JP3031530B2 - How to build a concrete pier - Google Patents

How to build a concrete pier

Info

Publication number
JP3031530B2
JP3031530B2 JP7238839A JP23883995A JP3031530B2 JP 3031530 B2 JP3031530 B2 JP 3031530B2 JP 7238839 A JP7238839 A JP 7238839A JP 23883995 A JP23883995 A JP 23883995A JP 3031530 B2 JP3031530 B2 JP 3031530B2
Authority
JP
Japan
Prior art keywords
steel
concrete
precast
reinforcing bar
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP7238839A
Other languages
Japanese (ja)
Other versions
JPH0978763A (en
Inventor
洋治郎 吉田
佳男 篠田
稔 田畑
一徳 河野
文則 佐藤
利哉 長崎
由剛 岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Maeda Corp
Original Assignee
JFE Steel Corp
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Steel Corp, Maeda Corp filed Critical JFE Steel Corp
Priority to JP7238839A priority Critical patent/JP3031530B2/en
Priority to TW85114692A priority patent/TW387959B/en
Publication of JPH0978763A publication Critical patent/JPH0978763A/en
Application granted granted Critical
Publication of JP3031530B2 publication Critical patent/JP3031530B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明はコンクリート橋脚の
築造方法、及びプレキャスト型枠に関する。
The present invention relates to a method for constructing a concrete pier and a precast formwork.

【0002】[0002]

【従来の技術】従来、鉄筋コンクリート構造物を築造す
る場合、帯鉄筋は、現場において配筋した主鉄筋にバイ
ンド線等で直接結束して組み立てるのが普通である。
2. Description of the Related Art Conventionally, when constructing a reinforced concrete structure, it is common practice to assemble a band reinforcing bar by directly binding it to a main reinforcing bar arranged at a site with a binding wire or the like.

【0003】一方、鉄骨コンクリート構造物、あるいは
鉄骨鉄筋コンクリート構造物の場合は、鉄骨に帯鉄筋を
直接結束することが困難なため、帯鉄筋の組立は、専用
の組立用の鉄筋または鋼材等を用いて現場合わせにより
行っていた。
On the other hand, in the case of a steel frame concrete structure or a steel frame reinforced concrete structure, since it is difficult to directly bind a steel bar to a steel frame, the steel bar is assembled using a special steel bar or steel material for assembly. Was done by site adjustment.

【0004】[0004]

【発明が解決しようとする課題】しかし、上述した従来
の方法では、帯鉄筋の組立に多くの手間と労力がかかり
工期の多くを占めることとなる。特に、鉄骨を使用した
場合には帯鉄筋の組立が困難であるため工期延長の原因
となっている。そしてこのような作業を、高所等の現場
で行うことは危険であり、作業の安全性の観点から好ま
しくない。
However, in the above-mentioned conventional method, assembling of the reinforcing bar requires a lot of labor and labor and occupies much of the construction period. In particular, when a steel frame is used, it is difficult to assemble the strip reinforcing bar, which causes an increase in the construction period. It is dangerous to perform such a work at a site such as a high place, and it is not preferable from the viewpoint of work safety.

【0005】さらに従来の方法では、コンクリート型枠
と帯鉄筋の位置精度が十分でないため、コンクリートの
かぶり精度がとれないという問題がある。また、鉄筋の
配置間隔等の組み立て精度も十分に得られないことも指
摘されていた。
[0005] Further, in the conventional method, there is a problem that the covering accuracy of the concrete cannot be obtained because the positional accuracy of the concrete formwork and the reinforcing bar is not sufficient. It has also been pointed out that sufficient assembling accuracy such as the arrangement interval of reinforcing bars cannot be obtained.

【0006】本発明は前記事項に鑑みてなされたもの
で、工期を短縮し、作業の安全性を増大させ、かつかぶ
り精度や組み立て精度を改善することができるようにし
たコンクリート構造物の築造方法と、その築造に使用す
るプレキャスト型枠を提供することを技術的課題とす
る。
SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and has a method for constructing a concrete structure capable of shortening a construction period, increasing work safety, and improving cover accuracy and assembly accuracy. And to provide a precast formwork used for the construction.

