JP3024076U - Concrete with steel rebar - Google Patents

Concrete with steel rebar

Info

Publication number
JP3024076U
JP3024076U JP1995013123U JP1312395U JP3024076U JP 3024076 U JP3024076 U JP 3024076U JP 1995013123 U JP1995013123 U JP 1995013123U JP 1312395 U JP1312395 U JP 1312395U JP 3024076 U JP3024076 U JP 3024076U
Authority
JP
Japan
Prior art keywords
steel
concrete
reinforced concrete
earthquake
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1995013123U
Other languages
Japanese (ja)
Inventor
益美 山田
Original Assignee
益美 山田
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 益美 山田 filed Critical 益美 山田
Priority to JP1995013123U priority Critical patent/JP3024076U/en
Application granted granted Critical
Publication of JP3024076U publication Critical patent/JP3024076U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

(57)【要約】 【課題】鉄筋コンクリート製のビルとか橋脚が地震によ
り倒壊したり又鉄筋コンクリート製パイルとかアースド
リル工法で地下に埋設する鉄筋コンクリート製の円柱
が、地震による地盤のゆるみにより折れ曲がったりする
問題。 【解決手段】本考案のH鋼使用の鉄骨鉄筋入りコンクリ
ート柱のビルとか鉄骨鉄筋入りコンクリートの橋脚はH
鋼の弾力により地震による倒壊を防ぐ来が出来、そして
H鋼使用の鉄骨鉄筋入りコンクリートパイルとアースド
リル工法によるH鋼使用の鉄骨鉄筋入りコンクリートの
円柱がH鋼の弾力により地震による地震のゆるみによる
折れ曲がりを防ぐ事が出来る。
(57) [Abstract] [Problem] The problem that a building or bridge pier made of reinforced concrete collapses due to an earthquake, or a reinforced concrete column or a reinforced concrete column buried underground by the earth drill method bends due to the looseness of the ground due to the earthquake. . SOLUTION: The building of a concrete column containing steel reinforced steel using the H steel of the present invention or a bridge pier of steel reinforced concrete is H
Due to the elasticity of steel, it is possible to prevent collapse due to an earthquake, and the concrete pile with steel-framed steel reinforcements using H-steel and the cylinder of steel-reinforced concrete using H-steel by the earth drill method are caused by the looseness of the earthquake caused by the earthquake due to the elasticity of H-steel. It is possible to prevent bending.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】 〔産業上の利用分野〕 本考案は地震或いは地震による地盤のゆるみにより鉄筋コンクリートビルとか鉄 筋コンクリートの橋脚が倒壊による危険防止対策に関するものである。[Field of Industrial Application] [0001] The present invention relates to a risk prevention measure against collapse of a reinforced concrete building or a reinforced concrete bridge pier due to an earthquake or loosening of the ground due to an earthquake.

【0002】 〔従来の技術〕 従来からの方法により鉄筋コンクリートパイルを建築現場のビルとか橋脚の柱部 下部周辺に専用機で適数本岩盤まで打ち込み基盤を作りそして鉄筋(異形棒鋼) を格子状に組み(鉄束線で鉄筋を縛り)そして組み付けた鉄筋の外回りをパネル とボルトとナットを使い鉄筋との適当な巾を取り枠を作り枠の中へ(現場で生コ ン車からコンクリートポンプ車の生コンクリート受け入れ口へ生コンクリートを 注ぎ、ポンプ車の(操作で)パイプ出口先端へ送り出されて来る生コンクリート を作業員によりバイブレーター等を使い隙間の無い様に打ち込み仕上げ鉄筋コン クリートの橋とかビルを建てたコンクリートの中は補強のための鉄筋入りだけで あった。そして鉄筋コンクリートパイルとかアースドリル工法により地下へ埋設 する鉄筋コンクリートの円柱も同じくコンクリートの中に埋め込まれている補強 のための鉄筋入りだけであった。[Prior Art] Using a conventional method, a reinforced concrete pile is driven up to a suitable number of rocks with a dedicated machine around the lower part of the pillar of a building or a bridge pier to form a foundation, and reinforcing bars (deformed steel bars) are formed into a grid pattern. Assemble (tie the reinforcing bar with a steel bundle wire) and the outer circumference of the assembled reinforcing bar by using a panel, bolts and nuts to make an appropriate width with the reinforcing bar and make a frame (from the raw concrete car to the concrete pump car at the site) The raw concrete is poured into the fresh concrete receiving port of the pump car, and the raw concrete that is sent to the pipe outlet end of the pump car (by operation) is driven by a worker using a vibrator etc. so that there is no gap in the finish Concrete reinforced concrete bridge or building The concrete in which the building was built only had reinforcing bars for reinforcement, and the reinforced concrete pile or earth drill method was used. The reinforced concrete cylinders that are buried more underground are also only filled with reinforcing bars that are embedded in the concrete.

