような構造とすることにより植生用孔3 0を貫通する苗木等がブロック本体10の上方を向くように生育できる。As shown in FIG. 6, the vegetation hole 30 penetrates the block main body 10 such that the surface 15 side of the block main body 10 has a large diameter and the bottom surface 14 has a small diameter. In addition, the vegetation hole 30 of this embodiment penetrates so that the center of the opening on the surface 15 side and the center of the opening on the bottom surface 14 are eccentric. It has a sloping structure. With such a structure, a seedling or the like penetrating through the vegetation hole 30 can grow so as to face upward of the block body 10.

【0024】 連結用孔40は図2,図4,図7に示すように、ブロック本体10の面方向に 沿って貫通するものであり、その内部には棒鋼が挿通すると共に、コンクリート が充填される。この連結用孔40は一のブロック本体10に対し、2条が設けら れるが、それ以上であっても良い。As shown in FIGS. 2, 4, and 7, the connection hole 40 penetrates along the surface direction of the block main body 10, and a steel bar is inserted therein, and concrete is filled therein. You. The connection hole 40 is provided in two lines with respect to one block main body 10, but may be more than two.

【0025】 次に、この実施の形態を用いて護岸を施工する手順を説明する。Next, a procedure for constructing a revetment using this embodiment will be described.

【0026】 図8に示すように場所打コンクリートをもって法留60を構築し、築堤下部と 法留コンクリートの間に透水性の裏込用の土砂61を詰めてつき固め、予め定め られた傾斜角の法面となるよう堤体盛土を仕上げる。その上に吸出し防止マット 62又は遮水シートを敷きその上にブロック本体10を所望の傾斜高さまで積み 上げる。As shown in FIG. 8, a cast-in-place concrete is used to construct a dorm 60, and a permeable backing earth and sand 61 is packed between the embankment lower part and the settled concrete, and the concrete is fixed to a predetermined inclination angle. Finish the embankment embankment so that it becomes the slope of. A suction-prevention mat 62 or a water-blocking sheet is laid thereon, and the block main body 10 is stacked thereon to a desired inclination height.

【0027】 このとき、ブロック本体10は、突リブ11の斜面11aが上方側に位置する ように配置する。更に水抜き孔20は、上下方向に貫通した位置となり浸透した 雨水等が堤体下面に排出される構造となる。At this time, the block body 10 is arranged such that the slope 11 a of the protruding rib 11 is located on the upper side. Further, the drain hole 20 is located at a position penetrating in the vertical direction, and has a structure in which permeated rainwater or the like is discharged to the lower surface of the embankment body.

【0028】 このとき、ブロック本体10の底面14は、平坦面となっており、雨水、流水 に対する堤防の強度保持に効果のある吸出し防止マットや、遮水シートを、突起 により穴あきや破るなどの破損を起こす心配がなく行なえ、施行効率を良く行な える。At this time, the bottom surface 14 of the block body 10 is a flat surface, and a protrusion or a perforation prevention mat that is effective for maintaining the strength of the embankment against rainwater and running water is perforated or broken by a projection. There is no need to worry about damage to the equipment, and the efficiency of enforcement can be improved.

【0029】 さらに、コンクリートブロックの底面と堤体の間に定着アンカーなどの間隙が 存在しないため、堤体下段から順に1段ごとに裏込め用の土砂を詰めながら所望 の傾斜高さまで積み上げる必要がなくブロック本体を次々と積み上げることがで き、施行効率が向上する。Furthermore, since there is no gap such as anchors between the bottom of the concrete block and the embankment, it is necessary to stack up to a desired inclination height while filling backfill earth and sand one by one from the bottom of the embankment. Blocks can be piled up one after another, improving the efficiency of enforcement.

