JP2935761B2 - Method and apparatus for re-installing steel frame - Google Patents

Method and apparatus for re-installing steel frame

Info

Publication number
JP2935761B2
JP2935761B2 JP18237391A JP18237391A JP2935761B2 JP 2935761 B2 JP2935761 B2 JP 2935761B2 JP 18237391 A JP18237391 A JP 18237391A JP 18237391 A JP18237391 A JP 18237391A JP 2935761 B2 JP2935761 B2 JP 2935761B2
Authority
JP
Japan
Prior art keywords
steel
steel column
steel frame
column
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP18237391A
Other languages
Japanese (ja)
Other versions
JPH0525942A (en
Inventor
達男 嶺
紀光 吉浜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP18237391A priority Critical patent/JP2935761B2/en
Publication of JPH0525942A publication Critical patent/JPH0525942A/en
Application granted granted Critical
Publication of JP2935761B2 publication Critical patent/JP2935761B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、鉄骨枠を地表におい
て組み立てて、既に組み上がった鉄骨構造体の上側に逐
次継ぎ足し高層化して鉄骨構造物を構築する工法に関
し、特に、鉄骨構造体の上側に継ぎ足される鉄骨枠の起
立姿勢を調整する鉄骨枠の建入れ直し方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of assembling a steel frame on the surface of the ground, successively adding the steel frame to an upper side of an already assembled steel structure, and forming a high-rise steel structure. The present invention relates to a method for re-installing a steel frame for adjusting a standing posture of a steel frame to be added to the steel frame.

【0002】[0002]

【従来の技術】鉄骨構造物が高層化するにつれて、使用
される鉄骨柱等の単体資材を地上から高所現場まで吊り
上げる揚重作業が多くなり、これに伴って工期も長大化
し、また危険度も増大する傾向にある。そこで、前記資
材の揚重作業を簡素化するために、地表において複数の
鉄骨柱や梁を前もって接合することでブロック化された
鉄骨枠を形成し、その鉄骨枠を高所現場までクレーンで
吊り上げて、既に組み上がった鉄骨構造体の上側へと継
ぎ足し逐次高層化して鉄骨構造物を構築する工法が採用
されている。
2. Description of the Related Art As a steel structure becomes higher in height, the lifting work for lifting a single material, such as a steel column, used from the ground to a high place is increased, and accordingly, the construction period is lengthened and the degree of danger is increased. Also tend to increase. Therefore, in order to simplify the lifting work of the material, a plurality of steel columns and beams are joined in advance on the ground surface to form a block-shaped steel frame, and the steel frame is lifted up to a high place by a crane. Therefore, a construction method is employed in which a steel structure is constructed by adding the steel structure already assembled to the upper side and successively increasing the height of the structure.

【0003】前記地組された鉄骨枠を、既に組み上がっ
ている鉄骨構造体の上側に継ぎ足す際に、従来は、地組
された鉄骨枠を地表から吊り上げ、その鉄骨枠下端に位
置する鉄骨柱の下端部を鉄骨構造体上部の鉄骨柱の上端
部に当てて、その上下に接続される鉄骨柱の端部側面に
夫々設けられているエレクションピースを連結して仮取
り付け(仮建込み)を実施し、さらに作業員が目視で確
認しながら鉄骨枠を吊っているクレーンを動かして該鉄
骨枠の起立姿勢を調整して建入れ直しを行い、続けて前
記エレクションピース間を固定する。
[0003] When the laid steel frame is added to the upper side of a steel structure already assembled, conventionally, the laid steel frame is lifted from the ground surface, and a steel frame located at the lower end of the steel frame is conventionally used. The lower end of the column is applied to the upper end of the steel column above the steel structure, and the erection pieces provided on the side of the end of the steel column connected above and below are connected and temporarily installed (temporary installation). Then, the worker moves the crane that suspends the steel frame while visually checking it, adjusts the standing posture of the steel frame, re-installs, and subsequently fixes the erection pieces.

【0004】そして、上下の鉄骨柱の当接部を溶着する
ことで鉄骨枠を接合した後、不要になったエレクション
ピースを切断する。
[0004] After the steel frames are joined by welding the contact portions of the upper and lower steel columns, unnecessary erection pieces are cut.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、鉄骨構
造物が高層になるにつれて上側に継ぎ足される鉄骨枠に
高度な精度の建入れが要求されるが、前記従来の建入れ
直し方法では、クレーンで吊り込まれた鉄骨枠が風など
によって揺れており、また、建入れ検査を目視で確認し
ているために、所定以上の建入れ精度を望むことができ
ないという問題がある。
However, as the height of the steel structure increases, it is required that the steel frame to be added to the upper side be installed with a high degree of precision. There is a problem in that the inserted steel frame is shaken by wind or the like, and the installation inspection is visually confirmed, so that it is not possible to expect an installation accuracy higher than a predetermined value.

【0006】特に、作業員が目視で確認しながら鉄骨構
造体の上側に継ぎ足し、上側の鉄骨枠の起立姿勢の傾き
の調整を該鉄骨枠の上部から吊り下げた重錘等によって
作業員が目視で確認しながら実施しているが、鉄骨枠全
体の起立姿勢をまとめてチェックしながら該鉄骨枠を二
方向以上から調整する必要があるために時間がかかり、
また、目視によって建入れ検査を実施しているため、前
記鉄骨枠の建入れ精度にばらつきがでるという問題があ
る。
[0006] In particular, while the worker visually confirms, he or she adds to the upper side of the steel frame structure, and adjusts the inclination of the standing posture of the upper steel frame by the weight suspended from the top of the steel frame. Although it is carried out while checking in, it takes time because it is necessary to adjust the steel frame from two or more directions while checking the standing posture of the entire steel frame collectively,
In addition, since the installation inspection is performed visually, there is a problem that the accuracy of the installation of the steel frame varies.

【0007】本発明は、前記のような問題点に着目して
なされたもので、上側に継ぎ足す鉄骨枠の建入れ精度を
上げると共に、その鉄骨枠の建入れ直しの調整作業を自
動化することを目的としている。
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems. It is an object of the present invention to improve the accuracy of setting the steel frame to be added to the upper side and to automate the work of adjusting the re-installation of the steel frame. The purpose is.

【0008】[0008]

【課題を解決するための手段】上記目的を達成するため
に、本発明の鉄骨枠の建入れ直し方法は、複数の鉄骨柱
や梁等によって地組された鉄骨枠を、既に組み上げられ
ている鉄骨構造体の上側に仮建込みを行い、その仮建込
みされた鉄骨枠を所定の起立姿勢に建入れ直しする方法
において、前記鉄骨枠を構成する複数の鉄骨柱のうちの
一本の鉄骨柱を基準鉄骨柱とみなし、その基準鉄骨柱に
対する目的とする起立姿勢からの傾斜方向や傾斜角度の
変位情報を検出することで、鉄骨枠を構成する複数の鉄
骨柱下端部によって形成される仮想的な平面の傾斜方向
及び傾斜角度を解析し、その解析情報をもとに、前記基
準鉄骨柱の下端部を支点とし、その基準鉄骨柱から相互
に異なる方向にある複数の鉄骨柱の下端部を、その鉄骨
柱の下部に設けられている各エレクションピースを介し
て所定量だけ駆動手段によって上下動させることで、前
記仮想的な平面の傾き具合を調整して鉄骨枠全体の起立
姿勢を調整することを特徴としている。
In order to achieve the above-mentioned object, a method for re-installing a steel frame according to the present invention is to provide a method for re-installing a steel frame which is erected by a plurality of steel columns, beams and the like. In the method of temporarily erection on the upper side of the structure and re-installing the tentatively erected steel frame to a predetermined standing posture, one steel column of the plurality of steel columns constituting the steel frame is Considering the reference steel column, by detecting the displacement information of the inclination direction and the inclination angle from the target standing posture with respect to the reference steel column, a virtual frame formed by a plurality of lower end portions of the steel frame constituting the steel frame is detected. Analyzing the inclination direction and inclination angle of the plane, based on the analysis information, with the lower end of the reference steel column as a fulcrum, the lower ends of a plurality of steel columns in mutually different directions from the reference steel column, At the bottom of the steel column By moving up and down by a predetermined amount the drive means via a respective erection piece it is, is characterized in that by adjusting the inclination degree of the virtual plane to adjust the vertical position of the entire steel frame.

【0009】また、前記鉄骨枠の建入れ直しに使用され
る装置としては、前記基準鉄骨柱から相互に異なる方向
に位置する複数の鉄骨柱の下部側面に設けられている各
エレクションピースを上下動する駆動手段と、前記基準
鉄骨柱の上部に取り付けられて側方に延設され該延設部
の下面に計測マークを有するターゲットと、前記基準鉄
骨柱の下端部と接合される鉄骨構造体の鉄骨柱上部若し
くはその近傍に設置されて受光軸を前記ターゲットの計
測マークに向けたカメラと、カメラに接続されて、該カ
メラからの画像信号を処理して前記計測マークの基準位
置に対する変位を求め、前記基準鉄骨柱の起立姿勢を判
断する画像処理装置と、画像処理装置に接続されて、該
画像処理装置からの信号により前記駆動装置を駆動して
前記鉄骨枠の各鉄骨柱下部側面のエレクションピースを
夫々所定量だけ上下動させる駆動制御装置とを備えたこ
とを特徴とする鉄骨枠の建入れ直し装置を使用するとよ
い。
Further, as an apparatus used for re-installing the steel frame, each erection piece provided on the lower side surface of a plurality of steel columns located in different directions from the reference steel column is vertically moved. Drive means, a target attached to the upper part of the reference steel column, extending laterally and having a measurement mark on the lower surface of the extension, and a steel frame of a steel structure joined to the lower end of the reference steel column A camera installed at the top of the pillar or in the vicinity thereof and having the light receiving axis directed toward the measurement mark of the target, connected to the camera, processing an image signal from the camera to determine a displacement of the measurement mark with respect to a reference position, An image processing device that determines the standing posture of the reference steel column; and an image processing device that is connected to the image processing device and drives the driving device based on a signal from the image processing device to drive each iron of the steel frame. Good to use the construction cycle device steel frame, characterized in that a drive control device for vertically moving the erection piece of the pillar lower side respectively by a predetermined amount.

【0010】[0010]

【作用】地組されてブロック化した鉄骨枠を、揚重機で
吊り込み、既に組み上げられた鉄骨構造体の上側に仮建
込みを実施する。仮建込みされた前記鉄骨枠を構成する
鉄骨柱のうちの一本に注目して基準鉄骨柱とみなしてそ
の基準鉄骨柱の起立姿勢を検出し、該基準鉄骨柱の下端
部を支点として相互に異なる方向、例えば互いに直交す
る方向にある2本の鉄骨柱を、該鉄骨柱に設けられてい
る各エレクションピースを介して所定量だけ上下動さ
せ、もって前記基準鉄骨柱の起立姿勢を目的とする姿勢
に調整することにより鉄骨枠全体の起立姿勢を調整す
る。
[Function] A steel frame which has been ground and blocked is suspended by a lifting machine, and temporary construction is carried out above a steel structure already assembled. Focusing on one of the steel columns constituting the temporarily built steel frame, it is regarded as a reference steel column, and the standing posture of the reference steel column is detected. In two different directions, for example, two steel columns in directions perpendicular to each other, up and down by a predetermined amount via each erection piece provided in the steel column, thereby aiming at the standing posture of the reference steel column The standing posture of the entire steel frame is adjusted by adjusting the standing posture.

【0011】なお、前記基準鉄骨柱の起立姿勢を調整す
ることにより鉄骨枠全体の起立姿勢を調整しているが、
これは、鉄骨枠を構成する鉄骨柱のうちの一本の下端部
を支点としてその支点から相互に異なる方向にある鉄骨
柱の下端部を上下動することで、建て込まれる鉄骨枠を
構成する複数の鉄骨柱下端部が形成する仮想的な平面の
傾き具合が調整されて該鉄骨枠の起立姿勢を調整するも
ので、その仮想的な平面の傾きの判定を、前記基準鉄骨
柱の起立姿勢で判定している。
The standing posture of the entire steel frame is adjusted by adjusting the standing posture of the reference steel column.
This constitutes a steel frame to be built by vertically moving the lower ends of the steel columns in mutually different directions from the fulcrum with the lower end of one of the steel columns constituting the steel frame as a fulcrum. The inclination of a virtual plane formed by the lower ends of the plurality of steel columns is adjusted to adjust the standing posture of the steel frame. The determination of the inclination of the virtual plane is determined by the standing posture of the reference steel column. Is determined.

【0012】前記基準鉄骨柱の起立姿勢を判断する手段
としては、例えば、基準鉄骨柱の上部にターゲットを取
り付け、その基準鉄骨柱の下端部と接合する鉄骨構造体
の鉄骨柱の上部等にカメラを据え付けて、そのカメラの
視野に前記ターゲットの計測マークが入るようにする。
そして、該カメラに写り出された計測マークの画像信号
を画像処理装置に送り、その画像処理装置によって、前
記画像信号を処理して座標情報等を算出し目的とした基
準位置からの前記計測マークの変位を求めて、その変位
から基準鉄骨柱の起立姿勢の傾き具合を判断する。
As means for judging the standing posture of the reference steel column, for example, a target is mounted on the upper portion of the reference steel column, and a camera is mounted on the upper portion of the steel column of the steel structure joined to the lower end of the reference steel column. So that the measurement mark of the target is included in the field of view of the camera.
Then, an image signal of the measurement mark reflected by the camera is sent to an image processing device, and the image processing device processes the image signal to calculate coordinate information and the like, and calculates the coordinate information and the like from the target reference position. Of the standard steel column is determined from the displacement.

【0013】そして、その情報によって制御装置が各エ
レクションピースを所定量だけ上下動させることで対応
する鉄骨柱下端部を所定量上下動させ、もって基準鉄骨
柱の起立姿勢を目的とした姿勢に近づけて鉄骨枠全体の
建入れ直しが実施される。前記基準鉄骨柱の起立姿勢の
調整は、許容精度になるまで自動的に繰り返す。
Based on the information, the control device moves each erection piece up and down by a predetermined amount to move the lower end of the corresponding steel column up and down by a predetermined amount, thereby bringing the standard steel column upright to the intended posture. The entire steel frame will be rebuilt. The adjustment of the standing posture of the reference steel column is automatically repeated until the accuracy becomes acceptable.

【0014】[0014]

【実施例】本発明の実施例を図面に基づいて説明する。
既に鉄骨枠等を継ぎ足して構築されて、図1に示すよう
に、高層になっている鉄骨構造体1の上部に、資材吊り
込み用のタワークレーン2が据え付けられており、その
クレーン2によって、地組されてブロック化した鉄骨枠
3が地表から前記鉄骨構造体1の上方に吊り上げられ
る。
An embodiment of the present invention will be described with reference to the drawings.
As shown in FIG. 1, a tower crane 2 for hanging materials is installed on an upper part of a high-rise steel structure 1 which is already constructed by adding a steel frame or the like, and as shown in FIG. The steel frame 3 that has been ground and blocked is lifted above the steel structure 1 from the ground surface.

【0015】本実施例では、前記クレーン2によって吊
り込まれる鉄骨枠3は、三本の起立した角型の鉄骨柱4
と、その3本の鉄骨柱4を水平に連結する大梁3a及び
小梁3bとから構成されていて、地表において所定の手
段により高精度な建入れを実施しながら形成されたもの
である。そして、前記3本の鉄骨柱4の上部側面及び下
部側面には夫々上部及び下部エレクションピース6,7
が前もって溶着されている。なお、図1ではエレクショ
ンピースは省略されている。
In this embodiment, the steel frame 3 suspended by the crane 2 is composed of three upright rectangular steel columns 4.
And a girder 3a and a small girder 3b connecting the three steel columns 4 horizontally, and are formed on the ground surface while performing high-precision installation by predetermined means. The upper and lower erection pieces 6, 7 are provided on the upper and lower side surfaces of the three steel columns 4, respectively.
Is welded in advance. In FIG. 1, the erection piece is omitted.

【0016】鉄骨柱4の上部側面に設けられた前記上部
エレクションピース6は、図2に示すように、鉄骨柱4
の上端部側面から側方に突出され且つ上方に延設されて
いて、鉄骨柱4の上端面に続く内端面部分に円弧状の切
り欠け部6aが形成されて上側から当接する他の鉄骨柱
との溶接を可能とし、また、外端面上部の角部が切り欠
かれて上端切り欠け部6bが形成され、該上端切り欠け
部6bの上に駆動装置であるジャッキ装置の設置を可能
にしている。
The upper erection piece 6 provided on the upper side surface of the steel column 4 is, as shown in FIG.
The other steel column projecting laterally from the upper end side surface and extending upward, and having an arc-shaped notch 6a formed in the inner end surface portion following the upper end surface of the steel column 4 and contacting from above. And the upper end notch 6b is formed by cutting out the upper corner of the outer end face, and the jack device as a driving device can be installed on the upper end notch 6b. I have.

【0017】また、鉄骨柱4下部に設けられた下部エレ
クションピース7は、鉄骨柱4の下端面から所定高さの
側面より側方に突出するように設けられていて、上下の
鉄骨柱を同軸に当接した際に、下側の鉄骨柱の上部エレ
クションピース7の上端面との間に1ミリ程度の間隙を
有する高さとなっている。なお、前記両エレクションピ
ース6,7には、夫々複数のルーズホール6c,7aが
開設されている。
The lower erection piece 7 provided at the lower part of the steel column 4 is provided so as to protrude laterally from a side surface having a predetermined height from the lower end surface of the steel column 4, and coaxially connects the upper and lower steel columns. , And has a gap of about 1 mm between the lower end of the steel column and the upper end surface of the upper erection piece 7. In addition, a plurality of loose holes 6c and 7a are opened in the erection pieces 6 and 7, respectively.

【0018】また、前記地組された鉄骨枠3を構成する
3本の鉄骨柱4のうち中央の柱を基準鉄骨柱4aとみな
し、その頂部には、地組される際に、ターゲット11が
取り付けられている。そのターゲット11は、図3に示
すように、鉄骨柱4の上端面に固定される当接部11a
と、該当接部11aから側方に延設された平板状のマー
ク部11bとからなる。前記当接部11a下面には前記
鉄骨柱4の上端面に磁着させるための磁石11cが取り
付けられており、また、マーク部11bの下面には中央
にガイド穴11dが開設されている黒丸が描かれ計測マ
ーク11eを形成している。
The center column among the three steel columns 4 constituting the laid steel frame 3 is regarded as a reference steel column 4a. Installed. The target 11 is, as shown in FIG. 3, a contact portion 11a fixed to the upper end surface of the steel column 4.
And a flat mark portion 11b extending laterally from the contact portion 11a. A magnet 11c for magnetically attaching to the upper end surface of the steel column 4 is attached to the lower surface of the contact portion 11a, and a black circle having a guide hole 11d at the center is formed on the lower surface of the mark portion 11b. The drawn measurement mark 11e is formed.

【0019】前記地組された鉄骨枠3は、鉄骨構造体1
の上部あるクレーン2によって吊り込まれ、図4に示す
ように、既に組み上がっている鉄骨構造体1の上側に継
ぎ足される。即ち、前記鉄骨構造体1上部の鉄骨柱1a
の上端面に、吊り込んでいる鉄骨枠3下部の鉄骨柱4の
下端面を上方よりガイド片1bで案内させながら当て、
図5に示すように、鉄骨構造体1側の鉄骨柱1aの上部
エレクションピース6の上端面と鉄骨枠3側の鉄骨柱4
の下部エレクションピース7の下端面とを上下に対向さ
せ、さらに、その上下のエレクションピース6,7の側
面に横方向から別の板状の連結用プレート12を当て
る。その連結用プレート12には上下のエレクションピ
ース6,7のルーズホールに対応する穴が開設されてお
り、その連結用プレート12の穴と上下のエレクション
ピース6,7のルーズホールを貫通するようにボルトを
通して仮取り付けを実施して、鉄骨枠3を鉄骨構造体1
の上側に仮建込みを実施する。なお、図4ではエレクシ
ョンピース6,7及び小梁3bは省略されている。
The laid steel frame 3 is a steel structure 1
And is added to the upper side of the already assembled steel structure 1 as shown in FIG. That is, the steel column 1a on the upper part of the steel structure 1.
The lower end surface of the steel column 4 below the suspended steel frame 3 is guided by the guide piece 1b from above,
As shown in FIG. 5, the upper end surface of the upper erection piece 6 of the steel column 1 a on the side of the steel structure 1 and the steel column 4 on the side of the steel frame 3.
The lower end surface of the lower erection piece 7 is vertically opposed, and another plate-like connecting plate 12 is applied to the side surfaces of the upper and lower erection pieces 6 and 7 from the lateral direction. Holes corresponding to the loose holes of the upper and lower erection pieces 6 and 7 are formed in the connecting plate 12 so as to pass through the holes of the connecting plate 12 and the loose holes of the upper and lower erection pieces 6 and 7. The steel frame 3 is temporarily attached through bolts, and the steel frame 3 is
Temporary erection is carried out on the upper side of. In FIG. 4, the erection pieces 6, 7 and the small beams 3b are omitted.

【0020】また、前記ターゲット11が取り付けられ
た基準鉄骨柱4aと接合される鉄骨構造体1の鉄骨柱1
aの上部外周に、図6に示すように、クランプ20b等
を使用してカメラ20を取り付け、そのカメラ20の受
光軸20aを上方の前記ターゲット11のマーク部11
bに向ける。なお、前記受光軸20aは、必ずしも垂直
方向である必要がなく、後述する画像処理装置21に仰
角の角度等を設定することで可能である。
The steel column 1 of the steel structure 1 to be joined to the reference steel column 4a to which the target 11 is attached.
As shown in FIG. 6, a camera 20 is attached to the upper periphery of the target 11 using a clamp 20b or the like, and the light receiving axis 20a of the camera 20 is positioned above the mark portion 11 of the target 11.
Turn to b. The light receiving axis 20a does not necessarily need to be in the vertical direction, but can be set by setting an angle of elevation or the like in an image processing device 21 described later.

【0021】そのカメラ20は、図7に示すように、画
像処理装置21に接続されていて、その画像処理装置2
1はカメラ20からの画像信号を入力して該画像信号の
解析を行う。その画像処理装置21は、入力した画像を
ディジタル変換するA/D変換部21aと、ディジタル
化した画像信号の画像解析をする画像処理部21bと、
基準座標等のデータを記憶するデータ記憶域21cと、
図示しないディスプレイへの表示を制御する表示制御部
21dと、図8に示すような仮想したX−Y軸テーブル
上での基準座標30と算出した座標情報31とのX及び
Y方向の変位量を求めるX−Y軸テーブル制御部21e
と、データの入力を制御する操作入力制御部21gと、
前記変位に応じたパルス信号を各駆動制御装置22に出
力するデータ出力部21fと、前記データ記憶域21
c,表示制御部21d,X−Y軸テーブル制御部21e
及びデータ出力部21fを制御するCPU21hとから
構成される。
The camera 20 is connected to an image processing device 21 as shown in FIG.
1 inputs an image signal from the camera 20 and analyzes the image signal. The image processing device 21 includes an A / D conversion unit 21a that performs digital conversion of an input image, an image processing unit 21b that performs image analysis of a digitized image signal,
A data storage area 21c for storing data such as reference coordinates,
The display control unit 21d that controls the display on a display (not shown), and the displacement amounts in the X and Y directions between the reference coordinates 30 and the calculated coordinate information 31 on the virtual XY axis table as shown in FIG. XY axis table control unit 21e to be obtained
An operation input control unit 21g for controlling data input;
A data output unit 21f for outputting a pulse signal corresponding to the displacement to each drive control device 22;
c, display controller 21d, XY axis table controller 21e
And a CPU 21h that controls the data output unit 21f.

【0022】前記画像処理装置21は、X軸駆動制御装
置22a及びY軸駆動制御装置22bに接続されて両駆
動制御装置22に各々パルス信号を出力し、その両駆動
制御装置22が各々前記ステップモータ23に接続され
て、該駆動制御装置22によってパルス数に応じた所定
回転角だけ該ステップモータ23が回動させられる。そ
して、そのステップモータ23は夫々ジャッキ装置24
に接続されている。
The image processing device 21 is connected to an X-axis drive control device 22a and a Y-axis drive control device 22b to output pulse signals to both drive control devices 22, respectively. The step motor 23 is rotated by a predetermined rotation angle corresponding to the number of pulses by the drive control device 22. The step motors 23 are respectively connected to jack devices 24.
It is connected to the.

【0023】前記ジャッキ装置24は、図5に示すよう
に、前記鉄骨枠3の鉄骨柱4の下部エレクションピース
7と、上下に対向する鉄骨構造体1の鉄骨柱1aの上部
エレクションピース6の外端面上部の上端切り欠け部6
bとの間に軸を上下に設置され、ジャッキの上端面を下
部エレクションピース7の下端面に当接させて、該ジャ
ッキ装置24の延び縮みによって、鉄骨柱4bの下部エ
レクションピース7を上下動可能に支持させる。
As shown in FIG. 5, the jack device 24 is provided outside the lower erection piece 7 of the steel column 4 of the steel frame 3 and the upper erection piece 6 of the steel column 1a of the steel structure 1 opposed vertically. Notch 6 at upper end of upper end
The lower end erection piece 7 of the steel column 4b is moved up and down by the expansion and contraction of the jack device 24, with the shaft being installed up and down between the lower erection piece 7 and the lower erection piece 7. Support as much as possible.

【0024】本実施例では、鉄骨枠3を構成する三本の
鉄骨柱4のうち両端に位置して、基準鉄骨柱4aに対し
て互いに直角方向にある2本の鉄骨柱4bの下部エレク
ションピース7と、その鉄骨柱4bと接合する鉄骨構造
体1の鉄骨柱1aの上部エレクションピース6との間
に、前記のようにジャッキ装置24を取り付けている。
そのジャッキ装置24を取り付けるエレクションピース
6,7は、基準鉄骨柱4aと対向している側面と反対側
の側面に設けられているエレクションピース(図10中
Aで示されているエレクションピース)で、その両端の
鉄骨柱4b側に取り付けたジャッキ装置24による上下
動によって、各エレクションピース7が上下動し、それ
に追従して対応する2本の鉄骨柱4b下端部が所定量上
下動する。なお、ジャッキ装置24を設置するエレクシ
ョンピースの位置は前記の位置に限定されるものではな
く、場合によっては一本の鉄骨柱4bにおける複数のエ
レクションピースに対してジャッキ装置24を設置し
て、対応する鉄骨柱4bを上下動させてもよい。
In this embodiment, the lower erection pieces of two steel columns 4b located at both ends of three steel columns 4 constituting the steel frame 3 and perpendicular to the reference steel column 4a. As described above, the jack device 24 is mounted between the steel column 7 and the upper erection piece 6 of the steel column 1a of the steel structure 1 joined to the steel column 4b.
The erection pieces 6, 7 to which the jack device 24 is attached are erection pieces (erection pieces shown by A in FIG. 10) provided on the side opposite to the side facing the reference steel column 4a. The erection pieces 7 move up and down by the vertical movement of the jack device 24 attached to the steel column 4b at both ends, and the lower ends of the corresponding two steel columns 4b move up and down by a predetermined amount. In addition, the position of the erection piece in which the jack device 24 is installed is not limited to the above-described position. In some cases, the jack device 24 is installed for a plurality of erection pieces in one steel pillar 4b, and May be moved up and down.

【0025】前記両端に位置する鉄骨柱4b下端部の上
下動は、上下動する鉄骨柱4bと基準鉄骨柱4aとを連
結している大梁3aが夫々テコの腕となって、前記上下
動量に対応した角度だけ基準鉄骨柱4aの傾き角度及び
方向を変更し、かくして、鉄骨枠3を構成する鉄骨柱4
下端部で形成される仮想的な平面Sの傾きの角度及び方
向が、基準鉄骨柱4aの下端部を支点として変更され
る。
The vertical movement of the lower ends of the steel columns 4b located at the both ends is caused by the vertical beams 3a connecting the vertically moving steel columns 4b and the reference steel columns 4a, each serving as a lever arm. The inclination angle and direction of the reference steel column 4a are changed by a corresponding angle, and thus the steel column 4 constituting the steel frame 3 is changed.
The angle and direction of the inclination of the virtual plane S formed at the lower end are changed with the lower end of the reference steel column 4a as a fulcrum.

【0026】前記基準鉄骨柱4aの傾き具合を検出する
ために、前処理として、基準鉄骨柱4aに取り付けられ
たマーク部11b以外の画像(空や遮蔽物等)が入らな
いようにウインドウを設定したり、2値化のための光
量,コントラスト及び閾値等を設定する。また、カメラ
20の倍率,カメラ20と鉄骨柱との距離やカメラ20
とターゲット11間の距離,1パルス当たりのジャッキ
装置24の上下の移動量等を操作入力制御部21gを介
して画像処理装置21に設定する。また、ジャッキ装置
24を取り付けたエレクションピースに対応する鉄骨柱
4bの基準鉄骨柱4aに対する方向及び距離等のベクト
ル情報と、仮想される2次元のX−Y軸テーブルでのX
軸,Y軸の方向が対応するように画像処理装置21に学
習させる。本実施例では、基準鉄骨柱4aから相互に直
交する方向にある両端の鉄骨柱4b方向を図10に示す
ようにX軸,Y軸に対応させている。
In order to detect the degree of inclination of the reference steel column 4a, a window is set as a preprocessing so that an image (such as a sky or a shield) other than the mark portion 11b attached to the reference steel column 4a does not enter. Or a light amount, a contrast, a threshold value, and the like for binarization. The magnification of the camera 20, the distance between the camera 20 and the steel column,
The distance between the target and the target 11, the amount of vertical movement of the jack device 24 per pulse, and the like are set in the image processing device 21 via the operation input control unit 21g. Further, vector information such as a direction and a distance of the steel column 4b corresponding to the erection piece to which the jack device 24 is attached with respect to the reference steel column 4a, and X in a virtual two-dimensional XY axis table.
The image processing device 21 is made to learn so that the directions of the axis and the Y axis correspond to each other. In this embodiment, the directions of the steel columns 4b at both ends in directions orthogonal to each other from the reference steel column 4a correspond to the X axis and the Y axis as shown in FIG.

【0027】なお、画像処理装置21において、カメラ
20で捕らえた計測マーク11eの画像信号を入力して
位置決めのための基準座標30を算出し、データ記憶域
21cに記憶させている。次に、基準鉄骨柱4a頂部の
計測マーク11eを対応するカメラ20で写し、該計測
マーク11eの画像信号を画像処理装置21に送る。画
像処理装置21は、入力した計測マーク11eの画像信
号をA/D変換部21aでディジタル変換し、さらに、
画像処理部21bで2値化等を実施して該計測マーク1
1eの座標情報31を算出する。
In the image processing device 21, an image signal of the measurement mark 11e captured by the camera 20 is input, a reference coordinate 30 for positioning is calculated, and stored in the data storage area 21c. Next, the measurement mark 11e at the top of the reference steel column 4a is photographed by the corresponding camera 20, and the image signal of the measurement mark 11e is sent to the image processing device 21. The image processing device 21 converts the input image signal of the measurement mark 11e into a digital signal by the A / D converter 21a.
The measurement mark 1
The coordinate information 31 of 1e is calculated.

【0028】次に、X−Y軸テーブル制御部21eにお
いて、その座標情報31と前記記憶した基準座標30と
の比較処理が行われ、該座標情報31と基準座標30と
の変位を、ベクトル分解して仮想した2次元のX軸,Y
軸の2方向の変位量を求める。そして、前記2方向の変
位量に比例したパルス数を、データ出力部から夫々X軸
駆動制御装置22a及びY軸駆動制御装置22bに個別
に伝達する。なお、前記パルスは正方向と負方向の二種
類のパルスが選択されて出力される。
Next, the XY-axis table controller 21e compares the coordinate information 31 with the stored reference coordinates 30. The displacement between the coordinate information 31 and the reference coordinates 30 is calculated by vector decomposition. Virtual 2D X axis, Y
The amount of displacement of the shaft in two directions is obtained. Then, the number of pulses proportional to the amount of displacement in the two directions is individually transmitted from the data output unit to the X-axis drive control device 22a and the Y-axis drive control device 22b. The pulse is selected and output from two types of pulses, a positive direction and a negative direction.

【0029】各駆動制御装置22は、入力したパルスに
よって指示された方向(正方向又は負方向)に各ステッ
プモータ23を回動するための電流を印加する。する
と、各ステップモータ23は、前記駆動制御装置22か
ら指示された方向に所定角度だけ回転する。該モータ2
3の回転角度は、画像処理装置21からの出力パルスの
数に比例して回転する。例えば、1パルス当たりのステ
ップモータ23のステップ角が1.8度とすると、10
パルスで18度回転する。
Each drive control device 22 applies a current for rotating each step motor 23 in the direction (positive direction or negative direction) specified by the input pulse. Then, each step motor 23 rotates by a predetermined angle in the direction specified by the drive control device 22. The motor 2
The rotation angle of 3 rotates in proportion to the number of output pulses from the image processing device 21. For example, if the step angle of the step motor 23 per pulse is 1.8 degrees, 10
Rotate 18 degrees with a pulse.

【0030】続いて、ステップモータ23の回転は減速
機25に伝達され、該減速機25を介してジャッキ装置
24を上下動する。前記減速機25は、ステップモータ
23からのトルクを増大し、また、回転角度を細分化し
てステップ角(1.8度)以下の精度をだして、ジャッ
キ装置24の1パルス単位の上下への移動量を小さくし
ている。
Subsequently, the rotation of the step motor 23 is transmitted to the speed reducer 25, and the jack device 24 moves up and down via the speed reducer 25. The speed reducer 25 increases the torque from the step motor 23, and subdivides the rotation angle to obtain an accuracy equal to or less than the step angle (1.8 degrees), and moves the jack device 24 up and down by one pulse unit. The amount of movement is reduced.

【0031】前記ジャッキ装置24の上下動に合わせて
下部エレクションピース7も上下動し、それに追従して
鉄骨柱4bを上下動され、該基準鉄骨柱4aの起立姿勢
を調整する。前記処理は、入力した計測マーク11eの
座標情報31と基準座標30との関係が許容範囲になる
まで、画像処理装置21がパルスを出し続けて基準鉄骨
柱4aの起立姿勢が調整され、もって鉄骨枠3の鉄骨柱
4下端部が形成する仮想的な平面Sの傾き具合が調整さ
れて鉄骨枠3の建入れ直しが実施される。
The lower erection piece 7 also moves up and down in accordance with the up-and-down movement of the jack device 24, and the steel column 4b is moved up and down following the lower erection piece 7 to adjust the standing posture of the reference steel column 4a. In the above-described processing, the image processing apparatus 21 continues to emit pulses until the relationship between the input coordinate information 31 of the measurement mark 11e and the reference coordinates 30 is within the allowable range, and the standing posture of the reference steel column 4a is adjusted. The inclination of the virtual plane S formed by the lower end of the steel frame column 4 of the frame 3 is adjusted, and the steel frame 3 is re-installed.

【0032】前記画像処理装置21に、X−Y軸テーブ
ルの2軸と、対象とする基準鉄骨柱4aの中心から相互
に直交する両鉄骨柱4bへの各方向とが対応するように
前もって学習させているが、X軸に対応する下部エレク
ションピース7の上下動と鉄骨柱の傾斜角度の変位との
関係は、図9に示すように、下部エレクションピース7
を介して鉄骨柱4b下端部を下降させると(図9中4
1)、該下降量に比例した角度だけ基準鉄骨柱4aを前
記鉄骨柱4b側へ正方向に傾斜させて(図9中51)、
X−Y軸テーブル上における前記計測マーク11eの座
標情報31をX軸の正方向に移動させ、また、下部エレ
クションピース7を上昇させると(図中42)、上昇量
に比例した角度だけ基準鉄骨柱4aを前記鉄骨柱4b側
へ負方向に傾斜させて(図中52)、X−Y軸テーブル
上における前記計測マーク1eの座標情報31をX軸の
負方向に移動させる。また、Y軸に対応する前記鉄骨柱
4b下端部の上下動と基準鉄骨柱4aの傾き具合の移動
との関係も同様である。
The image processing apparatus 21 learns in advance so that the two axes of the XY axis table correspond to the respective directions from the center of the target reference steel column 4a to the mutually orthogonal two steel columns 4b. However, the relationship between the vertical movement of the lower erection piece 7 corresponding to the X axis and the displacement of the inclination angle of the steel column is shown in FIG.
When the lower end of the steel column 4b is lowered through the
1) The reference steel column 4a is inclined in the forward direction toward the steel column 4b by an angle proportional to the descending amount (51 in FIG. 9),
When the coordinate information 31 of the measurement mark 11e on the XY-axis table is moved in the positive direction of the X-axis and the lower erection piece 7 is raised (42 in the figure), the reference steel frame is moved by an angle proportional to the amount of rise. The column 4a is inclined in the negative direction toward the steel column 4b (52 in the drawing), and the coordinate information 31 of the measurement mark 1e on the XY axis table is moved in the negative direction of the X axis. The same applies to the relationship between the vertical movement of the lower end of the steel column 4b corresponding to the Y axis and the movement of the inclination of the reference steel column 4a.

【0033】例えば、仮想したX−Y軸テーブル上での
座標情報31の位置が図8に示すように解析されたとす
ると、画像処理装置21から変位量に対応したX軸,Y
軸に対する個々の負方向に移動を指示するパルスが出力
されて、該X軸,Y軸に対応する各下部エレクションピ
ース7が前記パルス数に比例して上昇し、前記座標情報
31が基準座標30に近づく。
For example, if the position of the coordinate information 31 on the virtual XY-axis table is analyzed as shown in FIG. 8, the X-axis and Y-axis corresponding to the displacement amount are
A pulse instructing movement in the individual negative direction with respect to the axis is output, and each lower erection piece 7 corresponding to the X axis and the Y axis rises in proportion to the number of pulses, and the coordinate information 31 is changed to the reference coordinate 30. Approach.

【0034】これにより、仮想上のX−Y軸テーブルで
の基準座標30に計測マーク11eの座標情報31を近
づけることで、基準鉄骨柱4aの傾斜角度が基準とした
傾斜角度になり、もって鉄骨枠3の鉄骨柱4下端部が形
成する仮想的な平面に傾き具合が調整されて当該鉄骨枠
3の建入れ直しが高精度で実施できる。該鉄骨枠3の建
入れ直しが終了したら、各エレクションピース6,7と
連結用プレート12の仮止めしたボルトを加締めて該鉄
骨枠3の起立姿勢を固定し、続けて鉄骨枠3の各鉄骨柱
の下端部を当接している鉄骨構造体1の鉄骨柱1eとの
当接部を溶接して接合する。
Thus, by bringing the coordinate information 31 of the measurement mark 11e closer to the reference coordinates 30 on the virtual XY axis table, the inclination angle of the reference steel column 4a becomes the reference inclination angle. The degree of inclination is adjusted to a virtual plane formed by the lower end of the steel column 4 of the frame 3, so that the steel frame 3 can be re-installed with high accuracy. When the rebuilding of the steel frame 3 is completed, the temporarily fixed bolts of the erection pieces 6 and 7 and the connecting plate 12 are crimped to fix the standing posture of the steel frame 3, and subsequently the steel frames of the steel frame 3 are fixed. The contact portion of the steel structure 1 contacting the lower end of the column with the steel column 1e is welded and joined.

【0035】前記接合が終了したら連結用プレート12
を外し、不要になったエレクションピース6,7を鉄骨
柱から切断する。以上のように、継ぎ足される鉄骨枠3
の建入れ直しが自動化されて、手間が省け、さらに該建
入れの精度が向上して、鉄骨構造物の高層化に対応可能
となる。また、本実施例では、鉄骨柱4aを上下動する
ためにエレクションピース6,7間にジャッキ装置を設
置して実施しているため、該ジャッキ装置を上下の鉄骨
柱間に設置するための別の仮設用の部材を該鉄骨柱に設
ける必要がない。
When the joining is completed, the connecting plate 12
And the unnecessary erection pieces 6, 7 are cut from the steel column. As described above, the steel frame 3 to be added
The rebuilding of the building is automated, labor is saved, the accuracy of the building is improved, and it is possible to cope with an increase in the height of the steel structure. Further, in this embodiment, since the jack device is installed between the erection pieces 6 and 7 to move the steel column 4a up and down, the jack device is installed between the upper and lower steel columns. There is no need to provide a temporary member for the steel column.

【0036】なお、本実施例では、ターゲット11を基
準鉄骨柱の頂部に取り付けているが、クランプ等の公知
の手段で基準鉄骨柱4aの所定高さ位置に固定してもよ
い。また、本実施例では、地組した鉄骨枠を構成する鉄
骨柱は3本であるが、4本以上の鉄骨柱を有していても
よい。この場合も基準とする鉄骨柱を一本選択して、該
鉄骨柱の下端部を支点とし、該支点から相互に異なる方
向に位置する2本以上の鉄骨柱を下部エレクションピー
ス7を介して上下動させることで、基準鉄骨柱の起立姿
勢が調整され、もって鉄骨枠を構成する鉄骨柱が形成す
る仮想的な平面の傾き具合が調整されて、鉄骨枠全体の
建入れ直しが実施される。
In this embodiment, the target 11 is attached to the top of the reference steel column. However, the target 11 may be fixed to a predetermined height of the reference steel column 4a by a known means such as a clamp. In this embodiment, the number of steel columns constituting the grounded steel frame is three, but four or more steel columns may be provided. In this case as well, one steel column as a reference is selected, and the lower end of the steel column is used as a fulcrum, and two or more steel columns located in mutually different directions from the fulcrum are vertically moved via the lower erection piece 7. By moving the steel frame, the standing posture of the reference steel column is adjusted, whereby the degree of inclination of the virtual plane formed by the steel column forming the steel frame is adjusted, and the entire steel frame is re-installed.

【0037】また、本実施例では、ジャッキ装置24に
ステップモータ23を連結して下部エレクションピース
7を上下動させているが、油圧シリンダ装置を使用する
等、他の公知の駆動手段で上下動させても構わない。ま
た、本実施例では、基準鉄骨柱4aから相互に直交する
方向の鉄骨柱4bの下部を上下動させているが、上下動
させる鉄骨柱4bは、必ずしも直交している必要はな
く、同一方向に並ばなければ相互に120度等の方向の
鉄骨柱下部を上下動させても構わない。
Further, in this embodiment, the stepping motor 23 is connected to the jack device 24 to move the lower erection piece 7 up and down. However, it is possible to move the lower erection piece 7 up and down by other known driving means such as using a hydraulic cylinder device. You may let it. Further, in this embodiment, the lower part of the steel column 4b in the direction orthogonal to each other is moved up and down from the reference steel column 4a. However, the steel column 4b to be moved up and down is not necessarily required to be orthogonal and is in the same direction. Otherwise, the lower portions of the steel columns in directions such as 120 degrees may be moved up and down with respect to each other.

【0038】さらに、基準鉄骨柱4aの起立姿勢の検出
は、本実施例の手段に限らず、他の公知の装置によって
起立姿勢を検出してもよい。
Further, the detection of the standing posture of the reference steel column 4a is not limited to the means of the present embodiment, and the standing posture may be detected by another known device.

【0039】[0039]

【発明の効果】以上のように、本発明の鉄骨枠の建入れ
直し方法では、地組された鉄骨枠を、既に組み上げられ
た鉄骨構造体の上部に継ぎ足す際に、該鉄骨枠の建入れ
直しが自動化され、さらに、該鉄骨枠の建入れの精度が
向上して高層の鉄骨構造物にも対応可能となる。
As described above, in the method for re-installing a steel frame according to the present invention, when the laid steel frame is added to the upper part of the already assembled steel structure, the steel frame is re-installed. Is automated, and the accuracy of the installation of the steel frame is improved, making it possible to cope with a high-rise steel structure.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本実施例の鉄骨構造体及び鉄骨枠を示す斜視図
である。
FIG. 1 is a perspective view showing a steel frame structure and a steel frame of the present embodiment.

【図2】エレクションピースを示す側面図である。FIG. 2 is a side view showing an erection piece.

【図3】ターゲットを示す斜視図である。FIG. 3 is a perspective view showing a target.

【図4】本実施例の鉄骨構造体と鉄骨枠との連結を示す
斜視図である。
FIG. 4 is a perspective view showing the connection between the steel frame structure and the steel frame of the present embodiment.

【図5】上下のエレクションピースの連結及びジャッキ
装置を示す側面図である。
FIG. 5 is a side view showing the connection of the upper and lower erection pieces and the jack device.

【図6】カメラ及びターゲットの設置関係を示す側面図
である。
FIG. 6 is a side view showing an installation relationship between a camera and a target.

【図7】本実施例の建入れ直し装置を示すブロック図で
ある。
FIG. 7 is a block diagram showing a rebuilding device according to the present embodiment.

【図8】本実施例のX−Y軸テーブルを示す図である。FIG. 8 is a diagram illustrating an XY axis table according to the present embodiment.

【図9】本実施例の基準鉄骨柱の傾きの変更を表す模式
図である。
FIG. 9 is a schematic diagram illustrating a change in inclination of a reference steel column according to the present embodiment.

【図10】本実施例の仮想的な平面を示す図である。FIG. 10 is a diagram illustrating a virtual plane according to the present embodiment.

【符号の説明】[Explanation of symbols]

1 鉄骨構造体 3 鉄骨枠 4 鉄骨枠の鉄骨柱 6 上部エレクションピース 7 下部エレクションピース 11 ターゲット 11e 計測マーク、 20 カメラ 21 画像処理装置 22 駆動制御部 24 ジャッキ装置 30 基準座標 31 座標情報、 S 仮想的な平面 Reference Signs List 1 steel structure 3 steel frame 4 steel frame of steel frame 6 upper erection piece 7 lower erection piece 11 target 11e measurement mark, 20 camera 21 image processing device 22 drive control unit 24 jack device 30 reference coordinate 31 coordinate information, S virtual Plane

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 複数の鉄骨柱や梁等によって地組された
鉄骨枠を、既に組み上げられている鉄骨構造体の上側に
仮建込みを行い、その仮建込みされた鉄骨枠を所定の起
立姿勢に建入れ直しする方法において、前記鉄骨枠を構
成する複数の鉄骨柱のうちの一本の鉄骨柱を基準鉄骨柱
とみなし、その基準鉄骨柱に対する目的とする起立姿勢
からの傾斜方向や傾斜角度の変位情報を検出すること
で、鉄骨枠を構成する複数の鉄骨柱下端部によって形成
される仮想的な平面の傾斜方向及び傾斜角度を解析し、
その解析情報をもとに、前記基準鉄骨柱の下端部を支点
とし、その基準鉄骨柱から相互に異なる方向にある複数
の鉄骨柱の下端部を、その鉄骨柱の下部に設けられてい
る各エレクションピースを介して所定量だけ駆動手段に
よって上下動させることで、前記仮想的な平面の傾き具
合を調整して鉄骨枠全体の起立姿勢を調整することを特
徴とする鉄骨枠の建入れ直し方法。
1. A steel frame erected by a plurality of steel columns and beams is temporarily erected above a steel structure already assembled, and the temporarily erected steel frame is erected in a predetermined manner. In the method of rebuilding in the posture, one of the plurality of steel columns constituting the steel frame is regarded as a reference steel column, and the inclination direction and the inclination angle from the intended standing posture with respect to the reference steel column. By detecting the displacement information, the inclination direction and the inclination angle of the virtual plane formed by the lower end portions of the plurality of steel columns constituting the steel frame are analyzed,
Based on the analysis information, the lower end of the reference steel column is used as a fulcrum, and the lower ends of a plurality of steel columns in mutually different directions from the reference steel column are provided at the lower part of the steel column. A method of re-installing a steel frame, wherein the upright posture of the entire steel frame is adjusted by moving the erection piece up and down by a predetermined amount by a driving unit to adjust the degree of inclination of the virtual plane.
【請求項2】 既に組み上げられている鉄骨構造体の上
側に仮建込みされた鉄骨枠に対して、その鉄骨枠を構成
する複数の鉄骨柱のうち一本を基準鉄骨柱とみなし、そ
の基準鉄骨柱から相互に異なる方向に位置する複数の鉄
骨柱の下部側面に設けられている各エレクションピース
を上下動する駆動手段と、前記基準鉄骨柱の上部に取り
付けられて側方に延設され該延設部の下面に計測マーク
を有するターゲットと、前記基準鉄骨柱の下端部と接合
される鉄骨構造体の鉄骨柱上部若しくはその近傍に設置
されて受光軸を前記ターゲットの計測マークに向けたカ
メラと、カメラに接続されて、該カメラからの画像信号
を処理して前記計測マークの基準位置に対する変位を求
め、前記基準鉄骨柱の起立姿勢を判断する画像処理装置
と、画像処理装置に接続されて、該画像処理装置からの
信号により前記駆動装置を駆動して前記鉄骨枠の各鉄骨
柱下部側面のエレクションピースを夫々所定量だけ上下
動させる駆動制御装置とを備えたことを特徴とする鉄骨
枠の建入れ直し装置。
2. With respect to a steel frame temporarily erected above a steel structure already assembled, one of a plurality of steel columns constituting the steel frame is regarded as a standard steel column, A drive means for vertically moving each erection piece provided on a lower side surface of a plurality of steel columns located in mutually different directions from the steel column, and a driving means attached to an upper portion of the reference steel column and extending laterally; A target having a measurement mark on the lower surface of the extending portion, and a camera installed at or near the upper part of the steel column of the steel structure joined to the lower end of the reference steel column and having the light receiving axis directed toward the measurement mark of the target And an image processing device connected to a camera, which processes an image signal from the camera to determine a displacement of the measurement mark with respect to a reference position, and determines an upright posture of the reference steel column. A drive control device for driving the drive device in response to a signal from the image processing device to move the erection pieces on the lower side surface of each steel column of the steel frame up and down by a predetermined amount, respectively. Rebuilding equipment for steel frames.
JP18237391A 1991-07-23 1991-07-23 Method and apparatus for re-installing steel frame Expired - Lifetime JP2935761B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18237391A JP2935761B2 (en) 1991-07-23 1991-07-23 Method and apparatus for re-installing steel frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18237391A JP2935761B2 (en) 1991-07-23 1991-07-23 Method and apparatus for re-installing steel frame

Publications (2)

Publication Number Publication Date
JPH0525942A JPH0525942A (en) 1993-02-02
JP2935761B2 true JP2935761B2 (en) 1999-08-16

Family

ID=16117177

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18237391A Expired - Lifetime JP2935761B2 (en) 1991-07-23 1991-07-23 Method and apparatus for re-installing steel frame

Country Status (1)

Country Link
JP (1) JP2935761B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2822012B2 (en) * 1995-04-18 1998-11-05 川崎重工業株式会社 Steel column construction adjustment jig
JP5724236B2 (en) * 2010-07-23 2015-05-27 株式会社大林組 Method for setting virtual line parallel to core line of construction member, pair of virtual line setting jig for setting virtual line, and installation method for installing linearity measuring device on construction member
CN114370165A (en) * 2022-03-10 2022-04-19 中冶(上海)钢结构科技有限公司 Node construction method for correcting installation dislocation of box type steel column
CN114776031A (en) * 2022-04-26 2022-07-22 中铁二十局集团第三工程有限公司 Deviation rectifying construction control method, device, equipment, system and medium for special-shaped steel structure

Also Published As

Publication number Publication date
JPH0525942A (en) 1993-02-02

Similar Documents

Publication Publication Date Title
CN111268530B (en) Method and apparatus for measuring, positioning and installing elevator shaft
CN111622110B (en) Intelligent installation and construction method for prefabricated bent cap based on three-dimensional measurement lofting technology
JP2935761B2 (en) Method and apparatus for re-installing steel frame
JP7444710B2 (en) Hoistway measurement device and hoistway measurement system
CN110645454A (en) Be used for three-dimensional scanner automatically regulated support
CN111257586B (en) Leveling device for wind measuring instrument on large cable of large-span suspension bridge
CN113753759B (en) Lifting appliance positioning method, lifting appliance positioning device and lifting equipment
JPH01127939A (en) Scanning robot for surveying surface of building
JPH0640679A (en) Centering manipulator of elevator guide rail
JPH0719869A (en) Displacement detection method for structure and target plate used for it
JP2795159B2 (en) Bucket position measuring device
JPH09242339A (en) Vertical positioning method of building main post
JPH04309671A (en) Device for adjusting plumbing of field assembling steel structure
JPH07238684A (en) Method and device for erecting column of construction
JP2533317B2 (en) Displacement automatic detection system
JPH0213661A (en) Erecting method for building material
JPH10236767A (en) Automatic aligning hoisting accessory and hoisting method using this hoisting accessory
JP3498250B2 (en) Automatic measuring device and method for long structures such as bridge girder
JPH08120941A (en) Erection method for construction material and its device
JP2645419B2 (en) Automatic welding equipment
JPS59102061A (en) Pillar building method and apparatus
JPH06147896A (en) Erection measuring system for steel column
JPH03103512A (en) Manufacture of coupling structure and manufacture of long large bridge main tower block
CN117127814B (en) Cloud building factory manipulator for concrete leveling construction and construction method
JP2909808B2 (en) Automatic measuring device for long structures such as bridge box girder