JP2995430B2 - Drilling equipment for steel pipe pile with excavator for steel pipe pile and construction method of steel pipe pile - Google Patents

Drilling equipment for steel pipe pile with excavator for steel pipe pile and construction method of steel pipe pile

Info

Publication number
JP2995430B2
JP2995430B2 JP3293450A JP29345091A JP2995430B2 JP 2995430 B2 JP2995430 B2 JP 2995430B2 JP 3293450 A JP3293450 A JP 3293450A JP 29345091 A JP29345091 A JP 29345091A JP 2995430 B2 JP2995430 B2 JP 2995430B2
Authority
JP
Japan
Prior art keywords
steel pipe
excavator
excavation
frame
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP3293450A
Other languages
Japanese (ja)
Other versions
JPH05306518A (en
Inventor
広志 風間
秀武 石崎
洋之 堀田
健一 中川
裕之 久保
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP3293450A priority Critical patent/JP2995430B2/en
Publication of JPH05306518A publication Critical patent/JPH05306518A/en
Application granted granted Critical
Publication of JP2995430B2 publication Critical patent/JP2995430B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、大口径(2m以上)
の鋼管杭を大深度まで設置する際に使用される鋼管杭用
掘削機と該掘削機を備えた掘削装置およびこの装置を使
用して鋼管杭を施工する鋼管杭の施工方法に係り、特
に、ハンマー打設や振動打設を行うことなく、都市部で
の施工に適したものに関する。
The present invention relates to a large-diameter (2 m or more)
The present invention relates to a steel pipe pile excavator used when installing a steel pipe pile to a large depth, a drilling device equipped with the excavator, and a method of constructing a steel pipe pile using the device, and in particular, The present invention relates to a construction suitable for construction in an urban area without hammering or vibration placing.

【0002】[0002]

【従来の技術】周知のように、鋼管杭は、大きな水平抵
抗力が得られるため、桟橋、ドルフィンなどの港湾構造
物や橋台、橋脚などの水平力が作用する基礎に広く利用
されており、また、杭長の調節が容易に行える点、杭頭
部の加工が容易であるため、上部構造物と容易に結合で
きる点、コンクリート杭などに比べ軽量であるため、運
搬・取り扱いが容易である点等から、杭としての使用頻
度が益々高まりつつある。
2. Description of the Related Art As is well known, steel pipe piles are widely used for foundations on which horizontal forces act such as port structures such as piers and dolphins, and abutments and piers because they provide a large horizontal resistance. Also, the pile length can be easily adjusted, the pile head can be easily processed, it can be easily connected to the upper structure, and it is lighter than concrete piles, so it is easy to transport and handle. From the point of view, the frequency of use as a pile is increasing more and more.

【0003】このような鋼管杭を地中に沈設する施工法
として、従来より、ハンマー打設・または振動による
打設による施工法、鋼管の内部を掘削して鋼管杭を沈
設する施工法等が知られている。
[0003] As a construction method of sinking such a steel pipe pile into the ground, there have conventionally been a construction method of hammering or shaking with a hammer, and a construction method of excavating the inside of a steel pipe and sinking the steel pipe pile. Are known.

【0004】[0004]

【発明が解決しようとする課題】ところで、上記従来の
鋼管杭の施工方法においては以下のような、解決すべき
課題がある。すなわち、上記の施工法においては、 (1)沈設すべき鋼管の口径が大きくなれば鋼管杭を設
置するための機械が大型となるとともに、振動・騒音も
益々大きくなり、都市部での施工が殆ど不可能になる。
また、大口径(2m以上)の鋼管杭をハンマー打設、振
動打設によって設置する機械は現在のところ未だ開発さ
れていない。 (2)施工深度が深くなればなるほど、また鋼管の口径
が大きくなればなるほど鋼管の側面の抵抗が大きくなっ
て、ハンマー打設、振動打設による鋼管杭の沈設が困難
になる。
However, the above-mentioned conventional method for constructing a steel pipe pile has the following problems to be solved. In other words, in the above-mentioned construction method, (1) If the diameter of the steel pipe to be laid is large, the machine for installing the steel pipe pile becomes large, and the vibration and noise also increase. Almost impossible.
Further, a machine for setting a large-diameter (2 m or more) steel pipe pile by hammering or vibration driving has not yet been developed. (2) The deeper the construction depth and the larger the diameter of the steel pipe, the greater the resistance of the side surface of the steel pipe, making it difficult to settle the steel pipe pile by hammering or vibration.

【0005】また、上記の施工方法においては、上記
(1)および(2)に示す課題の他に、以下のような課
題もある。 (3)施工深度が深くなれば、鋼管を支えるための櫓が
高くなり、転倒などの危険が大きくなる。 (4)鋼管の内径以上に掘削することが不可能なため、
硬い土丹層などでは外部地山に抵抗が大きく、杭の沈設
が不可能となる。
[0005] In addition, the above-described construction method has the following problems in addition to the problems described in (1) and (2) above. (3) The deeper the construction depth, the higher the tower for supporting the steel pipe, and the greater the risk of falling. (4) Because it is impossible to excavate beyond the inner diameter of the steel pipe,
In the case of a hard earthen layer, the resistance to the ground outside is large, and the pile cannot be laid down.

【0006】この発明は上記事情に鑑みてなされたもの
で、周辺環境に騒音・振動等の悪影響を与えることな
く、大口径の鋼管を大深度まで沈設することができる鋼
管杭用掘削機を備えた鋼管杭用掘削装置および鋼管杭の
施工方法を提供することを目的としている。
[0006] The invention has been made in view of the above circumstances, without adversely affecting such noise and vibration in the surrounding environment, comprising a steel pipe piles for an excavator capable of sinking a steel pipe having a large diameter and large depth It is an object of the present invention to provide a drilling device for a steel pipe pile and a method for constructing a steel pipe pile.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するため
に、この発明の請求項1の鋼管杭用掘削装置は、鋼管杭
用掘削機と、該掘削機を懸吊支持する懸吊支持部材と、
該懸吊支持部材を支持して昇降させるとともに、鋼管を
下方に押圧する上部支持機構とを備えてなり、上記鋼管
杭用掘削機は、鋼管の内部に挿入可能な大きさに構成さ
れ、長尺な懸吊支持部材を介して上方より懸吊支持され
るフレームと、該フレームに支持された掘削部とを有
上記掘削部を、棒状をなし上記フレームに基端部が
首振り自在に支持された掘削アームと、この掘削アーム
の下端部に設けられた掘削ヘッドとから構成し、さら
に、上記フレームに、上記掘削アームを首振り揺動させ
る揺動機構と、上記鋼管の径方向に伸縮し、かつ該鋼管
の内壁に当接して上下に移動自在な車輪を有する複数の
ジャッキ部を設け、上記掘削アームを、上記フレームに
首振り自在に支持された円筒状の外筒と、この外筒の内
側に軸回りに回転自在に設けられた回転軸とから構成
し、該回転軸に上記掘削ヘッドを設けるとともに、上記
外筒に上記回転軸を回転駆動させる回転駆動機構を設け
てなり、上記上部支持機構は、上記鋼管の上端面に配置
される押込み力伝達材、及び該押込み力伝達材を介して
上記鋼管を下方に押圧するジャッキを含む駆動機構と、
上記押込み力伝達材に設けられ、上記懸吊支持部材を支
持して昇降させる懸吊支持部材支持機構とを備えて構成
されたものである
To achieve the above object, according to the solution to ## steel pipe piles drilling device according to claim 1 of the present invention, the steel pipe pile
Excavator, and a suspended support member for suspending and supporting the excavator,
While supporting and suspending the suspension support member, the steel pipe is
And an upper support mechanism for pressing downward.
The pile excavator is configured to have a size that can be inserted into a steel pipe, and has a frame that is suspended and supported from above through a long suspension support member, and an excavation unit that is supported by the frame. and, the drilling unit, composed of a base end portion to the frame a rod shape and a drilling arm that is supported in a freely swinging, and drilling head provided at the lower end of the excavating arm, further, to the frame a swinging mechanism for swinging the swing the excavating arm, and stretch in a radial direction of the steel tube, and a plurality of jack portions having movable wheels up and down in contact with the inner wall of the steel tube is provided, the excavation Arm to the above frame
A cylindrical outer cylinder supported to swing freely, and
With a rotating shaft that is rotatable around the axis on the side
And providing the excavating head on the rotating shaft,
The outer cylinder is provided with a rotation drive mechanism that drives the rotation shaft to rotate.
The upper support mechanism is disposed on the upper end surface of the steel pipe.
Pushing force transmitting material, and the pushing force transmitting material
A drive mechanism including a jack for pressing the steel pipe downward,
The pushing force transmitting member is provided to support the suspension support member.
And a suspension support member support mechanism for lifting and lowering
It was done .

【0008】請求項2の鋼管杭用掘削装置は、鋼管杭用
掘削機と、該掘削機を懸吊支持する懸吊支持部材と、該
懸吊支持部材を支持して昇降させるとともに、鋼管を下
方に押圧する上部支持機構とを備えてなり、上記鋼管杭
用掘削機は、鋼管の内部に挿入可能な大きさに構成さ
れ、長尺な懸吊支持部材を介して上方より懸吊支持され
るフレームと、該フレームに支持された掘削部とを有
し、上記掘削部を、上記フレームに回転自在に支持され
て軸回りに回転する回転体と、この回転体から水平に外
方に延びる複数の棒状の掘削シャフトとから構成すると
ともに、複数の掘削シャフトのうち一部のシャフトを上
記鋼管の径方向に伸縮自在に構成し、さらに、上記フレ
ームに上記鋼管の径方向に伸縮し、かつ該鋼管の内壁に
当接して上下に移動自在な車輪を有する複数のジャッキ
部を設けてなり、上記上部支持機構は、上記鋼管の上端
面に配置される押込み力伝達材、及び該押込み力伝達材
を介して上記鋼管を下方に押圧するジャッキを含む駆動
機構と、上記押込み力伝達材に設けられ、上記懸吊支持
部材を支持して昇降させる懸吊支持部材支持機構とを備
えて構成されたものである。
[0008] A second aspect of the present invention is a steel pipe pile excavator .
An excavator; a suspending support member for suspending and supporting the excavator;
While supporting and suspending the suspension support member, lower the steel pipe.
And an upper support mechanism for pressing the steel pipe pile
Excavator is sized to fit inside a steel pipe.
Is supported from above by a long suspension support member.
Frame and a digging section supported by the frame.
The excavation part is rotatably supported by the frame.
A rotating body that rotates around its axis
And a plurality of rod-shaped excavating shafts
In both cases, some shafts out of multiple
It is configured to be able to expand and contract in the radial direction of the steel pipe.
The tube expands and contracts in the radial direction of the steel pipe, and
Multiple jacks with wheels that can move up and down in contact
The upper support mechanism is provided at the upper end of the steel pipe.
Force transmitting member arranged on a surface, and the pressing force transmitting member
Drive including a jack for pressing the steel pipe downward through
A mechanism and the pushing force transmitting member, and the suspension support
A suspension support member support mechanism for supporting and raising and lowering the member.
It is composed of

【0009】請求項3の鋼管杭の施工方法は、鋼管杭を
地盤に大深度まで設置する鋼管杭の施工方法であって、
下記の工程を備えることを特徴としている。 a.筒状をなす鋼管を地盤上に設置して、該鋼管の先端
部を所定深さまで押し込む工程。 b.上記請求項1又は2に記載の鋼管杭用掘削装置の鋼
管杭用掘削機を懸吊支持部材によって所定の深さまで降
ろして、該鋼管杭用掘削機を鋼管内の所定の位置にセッ
トする工程。 c.上記掘削機の掘削部によって掘削を行いながら鋼管
を押し込む工程。 d.上記鋼管を所定の深さまで押し込んだ後、上記鋼管
杭用掘削機を支持している懸吊支持部材の上端部に、次
の懸吊支持部材を継ぎ足すとともに上記鋼管の上端部に
次の鋼管を継ぎ足す工程。 e.上記d工程の後、c、dの工程を順次所定回数繰り
返すことにより、懸吊支持部材と鋼管を継ぎ足しながら
所定の数の鋼管を上下に連ねて押し込む工程。
According to a third aspect of the present invention, there is provided a method for constructing a steel pipe pile.
A method of constructing a steel pipe pile to be installed at a large depth on the ground,
It is characterized by comprising the following steps. a. A tubular steel pipe is placed on the ground, and the tip of the steel pipe is
Pushing the part to a predetermined depth. b. The steel of the drilling rig for steel pipe piles according to claim 1 or 2.
The pipe pile excavator is lowered to a predetermined depth by the suspension support member.
And set the excavator for steel pipe pile at a predetermined position in the steel pipe.
Process. c. While excavating by the excavating part of the excavator,
Step of pushing. d. After pushing the steel pipe to a predetermined depth,
At the upper end of the suspension support member supporting the pile excavator,
Of the above steel pipe and
The process of adding the next steel pipe. e. After the step d, the steps c and d are sequentially repeated a predetermined number of times.
By returning, the suspension support member and steel pipe are added
A step of vertically pushing a predetermined number of steel pipes in a row.