【0030】 このとき、上下のブロック本体10は図9に示すように横方向に長さの1/2 づつ側方にずらして設置し、下側のブロック本体の連結用孔40の左側40aの 上に上側のブロック本体の連結用孔40の右側孔40bが連通するよう、いわゆ る布積状となす。At this time, as shown in FIG. 9, the upper and lower block main bodies 10 are laterally shifted by 1 / of the length in the lateral direction, and are set at the left side 40 a of the connection hole 40 of the lower block main body. A so-called cloth shape is formed so that the right side hole 40b of the connection hole 40 of the upper block body communicates with the upper side.

【0031】 このようにして、各ブロック本体10を順次積み上げて所定の高さに積み上げ る毎に連結用孔に棒鋼63を挿入し、充填孔にコンクリートを流し込み各ブロッ クを上下左右一体化することで積み上げ工程と連接棒鋼挿入連結を併行して進行 させることができる。In this manner, each time the block bodies 10 are sequentially stacked and stacked to a predetermined height, the bar steel 63 is inserted into the connecting hole, concrete is poured into the filling hole, and the blocks are integrated vertically and horizontally. This allows the stacking process and the connecting and connecting steel bars to proceed in parallel.

【0032】 このようにして、堤体法面に構築したコンクリート護岸の堤体最下部に止杭6 4を設け、排水を良くする拾石65を盛石した後、コンクリート護岸の表面に、 図8に示すように表層覆土66を覆土を敷設し、突き固める。In this manner, the retaining pile 64 is provided at the bottom of the embankment of the concrete revetment constructed on the slope of the embankment. As shown in (1), the surface covering soil 66 is laid with the covering soil and compacted.

【0033】 このとき、コンクリート護岸表面は、隣接するブロック本体10が組み合うこ とにより、図9に示すように、突リブ11が菱形の凹部と折れ線状の凹部を形成 し、盛土を保持するばかりでなく、突リブ11の上方向の斜面の角度が大きいた め、すべり出しの抑止と加えて突き固めを均一に行うことができる。At this time, as shown in FIG. 9, the protruding ribs 11 form a rhombic concave portion and a polygonal linear concave portion as shown in FIG. In addition, since the angle of the upward slope of the protruding rib 11 is large, it is possible to suppress the sliding and uniformly perform the compaction.

【0034】 さらに表層盛土に当って、堤体の強化と緑化のために植生用孔30の要所に苗 木などの樹木を植え込むことが望ましい。苗木の植え込みは、植生用孔30はブ ロック本体表面が大径となっているいわゆるすりばち状の貫通孔のため植え易い 他、貫通孔の中心が堤防の傾斜に対して垂直方向に偏心しているため根部をしっ かり植え込むことができる。植生しない孔も、堤体と表層盛土とのすべり出し防 止の働きを持つ。Furthermore, it is desirable to plant trees such as seedlings at key points of the vegetation holes 30 in order to reinforce the embankment body and to green the surface embankment. When planting seedlings, the vegetation hole 30 is easy to plant because of the so-called slash-shaped through hole in which the surface of the block body has a large diameter, and the center of the through hole is eccentric in the vertical direction with respect to the slope of the embankment. Therefore, the root can be firmly implanted. Holes that are not vegetated also have the function of preventing slippage between the embankment and the surface embankment.

【0035】 最後に、表層盛土には予め草類の種子肥料を混入させておくか、又は表面に芝 生類を貼りこれを生育させて植生となす(図示せず)。この草木が成育すること で、その根が盛土の土砂を保持し、強固に定着する。Finally, grass seed fertilizer is mixed in the surface embankment in advance, or lawn is pasted on the surface and grown to form vegetation (not shown). As the plants grow, their roots hold the embankment and become firmly established.

【0036】[0036]

【考案の効果】[Effect of the invention]

上述したように、本考案においては底面が平坦に形成されたブロック本体とす ることで、裏込め土砂の詰め込み工程がなく、ブロック本体Aの積上げ工程と鉄 筋等の連結鉄棒の挿入工程が併行して進めることができ施行効率が大幅に向上す る。 更に、堤体強度を補強する吸出しマットや遮水シートの破損を防止し強度を保 持することができる。 As described above, in the present invention, the block main body having a flat bottom surface eliminates the step of stuffing the backfill soil, and the step of stacking the block main body A and the step of inserting the connecting iron rods such as reinforcing bars. Enforcement efficiency can be greatly improved because it can proceed in parallel. Furthermore, it is possible to prevent breakage of the suction mat and the impermeable sheet that reinforce the strength of the embankment body and maintain the strength.