【0007】[0007]

【課題を解決するための手段】本発明は前記技術的課題
を解決するために、以下のような方法とした。即ち、
め形成した橋脚の基礎上に鉄骨を所要の高さまで建て込
む工程と、内側に帯鉄筋取付具を介して帯鉄筋が配され
た枠状のプレキャスト型枠を形成する工程と、前記鉄骨
を取り囲むようにこのプレキャスト型枠を複数積み重ね
る工程と、前記プレキャスト型枠内にコンクリートを打
設し硬化させ、前記鉄骨、前記帯鉄筋及びプレキャスト
型枠を一体化する工程と、を有するものとした。
The present invention employs the following method to solve the above technical problems. In other words, the pre
A steel frame is built up to the required height on the foundation of the formed pier.
And a reinforcing bar is arranged inside via a reinforcing bar
Forming a frame-shaped precast formwork; and
Stack this precast formwork to surround
And casting concrete into the precast formwork.
Set and harden, the steel frame, the band rebar and precast
And a step of integrating the formwork.

【0008】この方法で使用するプレキャスト型枠は、
コンクリートが打設される内側面に帯鉄筋取付具を固定
するとともに、この帯鉄筋取付具に帯鉄筋を取り付けた
ものである。
The precast formwork used in this method is:
A belt reinforcement is fixed to an inner surface on which concrete is cast, and a reinforcement is attached to the reinforcement.

【0009】以下、構成要素について説明する。 〔コンクリート橋脚〕 プレキャスト型枠工法によって構築される鉄骨コンクリ
ート、及び鉄筋と鉄骨を併用した鉄骨鉄筋コンクリート
のものをいう。 〔プレキャスト型枠〕 主にモルタルで形成され、通常、工場等で製造され現場
で組み立てられるものである。現場打ちコンクリートの
硬化後は、脱型をしないでそのまま構造物の一部を構成
する。表面は化粧がされてもよく、そのままでもよい。
これは工業製品であるので、これを使用して構築される
構造物の耐久性や美観の向上を製造段階で実現すること
ができる。
Hereinafter, the components will be described. [Concrete bridge pier] Steel reinforced concrete constructed by precast formwork, and steel reinforced concrete using both steel bars and steel frames. [Precast formwork] It is mainly formed of mortar, and is usually manufactured in a factory or the like and assembled on site. After the cast-in-place concrete is hardened, it is part of the structure without demolding. The surface may be decorated or left untouched.
Since this is an industrial product, the durability and aesthetics of a structure constructed using the product can be improved at the manufacturing stage.

【0010】また、製造時に各種の補強材、例えばスチ
ールファイバー、ステンレスファイバー、アラミド、ビ
ニロン、炭素繊維、及びガラス繊維等を混入することが
できる。これら補強材を混入することにより、プレキャ
スト型枠の引張強度を増加させることができる。またプ
レキャスト型枠の基材モルタルは水セメント比が20〜
60%のセメント系モルタルとすることが好ましい。こ
のような低水セメント比のモルタルを使用した場合に
は、塩分、二酸化炭素、酸素、水などの腐食因子の侵入
に対する抵抗性が大きくなり、構造物の耐久性を向上さ
せることができる。
Further, various reinforcing materials such as steel fiber, stainless fiber, aramid, vinylon, carbon fiber, glass fiber and the like can be mixed during the production. By incorporating these reinforcing materials, the tensile strength of the precast formwork can be increased. The base mortar of the precast mold has a water-cement ratio of 20 to
It is preferable to use a 60% cement mortar. When a mortar having such a low water cement ratio is used, the resistance to corrosion factors such as salt, carbon dioxide, oxygen, and water is increased, and the durability of the structure can be improved.

【0011】上記のようにして強化されたプレキャスト
型枠を使用するときは、通常鉄骨コンクリート構造で問
題となるひび割れ幅が大きく、変形が過大である等の問
題を解決することができる。 〔帯鉄筋〕 せん断補強筋とも呼ばれ、断面棒状あるいは板状であっ
て、型枠1の内面から離して設置するため帯鉄筋取付具
を介して固定する。帯鉄筋をその内側に設置する鉄骨ま
たは鉄筋と接触させない状態で中詰コンクリートを打設
する。〔帯鉄筋取付具〕 帯鉄筋取付具は例えば、Lアングルや小型のH鋼等を使
用でき、前記帯鉄筋を支持するとともに、型枠と帯鉄筋
との間に適度な間隙を形成するものである。中詰コンク
リート打設後はこの間隙がコンクリートのかぶりとな
る。 〔鉄骨〕 鉄骨はH型鋼が好適であるが、L型鋼も使用可能であ
る。前記基礎の上面から突出させた鉄骨やアンカーに接
続する。また鉄骨のフランジ面等に凹凸を設けるとコン
クリートの付着性が向上し、コンクリートとの一体性が
得られる。この凹凸は、後付けのものは勿論、製造段階
で表面に凹凸を形成したものであってもよい。
When the precast form reinforced as described above is used, it is possible to solve problems such as a large crack width and excessive deformation which are usually a problem in a steel concrete structure. [Band Reinforcing Bar] Also called a shear reinforcing bar, which has a bar-shaped or plate-shaped cross-section, and is fixed via a band-bar reinforcing member to be installed away from the inner surface of the formwork 1. The filling concrete is cast in a state where the belt reinforcing bar does not come into contact with the steel frame or the reinforcing bar installed inside. [Band Reinforcement Attachment] The band rebar attachment can use, for example, an L angle or a small H steel, and supports the band rebar and forms an appropriate gap between the formwork and the band rebar. is there. After casting concrete, this gap becomes the concrete cover. [Steel Frame] The steel frame is preferably an H-shaped steel, but an L-shaped steel can also be used. It is connected to a steel frame or an anchor projecting from the upper surface of the foundation. In addition, if irregularities are provided on the flange surface or the like of the steel frame, the adhesiveness of the concrete is improved, and the integrity with the concrete is obtained. The irregularities may be not only retrofitted ones but also irregularities formed on the surface at the manufacturing stage.

【0012】このように表面に突起を形成した鉄骨を使
用することにより、構造物のひび割れ幅の抑制やじん性
を改善することができる
By using the steel frame having the projections formed on the surface as described above, it is possible to suppress the crack width of the structure and improve the toughness.

【0013】[0013]

【発明の実施の形態】本発明のコンクリート橋脚の築造
方法について、図1ないし図4に基づいてさらに説明す
る。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A method for constructing a concrete pier according to the present invention will be further described with reference to FIGS.

【0014】本実施の形態では、図1に示すように、筒
状に形成したプレキャストコンクリート製のプレキャス
ト部材7を型枠1で囲まれる部分の中央部に設けるよう
になっており、以下の施工を行う前に予め基礎2の中央
部分に立設するようにしている。ただしこのプレキャス
ト部材7の設置は必須のものではない。なお、前記プレ
キャスト部材7は円形に形成され、その内径は3.1メ
ートル、厚みは0.1メートルとしてある。
In the present embodiment, as shown in FIG. 1, a precast member 7 made of a precast concrete formed in a cylindrical shape is provided at the center of a portion surrounded by the formwork 1. Before performing the above, it is erected in the center part of the foundation 2 in advance. However, the installation of the precast member 7 is not essential. The precast member 7 is formed in a circular shape, and has an inner diameter of 3.1 meters and a thickness of 0.1 meters.

【0015】前記型枠1は、最終的には橋脚の外壁とな
るもので、環状に形成したプレキャストコンクリート製
である。この型枠1はステンレススチール製の補強材を
体積比で1%ないし4%混入してあり、湾曲した板を接
続して一体の環状体としたものである。その断面は円形
であり、直径は4.5メートル、高さが2.5メート
ル、厚みが5センチメートルである。この型枠1はクレ
ーン(図示せず)で吊り下げて基礎2の上に積み重ね、
所望の高さを得る。
The formwork 1 finally becomes the outer wall of the pier, and is made of annularly formed precast concrete. The mold 1 contains a stainless steel reinforcing material in a volume ratio of 1% to 4%, and is formed by connecting curved plates to form an integral annular body. Its cross section is circular, 4.5 meters in diameter, 2.5 meters in height and 5 cm in thickness. The form 1 is suspended by a crane (not shown) and stacked on a foundation 2.
Get the desired height.

【0016】また前記プレキャスト型枠1の内面には図
4に示すように、L型鋼材で形成した取り付け帯鉄筋取
付具5aが1.2メートル間隔(したがってプレキャス
ト型枠1のひとつおきに)で取り付けられている。この
帯鉄筋取付具5aは、プレキャスト型枠1の内側円周上
に一定間隔をおいて設けたリング状の平鋼37の上に固
定される。35はつり下げ用平鋼であり、36はつり下
げ用の穴である。この帯鉄筋取付具5aには所定の間隔
をおいて組立鉄筋6が取り付けられている。この組立鉄
筋6は図4に示すように、橋脚の高さ方向に沿って設け
る。そして、この組立鉄筋6にこれに直交するように帯
鉄筋3が取り付けられ、これらは格子状となる。この帯
鉄筋3はプレキャスト型枠1の高さ方向に略15センチ
メートル間隔で設けられ、図3に示すように配筋され
る。
As shown in FIG. 4, on the inner surface of the precast form 1, mounting strip reinforcing members 5a formed of an L-shaped steel material are arranged at intervals of 1.2 meters (accordingly, every other one of the precast forms 1). Installed. The band reinforcing bar attachment 5 a is fixed on a ring-shaped flat steel 37 provided at a constant interval on the inner circumference of the precast form 1. Reference numeral 35 denotes a hanging flat steel, and reference numeral 36 denotes a hanging hole. Assembled reinforcing bars 6 are attached to the band reinforcing bar attachment 5a at predetermined intervals. As shown in FIG. 4, the rebar 6 is provided along the height of the pier. Then, the band reinforcing bar 3 is attached to the assembled reinforcing bar 6 so as to be orthogonal to the assembly reinforcing bar 6, and these are formed in a lattice shape. The band reinforcing bars 3 are provided at intervals of approximately 15 cm in the height direction of the precast formwork 1, and are arranged as shown in FIG.

【0017】この工程と前後して前記プレキャスト部材
7の周囲に鉄骨4を立設する。前記基礎2には予めアン
カーとして鉄骨4と同等以上の構造体(図示せず)が埋
設されており、この構造体に鉄骨4をボルト締めで接続
する。鉄骨4はH型鋼(H−318×313×15×2
4)が使用されており、図1に示すように、帯鉄筋3及
びプレキャスト部材7のいずれにも接触しない位置に建
て込む。この鉄骨4を立設する工程は、前記型枠1の積
み重ね工程あるいはプレキャスト材7の設置工程とその
施工の前後は問わない。
Before or after this step, the steel frame 4 is erected around the precast member 7. A structure (not shown) equal to or more than the steel frame 4 is embedded in the foundation 2 as an anchor in advance, and the steel frame 4 is connected to this structure by bolting. The steel frame 4 is an H-shaped steel (H-318 x 313 x 15 x 2
4) is used, and as shown in FIG. 1, it is erected at a position where it does not come into contact with any of the strip reinforcing bar 3 and the precast member 7. The step of erecting the steel frame 4 may be performed before or after the step of stacking the formwork 1 or the step of installing the precast material 7 and the execution thereof.

【0018】以上の施工を行うことで図2に示すような
半完成状態になる。型枠1と鉄骨4とを必要な段数接続
して橋脚を所望の高さとした後、前記プレキャスト部材
7と型枠1との間にコンクリートを打設し、これを硬化
させることにより完成する。 〔試験例1〕 本発明の鉄骨プレキャストコンクリート構造物と、従来
の鉄筋コンクリート構造物について、曲げせん断試験を
実施した。 (試験体) 試験体はいずれも図5に示すような長さ4.6メート
ル、幅0.5メートル、高さ0.8メートルのコンクリ
ート梁12である。
By performing the above construction, a semi-finished state as shown in FIG. 2 is obtained. After the formwork 1 and the steel frame 4 are connected to each other by the required number of steps to make the pier a desired height, concrete is poured between the precast member 7 and the formwork 1 and the concrete is hardened to complete. [Test Example 1] A bending-shear test was performed on the steel frame precast concrete structure of the present invention and a conventional reinforced concrete structure. (Specimen) Each specimen was a concrete beam 12 having a length of 4.6 meters, a width of 0.5 meters, and a height of 0.8 meters as shown in FIG.

【0019】試験体1は、従来の鉄筋コンクリート構造
(RC)であり、図6に示すように主鉄筋10に密着さ
せて帯鉄筋11を配置したものである。試験体2は本発
明の鉄骨プレキャストコンクリート構造(SC+PC
a)であり、図7のように帯鉄筋を鋼材(H型鋼)から
離して配置したものである。 (試験方法) 試験は両端部から夫々0.4メートルの位置に設けた支
承部から、夫々1.1メートル内側の2点を押圧した。 (試験結果) 試験体1の荷重とせん断補強ひずみの関係を図8に示
す。また試験体2の荷重とせん断補強ひずみの関係を図
9に示す。両者を比較すると鉄骨プレキャストコンクリ
ート構造は、帯鉄筋を鋼材から離して配置したにも関わ
らず、鉄筋コンクリート構造と同等のせん断補強効果を
有していることがわかる。 〔試験例2〕 本発明のコンクリート橋脚と同様の方法により製造した
コンクリート構造物について、正負交番載荷試験を実施
した。 (試験体) 図10に示すように、高さ0.75メートルのベース2
0上に外径0.9メートル、内径0.3メートル、高さ
2.6メートルの中空円筒柱21を形成した。
The test body 1 is a conventional reinforced concrete structure (RC), in which a belt reinforcing bar 11 is arranged in close contact with a main reinforcing bar 10 as shown in FIG. Specimen 2 is a steel precast concrete structure (SC + PC) of the present invention.
FIG. 7A shows a steel bar (H-shaped steel) in which a reinforcing steel strip is arranged as shown in FIG. (Test Method) In the test, two points 1.1 m inward were pressed from bearings provided at 0.4 m from both ends. (Test Results) FIG. 8 shows the relationship between the load of the test piece 1 and the shear reinforcing strain. FIG. 9 shows the relationship between the load of the test body 2 and the shear reinforcing strain. A comparison of the two shows that the steel precast concrete structure has the same shear reinforcing effect as the reinforced concrete structure, despite the arrangement of the strip reinforcing steel away from the steel material. Test Example 2 Positive and negative alternating loading tests were performed on a concrete structure manufactured by the same method as the concrete pier of the present invention. (Specimen) As shown in FIG. 10, a base 2 having a height of 0.75 meters
A hollow cylindrical column 21 having an outer diameter of 0.9 meters, an inner diameter of 0.3 meters, and a height of 2.6 meters was formed on the top of the cylinder.

【0020】図11はその内部構造を示す断面図であ
り、内部に8本のH型鋼23が設けられているととも
に、それらに接触しないように帯鉄筋25が配置されて
いる。 (試験方法) 前記試験体の上面には軸力負荷用ジャッキ30が設置さ
れ、このジャッキ30からPC鋼棒31を垂下させてそ
の下端をベース20内に埋設固定したアンカー32に接
続している。また上端のスタブ33と反力壁34の間に
はアクチュエータ35を設置し、その一端をスタブ33
に固定している。
FIG. 11 is a cross-sectional view showing the internal structure, in which eight H-section steels 23 are provided inside, and a strip rebar 25 is arranged so as not to contact them. (Test Method) An axial force loading jack 30 is provided on the upper surface of the test body, and a PC steel rod 31 is hung from the jack 30 and the lower end thereof is connected to an anchor 32 embedded and fixed in the base 20. . An actuator 35 is provided between the upper end stub 33 and the reaction wall 34, and one end of the actuator 35 is connected to the stub 33.
It is fixed to.

【0021】このような状態で、軸力負荷用ジャッキ3
0によってPC鋼棒31を引っ張ることにより試験体全
体に所定の軸力を付加しつつ、アクチュエータ35を作
動させて、このスタブ33部分に水平方向の正負加力を
繰り返して与えた。 (試験結果) 試験体1の載荷点水平変位を図12に、またせん断補強
筋ひずみをを図13にそれぞれ示す。
In such a state, the axial force loading jack 3
By applying a predetermined axial force to the entire test piece by pulling the PC steel bar 31 by 0, the actuator 35 was operated to repeatedly apply a horizontal positive / negative force to the stub 33 portion. (Test Results) FIG. 12 shows the horizontal displacement of the loading point of the test piece 1 and FIG. 13 shows the shear reinforcement strain.

【0022】上記の結果から、本発明の橋脚では帯鉄筋
がコアコンクリートに対する補強効果を十分に発揮し、
じん性の向上に寄与することが認められる。
From the above results, in the bridge pier according to the present invention, the band reinforcing bar sufficiently exerts the reinforcing effect on the core concrete,
It is recognized that it contributes to improvement in toughness.

【0023】以上のように、本発明の構造物は従来の鉄
筋コンクリート構造物に劣らない強度を有することが理
解される。またプレキャスト型枠を併用しているため大
幅な工期の短縮や安全性の確保が実現できる。
As described above, it is understood that the structure of the present invention has strength equal to that of the conventional reinforced concrete structure. In addition, since the pre-cast formwork is used together, the construction period can be significantly shortened and safety can be ensured.

【0024】[0024]

【発明の効果】本発明によれば、橋脚の築造の際、プレ
キャスト型枠の内側に帯鉄筋を設け、前記帯鉄筋の内側
に鉄骨を建て込み、前記型枠の内側にコンクリートを打
設するようにしたので、帯鉄筋や鉄骨の組み立てが極め
て容易になる。
According to the present invention, at the time of building a pier, a band reinforcing bar is provided inside the precast formwork, a steel frame is built inside the band reinforcing bar, and concrete is cast inside the formwork. As a result, the assembling of the reinforcing bar and the steel frame becomes extremely easy.

【0025】さらに、足場組みや型枠組みが不要である
ため工期を大幅に短縮することができるとともに、高所
作業が少ないため作業員の安全性が高い。しかも帯鉄筋
は型枠の内側に帯鉄筋取付具を介して固定されるもので
あるため、コンクリートかぶりや帯鉄筋の位置精度を高
めることができ橋脚の強度も改善することができる効果
がある。
Further, since no scaffolding or formwork is required, the construction period can be greatly reduced, and the work at high places is reduced, so that the safety of workers is high. Moreover, since the reinforcing bar is fixed to the inside of the form via the reinforcing bar attachment, it is possible to improve the covering accuracy of the concrete cover and the reinforcing bar and to improve the strength of the pier.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の形態を示す橋脚の断面図であ
る。
FIG. 1 is a cross-sectional view of a pier showing an embodiment of the present invention.

【図2】本発明の実施の形態を示す橋脚の施工工程の斜
視図である。
FIG. 2 is a perspective view of a pier construction process showing the embodiment of the present invention.

【図3】帯鉄筋を取り付けたプレキャスト型枠を示す概
略図である。
FIG. 3 is a schematic view showing a precast formwork to which a band reinforcing bar is attached.

【図4】帯鉄筋を取り付けたプレキャスト型枠を示す側
面図である。
FIG. 4 is a side view showing a precast formwork to which a band reinforcing bar is attached.

【図5】試験例1における試験体である梁の側面図であ
る。
FIG. 5 is a side view of a beam as a test body in Test Example 1.

【図6】試験体1の断面図である。FIG. 6 is a cross-sectional view of the test body 1.

【図7】試験体2の断面図である。FIG. 7 is a sectional view of a test body 2.

【図8】試験体1の荷重とせん断補強筋ひずみの関係を
示すグラフ図である。
FIG. 8 is a graph showing a relationship between a load of a test piece 1 and a shear reinforcing bar strain.

【図9】試験体2の荷重とせん断補強筋ひずみの関係を
示すグラフ図である。
FIG. 9 is a graph showing a relationship between a load of a test body 2 and a shear reinforcing bar strain.

【図10】試験例2における試験体と試験方法を示す図
である。
FIG. 10 is a view showing a test body and a test method in Test Example 2.

【図11】試験例2における試験体の断面図である。FIG. 11 is a cross-sectional view of a test body in Test Example 2.

【図12】試験例2における試験体の荷重と変位の関係
のグラフ図である。
FIG. 12 is a graph showing a relationship between a load and a displacement of a test body in Test Example 2.

【図13】試験例2における試験体の荷重とせん断補強
筋ひずみの関係のグラフ図である。
FIG. 13 is a graph showing a relationship between a load of a test body and a shear reinforcing bar strain in Test Example 2.

【符号の説明】[Explanation of symbols]

1・・型枠、 2・・基礎、 3・・帯鉄筋、 4・・鉄骨、 5・・コンクリート、 5a・・帯鉄筋取付具。 1. Formwork, 2. Foundation, 3. Band reinforcement, 4. Steel frame, 5. Concrete, 5a.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 田畑 稔 東京都千代田区富士見二丁目10番26号 前田建設工業株式会社内 (72)発明者 河野 一徳 東京都千代田区富士見二丁目10番26号 前田建設工業株式会社内 (72)発明者 佐藤 文則 東京都千代田区富士見二丁目10番26号 前田建設工業株式会社内 (72)発明者 長崎 利哉 東京都千代田区富士見二丁目10番26号 前田建設工業株式会社内 (72)発明者 岡 由剛 東京都千代田区内幸町二丁目2番3号 川崎製鉄株式会社内 (56)参考文献 特開 昭61−155521(JP,A) (58)調査した分野(Int.Cl.7,DB名) E04C 3/00 - 3/46 E01D 1/00 - 23/00 ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Minoru Tabata 2-10-26 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industries Co., Ltd. (72) Inventor Kazunori Kawano 2- 10-26 Fujimi, Chiyoda-ku, Tokyo Maeda Within Construction Industry Co., Ltd. (72) Inventor Fuminori Sato 2--10-26 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industry Co., Ltd. (72) Inventor Toshiya Nagasaki 2--10-26, Fujimi, Chiyoda-ku, Tokyo (72) Inventor Yugo Oka 2-3-2 Uchisaiwai-cho, Chiyoda-ku, Tokyo Kawasaki Steel Corporation (56) References JP-A-61-155521 (JP, A) (58) Fields investigated ( Int.Cl. 7 , DB name) E04C 3/00-3/46 E01D 1/00-23/00

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】予め形成した橋脚の基礎上に鉄骨を所要の
高さまで建て込む工程と、内側に帯鉄筋取付具を介して
帯鉄筋が配された枠状のプレキャスト型枠を形成する工
程と、前記鉄骨を取り囲むようにこのプレキャスト型枠
を複数積み重ねる工程と、前記プレキャスト型枠内にコ
ンクリートを打設し硬化させ、前記鉄骨、前記帯鉄筋及
びプレキャスト型枠を一体化する工程と、を有するコン
クリート橋脚の築造方法。
1. A step of laying a steel frame to a required height on a preformed pier foundation, and a step of forming a frame-shaped precast formwork on which a reinforcing steel bar is arranged via a reinforcing steel fastener inside. A step of stacking a plurality of the precast formwork so as to surround the steel frame, and a step of casting concrete in the precast formwork and hardening to integrate the steel frame, the band reinforcing bar and the precast formwork. How to build concrete piers.
【請求項2】コンクリートと接する表面に凹凸が形成さ
れている鉄骨を使用する請求項1に記載のコンクリート
橋脚の築造方法。
2. The method for constructing a concrete pier according to claim 1, wherein a steel frame having irregularities formed on a surface in contact with the concrete is used.
JP7238839A 1995-09-18 1995-09-18 How to build a concrete pier Expired - Lifetime JP3031530B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP7238839A JP3031530B2 (en) 1995-09-18 1995-09-18 How to build a concrete pier
TW85114692A TW387959B (en) 1995-09-18 1996-11-28 Construction method of concrete pier, construction method of concrete structure and precast form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7238839A JP3031530B2 (en) 1995-09-18 1995-09-18 How to build a concrete pier

Publications (2)

Publication Number Publication Date
JPH0978763A JPH0978763A (en) 1997-03-25
JP3031530B2 true JP3031530B2 (en) 2000-04-10

Family

ID=17036046

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7238839A Expired - Lifetime JP3031530B2 (en) 1995-09-18 1995-09-18 How to build a concrete pier

Country Status (1)

Country Link
JP (1) JP3031530B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104532740A (en) * 2015-01-21 2015-04-22 宁波大学 Energy-consuming rebar-attached unbonded post-tensioning prestressed concrete filled double-wall steel tube prefabricated assembly bridge pier
CN109505233A (en) * 2018-11-05 2019-03-22 安徽省交通规划设计研究总院股份有限公司 A kind of assembled steel reinforced concrete combined hollow bridge pier

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001020089A1 (en) * 1999-09-10 2001-03-22 Maeda Corporation Concrete structure and method of constructing the same
CN104328735B (en) * 2014-10-20 2016-11-09 广西交通科学研究院 Regeneration concrete Z-type pier stud
CN107268424B (en) * 2017-07-06 2019-05-03 东南大学 Can fast leveling precast assembly bridge pier structure and its construction method
CN114991172A (en) * 2022-06-20 2022-09-02 中国矿业大学 Template and steel bar integrated underwater pouring structure and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104532740A (en) * 2015-01-21 2015-04-22 宁波大学 Energy-consuming rebar-attached unbonded post-tensioning prestressed concrete filled double-wall steel tube prefabricated assembly bridge pier
CN109505233A (en) * 2018-11-05 2019-03-22 安徽省交通规划设计研究总院股份有限公司 A kind of assembled steel reinforced concrete combined hollow bridge pier

Also Published As

Publication number Publication date
JPH0978763A (en) 1997-03-25

Similar Documents

Publication Publication Date Title
KR101050956B1 (en) Rebar prefabricated column method
JP3031530B2 (en) How to build a concrete pier
JPH1030212A (en) Reinforced concrete structure and its construction method
JP4136049B2 (en) Concrete pier construction method
JP2947736B2 (en) Concrete columnar structure
JPS6145042A (en) Mold frame for casting concrete
JPH0978532A (en) Work execution method for concrete bridge pier
JP5024617B2 (en) Prestressed concrete beam and its construction method
WO2001020089A1 (en) Concrete structure and method of constructing the same
JPH083983A (en) Precast concrete product
JPH0652001B2 (en) Structural columns and frame structures
JPH0314483Y2 (en)
JP2000073448A (en) Connection method and structure for precast concrete beam and column
JP2019203331A (en) Reinforcement joint structure of reinforced concrete beam
JP7413233B2 (en) How to construct panel units and structures
CN218234361U (en) Special part reinforcing apparatus of shaped steel concrete integrated configuration
JPH07217069A (en) Construction method of reinforced concrete pole and constituting precast concrete member thereof
JPS6124735A (en) Mold frame for casting concrete
JP2643641B2 (en) Building method using PC members
JPH04357241A (en) Hollow pca column
JPH06104993B2 (en) Construction method of steel pipe precast concrete columns
JPH0197744A (en) Shearing reinforcing structure of shear head section in flat plate building
JPH09235912A (en) Column-shaped concrete structure and its construction
JP2001107320A (en) Construction of concrete structure and form member
JPH0835260A (en) Tower-form structure and building method thereof

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090210

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090210

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100210

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100210

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110210

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120210

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130210

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140210

Year of fee payment: 14

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313532

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

EXPY Cancellation because of completion of term