【0010】請求項4の鋼管杭の施工方法は、請求項3
記載の鋼管杭の施工方法において、掘削中に地盤が硬く
予掘が必要となった際に、鋼管の押し込みを停止して懸
吊部材を下方に降下させながら鋼管杭用掘削機を押し下
げることを特徴としている。
The method for constructing a steel pipe pile according to claim 4 is described in claim 3.
In the construction method of the steel pipe pile described in the
When excavation becomes necessary, stop pushing the steel pipe and suspend it.
Push down the excavator for steel pipe piles while lowering the suspension members
It is characterized by

【0011】請求項5の鋼管杭の施工方法は、請求項4
記載の鋼管杭の施工方法において、鋼管杭用掘削機の掘
削部が鋼管の底部より下方に達した際に、該鋼管の下部
を、鋼管の径方向外側まで掘削することを特徴としてい
る。
[0011] The method for constructing a steel pipe pile according to claim 5 is described in claim 4.
In the construction method of the steel pipe pile described,
When the shaved portion reaches below the bottom of the steel pipe, the lower part of the steel pipe
Is excavated to the outside of the steel pipe in the radial direction.
You.

【0012】[0012]

【作用】この発明の請求項1の鋼管杭用掘削装置にあっ
ては、掘削アームを首振り揺動させながら掘削を行うこ
とにより、この掘削アームの先端部の掘削ヘッドで鋼管
内の全面を掘削するので、従来のハンマー打設または振
動による打設の場合のように、掘削機自体が大型化する
ことなく、しかも、振動・騒音等も殆どなく、都市部で
の施工が可能になる。
According to the first aspect of the present invention, there is provided a drilling device for steel pipe piles.
Excavation while swinging the excavation arm.
And by the drilling head at the tip of this drilling arm with steel pipe
Since the entire surface is excavated, conventional hammering or shaking
Excavator itself becomes large, as in the case of dynamic driving
In urban areas without vibration and noise
Construction becomes possible.

【0013】また、掘削アームを首振り揺動させること
により掘削ヘッドによって鋼管の下部を、鋼管の径方向
外側まで掘削することができる。さらに、ジャッキ部の
ストロークを適宜調整することによって掘削機の鋼管径
方向の位置ぎめを容易かつ正確に行うとともに、ジャッ
キ部を鋼管内壁に上下に移動自在に当接することによっ
て掘削機自体の昇降をスムーズに行う。
Further , the excavating arm is swung.
The lower part of the steel pipe by the drilling head, due to the radial direction of the steel pipe
It can be drilled to the outside. In addition, the jack part
Excavator steel pipe diameter by adjusting the stroke appropriately
Position easily and accurately.
The key part abuts the steel pipe inner wall up and down
The lifting and lowering of the excavator itself is performed smoothly.

【0014】また、掘削アームの外筒を首振り揺動させ
るとともに、掘削ヘッドが取り付けられた回転軸を回転
駆動部によって軸回りに回転させることにより掘削アー
ムの首振り揺動と掘削ヘッドの回転とを容易に実現する
ことができる。
Further , the outer cylinder of the excavating arm is swung and swung.
And rotate the rotating shaft with the drilling head
The drilling arc is rotated by rotating the drive
Easily achieve swinging of the rocking head and rotation of the drilling head
be able to.

【0015】また、上部支持機構によって掘削機の鋼管
内の上下方向の位置を自由に調節することができるの
で、掘削すべき地盤が軟弱でも硬くても、鋼管杭の施工
に最適な位置での掘削を容易に実現することができる。
特に、地盤が硬い場合には、鋼管の押込みを停止してサ
ポート鋼管によって掘削機のみを押し下げながら予掘を
行うことができるので、鋼管の周辺摩擦力を大幅に低減
でき、よって鋼管の沈設を容易に行うことができる。
Further, the steel pipe of the excavator is provided by the upper support mechanism.
You can freely adjust the vertical position inside
Even if the ground to be excavated is soft or hard,
Excavation at an optimal position can be easily realized.
In particular, when the ground is hard, stop pushing the steel pipe to
Pre-digging while pushing down only the excavator with the port steel pipe
Can greatly reduce the frictional force around the steel pipe
Therefore, the steel pipe can be easily laid down.

【0016】また、懸吊支持部材を押込み力伝達材に設
けられた懸吊支持部材支持機構により支持して昇降さ
せ、この懸吊支持部材の昇降に際しては、ジャッキ部材
の車輪が鋼管内面に接して上下動する。したがって、懸
吊支持部材を鋼管上方の定位置で支持するため、掘削機
を確実に支持した状態で掘削作業ができ、正確な掘削作
業が行える。
Also, the suspension support member is provided on the pushing force transmitting member.
Supported by the suspended support member support mechanism
When lifting the suspension support member, the jack member
Wheels move up and down in contact with the inner surface of the steel pipe. Therefore,
The excavator is used to support the suspension support member at a fixed position above the steel pipe.
Excavation work can be performed with the
Work.

【0017】請求項の鋼管杭用掘削装置にあっては、
掘削部がいわゆるシールド掘進機のカッターと同様の構
成であるので、掘削面を一様に掘削することができ、上
記請求項1の掘削装置よりもさらに掘削にかかる時間を
大幅に短縮することができる。また、シャフトの一部を
鋼管の外側に突出させることにより、鋼管の径方向外側
まで掘削することができる。さらに、ジャッキ部のスト
ロークを適宜調整することによって掘削機の鋼管径方向
の位置ぎめを行うとともに、ジャッキ部を鋼管内壁に上
下に移動自在に当接することによって掘削機自体の昇降
をスムーズに行う。
[0017] In the drilling device for steel pipe piles of claim 2 ,
Since the excavation portion has the same configuration as a cutter of a so-called shield excavator, the excavation surface can be excavated uniformly, and the time required for excavation can be greatly reduced as compared with the excavator of the first aspect. it can. Also, by projecting a part of the shaft to the outside of the steel pipe, it is possible to excavate the steel pipe to the outside in the radial direction. Furthermore, the excavator itself is smoothly moved up and down by adjusting the stroke of the jack portion appropriately in the radial direction of the steel pipe of the excavator and by abutting the jack portion up and down on the inner wall of the steel pipe.

【0018】また、上部支持機構によって掘削機の鋼管
内の上下方向の位置を自由に調節することができるの
で、掘削すべき地盤が軟弱でも硬くても、鋼管杭の施工
に最適な位置での掘削を容易に実現することができる。
特に、地盤が硬い場合には、鋼管の押込みを停止してサ
ポート鋼管によって掘削機のみを押し下げながら予掘を
行うことができるので、鋼管の周辺摩擦力を大幅に低減
でき、よって鋼管の沈設を容易に行うことができる。
Further, the steel pipe of the excavator is provided by the upper support mechanism.
You can freely adjust the vertical position inside
Even if the ground to be excavated is soft or hard,
Excavation at an optimal position can be easily realized.
In particular, when the ground is hard, stop pushing the steel pipe to
Pre-digging while pushing down only the excavator with the port steel pipe
Can greatly reduce the frictional force around the steel pipe
Therefore, the steel pipe can be easily laid down.

【0019】また、懸吊支持部材を押込み力伝達材に設
けられた懸吊支持部材支持機構により支持して昇降さ
せ、この懸吊支持部材の昇降に際しては、ジャッキ部材
の車輪が鋼管内面に接して上下動する。したがって、懸
吊支持部材を鋼管上方の定位置で支持するため、掘削機
を確実に支持した状態で掘削作業ができ、正確な掘削作
業が行える。
Further , a suspension support member is provided on the pushing force transmitting member.
Supported by the suspended support member support mechanism
When lifting the suspension support member, the jack member
Wheels move up and down in contact with the inner surface of the steel pipe. Therefore,
The excavator is used to support the suspension support member at a fixed position above the steel pipe.
Excavation work can be performed with the
Work.

【0020】請求項の鋼管杭の施工方法にあっては、
鋼管内を掘削機によって掘削しつつ鋼管を押し込むよう
にしたので、沈設すべき鋼管の口径が大きくなっても、
従来のハンマー打設または振動による打設の場合のよう
に、振動・騒音等も殆どなく、都市部での施工が可能に
なる。また、サポート鋼管と鋼管を継ぎ足しながら施工
するとともに、上部支持機構によってサポート鋼管と鋼
管を下方に押し込む力を確実に得ることができるので、
施工深度が深くなっても容易かつ確実に施工することが
できる。さらに、サポート鋼管と鋼管を継ぎ足しながら
施工するとともに、最初の鋼管を沈設する際に、上部支
持機構によって鋼管の下端部を所定の深さまで押し込む
ようにしたので、鋼管の転倒などの危険性を回避するこ
とができる。
In the method for constructing a steel pipe pile according to claim 3 ,
Since the steel pipe was pushed while excavating inside the steel pipe, even if the diameter of the steel pipe to be laid was large,
Unlike a conventional hammering or driving by vibration, there is almost no vibration and noise, and construction in an urban area is possible. In addition, since the construction is performed while adding the support steel pipe and the steel pipe, the force for pushing the support steel pipe and the steel pipe downward by the upper support mechanism can be reliably obtained.
Even if the construction depth becomes deep, construction can be performed easily and reliably. In addition, construction is performed while adding the support steel pipe and the steel pipe, and the lower end of the steel pipe is pushed down to a predetermined depth by the upper support mechanism when the first steel pipe is sunk, avoiding the danger of falling down of the steel pipe can do.

【0021】請求項の鋼管杭の施工方法にあっては、
地盤が硬く予掘が必要となった際に、掘削機のみを押し
下げながら予掘を行うようにしたので、鋼管の周辺摩擦
力を大幅に低減でき、よって地盤が硬い場合でも鋼管の
沈設を容易に行うことができる。
In the method for constructing a steel pipe pile according to claim 4 ,
When the ground is hard and pre-digging is required, pre-digging is performed while pushing down only the excavator, so that the frictional force around the steel pipe can be significantly reduced, so that the steel pipe can be easily laid down even when the ground is hard Can be done.

【0022】請求項の鋼管杭の施工方法にあっては、
掘削部が鋼管の底部より下方に達した際に、該鋼管の下
部を、鋼管の径方向外側まで掘削するようにしたので、
さらに鋼管の沈降を容易に行うことができる。
In the method for constructing a steel pipe pile according to claim 5 ,
When the excavated part reached below the bottom of the steel pipe, the lower part of the steel pipe was excavated to the radial outside of the steel pipe,
Further, the steel pipe can be easily settled.

【0023】[0023]

【実施例】以下、この発明の実施例について図面を参照
しながら説明する。図1ないし図5はこの発明の鋼管杭
用掘削機の一実施例を示すものであり、図1は鋼管杭用
掘削機30Aを沈設すべき鋼管10と共に示す立断面
図、図2は図におけるB−B線に沿う矢視図である。
Embodiments of the present invention will be described below with reference to the drawings. 1 to 5 show an embodiment of a steel pipe pile excavator according to the present invention. FIG. 1 is an elevational sectional view showing a steel pipe pile excavator 30A together with a steel pipe 10 to be laid, and FIG. It is an arrow view along the BB line.

【0024】この鋼管杭用掘削機30Aは、該掘削機3
0Aの骨格を成すフレーム31の下部に掘削部32が支
持されて成る。上記フレーム31は、図2にも示すとお
り、その断面が上記鋼管10の内径よりも小径の円形を
呈するものとなっている。このフレーム31についてさ
らに説明すれば、該フレーム31は、同軸的に配置され
た上リング33,中リング34,下リング35と、これ
ら各リング33,34,35をそれぞれつなぐ複数本の
四角柱状をなすつなぎ材36,36,…およびつなぎ材
37,37,…を主体に構成されている。
The excavator 30A for steel pipe piles has
The excavation part 32 is supported by the lower part of the frame 31 which forms a skeleton of 0A. As shown in FIG. 2, the cross section of the frame 31 has a circular shape whose diameter is smaller than the inner diameter of the steel pipe 10. The frame 31 will be further described. The frame 31 includes an upper ring 33, a middle ring 34, and a lower ring 35 which are coaxially arranged, and a plurality of quadrangular prisms connecting these rings 33, 34, 35, respectively. The connecting members 36, 36,... And the connecting members 37, 37,.

【0025】このフレーム31の上記上リング33の内
側には、十字状をなす水平材38が該上リング33に固
定され、さらに上記つなぎ材36…に固定された補強鋼
材39…によって補強されている。上記水平材38の中
央部には、上記フレーム31を懸吊支持する円筒状のサ
ポート鋼管(懸吊支持部材)40の下端が接続されてい
る。このサポート鋼管40の上端は鋼管10を沈設を開
始した地盤上にまで延びており、後述する上部支持機構
70によって昇降可能に支持されている。
Inside the upper ring 33 of the frame 31, a horizontal member 38 having a cross shape is fixed to the upper ring 33, and further reinforced by reinforcing steel members 39 fixed to the connecting members 36. I have. The lower end of a cylindrical support steel pipe (suspension support member) 40 that suspends and supports the frame 31 is connected to the center of the horizontal member 38. The upper end of the support steel pipe 40 extends to the ground where the steel pipe 10 has started to be laid, and is supported by an upper support mechanism 70 described later so as to be able to move up and down.