【0037】 また、ブロック単体は大型であり施工性に優れ、連結鉄棒によってマット状に 一体化されることにより強固であるが堤体地盤の変化に対して適度の屈撓性を発 揮する。Further, the block itself is large and excellent in workability, and is strong by being integrated in a mat shape by a connecting iron bar, but exerts an appropriate flexing property against changes in the embankment ground.

【0038】 また、ブロック本体表面の突リブにより形成される上方に大きな角度を持つ菱 形の凹部及び折れ線状の凹部に表層盛土が嵌まり込み、容易にすべり出しを起こ さないため容易に洗い流れることがなく雨水により植生用孔に植えた苗木や、表 層土の植生草木により緑化が維持される。In addition, the surface embankment fits into a diamond-shaped concave portion and a polygonal concave portion having a large angle formed by the protruding rib on the surface of the block body, and the surface embankment does not easily slide out, so that it is easily washed off. The greenery is maintained by the seedlings planted in the vegetation holes by rainwater and vegetation on the surface soil.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本考案に係る護岸用コンクリートブロックの正
面図である。
FIG. 1 is a front view of a revetment concrete block according to the present invention.

【図2】同上の平面図である。FIG. 2 is a plan view of the same.

【図3】同上の背面図である。FIG. 3 is a rear view of the same.

【図4】同上の底面図である。FIG. 4 is a bottom view of the same.

【図5】同上の右側面図である。FIG. 5 is a right side view of the same.

【図6】正面図A−A線断面図である。FIG. 6 is a front view taken along line AA of FIG.

【図7】正面図B−B線断面図である。FIG. 7 is a front view taken along the line BB.

【図8】本考案に係る護岸の完成状態を示す鉄筋用横断
面図である。
FIG. 8 is a cross-sectional view of a reinforcing bar showing a completed state of the revetment according to the present invention.

【図9】同上の正面図である。FIG. 9 is a front view of the same.

【図10】同上の連結部拡大図である。FIG. 10 is an enlarged view of a connecting portion according to the embodiment.

【図11】特願平6−248627公知の護岸用コンク
リートブロックの平面図である。
FIG. 11 is a plan view of a seawall concrete block known in Japanese Patent Application No. 6-248627.

【符号の説明】[Explanation of symbols]

10 ブロック本体 11 突リブ 11a,11b 斜面 11e 頂面 14 底面 15 表面 20 水抜き孔 30 植生用孔 40 連結用孔 50 ブロック本体 51 アンカー部 52 突リブ 53 凹溝 54 コンクリート充填孔 60 法留 61 土砂 62 吸出し防止マット 63 棒鋼 64 止杭 65 拾石 66 表層覆土 DESCRIPTION OF SYMBOLS 10 Block main body 11 Protrusion rib 11a, 11b Slope 11e Top surface 14 Bottom surface 15 Surface 20 Drain hole 30 Vegetation hole 40 Connection hole 50 Block main body 51 Anchor part 52 Protrusion rib 53 Depression groove 54 Concrete filling hole 60 Dome 61 Sand 62 Suction prevention mat 63 Steel bar 64 Stop pile 65 Pick stone 66 Surface soil cover

Claims (2)