【0003】 〔考案が解決しようとする課題〕 従来の技術で述べた様に鉄筋入りコンクリート製のビルとか橋脚が地震により倒 壊したり又鉄筋コンクリート製パイルが地震によるゆるみにより折れ曲がったり するのを防止するコンクリート製品を提供しようとするものである。[Problems to be Solved by the Invention] As described in the prior art, it prevents the building or pier made of reinforced concrete from collapsing due to an earthquake and the reinforced concrete pile from bending due to looseness due to an earthquake. It is intended to provide concrete products.

【0004】 〔課題を解決するための手段〕 本考案は上記問題を解決するために鉄筋コンクリート製のビルの柱とか橋脚とか コンクリートパイルとかアースドリル工法により地下へ埋設するコンクリートの 円柱の中心部にH鋼の支柱を組み込み鉄骨鉄筋入りコンクリート製とする。[Means for Solving the Problems] In order to solve the above-mentioned problems, the present invention has a structure in which a column of a building made of reinforced concrete, a bridge pier, a concrete pile, or a concrete column to be buried underground by an earth drill method Steel struts will be incorporated and made of concrete with steel reinforcement.

【0005】 〔考案の実施の形態〕 本考案は前述の手段講じたので鉄骨鉄筋入りコンクリート製のビルとか橋脚がH 鋼の弾力により地震による倒壊を防ぎ又鉄骨鉄筋入りコンクリート製のパイルと 鉄骨鉄筋入りコンクリートの円柱が地震による地震のゆるみによる折れ曲がりを H鋼の弾力により防ぐ事が出来る。[Embodiment of the Invention] Since the present invention has taken the above-mentioned means, a building or a pier made of concrete with steel rebar is prevented from collapsing due to an earthquake due to the elasticity of H steel, and a concrete pile with steel rebar and steel rebar The bending of the filled concrete cylinder due to the earthquake can be prevented by the elasticity of the H steel.

【0006】 〔実施例〕 実施例について図面を参照して説明する。 図1においてコンクリートパイル10が岩盤に到達するまでパイル打ち専用機で 適数本打ち込んでありパイルの回りを基盤下部の枠石を敷く所までユンボで堀り 下げパイル上部適位置を削りパイル内の鉄筋を70cm位残す、パイル内のH鋼 は基盤より8cm位上部位置で酸素溶接機の切断バーナーで切り取る。(この場 合本考案のH鋼入り鉄筋コンクリートパイル使用にしたが従来通りの鉄筋コンク リートパイル使用としても良い。)そして砕石を敷き詰めランマーで固めその上 部へ十字型に鉄筋コンクリートの基盤を設けてその上部へH鋼の受体2になる適 当な長さのH鋼(あ)の両端を鉄板Cで溶接をするそして同じ長さになるH鋼( い、う)の両端に鉄板Cを溶接するそしてH鋼(あ)の中央両サイドにH鋼(い 、う)を十字型に溶接する、そしてH鋼(い、う)の鉄板Cの中心部に縦に内側 へ鉄板Bを補強のため溶接するそしてH鋼の受体2Aがパイル上部位置に来る様 にH鋼の受体2と受体2の間に補強を兼ね溶接を(鉄板Cを受体2Aの両端に溶 接してあり)4本行う、そして鉄板Cの内側と受体2の間に鉄板Bを縦に補強の ため8個所溶接する、そして受体下部とコンクリートパイルの中のH鋼11の上 部を全部溶接固定する(図3参照)Embodiments Embodiments will be described with reference to the drawings. In Fig. 1, a concrete pile 10 is driven by a dedicated pile driving machine until the concrete pile 10 reaches the bedrock, and it is dug around the pile with a yunbo to the place where the frame stone under the base is laid and the appropriate position above the pile is scraped off The H steel in the pile, which leaves about 70 cm of rebar, is cut off by a cutting burner of an oxygen welding machine at a position 8 cm above the base. (In this case, the reinforced concrete pile containing H steel of the present invention was used, but the conventional reinforced concrete pile may be used.) Then, crushed stones are spread and fixed with a rammer, and a cruciform reinforced concrete foundation is provided on the top. Weld both ends of H steel (A) of appropriate length to become the H steel receiver 2 with iron plate C and weld iron plate C to both ends of H steel (I, U) of the same length. Welding H steel (I, U) in a cross shape on both sides of the center of H steel (A), and reinforcing steel plate B vertically inward at the center of iron plate C of H steel (I, U). Welding is performed for welding, and welds are also provided between the H steel receivers 2 and 2 so that the H steel receiver 2A is located at the upper position of the pile (the steel plate C is welded to both ends of the receiver 2A. ) 4 pieces are performed, and for vertically reinforcing the iron plate B between the inside of the iron plate C and the receiving body 2. Weld at 8 points, and fix the lower part of the receiver and the upper part of H steel 11 in the concrete pile by welding (see Fig. 3).

【0007】 図2においてH鋼の受体2の中心部の上部にH鋼の支柱3を道路に対して図2に 示す様に(レッカー車を使い)据え付けそして垂直に立てH鋼の支柱3下部とH 鋼の受体2上部の当接個所を溶接する。そして図3と図4に示す様にH鋼の支柱 3の下方とH鋼の受体2上部の適位置にあらかじめ用意してある4本のH鋼の筋 交い4の両端の(H鋼の支柱3の側面は両サイド鉄板Aの溶接を行う)溶接を行 うそして鉄板AとH鋼の支柱3の間の中心に鉄板Bを縦に鉄板Dを補強のため両 サイド溶接を行う、そして橋脚上部もH鋼の支柱3の上端とH鋼の梁5の下部中 心部とをT字型に(レッカー車を使い)溶接固定する、そしてあらかじめ用意し てあるH鋼の筋交い6の両端をH鋼の支柱3上部とH鋼の梁5の中央寄り下部適 位置に左右1本づつ溶接固定する。そしてH鋼の梁5の両端は補強のため鉄板C を溶接する。In FIG. 2, an H steel support column 3 is installed above the center of the H steel support 2 with respect to the road as shown in FIG. Weld the abutting points on the upper part of the H steel receiver 2. Then, as shown in FIGS. 3 and 4, the four H steel braces 4 (H steel at both ends of the H steel braces 4 prepared in advance at appropriate positions below the H steel column 3 and above the H steel receiver 2 are provided. Weld both side iron plates A to the side of the column 3) Weld and perform both side welding to reinforce the iron plate B vertically and the iron plate D at the center between the columns 3 of the iron plates A and H steel, The upper part of the H-steel column 3 and the lower center part of the H-steel beam 5 are also welded and fixed in a T-shape (using a tow truck) to the upper part of the pier, and both ends of the H-steel brace 6 prepared in advance. Are welded to the upper portions of the H steel columns 3 and the lower portions of the H steel beams 5 near the center, one by one on the left and right. Then, both ends of the H steel beam 5 are welded with iron plates C 1 for reinforcement.

【0008】 図5においてH鋼の(支柱3、受体2、筋交い4、6梁5)回りを鉄筋7(異形 棒鋼)で組み付け鉄束線で鉄筋7の交差個所を縛り(コンクリートパイルの鉄筋 とH鋼の受体2周辺の鉄筋は溶接固定を行う)そして外回りをパネルにより外枠 を設けボルトとナットでパネルを締め付け固定しその中へ現場で生コン車からコ ンクリートポンプ車の生コンクリート受け入れ口へ生コンクリートを注ぎ入れポ ンプ車の(操作で)パイプ出口先端へ送り出されて来る生コンクリートを現場作 業員によりバイブレーターを使い生コンクリートの中へ気泡が入らぬ様に作業を 行い打ち込み仕上げる。In FIG. 5, the area around the H steel (the pillar 3, the receiving member 2, the braces 4, and the 6 beams 5) is assembled with the reinforcing bar 7 (deformed bar steel), and the crossing point of the reinforcing bar 7 is bound with the iron bundle wire (the reinforcing bar of the concrete pile). And the steel bars around the H steel receiver 2 are welded and fixed.) Then, an outer frame is provided by a panel on the outer circumference, and the panel is tightened and fixed with bolts and nuts. Pouring ready-mixed concrete into the mouth and finishing the concrete by sending it to the tip of the pipe exit of the pump car (by operation) using a vibrator to prevent bubbles from entering the ready-mixed concrete. .

【0009】 図6においてはパネルを外し基礎部の埋め戻しを行った完成図である。FIG. 6 is a completed view in which the panel is removed and the base portion is backfilled.

【0010】 図7と図8はビルの基礎と柱下部であり図1と図3と図4に示す方法と同じ方法 で工事を進める。FIG. 7 and FIG. 8 show the foundation of the building and the lower part of the pillar, and the construction will proceed in the same way as the method shown in FIGS. 1, 3 and 4.

【0011】 図9と図10においてはH鋼のそれぞれの階になるH鋼の桁30とH鋼の梁29 をボルトとナット、座金により締め付け固定する、そして建築物の天井とか壁に なる部分も(H鋼或いはチヤンネル又はアングルの)筋交い22を溶接或いはボ ルトとナット、座金により締め付け固定する。9 and 10, the H steel girder 30 and the H steel beam 29 on each floor of the H steel are fastened by bolts, nuts and washers and fixed to the ceiling or wall of the building. Brace 22 (of H steel or channel or angle) is also welded or clamped and fixed by bolts, nuts and washers.

【0012】 図11においては前述のH鋼の骨組みの外廻りを鉄筋17(異形棒鋼)で格子状 に組み付け交差個所を鉄束線で縛る、そして外廻りをパネルにより外枠を設けボ ルトとナットでパネルを締め付け固定しその中へ現場で生コン車からコンクリー トポンプ車の生コンクリート受け入れ口へ生コンクリートを注ぎポンプ車の(操 作で)パイプ出口先端へ送り出されて来るコンクリートを現場作業員によりバイ ブレーターを使い生コンクリートの中へ気泡が入らぬ様に作業を行い打ち込み仕 上げる。(基礎部から順番に1階づつ鉄筋を組み生コンクリート打ち作業を進め る。)In FIG. 11, the outer periphery of the above-mentioned H steel frame is assembled in a lattice shape with reinforcing bars 17 (deformed steel bars), the intersections are bound with iron bundle wires, and the outer periphery is provided with a panel to form a bolt. A panel worker tightens and fixes the panel with nuts, and then pouring fresh concrete from the fresh concrete car to the fresh concrete receiving port of the concrete pump car at the site, and the concrete sent out to the end of the pipe exit of the pump car (by operation) is Use a vibrator to perform work so that air bubbles do not enter into the ready-mixed concrete, and finish. (Reinforcing bars are assembled on the first floor in order from the foundation to proceed the concrete pouring work.)

【0013】 図12においてはパネルを外し基礎部の埋め戻し作業を行ったビルのコンクリー ト仕上げ工事が終わり完成としたビル9である。In FIG. 12, the building 9 is completed after the concrete finishing work of the building in which the panel has been removed and the foundation part has been backfilled.

【0014】 図13に示すH鋼18は鉄骨鉄筋入りコンクリートパイルの中心部の支柱材料で ある。図14に示す様にH鋼18の廻りを鉄筋31で円柱形に溶接仕上げを行い 、図15に示すコンクリートパイル製造用の半分に縦に割れる鉄製製造枠23( 円柱形)の中へ図14に示すH鋼と鉄筋の組み合わせとした骨組みを入れる、そ して製造枠23の双方を合わせ適間隔に付いているボルト用の穴にボルト24を 通しナット25により締め付け固定を行うそして生コンクリートを作業員により 鉄製パイプ枠23の中へ送り込み仕上げ図16に示す鉄骨鉄筋入りコンクリート パイル10を完成させる。The H steel 18 shown in FIG. 13 is a pillar material at the center of the concrete pile with steel reinforcement. As shown in FIG. 14, the H steel 18 is welded into a cylindrical shape around the H steel 18 with a reinforcing bar 31, and is vertically divided into halves for manufacturing the concrete pile shown in FIG. 15 into the iron manufacturing frame 23 (cylindrical shape). Insert the skeleton that is a combination of H steel and rebar shown in Fig. 2, and put both production frames 23 together, and insert bolts 24 through the holes for bolts at appropriate intervals, tighten them with nuts 25, and fix the concrete. It is sent by an operator into the steel pipe frame 23 and finished, and the concrete pile 10 with the steel frame rebar shown in FIG. 16 is completed.

【0015】 図17と図18においては本考案の鉄骨鉄筋入りコンクリートの支柱28をアー スドリル工法で仕上げる方法を順に説明すると長さ3m位で直径35cm位の鉄 のパイプを垂直に立てパイプ14の中へドリル状の回転軸を入れ回転軸にアース ドリル専用車のエンジンによる回転を伝え回転させ回転軸の先端のドリルの刃先 上部の長さ1、5m位のスクリュー部分にパイプ14の中で土を乗せ軸を引き上 げ土を繰り返しパイプ14の外へ搬出し地下深く堀り下げながらパイプ26と回 転軸の継ぎ(ボルトとナットで連結部を締め付け)足しを行い岩盤27までパイ プ26が到達したら回転軸の刃先付き回転軸をパイプ26から引き上げパイプ2 6の中へ(レッカー車を使い)円柱状に組み付けた長さ3m位の鉄筋を挿入する そしてこの鉄筋20の中心部に3m位の適当巾のH鋼を(レッカー車を使い)挿 入し岩盤に到達するまで継ぎ足し溶接を行い設置を終えたら現場で生コン車から コンクリートポンプ車の生コン受け入れ口へ生コンクリートを注ぎ込み、そして ポンプ車の(操作で)パイプ出口先端へ送り出されて来る生コンクリートを現場 作業員によりパイプ26の中へ流し込みバイブレーターを使い生コンクリートの 中に気泡が入らぬ様作業を行い、パイプ26を(レッカー車を使い)引き上げコ ンクリート仕上げを行い図19に示す鉄骨鉄筋入りコンクリートの円柱28を仕 上げる。Referring to FIG. 17 and FIG. 18, the method of finishing the steel-frame-reinforced concrete stanchions 28 of the present invention by the earth drill method will be described in order. An iron pipe having a length of about 3 m and a diameter of about 35 cm is set up vertically. Insert a drill-like rotary shaft into the ground and rotate the ground by transmitting the rotation of the engine of the dedicated drill car to the engine and rotate it to the tip of the rotary shaft. The pipe 26 is lifted up, the soil is repeatedly carried out to the outside of the pipe 14, and the pipe 26 and the rotating shaft are spliced together (tightening the connection part with bolts and nuts) while deeply excavating underground. When is reached, the rotary shaft with the blade tip of the rotary shaft is pulled up from the pipe 26 and inserted into the pipe 26 (using a wrecker) and the cylindrical reinforcing bar of about 3 m in length is inserted. Then, insert H steel of about 3 m in width (using a tow truck) into the center of the rebar 20, add and weld until reaching the bedrock, and after installation is completed, from the ready-mixed concrete truck to the ready-mixed concrete truck concrete concrete truck. The raw concrete is poured into the pipe 26, and the raw concrete that has been delivered to the pipe outlet tip of the pump car (by operation) is poured into the pipe 26 by the site worker so that air bubbles do not enter the raw concrete using the vibrator. Then, the pipe 26 is pulled up (using a tow truck) and concrete finish is carried out to finish the concrete cylinder 28 with steel-framed reinforcing bars shown in FIG.

【0016】 〔考案の効果〕 本考案は上述のとおり構成されているので、次に記載する効果を奏する。[Effects of the Invention] Since the present invention is configured as described above, it has the following effects.

【0017】 請求項1のH鋼使用の鉄骨鉄筋入りコンクリート柱のビルと鉄骨鉄筋入りコンク リートの橋脚においてはビルのコンクリート柱と橋脚に埋め込まれているH鋼の 弾力により地震による倒壊を防ぐ利点がある。In the case of the building of the steel reinforced concrete columns using the H steel and the pier of the steel reinforced concrete columns of claim 1, the advantage of preventing the collapse due to an earthquake due to the elasticity of the H steel embedded in the concrete columns of the building and the piers There is.

【0018】 請求項2のH鋼使用の鉄骨鉄筋入りコンクリートパイルを地下の岩盤まで打ち込 み使用した場合とアースドリル工法によるH鋼使用の鉄骨鉄筋入りコンクリート の円柱を地下の岩盤まで埋設した場合においてはコンクリートパイルとコンクリ ート柱に埋め込まれているH鋼の弾力により地震による地盤のゆるみによる折れ 曲がりを防ぐ利点がある。When the concrete pile containing steel-framed reinforced steel of claim 2 is driven into underground rock and used, and when the column of steel-reinforced concrete containing H-steel using earth drill method is buried up to underground rock In, the elasticity of H steel embedded in concrete piles and concrete columns has the advantage of preventing bending due to loosening of the ground due to an earthquake.

【図面の簡単な説明】[Brief description of drawings]

【図1】橋脚の基盤1と受体2、2aの平面図である。FIG. 1 is a plan view of a pier base 1 and receivers 2 and 2a.

【図2】H鋼の橋脚作業状態を示す断面正面図である。FIG. 2 is a sectional front view showing a working state of H steel piers.

【図3】橋脚基礎部を見やすくした正面図である。FIG. 3 is a front view in which a pier foundation portion is easily seen.

【図4】図3の断面平面図である。4 is a cross-sectional plan view of FIG.

【図5】図2の鉄骨の回りを鉄筋7で組み付けた正面図
である。
FIG. 5 is a front view in which the periphery of the steel frame in FIG. 2 is assembled with a reinforcing bar 7.

【図6】橋脚完成の正面図である。FIG. 6 is a front view of the completed pier.

【図7】ビルの基盤12と受体13、13Aの平面図で
ある。
FIG. 7 is a plan view of a building base 12 and receiving bodies 13 and 13A.

【図8】ビルの柱の基礎部分を見やすくした正面図であ
る。
FIG. 8 is a front view in which the basic portion of the pillar of the building is easily seen.

【図9】ビル工事の実施状態を示す正面図である。FIG. 9 is a front view showing an implementation state of building construction.

【図10】ビル工事の2階部分の断面斜視図である。FIG. 10 is a cross-sectional perspective view of the second floor portion of the building construction.

【図11】ビル工事の実施状態を示す正面図である。FIG. 11 is a front view showing an implementation state of building construction.

【図12】ビル完成を示す正面図である。FIG. 12 is a front view showing the completion of the building.

【図13】本考案に使用するH鋼の側面図である。FIG. 13 is a side view of H steel used in the present invention.

【図14】本考案に使用するH鋼18と鉄筋31の側面
図である。
FIG. 14 is a side view of the H steel 18 and the reinforcing bar 31 used in the present invention.

【図15】パイル製造過程の平面図である。FIG. 15 is a plan view of the pile manufacturing process.

【図16】鉄骨鉄筋入りパイル完成側面図である。FIG. 16 is a side view of the completed pile with steel rebar.

【図17】アースドリル工法実施状態の断面側面図であ
る。
FIG. 17 is a cross-sectional side view showing a state where the earth drilling method is carried out.

【図18】図17の平面図である。FIG. 18 is a plan view of FIG.

【図19】鉄骨鉄筋入りコンクリートの円柱28の完成
を見やすくした図である。
FIG. 19 is a view for making it easier to see the completion of the steel cylinder-reinforced concrete cylinder 28.

【符号の説明】[Explanation of symbols]

1 鉄筋コンクリートの基盤 2 H鋼の受体 2AH鋼の受体 3 H鋼の支柱 4 H鋼の筋交い 5 H鋼の梁 6 H鋼の筋交い 7 鉄筋(異形棒鋼) 8 鉄骨鉄筋入りコンクリートの橋脚 9 鉄骨鉄筋入りコンクリート製ビル 10 鉄骨鉄筋入りコンクリートパイル 11 H鋼 12 鉄筋コンクリートの基盤 13 H鋼の受体 13AH鋼の受体 14 H鋼の支柱 15 H鋼の筋交い 16 H鋼の筋交い 17 鉄筋(異形棒鋼) 18 H鋼 19 H鋼 20 鉄筋(異形棒鋼) 21 ボルト用鉄板 22 H鋼又はチヤンネル又はアングルの筋交い 23 パイル製造枠 24 ボルト 25 ナット 26 アースドリル用鉄製パイプ 27 岩盤 28 鉄骨鉄筋入りコンクリートの円柱 29 H鋼の梁 30 H鋼の桁 31 パイル用鉄筋 A 補強鉄板 B 補強鉄板 C 補強鉄板 D 補強鉄板 E 砕石 F 補強鉄板 G 補強鉄板 H 補強鉄板 K 補強鉄板 あ H鋼の受体 い H鋼の受体 う H鋼の受体 1 Reinforced concrete base 2 H steel receiver 2 AH steel receiver 3 H steel support 4 H steel braces 5 H steel beams 6 H steel braces 7 Reinforcing bars (deformed bars) 8 Steel reinforced concrete bridge piers 9 Steel frames Reinforced concrete building 10 Reinforced concrete pile 11 H steel 12 Reinforced concrete base 13 H steel receiver 13 AH steel receiver 14 H steel column 15 H steel braces 16 H steel braces 17 Rebar (deformed bar) 18 H steel 19 H steel 20 Rebar (deformed bar steel) 21 Steel plate for bolts 22 H Steel or channel or angle braces 23 Pile manufacturing frame 24 Bolts 25 Nuts 26 Iron pipes for earth drills 27 Bedrock 28 Concrete columns with steel reinforced bars 29 H Steel beam 30 H Steel girder 31 Pile rebar A Reinforced iron plate B Reinforced iron plate C Reinforced iron plate D Of strong iron plate E crushed stone F reinforcing iron plate G reinforcing iron plate H reinforcement iron plate K receiving body of reinforcing iron plate Oh H steel gastric H steel receptacle cormorant H steel of the receiving body

───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.6 識別記号 庁内整理番号 FI 技術表示箇所 E04H 9/02 301 ─────────────────────────────────────────────────── ─── Continuation of the front page (51) Int.Cl. 6 Identification code Internal reference number FI technical display location E04H 9/02 301

Claims (2)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】従来からある鉄筋コンクリート製の橋脚と
か鉄筋コンクリート製ビルの柱部に関して本考案の基礎
部にH鋼の受体2を十字型に溶接固定を行い、十字型の
H鋼の中心上部にH鋼の支柱3を1本立て当接個所の溶
接固定を行い、H鋼の筋交い4をH鋼の受体とH鋼の支
柱下部適位置へ4本溶接固定を行う、そして全体のH鋼
の回りを鉄筋7で組み付け、パネルとボルトとナットで
枠を作りコンクリート打ち作業を経て仕上げる本考案の
鉄骨鉄筋入りコンクリート柱と鉄骨鉄筋入りコンクリー
トの橋脚。
1. Regarding a conventional reinforced concrete bridge pier or a pillar portion of a reinforced concrete building, an H steel receiver 2 is welded and fixed to the foundation of the present invention in a cross shape, and is attached to the upper center of the cross H steel. One H steel strut 3 is welded and fixed at the abutting point, and four H steel braces 4 are welded and fixed to the H steel receiver and the appropriate lower position of the H steel strut, and the entire H steel strut is fixed. The surroundings are assembled with rebar 7, the frame is made up of panels, bolts and nuts, and the concrete pier work is completed.
【請求項2】従来からある鉄筋コンクリートパイルとか
アースドリル工法で工事を進め地下に埋設する鉄筋のコ
ンクリート柱の中心部に適当巾のH鋼を端から端まで取
り入れた本考案の鉄骨鉄筋入りコンクリートパイルと鉄
骨鉄筋入りコンクリートの円柱。
2. A steel-reinforced concrete pile of the present invention in which H steel of an appropriate width is incorporated from end to end at the center of a concrete column of reinforced concrete to be buried underground by proceeding with conventional reinforced concrete pile or earth drill method. And concrete columns with steel rebar.
JP1995013123U 1995-10-04 1995-10-04 Concrete with steel rebar Expired - Lifetime JP3024076U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1995013123U JP3024076U (en) 1995-10-04 1995-10-04 Concrete with steel rebar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1995013123U JP3024076U (en) 1995-10-04 1995-10-04 Concrete with steel rebar

Publications (1)

Publication Number Publication Date
JP3024076U true JP3024076U (en) 1996-05-17

Family

ID=43159325

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1995013123U Expired - Lifetime JP3024076U (en) 1995-10-04 1995-10-04 Concrete with steel rebar

Country Status (1)

Country Link
JP (1) JP3024076U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011032680A (en) * 2009-07-30 2011-02-17 Ohbayashi Corp Base for erecting steel pipe, and steel pipe erection structure using the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011032680A (en) * 2009-07-30 2011-02-17 Ohbayashi Corp Base for erecting steel pipe, and steel pipe erection structure using the same

Similar Documents

Publication Publication Date Title
KR101187369B1 (en) Cip use of underground motorways construction work method
JP3024076U (en) Concrete with steel rebar
KR200370107Y1 (en) Forms for edge girder construction
JP3486602B2 (en) Pier foundation method and pier foundation structure
JPH09296459A (en) Steel encased reinforced concrete
CN111648400B (en) Construction method for civil air defense engineering to meet thick-layer water-bearing sand layer through reverse method
CN104878763B (en) Main building basement supporting construction with annex
KR100553979B1 (en) Construction establishment method and the structure for underground tunnel formation
KR100351135B1 (en) Method of constructing arch ring of steel framed reinforced concrete arch bridge
JP3047415U (en) Steel reinforced concrete
JPS63280153A (en) Underground inverted lining method
JP3133598B2 (en) Construction method of small and medium-sized building with basement floor
JP4399062B2 (en) Construction method of viaduct underground beam
JPS61102911A (en) Steel cell
KR102392517B1 (en) Top-down method using by double beam system
JP4332651B2 (en) Foundation reinforcement device and foundation construction method
JPH07103583B2 (en) Construction method for large span underground structure
CN212641741U (en) Ring beam structure for connecting pile-wrapped concrete column and reinforced concrete floor
JP3039665U (en) Steel reinforced concrete
JPH04366229A (en) Temporary corresponding standard used for method of reverse driving construction
JPH04315620A (en) Foundation structure for steel-framed building
JPH0718675A (en) Sc pile and executing method thereof
JPS6011972Y2 (en) Brake cast concrete pile cap for steel pipe piles
JP3036881U (en) Garage
JPS6172126A (en) Method of building protection wall body