【0026】また、上記フレーム31の上記中リング3
4の中心部には、上記掘削部32が取り付けられてい
る。すなわち、上記掘削部32は中リング34から下方
に延びる掘削アーム48と、この掘削アーム48の先端
部(下端部)に設けられた掘削ヘッド51とを主体とし
て構成されており、該掘削アーム48の基端部(上端
部)が上記中リング34に首振り自在に取り付けられて
いる。この掘削アーム48は外筒49と、この外筒49
の内部に外筒49と同軸的にかつ軸回りに回転自在に挿
入された内筒(回転軸)50とによって構成されてい
る。上記内筒50の下端部は外筒49より若干下方に突
出しており、該下端部に上記掘削ヘッド51が取り付け
られている。この掘削ヘッド51は略半球状をなすヘッ
ド本体51aとこの本体51aの表面に固定された多数
のビット51b…によって構成されており、上記ヘッド
本体51aの上端面が上記内筒50に取り付けられてい
る。一方、上記外筒49は図1に示す如く中リング34
との取付け部において球形膨出部52を形成している。
中リング34中心部には、この球形膨出部52をその球
面に沿って摺動自在に支持するベアリング部53が構成
されている。上記構成により、上記掘削アーム48は上
記球形膨出部52を中心に首振り自在なものとなってい
る。
The middle ring 3 of the frame 31
The excavation part 32 is attached to the center part of 4. That is, the excavation section 32 is mainly configured by an excavation arm 48 extending downward from the middle ring 34 and an excavation head 51 provided at a tip end (lower end) of the excavation arm 48. Is attached to the middle ring 34 so as to swing freely. The excavating arm 48 includes an outer cylinder 49 and the outer cylinder 49.
And an inner cylinder (rotary shaft) 50 coaxially and rotatably inserted around an axis. The lower end of the inner cylinder 50 projects slightly below the outer cylinder 49, and the excavation head 51 is attached to the lower end. The excavating head 51 is composed of a substantially hemispherical head main body 51a and a number of bits 51b fixed to the surface of the main body 51a. The upper end surface of the head main body 51a is attached to the inner cylinder 50. I have. On the other hand, as shown in FIG.
And a spherical bulging portion 52 is formed at the mounting portion.
At the center of the middle ring 34, a bearing portion 53 for slidably supporting the spherical bulging portion 52 along its spherical surface is formed. With the above configuration, the excavating arm 48 can swing freely about the spherical bulging portion 52.

【0027】さらに、上記掘削アーム48の内筒50は
軸回りに回転するようになっているが、その回転駆動機
構45は下記の如き構成である。すなわち、上記外筒4
9の上端には図3および図4に示す如く円形鍔状に張り
出した外筒頂部プレート49aが設けられている。一
方、上記内筒50の上端は上記外筒頂部プレート49a
よりも若干上方に突出しており、外筒頂部プレート49
aと同様に外方に鍔状に張り出している。ただし、その
張り出しは外筒頂部プレート49aほど大きくはなくそ
の外周部にはギヤ54が形成されている。さらに、上記
外筒頂部プレート49aには油圧モーター55,55が
設けられており、それら油圧モーター55,55によっ
て駆動されるピニオン55a,55a(図4)が上記ギ
ヤ53と噛合している。なお、上記油圧モーター55お
よびピニオン55aは1組のみであってもよい。上記構
成に基づき、上記油圧モーター55の駆動により、上記
ピニオン55aを介して内筒50が自身の軸周りに回動
し、それによって掘削ヘッド51が回転するようになっ
ている。
Further, the inner cylinder 50 of the excavating arm 48 is configured to rotate around an axis, and the rotation driving mechanism 45 has the following configuration. That is, the outer cylinder 4
As shown in FIGS. 3 and 4, an outer cylinder top plate 49a that protrudes in a circular flange shape is provided at the upper end of the cylinder 9. On the other hand, the upper end of the inner cylinder 50 is connected to the outer cylinder top plate 49a.
Projecting slightly higher than the outer cylinder top plate 49.
As in a, it protrudes outward in a flange shape. However, the overhang is not as large as the outer cylinder top plate 49a, and a gear 54 is formed on the outer peripheral portion. Further, hydraulic motors 55, 55 are provided on the outer cylinder top plate 49a, and pinions 55a, 55a (FIG. 4) driven by the hydraulic motors 55, 55 mesh with the gear 53. The hydraulic motor 55 and the pinion 55a may be only one set. Based on the above configuration, by driving the hydraulic motor 55, the inner cylinder 50 rotates around its own axis via the pinion 55a, whereby the excavation head 51 rotates.

【0028】また、上記下リング35には上記掘削アー
ム48を首振り揺動させる揺動機構56が設けられてい
る。すなわち、図3および図5に示すように、上記掘削
アーム48の外筒49には左右一対のブラケット49
b,49bが設けられており、これらブラケット49
b,49bには、外筒49を挟んで対向して配置された
2本の油圧シリンダー57,57の伸縮ロッド57a,
57aがそれぞれピン結合されている。そして、これら
2本の油圧シリンダー57,57のうち一方の伸縮ロッ
ド57を伸張させ、他方の伸縮ロッド57aを退縮させ
ることにより、掘削アーム48は上記球形膨出部52を
中心として一方向(左右)に揺動するようになってい
る。
The lower ring 35 is provided with a swing mechanism 56 for swinging the excavating arm 48. That is, as shown in FIG. 3 and FIG.
b, 49b are provided.
b, 49b, telescopic rods 57a, 57 of two hydraulic cylinders 57, 57 disposed opposite to each other with the outer cylinder 49 interposed therebetween.
57a are respectively pin-connected. Then, by extending one telescopic rod 57 of these two hydraulic cylinders 57 and 57 and retracting the other telescopic rod 57a, the excavation arm 48 is moved in one direction (left and right) around the spherical bulge 52. ).

【0029】上記油圧シリンダー57,57は、図5に
示す如く、上記下リング35上に設けられた四角枠型の
前後移動架台58に取付けられている。上記下リング3
5内には図5に示すように2本のレール枕材59,59
が並行して設けられており、これらレール枕材59,5
9の上面にはそれぞれレール60,60が敷設されてい
る。上記前後移動架台58の下面には上記レール60,
60に係合してその上を転動する車輪61(図3)が左
右2個ずつ設けられている。この構成により前後移動架
台58は上記レール60に沿って前後方向に移動可能で
ある。なお、ここで、レール60の延在方向は上記油圧
シリンダー57,57に対して直角である。
As shown in FIG. 5, the hydraulic cylinders 57, 57 are mounted on a rectangular frame-type front-rear moving frame 58 provided on the lower ring 35. Lower ring 3
5, two rail pillows 59, 59 as shown in FIG.
Are provided in parallel, and these rail pillows 59, 5
Rails 60, 60 are laid on the upper surface of 9, respectively. The rail 60,
Two wheels 61 (FIG. 3) are provided on each of the left and right sides to engage with and roll on the wheel. With this configuration, the back-and-forth moving gantry 58 can move in the front-back direction along the rail 60. Here, the extending direction of the rail 60 is perpendicular to the hydraulic cylinders 57, 57.

【0030】また、上記前後移動架台58と下リング3
5との間には、上記レール60の長手方向に延在する油
圧シリンダー62,62,…がそれぞれ両側2本ずつ配
設されており(図5)、これら各油圧シリンダ62の基
端部は上記下リング35に、また各ピストンロッド62
aの先端部は上記前後移動架台58にそれぞれピン結合
されている。そして、上記前後移動架台58は、油圧シ
リンダ62…のピストンロッド62a…を伸縮すること
によってレール60,60に沿って移動せしめられるよ
うになっている。そして、上記構成の揺動機構56で
は、油圧シリンダ57,57によって掘削アーム48が
左右に揺動せしめらる一方、これら油圧シリンダ57,
57が油圧シリンダ62,62によって前後に揺動せし
められる前後移動架台58に設けられているので、これ
らシリンダ57,62に作動させることにより、掘削ア
ーム48を上記球形膨出部52を中心として前後左右に
首振り揺動させるようになっている。
Further, the back-and-forth moving base 58 and the lower ring 3
., Two hydraulic cylinders 62, 62,... Extending in the longitudinal direction of the rail 60 are provided on both sides (FIG. 5). The lower ring 35 and each piston rod 62
The distal end of a is pin-connected to the front-rear moving frame 58, respectively. The front / rear moving frame 58 can be moved along the rails 60 by extending and retracting the piston rods 62a of the hydraulic cylinders 62. In the swing mechanism 56 having the above-described configuration, the excavation arm 48 is swung right and left by the hydraulic cylinders 57 and 57, while the hydraulic cylinders 57 and 57 are rotated.
The excavating arm 48 is moved forward and backward about the spherical bulging portion 52 by operating the cylinders 57 and 62 since the excavating arm 48 is provided on the front and rear moving base 58 which is swung back and forth by the hydraulic cylinders 62 and 62. It swings right and left.

【0031】また、上記中リング34には、図1および
図2に示すように、該中リング34から半径方向外方に
延びる4本のジャッキ部63が周方向に等間隔で設けら
れている。このジャッキ部63は、上記鋼管10の径方
向に伸縮自在の伸縮アーム63aを備えており、この伸
縮アーム63aの先端部には車輪64が回転自在に取り
付けられている。この車輪64は、伸縮アーム63aを
伸張することによって鋼管10aの内壁に当接して上記
フレーム31の鋼管10内の径方向における位置決めを
行うとともに、該フレーム31を昇降させる際に鋼管1
0の内壁を転動してフレーム31の昇降をガイドするた
めのものである。なお、この実施例ではジャッキ部63
を4本設けたが、これに限ることなく少なくとも3本以
上設ければよい。
As shown in FIGS. 1 and 2, the middle ring 34 is provided with four jack portions 63 extending radially outward from the middle ring 34 at equal intervals in the circumferential direction. . The jack portion 63 includes a telescopic arm 63a that can expand and contract in the radial direction of the steel pipe 10, and a wheel 64 is rotatably attached to a distal end of the telescopic arm 63a. The wheel 64 abuts on the inner wall of the steel pipe 10a by extending the telescopic arm 63a to position the frame 31 in the radial direction within the steel pipe 10 and to move the frame 31 up and down when the frame 31 is moved up and down.
The inner wall 0 is rolled to guide the frame 31 up and down. In this embodiment, the jack 63 is used.
Although four are provided, at least three or more may be provided without being limited to this.

【0032】また、上記掘削アーム48の下端部には図
1に示す如く土砂輸送パイプ65aがその開口を掘削ヘ
ッド51に近接させて固定金具66によって取り付けら
れている。この土砂輸送パイプ65aは掘削アーム48
によって掘削土砂を泥水と共に地上まで引き上げるため
のものである。
As shown in FIG. 1, a sediment transport pipe 65a is attached to the lower end of the excavating arm 48 by a fixing bracket 66 with its opening close to the excavating head 51. The excavation arm 48
This is to lift the excavated earth and sand together with mud to the ground.

【0033】図6および図7は、上記掘削機30Aを備
えた掘削装置30Bを示すものであり、符号70は、上
記サポート鋼管40を支持して昇降させるとともに、鋼
管10を下方に押圧するため鋼管10の上端部に設置さ
れた上部支持機構を示している。この上部支持機構70
において符号71は押込み力伝達材で、鋼管10の上端
面に水平に載置状態とされている。この押込み力伝達材
71の外方端部には例えばPC鋼材等からなる引張部材
72,72,…の上端部が定着されている。これら引張
部材72の下端は、鋼管10の周囲の地盤に定着されて
いる。また、これら各引張部材72には該引張部材を緊
張するためのジャッキ(この場合PCジャッキ)73が
設けられている。本実施例においては、これら引張部材
72とジャッキ73とから駆動機構が構成される。
FIGS. 6 and 7 show an excavator 30B provided with the excavator 30A. Reference numeral 70 denotes a support steel pipe 40 for supporting and raising and lowering the same, and pressing the steel pipe 10 downward. The upper support mechanism installed at the upper end of the steel pipe 10 is shown. This upper support mechanism 70
In the figure, reference numeral 71 denotes a pushing force transmitting member, which is placed horizontally on the upper end surface of the steel pipe 10. The upper ends of the tension members 72, 72,... Made of, for example, PC steel are fixed to the outer end of the pushing force transmitting member 71. The lower ends of the tension members 72 are fixed to the ground around the steel pipe 10. Each of the tension members 72 is provided with a jack (PC jack in this case) 73 for tensioning the tension member. In this embodiment, these tension members
A drive mechanism is composed of the jack 72 and the jack 73.

【0034】上記押込み力伝達材71の上部には、上記
サポート鋼管40を支持して昇降させるサポート鋼管支
持機構74が設けられている。このサポート鋼管支持機
構74は、左右からサポート鋼管40を挟む一対の把持
板75a,75bおよび把持板76a,76bを上下二
段に有しており、下段の把持板76a,76bは上記押
込み力伝達材71の上面に固定されている。対を成す一
方(上方)の把持板75a,75b間には2本の押えジ
ャッキ77,77が設けられており、これら押えジャッ
キ77,77(図8)を操作することによって、対を成
す把持板75a,75bが互いに接近・離間してサポー
ト鋼管40の把持・解放を行うようになっている。同じ
く対を成す他方(下方)の把持板76a,76b間にも
2本の押えジャッキ78,78が設けられており、これ
ら押えジャッキ78,78(図7)を操作することによ
って、把持板76a,76bによってサポート鋼管40
の把持・解放を行うようになっている。
Above the pushing force transmitting member 71, there is provided a support steel pipe support mechanism 74 for supporting and raising and lowering the support steel pipe 40. This support steel pipe support mechanism 74 has a pair of upper and lower gripping plates 75a, 75b and gripping plates 76a, 76b sandwiching the support steel pipe 40 from the left and right. The lower gripping plates 76a, 76b transmit the pushing force. It is fixed to the upper surface of the member 71. Two pressing jacks 77, 77 are provided between the paired (upper) gripping plates 75a, 75b, and by operating these pressing jacks 77, 77 (FIG. 8), a pair of gripping jacks is formed. The plates 75a and 75b approach and separate from each other to grip and release the support steel pipe 40. Similarly, two pressing jacks 78, 78 are provided between the other (lower) gripping plates 76a, 76b that form a pair, and by operating these pressing jacks 78, 78 (FIG. 7), the gripping plates 76a, 76b are operated. , 76b support steel pipe 40
The gripping / releasing is performed.

【0035】また、上記上方の把持板75a,75bと
下方の把持板76a,76bとの間には図6ないし図8
に示す如く4本の上下ジャッキ79,79,…が設けら
れており、これら上下ジャッキ79…を一斉に操作する
ことにより、上方の把持板75a,75bを平行に上下
移動させることができるようになっている。
6 to 8 are provided between the upper gripping plates 75a and 75b and the lower gripping plates 76a and 76b.
Are provided, and by operating these upper and lower jacks 79 simultaneously, the upper grip plates 75a, 75b can be moved up and down in parallel. Has become.

【0036】そして、上記構成のサポート鋼管支持機構
74では、上記サポート鋼管40を上昇させる場合、以
下のようにして行う。上下ジャッキ79…を退縮させた
状態において、上段の把持板75a,75bによってサ
ポート鋼管10を把持し、その後、把持板76a,76
bを解放して上下ジャッキ79…を伸張することにより
サポート鋼管10をジャッキの1ストローク分だけ上昇
させ、次に把持板76a,76bによってサポート鋼管
40を把持した後、把持板75a,75bを解放して上
下ジャッキ79…を退縮する作業を順次繰り返すことに
よってサポート鋼管40を上昇させる。
In the support steel pipe support mechanism 74 having the above structure, when the support steel pipe 40 is raised, it is performed as follows. In a state in which the upper and lower jacks 79 are retracted, the support steel pipe 10 is gripped by the upper gripping plates 75a, 75b, and then the gripping plates 76a, 76
b is released and the upper and lower jacks 79 are extended to raise the support steel pipe 10 by one stroke of the jack. Next, the support steel pipe 40 is gripped by the gripping plates 76a and 76b, and then the gripping plates 75a and 75b are released. The support steel pipe 40 is raised by sequentially repeating the operation of retracting the upper and lower jacks 79.

【0037】また、サポート鋼管を下降させる場合、上
記と逆の作業、すなわち上下のジャッキ79…を伸張さ
せた状態において、上段の把持板75a,75bによっ
てサポート鋼管10を把持し、その後、把持板76a,
76bを解放して上下ジャッキ79…を退縮することに
よりサポート鋼管10をジャッキの1ストローク分だけ
下降させ、次に把持板76a,76bによってサポート
鋼管40を把持した後、把持板75a,75bを解放し
て上下ジャッキ79…を伸張する作業を順次繰り返すこ
とによってサポート鋼管40を下降させる。
When the support steel pipe is lowered, the support steel pipe 10 is gripped by the upper gripping plates 75a and 75b in the reverse operation, that is, in a state where the upper and lower jacks 79 are extended. 76a,
The support steel pipe 10 is lowered by one stroke of the jack by releasing the upper and lower jacks 79... After the release of the support steel pipe 40, and after the support steel pipe 40 is gripped by the gripping plates 76 a and 76 b, the gripping plates 75 a and 75 b are released. The operation of extending the upper and lower jacks 79... Is sequentially repeated to lower the support steel pipe 40.

【0038】なお、図6中において符号65bで示すも
のは、泥水注入用パイプである。この泥水注入用パイプ
65bおよび上記土砂輸送パイプ65aは、地盤に設置
された動力基地Dを介して、土砂分離プラントPに接続
されている。
The reference numeral 65b in FIG. 6 denotes a muddy water injection pipe. The muddy water injection pipe 65b and the earth and sand transport pipe 65a are connected to the earth and sand separation plant P via a power base D installed on the ground.

【0039】次に上記構成の鋼管杭用掘削装置Bを用い
て鋼管杭を施工する方法について説明する。 (1)まず、図10に示すように、地盤上の所定の位置
に鋼管10を設置する。これは、通常のクレーンにより
鋼管10を吊り下げて行う。 (2)次に、図11に示すように、鋼管10の先端面に
上記押込み力伝達部材71を設置して、この押込み力伝
達材71の外方端部に上記引張部材72…の上端部を定
着するとともに、これら引張部材72…の下端部を地盤
に定着する。その後、上記PCジャッキ73…によって
引張部材72…に緊張力を導入することによって、押込
み力伝達材71を下方に押圧し、これにより鋼管10の
下端部を地盤に所定深さまで押し込む。このように鋼管
10を押し込むことにより、特に、地盤の弱い所での鋼
管10の転倒等の危険性を回避することができる。
Next, a method of constructing a steel pipe pile using the steel pipe pile excavator B having the above configuration will be described. (1) First, as shown in FIG. 10, a steel pipe 10 is installed at a predetermined position on the ground. This is performed by suspending the steel pipe 10 using a normal crane. (2) Next, as shown in FIG. 11, the pushing force transmitting member 71 is installed on the distal end surface of the steel pipe 10, and the outer end of the pushing force transmitting member 71 has the upper end of the pulling members 72. And the lower ends of these tension members 72 are fixed to the ground. Thereafter, the pushing force transmitting member 71 is pressed downward by applying a tension to the tension members 72 by the PC jacks 73, whereby the lower end portion of the steel pipe 10 is pushed into the ground to a predetermined depth. By pushing the steel pipe 10 in this way, it is possible to avoid the danger of the steel pipe 10 tipping over, for example, where the ground is weak.

【0040】(3)次に、図12に示すように、上記掘
削機30Aをサポート鋼管40によって所定の深さまで
降ろして、該掘削機30Aを鋼管10内の所定の位置に
セットする。この場合、掘削機30Aを鋼管10内下方
に降ろすには、上記サポート鋼管支持機構74を用い
る。つまり、まず上記下段の把持板76a,76bのみ
でサポート鋼管40を把持する。そのためには上記2本
の押えジャッキ78,78を退縮させればよい。上方の
把持板75a,75bは上記押えジャッキ77,77を
伸張させることにより開放しておき、その状態で上記4
本の上下ジャッキ79を一斉に伸張させ、これにより上
方の把持板75a,75bを上方に移動させる。次い
で、今度は、上方の把持板75a,75bによってサポ
ート鋼管40を把持するとともに下方の把持板76a,
76bによる把持を解き、上方の把持板75a,75b
のみでサポート鋼管40を把持した状態とする。この状
態で上下ジャッキ79を一斉に退縮させればそのストロ
ーク分だけサポート鋼管40が下方に送られ、掘削機3
0Aを下方に移動させることができる。以降は、上記動
作を繰り返すことにより掘削機30Aを順次下方に送り
込んでいき、該掘削機30Aの上下の位置調整を行う。
(3) Next, as shown in FIG. 12, the excavator 30A is lowered to a predetermined depth by the support steel pipe 40, and the excavator 30A is set at a predetermined position in the steel pipe 10. In this case, the support steel pipe support mechanism 74 is used to lower the excavator 30A inside the steel pipe 10. That is, first, the support steel pipe 40 is gripped only by the lower gripping plates 76a and 76b. For this purpose, the two pressing jacks 78, 78 may be retracted. The upper holding plates 75a, 75b are opened by extending the pressing jacks 77, 77, and in this state,
The upper and lower jacks 79 are simultaneously extended, thereby moving the upper grip plates 75a and 75b upward. Next, this time, the support steel pipe 40 is gripped by the upper gripping plates 75a, 75b, and the lower gripping plates 76a,
Release the gripping by the upper gripping plates 75a, 75b
Only the support steel tube 40 is held. If the upper and lower jacks 79 are simultaneously retracted in this state, the support steel pipe 40 is sent downward by the stroke, and the excavator 3
OA can be moved downward. Thereafter, the excavator 30A is sequentially sent downward by repeating the above operation, and the up and down position of the excavator 30A is adjusted.

【0041】さらに、上記掘削機30Aを降ろす際にお
いては、上記4本のジャッキ部63…を用いて該フレー
ム31の平面的位置調整(鋼管10の径方向における位
置調整)を行う。すなわち、掘削機30Aを降ろす前
に、各ジャッキ部63の伸縮アーム63aを伸張して、
その先端部に設けられた車輪64を鋼管10の内壁に当
接する。この際、各伸縮アーム63aのストロークを適
宜調節することによって掘削機30Aは鋼管10内にそ
の径方向に対する位置決めがなされて固定される。ま
た、該掘削機30Aはその上記車輪64が鋼管10の内
壁に当接しているので、上下方向の移動をスムーズに行
うことができ、該掘削機30Aの上下位置の変更が容易
に行える。さらに、サポート鋼管40を押込み力伝達材
71に設けられたサポート鋼管支持機構74により支持
して昇降させるから、このサポート鋼管40の昇降に際
しては、サポート鋼管40を鋼管10上方の定位置で支
持することとなる。よって、掘削機30Aを確実に支持
した状態で掘削作業ができ、正確な掘削作業が行える。
When lowering the excavator 30A, the four jacks 63 are used to adjust the planar position of the frame 31 (position adjustment in the radial direction of the steel pipe 10). That is, before lowering the excavator 30A, the telescopic arms 63a of the jacks 63 are extended,
The wheel 64 provided at the distal end of the wheel abuts on the inner wall of the steel pipe 10. At this time, by appropriately adjusting the stroke of each telescopic arm 63a, the excavator 30A is positioned and fixed in the radial direction in the steel pipe 10. Also, since the wheels 64 of the excavator 30A are in contact with the inner wall of the steel pipe 10, the excavator 30A can move smoothly in the vertical direction, and the vertical position of the excavator 30A can be easily changed. Further, the support steel pipe 40 is pushed into
Supported by a support steel pipe support mechanism 74 provided at 71
When the support steel pipe 40 is raised and lowered,
Then, the support steel pipe 40 is supported at a fixed position above the steel pipe 10.
Will have. Therefore, the excavator 30A is reliably supported.
Excavation work can be performed in a state where it is done, and accurate excavation work can be performed.

【0042】(4)次に、上記のようにして上記掘削機
30Aの位置決めがなされた後、図13に示すように、
該掘削機30Aの掘削部32によって掘削を行いながら
鋼管10を押し込む。すなわち、上記掘削アーム48を
作動させることにより上記鋼管10の下端部の地山を掘
削する。掘削アーム48においては、上記油圧モーター
55,55を作動させることにより内筒50を介して掘
削ヘッド51を回転させる。それとともに、外筒49に
取付けられた上記油圧シリンダー57,57のそれぞれ
の伸縮ロッド57a,57aを交互に伸縮を繰り返すこ
とによって該掘削アーム48を球形膨出部52を中心と
して左右に振り動かす。さらに、上記前後移動架台58
を上記油圧シリンダー62…の伸縮を繰り返すことによ
り上記レール60上を前後に移動させる。これにより、
掘削アーム48の先端部に設けられた掘削ヘッド51は
鋼管10の全断面を掘削することができる。なお、上記
掘削の際には鋼管10内に上記泥水注入用パイプ65b
から泥水を注入し、常に掘削面の圧力よりも水圧を高く
保つように、泥水の水面を高く保って地山の崩壊を防止
する。
(4) Next, after the excavator 30A is positioned as described above, as shown in FIG.
The steel pipe 10 is pushed in while excavating by the excavation part 32 of the excavator 30A. That is, by operating the excavating arm 48, the ground at the lower end of the steel pipe 10 is excavated. In the excavating arm 48, the excavating head 51 is rotated via the inner cylinder 50 by operating the hydraulic motors 55, 55. At the same time, the extensible rods 57a, 57a of the hydraulic cylinders 57, 57 attached to the outer cylinder 49 are alternately expanded and contracted alternately to swing the excavating arm 48 right and left around the spherical bulging portion 52. Further, the back-and-forth moving mount 58
Are moved back and forth on the rail 60 by repeatedly expanding and contracting the hydraulic cylinders 62. This allows
The excavation head 51 provided at the tip of the excavation arm 48 can excavate the entire cross section of the steel pipe 10. At the time of the excavation, the pipe 65b for injecting the muddy water into the steel pipe 10 is used.
The muddy water is injected from the ground, and the water level of the muddy water is kept high to prevent the collapse of the ground, so that the water pressure is always higher than the pressure of the excavated surface.

【0043】掘削土砂は上記土砂輸送パイプ65aを通
して泥水と共に地盤に設置した土砂分離プラントPに送
り、そこで土砂分離した後泥水は上記泥水注入用パイプ
65bを通して掘削孔(鋼管10)内に還流させる。こ
こで、上記土砂輸送パイプ65aの下端部が上記掘削ア
ームの下端部に取り付けられて、該土砂輸送パイプ65
aの開口が掘削ヘッド51に近接しているので、該開口
は掘削ヘッド51と同じように掘削面全体を移動するこ
とになり、よって掘削土砂の取り込み残しが少なく確実
な取り込みを行うことができる。
The excavated earth and sand is sent together with the muddy water through the sediment transport pipe 65a to a sediment separation plant P installed on the ground, where the muddy water is returned to the excavation hole (steel pipe 10) through the muddy water injection pipe 65b. Here, the lower end of the sediment transport pipe 65a is attached to the lower end of the excavation arm, and
Since the opening of “a” is close to the excavation head 51, the opening moves on the entire excavation surface in the same manner as the excavation head 51, so that the remaining of excavated earth and sand can be reliably reduced. .

【0044】上記の掘削操作に伴い鋼管10を図7に示
す如く地盤内に押し込んでいく。鋼管10を押し込むに
は、上記PCジャッキ73により上記引張部材72,7
2,…を緊張し、それにより上記押込力伝達材71を下
方に押圧する。これにより、鋼管10は下方に圧入され
る。この時、上記サポート鋼管支持機構74によってサ
ポート鋼管40を把持しておけば、掘削機30Aも鋼管
10と共に下方に押し付けられることになる。通常は、
このように、鋼管10および掘削機30Aを同時に押し
込むこと、すなわち地盤掘削と鋼管10の圧入とを同時
に行うことができる。
With the above excavation operation, the steel pipe 10 is pushed into the ground as shown in FIG. To push the steel pipe 10 in, the PC jack 73 is used to pull the tension members 72, 7.
Are pressed, thereby pressing the pushing force transmitting member 71 downward. Thereby, the steel pipe 10 is press-fitted downward. At this time, if the support steel pipe 40 is gripped by the support steel pipe support mechanism 74, the excavator 30A is also pressed downward together with the steel pipe 10. Normally,
As described above, the steel pipe 10 and the excavator 30A can be simultaneously pushed in, that is, ground excavation and press-fitting of the steel pipe 10 can be performed simultaneously.

【0045】一方、掘削する地盤が特に硬く、予掘が必
要になった場合には、図9(a)に示すように、鋼管1
0の圧入を停止して掘削のみを行う。この場合、上記サ
ポート鋼管支持機構74を用い、サポート鋼管40を押
し込むことによって、掘削機30Aを押し下げることに
より行う。さらに、掘削機30Aの掘削ヘッド51が鋼
管10の底部より下方に達した時点で必要なら、さらに
掘削を行い鋼管10の下部を、該鋼管10の径方向外側
まで掘削する。この場合、上記油圧シリンダ57,62
のストロークを若干長くして、掘削アーム48の首振り
のストロークを長くすることによって、掘削ヘッド51
が鋼管10の外側まで移動するので、鋼管10の外側を
容易に掘削することができる。また、掘削する地盤が軟
弱な場合、図9(b)に示すように、鋼管10が自然沈
下を起こさない程度に鋼管10内に土砂を呼び込む。そ
して、この深さに掘削機30Aをセットして掘削を行
う。
On the other hand, when the ground to be excavated is particularly hard and preliminary excavation is required, as shown in FIG.
Stop the 0 injection and perform only excavation. In this case, the excavator 30A is pushed down by pushing in the support steel pipe 40 using the support steel pipe support mechanism 74. Further, if necessary, when the excavating head 51 of the excavator 30A reaches below the bottom of the steel pipe 10, further excavation is performed to excavate the lower part of the steel pipe 10 to the outside in the radial direction of the steel pipe 10. In this case, the hydraulic cylinders 57, 62
Of the excavation head 51 by slightly increasing the stroke of
Moves to the outside of the steel pipe 10, so that the outside of the steel pipe 10 can be easily excavated. Further, when the ground to be excavated is soft, as shown in FIG. 9B, sediment is drawn into the steel pipe 10 to such an extent that the steel pipe 10 does not cause natural settlement. Then, the excavator 30A is set at this depth to perform excavation.

【0046】(5)次に、上記鋼管10を所定の深さま
で押し込んだ後、上部支持機構70(押込み伝達部材7
1、引張部材72、ジャッキ73およびサポート鋼管支
持機構74)を撤去して、次いで図15に示すように、
上記サポート鋼管40の上端部に次のサポート鋼管4
0′を継ぎ足し、次いで、図16に示すように、上記鋼
管10の上端部に次の鋼管10′を継ぎ足す。この状態
において、上記サポート鋼管40′の上端部は鋼管1
0′から所定長さだけ上方に突出している。
(5) Next, after the steel pipe 10 is pushed into a predetermined depth, the upper supporting mechanism 70 (the pushing transmission member 7) is pressed.
1, the tension member 72, the jack 73 and the support steel pipe support mechanism 74) are removed, and then, as shown in FIG.
The next support steel pipe 4 is provided at the upper end of the support steel pipe 40.
0 'is added, and then the next steel pipe 10' is added to the upper end of the steel pipe 10 as shown in FIG. In this state, the upper end of the support steel pipe 40 'is
0 'protrudes upward by a predetermined length.

【0047】次に、図17に示すように、鋼管10′の
上端に再び上記上部支持機構70を設置して、上記
(4)と同様にして掘削部32によって掘削を行いなが
ら鋼管10を押し込み(図18)、さらに、上記(5)
と同様にしてサポート鋼管40、鋼管10を継ぎ足す工
程を順次繰り返すことによって、所定本数の鋼管10を
上下に連ねて押し込む(図19)。その後、上記サポー
ト鋼管支持機構74によって、サポート鋼管40を引き
上げることにより上記掘削機30Aを引き上げ(図2
0)、サポート鋼管40の繋ぎ目がサポート鋼管支持機
構74の上方に達したら、繋ぎ目を解体して上方のサポ
ート鋼管40を撤去する(図21)。さらに、引き続き
掘削機30Aを引き上げ、順次サポート鋼管40を撤去
する。
Next, as shown in FIG. 17, the upper support mechanism 70 is installed again at the upper end of the steel pipe 10 ', and the steel pipe 10 is pushed in while being excavated by the excavation section 32 in the same manner as (4). (FIG. 18) and the above (5)
By repeating the process of adding the support steel pipes 40 and the steel pipes 10 in the same manner as described above, a predetermined number of the steel pipes 10 are continuously pushed up and down (FIG. 19). Thereafter, the excavator 30A is raised by raising the support steel pipe 40 by the support steel pipe support mechanism 74 (FIG. 2).
0) When the joint of the support steel pipe 40 reaches above the support steel pipe support mechanism 74, the joint is disassembled and the upper support steel pipe 40 is removed (FIG. 21). Further, the excavator 30A is continuously raised, and the support steel pipes 40 are sequentially removed.

【0048】そして、繋いであるサポート鋼管40の全
ての解体撤去が完了し、掘削機30Aが最上部に達した
ら(図22)、掘削機30Aと上部支持機構70を一体
物として撤去し(図23)、これらを次の鋼管杭また
は、掘削機の仮置場(図示せず)に移動させる。その
後、強度などの観点から内部にコンクリートなどの充填
が必要な場合、上記鋼管10内にトレミー管(図示せ
ず)を設置して、図24に示すように、鋼管10内にコ
ンクリートKを打設する。なお、図示は省略してある
が、必要に応じ鋼管10の内部には鉄筋を設けてもよ
い。
When the disassembly and removal of all the supporting steel pipes 40 to be connected are completed and the excavator 30A reaches the uppermost position (FIG. 22), the excavator 30A and the upper support mechanism 70 are removed as an integral unit (FIG. 22). 23), move them to the next steel pipe pile or temporary storage (not shown) of the excavator. Thereafter, when the inside needs to be filled with concrete or the like from the viewpoint of strength or the like, a tremy pipe (not shown) is installed in the steel pipe 10, and concrete K is poured into the steel pipe 10 as shown in FIG. Set up. Although not shown, a reinforcing bar may be provided inside the steel pipe 10 as necessary.

【0049】しかして、上記掘削機30Aを備えた掘削
装置30Bおよびこれを使用して鋼管杭を施工する方法
によれば、以下のような効果を得ることができる。鋼
管10内を掘削機30Aによって掘削しつつ鋼管10を
押し込むようにしたので、沈設すべき鋼管の口径が大き
くなっても、従来のハンマー打設または振動による打設
の場合のように、掘削機自体が大型化することなく、し
かも、振動・騒音等も殆どなく、都市部での施工が可能
になる。 サポート鋼管40と鋼管10を継ぎ足しな
がら施工するとともに、上部支持機構70によってサポ
ート鋼管40と鋼管10を下方に押し込む力を確実に得
ることができるので、施工深度が深くなっても容易かつ
確実に施工することができる。
According to the excavator 30B having the excavator 30A and the method of constructing a steel pipe pile using the excavator 30B, the following effects can be obtained. Since the steel pipe 10 is pushed in while excavating the inside of the steel pipe 10 by the excavator 30A, even if the diameter of the steel pipe to be laid is increased, the excavator is driven as in the conventional hammer driving or vibration driving. The construction itself can be performed in an urban area without increasing the size of the apparatus itself and with little vibration or noise. The construction is performed while the support steel pipe 40 and the steel pipe 10 are added together, and the force for pushing the support steel pipe 40 and the steel pipe 10 downward can be reliably obtained by the upper support mechanism 70. Therefore, even when the construction depth is deep, the application is easily and reliably performed . Can be engineered.

【0050】サポート鋼管40と鋼管10を継ぎ足し
ながら施工するとともに、最初の鋼管10を沈設する際
に、上部支持機構70によって鋼管10の下端部を所定
の深さまで押し込むようにしたので、鋼管の転倒などの
危険性を回避することができる。 上部支持機構70によって掘削機30Aの鋼管内の上
下方向の位置を自由に調節することができるので、掘削
すべき地盤が軟弱でも硬くても、鋼管杭の施工に最適な
位置での掘削を容易に実現することができる。特に、通
常の方法では掘削の難しい土丹層などにおいては、鋼管
10の押込みを停止してサポート鋼管40によって掘削
機30Aのみを押し下げながら掘削する、すなわち予掘
を行うことができるので、鋼管10の沈設を容易に行う
ことができる。さらに、必要に応じて上記予掘の際にお
いて、掘削部32の掘削ヘッド51が鋼管10の底部よ
り下方に達した際に、該鋼管10の下部を、鋼管10の
径方向外側まで掘削するようにしたので、さらに容易に
鋼管10の沈設を行うことができる。
When the first steel pipe 10 is laid down, the lower end of the steel pipe 10 is pushed down to a predetermined depth by the upper support mechanism 70, so that the steel pipe 10 is overturned. Such dangers can be avoided. The vertical position of the excavator 30A in the steel pipe can be freely adjusted by the upper support mechanism 70, so that excavation at an optimum position for the construction of the steel pipe pile is easy even if the ground to be excavated is soft or hard. Can be realized. In particular, in the case of a soil layer or the like which is difficult to excavate in a normal method, the excavation can be performed while the pushing of the steel pipe 10 is stopped and only the excavator 30A is pushed down by the support steel pipe 40, that is, pre-digging can be performed. Can be easily installed. Further, if necessary, when the excavation head 51 of the excavation part 32 reaches below the bottom of the steel pipe 10 during the pre-digging, the lower part of the steel pipe 10 is excavated to the radial outside of the steel pipe 10. Therefore, the steel pipe 10 can be more easily laid down.

【0051】掘削部32の掘削アームに下端部が取り
付けられて地盤上に延びる土砂輸送パイプ65aによっ
て、掘削土砂を流体輸送するので、掘削深度が深くなっ
ても施工時間の大幅な増加がない。 鋼管10内に泥水注入用パイプ65bから泥水を入
れ、常に掘削面の圧力よりも泥水の水圧を高く保つよう
に、泥水の水面を高く保つようにしたので、地山の崩壊
を防止し、確実な施工を行うことができる。
Since the excavated soil is fluid-transported by the excavated arm of the excavated portion 32, the excavated arm is provided with a lower end portion and the excavated earth transport pipe 65a extends on the ground. Therefore, even if the excavation depth becomes deep, the construction time is not greatly increased. The muddy water is introduced from the muddy water injection pipe 65b into the steel pipe 10, and the muddy water surface is kept high so as to always keep the muddy water pressure higher than the excavated surface pressure. Construction can be performed.

【0052】図25ないし図28は、本発明に係る鋼管
杭用掘削機の第二実施例を示している。この鋼管杭用掘
削機30Cは、先の鋼管杭用掘削機30Aと同様、フレ
ーム31の下部に掘削部32を備えて成るものである
が、フレーム31および掘削部32の構成が上記掘削機
30Aとは異なっている。
FIGS. 25 to 28 show a second embodiment of a steel pipe pile excavator according to the present invention. This excavator 30C for steel pipe piles is provided with an excavation part 32 at the lower part of a frame 31 similarly to the excavator 30A for steel pipe piles, and the configuration of the frame 31 and the excavation part 32 is the same as that of the excavator 30A. Is different from

【0053】この鋼管杭用掘削機(以下、「掘削機」と
略称する)30Cのフレーム31′は、概略的には、上
記掘削機30Aの上記フレーム31における上記上リン
グ33のみを有した形態となっている。なお、上記掘削
機30Aと同じ構成要素には同一符号を付してある。ま
た、このフレーム31′もサポート鋼管40を介して上
方から懸吊支持されたものとなっている。
The frame 31 'of the steel pipe pile excavator (hereinafter, abbreviated as "excavator") 30C is generally configured to have only the upper ring 33 in the frame 31 of the excavator 30A. It has become. The same components as those of the excavator 30A are denoted by the same reference numerals. This frame 31 'is also suspended and supported from above via a support steel pipe 40.

【0054】上記フレーム31′の下部には、軸受部8
0を介して掘削部81が回転自在に設けられている。こ
の掘削部81は図26に示すように、上記軸受部80に
よって回転自在に支持された円筒状の回転体81aと、
この回転体81aの下端部に設けられて、外側に向けて
水平方向に延びる十字形の4本の掘削シャフト82…と
を主体として構成されており(図28)、これら掘削シ
ャフト82…にはそれぞれ多数のビット82aが設けら
れている。また、これら4本の掘削シャフト82は上記
回転体81aとともに鉛直軸回りに回転するようになっ
ている。さらに、これら4本の掘削シャフト82は、通
常は図26に示すように鋼管10の内径より多少短くな
っているが、そのうち対向位置にある2本の掘削シャフ
ト82′,82′は図27および図28に示すように、
その先端部82b,82bが伸張し、鋼管10の外径よ
りも外方に突出できる構成となっている。
At the lower part of the frame 31 ', a bearing portion 8 is provided.
The excavation part 81 is rotatably provided through the “0”. As shown in FIG. 26, the excavation portion 81 includes a cylindrical rotating body 81a rotatably supported by the bearing portion 80,
It is provided at the lower end of the rotating body 81a and mainly includes four cross-shaped excavating shafts 82 extending horizontally outward (FIG. 28). Each of them has a number of bits 82a. Further, these four excavating shafts 82 rotate around a vertical axis together with the rotating body 81a. Further, these four excavation shafts 82 are usually slightly shorter than the inner diameter of the steel pipe 10 as shown in FIG. 26, and the two excavation shafts 82 'and 82' at the opposing positions are shown in FIGS. As shown in FIG.
The distal ends 82b, 82b are configured to extend and protrude outward from the outer diameter of the steel pipe 10.

【0055】そして、予掘が必要な場合において、掘削
機30Cの掘削シャフト82…が鋼管10の底部より下
方に達した時点で必要なら、先端部82b,82bを伸
張させて、鋼管10の外径よりも外方に突出させ、さら
に掘削を行い鋼管10の下部を、該鋼管10の径方向外
側まで掘削する。
When pre-digging is necessary, if the excavating shaft 82 of the excavator 30C reaches below the bottom of the steel pipe 10, if necessary, the tips 82b, 82b are extended to extend the The lower part of the steel pipe 10 is excavated to the outside in the radial direction of the steel pipe 10 by projecting outward from the diameter.

【0056】また、この掘削装置30Cにおける土砂輸
送パイプ65aは、図26に示すように、上記サポート
鋼管40の内部を通して配設され、掘削シャフト82…
の上方で複数の管路65c…に分岐され、掘削シャフト
82…に沿った位置に複数開口したものとなっている。
このように、土砂の取込み口を掘削シャフト82…に沿
って複数かつ、それぞれ中心点からの距離を変化させて
設けることにより、該取込み口は掘削シャフト82…の
回転とともに、円軌道を描いて移動し、土砂を全面的に
吸い込むことができる。なお符号83はシーベルジョイ
ントであり、これによって掘削シャフト82が回転して
も上記土砂輸送パイプ65aにねじれ等の影響がないよ
うになっている。
Further, as shown in FIG. 26, the earth and sand transport pipe 65a in the excavator 30C is disposed through the inside of the support steel pipe 40, and the excavation shafts 82.
Are branched into a plurality of conduits 65c... At the positions along the excavating shafts 82.
In this manner, by providing a plurality of earth and sand intake ports along the excavation shafts 82 and changing the distances from the respective center points, the intake ports draw circular orbits with the rotation of the excavation shafts 82. It can move and suck in all the earth and sand. Reference numeral 83 denotes a seabel joint, which prevents the earth and sand transport pipe 65a from being twisted or the like even when the excavating shaft 82 rotates.

【0057】さらに、上記フレーム31′の上面には、
図25ないし図27に示すように、上記掘削機30Aと
同様の構成の4本のジャッキ部63…がそれぞれ固定部
材85…によって周方向に等間隔で設けられている。こ
のジャッキ部63は、伸縮アーム63aを伸張すること
によって車輪64を鋼管10の内壁に当接して上記掘削
機30Cの鋼管10内の径方向における位置決めを行う
とともに、該掘削機30Cを昇降させる際に鋼管10の
内壁を転動して掘削機30Cの昇降をガイドするための
ものである。また、上記フレーム31′の上面中央部に
は、ジャッキ部63…の反力を受けるための反力受材8
6…が固定されている。なお、この実施例ではジャッキ
部63を4本設けたが、これに限ることなく少なくとも
3本以上設ければよい。
Further, on the upper surface of the frame 31 ',
As shown in FIGS. 25 to 27, four jack portions 63 having the same configuration as that of the excavator 30A are provided at regular intervals in the circumferential direction by fixing members 85. The jack portion 63 extends the telescopic arm 63a so that the wheel 64 abuts against the inner wall of the steel pipe 10 to position the excavator 30C in the radial direction in the steel pipe 10, and to move the excavator 30C up and down. The inner wall of the steel pipe 10 is rolled to guide the excavator 30C up and down. A reaction force receiving member 8 for receiving a reaction force of the jacks 63 is provided at the center of the upper surface of the frame 31 '.
6 are fixed. Although four jacks 63 are provided in this embodiment, at least three or more jacks 63 may be provided.

【0058】また、上記フレーム31′の外周面には、
鋼管10の径方向外方に突出する伸縮アーム84aを有
した補助ジャッキ84が4本周方向に等間隔で設けられ
ている。これら補助ジャッキ84…は、鋼管10の内壁
に当接し、互いに突っ張り合うことにより上記フレーム
31′を支持して、掘削部81の回転反力によるフレー
ム31′の回転を防止するものである。このように、補
助ジャッキ84…を設け、さらに上記ジャッキ部63…
の車輪64…を鋼管10の内壁に当接させることによ
り、フレーム31′の回転を確実に防止することができ
る。
Further, on the outer peripheral surface of the frame 31 ',
Four auxiliary jacks 84 having telescopic arms 84a projecting radially outward of the steel pipe 10 are provided at equal intervals in the circumferential direction. These auxiliary jacks 84 abut against the inner wall of the steel pipe 10 and support the frame 31 ′ by abutting against each other to prevent the rotation of the frame 31 ′ due to the rotational reaction force of the excavation section 81. Thus, the auxiliary jacks 84 are provided, and the jack portions 63 are further provided.
Are brought into contact with the inner wall of the steel pipe 10, whereby the rotation of the frame 31 'can be reliably prevented.

【0059】なお、上記掘削機30Cは、上記掘削機3
0Aと同様に、サポート鋼管40によって懸吊支持さ
れ、さらにこのサポート鋼管40が上記上部支持機構7
0によって支持されて、さらに動力基地D、土砂分離プ
ラントPが設けられて全体として掘削装置を構成する。
The excavator 30C is provided with the excavator 3
0A, the supporting steel pipe 40 is suspended and supported by the supporting steel pipe 40.
0, and a power base D and a sediment separation plant P are further provided to constitute a drilling rig as a whole.

【0060】上記掘削機30Cを備えた掘削装置によっ
て鋼管杭を施工する施工要領は、上記掘削装置30Aの
場合とほぼ同様である。この掘削機30Cによれば、い
わゆるシールド掘進機のカッターと同様に掘削面を一様
に掘削するため、上記掘削機30Aよりもさらに掘削に
かかる時間を大幅に短縮することができる。シャフト8
2の回転による反力は、ジャッキ部63の車輪64を鋼
管10の内壁に圧接することにより、および上記補助ジ
ャッキ64を作動させてその先端部を鋼管10の内壁に
圧接させることにより支持することができる。
The procedure for constructing the steel pipe pile by the excavator equipped with the excavator 30C is almost the same as that of the excavator 30A. According to the excavator 30C, since the excavation surface is uniformly excavated similarly to the cutter of a so-called shield excavator, the time required for excavation can be significantly reduced as compared with the excavator 30A. Shaft 8
The reaction force due to the rotation of 2 is supported by pressing the wheel 64 of the jack part 63 against the inner wall of the steel pipe 10 and by operating the auxiliary jack 64 to press the tip part against the inner wall of the steel pipe 10. Can be.

【0061】また、シャフト82′,82′の先端部8
2a,82aを突出させることにより鋼管10の下方を
鋼管10の外径よりも大きく予掘することができる。こ
れにより、鋼管10の周辺摩擦力を大幅に低減でき、鋼
管10の沈設を容易にできる。その際、先端部82a,
82aを伸張させた状態ではシャフト82′,82′に
掘削ビット81が存在しない部分が生ずるが、その部分
については固定された他方のシャフト82,82の掘削
ビット81が掘削するため掘り残しはない。なお、上述
した掘削機30Aを用いた場合による効果を得ることが
できるのは言うまでもない。
Further, the tip portions 8 of the shafts 82 ', 82'
By protruding the 2a and 82a, a portion below the steel pipe 10 can be pre-drilled larger than the outer diameter of the steel pipe 10. Thereby, the peripheral frictional force of the steel pipe 10 can be significantly reduced, and the steel pipe 10 can be easily laid down. At that time, the tip portions 82a,
In the state where 82a is extended, there is a portion where the excavation bit 81 does not exist on the shafts 82 'and 82'. However, since the excavation bit 81 of the other fixed shafts 82 and 82 excavates the portion, no excavation remains. . Needless to say, the effect obtained by using the excavator 30A described above can be obtained.

【0062】さらに、上記実施例では、鋼管10を沈設
する場合、鋼管10に押込み力伝達部材71を載置し、
該押込み力伝達部材71に引張部材72を取り付け、該
引張部材72にPCジャッキ73に緊張力を導入して、
押込み力伝達部材71を下方に押圧することによって行
ったが、この他、例えば図29に示すように、押込み力
伝達部材10の上方に反力受鋼材87を配設し、これら
押込み力伝達部材71と反力受鋼材87との間に押込用
ジャッキ88…を設け、さらに反力受鋼材87に下方へ
の力を得るためにPC鋼線89等によりアンカーを取る
ことによって行ってもよい。なお、反力受鋼材87はジ
ャッキ盛り代え時点で下に落ちないように図示していな
いが鋼材等によりサポートSを行っておく。そして、鋼
管10の押込みはジャッキ88が伸びきった時点でジャ
ッキ88を縮め、ジャッキ88の縮んだ分の長さの鋼管
10をセットし、再度ジャッキ88で鋼管10を押し込
むことにより行う。なお、鋼管10はジョイント用ソケ
ット90等を使用すれば簡単に取り付けることができ
る。
Further, in the above embodiment, when the steel pipe 10 is laid, the pushing force transmitting member 71 is placed on the steel pipe 10,
A tension member 72 is attached to the pushing force transmission member 71, and a tension is applied to the PC jack 73 to the tension member 72,
The pressing force transmitting member 71 was pressed downward, but the reaction force receiving member 87 was disposed above the pressing force transmitting member 10 as shown in FIG. 29, for example. A push-in jack 88 may be provided between the base member 71 and the reaction force receiving steel material 87, and the reaction force receiving steel material 87 may be anchored with a PC steel wire 89 or the like in order to obtain a downward force. Note that the reaction force receiving steel material 87 is not shown so as to not fall down when the jack is replaced, but the support S is performed by a steel material or the like. The pushing of the steel pipe 10 is performed by shrinking the jack 88 when the jack 88 is completely extended, setting the steel pipe 10 having a length corresponding to the contracted length of the jack 88, and pushing the steel pipe 10 by the jack 88 again. The steel pipe 10 can be easily attached by using a joint socket 90 or the like.

【0063】[0063]

【発明の効果】以上説明したように、この発明の請求項
1の鋼管杭用掘削装置によれば、フレームに掘削アーム
が首振り揺動自在に支持され、この掘削アームの先端部
に掘削ヘッドが設けられているので、鋼管内の全面を容
易かつ確実に掘削することができる。また掘削機自体が
鋼管内に挿入できる大きさに構成されているので、沈設
すべき鋼管の口径が大きくなっても、従来のハンマー打
設または振動による打設の場合のように、掘削機自体が
大型化することなく、しかも、振動・騒音等も殆どな
く、都市部での施工が可能になる。また、掘削アームが
首振り揺動するので、掘削ヘッドによって鋼管の下部
を、鋼管の径方向外側まで掘削することができる。さら
に、ジャッキ部のストロークを適宜調整することによっ
て掘削機の鋼管径方向の位置ぎめを容易かつ正確に行う
ことができるとともに、該ジャッキ部の車輪が鋼管の内
壁に上下に移動自在に当接するので掘削機自体の昇降を
スムーズに行うことができる。また、懸吊支持部材を押
込み力伝達材に設けられた懸吊支持部材支持機構により
支持して昇降させるから、この懸吊支持部材の昇降に際
しては、懸吊支持部材を鋼管上方の定位置で支持するこ
ととなる。よって、掘削機を確実に支持した状態で掘削
作業ができ、正確な掘削作業が行える。
As described in the foregoing, according to the steel pipe piles for drilling device according to claim 1 of the present invention, drilling arm frame is supported in a freely swinging swing, drilling head to the tip of the excavating arm Is provided, so that the entire surface inside the steel pipe can be easily and reliably excavated. Also, since the excavator itself is configured to have a size that can be inserted into the steel pipe, even if the diameter of the steel pipe to be submerged becomes large, the Can be constructed in an urban area without increasing the size and with almost no vibration and noise. Further, since the excavation arm swings and swings, the lower portion of the steel pipe can be excavated by the excavation head to the outside in the radial direction of the steel pipe. Further, by appropriately adjusting the stroke of the jack portion, it is possible to easily and accurately position the excavator in the radial direction of the steel pipe, and the wheel of the jack portion comes into contact with the inner wall of the steel pipe movably up and down. The excavator itself can be moved up and down smoothly. Also, press the suspension support member.
By the suspension support member support mechanism provided on the
Because it is supported and raised and lowered,
For this purpose, support the suspension support member at a fixed position above the steel pipe.
And Therefore, excavation is performed with the excavator securely supported.
Work can be performed and accurate excavation work can be performed.

【0064】また、掘削アームを外筒とこの外筒内に回
転自在に設けられた回転軸とから構成し、回転軸に掘削
ヘッドを設けるとともに外筒に回転軸を回転させ回転駆
動部を設けたので、掘削アームの首振り揺動と掘削ヘッ
ドの回転とを容易に実現することができる。
[0064] Further, it consists of the drilling arm and the outer cylinder and rotatably provided rotation axis to the outer tube, provided with a rotation driving unit to rotate the rotary shaft to the outer cylinder provided with a drilling head to the rotating shaft Therefore, swinging of the excavation arm and swinging of the excavation head can be easily realized.

【0065】また、上部支持機構によって掘削機の鋼管
内の上下方向の位置を自由に調節することができるの
で、掘削すべき地盤が軟弱でも硬くても、鋼管杭の施工
に最適な位置での掘削を容易に実現することができる。
特に、通常の方法では掘削の難しい土丹層などにおいて
は、鋼管の押込みを停止してサポート鋼管によって掘削
機のみを押し下げながら掘削する、すなわち予掘を行う
ことができるので、鋼管の周辺摩擦力を大幅に低減で
き、よって鋼管の沈設を容易に行うことができる。
The steel pipe of the excavator is provided by the upper support mechanism.
You can freely adjust the vertical position inside
Even if the ground to be excavated is soft or hard,
Excavation at an optimal position can be easily realized.
Especially in the soil layer where it is difficult to drill
Stop pushing steel pipe and drill by support steel pipe
Excavation while pushing down only the machine, that is, pre-digging
Can greatly reduce the frictional force around the steel pipe.
Therefore, the steel pipe can be easily laid down.

【0066】請求項2の鋼管杭用掘削装置によれば、掘
削部を、いわゆるシールド掘進機のカッターと同様に、
回転体と複数の掘削シャフトとから構成したので、掘削
面を一様に掘削することができ、上記請求項1の掘削装
置よりもさらに掘削にかかる時間を大幅に短縮すること
ができる。また、掘削シャフトの一部を鋼管の径方向に
伸縮自在に構成したので、該シャフトの一部を鋼管の外
側に突出させることにより、鋼管の径方向外側まで掘削
することができる。さらに、ジャッキ部のストロークを
適宜調整することによって掘削機の鋼管径方向の位置ぎ
めを容易かつ正確に行うことができるとともに、該ジャ
ッキ部が鋼管の内壁に上下に移動自在に当接するので掘
削機自体の昇降をスムーズに行うことができる。
According to the drilling device for steel pipe piles of the second aspect,
Like the so-called shield excavator cutter,
Since it is composed of a rotating body and multiple drilling shafts,
The drilling device according to claim 1, wherein the surface can be dug uniformly.
Drastically reduce the time required for excavation
Can be. Also, a part of the drilling shaft is
Because it is telescopic, a part of the shaft is outside the steel pipe.
Excavation to the outside in the radial direction of the steel pipe by projecting to the side
can do. In addition, the stroke of the jack
Adjust the position of the excavator in the radial direction of the steel pipe by making appropriate adjustments.
Can be performed easily and accurately, and
Dig because the hook abuts the inner wall of the steel pipe so that it can move up and down
The cutter itself can be moved up and down smoothly.

【0067】また、懸吊支持部材を押込み力伝達材に設
けられた懸吊支持部材支持機構により支持して昇降させ
るから、この懸吊支持部材の昇降に際しては、懸吊支持
部材を鋼管上方の定位置で支持することとなる。よっ
て、掘削機を確実に支持した状態で掘削作業ができ、正
確な掘削作業が行える。また、上部支持機構によって掘
削機の鋼管内の上下方向の位置を自由に調節することが
できるので、掘削すべき地盤が軟弱でも硬くても、鋼管
杭の施工に最適な位置での掘削を容易に実現することが
できる。特に、通常の方法では掘削の難しい土丹層など
においては、鋼管の押込みを停止してサポート鋼管によ
って掘削機のみを押し下げながら掘削する、すなわち予
掘を行うことができるので、鋼管の周辺摩擦力を大幅に
低減でき、よって鋼管の沈設を容易に行うことができ
る。
Further , the suspension support member is provided on the pushing force transmitting member.
Supported by the suspended support member support mechanism
Therefore, when raising and lowering the suspension support member,
The member will be supported at a fixed position above the steel pipe. Yo
Drilling work with the excavator securely supported.
Excavation work can be performed reliably. It is also excavated by the upper support mechanism.
It is possible to freely adjust the vertical position within the steel pipe of the milling machine.
It is possible to use steel pipes even if the ground to be excavated is soft or hard.
Easy excavation at the optimal position for pile construction
it can. In particular, such as the Dotan layer, which is difficult to excavate with ordinary methods
, Stop pushing the steel pipe and
Drilling while pushing down the excavator only,
Drilling can significantly reduce the frictional force around the steel pipe
And the steel pipe can be laid down easily.
You.

【0068】請求項の鋼管杭の施工方法によれば、鋼
管内を掘削機によって掘削しつつ鋼管を押し込むように
したので、沈設すべき鋼管の口径が大きくなっても、従
来のハンマー打設または振動による打設の場合のよう
に、振動・騒音等も殆どなく、都市部での施工が可能に
なる。また、サポート鋼管と鋼管を継ぎ足しながら施工
するとともに、上部支持機構によってサポート鋼管と鋼
管を下方に押し込む力を確実に得ることができるので、
施工深度が深くなっても容易かつ確実に施工することが
できる。さらに、サポート鋼管と鋼管を継ぎ足しながら
施工するとともに、最初の鋼管を沈設する際に、上部支
持機構によって鋼管の下端部を所定の深さまで押し込む
ようにしたので、鋼管の転倒などの危険性を回避するこ
とができる。
According to the method for constructing a steel pipe pile according to the third aspect, since the steel pipe is pushed in while excavating the inside of the steel pipe by the excavator, the conventional hammer driving method can be performed even if the diameter of the steel pipe to be submerged becomes large. Or, as in the case of casting by vibration, there is almost no vibration or noise, and construction in an urban area is possible. In addition, since the construction is performed while adding the support steel pipe and the steel pipe, the force for pushing the support steel pipe and the steel pipe downward by the upper support mechanism can be reliably obtained.
Even if the construction depth becomes deep, construction can be performed easily and reliably. In addition, construction is performed while adding the support steel pipe and the steel pipe, and the lower end of the steel pipe is pushed down to a predetermined depth by the upper support mechanism when the first steel pipe is sunk, avoiding the danger of falling down of the steel pipe can do.

【0069】請求項の鋼管杭の施工方法によれば、地
盤が硬く予掘が必要となった際に、鋼管の押込みを停止
して掘削機のみを押し下げながら予掘を行うようにした
ので、鋼管の周辺摩擦力を大幅に低減でき、よって地盤
が硬い場合でも鋼管の沈設を容易に行うことができる。
[0069] According to the construction method of the steel pipe pile according to claim 4, when the ground is needed is hard予掘, since to perform予掘while pressing down only excavator to stop pushing the steel pipe In addition, the peripheral frictional force of the steel pipe can be greatly reduced, so that the steel pipe can be easily laid down even when the ground is hard.

【0070】請求項の鋼管杭の施工方法によれば、鋼
管杭用掘削機の掘削部が鋼管の底部より下方に達した際
に、該鋼管の下部を、鋼管の径方向外側まで掘削するよ
うにしたので、さらに鋼管の沈降を容易に行うことがで
きる。
According to the method for constructing a steel pipe pile according to the fifth aspect , when the excavated portion of the excavator for a steel pipe pile reaches below the bottom of the steel pipe, the lower part of the steel pipe is excavated to the outside in the radial direction of the steel pipe. As a result, the steel pipe can be easily settled.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の鋼管杭用掘削機の一実施例を示す縦断
面図である。
FIG. 1 is a longitudinal sectional view showing one embodiment of an excavator for steel pipe piles of the present invention.

【図2】図1におけるBーB線視断面図である。FIG. 2 is a sectional view taken along line BB in FIG.

【図3】一実施例の掘削機の揺動機構を示す縦断面図で
ある。
FIG. 3 is a longitudinal sectional view showing a swinging mechanism of the excavator according to the embodiment.

【図4】図3におけるCーC線視図である。FIG. 4 is a view taken along the line CC in FIG. 3;

【図5】図3におけるDーD線視断面図である。FIG. 5 is a sectional view taken along line DD in FIG. 3;

【図6】一実施例の掘削機を備えた掘削装置を示す断面
図である。
FIG. 6 is a cross-sectional view showing a drilling device provided with an excavator according to one embodiment.

【図7】一実施例の掘削機を備えた掘削装置の要部を示
す断面図である。
FIG. 7 is a cross-sectional view illustrating a main part of an excavator equipped with an excavator according to one embodiment.

【図8】図7におけるEーE線視断面図である。8 is a sectional view taken along line EE in FIG. 7;

【図9】地盤が硬い場合と軟弱な場合における掘削機の
位置を示す縦断面図である。
FIG. 9 is a longitudinal sectional view showing positions of the excavator when the ground is hard and when the ground is soft.

【図10】鋼管を地盤に載置した状態を示す縦断面図で
ある。
FIG. 10 is a longitudinal sectional view showing a state where a steel pipe is placed on the ground.

【図11】鋼管の下端部を地盤に押し込んだ状態を示す
縦断面図である。
FIG. 11 is a longitudinal sectional view showing a state where the lower end of the steel pipe is pushed into the ground.

【図12】鋼管内に掘削機をセットした状態を示す縦断
面図である。
FIG. 12 is a longitudinal sectional view showing a state where an excavator is set in a steel pipe.

【図13】掘削機によって掘削をしている状態を示す縦
断面図である。
FIG. 13 is a longitudinal sectional view showing a state where the excavator is excavating.

【図14】1本目の鋼管を沈設し終えた状態を示す縦断
面図である。
FIG. 14 is a longitudinal sectional view showing a state where the first steel pipe has been laid down.

【図15】サポート鋼管を継ぎ足した状態を示す縦断面
図である。
FIG. 15 is a longitudinal sectional view showing a state where a support steel pipe is added.

【図16】鋼管を継ぎ足した状態を示す縦断面図であ
る。
FIG. 16 is a longitudinal sectional view showing a state where steel pipes are added.

【図17】再び上部支持機構をセットした状態を示す縦
断面図である。
FIG. 17 is a longitudinal sectional view showing a state where the upper support mechanism is set again.

【図18】掘削機によって掘削をしている状態を示す縦
断面図である。
FIG. 18 is a longitudinal sectional view showing a state where the excavator is excavating.

【図19】3本目以降の鋼管を沈設し終えた状態を示す
縦断面図である。
FIG. 19 is a longitudinal sectional view showing a state where the third and subsequent steel pipes have been laid down.

【図20】掘削機を引き上げている状態を示す縦断面図
である。
FIG. 20 is a longitudinal sectional view showing a state where the excavator is raised.

【図21】サポート鋼管を解体・撤去している状態を示
す縦断面図である。
FIG. 21 is a longitudinal sectional view showing a state where a support steel pipe is being dismantled and removed.

【図22】掘削機を鋼管の最上部まで引き上げた状態を
示す縦断面図である。
FIG. 22 is a longitudinal sectional view showing a state where the excavator is pulled up to the uppermost part of the steel pipe.

【図23】所定本数の鋼管を沈設し終えた状態を示す縦
断面図である。
FIG. 23 is a longitudinal sectional view showing a state where a predetermined number of steel pipes have been laid down.

【図24】鋼管内にコンクリートを打設した状態を示す
縦断面図である。
FIG. 24 is a longitudinal sectional view showing a state in which concrete is poured into a steel pipe.

【図25】本発明の第二実施例の掘削機を示す横断面図
である。
FIG. 25 is a cross-sectional view showing an excavator according to a second embodiment of the present invention.

【図26】図25におけるFーF線視断面図である。26 is a sectional view taken along line FF in FIG. 25.

【図27】掘削シャフトを伸張した状態を示す掘削機の
縦断面図である。
FIG. 27 is a longitudinal sectional view of the excavator showing a state where the excavation shaft is extended.

【図28】図27におけるGーG線視断面図である。FIG. 28 is a sectional view taken along line GG in FIG. 27.

【図29】鋼管沈設の他の方法を説明するための鋼管上
部付近における縦断面図である。
FIG. 29 is a longitudinal sectional view in the vicinity of the upper portion of a steel pipe for explaining another method of depositing the steel pipe.

【符号の説明】[Explanation of symbols]

10 鋼管 30A,30C 鋼管杭用掘削機 30B 鋼管杭用掘削装置 31,31′ フレーム 32,81 掘削部 40,40′ サポート鋼管 45 回転駆動機構 48 掘削アーム 49 外筒 50 内筒(回転軸) 51 掘削ヘッド 52 球形膨出部 56 揺動機構 63 ジャッキ部 70 上部支持機構 74 サポート鋼管支持機構 81a 回転体 82,82′ 掘削シャフト Reference Signs List 10 steel pipe 30A, 30C steel pipe pile excavator 30B steel pipe pile excavator 31, 31 'frame 32, 81 excavator 40, 40' support steel pipe 45 rotation drive mechanism 48 excavation arm 49 outer cylinder 50 inner cylinder (rotating shaft) 51 Excavating head 52 Spherical bulging part 56 Swinging mechanism 63 Jack part 70 Upper supporting mechanism 74 Support steel pipe supporting mechanism 81a Rotating body 82, 82 'Excavating shaft

───────────────────────────────────────────────────── フロントページの続き (72)発明者 中川 健一 東京都港区芝浦一丁目2番3号 清水建 設株式会社内 (72)発明者 久保 裕之 東京都港区芝浦一丁目2番3号 清水建 設株式会社内 (56)参考文献 特開 平3−233019(JP,A) 特開 昭54−119705(JP,A) (58)調査した分野(Int.Cl.6,DB名) E02D 7/00 E21B 7/20 ──────────────────────────────────────────────────続 き Continuation of the front page (72) Inventor Kenichi Nakagawa 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation (72) Inventor Hiroyuki Kubo 1-2-3 Shibaura, Minato-ku, Tokyo Shimizu (56) References JP-A-3-233019 (JP, A) JP-A-54-119705 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E02D 7 / 00 E21B 7/20

Claims (5)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 鋼管杭用掘削機と、該掘削機を懸吊支持
する懸吊支持部材と、該懸吊支持部材を支持して昇降さ
せるとともに、鋼管を下方に押圧する上部支持機構とを
備えてなり、 上記鋼管杭用掘削機は、 鋼管の内部に挿入可能な大きさ
に構成され、長尺な懸吊支持部材を介して上方より懸吊
支持されるフレームと、該フレームに支持された掘削部
とを有し上記掘削部を、棒状をなし上記フレームに基
端部が首振り自在に支持された掘削アームと、この掘削
アームの下端部に設けられた掘削ヘッドとから構成し、
さらに、上記フレームに、上記掘削アームを首振り揺動
させる揺動機構と、上記鋼管の径方向に伸縮し、かつ該
鋼管の内壁に当接して上下に移動自在な車輪を有する
数のジャッキ部を設け、上記掘削アームを、上記フレー
ムに首振り自在に支持された円筒状の外筒と、この外筒
の内側に軸回りに回転自在に設けられた回転軸とから構
成し、該回転軸に上記掘削ヘッドを設けるとともに、上
記外筒に上記回転軸を回転駆動させる回転駆動機構を設
けてなり、 上記上部支持機構は、上記鋼管の上端面に配置される押
込み力伝達材、及び該押込み力伝達材を介して上記鋼管
を下方に押圧するジャッキを含む駆動機構と、上記押込
み力伝達材に設けられ、上記懸吊支持部材を支持して昇
降させる懸吊支持部材支持機構とを備えて構成されてい
ことを特徴とする鋼管杭用掘削装置
An excavator for a steel pipe pile and a suspended support for the excavator.
A suspending support member that supports the suspending support member and
And an upper support mechanism that presses the steel pipe downward.
The excavator for steel pipe piles is configured to have a size that can be inserted into a steel pipe, and is supported by the frame from a frame suspended from above through a long suspension support member, and supported by the frame. and a drilling unit, and consists of the excavation, and excavation arm having a base end portion to the frame without a rod is movably supported swing, and drilling head provided at the lower end of the excavating arm ,
Further, the frame has a swinging mechanism for swinging the excavating arm and a wheel that expands and contracts in the radial direction of the steel pipe and that can move up and down in contact with the inner wall of the steel pipe. > Provide the number of jacks and attach the excavating arm to the frame
A cylindrical outer cylinder supported swingably by the
And a rotating shaft provided rotatably around the axis inside the
And the drilling head is provided on the rotating shaft.
The outer cylinder is provided with a rotation drive mechanism for rotating the rotation shaft.
Only it becomes and, the upper support mechanism, push disposed on the upper end face of the steel tube
Pushing force transmitting member, and the steel pipe via the pushing force transmitting member
Drive mechanism including a jack for pressing the
Provided on the force transmitting member, supporting the suspension
And a suspension support member supporting mechanism for lowering
Steel pipe for drilling and wherein the that.
【請求項2】 鋼管杭用掘削機と、該掘削機を懸吊支持
する懸吊支持部材と、該懸吊支持部材を支持して昇降さ
せるとともに、鋼管を下方に押圧する上部支持機構とを
備えてなり、 上記鋼管杭用掘削機は、鋼管の内部に挿入可能な大きさ
に構成され、長尺な懸吊支持部材を介して上方より懸吊
支持されるフレームと、該フレームに支持された掘削部
とを有し、上記掘削部を、上記フレームに回転自在に支
持されて軸回りに回転する回転体と、この回転体から水
平に外方に延びる複数の棒状の掘削シャフトとから構成
するとともに、複数の掘削シャフトのうち一部のシャフ
トを上記鋼管の径方向に伸縮自在に構成し、さらに、上
記フレームに上記鋼管の径方向に伸縮し、かつ該鋼管の
内壁に当接して上下に移動自在な車輪を有する複数のジ
ャッキ部を設けてなり、 上記上部支持機構は、上記鋼管の上端面に配置される押
込み力伝達材、及び該押込み力伝達材を介して上記鋼管
を下方に押圧するジャッキを含む駆動機構と、上記押込
み力伝達材に設けられ、上記懸吊支持部材を支持して昇
降させる懸吊支持部材支持機構とを備えて構成されてい
ことを特徴とする鋼管杭用掘削装置
2. An excavator for a steel pipe pile, and a suspended support for the excavator.
A suspending support member that supports the suspending support member and
And an upper support mechanism that presses the steel pipe downward.
The excavator for steel pipe piles has a size that can be inserted inside the steel pipe.
And is suspended from above via a long suspension support member.
Frame supported and excavation supported by the frame
The excavating part is rotatably supported on the frame.
A rotating body that is held and rotates around an axis, and
Consists of a plurality of rod-shaped excavating shafts extending flat outward
And some of the shafts
The steel pipe is configured to be able to expand and contract in the radial direction of the steel pipe.
The frame expands and contracts in the radial direction of the steel pipe, and
A plurality of jigs having wheels that can move up and down in contact with the inner wall
A jack portion is provided, and the upper support mechanism is provided with a pusher disposed on an upper end surface of the steel pipe.
Pushing force transmitting member, and the steel pipe via the pushing force transmitting member
Drive mechanism including a jack for pressing the
Provided on the force transmitting member, supporting the suspension
And a suspension support member supporting mechanism for lowering
Steel pipe for drilling and wherein the that.
【請求項3】 鋼管杭を地盤に大深度まで設置する鋼管
杭の施工方法であって、下記の工程を備えることを特徴
とする鋼管杭の施工方法。 a.筒状をなす鋼管を地盤上に設置して、該鋼管の先端
部を所定深さまで押し込む工程。 b.上記請求項1又は2に記載の鋼管杭用掘削装置の鋼
管杭用掘削機を懸吊支持部材によって所定の深さまで降
ろして、該鋼管杭用掘削機を鋼管内の所定の位置にセッ
トする工程。 c.上記掘削機の掘削部によって掘削を行いながら鋼管
を押し込む工程。 d.上記鋼管を所定の深さまで押し込んだ後、上記鋼管
杭用掘削機を支持している懸吊支持部材の上端部に、次
の懸吊支持部材を継ぎ足すとともに上記鋼管の上端部に
次の鋼管を継ぎ足す工程。 e.上記d工程の後、c、dの工程を順次所定回数繰り
返すことにより、懸吊支持部材と鋼管を継ぎ足しながら
所定の数の鋼管を上下に連ねて押し込む工程。
3. A steel pipe in which a steel pipe pile is installed on the ground to a large depth.
A method for constructing a pile, comprising the following steps:
Steel pipe pile construction method. a. A tubular steel pipe is placed on the ground, and the tip of the steel pipe is
Pushing the part to a predetermined depth. b. The steel of the drilling rig for steel pipe piles according to claim 1 or 2.
The pipe pile excavator is lowered to a predetermined depth by the suspension support member.
And set the excavator for steel pipe pile at a predetermined position in the steel pipe.
Process. c. While excavating by the excavating part of the excavator,
Step of pushing. d. After pushing the steel pipe to a predetermined depth,
At the upper end of the suspension support member supporting the pile excavator,
Of the above steel pipe and
The process of adding the next steel pipe. e. After the step d, the steps c and d are sequentially repeated a predetermined number of times.
By returning, the suspension support member and steel pipe are added
A step of vertically pushing a predetermined number of steel pipes in a row.
【請求項4】 請求項3記載の鋼管杭の施工方法におい
て、掘削中に地盤が硬く予掘が必要となった際に、鋼管
の押し込みを停止して懸吊部材を下方に降下させながら
鋼管杭用掘削機を押し下げることを特徴とする鋼管杭の
施工方法。
4. A method for constructing a steel pipe pile according to claim 3.
When excavation is required due to the hard ground,
Stop pushing the suspension member down
Depressing excavator for steel pipe pile
Construction method.
【請求項5】 請求項4記載の鋼管杭の施工方法におい
て、鋼管杭用掘削機の掘削部が鋼管の底部より下方に達
した際に、該鋼管の下部を、鋼管の径方向外側まで掘削
することを特徴とする鋼管杭の施工方法。
5. The method for constructing a steel pipe pile according to claim 4.
The excavator of the steel pipe pile excavator reaches below the bottom of the steel pipe.
Excavated the lower part of the steel pipe to the outside in the radial direction of the steel pipe.
A method for constructing a steel pipe pile.
JP3293450A 1991-11-08 1991-11-08 Drilling equipment for steel pipe pile with excavator for steel pipe pile and construction method of steel pipe pile Expired - Fee Related JP2995430B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3293450A JP2995430B2 (en) 1991-11-08 1991-11-08 Drilling equipment for steel pipe pile with excavator for steel pipe pile and construction method of steel pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3293450A JP2995430B2 (en) 1991-11-08 1991-11-08 Drilling equipment for steel pipe pile with excavator for steel pipe pile and construction method of steel pipe pile

Publications (2)

Publication Number Publication Date
JPH05306518A JPH05306518A (en) 1993-11-19
JP2995430B2 true JP2995430B2 (en) 1999-12-27

Family

ID=17794923

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3293450A Expired - Fee Related JP2995430B2 (en) 1991-11-08 1991-11-08 Drilling equipment for steel pipe pile with excavator for steel pipe pile and construction method of steel pipe pile

Country Status (1)

Country Link
JP (1) JP2995430B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5450315B2 (en) * 2010-08-20 2014-03-26 株式会社東亜利根ボーリング Excavator tilt correction device
JP2013019251A (en) * 2011-07-14 2013-01-31 Sanwa Kiko Kk Method for excavating rock mass
JP6041768B2 (en) * 2013-08-07 2016-12-14 株式会社オーク Drilling rig
JP5462402B1 (en) * 2013-08-23 2014-04-02 株式会社オーク Drilling rig
CN112302081A (en) * 2020-11-16 2021-02-02 国网新疆电力有限公司克州供电公司 Automated equipment that rock foundation dug
CN117090254B (en) * 2023-10-20 2024-02-06 中国电建集团山东电力建设第一工程有限公司 Deep foundation pit inclined shaft excavation system and operation method thereof

Also Published As

Publication number Publication date
JPH05306518A (en) 1993-11-19

Similar Documents

Publication Publication Date Title
CN114855794B (en) Rock-socketed single pile construction method based on double-pile-casing pile-stabilizing platform
JP2008255603A (en) Driving method of inner excavation pile under low and narrow restriction
JP2995430B2 (en) Drilling equipment for steel pipe pile with excavator for steel pipe pile and construction method of steel pipe pile
JPS6319328A (en) Method and apparatus for constructing turning-penetrating type large-diameter steel tube
JP3996012B2 (en) Pile construction method and construction equipment
JP3151453B2 (en) Drilling rig for pipe burial
JP4831511B2 (en) Construction method of foundation pile
JP3426556B2 (en) Ground improvement device and ground improvement method
JP4074198B2 (en) How to remove existing piles
JP2003082663A (en) Pile driving equipment
JP4635725B2 (en) Pile construction system
JP3221895B2 (en) Construction method of large-diameter underground wall body and excavation equipment for burying pipes
JPH0941857A (en) Pile hole drilling method
JP2004324381A (en) Erection method with enlarged diameter part of precast pile, and enlarging excavating rod used for the same
KR100479514B1 (en) Apparatus for and a method of boring the ground
JPH1018744A (en) Rotary excavator
CN217734010U (en) Bearing diagonal construction equipment for foundation ditch
JPH11229740A (en) Subsoil excavation method and device
JP2003049424A (en) Construction method of composite pile, diameter enlarging device and inter-pile cutting device
JP3239950B2 (en) Pile press-in system and pile press-in method using the same
JP3648310B2 (en) Excavation method and apparatus
CN212561495U (en) Foundation reinforcing pile
JPH073049B2 (en) Construction method for steel pipe piles
JP2000248867A (en) Method and apparatus for manufacturing dry pillar body for base ground
JP2006028920A (en) Method of settling cylindrical precast concrete member, and apparatus for use therein

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990831

LAPS Cancellation because of no payment of annual fees