【実用新案登録請求の範囲】[Utility model registration claims] 【請求項1】 底面が平坦面に形成され、表面にたすき
掛け状の突リブが突出したブロック本体と、 前記ブロック本体における突リブの交差部分を貫通する
水抜き孔と、 前記ブロック本体における突リブ形成部位以外の部分に
設けられ、ブロック本体の厚さ方向に貫通する植生用孔
と、 前記ブロック本体の面方向に沿って貫通し、ブロック本
体が隣接して並べられたとき、相互に連通して内部に棒
鋼が挿通される連結用孔とを備え、 前記突リブがブロック本体から異なった角度で立ち上が
る2つの斜面を有しており、大きな角度で立ち上がる斜
面が小さな角度で立ち上がる斜面の上方側に位置するよ
うに前記ブロック本体が並べられることを特徴とする護
岸用コンクリートブロック。
1. A block main body having a flat bottom surface and projecting cross-shaped protruding ribs on the surface, a drain hole penetrating an intersection of the protruding ribs in the block main body, and a protrusion in the block main body. A vegetation hole provided in a portion other than the rib forming portion and penetrating in the thickness direction of the block main body; and a vegetation hole penetrating along the surface direction of the block main body and communicating with each other when the block main bodies are arranged adjacent to each other. And a connecting hole through which a steel bar is inserted. The projecting rib has two slopes rising at different angles from the block body, and the slope rising at a large angle is located above the slope rising at a small angle. A concrete block for revetment, wherein the block bodies are arranged so as to be located on the side.
【請求項2】 前記植生用孔はブロック本体の表面側が
大径で、且つ、底面側が小径となるようにブロック本体
を貫通すると共に、表面側と底面側で偏心していること
を特徴とする請求項1記載の護岸用コンクリートブロッ
ク。
2. The vegetation hole penetrates the block main body so that the surface side of the block main body has a large diameter and the bottom side has a small diameter, and is eccentric on the front side and the bottom side. Item 2. A concrete block for revetment according to item 1.
JP2000005771U 2000-08-10 2000-08-10 Revetment concrete block Expired - Fee Related JP3079381U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000005771U JP3079381U (en) 2000-08-10 2000-08-10 Revetment concrete block

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000005771U JP3079381U (en) 2000-08-10 2000-08-10 Revetment concrete block

Publications (1)

Publication Number Publication Date
JP3079381U true JP3079381U (en) 2001-08-17

Family

ID=43212262

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000005771U Expired - Fee Related JP3079381U (en) 2000-08-10 2000-08-10 Revetment concrete block

Country Status (1)

Country Link
JP (1) JP3079381U (en)

Similar Documents

Publication Publication Date Title
US6715965B2 (en) Retaining wall blocks and retaining walls constructed from such blocks
US20070110522A1 (en) Retaining wall constructed using sandbags
CN117926849A (en) Construction method and application of high-strength gravity retaining wall
KR20110047424A (en) Vegetation retaining wall using vegetation spaces formed by continuous connection of concrete files and constructing method thereof
KR100654936B1 (en) Method for constructing retaining wall
KR100402843B1 (en) Afforestation Retaining-Wall laying Concrete-block
JP3079381U (en) Revetment concrete block
KR200442424Y1 (en) The block for a breast wall with grass growing structure
KR101334749B1 (en) Vegetation block in tiers for retaining wall and method for construction of retaining wall using the same
CN113322895A (en) Three-dimensional water and soil protection revetment and construction method thereof
KR100536304B1 (en) Vegetation revetment structures and method constructing blocktype revetment using the same
KR101055295B1 (en) Revetment construction method using revetment structure of vegetational gabion with grid in a body and vegetational gabion therewith
JP2000136519A (en) Concrete block for revetment
KR200247050Y1 (en) Embankment block
JP3266876B2 (en) Soil / cover soil block and construction method
KR100946224B1 (en) Soil mass block for front side vegetation and Retaining wall using the same
KR200357964Y1 (en) Block for retaining wall
CN211006542U (en) River course revetment reinforced structure
KR20130050408A (en) Revet block with plant earth bag and its construction method
CN216130149U (en) Slope protection system for artificial side slope
KR200235107Y1 (en) Afforestation Retaining-Wall laying Concrete-block
CN216474808U (en) Ecological revetment with ecological frame and three-dimensional soil fixation net pad combined
CN219975613U (en) Ecological bag staggered joint lamination connecting piece for relief restoration
JPS5820338B2 (en) Slope stabilization method
JP3236880B2 (en) Greening seawall and concrete block for seawall

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees